IN THE MATTER OF THE NEW JERSEY PINELANDS COMMISSION'S APPROVAL OF NEW JERSEY NATURAL GAS'S APPLICATION (NO. 2014-0045.001), FOR THE INSTALLATION AND OPERATION OF THE SOUTHERN RELIABILITY LINK PROJECT AS TO THE COMMISSION'S RESOLUTION PC4-17-10. (NEW JERSEY PINELANDS COMMISSION) (CONSOLIDATED) ( 2021 )


Menu:
  •                              NOT FOR PUBLICATION WITHOUT THE
    APPROVAL OF THE APPELLATE DIVISION
    This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the
    internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
    SUPERIOR COURT OF NEW JERSEY
    APPELLATE DIVISION
    DOCKET NO. A-0925-17
    A-1004-17
    IN THE MATTER OF THE
    NEW JERSEY PINELANDS
    COMMISSION'S APPROVAL OF
    NEW JERSEY NATURAL GAS'S
    APPLICATION (NO. 2014-0045.001)
    FOR THE INSTALLATION AND
    OPERATION OF THE SOUTHERN
    RELIABILITY LINK PROJECT,
    COMMISSION RESOLUTION
    PC4-17-10
    ______________________________
    Argued January 20, 2021 – Decided April 29, 2021
    Before Judges Yannotti, Haas, and Natali.
    On appeal from the New Jersey Pinelands Commission,
    No. 2014-0045.001.
    Daniel A. Greenhouse argued the cause for appellant
    Sierra Club (Eastern Environmental Law Center,
    attorneys; Daniel A. Greenhouse, on the brief).
    Paul Leodori argued the cause for appellant Pinelands
    Preservation Alliance (Law Offices of Paul Leodori,
    PC, attorneys; Amy Huber, on the brief).
    Kristina Miles, Deputy Attorney General, argued the
    cause for respondent New Jersey Pinelands
    Commission (Gurbir S. Grewal, Attorney General,
    attorney; Melissa H. Raksa, Assistant Attorney
    General, of counsel; Kristina Miles, on the brief).
    Dennis J. Krumholz argued the cause for respondent
    New Jersey Natural Gas Company (Riker, Danzig,
    Scherer, Hyland & Perretti, LLP, attorneys; Dennis J.
    Krumholz, of counsel and on the brief; Michael S.
    Kettler, on the brief).
    PER CURIAM
    Sierra Club (SC) (A-0925-17) and Pinelands Preservation Alliance (PPA)
    (A-1004-17) appeal from the final decision of the Pinelands Commission to
    approve an application by New Jersey Natural Gas Company (NJNG) for the
    construction and installation of a natural gas pipeline known as the Sou thern
    Reliability Link (SRL) within the Pinelands Area. We address both appeals in
    this opinion. For the following reasons, we affirm.
    I.
    In 2015, NJNG proposed the construction and installation of the SRL, an
    approximately thirty-mile, thirty-inch intrastate high-pressure natural gas
    transmission pipeline to service its existing customers in Burlington, Monmouth
    and Ocean Counties. The proposed pipeline would connect NJNG's existing
    natural gas system, which serves its customers in those counties, to a new
    A-0925-17
    2
    interstate supply point located in Chesterfield and operated by Transcontinental
    Pipeline Company (Transco).         The SRL would run eastward through
    Chesterfield, North Hanover, Upper Freehold, Plumsted, Jackson, and
    Manchester Townships.
    As proposed, a 12.1-mile section of the pipeline would cross the State-
    designated Pinelands Preservation Area running through three municipalities in
    Ocean County. That portion of the pipeline would be installed almost entirely
    within existing rights-of-way and roads. The SRL would cross three Pinelands
    Management Areas: (1) 10.45 miles in the Military and Federal Installation Area
    on the federal military's Joint Base, McGuire-Dix-Lakehurst (Joint Base); (2)
    1.42 miles in a Rural Development Area (RDA); and (3) 0.21 miles in a Regional
    Growth Area (RGA). NJNG maintains a natural gas distribution system that
    serves many of the buildings and facilities in the Joint Base's Lakehurst section.
    Public Service Electric and Gas Company (PSE&G) services the larger
    remaining section of the Joint Base.
    In April 2015, NJNG submitted an application to the Commission seeking
    approval to construct and install a section of the SRL in the Pinelands Area.
    NJNG also filed a petition pursuant to N.J.A.C. 14:7-1.4, seeking the Board's
    approval to install and operate a natural gas pipeline "with a maximum operating
    A-0925-17
    3
    pressure in excess of 250 psig [pounds per square inch gauge] within 100 feet
    of any building intended for human occupancy" (the Safety Petition); and a
    petition pursuant to the Municipal Land Use Law (MLUL), N.J.S.A. 40:55D-1
    to -163, seeking a determination that the SRL is "reasonably necessary for the
    service, convenience or welfare of the public," N.J.S.A. 40:55D-19, along with
    an application to designate a "practicable" route for the pipeline pursuant to
    N.J.S.A. 48:9-25.4 (the MLUL Petition).
    NJNG later revised the SRL's proposed route and submitted an amended
    application to the Commission and amended petitions to the Board.            The
    Commission's staff reviewed NJNG's amended application pursuant to the
    coordinated permitting process in the Comprehensive Management Plan (CMP)
    Rules, N.J.A.C. 7:50-4.81 to -4.85. The staff issued a "certificate of filing" in
    December 2015, finding the SRL project was consistent with the minimum
    standards of the CMP. Thereafter, the Commission's Executive Director sent a
    letter to the Board dated March 10, 2016, stating that the project was consistent
    with the CMP.     Various parties appealed to this court from the Executive
    Director's determination.
    Meanwhile, in January 2016, the Board granted NJNG's petitions.
