Estate of James Kirk, Appeal of: James Kirk ( 2021 )


Menu:
  • J-S09032-21
    NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
    ESTATE OF: JAMES KIRK A/K/A           :    IN THE SUPERIOR COURT OF
    JAMES ALLEN KIRK A/K/A JAMES          :         PENNSYLVANIA
    ALLAN KIRK                            :
    :
    :
    APPEAL OF: ESTATE OF JAMES KIRK       :
    :
    :
    :    No. 1442 EDA 2020
    Appeal from the Decree Entered June 24, 2020
    In the Court of Common Pleas of Philadelphia County Orphans’ Court at
    No(s): No. 189DE of 2018
    BEFORE: OLSON, J., McCAFFERY, J., and MUSMANNO, J.
    MEMORANDUM BY MUSMANNO, J.:                          FILED APRIL 13, 2021
    The Estate of James Kirk (“the Estate”) appeals from the June 24, 2020,
    Decree, which reversed and vacated a Decree entered on January 17, 2020,
    and reinstated in its entirety a Decree entered on January 3, 2020.      The
    January 3, 2020, Decree had found in favor of Stapleton Roofing, Inc.
    (“Stapleton”). We affirm.
    For the purpose of this appeal, we adopt the trial court’s recitation of
    the factual and procedural history of the instant case, as set forth in its
    Opinion. See Trial Court Opinion, 11/2/20, at 1-6.
    The Estate presents the following claims for our review:
    A. Did the Orphans’ Court err when it found that the contract
    failed to satisfy the requirements of the Home Improvement
    Consumer Protection Act[,] 73 P.S. §[§] 517.1[-517.18, (“the
    Act”)] and entered an award in favor of [Stapleton] in quantum
    meruit?
    J-S09032-21
    B. Did the Orphans’ Court err in finding for “Stapleton Roofing,
    Inc.[,]” when the agreement was with “Stapleton Contract,
    Inc.[,]” an entity which does not exist?
    C. Did the Orphans’ Court err in finding that the amount due to
    [Stapleton], $61,716.03, was correctly calculated?
    D. Did the Orphans’ Court err by denying [the Estate’s] Motion for
    Reconsideration?
    Brief for Appellant at 5.
    As this Court has explained,
    [t]he findings of a judge of the [O]rphans’ [C]ourt division,
    sitting without a jury, must be accorded the same weight
    and effect as the verdict of a jury, and will not be reversed by an
    appellate court in the absence of an abuse of discretion or a lack
    of evidentiary support. This rule is particularly applicable to
    findings of fact which are predicated upon the credibility of the
    witnesses, whom the judge has had the opportunity to hear and
    observe, and upon the weight given to their testimony. In
    reviewing the Orphans’ Court’s findings, our task is to ensure that
    the record is free from legal error and to determine if the Orphans’
    Court’s findings are supported by competent and adequate
    evidence and are not predicated upon capricious disbelief of
    competent and credible evidence.
    When the trial court has come to a conclusion through the
    exercise of its discretion, the party complaining on appeal has a
    heavy burden. It is not sufficient to persuade the appellate court
    that it might have reached a different conclusion if, in the first
    place, charged with the duty imposed on the court below; it is
    necessary to go further and show an abuse of the discretionary
    power. An abuse of discretion is not merely an error of judgment,
    but if in reaching a conclusion the law is overridden or misapplied,
    or the judgment exercised is manifestly unreasonable, or the
    result of partiality, prejudice, bias or ill-will, as shown by the
    evidence of record, discretion is abused. A conclusion or judgment
    constitutes an abuse of discretion if it is so lacking in support as
    to be clearly erroneous.
    We are not constrained to give the same level of deference
    to the [O]rphans’ [C]ourt’s resulting legal conclusions as we are
    -2-
    J-S09032-21
    to its credibility determinations. We will reverse any decree based
    on palpably wrong or clearly inapplicable rules of law. … [W]e
    will not lightly find reversible error and will reverse
    an [O]rphans’ [C]ourt decree only if the Orphans’ [C]ourt applied
    an incorrect rule of law or reached its decision on the basis of
    factual conclusions unsupported by the record.
    In re Jackson, 
    174 A.3d 14
    , 23-24 (Pa. Super. 2017) (citation omitted). In
    the exercise of the limited jurisdiction conferred on it by            statute,
    the Orphans’ Court must apply the rules and principles of equity. Estate of
    Hahn, 
    369 A.2d 1290
    , 1292 (Pa. 1977); accord In re Estate of Pedrick,
    
    482 A.2d 215
    , 222 (Pa. 1984)
    The Estate first claims that the Orphans’ Court erred when, despite
    finding that the contract between the Estate and Stapleton failed to comply
    with the Act, the court nevertheless awarded Stapleton “the reasonable value
    of services performed pursuant to 73 P.S. § 517.7(g), under the theory of
    quantum meruit.” Brief for Appellant at 17 (emphasis omitted). The Estate
    argues that Stapleton never pled quantum meruit or unjust enrichment as a
    basis for relief. Id. According to the Estate, the Act applies to “compliant
    contractors.” Id. at 18 (emphasis omitted). The Estate asserts that “to allow
    quantum meruit [recovery] to non-compliant contractors would eviscerate the
    protections of the Act.” Id.
