Sutton v. Catawba Power Co. , 104 S.C. 405 ( 1916 )


Menu:
  • July 3, 1916. The opinion of the Court was delivered by This is an action for damages to the lands of the plaintiff, alleged to have been caused by the erection of a dam across the Catawba River, a navigable stream.

    It is admitted by counsel that the dam was built, by authority of the General Assembly of South Carolina, in 1904, and that it is a permanent structure.

    The complaint thus describes the manner in which the lands in question were damaged:

    "That the large volumes of water stored by the said dam were and are diverted from their natural and proper channel, and were and are thrown upon and against the said lands, in much greater force and volume than they otherwise would have been, and would be; and, during the six years next before the commencement of this action, have continually undermined the embankments and washed away the same, thus subjecting the lands to the full destructive force of the floods. * * *"

    The defendant interposed the defense that the cause of action accrued more than six years before the commencement of this action, and is therefore barred by the statute of limitations.

    There was testimony to the effect that the injuries to the said lands commenced in 1905, and continued until the commencement of this action, on the 21st of July, 1913.

    At the close of the testimony, the defendant made a motion for a direction of a verdict, on the following grounds:

    "That the undisputed testimony shows that the alleged damage, if any, to plaintiff's land, arose from the construction of a dam across Catawba River, which dam was erected by legislative authority, and that the dam is a permanent structure, and that the undisputed proof shows that the plaintiff's cause of action arose more than six years before *Page 408 the commencement of this action, and that she is therefore barred by the statute of limitations. The undisputed testimony shows that the damages * * * after the erection of the dam began in June or July, 1905, and her cause of action arose at that time, for all damages, past, present, and prospective."

    The refusal of this motion is made the basis of the appeal.

    The statute of this State adopted in 1899 (23 statutes 207) authorizing the building of said dam contains the following proviso:

    "Provided, That said corporation shall be liable for all damages caused by building said dam."

    The general rule is thus stated in 21 Enc. of Law 724:

    "Since every continuance of a nuisance is a new nuisance, authorizing a fresh action, an action may be brought, for the recovery of all damages, resulting from the continuance of a nuisance, within the statutory period of the statute of limitations, for which no previous recovery has been had, even though the original cause of action is barred, unless the nuisance has been so long continued, as to raise the presumption of a grant, or in case of injury to real property, unless the plaintiff's right of entry is barred. But when the injury is of such a nature, that all the damages resulting therefrom, whether past or prospective, are recoverable in one action, the statute of limitations begins to run, from the time of the completed erection of the nuisance. This rule, however, is subject to the modification, that when the cause of action is the consequential injury, from an act of erection which is not, in itself, an actionable nuisance, the statute does not begin to run, until the injury is actually inflicted."

    In the case of Lawton v. Railway, 75 S.C. 82,55 S.E. 128, it was held that the negligent construction and maintenance of an embankment, across a natural stream, by which lands of another are flooded, is continuous in its nature, and an action may be brought for damages to the *Page 409 land, after six years from its construction, and damages awarded for the six years, before commencing the action. In that case the Court says:

    "The vital question in the case is whether the alleged negligent construction of the embankment across the watercourse, whereby the plaintiff's lands were overflowed and damaged, was a wrong, continuous in its nature."

    And, after reviewing the authorities, the Court proceeded as follows:

    "These authorities conclusively show that the alleged wrong was continuous in its nature, and that it was not alone the original negligent construction of the embankment that was capable of giving rise to a right of action."

    These authorities show that the motion was properly refused.

    Judgment affirmed. *Page 410

Document Info

Docket Number: 9439

Citation Numbers: 89 S.E. 353, 104 S.C. 405

Judges: MR. CHIEF JUSTICE GARY.

Filed Date: 7/3/1916

Precedential Status: Precedential

Modified Date: 1/13/2023