    Addressing the MLUL Petition, the Board found that the proposed SRL pipeline
    A-0925-17
    4
    was "reasonably for the service, convenience and welfare of the public pursuant
    to N.J.S.A. 40:55D-19." The Board noted that the SRL was intended to provide
    adequate supply, reliability and redundancy to the southern portion of NJNG's
    service territory, which includes the Joint Base. Thereafter, the Board submitted
    its record to the Commission, including all public comments and documents
    submitted as part of its proceedings.1
    In November 2016, we issued our opinion in In re Petition of South Jersey
    Gas Co. (SJG), 
    447 N.J. Super. 459
    , 465 (App. Div. 2016), a case in which
    various parties had challenged the Commission's approval of a similar pipeline
    proposed by South Jersey Gas Company, arguing that the Executive Director did
    not have authority to issue a final decision on whether a particular use is
    consistent with the minimum standards of the CMP. We held that only the
    Commission had "the authority to render final decisions on CMP compliance
    . . . in the coordinated permitting process." 
    Id. at 477
    . Consequently, we
    remanded the matter to the Commission with specific instructions on the manner
    1
    PPA and SC have filed appeals from the Board's approval of the MLUL
    Petition. The appeals are docketed under A-3666-15 and A-3752-15. PPA also
    has appealed from the Board's approval of the Safety Petition. That appeal is
    docketed as A-2876-15. In opinions filed this date, we affirm the Board's
    decisions.
    A-0925-17
    5
    in which further proceedings on the application should proceed. 
    Id. at 478-79, 484
    .
    Following our decision in SJG, the Commission filed motions in the
    pending appeals from the approval of the SRL so it could re-review NJNG's
    amended application under the same procedural guidelines that we set forth in
    SJG. We granted the motions, remanded the matters to the Commission, and
    dismissed the appeals.
    At its meeting on June 9, 2017, the Commission adopted Resolution No.
    PC4-17-10, which set forth its process for determining whether the SRL was
    consistent with the CMP's minimum standards.             In the resolution, the
    Commission stated it would incorporate the extensive record developed before
    the Board on the MLUL and Safety Petitions into its own record.
    The Commission decided that it would not refer the matter to the Office
    of Administrative Law (OAL) for an evidentiary hearing, finding that such a
    hearing was unnecessary in view of the issues to be decided and extensive record
    already developed. In addition, the Commission established a process for public
    comment, and stated that a party could request an adjudicatory hearing if the
    party had a statutory or constitutional basis for such a proceeding.
    A-0925-17
    6
    PPA and certain individuals (Daniel Caruso, Patricia Caruso, and Jean
    Kovath) then filed requests with the Commission seeking an adjudicatory
    hearing on NJNG's application. The Commission denied the requests finding
    that the PPA and the individuals did not have a statutory or constitutional right
    to an adjudicatory hearing. 2
    Thereafter, at a public hearing conducted in July 2017, forty-five
    individuals, including representatives from SC and PPA, provided oral
    comments on NJNG's application. The Commission also received 1319 written
    comments on the application.
    On August 29, 2017, the Executive Director issued a report recommending
    approval of NJNG's application with conditions to ensure the project would not
    have any unanticipated adverse impacts on the Pinelands area. The report
    addressed all public comments and recommended that the Commission find
    NJNG's proposal was consistent with the minimum requirements of all relevant
    CMP standards.
    2
    PPA and the individuals have appealed from the denial of their hearing
    requests. The appeals were docketed under A-0999-17 and A-1005-18. PPA
    also has appealed from the adoption of PC4-17-10, and that appeal was docketed
    as A-4997-16. In opinions also filed this date, we affirm the Commission's
    adoption of PC4-17-10, and its decisions on the hearing requests.
    A-0925-17
    7
    While the matter was pending before the Commission, PPA and others
    submitted separate letters to the Commission's ethics liaison officer and the State
    Ethics Commission (SEC), asserting that Commissioners Alan Avery and Gary
    Quinn should be disqualified from participating in the Commission's vote on
    NJNG's application due to alleged conflicts of interest.       The SEC's acting
    Executive Director determined that neither Commissioner had a conflict of
    interest requiring recusal.
    On September 14, 2017, the Commission approved NJNG's application
    for the construction and installation of the SRL through the Pinelands Area,
    subject to conditions suggested by the Executive Director. The Commission
    noted that it had reviewed the public's comments, the extensive evidentiary
    record, and the Executive Director's recommendation report.
    The Commission found "ample evidence" demonstrating that the proposed
    installation of the SRL, with the recommended conditions, was consistent with
    the minimum standards of the CMP. The Commission memorialized its action
    in Resolution No. PC4-17-27. The Commission also denied a motion to stay
    installation of the SRL pending appeal. These appeals followed. In July 2020,
    SC moved before this court for a stay of construction of the pipeline. We denied
    the motion.
    A-0925-17
    8
    In its appeal, SC argues: (1) the SRL does not meet the CMP's minimum
    standards for development and land use in a RDA of the Pinelands; (2) the
    Commission arbitrarily and capriciously decided that the need for the pipeline
    overrides the importance of protecting wetlands in the Pinelands; (3) the
    Commission erred by finding that installation of the SRL in forested wetlands
    and the removal of trees from that area will not result in a substantial impairment
    to that area; (4) the Commission mistakenly relied on the Board's assessment of
    the risks of potential pipeline accidents; and (5) the Commission erred by
    finding that construction of the SRL will not have an irreversible adverse impact
    on threatened and endangered species and their habitats.
    In its appeal, PPA raises the following arguments: (1) the Commission's
    review process violated due process and the applicable laws; (2) the
    Commission's approval of the SRL was invalid because two Commissioners
    participated and voted on the application despite known conflicts of interest; and
    (3) the Commission's approval of the SRL was arbitrary and capricious because
    it violates the environmental protections in the Pinelands Protection Act
    (Pinelands Act), N.J.S.A. 13:18A-1 to -29, and the CMP.
