Hyperion I & II , 2013 S.D. 10 ( 2013 )


Menu:
  • #26290, #26293-a-SLZ
    
    2013 S.D. 10
    IN THE SUPREME COURT
    OF THE
    STATE OF SOUTH DAKOTA
    ****
    IN THE MATTER OF THE
    PREVENTION OF SIGNIFICANT
    DETERIORATION (PSD) AIR
    QUALITY PERMIT APPLICATION OF
    HYPERION ENERGY CENTER –
    HYPERION REFINING, LLC –
    PERMIT #28.0701 – PSD.
    ****
    APPEAL FROM THE CIRCUIT COURT OF
    THE SIXTH JUDICIAL CIRCUIT
    HUGHES COUNTY, SOUTH DAKOTA
    ****
    THE HONORABLE MARK BARNETT
    Judge
    ****
    (#26290)
    MARTY JACKLEY
    Attorney General
    ROXANNE GIEDD
    Deputy Attorney General
    Pierre, South Dakota                        Attorneys for appellee South
    Dakota Department of
    Environment & Natural Resources.
    MARTY JACKLEY
    Attorney General
    CHARLES D. MCGUIGAN
    Chief Deputy Attorney General
    Pierre, South Dakota                        Attorneys for appellee South
    Dakota Board of Minerals and
    Environment.
    ****
    ARGUED ON OCTOBER 3, 2012
    OPINION FILED 01/23/13
    FREDERICK W. ADDISON, III
    AMY L. RICKERS of
    Munsch, Hardt, Kopf & Harr, PC
    Dallas, Texas
    and
    TODD MEIERHENRY of
    Meierhenry Sargent, LLP
    Sioux Falls, South Dakota                   Attorneys for appellee Hyperion
    Refining, LLC.
    ROBERT L. GRAHAM
    GABRIELLE SIGEL of
    Jenner & Block, LLP
    Chicago, Illinois
    JOHN H. DAVIDSON, JR.
    Vermillion, South Dakota
    and
    SAM E. KHOROOSI
    Sioux Falls, South Dakota                   Attorneys for intervenors and
    appellants Sierra Club, Save Union
    County, and Citizens Opposed to
    Oil Pollution.
    (#26293)
    MARTY JACKLEY
    Attorney General
    ROXANNE GIEDD
    Deputy Attorney General
    Pierre, South Dakota                        Attorneys for appellee South
    Dakota Department of
    Environment & Natural Resources.
    MARTY JACKLEY
    Attorney General
    CHARLES D. MCGUIGAN
    Chief Deputy Attorney General
    Pierre, South Dakota                        Attorneys for appellee South
    Dakota Board of Minerals and
    Environment.
    FREDERICK W. ADDISON, III
    AMY L. RICKERS of
    Munsch, Hardt, Kopf & Harr, PC
    Dallas, Texas
    and
    TODD MEIERHENRY of
    Meierhenry Sargent, LLP
    Sioux Falls, South Dakota                   Attorneys for appellant Hyperion
    Refining, LLC.
    #26290, #26293
    ZINTER, Justice
    [¶1.]         The Board of Minerals and Environment (Board) authorized the
    Department of Environment and Natural Resources (DENR) to issue an air quality
    permit to Hyperion Refining, LLC (Hyperion). The permit was necessary for
    Hyperion to begin construction of a proposed petroleum refinery and power plant.
    Three citizens groups appealed to circuit court. Hyperion also appealed a permit
    condition limiting the amount of carbon monoxide that could be emitted from the
    proposed facility. The circuit court affirmed the Board’s decision in all respects.
    The citizens groups now appeal the issuance of the permit, and Hyperion appeals
    the permit’s carbon monoxide limit. We affirm.
    Facts and Procedural History
    [¶2.]         This case involves the issuance of a “Prevention of Significant
    Deterioration Air Quality” permit (PSD permit) to Hyperion. Hyperion proposed to
    construct a large petroleum refinery and power plant in Union County. 1 Federal
    and state regulations required Hyperion to obtain a PSD permit before constructing
    the facility. Among other things, a PSD permit regulates air quality by limiting the
    pollutants a facility may emit into the ambient air.
    [¶3.]         In December 2007, Hyperion submitted a PSD permit application
    containing 613 pages of materials to DENR. Three citizens groups—Save Union
    1.      Hyperion’s proposed facility includes a refinery and a power plant. Hyperion
    proposed to refine Canadian crude from oil sands into ultralow sulfur
    gasoline, heating oil, diesel fuel, and low sulfur jet fuel. The power plant
    would provide most of the electricity needed by the refinery. Additional
    electricity would be purchased commercially.
    -1-
    #26290, #26293
    County, Citizens Opposed to Oil Pollution, and the Sierra Club (collectively,
    “Citizens”)—intervened and contested issuance of the permit.
    [¶4.]         Citizens also requested that a state environmental impact statement
    (EIS) be prepared before the permit was issued. DENR, the state agency in charge
    of preparing EISs and considering PSD permits, denied Citizens’ request. On
    December 15, 2008, after extensive study and responses to public comments, DENR
    recommended approval of a PSD permit with ninety-six pages of conditions.
    [¶5.]         DENR’s recommendation was challenged, and in the summer of 2009,
    the proposed permit was litigated in ten days of contested case hearings before the
    Board. Twice during the hearings, Citizens renewed their request for an EIS. The
    requests were denied. 2 On August 20, 2009, the Board authorized DENR to issue
    the permit.
    [¶6.]         One permit condition imposed a “commence construction” deadline of
    eighteen months, which was February 20, 2011. The permit provided that, if
    construction of the facility was not commenced by that date, the permit “[became]
    invalid.” The permit, however, allowed DENR’s Secretary to grant an extension of
    time to commence construction if Hyperion applied for the extension within the
    eighteen-month time period and demonstrated that the extension was justified.
