The Kitchen Planners v. Friedman ( 2020 )


Menu:
  •                     THE STATE OF SOUTH CAROLINA
    In The Court of Appeals
    The Kitchen Planners, LLC, Appellant,
    v.
    Samuel E. Friedman and Jane Breyer Friedman and
    Branch Banking and Trust, Respondents.
    Appellate Case No. 2017-001522
    Appeal From Richland County
    Robert E. Hood, Circuit Court Judge
    Opinion No. 5738
    Heard December 10, 2019 – Filed July 1, 2020
    AFFIRMED
    Jean Perrin Derrick, of Jean Perrin Derrick, LLC, of
    Lexington, for Appellant.
    Charles A. Krawczyk, of Finkel Law Firm, LLC, of
    Columbia, for Respondents.
    LOCKEMY, C.J.: The Kitchen Planners, LLC (Kitchen Planners) appeals the
    circuit court's order granting summary judgment in favor of Samuel E. and Jane
    Breyer Friedman (collectively, the Friedmans) as to Kitchen Planners' action for a
    mechanic's lien and foreclosure. Kitchen Planners argues the circuit court erred by
    (1) finding there was no genuine issue of material fact as to its claim for a
    mechanic's lien, (2) denying its motion to strike Mr. Friedman's affidavit, and (3)
    awarding attorney's fees to the Friedmans. We affirm.
    FACTS
    In 2015, the Friedmans and Kitchen Planners entered into a contract, pursuant to
    which Kitchen Planners was to provide and install kitchen cabinets in the
    Friedmans' home in exchange for $49,784.04, plus $2,995 for delivery and
    installation. The parties agreed the Friedmans would pay the contract price in
    three installments consisting of one-third at the time of ordering, one-third at the
    time of shipment, and the final third at the time of delivery. The Friedmans paid
    two-thirds of the contract price prior to delivery of the cabinets. However, when
    the cabinets arrived at their home on May 21, 2015, they were dissatisfied with the
    product and never paid the final one-third of the contract price.
    Kitchen Planners filed a mechanic's lien and statement of account on November
    12, 2015, pursuant to sections 29-5-10 to -440 of the South Carolina Code (2007 &
    Supp. 2019). It served the Friedmans on November 17, 2015, and filed its
    complaint and a lis pendens on January 13, 2015. Kitchen Planners alleged in its
    complaint that it "furnished materials, supplies, and labor beginning in or around
    March 16, 2015 and continuing through August 18, 2015." In their answer, the
    Friedmans asserted several defenses, including failure to properly file a mechanic's
    lien and violation of section 29-5-100. The Friedmans also asserted counterclaims
    against Kitchen Planners, including breach of contract, negligent supervision, and
    negligent misrepresentation. They alleged Kitchen Planners' measurements were
    incorrect and the cabinets had remained in their garage and were never installed in
    their home.
    Subsequently, on January 19, 2017, the Friedmans filed a motion titled "motion to
    dismiss mechanic's lien and foreclosure," requesting "dismissal pursuant to
    [sections] 29-5-10[ and] 29-5-100 and South Carolina Rule[] of Civil Procedure
    56(a) [sic]." They sought dismissal of the lien and of Kitchen Planners' causes of
    action with prejudice, arguing the lien was invalid and "there [wa]s no issue of fact
    to support" Kitchen Planners' claims.
    The Friedmans deposed Patricia Comose, the sole member of Kitchen Planners, on
    April 7, 2017. Comose testified she held a degree in interior design and a retail
    license that allowed her to purchase items at wholesale and sell them for retail
    value. She explained the Friedmans contacted her because they wished to purchase
    cabinets manufactured by Crystal Cabinets and she was the only dealer for Crystal
    Cabinets in the Columbia area. Comose stated the Friedmans had incurred water
    damage in their kitchen and "wanted the kitchen designed" to enable them to
    replace the cabinets. She recalled some of the elements of the design were the
    same as the existing designs. Comose stated she visited the Friedmans' home on
    January 23, 2015, and they signed a "design retainer agreement" and paid a $500
    retainer for the planning of the kitchen. The agreement provided that if the
    Friedmans decided to purchase the cabinets through Kitchen Planners, the $500 fee
    would be deducted from the purchase price. She stated they discussed the design
    several times between January 23 and March 16, 2015, and on March 16, Kitchen
    Planners and the Friedmans entered an agreement "for the ordering of the
    cabinets." Comose stated she purchased the cabinets for $28,953.58 and her profit
    margin was thirty-three percent. She acknowledged that prior to delivery of the
    cabinets, Kitchen Planners had already realized a profit of $4,175 and made
    additional profit from other items, such as the sink and the cabinet pulls. Comose
    explained that rather than charging by the hour, she earned profits by purchasing
    items at wholesale and selling them at retail and did not charge for her time
    "basically at all."
