Tri-City Associates v. Belmont , 845 N.W.2d 911 ( 2014 )


Menu:
  • #26755-rev & rem-SLZ
    
    2014 S.D. 23
    IN THE SUPREME COURT
    OF THE
    STATE OF SOUTH DAKOTA
    ****
    TRI-CITY ASSOCIATES, LP,                    Plaintiff and Appellant,
    v.
    BELMONT, INC., a South Dakota
    corporation and JOSEPH Z. ERBA,             Defendants and Appellees.
    ****
    APPEAL FROM THE CIRCUIT COURT OF
    THE SEVENTH JUDICIAL CIRCUIT
    PENNINGTON COUNTY, SOUTH DAKOTA
    ****
    THE HONORABLE ROBERT A. MANDEL
    Judge
    ****
    MARK F. MARSHALL of
    Bangs, McCullen, Butler,
    Foye & Simmons, LLP
    Rapid City, South Dakota                    Attorneys for plaintiff
    and appellant.
    STAN H. ANKER
    JORDAN D. BORDEWYK of
    Anker Law Group, PC
    Rapid City, South Dakota                    Attorneys for defendants
    and appellees.
    ****
    CONSIDERED ON BRIEFS
    ON FEBRUARY 18, 2014
    OPINION FILED 04/16/14
    #26755
    ZINTER, Justice
    [¶1.]        Belmont, Inc. leased unfinished commercial real-estate space from Tri-
    City Associates, L.P. The parties later filed claims against each other for breach of
    the lease. The circuit court entered a judgment in favor of Belmont on all claims.
    The court reasoned that although both parties failed to fulfill certain obligations
    under the lease, Tri-City materially breached the lease, thus excusing Belmont from
    performance. Tri-City appeals contending that its failure to complete its initial
    construction obligations and its failure to deliver the space in “broom clean”
    condition were excused by the lease’s “as is” clause. Tri-City also contends that it
    was excused by Belmont’s failure to give notice of breach and an opportunity to
    cure. We reverse and remand for the circuit court to enter findings of fact and
    conclusions of law on the effect of Belmont’s failure to give notice of breach and an
    opportunity to cure.
    Facts and Procedural History
    [¶2.]        Tri-City was the owner and developer of a shopping center in Rapid
    City. Belmont was formed to operate a meat and produce business in Rapid City.
    In May 2006, Belmont and Tri-City entered into a commercial real-estate lease for a
    space in the shopping center that Tri-City was developing. The lease was to start
    on August 1, 2006.
    [¶3.]        A “work letter” attached to the lease allocated some of the initial
    construction work between Tri-City and Belmont. That work was necessary to
    ready the premises for occupancy and use in Belmont’s meat and produce business.
    The work letter also required Tri-City to provide the premises in “broom clean”
    -1-
    #26755
    condition. The work letter further recited that Belmont had inspected the premises
    and was taking them in “as is” condition. 1 Nevertheless, there is no dispute that
    Tri-City did not complete its allocated portion of the initial construction, nor did it
    deliver the premises in broom clean condition by August 1, 2006.
    [¶4.]         Even though the August 1 start date passed without Tri-City fulfilling
    its obligations, Belmont worked with Tri-City, attempting to complete construction
    and ready the premises for occupancy and use. However, the parties encountered
    numerous problems and delays that rendered their attempts unsuccessful. In
    December 2006, Tri-City proposed moving the start date of the lease from August 1,
    2006, to January 15, 2007. Belmont did not sign the proposed modification
    agreement.
    1.      The work letter provided, in relevant part:
    LANDLORD’S WORK which Landlord is obligated to initially
    construct and pay for, shall consist of the following work: [listing
    construction obligations]. Except for Landlord’s obligation to
    put the Premises in a “broom clean” condition, Tenant agrees
    that Landlord has no other construction obligations, other than
    the aforementioned, with respect to Tenant’s initial occupancy of
    the Premises and that Tenant has inspected the Premises and is
    taking the Premises in its “AS IS” condition, with no
    representations or warranties of any kind with respect to the
    condition of the Premises and its building systems or its
    suitability of the Premises for Tenant’s business.