    2.      Citizens requested the Board to review DENR’s decision to not order an EIS.
    Citizens also requested the Board to order an EIS. In its findings of fact and
    conclusions of law, the Board ruled that “an EIS is not necessary for
    consideration in this matter, and the DENR properly exercised its authority
    and discretion [in] choosing not to perform an EIS.” DENR contends that the
    Board had no authority to review DENR’s decision. We do not address that
    contention because we conclude that neither the Board nor DENR abused its
    discretion in declining to order an EIS.
    -2-
    #26290, #26293
    [¶7.]          Another permit condition required that carbon monoxide emissions
    from the proposed facility’s twenty large “process heaters” could not exceed certain
    “Best Available Control Technology” (BACT) limits. BACT limits are designed to
    require the maximum degree of reduction of pollutant emissions that is achievable.
    The permit imposed a carbon monoxide BACT limit of 0.007 lb/mmBtu (pounds per
    million British thermal units) for the process heaters.
    [¶8.]          Citizens appealed the issuance of the permit to circuit court. Hyperion
    filed a separate appeal challenging the carbon monoxide BACT limit. Hyperion
    argued that 0.010 lb/mmBtu was the achievable limit.
    [¶9.]          On June 23, 2010, while the appeals were pending, the circuit court
    granted a Hyperion motion to remand the matter to allow the Board to consider
    additional evidence on several issues, including a request to extend the commence
    construction deadline. On the same date, Hyperion filed an application with DENR
    to extend the commence construction deadline to August 20, 2012.
    [¶10.]         DENR then began the process of investigating, soliciting public
    comments, and considering new evidence on the new issues and the request to
    extend the commence construction deadline. Over the next eight months, DENR
    made numerous requests of Hyperion for additional information to address the new
    issues and the request for an extension. 3 DENR ultimately proposed a draft
    amended permit, which included an extension of the commence construction
    deadline. The draft amended permit was made available for public comment on
    3.       All requested information was submitted by February 14, 2011.
    -3-
    #26290, #26293
    February 14, 2011, six days before the original commence construction deadline was
    to expire. The public comment period ran from February 14, 2011, to April 1, 2011.
    [¶11.]         On March 21, 2011, the Board entered a scheduling order. The order
    set a July 2011 contested case hearing to consider the proposed amended permit.
    On March 31, 2011, Hyperion filed its comments on the draft amended permit. In
    its comments, Hyperion requested that the commence construction deadline be
    extended to eighteen months after the Board approved the amended permit. 4
    [¶12.]         After public comments and DENR’s response to public comments, a
    four-day contested case hearing on the amended permit was held in July 2011.
    Extensive expert testimony and nearly 4,000 pages of exhibits were presented to the
    Board. Hyperion indicated that it had not commenced construction because of the
    national economic downturn; the need to address new federal regulations regarding
    sulfur dioxide and nitrogen dioxide emissions; the identification of a new emission
    source that required correction of the initial permit; and the uncertainty of the
    permit’s status as a result of the ongoing litigation.
    [¶13.]         On September 16, 2011, the Board entered findings and conclusions
    approving DENR’s issuance of the amended permit. The amended permit
    incorporated Hyperion’s request to extend the commence construction deadline to
    eighteen months after the effective date of the amended permit. The amended
    permit retained the carbon monoxide 0.007 lb/mmBtu BACT limit.
    4.       Neither DENR nor the Board formally and finally acted on this request for an
    amended commenced construction deadline until the conclusion of the
    contested case proceedings.
    -4-
    #26290, #26293
    [¶14.]       Citizens then appealed the Board’s September 2011 decision. The
    circuit court consolidated the 2011 appeal with Hyperion’s and Citizens’ 2009
    appeals. In a detailed memorandum decision, the court ultimately affirmed the
    decisions not to order an EIS, affirmed the determination that Hyperion presented
    satisfactory justification for the extension of the commence construction deadline,
    affirmed the issuance of the amended permit, and affirmed the carbon monoxide
    0.007 lb/mmBtu BACT limit.
    [¶15.]       We consider the following issues raised by Citizens:
    1. Whether an EIS should have been ordered before the issuance of
    the PSD permit.
    2. Whether the initial permit “became invalid” when the Board
    neither ruled on Hyperion’s request to extend the commence
    construction deadline within the original eighteen-month period nor
    adopted the ultimate deadline that was requested within that
    period.
    3. Whether Hyperion presented satisfactory justification for its
    request to extend the commence construction deadline.
    We consider the following issue raised by Hyperion:
    4. Whether the Board clearly erred in determining the carbon
    monoxide BACT limit.
    Decision
    [¶16.]       “We review agency decisions the same as the circuit court . . . .” St.
    Pierre v. State ex rel. S.D. Real Estate Comm’n, 
    2012 S.D. 25
    , ¶ 14, 
    813 N.W.2d 151
    ,
    156. We “give great weight to the findings made and inferences drawn by an agency
    on questions of fact.” SDCL 1-26-36. “[Q]uestions of law are reviewed de novo.”
    Brown v. Douglas Sch. Dist., 
    2002 S.D. 92
    , ¶ 9, 
    650 N.W.2d 264
    , 267. We may
    reverse agency decisions when “substantial rights of the appellant have been
    -5-
    #26290, #26293
    prejudiced because the administrative findings, inferences, conclusions, or
    decisions” are, among other things, in violation of statutes, affected by an error of
    law, are clearly erroneous, or constitute an abuse of discretion. SDCL 1-26-36.
    1. Environmental Impact Statement
    [¶17.]         SDCL chapter 34A-9 is South Dakota’s Environmental Policy Act.