    The Estate argues that case law, including our Supreme Court’s holding
    in Shafer Elec. Constr. v. Mantia, 
    96 A.3d 989
     (Pa. 2014) (“Shafer
    Electric”), “simply allows quantum meruit recovery for contractors that have
    complied with the requirements of the Act, but was not intended to deny
    -3-
    J-S09032-21
    quantum meruit for contractors that were non-compliant with the Act.” Brief
    for Appellant at 18. The Estate argues that the trial court’s interpretation of
    the Act would allow contractors to recover for quantum meruit no matter how
    egregious the contractor’s non-compliance with the Act. 
    Id.
     According to the
    Estate, the record clearly indicates that Stapleton did not advise the Estate of
    “the basic material facts of the contract[,] and never required change orders
    for additional charges.” 
    Id.
    Issues of statutory interpretation present this Court with questions of
    law; accordingly, our standard of review is de novo, and our scope of review
    is plenary. Shafer Electric, 96 A.3d at 994. The interpretation of Section
    517.7(g) is guided by the Statutory Construction Act, 1 Pa.C.S.A. §§ 1501-
    1991. Pursuant to the Statutory Construction Act, the object of all statutory
    construction is to ascertain and effectuate the General Assembly’s intention.
    1 Pa.C.S.A. § 1921(a). When the words of a statute are clear and free from
    ambiguity, the letter of the statute is not to be disregarded under the pretext
    of pursuing its spirit. 1 Pa.C.S.A. § 1921(b). Finally, “it is not for the courts
    to add, by interpretation, to a statute, a requirement which the legislature did
    not see fit to include.” Commonwealth v. Rieck Inv. Corp., 
    213 A.2d 277
    ,
    282 (Pa. 1965); accord Shafer Electric, 96 A.3d at 994.
    Section 517.7(g) provides as follows:
    (g) CONTRACTOR’S RECOVERY RIGHT.— Nothing in this
    section shall preclude a contractor who has complied with
    subsection (a) from the recovery of payment for work performed
    based on the reasonable value of services which were requested
    -4-
    J-S09032-21
    by the owner if a court determines that it would be inequitable to
    deny such recovery.
    73 P.S. § 517.7(g).
    In its Opinion, the Orphans’ Court addressed the Estate’s claim and
    concluded that it lacks merit. See Orphans’ Court Opinion, 11/2/20, at 7-11.
    We agree with the sound reasoning of the Orphans’ Court and, discerning no
    error, affirm on this basis with regard to the Estate’s first claim. See id.
    In its second claim, the Estate argues that the Orphans’ Court
    improperly found in favor of “Stapleton Roofing, Inc.,” where the Estate’s
    agreement was with “Stapleton Contract, Inc.,” an entity that does not exist.
    Brief for Appellant at 19. The Estate argues that Stapleton Contracting, Inc.
    was never legally created, and there is no fictitious name registration for that
    entity. Id.
    In its Opinion, the Orphans’ Court addressed this claim and concluded
    that it lacks merit. See Orphans’ Court Opinion, 11/2/20, at 12-13. We agree
    with the sound reasoning of the Orphans’ Court, and affirm on the basis of its
    Opinion with regard to the Estate’s second claim. See id.
    In its third claim, the Estate challenges the Orphans’ Court’s calculation
    of the amount due to Stapleton. See Brief for Appellant at 19. According to
    the Estate, although the award is presumably based upon quantum meruit,
    there was no testimony regarding the value of the specific services rendered
    by Stapleton; there was no testimony regarding credit for items not
    performed; and there was no testimony regarding charges that were
    -5-
    J-S09032-21
    duplicative. Id. The Estate claims that change orders were never properly
    prepared or signed by the Estate. Id. at 20. Further, the Estate claims that
    “Stapleton charged for extras that were not included in the initial proposal[,]
    in almost every instance.” Id. In addition, the Estate asserts that there were
    contracted items never completed, such as sanding and refinishing of wood
    steps, and drywall of the outside walls.”     Id.   The Estate also directs our
    attention to Thomas Stapleton’s testimony that his company was paid
    $40,183.97. Id. However, the Estate asserted that Stapleton was paid a total
    of $50,183.97, as evidenced by a check. Id.
