Brude v. Breen , 900 N.W.2d 301 ( 2017 )


Menu:
  • #28064-r-GAS
    
    2017 S.D. 46
    IN THE SUPREME COURT
    OF THE
    STATE OF SOUTH DAKOTA
    ****
    SUZANNE BRUDE,                           Plaintiff and Appellant,
    v.
    SHANE BREEN d/b/a YELLOW JACKET
    IRRIGATION AND LANDSCAPING,              Defendant, Third-Party
    Plaintiff, and Appellee,
    v.
    GREGORY AND ELIZABETH JAMISON,           Third-Party Defendants.
    ****
    APPEAL FROM THE CIRCUIT COURT OF
    THE SECOND JUDICIAL CIRCUIT
    MINNEHAHA COUNTY, SOUTH DAKOTA
    ****
    THE HONORABLE JOHN R. PEKAS
    Judge
    ****
    RONALD A. PARSONS, JR.
    STEVEN M. JOHNSON
    KIMBERLY L. JOHNSON of
    Johnson Janklow Abdallah
    Reiter & Parsons LLP
    Sioux Falls, South Dakota                Attorneys for appellant.
    MELANIE L. CARPENTER
    JORDAN J. FEIST of
    Woods, Fuller, Shultz
    and Smith, PC
    Sioux Falls, South Dakota                Attorneys for appellee.
    ****
    ARGUED MAY 30, 2017
    OPINION FILED 08/02/17
    #28064
    SEVERSON, Justice
    [¶1.]        Suzanne Brude brought suit against Shane Breen, doing business as
    Yellow Jacket Irrigation and Landscaping (Yellow Jacket), for negligence in
    constructing a retaining wall from which Brude suffered an injury. Yellow Jacket
    moved for summary judgment, asserting that the claim was barred by the statute of
    repose. The circuit court granted summary judgment in favor of Yellow Jacket.
    Brude appeals, asserting that the court erred because the ten-year limitation in the
    statute of repose had not expired. We reverse and remand.
    Background
    [¶2.]        In 2005, Yellow Jacket Irrigation and Landscaping contracted for and
    completed a landscaping project at the residence of Greg and Elizabeth Jamison. At
    issue in this case is landscaping that Yellow Jacket originally completed in
    September 2005. The area of landscaping at issue includes a patio with retaining
    walls on its sides and a fire pit above a section of the retaining wall. The retaining
    walls were repaired in 2007. At that time, Yellow Jacket fixed some stone pavers
    that had settled and shifted. The Jamisons and Breen have different recollections
    of the next time that Yellow Jacket worked on the retaining wall; it was either 2011
    or 2013. The Jamisons asked Yellow Jacket to fix their patio area because some of
    the landscaping stones settled and leaned. Greg Jamison testified in his deposition
    that because the fix was fairly extensive and would require the retaining walls to be
    torn down and rebuilt, the Jamisons asked Yellow Jacket to make the fire pit area a
    little larger at the same time.
    -1-
    #28064
    [¶3.]        Suzanne Brude was at the Jamison residence on October 7, 2014. In
    order to retrieve some branches from the fire pit area, she stepped onto the portion
    of the retaining wall in front of the Jamison’s fire pit. One of the capstones she
    stepped on gave way, and she fell onto the patio below. She suffered an injury that
    required surgery the next day. On November 6, 2015, Brude commenced this action
    against Shane Breen, the sole proprietor operating Yellow Jacket Irrigation and
    Landscaping. Yellow Jacket filed a third-party complaint against the Jamisons,
    contending that the Jamisons were responsible for any damages awarded to Brude.
    The Jamisons have since settled this matter and take no position in this appeal.
    [¶4.]        On July 29, 2016, Yellow Jacket moved for summary judgment
    asserting that the statutory time period to bring a claim had expired because the
    retaining wall and fire pit had been substantially completed more than ten years
    prior to the commencement of this action. See SDCL 15-2A-3. After submissions by
    the parties and a hearing on the motion, the circuit court granted summary
    judgment for Yellow Jacket. Brude appeals raising one issue for our review. She
    asserts that the changes to the landscaping that occurred in either 2011 or 2013
    constituted “an improvement to real property” under SDCL 15-2A-3 and therefore
    restarted the ten-year period to bring a claim. Thus, she claims that the court erred
    when it granted summary judgment.
    Standard of Review
    [¶5.]        “In reviewing a grant or denial of summary judgment we must
    determine whether the moving party demonstrated the absence of any genuine
    issue of material fact and established entitlement to judgment on the merits as a
    -2-
    #28064
    matter of law.” Clark Cty. v. Sioux Equip. Corp., 
    2008 S.D. 60
    , ¶ 8, 
    753 N.W.2d 406
    ,
    409 (quoting Behrens v. Wedmore, 
    2005 S.D. 79
    , ¶ 18, 
    698 N.W.2d 555
    , 565).