    Comose confirmed that when the cabinets were delivered to the Friedmans' home
    on May 20, 2015, they had some concerns with the product. Comose stated that
    when the installer arrived the next day to install the cabinets, Mr. Friedman told
    her he wanted the cabinets removed from the home and a refund. She recalled she
    and the installer spent several hours at the home that day, unboxing the cabinets
    and setting them in place so the Friedmans could see how they would look.
    Comose stated she offered to reorder any portions of the cabinets they were
    dissatisfied with. She testified she spent the next two or three days preparing a list
    of items to reorder. Comose stated that when she began reordering items, the
    Friedmans removed her from the project. She explained the Friedmans contacted
    Crystal Cabinets directly and Derrick Tackett, a sales representative, took over the
    reorder process. Comose stated the Friedmans arranged with Tackett to pay dealer
    cost for the reorder. Comose stated she did not "have anything more to do with the
    project" after June 18 when Tackett informed her the Friedmans did not want her
    to be involved. Comose agreed that on August 18, 2015, she received an email
    from Tackett informing her the Friedmans had taken him off the job as well.
    Comose admitted, "I understand that we were not allowed to install [the cabinets]."
    When asked about a check for $550.61 paid on September 29, 2015, for "a re-order
    of boxes" for the kitchen island, she explained she reordered drawer boxes after
    Mrs. Friedman complained the boxes they received "could have been deeper."
    However, Comose did not know why she wrote this check in September as
    opposed to an earlier date, and she commented, "And I have those, by the way."
    On April 13, 2017, the Friedmans served a copy of Mr. Friedman's affidavit upon
    Kitchen Planners by mail. The Friedmans then filed a memorandum titled
    "memorandum in support of defendant's motion for summary judgment" on April
    20, 2017. On April 24, 2017, Kitchen Planners filed a motion to strike the
    affidavit, arguing it was improper because (1) the Friedmans filed a motion to
    dismiss and motions to dismiss must be determined by the pleadings only and (2)
    the affidavit should have been served concurrently with the Friedmans' motion
    pursuant to Rule 6, SCRCP. It also served and filed Comose's affidavit in
    opposition, in which she stated she continued to work with Tackett "through
    November 2015." Comose stated, "For example, on September 29, 2015, I
    reordered drawer boxes for the island in the kitchen, and paid $550.61."
    Additionally, she attested another contractor, Viggiano Remodeling, finished the
    project and "utilized some of the cabinets [she] furnished." In support of this, she
    attached the contractor's estimate, which stated, "All useable hardware and drawers
    from the existing Crystal cabinets will be reflected as a credit in final price."
    The circuit court heard the Friedmans' motion on April 25, 2017. At the outset of
    the hearing, Kitchen Planners moved to strike Mr. Friedman's affidavit, relying on
    its written motion to strike and arguing the document was outside of the pleadings
    and untimely. The Friedmans argued they timely served the affidavit and their
    motion was a Rule 56, SCRCP, motion for summary judgment rather than a Rule
    12(b)(6), SCRCP, motion to dismiss. The court denied the motion to strike, noting
    Kitchen Planners had sufficient time to review and submit a response to the
    affidavit. The court then proceeded with the hearing as a hearing on a motion for
    summary judgment, and Kitchen Planners did not object.
    The circuit court granted the Friedmans' motion, finding there was no question of
    material fact that Kitchen Planners failed to timely file and serve the lien according
    to section 29-5-90. See § 29-5-90 (providing that "within ninety days after he
    ceases to labor on or furnish labor or materials for such building," a person seeking
    to enforce a mechanic's lien must "serve[] upon the owner . . . a statement of a just
    and true account of the amount due him"). It reasoned the face of the lien stated
    Kitchen Planners furnished materials and labor from "on or about March 11, 2015
    through on or about August 18, 2015," and it served the lien on November 17,
    2015—which was a difference of ninety-one days. The court noted "no credible
    evidence exist[ed] to show [Kitchen Planners] provided any materials or labor"
    after August 18. Additionally, it concluded the materials furnished were not
    actually used in the erection, alteration, or repair of a building and that Kitchen
    Planners knowingly claimed more than it was due in violation of section 29-5-100
    and failed to commence the foreclosure action within six months. Kitchen
    Planners filed a motion to reconsider pursuant to Rule 59(e), SCRCP, which the
    circuit court denied. This appeal followed.