    The Orphans’ Court’s Opinion addresses this claim and concludes that it
    is without merit. See Orphans’ Court Opinion, 11/2/20, at 13-14. We agree
    with the Orphans’ Court’s reasoning and conclusion, and affirm on the basis
    of its Opinion with regard to the Estate’s third claim. See id.
    Finally, the Estate argues that the Orphans’ Court erred in not granting
    its Motion for Reconsideration. See Brief for Appellant at 21. However, the
    refusal of a trial court to reconsider a final decree is not reviewable on appeal.
    See Huntington Nat’l Bank v. K-Cor, Inc, 
    107 A.3d 783
    , 787 (Pa. Super.
    2014) (stating that “Pennsylvania case law is absolutely clear that the refusal
    of a trial court to reconsider, rehear, or permit reargument of a final decree is
    not reviewable on appeal.”) (quotation omitted).       We therefore affirm the
    Decree of the Orphans’ Court.
    Decree affirmed.
    -6-
    J-S09032-21
    Judgment Entered.
    Joseph D. Seletyn, Esq.
    Prothonotary
    Date: 4/13/2021
    -7-
    Circulated 03/31/2021 05:05 PM
    IN THE COURT OF COMMON PLEAS OF PHILADELPHIA
    ORPHANS' COURT DIVISION
    O.C. No. 189 DE of 2018
    Control #200283
    Estate of JAMES KIRK, Deceased
    OPINION SUR APPEAL
    Christina Lynne Parker, Administratrix of the Estate of James Kirk
    (hereinafter "Appellant") appeals the Orphans' Court's Decree dated June 24, 2020,
    which reversed and vacated the Decree of January 17, 2020 and reinstated, in its
    entirety, the Decree dated January 3, 2020, finding in favor of Stapleton Roofing,
    Inc. (hereinafter "Appellee").' The Orphans' Court issues this Opinion pursuant to
    Pa. R.A.P. 1925(a).
    Facts and Procedural Historv:
    Appellant was appointed Administratrix of the Estate of James Kirk, a/k/a
    James Allen Kirk, a/k/a James Allan Kirk on December 6, 2016. At the time of his
    death on February 15, 2016, Decedent, Appellant's father, owned a row home
    located    at    7462    Brockton       Road,        Philadelphia,   Pennsylvania     (hereinafter
    "Property"). Appellant retained licensed public insurance Adjuster Blaine Ronald
    Jelus (hereinafter "Adjuster Jelus") to represent the Estate in settling three property
    damage claims with Decedent's homeowners' insurance company, State Farm
    James Kirk, Deceased
    COPIES SENT PURSUANT TO Pa.R.C.P. 236(b) D. PATETE 11/02/2020
    1111111111111111111111111111111
    Insurance Company.       The Property suffered from storm, plumbing, and "death
    exposure" damage. As described by Adjuster Jelus: "[Appellant]'s father had died
    in the building, and Idid an adjustment there for death exposure from what happened
    when the body decomposed in the building. There were two previous claims: one
    for storm damage and one for failure of aplumbing system."' Adjuster Jelus referred
    Appellant to Tom Stapleton of Stapleton Roofing, Inc. (hereinafter "Appellee") to
    make the necessary repairs.'
    The value of the Property, as determined by Appellant in her petition for grant
    of letters filed with the Register of Wills, was $50,000. 4 Appellant submitted no
    conflicting proof of value. Appellee testified credibly that his agreement for repairs
    to the Property was drawn up to coincide with the insurance loss, 5 and was set forth
    on Exhibits P2 and P3 which were to be read together.' The initial proposal dated
    February 27, 2017 laid out the work to be completed for $67,400.00. 7The Contractor
    Agreement between the parties dated May 25, 2017 was prepared with the assistance
    of Adjuster Jelus, contained the terms of payment, and was signed in counterparts
    by Appellant and Appellee on May 25, 2017, and May 30, 2017, respectively,
    (hereinafter, the "Agreement").' The Agreement called for Appellee to complete all
    contracted work for $67,400.00 with the first $46,847.50 to be paid from insurance
    settlement proceeds and the remaining balance of $20,552.50 from the proceeds of
    the sale of the Property.'
    2
    During the course of the work, Appellant's husband David Parker (hereinafter
    "Mr. Parker") visited the job site multiple times each week and observed the
    Appellee's progress. 10 Mr. Parker renovated houses for profit in the past, though he
    was not doing the renovations in this instance because, according to him, he lacked
    funding. 11   Appellant and Appellee were on the job site at the same time once,
    approximately aweek prior to the completion of the work."