    TENANT’S WORK, for which Tenant is obligated to construct
    and pay for, shall consist of the items of work described below,
    and all other work necessary to complete the improvements in
    the Premises in accordance with the Approval Tenant Plans,
    except any items of work expressly included in Landlord’s Work.
    Tenant to invest a minimum of $50,000.00 in
    renovation/fixturing costs and provide evidence of same to
    Landlord.
    -2-
    #26755
    [¶5.]         In March 2007, Tri-City served Belmont with a notice to quit and
    vacate. In April 2007, Tri-City sued to evict Belmont and recover damages for
    unpaid rent and other Belmont obligations under the lease. In July 2007, based on
    a stipulation between the parties, the circuit court awarded possession of the
    premises to Tri-City.
    [¶6.]         In October 2007, Belmont filed an amended answer and added a
    counterclaim. Belmont denied liability for damages and claimed that Tri-City
    materially breached the lease by failing to fulfill its initial construction and broom
    clean obligations. Tri-City responded that even if it failed to perform those
    obligations, Belmont was liable for rent, and Belmont’s counterclaim was barred
    because Belmont accepted the property as is. Tri-City also contended that Belmont
    failed to provide Tri-City with written notice of its alleged breach and an
    opportunity to cure as required by another provision in the lease. 2
    2.      The notice-and-cure provision provided, in relevant part:
    Landlord’s Default. Landlord shall be in default under this
    Lease upon . . . (b) the failure of Landlord to observe, keep or
    perform any of the other terms, covenants, agreements or
    conditions contained in this Lease on the part of Landlord to be
    observed or performed and such failure continues for a period of
    thirty (30) days after written notice by Tenant to Landlord or, if
    such failure is not reasonably susceptible to cure within thirty
    (30) days, then within a reasonable period of time so long as
    Landlord shall have commenced to cure such failure within such
    thirty (30) day period and shall thereafter diligently pursue such
    cure to completion. Tenant may not exercise any remedies
    available to it under this Lease, at law or in equity until
    Landlord has been afforded the cure periods described in this
    Paragraph 48 . . . .
    -3-
    #26755
    [¶7.]        After a court trial, the circuit court found that Tri-City failed to deliver
    the premises in broom clean condition and failed to complete its allocated portion of
    the initial construction. The court concluded that Tri-City’s failures were material
    breaches that excused Belmont from liability and rendered Tri-City liable on
    Belmont’s counterclaim. The court made no findings of fact or conclusions of law on
    Tri-City’s claim that Belmont’s failure to follow the lease’s notice-and-cure provision
    barred Belmont’s defense and counterclaim.
    [¶8.]        Tri-City appeals, contending that Belmont’s defense and counterclaim
    were barred as a matter of law by: (1) the lease provision in which Belmont accepted
    the premises as is, and (2) Belmont’s failure to give Tri-City notice of its alleged
    breach and an opportunity to cure.
    Decision
    [¶9.]        The questions on appeal involve the interpretation of the lease. A
    lease is a contract, so contract principles govern its interpretation. See Icehouse,
    Inc. v. Geissler, 
    2001 S.D. 134
    , ¶ 21, 
    636 N.W.2d 459
    , 465 (“As a lease is a contract
    we will follow the law of contract in regard to breach.” (citation omitted)). Contract
    interpretation is a question of law that we review de novo. Poeppel v. Lester, 
    2013 S.D. 17
    , ¶ 16, 
    827 N.W.2d 580
    , 584 (citation omitted).
    [¶10.]       Tri-City first contends that Belmont’s execution of the lease containing
    the as is clause barred a judgment in favor of Belmont as a matter of law. We
    disagree.
    [¶11.]       The goal of contract interpretation is to determine the parties’ intent.
    See 
    id. To determine
    intent, we look “to the language that the parties used in the
    -4-
    #26755
    contract[.]” 
