Port Vue Plumbing v. Rite Fence ( 2020 )


Menu:
  • J-A29025-19
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
    PORT VUE PLUMBING                          :   IN THE SUPERIOR COURT OF
    :        PENNSYLVANIA
    Appellant               :
    :
    :
    v.                             :
    :
    :
    RITE FENCE AND ANTHONY S.                  :   No. 677 WDA 2019
    NEINO, INDIVIDUALLY                        :
    Appeal from the Judgment Entered on May 2, 2019,
    in the Court of Common Pleas of Allegheny County,
    Civil Division at No(s): GD-17-013715.
    BEFORE:      BENDER, P.J.E., KUNSELMAN, J., and PELLEGRINI, J.*
    MEMORANDUM BY KUNSELMAN, J.:                            FILED MARCH 30, 2020
    Port Vue Plumbing appeals from the judgment entered in favor of Rite
    Fence1 and Anthony S. Neino (collectively "Subcontractor"), in this breach of
    contract action. After careful review, we affirm.
    In 2015, Port Vue won a bid to be the general contractor under a
    construction contract with the Westmoreland Fayette Municipal Sewage
    Authority for the construction of a Wastewater Treatment Facility and the
    Swedetown Pump Station. As part of the project, Port Vue was required to
    supply and construct a perimeter fence with gates around the Treatment Plant.
    In December 2016, Port Vue retained Subcontractor to install this fence.
    ____________________________________________
    *   Retired Senior Judge assigned to the Superior Court.
    1Rite Fence is a fictitious business name of a sole proprietorship owned and
    operated by Anthony S. Neino.
    J-A29025-19
    Port Vue agreed to supply the fence materials and concrete for the
    project; Subcontractor agreed to provide labor and equipment for installation
    of the fence.   Port Vue agreed to pay Subcontractor $38,000.00 for its
    services. On December 21, 2016, Port Vue gave Subcontractor a purchase
    order, along with an initial payment of $5,000.00.
    Port Vue and the Authority’s Engineer provided Subcontractor with the
    specifications for the fence installation.   In particular, the specifications
    required that corner post holes be excavated and filled with concrete at a
    width of 12" and a depth of 30", and that line post holes be excavated and
    filled with concrete at a width of 9" and a depth of 30".
    Shortly thereafter, on December 26, 2016, Subcontractor began
    construction of the fence at the Treatment Plant. As work progressed, Port
    Vue made progress payments on January 3, 2017 ($10,000.00) and on
    February 1, 2017 ($7,500.00). At the time of these payments, no issues were
    raised about Subcontractor’s performance.
    On February 27, 2017, the Authority’s Engineer notified Port Vue that
    some of the line posts were wobbly. Subcontractor acknowledged that there
    were posts near the gravel parking lot that were unstable; the condition of the
    soil in that area prevented the posts from staying in place with their concrete
    footings. At that point, Subcontractor had completed about 2/3 of the work.
    -2-
    J-A29025-19
    Port Vue and the Authority’s Engineer proceeded to check several posts.
    Because the project was behind schedule and funds for inspection were low,
    the Authority authorized only limited inspection. Upon inspection, Port Vue
    and the Authority’s Engineer allegedly found posts with insufficient concrete
    or hole depth. Because of this deficiency, the Authority’s Engineer determined
    that 200 posts had to be removed and reinstalled. Subcontractor disputed
    that the work did not comply with the contract specifications and rejected this
    resolution, but was willing to try to work out an alternative solution.
    One day later, on April 11, 2017, the Authority directed that 200 posts
    be removed and reset. The following day, the Authority’s Engineer sent Port
    Vue a letter notifying it that the posts were to be removed and replaced.
    On April 13, 2017, Port Vue hired another contractor to reinstall the
    fence posts once Port Vue had removed them. The next day, Port Vue notified
    Subcontractor that it intended to take legal action against it for failing to install
    the fence posts in accordance with the specifications and complete the project.
    Port Vue filed suit against Subcontractor on October 5, 2017, asserting
    claims for breach of contract and unjust enrichment, and seeking damages in
    the amount of $34,458.27.
    On March 27 and 28, 2019, the court held a bench trial. Thereafter, on
    April 8, 2019, the trial court ruled in favor of Subcontractor and against Port
    Vue on both its breach of contract and unjust enrichment claims.
    Port Vue filed post-trial motions asking the trial court to set aside the
    verdict and direct judgment in Port Vue’s favor, which the trial court denied.
    -3-
    J-A29025-19
    Port Vue timely appealed. Both Port Vue and the trial court complied with
    Pennsylvania Rule of Appellate Procedure 1925.