    Appellee and Adjuster Jelus testified that shortly after the work began it
    became apparent that additional repairs to the Property's plumbing and electrical
    systems would be necessary. 13 Work ceased so that Adjuster Jelus could inquire if
    the additional repairs might be covered and paid for by insurance. 14 After Adjuster
    Jelus determined that the additional repairs were not covered by insurance, he spoke
    with Appellant about the additional work, conveying to her that "they wouldn't be
    able to fix her home properly without the plumbing and electrical work being done,
    and she had to speak with [Appellee] directly.""       When asked whether he had
    discussed the repairs and their costs with Appellant, Adjuster Jelus testified "We had
    discussions over the phone." 16 Thereafter, Appellant told Appellee that "he had to
    go —move forward." 17
    Appellee performed and completed the additional work totaling $34,500.00. 18
    Shortly before the completion of work, Appellee was unable to contact Mr. Parker.
    "His phone was off, disconnected, not responding to any emails of the email that I
    3
    had at the present time." 19 Appellant contacted Appellee informing him that she
    would be his point of contact. 20 Sometime thereafter, Appellee finished work and
    was subsequently locked out of the Property.
    "[A] few weeks" after being locked out of the Property, Patrick Shea, Esq.,
    Appellant's attorney at the time, contacted Appellee. Attorney Shea provided
    Appellee with apunch list and anew phone number for Mr. Parker. 21 Mr. Parker
    instructed Appellee to, per the single item on the punch list, install sheetrock on the
    garage ceiling, and Appellee completed this item. 22 At this point, Appellee received
    $25,941.49 in payments from insurance proceeds by way of four checks. One check
    was for $10,000.00 and the other for $1,132.67, both dated June 23, 2017, and
    Appellee received and deposited both. 23 Appellee received two additional checks
    later that summer, dated July 21, 2017, in the amounts of $13,959.31 and $849.51,
    and Appellee received and deposited both. z4
    The day before settlement on the Property, having received no further
    payments, Appellee filed aMechanics Lien on the property for $75,958.51. 25 In
    order to complete the closing and remove the Mechanics Lien, the parties agreed that
    Appellant would immediately pay $14,242.48 to Appellee, with the parties' counsel
    opening ajoint escrow account in the amount of $61,716.03 from the sale proceeds
    to be deposited therein. The parties reduced the agreement for escrow to writing and
    funded the escrow account on December 15, 2017. 26 The property was sold for
    4
    $174,500. 27   Appellee was paid the $14,242.48. 28 Appellee testified that he
    completed all work and received a total of $40,183.97 in payments. 29             The
    Agreement was $67,400 for the contracted work, with an additional $34,500 agreed
    for the plumbing and electrical work.      $61,716.03 remained unpaid and due to
    Appellee.
    On February 16, 2018, Appellee, Petitioner below, filed aPetition to Show
    Cause Why the Administratrix Should Not Release Funds Held in Escrow, or in the
    alternative, File an Accounting for Audit with the Orphans' Court.          Appellant
    responded filing an Answer with New Matter and Counterclaims. In accordance
    with the Court's Case Management Decree, Appellee filed aMotion in Limine to
    preclude Appellant from calling witnesses or presenting documentary evidence for
    Appellant's failure to comply with the Decree. On May 6, 2019, that Motion was
    granted, however at trial, in the interest of justice, the undersigned Judge permitted
    Appellant to introduce limited documentary evidence and rebuttal testimony.
    Neither the Motion in Limine nor any issues arising from its determination are the
    subject of this appeal.
    Following the adjudicatory hearing held on June 26, 2019, and after
    consideration of all post-trial submissions, the Orphans' Court issued aDecree dated
    January 3, 2020 finding that Appellee, Stapleton Roofing, Inc., was entitled to
    recover in the amount of $61,716.03 for the reasonable value of services performed
    5
    pursuant to 73 P.S. §517.1(g)[sic], under quantum meruit. Said sum was ordered
    released from escrow in order to pay Appellee.
    On January 15, 2020, Appellant filed aMotion for Reconsideration of the
    January 3, 2020 Decree. The Court granted Appellant's request for reconsideration
    by Decree dated January 17, 2020 and gave Appellee time to respond. After review
    of the response and submission, the Orphans' Court issued aDecree dated June 24,
    2020, reversing and vacating the January 17, 2020 Decree and reinstating the
    January 3, 2020 Decree in its entirety. The timely appeal followed from the Decree
    dated June 24, 2020 reinstating the January 3, 2020 Decree in its entirety.