    SDCL 34A-9-4 provides in relevant part: “All agencies may prepare, or have
    prepared by contract, an environmental impact statement on any major action they
    propose or approve which may have a significant effect on the environment.” 5
    However, the Act is separate from, and involves environmental concerns in addition
    5.       The Board and DENR are “agencies.” See SDCL 34A-9-1 (defining an
    “[a]gency” as “the executive and administrative departments, offices, boards,
    commissions, and other units of the state government”). The parties,
    however, disagree whether issuing a PSD permit is an “action” that allows
    both agencies to order an EIS under SDCL chapter 34A-9. Citizens argue
    that SDCL 34A-9-2(3) specifically defines the issuance of a PSD permit as an
    agency “action.” That statute provides: “As used in [chapter 34A-9], the term,
    actions, includes . . . [t]he issuance by one or more public agencies of a lease,
    permit, license, certificate, or other public entitlement to an applicant.”
    SDCL 34A-9-2. The Board and Hyperion argue that issuing a PSD permit is
    not an agency “action.” They rely on SDCL 34A-9-3(5), which provides: “As
    used in [chapter 34A-9], the term, actions, does not include . . . [a]ctions of an
    environmentally protective regulatory nature.” The Board and Hyperion
    contend that PSD permits are environmentally protective regulations.
    Environmentally protective regulations are substantially different than PSD
    permits. A permit (like the PSD permit) is issued to an individual party (like
    Hyperion), authorizing that party to engage in a particular activity. In
    contrast, environmentally protective regulations have broad non-
    individualized application. Regulations apply to the citizenry as a whole.
    Because a PSD permit only authorizes an identified permit holder to engage
    in identified activities, it is not an environmentally protective regulation
    within the meaning of SDCL 34A-9-3(5). We also note that SDCL 34A-9-2(3)
    is the more specific statute. We conclude that PSD permitting is governed by
    SDCL 34A-9-2(3), which specifically makes permitting an agency “action.”
    The Board and DENR were authorized to order an EIS before issuing
    Hyperion’s PSD permit.
    -6-
    #26290, #26293
    to those that are relevant in PSD air quality permitting. Compare South Dakota
    Environmental Policy Act’s broad application to any action that may have a
    significant impact on the environment with ARSD 74:36:09:02’s provisions only
    involving air quality.
    [¶18.]       Citizens first argue that the Board erroneously determined it had no
    jurisdiction to order an EIS under SDCL chapter 34A-9. Citizens misconstrue the
    Board’s determination. The Board did not determine that it had no jurisdiction to
    order an EIS. The Board determined that “an EIS is much broader and
    encompasses many subject matters over which the Board has no jurisdiction.” We
    agree with the Board’s determination.
    [¶19.]       Citizens acknowledge that, in addition to an assessment of air quality,
    an EIS would assess the proposed project’s other environmental effects, such as
    effects on roads, soils, water resources, noise, waste disposal, etc. But the only
    “action” proposed to be approved was the issuance of a PSD permit. See SDCL 34A-
    9-2, -4. Therefore, the Board’s jurisdiction in this proceeding did not include
    regulatory authority over “all the [other environmental] factors which the [Citizens]
    deem relevant to the [permit] consideration.” See In re Solid Waste Disposal Permit
    Application, 
    268 N.W.2d 599
    , 601 (S.D. 1978). The Board’s jurisdiction was limited
    to the specific requirements established in the statutes and regulations for issuance
    of the air quality permit. See id. at 600-01. Thus, the Board correctly recognized
    that its jurisdiction was limited to the PSD permit issues, and the Board had no
    jurisdiction to regulate the other environmental effects of the proposed facility in
    this PSD proceeding.
    -7-
    #26290, #26293
    [¶20.]       Citizens also argue that the Board and DENR abused their discretion
    in determining that an EIS was not necessary. Under SDCL 34A-9-4, “an EIS is
    optional, not mandatory.” In re SDDS, Inc., 
    472 N.W.2d 502
    , 507 (S.D. 1991). See
    also In re S.D. Water Mgmt. Bd. Approving Water Permit No. 1791-2, 
    351 N.W.2d 119
    , 124 (S.D. 1984) (concluding that the EIS statute “evidence[s] a legislative
    intent not to require an environmental impact statement every time [the] Board
    rules on a . . . permit”). “Since the [decision to order an EIS] is one which lies in the
    discretion of the agency, we can reverse its decision only if it reflects a clearly
    unwarranted exercise of discretion.” In re SDDS, 472 N.W.2d at 507.
    [¶21.]       The purpose of an EIS is “to inform the public and other public
    agencies as early as possible about proposed actions” and “to solicit comments which
    will assist the agency in determining the environmental consequences of the
    proposed action.” SDCL 34A-9-6. These purposes were addressed in the Board’s
    and DENR’s administrative process. That process included a detailed technical
    review of Hyperion’s permit application, publication of the proposed action, DENR’s
    solicitation and response to public comments, and consideration of the evidence
    presented at the contested case hearings.
    [¶22.]       DENR first performed an extensive technical review of Hyperion’s
    application. After issuing public notices of the application and DENR’s proposed
    action, DENR then received extensive commentary from the public, other agencies,
    and environmental groups. Those commenting included the United States
    Department of Interior, the United States Environmental Protection Agency (EPA),
    and Plains Justice. DENR then considered the comments, issued responses, and
    -8-
    #26290, #26293
    made changes to the proposed permit. In its response to comments, DENR noted
    that an EIS was unnecessary because “the procedural and substantive
    requirements for obtaining an air quality permit provide the agency [with]
    information that is functionally equivalent to the relevant information that would
    be provided by an environmental impact statement.” (Emphasis added.)
    [¶23.]       A public contested hearing was then held before the Board. The Board
    considered the filed comments and DENR’s responses. The Board heard the
    extensive evidence for and against the project. The Board considered alternatives
    to Hyperion’s proposed equipment. The Board assessed the facility’s proposed
    design and operational limits. The Board reviewed Hyperion’s additional impacts
    analysis and determined that “no adverse impacts are expected to air quality,
    visibility, or soils and vegetation as a result of [Hyperion’s proposed facility] and
    associated commercial, residential, and industrial growth.”