    ISSUES ON APPEAL
    1. Did the circuit court err by granting the Friedmans' motion for summary
    judgment?
    2. Did the circuit court err by denying Kitchen Planners' motion to strike?
    3. Did the circuit court err by awarding attorney's fees to the Friedmans?
    STANDARD OF REVIEW
    "When reviewing an order granting summary judgment, the appellate court applies
    the same standard as the trial court." David v. McLeod Reg'l Med. Ctr., 
    367 S.C. 242
    , 247, 
    626 S.E.2d 1
    , 3 (2006). "On appeal from an order granting summary
    judgment, the appellate court will review all ambiguities, conclusions, and
    inferences arising in and from the evidence in a light most favorable to the
    non-moving party below." Hurst v. E. Coast Hockey League, Inc., 
    371 S.C. 33
    , 36,
    
    637 S.E.2d 560
    , 561-62 (2006). "Summary judgment is appropriate when 'the
    pleadings, depositions, answers to interrogatories, and admissions on file, together
    with the affidavits, if any, show that there is no genuine issue as to any material
    fact and that the moving party is entitled to a judgment as a matter of law.'"
    Hansson v. Scalise Builders of S.C., 
    374 S.C. 352
    , 354-55, 
    650 S.E.2d 68
    , 70
    (2007) (quoting Rule 56(c), SCRCP). "[I]n cases applying the preponderance of
    the evidence burden of proof, the non-moving party is only required to submit a
    mere scintilla of evidence in order to withstand a motion for summary judgment."
    Hancock v. Mid-S. Mgmt. Co., 
    381 S.C. 326
    , 330, 
    673 S.E.2d 801
    , 803 (2009). "A
    court considering summary judgment neither makes factual determinations nor
    considers the merits of competing testimony; however, summary judgment is
    completely appropriate when a properly supported motion sets forth facts that
    remain undisputed or are contested in a deficient manner." Gecy v. S.C. Bank &
    Tr., 
    422 S.C. 509
    , 516, 
    812 S.E.2d 750
    , 754 (Ct. App. 2018) (quoting M&M Grp.,
    Inc. v. Holmes, 
    379 S.C. 468
    , 473, 
    666 S.E.2d 262
    , 264 (Ct. App. 2008)).
    "When evidence is susceptible to more than one reasonable inference, the issue
    should be submitted to the jury." Murphy v. Tyndall, 
    384 S.C. 50
    , 54, 
    681 S.E.2d 28
    , 30 (Ct. App. 2009).
    LAW/ANALYSIS
    I. Summary Judgment
    Kitchen Planners argues the circuit court erred by granting summary judgment in
    favor of the Friedmans. We disagree.
    A. Mechanic's Lien
    "A mechanic's lien is purely statutory. Therefore, the requirements of the statute
    must be strictly followed." Butler Contracting, Inc. v. Court St., LLC, 
    369 S.C. 121
    , 130, 
    631 S.E.2d 252
    , 257 (2006); see also Shelley Constr. Co. v. Sea Garden
    Homes, Inc., 
    287 S.C. 24
    , 27, 
    336 S.E.2d 488
    , 490 (Ct. App. 1985) ("[M]echanic's
    liens are purely statutory and can only be acquired and enforced in accordance with
    the conditions of the statute creating them.").
    Sections 29-5-10 to -440 of the South Carolina Code (2007 & Supp. 2019) set forth
    the requirements for establishing and enforcing a mechanic's lien. "The statutory
    process encompasses several steps, including the (1) creation, (2) perfection, and
    (3) enforcement of the lien." Ferguson Fire & Fabrication, Inc. v. Preferred Fire
    Prot., L.L.C., 
    409 S.C. 331
    , 340, 
    762 S.E.2d 561
    , 565 (2014). "For . . . [the] lien to
    become valid, the lien must be perfected and enforced in compliance with South
    Carolina's mechanic's lien statutes." 
    Id. at 342
    , 762 S.E.2d at 566. Section
    29-5-10(a) provides,
    A person to whom a debt is due for labor performed or
    furnished or for materials furnished and actually used in
    the erection, alteration, or repair of a building . . . by
    virtue of an agreement with, or by consent of, the owner
    of the building . . . shall have a lien upon the building or
    structure and upon the interest of the owner of the
    building . . . to secure the payment of the debt due to
    him. . . . As used in this section, labor performed or
    furnished in the erection, alteration, or repair of any
    building or structure upon any real estate includes the
    preparation of plans, specifications, and design
    drawings . . . . As used in this section, materials
    furnished and actually used include tools, appliances,
    machinery, or equipment supplied for use on the building
    or structure to the extent of their reasonable rental value
    during their actual use. . . . For purposes of this section,
    the term "materials" includes flooring, floor coverings,
    and wall coverings.