    “Those resisting summary judgment must show that they will be able to place
    sufficient evidence in the record at trial to support findings on all the elements on
    which they have the burden of proof.” 
    Id. (quoting Bordeaux
    v. Shannon Cty. Sch.,
    
    2005 S.D. 117
    , ¶ 14, 
    707 N.W.2d 123
    , 127). We must determine the applicability of
    the statute of repose to Yellow Jacket’s latest work on the retaining wall. “Because
    the application of a legal test to the historical facts of this case requires us to
    consider legal concepts and ‘exercise judgment about the values that animate legal
    principles,’ we review the . . . determination de novo.” 
    Id. ¶ 10,
    753 N.W.2d at 410
    (quoting In re Dorsey & Whitney Tr. Co., 
    2001 S.D. 35
    , ¶ 6, 
    623 N.W.2d 468
    , 471).
    Analysis
    [¶6.]         A statute of repose is an affirmative defense, and Yellow Jacket had
    the initial burden of proving entitlement to it. See 
    id. ¶ 17,
    753 N.W.2d at 412.
    “[W]here a defendant, by motion for summary judgment, asserts this type of
    affirmative defense that bars an action ‘and presumptively establishes the defense
    by showing the case was instituted beyond the statutory period, the burden then
    shifts to the plaintiff to establish the existence of material facts in avoidance of the
    statute.’” 
    Id. (quoting Conway
    v. Conway, 
    487 N.W.2d 21
    , 23 (S.D. 1992)). The
    statute of repose at issue, SDCL 15-2A-3, provides:
    No action to recover damages for any injury to real or personal
    property, for personal injury or death arising out of any
    deficiency in the design, planning, supervision, inspection, and
    observation of construction, or construction, of an improvement
    to real property, nor any action for contribution or indemnity for
    damages sustained on account of such injury or death, may be
    -3-
    #28064
    brought against any person performing or furnishing the design,
    planning, supervision, inspection, and observation of
    construction, or construction, of such an improvement more than
    ten years after substantial completion of such construction. The
    date of substantial completion shall be determined by the date
    when construction is sufficiently completed so that the owner or
    his representative can occupy or use the improvement for the
    use it was intended.
    The parties agree that the initial construction of the landscaping was completed in
    September 2005 and that it constituted an improvement to real property at that
    time. Brude was injured in October 2014, and the claim was brought in November
    2015. Therefore, Yellow Jacket met its initial burden of presumptively showing
    that the action was brought beyond the statutory period in SDCL15-2A-3. See also
    SDCL 15-2A-5 (providing that an injury occurring in the tenth year after
    substantial completion may be brought within one year after the date on which the
    injury occurred but may not be brought more than eleven years after the
    substantial completion of construction).
    [¶7.]         The next question before this Court is whether Brude met her burden
    to establish the existence of material facts in avoidance of the statute. In response
    to Yellow Jacket’s motion for summary judgment and its statement of undisputed
    material facts, Brude maintained that Yellow Jacket’s work in 2011/2013 restarted
    the statute of repose because it constituted construction of an improvement to real
    property. She provided a report indicating that the latest work in 2011/2013 was
    not done in accordance with industry standards.∗ She also provided her own
    statement of undisputed material facts, which set forth that the rebuild was not
    ∗       The Court was unable to find any other report in the record indicating that
    the original construction was performed negligently.
    -4-
    #28064
    performed correctly and caused the capstones to dislodge. And Brude set forth facts
    indicating that her injuries arose from a portion of the retaining wall where Yellow
    Jacket performed work in 2011/2013.
    [¶8.]        Before we can determine whether Brude met her burden to set forth
    material facts in avoidance of the statute, we must clarify how the ten-year time
    frame under SDCL 15-2A-3 is calculated. Citing to this Court’s decision in Pitt-
    Hart v. Sanford USD Med. Ctr., 
    2016 S.D. 33
    , ¶ 18, 
    878 N.W.2d 406
    , 413, Brude
    asserts that her time in which to bring an action is measured from the latest
    construction that led to her injury and that the ten-year period started in
    2011/2013. In Pitt-Hart, we addressed SDCL 15-2-14.1, which provides that “[an]
    action . . . can be commenced only within two years after the alleged malpractice,
    error, mistake, or failure to cure shall have occurred[.]” (Emphasis added.); Pitt
    Hart, 
    2016 S.D. 33
    , ¶ 
    18, 878 N.W.2d at 413
    . We noted that “[a] statute of
    repose . . . is measured not from the date on which the claim accrues but instead
    from the date of the last culpable act or omission of the defendant.” Pitt Hart, 
    2016 S.D. 33
    , ¶ 
    18, 878 N.W.2d at 413
    (quoting CTS Corp. v. Waldburger, ___ U.S. ___,
    ___, 
    134 S. Ct. 2175
    , 2182, 
    189 L. Ed. 2d 62
    (2014)).