    II.
    A-0925-17
    9
    NJNG asserts that construction and installation of the portion of the SRL
    in the Pinelands Area was completed in January 2020. NJNG therefore argues
    that the issues that SC and PPA have raised on appeal are moot. It contends a
    decision in favor of appellants would have no effect at this time and the appeals
    should be dismissed.
    A matter is moot when the requested decision "can have no practical effect
    on the existing controversy."    Redd v. Bowman, 
    223 N.J. 87
    , 104 (2015)
    (quoting Deutsche Bank Nat'l Trust Co. v. Mitchell, 
    422 N.J. Super. 214
    , 221-
    22 (App. Div. 2011)). Dismissal for mootness is appropriate when "a judgment
    cannot grant effective relief." Caput Mortuum, LLC v. S & S Crown Servs.,
    Ltd., 
    366 N.J. Super. 323
    , 330 (App. Div. 2004).
    Generally, our courts "do not resolve issues that have become moot due
    to the passage of time or intervening events." Wisniewski v. Murphy, 
    454 N.J. Super. 508
    , 518 (App. Div. 2018) (alteration in original) (quoting State v.
    Davila, 
    443 N.J. Super. 577
    , 584 (App. Div. 2016)). However, "[i]n limited
    instances, a court will address the merits of an appeal that has become moot
    'where the underlying issue is one of substantial importance, [that is] likely to
    reoccur but capable of evading review.'" 
    Id. at 519
     (quoting Zirger v. Gen.
    Accident Ins. Co., 
    144 N.J. 327
    , 330 (1996)). Courts may "decline to dismiss a
    A-0925-17
    10
    matter on mootness grounds in order to address an important matter of public
    interest." 
    Ibid.
    Since the portion of the SRL is the Pinelands Area has been constructed,
    the issues that SC and PPA have raised on appeal are technically moot.
    However, SC and PPA have raised issues of substantial importance. Moreover,
    it is likely the same issues will be raised with regard to other applications, but
    they would evade review under similar circumstances. Therefore, we will
    address the issues raised by SC and PPA.
    III.
    PPA argues that the Commission's approval of NJNG's application should
    be reversed because two Commissioners who participated in the decision
    allegedly had disqualifying conflicts of interest. We are not persuaded by PPA's
    argument.
    The Pinelands Act provides in pertinent part that members of the
    Commission may not participate in matters in which the member has a financial
    interest. N.J.S.A. 13:18A-17(a). The Act states that "[n]o member, officer,
    employee, or agent of the commission shall take any official action on any
    matter in which he has a direct or indirect financial interest . . . ." 
    Ibid.
    Furthermore, the New Jersey Conflict of Interest Law (COIL) states that:
    A-0925-17
    11
    No State officer or employee or special State
    officer or employee should knowingly act in any way
    that might reasonably be expected to create an
    impression or suspicion among the public having
    knowledge of his acts that he may be engaged in
    conduct violative of his trust as a State officer or
    employee or special State officer or employee.
    [N.J.S.A. 52:13D-23(e)(7).]
    Moreover, N.J.A.C. 19:61-7.4, a regulation adopted pursuant to the COIL,
    provides in part that:
    (d) A State official must recuse himself or herself
    from an official matter if he or she has:
    1. Any financial interest, direct or indirect,
    that is incompatible with the discharge of the
    State official's public duties; or
    2. Any personal interest, direct or indirect,
    that is incompatible with the discharge of the
    State official's public duties.
    (e) For purposes of (d) above, an incompatible
    financial or personal interest includes, but is not limited
    to . . . a leadership role in a professional or trade
    organization, which interest might reasonably be
    expected to impair a State official's objectivity and
    independence of judgment in the exercise of his or her
    official duties or might reasonably be expected to create
    an impression or suspicion among the public having
    knowledge of his or her acts that he or she may be
    engaged in conduct violative of his or her trust as a
    State official.
    A-0925-17
    12
    In addition, under the common law, a public official is disqualified from
    participating in proceedings "in which the official has a conflicting interest that
    may interfere with the impartial performance of his [or her] duties."
    Paruszewski v. Twp. of Elsinboro, 
    154 N.J. 45
    , 58 (1998) (quoting Scotch
    Plains-Fanwood Bd. of Educ. v. Syvertsen, 
    251 N.J. Super. 566
    , 568 (App. Div.
    1991)). "The test for disqualification is fact-sensitive and depends on whether,
    under the circumstances, a particular interest 'had the likely capacity to tempt
    the official to depart from his sworn public duty.'" Thompson v. City of Atl.
    City, 
    190 N.J. 359
    , 375 (2007) (quoting Van Itallie v. Borough of Franklin
    Lakes, 
    28 N.J. 258
    , 268 (1958)).
    Here, the record shows that Avery was the uncompensated Director of the
    Defense Enhancement Coalition (DEC), a non-profit advocacy group that works
    with the Joint Base to ensure that the base remains vital to the federal Defense
    Department and is not subject to closure. It appears that the DEC has supported
    the construction of the SRL. The record also shows that Quinn served as a
    member of the Lacey Township governing body when it passed a resolution
    expressing its interest in having a new gas-fueled power plant constructed on
    the site of the Oyster Creek nuclear power plant, which was being closed.
    A-0925-17
    13
    PPA and some members of the public asserted that Avery and Quinn had
    disqualifying conflicts of interest which precluded them from participating in
    the Commission's decision on NJNG's application. The Commission forwarded
    the matter to the SEC for its review. Mark T. Holmes, the SEC's Acting
    Executive Director, issued letters dated September 7, 2017, which stated that
    neither Avery nor Quinn had any real or apparent conflict of interest that would
    require their recusal from participating in the Commission's consideration of
    NJNG's application for approval of the SRL.