    "[W]hen the labor is performed or material is furnished, the right exists but the lien
    has not been perfected." Ferguson Fire, 409 S.C. at 341, 762 S.E.2d at 566
    (quoting Butler Contracting, 
    369 S.C. at 128
    , 
    631 S.E.2d at 256
    )). "Any material
    supplied for improving real estate by the erection of a building or structure
    ordinarily gives rise to a mechanics' lien. Materials must, of course, be
    incorporated into the structure or become fixtures." 22 S.C. Jur. Mechanics' Liens
    § 14 (2020) (footnotes omitted).
    Section 29-5-90 provides that "within ninety days after he ceases to labor on or
    furnish labor or materials for such building," a person seeking to enforce a
    mechanics lien must "serve[] upon the owner . . . a statement of a just and true
    account of the amount due him." Otherwise, the "lien shall be dissolved." Id.; see
    also Butler Contracting, 
    369 S.C. at 131
    , 
    631 S.E.2d at 257
     ("The deadline to
    serve . . . a mechanic's lien begins running from the date the last material was
    furnished . . . ."). The court in Butler explained,
    [W]he[n] a claimant, after a contract is substantially
    completed, . . . furnishes additional material [that] is
    necessary for the proper performance of his contract, and
    which is done in good faith at the request of the owner or
    for the purpose of fully completing the contract, and not
    merely as a gratuity or act of friendly accommodation,
    the period for filing the lien will run from
    the . . . furnishing of such materials, irrespective of the
    value thereof.
    Butler Contracting, 
    369 S.C. at 130-31
    , 
    631 S.E.2d at 257
     (first alteration in
    original) (quoting Wood v. Hardy, 
    235 S.C. 131
    , 140, 
    110 S.E.2d 157
    , 161 (1959)).
    Thus, as we stated in Shelley Construction,
    [T]o perfect and enforce the lien against the property, the
    person claiming it must: (1) serve and record a certificate
    of lien within ninety days after he ceases to furnish labor
    or materials . . . ; (2) bring suit to foreclose the lien
    within six months after he ceases to furnish labor or
    materials . . . ; and (3) file notice of pendency of the
    action within six months after he ceases to furnish labor
    or materials . . . .
    287 S.C. at 27, 336 S.E.2d at 490 (emphases added). If the person claiming the
    lien "fails to take any one of these steps, the lien against the property is dissolved."
    Id.1
    Section 29-5-100 provides "[n]o inaccuracy in [the] statement relating to the
    property to be covered by the lien, if the property can be reasonably recognized, or
    in stating the amount due for labor or materials shall invalidate the proceedings,
    unless it appear that the person filing the certificate has wil[l]fully and knowingly
    claimed more than is his due." See also Zepsa Constr. Inc. v. Randazzo, 
    357 S.C. 32
    , 38, 
    591 S.E.2d 29
    , 31-32 (Ct. App. 2004) (holding overhead and profit are
    recoverable under the mechanic's lien statute only "in the limited situation where
    the terms of overhead and profit are agreed upon by the parties and are
    subsequently embodied within a contract").
    "Minor imperfections and mistakes in the complaint or petition to foreclose a lien
    do not affect its validity." 22 S.C. Jur. Mechanics' Liens § 19 (2020). "The court
    may at any time allow either party to amend his pleadings as in other civil actions."
    § 29-5-180; see also 22 S.C. Jur. Mechanics' Liens § 19 ("Allegations in a
    complaint to foreclose a mechanics' lien may be amended."). However, "[i]t is
    well settled that parties are judicially bound by their pleadings unless withdrawn,
    altered or stricken by amendment or otherwise." Postal v. Mann, 
    308 S.C. 385
    ,
    387, 
    418 S.E.2d 322
    , 323 (Ct. App. 1992)); see also Johnson v. Alexander, 
    413 S.C. 196
    , 202, 
    775 S.E.2d 697
    , 700 (2015) ("Parties are generally bound by their
    pleadings and are precluded from advancing arguments or submitting evidence
    contrary to those assertions."); Postal, 308 S.C. at 387, 418 S.E.2d at 323 ("The
    allegations, statements, or admissions contained in a pleading are conclusive as
    against the pleader and a party cannot subsequently take a position contradictory
    of, or inconsistent with, his pleadings and the facts which are admitted by the
    pleadings are taken as true against the pleader for the purpose of the action.").