    Port Vue raises three issues on appeal for our review:
    I. Whether the trial court erred in refusing to enter Port Vue's
    photographs into evidence?
    II. Whether the trial court erred in ignoring competent evidence
    favorable to Port Vue and weighing the testimony and evidence at
    trial?
    III. Whether the trial court erred in entering a verdict in favor of
    Subcontractor and against Port Vue?
    Port Vue’s Brief at 2.
    In its first issue, Port Vue contends that the trial court erred in refusing
    to admit certain photographs into evidence at trial. According to Port Vue, the
    pictures depicted various line posts and holes after the line posts had been
    removed. Port Vue claims the photos showed insufficient concrete was used
    to set the posts. It claims the trial court should have admitted these photos
    as evidence to show that Subcontractor failed to use the required amount of
    concrete and, therefore, breached the agreement. Port Vue’s Brief at 11.
    Generally, we note that our standard of review for evidentiary rulings is
    a narrow one:
    When we review a trial court's ruling on admission of evidence,
    we must acknowledge that decisions on admissibility are within
    the sound discretion of the trial court and will not be overturned
    absent an abuse of discretion or misapplication of law. In addition,
    for a ruling on evidence to constitute reversible error, it must have
    been harmful or prejudicial to the complaining party.
    -4-
    J-A29025-19
    Reott v. Asia Trend, Inc., 
    7 A.3d 830
    , 839 (Pa. Super. 2010), affirmed, 
    55 A.3d 1088
    (2012).
    For a document or photograph to be admissible trial, it must first be
    authenticated by “evidence sufficient to support a finding that the item is what
    the proponent claims it is.” Pa.R.E. 901(a); see also Zuk v. Zuk, 
    55 A.3d 102
    , 112 (Pa. Super. 2012). More specifically, it is well-established that
    “[b]efore a photograph is admissible it must be verified[.] Such verification
    must be by someone who has sufficient knowledge to state that it fairly and
    truthfully represents the object or the place reproduced.” Taylor v. Modena,
    
    87 A.2d 195
    , 196 (Pa. 1952) (citations omitted).
    The trial court denied admission of the photographs, because Port Vue’s
    witnesses were unable to state who took the photos, at what time during the
    course of construction the photos were taken, and where specifically on the
    engineering plan each photographed post was located. Trial Court Opinion,
    7/17/19, at 7. Thus, it found the photos could not prove or explain any alleged
    inadequacy of the depth of the post holes or insufficient amount of concrete.
    Id. At trial,
    the Authority’s Engineer testified that the pictures generally
    represented what they discovered when the posts were removed. Another
    witness for Port Vue hesitated when stating that the photos were of different
    holes. However, considering no one could state when or where the photos
    were taken, the trial court was not convinced that the photos were properly
    verified as required by Rule of Evidence 901(a). Given the uncertainty about
    -5-
    J-A29025-19
    what the pictures represented, we do not find that the trial court abused its
    discretion or committed an error of law in refusing to admit the photos into
    evidence.
    Even if the photos were admissible, the trial court’s refusal to admit
    them was not harmful or prejudicial to Port Vue. The trial court explained that
    although it did not admit the photographs into evidence, it examined the
    photos and heard the testimony related to them.
    Id. Therefore, because
    Port
    Vue was not prejudiced by this evidentiary ruling, the court’s refusal to admit
    the photos in this bench trial was not reversible error. Port Vue’s first issue
    merits not relief.
    In its second issue, Port Vue claims that the trial court’s verdict was
    against the weight of evidence. Specifically, Port Vue claims that the trial
    court ignored competent evidence favorable to Port Vue in weighing the
    evidence and rendering its decision. Port Vue’s Brief at 14, 16. According to
    Port Vue, the weight of the evidence clearly favored a finding that
    Subcontractor utilized insufficient concrete when it installed numerous line
    posts, and thus, the trial court’s verdict should be reversed.
    Id. at 18.
    When reviewing a weight claim, we are mindful of the following
    principles:
    Appellate review of a weight claim is a review of the [trial court's]
    exercise of discretion, not of the underlying question of whether
    the verdict is against the weight of the evidence. Because the trial
    judge has had the opportunity to hear and see the evidence
    presented, an appellate court will give the gravest consideration
    to the findings and reasons advanced by the trial judge when
    reviewing a trial court's determination that the verdict is against
    -6-
    J-A29025-19
    the weight of the evidence. One of the least assailable reasons for
    granting or denying a new trial is the lower court's conviction that
    the verdict was or was not against the weight of the evidence and
    that a new trial should be granted in the interest of justice.