    On appeal, PPA argues the Commission's decision must be reversed
    because Avery and Quinn improperly participated in that decision.           The
    Commission and NJNG contend, however, that the Pinelands Act only prohibits
    members of the Commission from participating in matters when the
    Commissioner has an actual disqualifying financial interest. The Commission
    and NJNG therefore argue that the Pinelands Act controls and precludes
    application of the COIL or the common law.
    We need not address this issue because, like the SEC, we are convinced
    neither Avery nor Quinn had an actual or apparent conflict of interest that
    required their recusal from participating in the Commission's decision on the
    A-0925-17
    14
    SRL. Their participation in the Commission's decision was not barred by the
    Pinelands Act, the COIL, or the common law.
    The record shows that Avery did not receive any compensation for his
    service on the DEC, and he did not participate in any DEC matters after
    December 12, 2016, which was before the Commission considered and approved
    the SRL. There also is no evidence in the record that the DEC took an official
    position on the SRL project before that date, or while the Commission's staff
    and Executive Director were reviewing NJNG's amended application.
    It appears that in October 2016, another member of the DEC's board spoke
    in favor of the SRL at a public hearing before the New Jersey Department of
    Environmental Protection (NJDEP). However, that individual was not acting in
    an official capacity for the DEC.
    Avery also has asserted that he did not have any personal involvement in
    the development of the DEC's positions or statements regarding the SRL. He
    resigned his position with the DEC in August 2017, which was before the
    Commission heard public comments and voted on NJNG's application for
    approval of the SRL.
    Furthermore, Quinn did not have a disqualifying conflict of interest
    arising from his position as a member of the Lacey Township governing body.
    A-0925-17
    15
    It appears that Quinn expressed support when it was suggested that a new gas-
    fueled power plant could be constructed on the site of the Oyster Creek power
    station.    Quinn did not, however, express support for the SRL project or
    comment on whether the SRL would provide natural gas to a new power plant
    at Oyster Creek.
    In addition, Lacey Township did not have a concrete plan for the
    construction of a new power plant at Oyster Creek, no power company had
    expressed an interest in building or operating such a facility, and there was no
    evidence that the SRL was part of any plan to provide gas service to a new power
    plant.
    Thus, Avery and Quinn were not disqualified from participating in the
    Commission's decision on the SRL. As the SEC correctly determined, neither
    Avery nor Quinn had a direct or indirect financial or personal interest in the SRL
    project that would be incompatible with the proper discharge of their official
    duties as members of the Commission.
    IV.
    SC and PPA argue that the Commission's approval of the SRL was
    arbitrary, capricious, and unreasonable.     They contend the record does not
    A-0925-17
    16
    support the Commission's finding that the SRL is consistent with the minimum
    standards of the CMP.
    The scope of our review of a final decision of an administrative agency is
    strictly limited. In re Carter, 
    191 N.J. 474
    , 482 (2007). We may reverse an
    agency's decision only if it is arbitrary, capricious, or unreasonable. In re
    Proposed Quest Acad. Charter Sch. of Montclair Founders Grp., 
    216 N.J. 370
    ,
    385 (2013). Our review of an agency's decision is limited to considering
    (1) whether the agency's action violates express or
    implied legislative policies, that is, did the agency
    follow the law; (2) whether the record contains
    substantial evidence to support the findings on which
    the agency based its action; and (3) whether in applying
    the legislative policies to the facts, the agency clearly
    erred in reaching a conclusion that could not reasonably
    have been made on a showing of the relevant factors.
    [Id. at 385-86 (quoting Mazza v. Bd. of Trs., 
    143 N.J. 22
    , 25 (1995)).]
    We are required to affirm an agency's findings of fact if "supported by
    adequate, substantial and credible evidence." In re Taylor, 
    158 N.J. 644
    , 656-
    57 (quoting Rova Farms Resort, Inc. v. Inv.'s Ins. Co. of Am., 
    65 N.J. 474
    , 484
    (1974)). We also must "give due deference to the view of those charged with
    the responsibility of implementing legislative programs." In re Reallocation of
    Prob. Officer, 
    441 N.J. Super. 434
    , 444 (App. Div. 2015) (quoting In re N.J.
    A-0925-17
    17
    Pinelands Comm'n Resol. PC4-00-89, 
    356 N.J. Super. 363
    , 372 (App. Div.
    2003)).
    The Pinelands Act established the Commission, N.J.S.A. 13:18A-4(a),
    and directed the Commission "to prepare and adopt a comprehensive
    management plan [(CMP)]" for the different portions of the Pinelands Area.
    N.J.S.A. 13:18A-8. Among other things, the Act provides that the CMP must
    be implemented "in a manner that will insure the continued, uniform, and
    consistent protection of the pinelands area in accord with the purposes and
    provisions of the [state and federal legislation]." N.J.S.A. 13:18A-8(i).
    Accordingly, the Commission adopted the CMP Rules, which established
    eight specific Pinelands Management Areas with different goals, objectives,
    development intensities, and permitted uses. N.J.A.C. 7:50-5.11 and -5.12(a).
    RDAs and Military and Federal Installation Areas are two of the Pinelands
    Management Areas established by the CMP.
    A. RDA.
    SC contends the Commission erred by finding the installation of the SRL
    in the Pinelands was consistent with the CMP Rules for development in a RDA.
    N.J.A.C. 7:50-5.26(b). SC argues that a natural gas pipeline is not a permitted
    use in that area, and that the Commission erred by failing to make a finding that
    A-0925-17
    18
    the SRL was "compatible with the essential character of the Pinelands
    environment." 
    Ibid.
    NJNG's application indicates that approximately 1.42 miles of the SRL
    would be constructed and installed in a RDA. N.J.A.C. 7:50-5.26 governs the
    minimum standards for development and land use in a RDA and states in
    relevant part:
    (a) The following uses shall be permitted in a
    [RDA]:
    1. Residential cluster development . . . .
    ....