    [¶9.]        In this case, the statute of repose explicitly provides for a different date
    from which to measure. It states, in pertinent part,
    No action to recover damages . . . for personal injury or death
    arising out of any deficiency in the design, planning,
    supervision, inspection, and observation of construction, or
    construction, of an improvement to real property . . . may be
    brought . . . more than ten years after substantial completion of
    such construction. The date of substantial completion shall be
    determined by the date when construction is sufficiently
    -5-
    #28064
    completed so that the owner or his representative can occupy or
    use the improvement for the use it was intended.
    SDCL 15-2A-3 (emphasis added). The time to bring a claim did not begin to run
    upon the last culpable act of Yellow Jacket but instead upon the date of substantial
    completion of the improvement to real property. Thus, if the latest construction of
    the retaining wall and fire pit was not an improvement to real property, then
    substantial completion of construction occurred in September 2005, making Brude’s
    claim untimely. If, however, construction in 2011/2013 constituted an improvement
    to real property, then the statute of repose started that year upon substantial
    completion of the construction, and the time period in SDCL 15-2A-3 had not run in
    November of 2015 when Brude commenced suit.
    [¶10.]       Yellow Jacket asserts that Brude’s claim is untimely because the work
    in 2011/2013 was not an improvement and only amounted to repairs. Even if the
    work in 2011/2013 amount to a repair, Brude’s claim may still be timely if the
    injury arose out of the work done in 2011/2013 and the repair was not within the
    scope of SDCL 15-2A-3. However, Brude’s claim may still be timely if the work in
    2011/2013 amounted to a repair, the injury arose out of the 2011/2013 work, and a
    repair is not within the scope of SDCL 15-2A-3. Brude set forth facts indicating
    that she fell from a portion of the wall that was negligently repaired by Yellow
    Jacket in either 2011 or 2013 and that, therefore, her injury did not arise from the
    original construction of an improvement to real property. Accordingly, we must
    determine whether a repair to an improvement to real property falls within the
    scope of SDCL 15-2A-3.
    -6-
    #28064
    [¶11.]       South Dakota does not have an explicit statute providing that repairs
    to an improvement to real property fall outside the scope of the statute of repose.
    But the plain language of SDCL 15-2A-3 clearly provides that it will only apply to
    this case if the injury arose out of the construction of an improvement to real
    property. This Court distinguished improvements to real property from repairs in
    Clark Cty. v. Sioux Equip. Corp., 
    2008 S.D. 60
    , ¶ 11-12, 
    753 N.W.2d 406
    , 410-11. In
    that case, Clark County sued Sioux Equipment in 2006 for negligence, breach of
    implied and express warranties, and breach of implied warranty of fitness for a
    particular purpose in regard to a fuel storage and dispensing system that was
    installed in 1991. A fuel leak occurred in 2003 for which the County incurred
    remediation expenses. Sioux Equipment argued that the 1991 installation was an
    improvement to real property and that, therefore, the claim was barred under
    SDCL 15-2A-3. The county argued that the installation was a replacement or
    repair of a previous system, not an improvement, so SDCL 15-2A-3 did not apply.
    We applied a common-sense test to determine whether there was an “improvement
    to real property.” Under the test, we determine whether there is “[a] permanent
    addition to or betterment of real property that enhances its capital value and that
    involves the expenditure of labor or money and is designed to make the property
    more useful or valuable as distinguished from ordinary repairs.” Clark Cty., 
    2008 S.D. 60
    , ¶ 
    11, 753 N.W.2d at 410
    (emphasis added). Thus, if an ordinary repair is
    not an improvement and SDCL 15-2A-3 applies only to improvements, it is inherent
    that SDCL 15-2A-3 does not apply to claims for injuries arising from ordinary
    repairs.
    -7-
    #28064
    [¶12.]       We find helpful the Wisconsin Court of Appeals’ explanation of
    Wisconsin’s statute of repose as follows:
    The purpose of the statute of repose is to protect contractors who
    are involved in permanent improvements to real property. Daily
    repairs are not improvements to real property as that phrase is
    used in the statute of repose. The legislature has chosen to
    protect persons or entities which make permanent
    improvements to real property, not to absolve those who make
    regular repairs or do maintenance work. This distinction is
    reasonable because improvements to real property have a
    completion date whereas regular repairs and maintenance can
    continue ad infinitum.