    In re Estate of Smaling, 
    80 A.3d 485
    , 490 (Pa. Super. 2013) (citing
    Commonwealth v. Clay, 
    64 A.3d 1049
    , 1055 (Pa. 2013)). The trial court
    may award a judgment notwithstanding the verdict or a new trial “only when
    the jury's verdict is so contrary to the evidence as to shock one's sense of
    justice. In determining whether this standard has been met, appellate review
    is limited to whether the trial judge's discretion was properly exercised, and
    relief will only be granted where the facts and inferences of record disclose a
    palpable abuse of discretion.” Samuel–Bassett v. Kia Motors Am., Inc.,
    
    34 A.3d 1
    , 39 (Pa. 2011)(citing Commonwealth v. Cousar, 
    928 A.2d 1025
    ,
    1035–36 (Pa. 2007)).
    Typically, a weight claim is filed after a jury trial in the hope that the
    trial court judge who, like the jury, had an opportunity to hear the evidence
    and observe the demeanor of the witnesses, ‘will conclude that the verdict
    was so contrary to what it heard and observed that it will deem the jury’s
    verdict such a miscarriage of justice and trigger the court’s time-honored and
    inherent power to take corrective action.” Criswell v. King, 
    834 A.2d 505
    ,
    512 (Pa. 2003). Here, however, a non-jury trial was held. Although weight
    of the evidence claims have been addressed in non-jury cases, there is a
    logical inconsistency in asking a trial judge to conclude that his non-jury
    -7-
    J-A29025-19
    decision shocked his own conscience.         Notwithstanding this, we consider
    whether the trial court’s decision was against the weight of the evidence.
    Obviously, the trial court here concluded that its non-jury decision was
    not against the weight of the evidence. In reaching this conclusion, the trial
    court reviewed the evidence presented by the parties concerning whether the
    posts had insufficient concrete or hole depth and whether any breach of
    contract caused the wobbly fence posts. The trial court found that Port Vue
    failed to adequately identify whether holes were not dug to specification or
    had insufficient concrete.     Instead, the trial court credited Subcontractor’s
    testimony regarding the location and cause of the wobbly posts and relied on
    it in weighing the evidence.
    The trial court further credited Subcontractor’s testimony as to why it
    was unable to complete the project.       The trial court found that, after the
    wobbly posts were discovered, the decision to remove 200 posts was arbitrary,
    particularly in light of Subcontractor’s contention that no more than 10 posts
    were wobbly.    Additionally, Port Vue did not give Subcontractor adequate
    notice of the problem or an opportunity to cure the alleged defect. Port Vue
    also did not submit a change order to the Authority for additional work,
    assuming that the original specifications were inadequate to support the line
    posts in some areas. While Subcontractor was waiting to hear from Port Vue
    regarding an alternative resolution, Port Vue immediately went out and hired
    another contractor to finish the job. Moreover, not only did the replacement
    -8-
    J-A29025-19
    contractor complete the work, but totally ripped out the work Subcontractor
    had already performed.
    Based upon our review of the record and the trial court’s consideration
    of the same, we discern no abuse of discretion in the trial court’s rejection of
    Port Vue’s weight of the evidence claim. Here, there was conflicting testimony
    as to the location and cause of the wobbly fence posts. Additionally, there
    was conflicting testimony as to whether all 200 posts had to be removed to
    resolve the problem. A mere conflict in testimony will not suffice as grounds
    for a new trial. Winschel v. Jain, 
    925 A.2d 783
    , 788 (Pa. Super. 2007).
    Furthermore, the factfinder is free to believe all, part, or none of the
    evidence and to determine the credibility of the witnesses.”           Samuel–
    
    Bassett, 34 A.3d at 39
    . Here, the trial court acknowledged that its decision
    in this case turned on credibility. The trial court found Subcontractor more
    credible, and resolved any conflicts in the testimony in its favor. We further
    note that the trial court considered the evidence as a whole, not just the
    limited excerpts of testimony Port Vue has identified in arguing this issue. For
    these reasons, Port Vue second claim challenging the weight of the evidence
    warrants no relief.
    In its third issue, Port Vue claims that the trial court erred in entering a
    verdict in favor of Subcontractor and against Port Vue. Essentially, Port Vue
    argues that the evidence established that Subcontractor breached the contract
    or was unjustly enriched.     According to Port Vue, Subcontractor failed to
    properly excavate and fill with concrete the line post holes as required by the
    -9-
    J-A29025-19
    contract specifications. Consequently, Port Vue had to remove a significant
    portion of the fence and hire another contractor to reconstruct it. Additionally,
    Port Vue paid Subcontractor $22,500 for work it claims Subcontractor failed
    to perform. Therefore, Port Vue argues the trial court should have entered
    judgment in its favor. Port Vue’s Brief at 19-21.