    Id. (quoting Detmers
    v. Costner, 
    2012 S.D. 35
    , ¶ 20, 
    814 N.W.2d 146
    ,
    151). We do not, however, interpret “particular words and phrases . . . in isolation.”
    Casey Ranch Ltd. P’ship v. Casey, 
    2009 S.D. 88
    , ¶ 11, 
    773 N.W.2d 816
    , 821 (quoting
    In re Dissolution of Midnight Star Enters., 
    2006 S.D. 98
    , ¶ 12, 
    724 N.W.2d 334
    ,
    337). Nor do we interpret language “in a manner that renders a portion of [the
    contract] meaningless.” Estate of Fisher v. Fisher, 
    2002 S.D. 62
    , ¶ 14, 
    645 N.W.2d 841
    , 846 (citation omitted). Instead, we interpret the contract to give “a reasonable
    and effective meaning to all [its] terms[.]” Casey Ranch, 
    2009 S.D. 88
    , ¶ 
    11, 773 N.W.2d at 821
    (quoting Midnight Star, 
    2006 S.D. 98
    , ¶ 
    12, 724 N.W.2d at 337
    ).
    [¶12.]       In this case, the lease obligated Tri-City to deliver the premises to
    Belmont on the start date in broom clean condition, with Tri-City’s allocated portion
    of the initial construction completed. Tri-City does not dispute that it failed to
    fulfill those obligations. Instead, Tri-City contends that it was essentially absolved
    of responsibility to satisfy those obligations because Belmont accepted the premises
    in as is condition when it signed the lease in May 2006. Tri-City’s position does not
    give a reasonable and effective meaning to all terms of the lease.
    [¶13.]       The as is clause appears in the same paragraph as the clauses
    requiring Tri-City to provide certain construction and to present the premises in
    broom clean condition. Yet Tri-City’s interpretation would read the as is clause to
    abrogate its construction and broom clean obligations, rendering the broom clean
    and construction clauses meaningless. Tri-City’s interpretation also fails to
    recognize that the parties signed the lease in May 2006, but use and occupancy of
    the premises were not contemplated until August 1, 2006. Therefore, although the
    -5-
    #26755
    lease provided that Belmont was taking the premises in as is condition on the date
    the lease was executed, it expressly contemplated that Tri-City would provide
    initial construction and present the premises in broom clean condition after the
    lease was executed. Tri-City’s interpretation would abrogate its future obligations
    by signing the lease, an absurd result that could not have been intended.
    [¶14.]       A harmonious reading of all provisions reflects that the as is clause did
    not abrogate Tri-City’s post-execution obligations to perform initial construction
    and to deliver the premises in broom clean condition. Indeed, the work letter
    specifically provided that Belmont was taking the premises as is “[e]xcept for” Tri-
    City’s obligation to put the premises in broom clean condition and “other than [Tri-
    City’s] aforementioned” allocated construction obligations. We conclude that the as
    is clause did not bar the judgment in favor of Belmont as a matter of law.
    [¶15.]       Tri-City alternatively argues that Belmont’s defense and counterclaim
    were barred by the notice-and-cure provision. Tri-City emphasizes that this
    provision required Belmont to give Tri-City written notice and time to cure any
    default before Belmont could “exercise any remedies available to it[.]” Tri-City
    contends that because Belmont did not comply with this provision, a judgment in
    Belmont’s favor was barred as a matter of law.
    [¶16.]       Belmont responds first by arguing that our standard of review is
    limited to determining whether the circuit court’s findings of fact support its
    conclusions of law—Belmont claims they do. Belmont contends that limited review
    is mandated under Canyon Lake Park, L.L.C. v. Loftus Dental, P.C., 
    2005 S.D. 82
    ,
    
    700 N.W.2d 729
    , because Tri-City did not submit both “its own findings of fact and
    -6-
    #26755
    conclusions of law and object to the trial court’s findings of fact and conclusions of
    law.” Belmont misreads Canyon Lake.