    [¶24.]       The Board also considered expert testimony on the need for an EIS.
    Kyrik Rombough, DENR’s Natural Resources Engineering Director, was the lead
    permit writer for the PSD permit program. Since beginning work at DENR, he had
    processed and reviewed hundreds of air quality permits. Rombough testified that
    DENR’s review of Hyperion’s permit application indicated an EIS was unnecessary.
    Colin Campbell, Hyperion’s expert, oversaw air permitting projects and worked
    with state agencies in implementing air permitting programs. He testified that,
    when he was involved in Arizona’s and Utah’s air permitting processes, neither
    state required EISs. He also testified that, based on his experience, EISs were not
    typically prepared for similar projects, such as refinery expansions.
    -9-
    #26290, #26293
    [¶25.]         The federal EIS experience is also instructive. Under the National
    Environmental Policy Act, EISs are generally mandated. 
    42 U.S.C.A. § 4332
    (c)
    (West 2012). Nevertheless, federal air quality permits, including PSD permits, are
    exempt from the mandate. 
    15 U.S.C.A. § 793
    (c)(1) (West 2012); 
    40 C.F.R. § 124.9
    (b)(6). See also In re Knauf Fiber Glass, 
    8 E.A.D. 121
    , 35 (EAB 1999). We
    acknowledge that the federal statutory exemption does not control the discretionary
    decision under SDCL 34A-9-4. But the federal law’s exemption does suggest that
    Congress determined EISs are generally not required to protect the environment in
    determining entitlement to PSD air quality permits.
    [¶26.]         Finally, we note the record reflects that other environmental concerns
    typically addressed in an EIS will not be overlooked. Although an EIS was not
    prepared in the air quality permitting portion of this regulatory proceeding, the
    record indicates that other EIS concerns will be addressed in other regulatory
    proceedings that are necessary to construct and operate the proposed facility. In
    denying the Citizens’ request for an EIS, the Secretary of DENR explained:
    We [ ] disagree with your assertions that other
    environmental concerns, such as water withdrawals, water
    use, groundwater, surface water, water quality, stormwater,
    waste disposal, wastewater, and spill response, will not be
    considered. While these issues are not addressed in the
    draft [PSD permit] that is currently under review, those other
    environmental issues will be fully considered when Hyperion
    complies with a host of other permitting and regulatory
    processes, such as a water right permit, discharge permits,
    waste disposal permit, etc. . . . 6
    6.       At oral argument, the Court was informed that Hyperion will most likely be
    required to obtain a federal “404 permit” for the proposed facility’s surface
    water discharges. The Court was further informed that, in most
    circumstances, the United States Army Corp of Engineers must prepare
    (continued . . .)
    -10-
    #26290, #26293
    [¶27.]         In sum, the Board’s and DENR’s decisions to deny the requests for an
    EIS were supported by DENR’s technical review of Hyperion’s application and other
    agency and public comments; DENR’s response to those agency and public
    comments; and the testimony and environmental evidence considered in the
    administrative process. 7 We conclude that the Board and DENR did not abuse their
    discretion in denying the requests for an EIS.
    2. Validity of the Permit
    [¶28.]         Citizens point out that original permit condition 2.1 imposed a
    commence construction deadline of February 20, 2011. Citizens argue that the
    permit expired because Hyperion did not commence construction or obtain an
    extension before that initial deadline. Citizens also argue that because the
    amended deadline ultimately adopted was not requested within the initial eighteen-
    month period, the Board was without authority to authorize that amended deadline.
    Citizens rely on the language of original permit condition 2.1, ARSD 74:36:09:02,
    and 40 C.F.R. section 52.21(r)(2).
    [¶29.]         The interpretation of a permit is analogous to the interpretation of a
    contract or statute. “Contract and statutory interpretation are questions of law we
    review de novo.” AFSCME Local 1025 v. Sioux Falls Sch. Dist., 
    2011 S.D. 76
    , ¶ 11,
    
    809 N.W.2d 349
    , 352. “Administrative regulations are subject to the same rules of
    ________________________
    (. . . continued)
    either an EIS or Environmental Assessment when determining whether to
    issue a 404 permit. See 
    33 C.F.R. § 336.1
    (b)(6).
    7.       On appeal, Citizens have not contended that the Board erred in refusing any
    offered environmental evidence.
    -11-
    #26290, #26293
    construction as are statutes.” WestMed Rehab, Inc. v. Dep’t of Soc. Servs., 
    2004 S.D. 104
    , ¶ 8, 
    687 N.W.2d 516
    , 518.
    [¶30.]         Condition 2.1 imposed a commence construction deadline but allowed
    extensions. Condition 2.1 provided:
    In accordance with ARSD 74:36:09:02, as referenced to 
    40 C.F.R. § 52.21
    (r)(2), the owner or operator shall commence construction
    within 18 months of the effective date of this permit. If
    construction is delayed or interrupted for a period of 18 months
    or more this permit becomes invalid. The owner or operator
    may apply, before the end of the 18-month period, to the
    Secretary [of DENR] for an extension. The Secretary may grant
    an extension after the owner or operator satisfactorily
    demonstrates that an extension is justified.
    Condition 2.1 is premised upon ARSD 74:36:09:02, 8 which incorporates 40 C.F.R.
    section 52.21(r)(2). 9
    [¶31.]         There is no dispute that Hyperion did not commence construction by
    February 20, 2011. Citizens’ first argument is that, even though Hyperion’s initial
    extension application was filed within the eighteen-month time to commence
    8.       ARSD 74:36:09:02 provides, that “the state’s definitions and requirements for
    the prevention of significant deterioration are those in 
    40 C.F.R. § 52.21
     . . . .”
    9.       40 C.F.R. section 52.21(r)(2) provides:
    Approval to construct shall become invalid if construction is not
    commenced within 18 months after receipt of such approval, if
    construction is discontinued for a period of 18 months or more,
    or if construction is not completed within a reasonable time.