    Our scope and standard of review of these claims is well-defined:
    Our appellate role in cases arising from non-jury trial [decisions]
    is to determine whether the findings of the trial court are
    supported by competent evidence and whether the trial court
    committed error in any application of the law. The findings of fact
    of the trial judge must be given the same weight and effect on
    appeal as the verdict of a jury. We consider the evidence in a light
    most favorable to the verdict winner.
    J.J. DeLuca Company, Inc. v. Toll Naval Associates, 
    56 A.3d 402
    , 410
    (Pa. Super. 2012) (quotation marks, formatting, and citations omitted).
    The trial court ruled against Port Vue for two reasons. First, the trial
    court found that Port Vue failed to prove that Subcontractor’s work did not
    comply with the contract specifications, and thus did not breach its contract
    with Port Vue. See Trial Court Opinion, 7/17/19, at 8. Second, the trial court
    found that Port Vue’s own conduct excused Subcontractor’s continued
    performance under the contract.
    Id. at 8-9.
    To establish a breach of contract claim, a plaintiff must prove: (1) the
    existence of a contract, including its essential terms, (2) a breach of the
    contract; and, (3) resultant damages. J.F. Walker Co., Inc. v. Excalibur
    Oil Grp., Inc., 
    792 A.2d 1269
    , 1272 (Pa. Super. 2002).
    - 10 -
    J-A29025-19
    Here, viewing the evidence in the light most favorable to Subcontractor
    as the verdict winner, we conclude that the record supports the trial court’s
    finding that Port Vue failed to prove its case that Subcontractor did not comply
    with the contract specifications. Therefore, the trial court correctly concluded
    that Port Vue failed to establish a breach of contract claim against
    Subcontractor.2
    Furthermore, under Pennsylvania law, the conduct of one party that
    prevents the other from performing is an excuse for non-performance. A party
    is excused from performance under the contract if the other party's conduct
    impedes his performance. See Slater v. General Cas. Co. of Am., 
    25 A.2d 697
    , 699 (Pa. 1942); see also Liddle v. Scholze, 
    768 A.2d 1183
    , 1185 (Pa.
    Super. 2001).
    Similarly, we have held that “a material breach by one party to a
    contract entitles the non-breaching party to suspend performance.” Widmer
    Eng’g Inc. v. Dufalla, 
    837 A.2d 459
    , 467 (Pa. Super. 2003) (emphasis
    added). “‘If a breach constitutes a material failure of performance, then the
    non-breaching party is discharged from all liability under the contract.’”
    Id. (quoting Lane
    Enterprises v. L.B. Foster Co., 
    700 A.2d 465
    (Pa. Super.
    ____________________________________________
    2 Port Vue also asserted a claim for unjust enrichment. However, both parties
    acknowledged they had a written contract. Additionally, the trial court decided
    the case under contract principles. Where a written or express contract
    between the parties exists, the equitable theory of unjust enrichment does not
    apply. See Mitchell v. Moore, 
    729 A.2d 1200
    , 1203 (Pa. Super. 1999). We
    therefore confine our analysis to the contract theories of this case.
    - 11 -
    J-A29025-19
    1997), rev’d on other grounds, 
    710 A.2d 54
    (Pa. 1998) (internal citations
    omitted).
    Here, viewing the evidence in the light most favorable to Subcontractor
    as the verdict winner, we conclude that the record supports the trial court’s
    finding that Port Vue’s actions prevented Subcontractor from completing the
    project.
    The record also supports the trial court’s finding that Port Vue failed to
    deal with Subcontractor fairly and reasonably. “Every contract imposes a duty
    of good faith and fair dealing on the parties in the performance and the
    enforcement of the contract.” Giant Food Stores, LLC v. THF Silver Spring
    Dev., L.P., 
    959 A.2d 438
    , 447–48 (Pa. Super. 2008), appeal denied, 
    972 A.2d 522
    (2009) (citation omitted).         Under the circumstances of this case, Port
    Vue’s breach was material.3
    Applying the foregoing legal principles to this case, the trial court did
    not err in concluding that Subcontractor’s non-performance was excused. Port
    Vue’s third issue also warrants no relief.
    Judgment affirmed.
    ____________________________________________
    3 We note that the trial court did not specifically state that Port Vue’s breach
    was material. However, we infer that the trial court found it to be material
    based upon its conclusion that Subcontractor’s performance was excused, in
    part, because of Port Vue’s failure deal with Subcontractor in good faith and
    fair dealing.
    - 12 -
    J-A29025-19
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 3/30/2020
    - 13 -