    2. Residential dwelling units . . . .
    (b) In addition to the residential uses permitted
    under (a) above, a municipality may permit any use
    which is compatible with the essential character of the
    Pinelands environment and is similar in character,
    intensity and impact to the following uses:
    ....
    10. Public service infrastructure except that
    centralized waste water treatment and collection
    facilities shall be permitted to service the Rural
    Development Area only in accordance with N.J.A.C.
    7:50–6.84(a)2; . . . .
    [(Emphasis added).]
    A-0925-17
    19
    "Public service infrastructure" is defined in the CMP Rules as "gas . . . and other
    public utilities developed linearly . . . provided or maintained by any public or
    private entity." N.J.A.C. 7:50-2.11.
    SC argues that a use is permitted in an RDA only if it is "similar in
    character, intensity and impact" to one of the uses enumerated in N.J.S.A. 7:50-
    5.26, and such use must be "compatible with the essential character of the
    Pinelands environment." SC contends the Commission erred by concluding that
    under N.J.S.A. 7:50-5.26, the SRL is a permitted use in a RDA because it is a
    "public safety infrastructure," and there was no need for the Commission to find
    the SRL is "compatible with the essential character of the Pinelands
    environment." We disagree.
    According to the CMP Rules, RDAs are management sections of the
    Pinelands Area that have been "slightly modified" from their natural state and
    "represent a balance of environmental and development values that is
    intermediate between the pristine Forest Areas and existing growth areas."
    N.J.A.C. 7:50-5.13(e). N.J.A.C. 7:50-5.26(b) identifies sixteen uses that are
    permitted in an RDA, one of which is a "public safety infrastructure." The term
    "[p]ublic service infrastructure" is defined in the CMP Rules as "gas . . . and
    A-0925-17
    20
    other public utilities developed linearly . . . provided or maintained by any public
    or private entity." N.J.A.C. 7:50-2.11.
    Here, the Commission found that under the regulation, the sixteen
    enumerated uses are permitted in a RDA. Other uses are permitted in a RDA if
    they are "compatible with the essential character of the Pinelands environment,"
    and are "similar in character and intensity" with the uses enumerated in the
    regulation. Since the SRL is a "public safety infrastructure," as defined in
    N.J.S.A. 7:50-2.11, the Commission found the SRL is a permitted use in a RDA.
    We note that we are "in no way bound by the agency's interpretation of a
    statute or its determination of a strictly legal issue." Ardan v. Bd. of Review,
    
    231 N.J. 589
    , 604 (2018) (quoting U.S. Bank, N.A. v. Hough, 
    210 N.J. 187
    , 200
    (2012)). Nevertheless, we will defer to an agency's interpretation of the statute
    and the regulations it is charged with enforcing "unless the agency's
    interpretation is plainly unreasonable." 
    Ibid.
     (quoting In re Election Law Enf't
    Comm'n Advisory Op. No. 01-2008, 
    201 N.J. 254
    , 260 (2010)).
    We are convinced that the Commission's interpretation of N.J.S.A.
    7:50-5.26(a) is reasonable and consistent with the plain language of N.J.A.C.
    7:50-5.26(b). The regulation clearly unambiguously allows the construction of
    a "public safety infrastructure" in a RDA, and the SRL meets the definition of
    A-0925-17
    21
    such a use. There is no merit to SC's contention that the SRL cannot be
    constructed in a RDA unless the Commission specifically finds that it is
    "compatible with the essential character of the Pinelands environment with the
    essential character of the Pinelands environment and is similar in character,
    intensity and impact to" the uses permitted in a RDA. N.J.S.A. 7:50-5.26(b).
    B. Military and Federal Installation Area.
    PPA argues the Commission erred by finding the SRL project complied
    with the CMP Rules for development in a Military and Federal Installation Area.
    The record shows that approximately 10.45 miles of the SRL will traverse the
    Joint Base and be located within the Military and Federal Installation Area of
    the Pinelands.
    N.J.A.C. 7:50-5.29 sets forth the minimum standards for development in
    that area, and states in part:
    (a) Any use associated with the function of the
    Federal Installation may be permitted in a Military and
    Federal Installation Area, provided that:
    1. Where feasible, development shall be located
    in that portion of the installation located within the
    Pinelands Protection Area;
    2. The use shall not require any development,
    including public service infrastructure, in the
    Preservation Area District or in a Forest Area; . . .
    A-0925-17
    22
    [(Emphasis added).]
    1. Location Within the Pinelands Preservation Area.
    PPA argues that the Commission erred by finding that a portion of SRL
    may be constructed and installed on the Joint Base in the Preservation Area,
    rather than in the Protection Area. PPA contends the Commission's finding is
    inconsistent with N.J.A.C. 7:50-5.29(a)(1). We disagree.
    The National Parks and Recreation Act of 1978, 16 U.S.C. § 471i,
    established the Pinelands National Reserve in New Jersey. The Pinelands Act
    established the Pinelands Area within the National Reserve, and divided the
    Pinelands Area into the Preservation and Protection Areas. N.J.S.A. 13:18A-2;
    -3(j) and (k); -9, and -11(b). Two thirds of the Joint Base, including its entire
    Lakehurst section where NJNG proposed to construct the SRL, is within the
    Preservation Area, and one third is within the Protection Area.
    The record shows that NJNG considered several alternative routes
    including a route in the Protection Area, but officials at the Joint Base decided
    that route would not be feasible. One of the Base Commanders noted that a
    route through the Protection Area "would have to transverse the range
    complex[,] an area that has the potential for encountering unexploded
    ordnance." Two other Base Commanders rejected other routes because of their
    A-0925-17
    23
    proximity to "aircraft hangars, hazardous materials storage areas, jet engine fuel
    storage tanks, munitions storage, live fire ranges and military housing units ."