    The Administrator may extend the 18-month period upon a
    satisfactory showing that an extension is justified. This
    provision does not apply to the time period between construction
    of the approved phases of a phased construction project; each
    phase must commence construction within 18 months of the
    projected and approved commencement date.
    -12-
    #26290, #26293
    construction, the permit became invalid because the Board did not grant the
    extension until after the initial eighteen-month period expired. 10 Citizens point out
    that condition 2.1 and 40 C.F.R. section 52.21(r)(2) do not explicitly state that the
    original permit remains in effect or that the permit’s expiration is stayed while the
    Secretary considers a request for an extension. Thus, Citizens contend that when
    the Secretary failed to grant an extension before the expiration of the initial
    commence construction deadline, the original permit automatically expired,
    precluding any amendment. 11 Citizens contend that the original and amended
    10.   Hyperion and DENR argue that SDCL 1-26-28 extended the validity of
    Hyperion’s permit while the application for an extension was pending. SDCL
    1-26-28 provides:
    If a licensee has made timely and sufficient application for
    renewal of a license or a new license with reference to any
    activity of a continuing nature, the existing license, or a right to
    continue the activity, does not expire until the application has
    been finally determined by the agency and for ten days following
    receipt, or failure to accept delivery, of notice of such
    determination by the licensee.
    (Emphasis added.) A permit is a “license” for purposes of this statute. See
    SDCL 1-26-1(4). However, SDCL 1-26-28 did not apply to Hyperion’s
    application for the extension. Hyperion requested that condition 2.1 be
    amended to extend the construction deadline. Hyperion did not request a
    “renewal” or a “new” permit. See 
    id. 11
    .   Citizens rely on Sierra Club v. Franklin County Power of Illinois, LLC, 
    546 F.3d 918
     (7th Cir. 2008). However, in Franklin County, no extension
    application had been filed. The dispute was whether a permittee had
    “commenced construction” by entering a construction memorandum and
    conducting engineering research and excavation work. 
    Id. at 929-31
    .
    Franklin County does not support Citizens’ argument that PSD permits
    automatically expire even though a timely extension application is pending.
    Citizens also argue that Hyperion was required to request a temporary
    extension when it appeared that DENR would be unable to act on the
    (continued . . .)
    -13-
    #26290, #26293
    permits cannot be upheld because “it is beyond the role of the courts to supply
    omitted language” authorizing PSD permits to remain in effect until the Secretary
    rules on extension requests.
    [¶32.]       The language of 40 C.F.R. section 52.21(r)(2) and condition 2.1 cannot,
    however, be read to require an automatic expiration of the PSD permit if a timely
    application for extension is pending and the Secretary is unable to rule on the
    application within the original time limit. It must be noted that 40 C.F.R. section
    52.21(r)(2) does not impose any time limits for filing extension requests, and
    condition 2.1 allowed the extension request to be filed any time before the eighteen-
    month period expired. It must also be noted that both the condition and the rule
    contemplate that the Secretary must have time to consider additional evidence
    before deciding extension requests. Condition 2.1 provides that the Secretary may
    grant an extension only “after the owner or operator satisfactorily demonstrates
    that an extension is justified.” (Emphasis added.) Similarly, 40 C.F.R. section
    52.21(r)(2) authorizes extensions only “upon a satisfactory showing that an
    extension is justified.” (Emphasis added.) Thus, the condition and rule allow
    extension requests to be filed up to the last day of the eighteen-month period, but
    require the extension to be preceded by a satisfactory showing that the extension is
    justified. We conclude the rule and condition necessarily contemplated that a final
    decision may not necessarily be made within the initial deadline.
    ________________________
    (. . . continued)
    requested extension within the initial eighteen-month deadline. We decline
    to consider this argument. Citizens presented no authority allowing DENR
    to grant temporary extensions without determining whether the extension
    was justified.
    -14-
    #26290, #26293
    [¶33.]       Indeed, it may be impossible to obtain a final ruling on an extension
    request within the original deadline. As this case demonstrates, extension requests
    may be complicated matters that require extensive time to administratively resolve.
    Because an extension request seeks to amend a condition of a PSD permit, the
    request must be processed under the same administrative procedure as a permit
    application, which requires lengthy administrative proceedings. And if the initial
    permit is on appeal, the administrative process must be preceded by filing a motion
    with the reviewing court to seek the permit’s return to the Board to allow the
    consideration of additional evidence. See Jundt v. Fuller, 
    2007 S.D. 62
    , ¶ 7, 
    736 N.W.2d 508
    , 512. If the reviewing court grants the motion, the permit holder must
    then apply for an extension with the Secretary. Next, the Secretary must
    recommend an amended permit, publish the proposed permit, and provide time for
    a contested case hearing. See ARSD 74:36:09:03. Finally, interested parties may
    litigate the matter before the Board. Considering the many months necessary to
    complete this administrative process, it would be impossible to obtain a final ruling
    on many extension requests within the initial eighteen-month period, even requests
    filed early within the initial eighteen-month period.
    [¶34.]       In this case, Hyperion submitted its initial extension application on
    June 23, 2010. During its review of the application, DENR requested additional
    information from Hyperion. DENR’s draft amended permit was not made available
    for public comment until February 14, 2011, six days before the initial deadline was
    to expire. DENR received over 350 public comments on the draft amended permit,
    and DENR responded to those comments when issuing its final proposed amended
    -15-
    #26290, #26293
    permit. A contested case hearing was requested, and on March 21, 2011, the Board
    scheduled a contested case proceeding for July 25, 2011, over thirteen months after
    the initial extension request. The Board heard closing arguments on September 15,
    2011, and issued its findings of fact and conclusions of law on September 16, 2011.
    In total, the administrative process took almost fifteen months to complete, not
    counting the time necessary to resolve appeals of the Board’s decision in the courts.