    1
    We also noted dissolution of the lien would not preclude a claimant from
    maintaining an action on the debt. See id.; § 29-5-420 ("Nothing in this chapter
    shall be construed to prevent a creditor in such contract from maintaining an action
    thereon in like manner as if he had no such lien for the security of his debt.").
    1. Timeliness
    Kitchen Planners contends it timely served and filed its mechanic's lien pursuant to
    section 29-5-90, an amendment pursuant to section 29-5-180 could easily cure the
    "slight discrepancy" between the date alleged in the lien and the actual date of the
    last work, and any inaccuracy in the statement of account would not invalidate the
    proceedings pursuant to section 29-5-100. Kitchen Planners argues that although
    its lien stated it last furnished materials or labor "on or about August 18, 2015,"
    evidence showed its work did not conclude until September 29, 2015, when it
    reordered drawer boxes and issued a check to Crystal Cabinets for $550.61. It
    argues it served and filed its lien within ninety days of September 29, 2015.
    Kitchen Planners asserts that it also timely commenced the suit for foreclosure on
    January 13, 2016, which was less than six months after the last work it performed.
    We disagree.
    First, we find Kitchen Planners is bound by the dates asserted in its pleadings and
    on the face of the lien. A claimant seeking to enforce a mechanic's lien must
    strictly follow the requirements of the statute. See Butler Contracting, 
    369 S.C. at 130
    , 
    631 S.E.2d at 257
    . To perfect a mechanic's lien, a claimant must "serve and
    record a certificate of lien within ninety days after he ceases to furnish labor or
    materials." Shelley Constr. Co., 287 S.C. at 27, 336 S.E.2d at 490 (emphases
    added); see also § 29-5-90. Here, on the face of the lien, Kitchen Planners asserted
    its lien was for materials and labor furnished "beginning on or about March 11,
    2015 through on or about August 18, 2015." In its complaint, Kitchen Planners
    asserted its lien was for labor and materials furnished beginning "in or around
    March 16, 2015 and continuing through August 18, 2015." Thus, we find Kitchen
    Planners is bound by the dates asserted in its pleadings and on the face of the lien.
    See Johnson, 413 S.C. at 202, 775 S.E.2d at 700; see also Postal, 308 S.C. at 387,
    418 S.E.2d at 323. Although Kitchen Planners argues it was entitled to amend its
    complaint to change the date it last provided materials, it never requested leave of
    the circuit court to amend its pleadings; rather, it raises this argument for the first
    time on appeal. Thus, we find this argument is unpreserved. See Herron v.
    Century BMW, 
    395 S.C. 461
    , 465, 
    719 S.E.2d 640
    , 642 (2011) ("At a minimum,
    issue preservation requires that an issue be raised to and ruled upon by the trial
    judge. It is 'axiomatic that an issue cannot be raised for the first time on appeal.'"
    (citation omitted) (quoting Wilder Corp. v. Wilke, 
    330 S.C. 71
    , 76, 
    497 S.E.2d 731
    ,
    733 (1998))).
    Second, we find the evidence was not sufficient to contest the Friedmans' assertion
    that August 18, 2015, was the last date labor or materials were furnished. Neither
    Comose's testimony nor her statement in her affidavit that she paid for a reorder of
    drawer boxes on September 29, 2015, created a genuine issue of material fact as to
    when Kitchen Planners last furnished materials. See Gecy, 422 S.C. at 516, 812
    S.E.2d at 754 ("[S]ummary judgment is completely appropriate when a properly
    supported motion sets forth facts that remain undisputed or are contested in a
    deficient manner." (quoting M&M Grp., 379 S.C. at 473, 666 S.E.2d at 264)).
    Here, Comose testified she provided no materials to the Friedmans after June 18,
    2015, and did not know why she did not pay for the drawer boxes until September
    29. Although she explained she reordered the drawer boxes because Mrs.
    Friedman pointed out they could have been deeper, she never stated the Friedmans
    specifically requested or directed her to reorder them. Comose offered no
    testimony or other evidence to show these drawer boxes were ever delivered to the
    Friedmans, and when she testified about this reorder, she stated, "And I have those,
    by the way." Viewing the evidence in the light most favorable to Kitchen
    Planners, we find the only inference to be gleaned from this testimony is that these
    additional items were never delivered to the Friedmans or installed in their home.