    In addition, the Commission's staff rejected an alternative route through
    the Protection Area. The staff found that selection of this route would require
    installation of the pipeline in the Forest Area or the Preservation Area District
    along the pipeline's route outside the Joint Base, which would be contrary to
    CMP Rules.
    Thus, there is sufficient credible evidence in the record to support the
    Commission's finding that the SRL route through the Preservation Area on the
    Joint Base was permissible under N.J.A.C. 7:50-5.29(a)(2). The record supports
    the Commission's determination that alternative routes through the Protection
    Area were not feasible.
    PPA argues, however, that the Commission erred because it failed to
    consider alternative routes that would have completely avoided the Joint Base.
    N.J.A.C. 7:50-5.29 does not, however, require the Commission to consider
    potential routes for installation outside the Joint Base. The Commission was
    only required to find that routes though the Protection Area were not feasible,
    and the record supports that finding.
    A-0925-17
    24
    2. Relationship of the SRL to the Function of the Joint Base.
    As noted, N.J.A.C. 7:50-5.29(a) states in part that "[a]ny use associated
    with the function of the Federal Installation may be permitted" within the
    Military and Federal Installation Area of the Pinelands. PPA contends the
    record does not support the Commission's finding that the SRL is "associated
    with the function" of the Joint Base.
    As we noted previously, we defer to an agency's interpretation of the
    statute and regulations it is charged with enforcing, unless the agency's
    interpretation is "plainly unreasonable."      Ardan, 231 N.J. at 604 (quoting
    Election Law Enf't Comm'n, 
    201 N.J. at 260
    ).
    Here, the Commission essentially interpreted N.J.S.A. 7:50-5.29(a) to
    permit development that is "related to the function of the installation." The
    Commission's interpretation is reasonable.       It is consistent with the plain
    language of the regulation and the ordinary meaning of the phrase "associated
    with."
    In addition, statements by the Joint Base Commanders support the
    Commission's finding that the SRL will be associated with the function of that
    facility. In February 2015, Colonel James C. Hodges wrote that the Joint Base
    was interested in the proposed pipeline because it would provide energy
    A-0925-17
    25
    reliability and redundancy to the facility. Colonel Hodges stated that the SRL
    would be "absolutely critical" to Joint Base's mission.
    Moreover, Colonel Frederick D. Thaden indicated that the "natural gas
    redundancy" would be a benefit to the Joint Base, and Colonel Neil R.
    Richardson, who was the Base Commander in 2017, stated that any loss of
    natural gas supply to the Joint Base would "cripple" its mission. Thus, there is
    sufficient credible evidence in the record to support the Commission's finding
    that the SRL is "associated with the function" of the Joint Base.
    PPA argues, however, that the SRL is not "associated with the function"
    of the Joint Base because it will not connect directly with the existing natural
    gas distribution system at Lakehurst. However, as NJNG points out, this is a
    distinction without a difference. The SRL will provide natural gas to the Joint
    Base by means of a connection to the NJNG's distribution system, which serves
    all of NJNG's customers, including the Joint Base.
    The record shows that the SRL will provide reliability and redundancy to
    NJNG's supply of natural gas to the Joint Base and that the SRL will be capable
    of providing natural gas to the base in the event of a service disruption. We
    therefore reject PPA's contentions that the SRL will not be "associated with the
    function" of the Joint Base.
    A-0925-17
    26
    PPA further argues that the Commission's finding lacks support because
    Colonel Thaden apparently thought that the SRL would connect directly with
    the Joint Base. However, Thaden noted that NJNG's customers at the southern
    end of its service territory were vulnerable to a disruption of gas supply from
    the single existing connection at the northern end of the service territory.
    Thaden believed the SRL would address this vulnerability.
    Thaden's apparent belief that the SRL would connect directly to the Joint
    Base is of no consequence. He was of the view that the SRL will provide
    reliability and redundancy for the supply of natural gas to the Joint Base , and
    that would be so regardless of whether the SRL is connected directly to the Joint
    Base.
    PPA also contends that the SRL's route through the Joint Base was merely
    a pretext to secure Commission approval of the pipeline. PPA asserts that
    installation of a part of the pipeline in the Joint Base was an "afterthought"
    suggested by the Commission's staff.
    In support of this contention, the PPA relies on certain emails, which were
    exchanged during pre-application discussions between representatives of NJNG
    and the Commission's staff. There was, however, nothing improper about the
    A-0925-17
    27
    staff suggesting changes to the proposed pipeline route during pre-application
    discussions to ensure compliance with the CMP Rules.
    PPA further argues that the SRL is not "associated with the function" of
    the Joint Base because the pipeline is designed to transport more gas than the
    base may require. As the Commission found, however, the SRL will provide a
    reliable source of natural gas for the Joint Base. The pipeline will be "associated
    with the function" of the Joint Base even though it will also provide natural gas
    to NJNG's other customers.
    In support of its argument, PPA also relies upon statements in a 2014
    Environmental Assessment that the Joint Base's then-current natural gas supply
    was "a non-interruptible system" and that "supply capacity is not considered an
    issue for future growth." The statements are not relevant. They do not pertain
    to the purpose of the SRL, which is to ensure an adequate and reliable source of
    natural gas to NJNG's customers in the southern end of its service territory ,
    including the Joint Base.
    C. Compliance With the CMP's Environmental Standards.
    SC and PPA contend the SRL does not comply with the environmental
    standards for forested wetlands and threatened and endangered species in the
    A-0925-17
    28
    CMP. In addition, PPA argues that the SRL fails to comply with the CMP's
    minimum environmental standards for water quality.