    Peter v. Sprinkmann Sons Corp., 
    860 N.W.2d 308
    , 315 (Wis. Ct. App. 2015).
    Despite the absence of an explicit provision in our statutes, the purpose of a statute
    of repose as stated by the Wisconsin Court of Appeals is similar to the findings set
    forth by South Dakota’s Legislature. SDCL 15-2A-1 provides in part:
    The Legislature finds that subsequent to the completion of
    construction, persons involved in the planning, design, and
    construction of improvements to real estate lack control over the
    determination of the need for, the undertaking of and the
    responsibility for maintenance, and lack control over other
    forces, uses and intervening causes which cause stress, strain,
    wear, and tear to the improvements and, in most cases, have no
    right or opportunity to be made aware of or to evaluate the effect
    of these forces on a particular improvement or to take action to
    overcome the effect of these forces. Therefore, it is in the public
    interest to set a point in time following the substantial
    completion of the project after which no action may be brought
    for errors and omissions . . . .
    Therefore, the Legislature also recognized the difference between the initial
    “planning, design, and construction of improvements to real estate” and the
    “maintenance” or repairs of said improvements. Here, Yellow Jacket did have
    control over the repair work because it performed the work. See Hartford Fire Ins.
    Co. v. Westinghouse Elec. Corp., 
    450 N.W.2d 183
    , 186 (Minn. Ct. App. 1990)
    -8-
    #28064
    (holding that replacement of generator seal constituted ordinary repair and
    therefore was not subject to the statute of repose).
    [¶13.]       Having determined that repairs do not fall under the statute of repose,
    Brude has met her burden to set forth material facts to avoid application of the
    statute. She set forth facts indicating that the work in 2011/2013 could be
    considered an improvement to real property (restarting the period of repose)
    because it involved, among other things, enlarging the landscaping area and the
    expenditure of labor. Furthermore, even if it was not an improvement, she set forth
    sufficient facts that her injury did not arise out of the 2005 construction of an
    improvement to real property; it allegedly arose out of Yellow Jacket’s latest
    2011/2013 work on the landscaping. Therefore, we need not determine whether the
    work in 2011/2013 was a repair or an improvement. In either case, SDCL 15-2A-3
    does not bar Brude’s claim. The circuit court erred by granting summary judgment
    to Yellow Jacket on the basis of SDCL 15-2A-3.
    [¶14.]       Our decision is consistent with the Illinois case regarding a retaining
    wall that the parties have discussed. See Schott v. Halloran Constr. Co., 
    982 N.E.2d 965
    (Ill. App. Ct. 2013). In Schott, plaintiff brought a suit in 2010 after she
    fell off an unguarded retaining wall in 2001. The plaintiff alleged that defendant
    negligently failed to build a barrier to prevent people from falling off the wall. The
    retaining wall was built in 1990 and portions were rebuilt in 1994 after a heavy
    rain caused portions to fall over. Plaintiff fell from a portion of the wall that was
    not repaired in 1994. The Illinois Appellate Court determined that the retaining
    wall was an improvement to real property at the time when it was built in 1990. 
    Id. -9- #28064
    at 969-70. It also concluded that the work done in 1994 was a mere repair of an
    existing structure and did not constitute the “‘construction of an improvement to
    real property’ within the meaning of the statute of repose.” 
    Id. at 970.
    Therefore,
    plaintiff’s claim was barred by the statute of repose. The court also noted that the
    second reason it rejected plaintiff’s claims was because “the portion of the retaining
    wall from which [plaintiff] stepped or fell was not damaged by rain and was not
    repaired or rebuilt in 1994. The portion of the wall from which [plaintiff] stepped or
    fell was the original retaining wall built . . . in 1990, more than 10 years prior to the
    accident.” 
    Id. Thus, the
    court saw “no reason why an improvement to some portion
    of the property other than that on which the plaintiffs were injured should extend
    or renew the statute of repose with respect to their injuries.” Such a determination
    indicates that a claim with respect to repairs is distinguished from those that arise
    from the construction of an improvement to real property.
    Conclusion
    [¶15.]          The circuit court erred when it granted summary judgment in favor of
    Yellow Jacket on the basis of SDCL 15-2A-3. Regardless of whether the work in
    2011/2013 constituted a repair or an improvement to real property, SDCL 15-2A-3
    does not bar the claim at issue. We reverse and remand.
    [¶16.]          GILBERTSON, Chief Justice, and ZINTER and KERN, Justices, and
    RANK, Circuit Court Judge, concur.
    [¶17.]          RANK, Circuit Court Judge, sitting for WILBUR, Retired Justice,
    disqualified.
    -10-