    [¶17.]        In Canyon Lake, “neither party specifically objected to [the circuit
    court’s] findings of fact or conclusions of law, nor did they submit their own findings
    of fact or conclusions of law.” 
    Id. ¶ 10.
    We held that the failure to either object to or
    propose findings or conclusions limited our “review to the question of whether the
    findings support[ed] the conclusions of law and judgment.” 
    Id. ¶ 11
    (quoting
    Premier Bank, N.A. v. Mahoney, 
    520 N.W.2d 894
    , 895 (S.D. 1994)). We also cited
    Selway Homeowners Association v. Cummings, for a similar holding, explaining
    that because “the appellant failed to either object to findings of fact or conclusions of
    law proposed by the appellee, or propose findings of fact and conclusions of law of
    their own,” our review was limited to determining “whether the findings supported
    the conclusions of law and judgment[.]” Canyon Lake, 
    2005 S.D. 82
    , ¶ 
    11, 700 N.W.2d at 733
    (emphasis added) (citing Selway, 
    2003 S.D. 11
    , ¶ 14, 
    657 N.W.2d 307
    , 312).
    [¶18.]        Thus, under our cases, there are two methods to preserve our ordinary
    standard of review. Review is not limited unless the appealing party failed to object
    to and failed to propose findings of fact and conclusions of law. Either alternative
    satisfies the purpose of the rule, which is to bring the issue to the attention of the
    circuit court for a ruling.
    [¶19.]        In this case, although Tri-City did not object to the circuit court’s
    findings of fact and conclusions of law, Tri-City did propose findings and conclusions
    on the notice-and-cure issue. Because Tri-City proposed findings of fact and
    -7-
    #26755
    conclusions of law on this issue, our review is not limited. We review findings of
    fact for clear error and conclusions of law de novo. See Eagle Ridge Estates
    Homeowners Ass’n v. Anderson, 
    2013 S.D. 21
    , ¶ 12, 
    827 N.W.2d 859
    , 864 (citing
    SDCL 15-6-52(a)); Detmers, 
    2012 S.D. 35
    , ¶ 
    9, 814 N.W.2d at 149
    .
    [¶20.]       Belmont next argues that Tri-City cannot rely on the notice-and-cure
    provision for two reasons. First, Belmont contends that by bringing this suit, Tri-
    City demonstrated that it had no intent to perform its obligations and cure its
    default. Second, Belmont contends that even if Tri-City can rely on the notice-and-
    cure provision, Belmont’s motion to amend its answer and assert a counterclaim
    provided the required notice of Tri-City’s defaults. Belmont points out that after it
    moved to add the counterclaim, which identified Tri-City’s defaults, Tri-City had
    sufficient time to cure but did not.
    [¶21.]       Tri-City requested that the circuit court rule on the notice-and-cure
    issue. Tri-City proposed findings of fact and conclusions of law to the effect that
    Belmont’s claims were barred by the notice-and-cure provision. Although this issue
    was presented to the circuit court, the court did not address the effect of the notice-
    and-cure provision on Belmont’s counterclaim.
    [¶22.]       The circuit court’s failure to address the notice-and-cure issue is
    problematic because some courts have concluded that the failure to abide by a
    notice-and-cure provision precludes judicial relief. For example, in Kinstler v. RTB
    South Greeley, LTD. LLC, the Wyoming Supreme Court affirmed a trial court’s
    rejection of a tenant’s claim that he was excused from paying rent because his
    landlord materially breached a lease. 
    160 P.3d 1125
    , 1126 (Wyo. 2007). The court
    -8-
    #26755
    noted that the tenant correctly argued “that, under some circumstances, one party’s
    material breach of an agreement may excuse the other party’s performance under
    that agreement.” 
    Id. at 1127
    (citation omitted). But the court explained that
    “[w]hen a party fails to provide notice of a material breach, if required by the terms
    of the lease, reliance on that breach to excuse contractual performance is improper.”