    Issues and Jurisdiction
    This Orphans' Court has jurisdiction over the underlying matter pursuant to
    20 Pa. C.S. Sections 711 and 712.
    Appellant filed its Pa. R.A.P. 1925(b) Statement of Matters Complained of on
    Appeal on August 17, 2020, pursuant to the Orphans' Court Decree dated July 27,
    2020. The Statement is neither concise nor clear, and the statement is repetitive,
    confusing, and lacking essential details while misstating others. In an attempt to
    fully and fairly address the issues, the Orphans' Court has restated the same, without
    repetition in aform most amenable to afair and fruitful discussion. Any issues not
    preserved should be dismissed from consideration.
    6
    The restated issues are as follows:
    I.      Did the Orphans' Court err when it found that the contract failed
    to satisfy the requirements of the Home Improvement Consumer
    Protection Act 73 P.S. §517.1 and entered an award in favor of
    Appellee in quantum meruit?
    II.     Did the Orphans' Court err in finding for "Stapleton Roofing, Inc."
    when the agreement was with "Stapleton Contracting, Inc." an
    entity which did not exist?
    III.    Did the Orphans' Court err in finding that the amount due to
    Appellee, $61,716.03, was correctly calculated?
    IV.      Did the Orphans' Court err by denying Appellant's Motion for
    Reconsideration?
    Discussion
    I.       The Orphans' Court did not err when it found that the contract failed
    to satisfy the requirements of the Home Improvement Consumer
    Protection Act 73 P.S. §517.1 and entered an award in favor of
    Appellee in quantum meruit.
    A. The Home Improvement Consumer Protection Act does not
    preclude recovery under atheory of quantum meruit.
    Appellant contends that the Home Improvement Consumer Protection Act
    disallows recovery by Appellee against ahome owner in quantum meruit unless a
    home improvement contract meets the requirements of 73 P.S. §517.7(a).
    This exact issue was addressed and answered by our learned Supreme Court
    in Shafer Electric & Construction v. Mantia wherein the Court stated that Section
    7
    517.7(g) "speaks only to the availability of remedies to acontractor who complies
    with Section 517.7(a)" ... and "does not contemplate the preclusion of common law
    equitable remedies such as quantum meruit when a party fails to comply with
    subsection (a). ""
    Appellant is mistaken regarding Supreme Court precedent. The Orphans'
    Court correctly determined that the contract between the parties did not satisfy the
    requirements of the Home Improvement Consumer Protection Act, and therefore
    was not an enforceable contract under the Act, however, as stated by the Supreme
    Court in Shafer Electric and Construction v. Mantia, that finding does not preclude
    the award of damages under quantum meruit. In accordance with Supreme Court
    precedent and supported by evidence of record, the Orphans' Court properly found
    that the Appellee Stapleton Roofing, Inc. was entitled to recovery under the common
    law principle of quantum meruit.
    B. The Orphans' Court properly applied the equitable
    remedy of Quantum Meruit.
    The Orphans' Court granted Appellee recovery under quantum meruit,
    "[which] is an equitable remedy to provide restitution for unjust enrichment in the
    amount of the reasonable value of services. "31 Quantum meruit requires the presence
    of three elements: "(1) benefits conferred on defendant by plaintiff, (2) appreciation
    of such benefits by defendant; and (3) acceptance and retention of such benefits
    8
    under such circumstances that it would be inequitable for defendant to retain the
    benefit without payment of value. "32 "In determining if the doctrine applies, our
    focus is not on the intention of the parties, but rather on whether the defendant has
    been unjustly enriched. "33 "Where unjust enrichment is found, the law implies a
    contract, which requires the defendant to pay to the plaintiff the value of the benefit
    conferred. ""
    Appellee's renovation of the Property resulted in the sale of ahouse, initially
    valued at $50,000.00, for $174,500.00. The renovation amounted to an increase in
    value of $124,500.00, from which Appellant only paid Appellee the total sum of
    $40,183.97. For Appellant to retain the net profit of $84,316.03 without adequately
    compensating Appellee is grossly unjust in that it was only through Appellee's labor
    and materials that the property was enriched.
    Appellant retained the services of Adjuster Jelus, alicensed public adjuster,
    who negotiated with the insurance company and provided estimates of damages and
    costs of repairs/replacement, totaling $101,900.00, in conformity with industry
    standards. All parties, including Appellant, agreed to the sum. The parties relied
    upon the expertise of Adjuster Jelus; neither party objected to his testimony or to the
    charges for additions. The Orphans' Court, as the trier of fact, found the testimony
    of Adjuster Jelus on the repairs needed, the associated costs, and inspections of the
    completed work, credible.
    9
    Appellant knew of all work performed because her husband David Parker
    personally observed the work being done and while using his prior contracting
    expertise, he passed along his observations as well as work proposals to Appellant."