    See § 29-5-10 (providing materials must be "furnished and actually used in the
    erection, alteration, or repair of a building" to give rise to a lien (emphasis added));
    22 S.C. Jur. Mechanics' Liens § 14 (noting the materials furnished must ordinarily
    "be incorporated into the structure or become fixtures"); Shelley Constr. Co., 287
    S.C. at 27, 336 S.E.2d at 490 ("[T]o perfect and enforce the lien against the
    property, the person claiming it must . . . serve and record a certificate of lien
    within ninety days after he ceases to furnish labor or materials . . . ."); Butler
    Contracting, 
    369 S.C. at 130-31
    , 
    631 S.E.2d at 257
     ("[W]he[n] a claimant, after a
    contract is substantially completed, . . . furnishes additional material [that] is
    necessary for the proper performance of his contract, and which is done in good
    faith at the request of the owner or for the purpose of fully completing the contract,
    and not merely as a gratuity or act of friendly accommodation, the period for filing
    the lien will run from the . . . furnishing of such materials, irrespective of the value
    thereof." (first alteration in original) (quoting Wood, 
    235 S.C. at 140
    , 
    110 S.E.2d at 161
    )). Accordingly, we find the evidence and the pleadings show there was no
    genuine issue of material fact as to the date—August 18, 2015—that Kitchen
    Planners last furnished materials to the Friedmans. Ninety days from August 18,
    2015, would have been November 16, 2015; Kitchen Planners served the
    Friedmans on November 17, 2015, which was ninety-one days after Kitchen
    Planners last furnished materials to the Friedmans. Therefore, we find the circuit
    court did not err by concluding Kitchen Planners failed to timely serve the lien.
    Further, because Kitchen Planners failed to serve the lien within ninety days, it
    must be dissolved, regardless of whether the foreclosure action was filed within six
    months.2 See Shelby Constr., 287 S.C. at 27, 336 S.E.2d at 490 (stating if a person
    claiming a lien fails to take any one of the three steps required to perfect and
    enforce the lien, the lien against the property is dissolved). Based on the
    foregoing, we find the circuit court did not err by granting the Friedmans' motion
    for summary judgment.
    2. Actual Use
    Next, Kitchen Planners argues there is a genuine issue of material fact as to
    whether its labor or materials were installed in the Friedmans' home. It contends
    Viggiano's estimate demonstrated some of the materials it furnished were installed
    and argues it satisfied section 29-5-10 because it performed all of the labor
    required under the contract, which was used in the design of the kitchen. Kitchen
    Planners concedes it recovered the actual wholesale cost of the cabinets but argues
    it spent "hundreds of hours" designing and implementing the remodeling of the
    kitchen and was entitled to the balance of the contract price for its labor and the
    expense of the cabinets.3 We disagree.
    Viewing the evidence in the light most favorable to Kitchen Planners, we find it
    failed to show the materials were actually used in the Friedmans' home. See
    § 29-5-10 ("A person to whom a debt is due for . . . materials furnished and
    actually used in the erection, alteration, or repair of a building . . . shall have a lien
    upon the building . . . to secure the payment of the debt due to him." (emphasis
    2
    We note Kitchen Planners argues the circuit court should not have made
    decisions concerning credibility when, in denying her motion to reconsider, the
    court stated Comose's affidavit "was not credible as it was a self-serving
    statement" and contradicted all other evidence, including Comose's deposition.
    Though we note witness credibility is not a proper consideration in deciding a
    motion for summary judgment, given our standard of review on appeal, we need
    not consider this argument. See David, 
    367 S.C. at 247
    , 
    626 S.E.2d at 3
     ("When
    reviewing an order granting summary judgment, the appellate court applies the
    same standard as the trial court."); Gecy, 422 S.C. at 516, 812 S.E.2d at 754 ("A
    court considering summary judgment neither makes factual determinations nor
    considers the merits of competing testimony . . . ." (quoting M&M Grp., Inc., 379
    S.C. at 473, 666 S.E.2d at 264)).
