Frederick Jones v. Reda Homebuilders, Inc. ( 2021 )


Menu:
  •                                                                                         06/10/2021
    IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    May 5, 2021 Session
    FREDERICK JONES ET AL. v. REDA HOMEBUILDERS, INC.
    Appeal from the Chancery Court for Montgomery County
    No. MCCHCVCD16-8 Laurence M. McMillan, Jr., Chancellor
    ___________________________________
    No. M2020-00597-COA-R3-CV
    ___________________________________
    Appellants purchased a home from Appellee home builder and later discovered numerous
    defects in the construction of the home. Appellants sued Appellee for breach of contract,
    breach of warranty, and negligence, and the trial court entered judgment in favor of
    Appellants. Appellants appeal the trial court’s denial of their motion for attorney’s fees
    under the provisions of the parties’ contract. Appellee appeals the trial court’s award of
    damages as speculative. We affirm the trial court’s award of damages in favor of
    Appellants and reverse the trial court’s denial of Appellants’ motion for attorney’s fees.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court
    Affirmed in Part, Reversed in Part, and Remanded
    KENNY ARMSTRONG, J., delivered the opinion of the court, in which FRANK G. CLEMENT,
    JR., P.J., M.S., and W. NEAL MCBRAYER, J., joined.
    Jean Dyer Harrison, Nashville, Tennessee, for the appellants, Frederick Jones, and
    Kimberly Jones.
    Sheri S. Philips, Clarksville, Tennessee, for the appellee, Reda Home Builders, Inc.
    OPINION
    I. Background
    On or about April 21, 2014, Appellants Frederick and Kimberly Jones and Appellee
    Reda Homebuilders, Inc. (“Reda”) entered into a “New Construction Purchase and Sale
    Agreement” (the “Contract”) for the purchase of a home at 1621 Wonderboy Court (the
    “Home”). At closing, Reda provided Appellants with a one-year builder’s warranty, i.e.,
    the “Warranty of Completion of Construction,” and all of Appellants’ claims occurred
    within this one-year period. The Home is a two-story structure constructed over a
    basement, which is covered with brick veneer and some stone veneer. At the time the
    Contract was entered, the Home was under construction, and Appellants took numerous
    photographs of the construction progress before moving into the home in July 2014. Some
    of these photographs were entered into evidence.
    Within 60 days of moving into the Home, Appellants noticed water intruding into
    the basement of the Home. Although Reda performed repairs, the water problems were
    not abated and recurred in April 2015. In a second attempt to address the problem, Reda
    removed the concrete garage floor, exposed the foundation, and discovered that the
    foundation under the garage, which forms a portion of the basement walls, had not been
    waterproofed. Reda also dug up the exterior foundation downhill from the garage and
    applied damp-proofing material. The water issues recurred in May 2015, and Appellants
    hired a structural engineer to assess the problem. The parties ultimately agreed that there
    were numerous defects in the construction of the Home.
    On March 31, 2016, Appellants filed suit against Reda for breach of contract, breach
    of warranty, and negligence, alleging that Reda constructed the Home in an unworkmanlike
    manner. On May 13, 2016, Reda filed an answer. On June 12, 2017, Reda made an offer
    of judgment to purchase the Home back from Appellants for the initial purchase price of
    $399,000.00. Appellants declined the offer. After a failed attempt at mediation in April
    2019, the case proceeded to trial on September 17, 2019.
    On December 19, 2019, the trial court entered its memorandum and order, wherein it
    granted Appellants judgment in the amount of $125,343.00 on their breach of contract and
    negligence claims. On January 15, 2020, Appellants filed a motion for attorney’s fees of
    $50,380.00 and discretionary costs of $4,602.25 under paragraph 25 of the Contract, which
    addresses defaults. By order of March 17, 2020, the trial court awarded Appellants’
    $4,602.25 in discretionary costs and denied their motion for attorney’s fees.
    II. Issues
    Appellants raise two issues for review:
    1. Whether the Chancery Court erred in not awarding [Appellants’]
    attorneys’ fees.
    2. Whether the Appellants are entitled to an award of attorneys’ fees incurred
    on appeal.
    In the posture of Appellee, Reda raises the additional issue of: Whether the trial
    court erred in awarding a judgment to Appellants given that their damages were
    speculative.
    -2-
    III. Standard of Review
    When reviewing a trial court’s findings following a bench trial, this Court reviews
    the record de novo and presumes that the trial court’s findings of fact are correct unless the
    preponderance of the evidence is otherwise.” M & M Elec. Contractor, Inc. v.
    Cumberland Elec. Membership Corp., 
    529 S.W.3d 413
    , 422 (Tenn. Ct. App. 2016) (citing
    Nashville Ford Tractor, Inc. v. Great Am. Ins. Co., 
    194 S.W.3d 415
    , 424 (Tenn. Ct. App.
    2005)). However, we review a trial court’s legal conclusions without a presumption of
    correctness. 
    Id.