    The Orphans' Court found Appellee's testimony as to his communications with
    David Parker more credible than Mr. Parker's denials of the same.      Further, the
    Orphans' Court found that Mr. Parker held himself out as and acted as Appellant's
    de facto project manager based on his presence on site, and his experience in
    rehabilitating and selling properties for profit. Appellant was aware that extra
    plumbing and electrical work was necessary. Appellant's insurance adjuster, Jelus,
    submitted a claim in the exact amount Appellee contends the work was worth.
    Appellant was physically present at the site after asubstantial amount of work had
    been completed. The Appellant locked Appellee out of the property sometime
    afterward, and then allowed him back on the property to complete aone item punch
    list, which Appellee completed.
    By allowing Appellee to continue working, Appellant accepted the benefits of
    Appellee's labor and materials; Appellant unjustly retained those benefits by not
    paying Appellee. Accordingly, it would be unjust to allow Appellant to retain the
    benefit of the increase in the value of the Property which directly resulted from
    Appellee's work. Therefore, the Orphans' Court properly concluded that all
    10
    elements for recovery in quantum meruit were present and that such arecovery was
    required.
    C. Appellee's pleadings were sufficient for the Court to grant recovery
    under quantum meruit.
    Appellant contends that the Court erred when it granted Appellee recovery
    under unjust enrichment which Petitioner did not plead.
    The Orphans' Court functioning in equity has broad discretion in determining
    relief and fashioning remedies.      Equitable remedies "are distinguished by their
    flexibility, their unlimited variety," and that there "is in fact no limit of their variety
    and application. 36
    In the instant case, Appellee averred sufficient facts in its Petition and proved
    at trial the reasonable value of its services for the work performed. Appellant hired
    Appellee hired in connection with the property damage claim submitted to the
    decedent's homeowner's insurance company, and for additional work not covered
    by insurance. Appellee completed the work. The property sold for $174,500.00 an
    increase of $124,500 over the initial property value, and Appellee had filed a
    mechanics lien in the amount of $75,958.51 due to non-payment. Pursuant to the
    written escrow agreement, Appellee withdrew its mechanics lien and received
    $14,242.49, with the balance of $61,716.03 placed into the escrow account held in
    the parties' attorneys' names. 17 The Orphans' Court, within its broad discretion
    while fashioning equitable remedies, properly awarded quantum meruit damages in
    11
    accordance with Appellee's request for the funds in escrow. Appellee's Petition
    filed in this matter plead facts sufficient for aclaim for quantum meruit, and the
    Orphans' Court is empowered to grant this relief.
    II.      The Orphans' Court did not err in finding for "Stapleton Roofing,
    Inc." when the Agreement used the entity name "Stapleton
    Contracting, Inc." where no entity with that exact name existed.
    Our Courts have consistently held that avariance in the name used by an entity
    will not necessarily bar that entity from recovery:
    The plaintiff ...is the person with whom defendants
    actually contracted, and they have received from it the
    goods they contracted to buy. It would be inequitable to
    permit that which as at best amere misnomer to prevent
    their being compelled to pay their just debt to the plaintiff.
    ... The proper plaintiff by its proper name has brought
    suit, and to escape the duty of paying for the goods which
    they bought and received, the defendants should at least
    show, if it be true, that they were in some manner
    prejudiced or injured by the plaintiff of an assumed name
    in the execution of the contract. 38
    Appellant has not shown, nor argued, that she was in some way prejudiced or injured
    by the difference in name on the Agreement. In the present situation, the reasons for
    permitting the entity of "Stapleton Roofing, Inc." to recover are justifiable, if not
    compelling.
    In finding for the Appellee, Orphans' Court gave great significance to the
    contents of Exhibit Rl, which consisted of six checks from Wells Fargo Home
    12
    Mortgage totaling $50,183.97 made payable to "Stapleton Roofing, Inc." and Estate
    of James A. Kirk. All but Check No. 4842 in the amount of $10,000.00 are endorsed
    by both Appellee and Appellant. 39
    The issuance and use of these checks conclusively establishes that all parties
    knew that "Stapleton Roofing, Inc." was the entity performing the services and was
    the entity bound to perform subject to the approval of the co-payee, the Estate of
    James A. Kirk. The fact that Appellant never objected to the name on these checks,
    and that Appellant endorsed them over to Stapleton Roofing, Inc. constituted clear
    and convincing evidence that Appellant acknowledged on behalf of the Estate that
    she had an agreement with Stapleton Roofing, Inc. and that it was the same as
    Stapleton Contracting, Inc.
    It must also be noted that the record is void of any evidence, or even an
    assertion that said use has caused any prejudice. Further, by endorsing the checks
    and using them to pay Stapleton Roofing, Inc. she not only acknowledged the
    business relationship between the Estate and Stapleton Roofing, Inc., but is also now
    estopped from denying its existence. 40
    III.     The Orphans' Court did not err in finding that the amount due to
    Appellee, $61,716.03, was correctly calculated.