    3
    Kitchen Planners asserts Comose's hourly rate was $125 per hour. However, this
    figure does not appear in the record. Further, the record contains no evidence as to
    the number of hours Kitchen Planners spent on the project.
    added)); 22 S.C. Jur. Mechanics' Liens § 14 (noting the materials furnished must
    "be incorporated into the structure or become fixtures"). In their answer, the
    Friedmans asserted the cabinets were never installed. In its responsive pleading,
    Kitchen Planners admitted those allegations, and Comose acknowledged the
    cabinets were not installed. Although Kitchen Planners asserts that because the
    Friedmans refused to allow the cabinets to be installed they should be estopped
    from avoiding the lien on this basis, it raises this argument for the first time on
    appeal. See Herron, 
    395 S.C. at 465
    , 
    719 S.E.2d at 642
     ("It is 'axiomatic that an
    issue cannot be raised for the first time on appeal.'" (quoting Wilder Corp., 
    330 S.C. at 76
    , 
    497 S.E.2d at 733
    )). Further, the Viggiano estimate does not create a
    genuine issue of material fact because the statement "[a]ll useable hardware and
    drawers from the existing Crystal cabinets will be reflected as a credit in final
    price" is not probative of whether any such items were actually installed. Based on
    the foregoing, we find the only reasonable inference that can be drawn from the
    pleadings and evidence is that the materials were never installed in the Friedmans'
    home. See Hansson, 374 S.C. at 354-55, 650 S.E.2d at 70 ("Summary judgment is
    appropriate when 'the pleadings, depositions, answers to interrogatories, and
    admissions on file, together with the affidavits, if any, show that there is no
    genuine issue as to any material fact and that the moving party is entitled to a
    judgment as a matter of law.'" (quoting Rule 56(c), SCRCP)). Accordingly, we
    find there was no genuine issue of material fact as to whether the materials were
    installed in the Friedmans' home.
    3. Overhead and Profit
    Kitchen Planners contends the circuit court erred by concluding it claimed more
    than it was entitled to under the lien in violation of section 29-5-100. See
    § 29-5-100 (providing an "inaccuracy . . . in stating the amount due for labor or
    materials shall invalidate the proceedings[ if] it appear[s] that the person filing the
    certificate has wil[l]fully and knowingly claimed more than is his due"); see also
    Zepsa Constr. Inc., 
    357 S.C. 32
    , 
    591 S.E.2d 29
     (holding overhead and profit are
    recoverable only "in the limited situation where the terms of overhead and profit
    are agreed upon by the parties and are subsequently embodied within a contract").
    Because we have concluded Kitchen Planners failed to satisfy the statutory
    requirements to establish the existence of a valid lien, we need not address this
    issue. See Futch v. McAllister Towing of Georgetown, Inc., 
    335 S.C. 598
    , 613, 
    518 S.E.2d 591
    , 598 (1999) (stating an appellate court need not address remaining
    issues when its determination of a prior issue is dispositive).
    For the foregoing reasons, we find there was no genuine issue of material fact as to
    Kitchen Planners' claim for a mechanic's lien and foreclosure. Thus, we find the
    circuit court did not err by granting summary judgment in favor of the Friedmans.
    II. Motion to Strike
    Kitchen Planners argues the Friedmans failed to serve Mr. Friedman's affidavit
    with their motion to dismiss and therefore the circuit court erred by denying its
    motion to strike the affidavit as untimely pursuant to Rule 6(d), SCRCP.
    Additionally, it contends the circuit court erred by allowing the Friedmans to
    convert a motion to dismiss into a motion for summary judgment. We disagree.
    First, we find unpreserved Kitchen Planners' argument the circuit court improperly
    treated the motion to dismiss as a motion for summary judgment because it
    advances this argument for the first time on appeal. See Herron, 
    395 S.C. at 465
    ,
    
    719 S.E.2d at 642
     ("It is 'axiomatic that an issue cannot be raised for the first time
    on appeal.'" (quoting Wilder Corp., 
    330 S.C. at 76
    , 
    497 S.E.2d at 733
    )).
    Regardless, even assuming the argument is preserved, we find the circuit court did
    not err by treating the motion as one for summary judgment. Rule 12(b), SCRCP,
    provides:
    If, on a motion . . . to dismiss for failure of the pleading
    to state facts sufficient to constitute a cause of action,
    matters outside the pleading are presented to and not
    excluded by the [c]ourt, the motion shall be treated as
    one for summary judgment and disposed of as provided
    in Rule 56, and all parties shall be given reasonable
    opportunity to present all material made pertinent to such
    a motion by Rule 56.
    (emphasis added). When the court treats a motion to dismiss as a motion for
    summary judgment, the "parties shall be given reasonable opportunity to present
    all material made pertinent to such a motion by Rule 56." See Rule 12(b), SCRCP.
    Here, although the Friedman's motion was titled "motion to dismiss," the body of
    the motion referenced only Rule 56 and did not reference Rule 12(b)(6).