    1. Forested Wetlands.
    N.J.A.C. 7:50-6.6 states in pertinent part that: "[d]evelopment shall be
    prohibited in all wetlands . . . in the Pinelands except as specifically authorized
    in this Part." N.J.A.C. 7:50-6.13 sets forth five factors that must be met for
    certain linear improvements to be permitted in wetlands:
    (a) Bridges, roads, trails and utility transmission
    and distribution facilities and other similar linear
    facilities shall be permitted in wetlands provided that:
    1. There is no feasible alternative route for the
    facility that does not involve development in a wetland
    or, if none, that another feasible route which results in
    less significant adverse impacts on wetlands does not
    exist;
    2. The need for the proposed linear improvement
    cannot be met by existing facilities or modification
    thereof;
    3. The use represents a need which overrides the
    importance of protecting the wetland;
    4. Development of the facility will include all
    practical measures to mitigate the adverse impact on the
    wetland; and
    5. The resources of the Pinelands will not be
    substantially impaired as a result of the facility and its
    A-0925-17
    29
    development as determined exclusively based on the
    existence of special and unusual circumstances.
    The record shows that the SRL will run predominantly under existing
    roadways or shoulders; however, the pipeline will disturb 390.3 square feet of
    forested wetlands in the Pinelands. Applying the five factors in N.J.A.C. 7:50-
    6.13, the Commission's staff found that the SRL is permitted in this area. The
    Commission accepted the staff's analysis.
    The Commission found there were no feasible alternative routes for the
    section of the SRL that would result in the disturbance of fewer wetlands. The
    Commission determined that the need for gas supply resiliency and redundancy
    in the southern end of NJNG's service territory could not be met by other existing
    energy facilities, and this need overrode the importance of protecting affected
    wetlands.
    The Commission also found that NJNG would mitigate the pipeline's
    impacts upon the wetlands by using Horizontal Directional Drilling (HDD) in
    construction of the pipeline. The use of HDD would avoid ground impacts and
    minimize the impact on wetland vegetation that would result from the hand
    cutting of trees. The Commission found the SRL will not result in a substantial
    impairment of the resources in the Pinelands.          The record supports the
    Commission's findings.
    A-0925-17
    30
    SC argues, however, that the Commission should not have approved
    NJNG's application because the removal of trees in a 390.3 square foot area of
    forested wetland, by its very definition, is a substantial impairment. N.J.A.C.
    7:50-6.7 states:
    (a) A significant adverse impact shall be deemed
    to exist where it is determined that one or more of the
    following modifications of a wetland will have an
    irreversible effect on the ecological integrity of the
    wetland and its biotic components including, but not
    limited to, threatened or endangered species of plants
    or animals:
    1. An increase in          surface   water   runoff
    discharging into a wetland;
    2. A change in the normal seasonal flow patterns
    in the wetland;
    3. An alteration of the water table in the wetland;
    4. An increase in erosion resulting in increased
    sedimentation in the wetland;
    5. A change in the natural chemistry of the
    ground or surface water in the wetland;
    6. A loss of wetland habitat;
    7. A reduction in wetland habitat diversity;
    8. A change in wetlands species composition; or
    A-0925-17
    31
    9. A significant disturbance of areas used by
    indigenous and migratory wildlife for breeding,
    nesting, or feeding.
    (b) Determinations under (a) above shall consider
    the cumulative modifications of the wetland due to the
    development being proposed and any other existing or
    potential development which may affect the wetland[.]
    SC contention lacks sufficient merit to warrant discussion.       R. 2:11-
    3(e)(1)(E). We are convinced that there is sufficient credible evidence in the
    record to support the Commission's finding that the SRL will not have a
    "significant adverse impact" upon forested wetlands, as that phrase is defined in
    N.J.A.C. 7:50-6.7.
    2. Threatened and Endangered Species.
    SC argues that installation of the SRL will cause irreversible adverse
    impacts on threatened and endangered species and their habitats in the Pinelands
    Area, which is not permitted by the CMP Rules. SC contends the Commission
    did not adequately explain how NJNG will avoid irreversible adverse impacts to
    the sickle-leaved golden aster, a threatened and endangered plant species.
    N.J.A.C. 7:50-6.27(a) states:
    No development shall be carried out by any
    person unless it is designed to avoid irreversible
    adverse impacts on the survival of any local
    populations of those plants designated by the
    Department of Environmental Protection as endangered
    A-0925-17
    32
    plant species pursuant to N.J.A.C. 7:5C-5.1 as well as
    the following plants, which are hereby found and
    declared to be threatened or endangered plants of the
    Pinelands . . . .
    One of the plant species listed in the regulations is the sickle-leaved golden aster
    (Pityopsis falcata, formerly Chrysopsis falcata). N.J.A.C. 7:50-6.27(a)(7).
    During its review of the application, the Commission's staff obtained from
    NJNG reports and information that identified a small population (0.20 acres or
    456 plants) of sickle-leaved golden aster in an area of the Joint Base that would
    be used as "lay-down areas" for the temporary storage and assembly of
    construction equipment and supplies related to the use of HDD. To address this
    concern, NJNG revised the SRL project to eliminate the use of HDD for that
    section of the pipeline.
    Instead, NJNG proposed using conventional bore drilling, which would
    eliminate the need for lay down areas and thereby would avoid any impact on
    the threatened and endangered plant species. The Commission's staff explained
    that, with removal of the lay down areas, the SRL "would be installed within the
    limits of the existing road using a conventional bore installation process. That
    revision eliminated all potential impacts to the local population of [s]ickle-
    leaved golden aster."
    A-0925-17
    33
    After considering all of NJNG's submissions, including surveys, maps,
    and changes to the planned construction, the Commission's staff concluded,
    "that given the redesign, and that the proposed natural gas pipeline will be
    constructed almost entirely within existing rights-of-way and roads, the
    proposed project will not result in irreversible adverse impact on the survival of
    the local population of this [threatened and endangered] species." To ensure
    that no unforeseen impacts occur, the Commission required NJNG to have a
    biologist for both animal and plant species on site during construction.