    [¶35.]       Considering the realities of environmental permitting, Citizens’
    interpretation of 40 C.F.R. section 52.21(r)(2) and condition 2.1 leads to an absurd
    result. Because of the lengthy time necessary to obtain a final ruling on an
    extension request in complicated cases, few, if any, such extension requests could be
    considered under Citizens’ interpretation. Citizens’ interpretation of condition 2.1
    would abrogate what condition 2.1 and 40 C.F.R. section 52.21(r)(2) expressly
    authorize: an opportunity to obtain an extension after a timely application and a
    full consideration by the Secretary and the Board of conflicting evidence relating to
    the request. We conclude that the permit did not become invalid solely because the
    Secretary was procedurally unable to grant a final extension within the original
    eighteen-month period. We do not interpret language to reach an absurd result.
    State v. Robert, 
    2012 S.D. 27
    , ¶ 10, 
    814 N.W.2d 122
    , 125.
    [¶36.]       Citizens, however, contend that allowing the Secretary an indefinite
    timeframe to rule on an extension request thwarts the purposes of the deadline.
    According to DENR’s and Hyperion’s experts, there are two reasons for the
    eighteen-month deadline. First, the deadline ensures that BACT determinations
    are current. See Ky. Mountain Power, LLC v. Energy & Env’t Cabinet, No. DAQ-
    -16-
    #26290, #26293
    29109-039, 
    2009 WL 6214729
    , at *38 (Ky. Envtl. & Pub. Protection Cabinet Dec. 1,
    2009) (“[D]ecisions about pollution control methods and associated emissions
    limitations are made based on the most current information possible.”). Second, the
    deadline ensures that permit holders do not, by delay or inaction, obtain longer time
    periods than allowed to build new facilities, thereby unnecessarily tying up a state’s
    air resources and industrial growth rights.
    [¶37.]       The additional time taken by the Secretary did not frustrate these
    purposes. When preparing the draft amended permit, DENR reevaluated BACT
    limits and reviewed new regulations, which ensured that the BACT determinations
    were up to date. DENR also required modeling to ensure the proposed facility
    would comply with new emission standards. Finally, there was no evidence that
    Hyperion had tied up the State’s air resources or restricted any other competing
    industrial growth.
    [¶38.]       Citizens also argue that, even if the Board was authorized to grant
    Hyperion’s initial extension application after the eighteen-month period had
    expired, the finally adopted extension was invalid. Citizens contend that the finally
    adopted extension was invalid because Hyperion did not make that particular
    extension request before the initial eighteen-month deadline had expired. This
    argument overlooks the nature of the finally adopted request in the context of the
    required administrative proceedings.
    [¶39.]       Hyperion’s initial June 2010 request for an August 20, 2012 extended
    deadline was made within the original eighteen-month period. But the Secretary
    did not act on Hyperion’s request until he issued a proposed draft amended permit
    -17-
    #26290, #26293
    and notice of opportunity for public comment on February 14, 2011. At that point,
    the public notice comment period remained open until April 1, 2011, well after the
    initial commence construction deadline would expire. On March 31, 2011, Hyperion
    filed its comments to DENR’s draft amended permit. In those comments, Hyperion
    requested that the deadline be extended to eighteen months after the amended
    permit was ultimately issued. Hyperion indicated that it amended its request for
    an extension “in light of the unpredictable timeline associated with the approval of
    the amended permit.” Thus, Hyperion made a timely application for an extension;
    Hyperion was aware that DENR was recommending that an extension be granted;
    but the original deadline was expiring and substantial additional time would be
    needed before Hyperion would receive a final determination on the extension
    request. Under these circumstances, Hyperion’s amended request for an extension,
    made within the proceeding to determine the initial extension request, was an
    amendment that did not constitute a new and therefore untimely application. Cf.
    Bitterroot River Protective Ass’n v. Siebel, 
    108 P.3d 518
    , 522, 524 (Mont. 2005)
    (holding that amendments to substantially deficient water appropriation
    applications constituted new applications because the “changes were so significant
    that the amended applications bear[ed] little resemblance, if any, to the original
    applications[,]” and therefore, the amendments did not relate back to the date of the
    timely filed deficient applications).
    [¶40.]       We conclude that DENR and the Board were not required to render a
    final decision on the initial timely extension request within the initial eighteen-
    month period. Further, the subsequent amendment to the request was made
    -18-
    #26290, #26293
    during the extension proceedings, and that amendment was not so different as to
    constitute a new application. Therefore, Hyperion’s permit did not become invalid.
    3. Justification to Extend the Commence Construction Deadline
    [¶41.]       Citizens argue that Hyperion did not sufficiently justify its request for
    an extension of the commence construction deadline. Citizens contend that the
    Board’s contrary determination was clearly erroneous. “For an agency finding of
    fact to be clearly erroneous, a court must be definitely and firmly convinced, after
    reviewing all the evidence, that the agency made a mistake.” McKibben v. Horton
    Vehicle Components, Inc., 
    2009 S.D. 47
    , ¶ 11, 
    767 N.W.2d 890
    , 894. “However, we
    defer to the agency on the credibility of a witness who testified live because the
    agency ‘is in a better position . . . to evaluate the persuasiveness of [witness]
    testimony.’” 
    Id.
     (second alteration in original) (quoting Lends His Horse v. Myrl &
    Roy’s Paving, Inc., 
    2000 S.D. 146
    , ¶ 15, 
    619 N.W.2d 516
    , 520). See also Burke v.
    Butte Cnty., 
    2002 S.D. 17
    , ¶ 16, 
    640 N.W.2d 473
    , 478 (stating that “[the agency] is
    entitled to weigh the credibility of the witnesses and is free to choose between
    conflicting testimony”).
    [¶42.]       In its 2011 findings of fact and conclusions of law, the Board found that
    Hyperion presented satisfactory justification for the extension.