    The Orphans' Court correctly calculated the amount due to Appellee. The
    parties agreed to pay Appellee $67,400.00 for the work set forth in the Agreement,
    13
    and the parties agreed to pay $34,500.00 for the additional work on the Property's
    plumbing and electrical systems, the work totaling $101,900.00.         The Orphans'
    Court credited Appellee with receipt of $40,183.97, composed of the five checks,
    and Appellee and Appellant endorsed each check: Check No. 4640 in the amount of
    $10,000.00, Check No. 4641 in the amount of $1,132.67, Check No. 6847 in the
    amount of $13,959.31, Check No. 7054 in the amount of $849.51, and Check. No.
    1187 in the amount of $14,242.48. 41 The Orphans' Court found Appellee's credible
    testimony that it never received Check No. 4842 in the amount of $10,000 clear and
    convincing. Accordingly, Appellee received $61,716.03 less than the agreed upon,
    reasonable value of his services.
    The Orphans' Court found the testimony presented by Appellee credible as to
    the payments received and the work performed. However, the testimony from
    Appellant's only witness, her husband, was riddled with inconsistencies, including
    the failure to come forth with testimony/evidence to rebut Appellee's showing that
    it was asking for the value of its services which it had not otherwise received.
    Regretfully, Appellant's complained of issue regarding the calculation of the
    amount awarded Appellee lacked such conciseness as to permit the Orphans' Court
    from giving amore specific discussion.
    14
    IV.    The Orphans' Court did not err by denying Appellant's Motion for
    Reconsideration.
    Appellant's allegation of error is based upon the incorrect assertion that the
    Motion for Reconsideration was denied. In fact, the Orphans' Court granted the
    motion on January 17, 2020, with the Orphans' Court vacating the prior January 3,
    2020 Decree wherein it found for Appellee. Thereafter, the Court did reconsider its
    decision and on June 24, 2020 reentered its January 3, 2020 Decree. Appellant's
    allegation that the Court did not render reconsideration is plainly incorrect.
    Regardless of Appellant's position, this Honorable Superior Court, as well as
    all other Pennsylvania Appellate Courts, has long held that an order denying a
    Motion for Reconsideration is not appealable.      In Blackburn v. King Investment
    Group, LLC, the Court held "Pennsylvania case law is absolutely clear that the
    refusal of atrial court to reconsider, rehear, or permit reargument of afinal decree is
    not reviewable on appeal.""
    Apparently, Appellant would have the Orphans' Court address the alleged
    errors regarding denying reconsideration as well as the alleged errors in its ultimate
    decision, basically attempting to require the Orphans' Court to answer the same
    errors twice. The Orphans' Court respectfully suggests this issue is improper and
    should require no further response.
    15
    Conclusion
    It is respectfully submitted that the Orphans' Court properly found that
    Appellant was liable to Appellee for the monetary value of the labors and materials
    by which she was unjustly enriched, even though recovery under the contract itself
    was barred by the Home Improvement Consumer Protection Act, 73 P.S. §517.1, et
    seq.   The Act was designed to prevent unfair and predatory practices by those in the
    home improvement industry. Especially important are the Act's requirements that
    in order for acovered home improvement contract to be enforceable, the contractor
    must register with the Pennsylvania Bureau of Consumer Protection, and the contract
    must conform to the Act's specific requirements. Our legislature wisely envisaged
    situations such as here, where, in reality the victim was not the homeowner, but the
    contractor.
    This Orphans' Court has not taken lightly its duty to extend relief only to
    prevent manifest injustice. It considered all relevant and credible evidence, such as
    the fact that the "homeowner" was pursuing renovations for purposes of financial
    gain upon resale and that the "homeowner" had not lived in the property or intended
    to live in the property in the future. Further, unlike most consumer homeowners,
    Appellant was aided by the expertise of alicensed public adjuster, her insurance
    company, and her husband with his experience in rehabbing properties in
    determining the value of the loss as well as the agreed upon cost of the subsequent
    16
    additions. The adjustment of the original loss was with the approval of Appellant,
    which established the value of repairs, leaving her argument that the Orphans' Court
    had no basis for calculating damages meritless. Likewise, the assistance rendered
    Appellant with her husband and her Adjuster, and her subsequent agreement with
    Appellee for subsequent repairs clearly established the value of services performed.
    In rendering its decision, the question of credibility was one of great
    importance. Appellant made allegations concerning performance of work and
    payments which simply did not comport with the documents or the evidence. And,
    Appellant did not establish other allegations of improper performance to any degree
    of particularity.