    On appeal, SC contends the Commission erred by accepting the claim that
    conventional boring techniques would eliminate any adverse impacts to the
    sickle-leaved golden aster.      SC asserts that the Commission should have
    requested further information on this issue. It contends NJNG provided no
    concrete evidence on the effects conventional boring would have on the plants
    in question.
    We are convinced, however, that the Commission reasonably relied upon
    the technical expertise of its staff in finding that use of conventional bore drilling
    would avoid adverse impacts to the sickle-leaved golden aster by eliminating
    the use of HDD in areas where these plants are found. Moreover, as noted, the
    Commission required NJNG to have a biologist on site during construction to
    A-0925-17
    34
    ensure that the installation of the pipeline will not adversely affect the plant
    species at issue.
    3. Water Quality.
    PPA contends the Commission erred by approving the SRL without
    considering whether the pipeline will be constructed in the same general area as
    two Superfund sites with groundwater contamination in the Joint Base area.
    PPA argues that the Commission's decision is inconsistent with the CMP Rules.
    N.J.A.C. 7:50-6.81 states in pertinent part that the Pinelands Act and the
    CMP are intended to "protect and maintain the quality of surface and ground
    water [in the Pinelands environment] through the control and development o f
    land use and close cooperation and coordination with local, state and federal
    agencies of government." In addition, N.J.A.C. 7:50-6.83 states:
    (a) All development permitted under this Plan . . .
    shall be designed and carried out so that the quality of
    surface and ground water will be protected and
    maintained. . . .
    (b) Except as specifically authorized in this Part,
    no development which degrades surface or ground
    water quality or which establishes new point sources of
    pollution shall be permitted.
    (c) No development shall be permitted which
    does not meet the minimum water quality and potable
    water standards of the State of New Jersey or the United
    States.
    A-0925-17
    35
    In addressing the public comments regarding the groundwater
    contamination of the Superfund sites, the Commission's staff noted that the New
    Jersey Department of Environmental Protection (NJDEP) and the United States
    Environmental Protection Agency (USEPA) had addressed the issues related to
    these sites. The staff stated:
    The NJDEP's review concluded that the pipeline is
    proposed in areas where there is no soil contamination.
    The NJDEP notes that there is groundwater
    contamination in some areas; however, it is 50 to 70
    feet below ground surface and the pipeline will not be
    deeper than 20 feet below ground surface. Therefore,
    contaminated groundwater will not be encountered.
    The USEPA reviewed [the Joint Base's] March 2017
    Environmental Assessment regarding the project and
    made a finding of no significant impact.
    Thus, the record supports the Commission's finding that the installation of
    the SRL will not adversely affect the groundwaters or soil in the Pinelands Area.
    PPA argues, however, that the Commission erred by failing to require additional
    studies of soil and groundwater contamination, geology, and the water table
    along the proposed pipeline route.
    PPA asserts that the Commission erroneously relied upon "limited
    studies" previously conducted on the Superfund sites and outdated well testing.
    PPA contends that without any current or specific evaluation of the soil and
    ground water contamination along the SRL's route and any construction related
    A-0925-17
    36
    thereto, the Commission's finding that the SRL will not "cause further issues of
    contamination is unjustified and unreliable."
    PPA's argument lacks sufficient merit to warrant extended comment. R.
    2:11-3(e)(1)(E). We are convinced there is sufficient credible evidence in the
    record to support the Commission's finding that the SRL will not have a
    significant adverse impact upon the groundwater quality in the Pinelands, and
    that further testing of the soil and groundwaters along the pipeline route was not
    required.
    D. Reliance on the Board's Findings.
    SC argues that the Commission erred by relying on the Board's risk
    assessments for corrosion, ruptures, and other pipeline accidents. It claims the
    Commission failed to perform an independent review of the need for the SRL in
    light of the heightened protections required by the Pinelands Act and the CMP
    Rules. SC further argues that the Commission erred by relying on the Board's
    determination that the pipeline will be operated and installed safely.
    Our Supreme Court has emphasized the importance of "comity and
    deference to sibling agencies" where the government oversees "complex and
    manifold activities that are also the appropriate statutory concern of other
    governmental bodies." Hinfey v. Matawan Reg'l Bd. of Educ., 
    77 N.J. 514
    , 531
    A-0925-17
    37
    (1978). The Board had the authority and expertise to determine: (1) whether the
    entire SRL met the applicable safety requirements to be installed and operated
    "with a maximum operating pressure in excess of 250 [pounds force per square
    inch gauge pressure] within 100 feet of any building intended for human
    occupancy," N.J.A.C. 14:7-1.4; (2) whether the SRL was "necessary for the
    service, convenience or welfare of the public," N.J.S.A. 40:55D-19, and whether
    the proposed route was "practicable," N.J.S.A. 48:9-25.4. The Commission
    reasonably relied upon the Board's decision on these issues.
    Nevertheless, the Commission's Executive Director and its staff
    independently evaluated the SRL in light of the requirements in the Pinelands
    Act and CMP Rules. The Commission imposed additional conditions upon its
    approval to address safety issues, including installation of vales for emergency
    shutdowns, safety inspections, and protections for T&E species.
    Thus, there is no merit to SC's contention that the Commission mistakenly
    relied upon the Board's assessment of the risks associated with corrosion,
    ruptures, and pipeline accidents.
    V.
    PPA also contends that the Commission's review process violates due
    process, the Pinelands Act, and the CMP. We reject these arguments for the
    A-0925-17
    38
    reasons stated in our opinion on the PPA's appeal from the adoption of PC4 -17-
    10 (A-4997-16) and on PPA's appeal from the Commission's denial of its request
    for an adjudicatory hearing (A-999-17).
    We have considered the other arguments raised by SC and PPA and
    conclude these arguments lack sufficient merit to warrant discussion in this
    opinion. R. 2:11-3(e)(1)(E).
    Affirmed.
    A-0925-17
    39