    The Board determines that the evidence submitted in support of
    Hyperion’s request for an extension of the commence
    construction deadline is justified given the economic recession,
    which caused delays in development of large capital projects
    such as [Hyperion’s proposed facility], the pending appellate
    process regarding the status of the permit, the recent discovery
    of the additional emission unit for [Hyperion’s proposed facility],
    -19-
    #26290, #26293
    the coker quench water system, as well as the additional
    National Ambient Air Quality Standards for SO2 and NO2.
    The record supports this finding.
    [¶43.]       At the 2011 contested hearing, a Hyperion vice-president testified that
    the recession affected Hyperion’s ability to begin constructing the facility. He also
    indicated that the uncertainty of the permit’s status and the need to address two
    new federal emission requirements justified an extension. The vice-president
    finally indicated that Hyperion had recently identified a “coker quench” water
    system as an additional emission source, and therefore, Hyperion needed an
    extension to obtain an amended permit to include that emission source.
    [¶44.]       Citizens, however, contend that Hyperion did not specifically identify
    how the economic recession and the ongoing litigation affected Hyperion’s ability to
    meet the commence construction deadline. Citizens also contend that Hyperion
    contributed to the uncertainty of the permit’s status because Hyperion itself
    appealed the BACT limit for the process heaters. Further, Citizens contend that
    the two new federal emission requirements did not justify an extension because
    those new requirements would not have applied if Hyperion had not requested to
    amend its permit. Finally, Citizens contend that Hyperion had ample time to
    correct the coker quench water system oversight before the initial deadline expired.
    [¶45.]       Although Citizens cross-examined Hyperion’s vice-president regarding
    the reasons for the extension, the Board was best suited to determine the credibility
    of the vice-president and the weight to be given to his testimony. Further, Citizens
    provided no contradicting testimony. Therefore, after reviewing the entire record,
    we are not definitely and firmly convinced that the Board made a mistake. The
    -20-
    #26290, #26293
    Board did not clearly err in finding satisfactory justification for extension of the
    commence construction deadline.
    4. Carbon Monoxide “Best Available Control Technology” Limit
    [¶46.]       Large process heaters at Hyperion’s proposed facility will burn refinery
    gas to heat equipment used in the refinery process. There is no dispute that a
    carbon monoxide BACT limit is required for the heaters. The dispute is the
    achievable BACT limit.
    [¶47.]       ARSD 74:36:09:02 incorporates 40 C.F.R. section 52.21(b)(12), which
    defines the “best available control technology” for limiting regulated pollutant
    emissions at the proposed facility:
    Best available control technology means an emissions limitation
    (including a visible emission standard) based on the maximum
    degree of reduction for each pollutant subject to regulation . . .
    which would be emitted from any proposed major stationary
    source or major modification which the Administrator, on a case-
    by-case basis, taking into account energy, environmental, and
    economic impacts and other costs, determines is achievable for
    such source or modification through application of production
    processes or available methods, systems, and techniques,
    including fuel cleaning or treatment or innovative fuel
    combustion techniques for control of such pollutant. . . .
    To establish a proper BACT limit for a permit under this rule, the proposed limit
    must be shown to be both: 1) the maximum degree of reduction of a pollutant
    subject to regulation (considering energy, environmental, and economic impacts and
    other costs), and 2) achievable for such source. 
    Id.
     A BACT limit is achievable if
    the facility, when operating, is able to comply with that emission limit.
    [¶48.]       DENR proposed the 0.007 lb/mmBtu BACT limit, which the Board
    adopted. Hyperion argues that limit is not supported by evidence and is
    -21-
    #26290, #26293
    unachievable for its facility. Hyperion argues that a 0.010 lb/mmBtu limit is
    supported by the evidence. Hyperion contends that the Board clearly erred in
    adopting DENR’s proposed limit. We “give great weight to the findings of the
    agency and reverse only when those findings are clearly erroneous in light of the
    entire record.” Williams v. S.D. Dep’t of Agric., 
    2010 S.D. 19
    , ¶ 5, 
    779 N.W.2d 397
    ,
    400.
    [¶49.]         Because a PSD permit must be issued before construction is initiated,
    the achievable BACT limit is based on agency review of estimates and projections of
    pollutants that will be emitted by the proposed facility. 12 These estimates and
    projections are based on engineering analysis, computer modeling, and regulatory
    data from other states and the EPA. DENR supported its proposed 0.007 lb/mmBtu
    limit by evidence of other facilities’ emission limits. The Board adopted DENR’s
    proposed 0.007 lb/mmBtu limit, finding that DENR’s proposed limit was based on
    performance testing and other permits. The Board also found that the 0.007
    lb/mmBtu limit was achievable.
    [¶50.]         Hyperion argues that the Board clearly erred in relying on DENR’s
    evidence. Hyperion contends that the other facilities and their carbon monoxide
    emission limits were not comparable to Hyperion’s proposed facility.
    [¶51.]         Kyrik Rombough, DENR’s Natural Resources Engineering Director,
    testified at the 2009 hearing. He testified that he converted emission limit
    12.      After a PSD permit is issued and the facility is constructed, the facility’s
    operator must apply for a “Part 70” (a/k/a “Title V”) operating permit within
    the first year of operation. ARSD 74:36:05:08. It is not until that time that
    actual emissions data from performance tests exist to demonstrate
    compliance with emissions limits. ARSD 74:36:05:06.
    -22-
    #26290, #26293
    measurements used by the reviewed facilities to the “lb/mmBtu” emission limit
    measurement imposed in this permit. Rombough indicated that after the
    conversion, the other facilities’ emission limits were equivalent to the 0.007
    lb/mmBtu limit. Hyperion challenges the comparison of the emission limit
    measurements from other facilities.