    Therefore, we find the reference to Rule 56 in the body of motion was sufficient to
    place Kitchen Planners on notice that the Friedmans intended to proceed with a
    motion for summary judgment. Kitchen Planners did not argue it had an
    insufficient opportunity to present evidence in opposition to the Friedmans' motion,
    and in fact it did present evidence in opposition. Accordingly, even assuming the
    issue is preserved, we find the circuit court did not err by treating the motion as a
    motion for summary judgment.
    Finally, we find the circuit court did not abuse its discretion by refusing to strike
    Mr. Friedman's affidavit. See Peterson v. Nat'l R.R. Passenger Corp., 
    365 S.C. 391
    , 399, 
    618 S.E.2d 903
    , 907 (2005) ("The admission of evidence is within the
    sound discretion of the trial judge, and absent a clear abuse of discretion
    amounting to an error of law, the trial court's ruling will not be disturbed on
    appeal."). Rule 6(d), SCRCP, provides, "A written motion . . . shall be served not
    later than ten days before the time specified for the hearing . . . . When a motion is
    to be supported by affidavit, the affidavit shall be served with the motion . . . ."
    However, Rule 56, SCRCP, governs motions for summary judgment and does not
    require that the moving party support its motion with affidavits. See Rule 56(b),
    SCRCP ("A party against whom a claim, counterclaim, or cross-claim is
    asserted . . . may, at any time, move with or without supporting affidavits for a
    summary judgment in his favor as to all or any part thereof." (emphases added)).
    Pursuant to Rule 56(c), the party moving for summary judgment must serve the
    motion at least ten days before the hearing. Rule 56(c), SCRCP. Here, the motion
    for summary judgment was filed on January 17, 2017. The hearing on the
    Friedmans' motion was held April 25, 2017. Although they filed their
    memorandum and exhibits on April 20, 2017, the Friedmans served Kitchen
    Planners with Mr. Friedman's affidavit on April 13, 2017. Further, Kitchen
    Planners had an opportunity to—and did submit—an opposing affidavit, which the
    circuit court accepted. Therefore, we find the circuit court did not abuse its
    discretion by refusing to exclude the affidavit.
    III. Attorney's Fees
    Kitchen Planners argues the circuit court erred by awarding attorney's fees because
    the Friedmans did not properly prove they were entitled to such fees. We disagree.
    A party defending against a mechanic's lien may recover a reasonable attorney's
    fee in defending against the lien. See § 29-5-20(a) ("If the party defending against
    the lien prevails, the defending party must be awarded . . . a reasonable attorney's
    fee as determined by the court. The fee and the court costs may not exceed the
    amount of the lien."). Because we concluded the Friedmans were entitled to
    summary judgment, we find the circuit court did not err by concluding they were
    entitled to reasonable attorney's fees as the prevailing party. See §§ 29-5-10, -20.
    When determining a reasonable attorney's fee, courts should consider the six
    factors set forth in Jackson v. Speed, 
    326 S.C. 289
    , 308, 
    486 S.E.2d 750
    , 760
    (1997). Here, the Friedmans set forth their request for $16,594.68 in attorney's
    fees in the memorandum supporting their motion for summary judgment and an
    accompanying affidavit, which they filed several days before the hearing. The
    circuit court granted the request, finding the fees set forth in the affidavit met "the
    factors necessary to determine reasonable attorney's fees as set out in Rule 407,
    [SCACR], and Jackson v. Speed" but did not specify or analyze these factors.
    Although Kitchen Planners challenges the amount and reasonableness of the fee, it
    raised this argument for the first time in its Rule 59, SCRCP, motion. Because
    Kitchen Planners could have raised this argument at or before the hearing, we find
    it unpreserved for our review. See Johnson v. Sonoco Prods. Co., 
    381 S.C. 172
    ,
    177, 
    672 S.E.2d 567
    , 570 (2009) ("An issue may not be raised for the first time in a
    motion to reconsider."). Accordingly, we find the circuit court did not err by
    awarding $16,594.68 in attorney's fees.
    CONCLUSION
    We find Kitchen Planners failed to serve and file its mechanic's lien within ninety
    days of the last date it supplied materials or labor and no evidence showed the
    materials were actually used in the home. Therefore, we affirm the circuit court's
    order granting summary judgment in favor of the Friedmans pursuant to sections
    29-5-10 and -90. Further, we find the circuit court did not err by treating the
    motion as a motion for summary judgment or by refusing to strike Mr. Friedman's
    affidavit. Finally, we find the circuit court did not err by awarding attorney's fees
    to the Friedmans. For the foregoing reasons, the ruling of the circuit court is
    AFFIRMED.
    KONDUROS and HILL, JJ., concur.