    
    Id. at 1128
    (citation omitted); see also Huttenbauer Land Co. v. Harley Riley, Ltd.,
    No. C-110842, 
    2012 WL 4760871
    , at *2 (Ohio Ct. App. Oct. 5, 2012) (unreported
    opinion) (“Because the lease provides that [the landlord] is entitled to notice and an
    opportunity to cure an alleged default, and because such notice and opportunity
    were not provided . . ., [the landlord’s] default did not result in a breach of the lease
    and its actions could not have served as a basis to excuse [the tenant’s] performance
    under the lease.”); Hoover v. Wukasch, 
    274 S.W.2d 458
    , 460 (Tex. Civ. App. 1955)
    (holding that a lease’s notice-and-cure provision, requiring that the tenant give
    written notice to the landlord about needed roof repairs, precluded the tenant from
    withholding rent because the tenant had failed to give required notice).
    [¶23.]       Other courts, however, have concluded that a failure to strictly comply
    with a notice-and-cure provision does not necessarily preclude recovery. In an
    unreported opinion, the Ohio Court of Appeals, citing a number of reported
    opinions, explained why such a provision may not preclude recovery:
    “Although courts generally should give effect to the plain
    meaning of the parties’ unambiguously expressed intentions, in
    some circumstances, courts will not strictly enforce contractual
    language requiring notice in writing.” [Gollihue v. Nat’l City
    Bank, 
    969 N.E.2d 1233
    , 1238 (Ohio Ct. App. 2011).] In those
    cases, a failure to provide notice according to the terms of the
    contract may not preclude recovery on the contract where the
    party has received actual notice. [Id. at 1238-39; Adair v.
    -9-
    #26755
    Landis Props., No. 08AP-139, 
    2008 WL 4174130
    , at *3-*4 (Ohio
    Ct. App. Sept. 11, 2008); Daniel E. Terreri & Sons, Inc. v.
    Mahoning Cnty. Bd. of Comm’rs, 
    786 N.E.2d 921
    , 932 (Ohio Ct.
    App. 2003).] “The purpose of requiring written notice is not to
    be hypertechnical but, instead, to create certainty.” [McGowan
    v. DM Grp. IX, 
    455 N.E.2d 1052
    , 1055 (Ohio Ct. App. 1982).]
    Marion Forum, L.L.C. v. Lynick Enters., Inc., No. 9-12-13, 
    2012 WL 6571388
    , at *4-
    *5 (Ohio Ct. App. Dec. 17, 2012) (finding that the record demonstrated that the
    landlord had received actual notice of maintenance issues, even though the tenant
    had failed to strictly comply with a notice-and-cure provision).
    [¶24.]       Because of the conflicting authority and the circuit court’s failure to
    address the notice-and-cure provision, we decline to review this issue. Further
    proceedings are necessary to answer unresolved questions such as substantial
    compliance, actual notice, and materiality. We reverse and remand for the entry of
    findings of fact and conclusions of law on the effect of Belmont’s failure to give
    notice of breach and an opportunity to cure.
    [¶25.]       Both parties have moved for appellate attorney’s fees, and each has
    filed accompanying itemized statements of expenses. “[A]ttorney fees may only be
    awarded by contract or when explicitly authorized by statute.” In re Estate of
    O’Keefe, 
    1998 S.D. 92
    , ¶ 17, 
    583 N.W.2d 138
    , 142 (quoting Schuldies v. Millar, 
    1996 S.D. 120
    , ¶ 37, 
    555 N.W.2d 90
    , 100). In this case, the lease governs attorney fees,
    and it provides that fees are recoverable by “the prevailing party.” However, at this
    point, neither party has prevailed. We decline to award attorney’s fees to either
    party.
    [¶26.]       Reversed and remanded for further proceedings on the notice-and-cure
    provision of the lease.
    -10-
    #26755
    [¶27.]      GILBERTSON, Chief Justice, and KONENKAMP, SEVERSON, and
    WILBUR, Justices, concur.
    -11-