    [¶52.]       Hyperion first challenges DENR’s reliance on the Baytown refinery in
    Texas. Hyperion points out that Baytown was an ethylene production facility,
    unlike Hyperion’s proposed oil refinery. Hyperion also points out that Baytown’s
    carbon monoxide BACT limit was revised and is currently less stringent than
    Hyperion’s proposed 0.010 lb/mmBtu limit. However, Rombough testified that the
    fuels burned in Baytown’s process heaters were similar to Hyperion’s proposed
    fuels. Rombough further testified he had verified with the Texas permitting agency
    that Baytown’s achievable limit was equivalent to a 0.007 lb/mmBtu limit.
    [¶53.]       Hyperion also challenges DENR’s reliance on the CENCO refinery.
    Hyperion contends that this facility never operated, and therefore, its ability to
    achieve a limit equivalent to 0.007 lb/mmBtu was not substantiated through
    performance tests. Rombough acknowledged that CENCO never operated.
    Rombough, however, indicated that CENCO’s limit—a limit that converted to a
    0.007 lb/mmBtu limit—was based on two operational facilities (TOSCO and All Air
    Products) whose permits required a limit equivalent to 0.007 lb/mmBtu. Rombough
    also testified that he had analyzed a TOSCO performance test, which indicated that
    TOSCO had complied with an emission limit equivalent to the 0.007 lb/mmBtu
    limit. Although Hyperion relies on its expert, who opined that these facilities were
    -23-
    #26290, #26293
    not comparable because of differences in the refinery fuel gases, the Board was best
    suited to adopt the expert’s testimony that the Board believed was more persuasive.
    [¶54.]         Hyperion finally contends that the Board erred in relying on the Big
    West refinery because it was never permitted or built. However, in Big West’s
    application for a PSD permit, the applicant itself asserted that a 0.007 lb/mmBtu
    limit was achieved by process heaters burning refinery gas in testing conducted by
    California. Although Big West never operated, the evidence reflects that the limit
    was determined by performance testing. Again, the Board was in the best position
    to accept or reject the comparability of the evidence with respect to Big West. 13
    [¶55.]         We also note that Hyperion’s permit was reconsidered by the Board in
    the 2011 contested case proceedings. DENR had reevaluated Hyperion’s BACT
    limit to ensure that it was current. DENR considered updated data, new permits,
    and new regulations regarding BACT limits. Both DENR and the Board reaffirmed
    the 0.007 lb/mmBtu limit in light of new developments regarding carbon monoxide
    BACT limits.
    [¶56.]         Hyperion, however, contends that publication of new EPA regulations
    before the 2011 hearing substantiated its inability to achieve a 0.007 lb/mmBtu
    limit. 14 Hyperion points out that some of the EPA regulations, using a different
    13.      In its findings, the Board acknowledged that Big West’s application was
    withdrawn and no performance data existed for that facility. The Board also
    acknowledged that the EPA “cautions against the use of cancelled permits for
    BACT analysis.” The Board, however, did not indicate that the actual
    performance testing used in Big West’s application was suspect.
    14.      DENR argues that Hyperion’s evidence regarding new EPA evaluations of
    emissions data provided in the amended permit proceeding is not reviewable
    (continued . . .)
    -24-
    #26290, #26293
    numerical limit, indicate upper predictive carbon monoxide limits that were higher
    than the limit adopted by the Board. Hyperion argues that the DENR’s reliance on
    the EPA’s lower limits was misplaced because the lower limits were averages and
    an average emission level does not indicate an “achievable” limit over an extended
    period of operation.
    [¶57.]       DENR, however, explained that when the new EPA background
    testing data was converted for comparison purposes, it revealed 423 test results at
    new facilities with limits less than the EPA average. Therefore, in DENR’s view,
    the new regulations supported a 0.007 lb/mmBtu BACT limit. Further, Rombough
    testified that the EPA employed a limits testing method that differed from
    Hyperion’s method. The Board adopted DENR’s view, finding that Hyperion’s limit
    “contain[ed] both filterable and condensable particulate matters, whereas EPA’s
    new regulation only include[d] filterable material.”
    [¶58.]       We acknowledge that Hyperion presented testimony supporting its
    proposed limit. We also acknowledge that some of DENR’s comparative evidence
    was subject to different interpretations. But ultimately, the comparability of other
    facilities involved conflicting evidence. As previously noted, under these
    ________________________
    (. . . continued)
    because Hyperion did not specifically raise the issue at the 2011 contested
    hearing. However, the carbon monoxide emission limit remained in issue
    since the 2009 hearing. In fact, Hyperion’s appeal of the imposed limit
    following the 2009 hearing was still pending at the time of the 2011 hearing.
    Further, Hyperion gave notice that it was continuing to contest the 2009
    decision, and Hyperion submitted evidence on this contested issue in its
    September 2010 letter responding to DENR’s request that Hyperion review
    the EPA’s evaluations. Therefore, the issue was raised at the Department
    level and may be reviewed by this Court. See Stuckey v. Sturgis Pizza Ranch,
    
    2011 S.D. 1
    , ¶ 19 n.3, 
    793 N.W.2d 378
    , 386 n.3.
    -25-
    #26290, #26293
    circumstances, we “defer to the agency on the credibility of a witness who testified
    live because the agency ‘is in a better position . . . to evaluate the persuasiveness of
    [witness] testimony.’” McKibben, 
    2009 S.D. 47
    , ¶ 11, 
    767 N.W.2d at 894
     (second
    alteration in original) (quoting Lends His Horse, 
    2000 S.D. 146
    , ¶ 15, 
    619 N.W.2d at 520
    ). The Board did not clearly err in deciding that the 0.007 lb/mmBtu BACT limit
    was achievable for Hyperion’s project.
    [¶59.]       Affirmed.
    [¶60.]       GILBERTSON, Chief Justice, and KONENKAMP and SEVERSON,
    Justices, and CALDWELL, Retired Circuit Court Judge, concur.
    [¶61.]       CALDWELL, Retired Circuit Court Judge, sitting for WILBUR,
    Justice, disqualified.
    -26-