    Under all circumstances Appellant received the services that she actively and
    intelligently bargained for, and as has already been established, that bargaining
    cannot be legally enforced. However, the evidence surrounding the bargain firmly
    establishes the value of the services performed and thus the unjust enrichment
    conferred on Appellant.
    It is therefore respectfully submitted that the appeal of this Court's Decree be
    affirmed.
    17
    2-,,o   z-6
    Date                                       ATTHEW A. CARRAFIELLO, I
    Richard Colden, Jr., Esquire
    Robert DeLuca, Esquire
    1 As set forth in more detail below, the Orphans' Court Decree of January 3, 2020 was vacated
    by Decree dated January 17, 2020 which granted Appellant's request for reconsideration and
    gave Appellee time to respond. After review of the response and submission, the Orphans'
    Court issued its June 24, 2020 Decree reversing and vacating the January 17, 2020 Decree and
    reinstating the January 3, 2020 Decree in its entirety.
    2 N.T. p. 14-15.
    3N.T. p. 15. Appellee's president and owner operator, Thomas J. Stapleton, III, who at all times
    relevant acted on its behalf, is likewise referred to as "Appellee."
    4 Exhibit P1.
    5 N.T. p. 74,103.
    6 N.T. p. 76-77, 106.
    7 N.T. p. 75, Exhibit P2.
    'N.T. p. 77,108-09.
    9 Exhibit P3.
    to N.T. p. 85.
    11 N.T. p.    130.
    12 N.T. p.    88.
    13 N.T. p.   20, 84-85.
    14 N.T. p.   23, 85.
    15 N.T. p.   22-23.
    16 N.T. p.   23.
    17 id.
    " N.T. p. 86.
    N.T. p. 94.
    19
    20 id.
    N.T. p. 95.
    22 id.
    N.T. p. 78. A third check dated June 23, 2017 for $10,000.00 listed on Exhibit R1 was not
    received by Appellee, endorsed or deposited. N.T. p. 79.
    24 Exhibit R1.
    25 N.T. p. 81.
    26   Exhibit P8; Exhibit P9.
    27   N.T. p. 6, Stipulated Fact No. 15.
    18
    28   N.T. p. 81, Exhibit R1.
    29   N.T. p. 75, 85-86, 78-81.
    30Shafer Elec. & Const. v. Mantia, 
    626 Pa. 258
    , 269, 
    96 A.3d 989
    , 996 (2014).
    31 Durst v. Milroy Gen. Contracting, Inc.,
    
    2012 PA Super 179
    , 
    52 A.3d 357
    , 360 (2012) (citing
    Am. & Foreign Ins. Co. v. Jerry's Sport Ctr. ,Inc., 
    606 Pa. 584
    , 2A.3d 526, 532 fn. 8(2010) (citing
    Black's Law Dictionary (8th ed.2004)).
    32 Durst v. Milroy Gen. Contracting, Inc.,
    
    2012 PA Super 179
    , 
    52 A.3d 357
    , 360 (2012) (citing
    Schenck v. K.E. David, Ltd., 
    446 PA Super 94
    , 
    666 A.2d 327
     (1995).
    33 Id
    34 Id
    35    N.T. p. 141-42.
    36 See generally, Jackson v. Hendrick, 
    457 Pa. 405
    , 411, 
    321 A.2d 603
    , 606 (1974) (citing 1J.
    Pomeroy, Treatise on Equity Jurisprudence.)
    37 Petitioner's Petition to Show Cause Why the Administratrix Should Not Release Funds Held
    in Escrow, Or, in the Alternative, File an Accounting for Audit; See Durst v. Milroy General
    Contracting, Inc., 
    2012 PA Super 179
    , 
    52 A.3d 357
    , 360 (2012) (Finding that were the home
    owner had accepted and retained abenefit from the contractor, it would be inequitable for the
    home owner's to retain the home improvements without compensating the contractor.).
    38 Berg Co. v. Douredoure Bros., 5Pa. D. & C 597 (1925).
    39 N.T. p. 67, 78-81.
    40 See Stash & Sons v. New Holland Credit Co., 
    905 A.2d 541
     (Pa. Super. 2006) (Finding that
    Defendant below was estopped from using the Fictitious Names Act to claim Plaintiff lacked the
    legal capacity to sue when Defendant accepted the benefits of the business transactions, had full
    knowledge of the party's true identity notwithstanding the fictitious name, and did not show that
    they were harmed by the fictitious name.).
    41 N.T. p. 78-81.
    42 Blackburn v. King Inv. Grp., LLC, 
    2017 PA Super 89
    , 
    162 A.3d 461
    , 464 (2017) (quoting
    Provident Nat'l Bank v. Rooklin, 
    250 Pa.Super. 194
    , 
    378 A.2d 893
    , 897 (1977)).
    19