    IV. Damages
    We begin with Appellee’s issue concerning whether the trial court erred in awarding
    Appellants damages. The crux of Reda’s argument is that the amount of damages was
    speculative and, thus, not recoverable. The party seeking damages assumes the burden of
    proof as to those damages. Waggoner Motors, Inc. v. Waverly Church of Christ, 
    159 S.W.3d 42
    , 57 (Tenn. Ct. App. 2004); Inman v. Union Planters Nat’l Bank, 
    634 S.W.2d 270
    , 272 (Tenn. Ct. App. 1982). Damages cannot be based on mere conjecture or
    speculation. Overstreet v. Shoney’s, Inc., 
    4 S.W.3d 694
    , 703 (Tenn. Ct. App. 1999).
    Uncertain, contingent, or speculative damages are unrecoverable. Western Sizzlin, Inc. v.
    Harris, 
    741 S.W.2d 334
    , 336 (Tenn. Ct. App. 1987) (quoting Maple Manor Hotel, Inc. v.
    Metro. Gov’t of Nashville & Davidson Cnty, 
    543 S.W.2d 593
    , 599 (Tenn. Ct. App. 1975)).
    An award for damages requires proof of damages within a reasonable degree of certainty.
    Western Sizzlin, 
    741 S.W.2d at 336
     (citation omitted). “This ‘reasonable certainty’
    standard applies to evidence regarding the existence of damages,” not the “amount of
    damages.” Tennison Brothers v. Thomas, No. W2016-00795-COA-R3-CV, 
    2017 WL 6403888
    , at *17-18 (Tenn. Ct. App. Dec. 15, 2017) (citing Waggoner, 
    159 S.W.3d at 58
    ).
    Turning to the trial court’s December 19, 2019 order, although the trial court
    concedes that, “The damage calculation is the difficulty in this case,” it acknowledges that,
    “The parties are in agreement that the home is defective in many respects.” This finding
    is undisputed. As such, Appellees concede that Appellants suffered damages in this case
    because the Home was defective. Only the amount of damages is disputed; as the trial
    court stated, “[T]here is disagreement between the parties on the extent of the defects and
    the costs required to remedy the problems. [Appellants] claim that they are entitled to
    judgment in the amount of $253,810.00. [Appellee] is of the opinion that the court should
    award a judgment against it in the amount of $41,000.00.” “Speculative damages . . . are
    only prohibited when the existence of damages is uncertain, not when the amount of
    damage is uncertain.” Jennings v. Hayes, 
    787 S.W.2d 1
    , 3 (Tenn. Ct. App. 1990) (citing
    Cummins v. Brodie, 
    667 S.W.2d 759
    , 765 (Tenn. Ct. App. 1983)). Here, the existence of
    damages is not uncertain. In its order, the trial court enumerated the numerous building
    defects, on which the parties agreed:
    -3-
    13. The parties agree that the [H]ome was not properly framed and that an
    LVL beam needs to be installed in the kitchen as well as other additional
    framing below the kitchen floor for the floors to be leveled, and the loads in
    the home to be properly distributed. There was further agreement that the
    kitchen cabinets, countertops and appliances will need to be removed and
    reinstalled to accomplish these repairs.
    14. The parties agree that the brick on the rear of the house is resting on and
    being supported by the wooden deck and that this condition must be repaired.
    15. The parties are in agreement that the [H]ome’s foundation is not properly
    supporting the [H]ome and that cracks in the brick veneer are occurring. This
    condition is getting worse over time. [Appellee’s] expert testified that steel
    piers would need to be installed under the right rear of the [H]ome to remedy
    this situation. [Appellants’] contractor testified that steel piers may also be
    necessary under the chimney on the rear of the home.
    16. The parties are in agreement that the foundation under the right rear side
    of the [H]ome needs to be re-excavated and proper waterproofing applied.
    There is further agreement that the grade on the right side and rear of the
    house needs to be lowered to ensure that the finished grade is below the floors
    in the basement. [Appellee’s] expert testified that the side grade could be
    lowered, or a gravity wall installed/built to “push” water away from the
    foundation.
    17. Another area of agreement between the experts is the necessity for a
    functional, physical footer drain and that the existing gravel only drain is
    unsatisfactory.
    18. The experts also agree that the cracks in the brick veneer need to be
    repaired. [Appellants’] expert calls for the removal and replacement of the
    brick. [Appellee’s] expert calls for the cracks to be repaired in connection
    with stabilizing the foundation and the installation of a brick lintel where the
    back deck is supporting the brick. The court is of the opinion that removing
    the brick on the rear of the [H]ome is unnecessary, and that the cracks can be
    repaired as suggested by [Appellee’s] expert.
    The trial court went on to note areas of disagreement between the parties:
    19. There are several areas of disagreement between the parties. One of
    these areas involves the foundation under the bay window. As numerous
    photographs show, the bay window was built in an area that had no
    foundation for it. The actual foundation was six to ten feet to the left of the
    window. [Appellants] want to be compensated for this. However, as other
    photographs show, [Appellee] poured a monolithic concrete slab in the entire
    bay window thereby curing the problem. As [Appellee’s] expert explained,
    it was an “unconventional fix, but it works.” The court is of the opinion that
    -4-
    the [Appellants] have failed to carry their burden of proof that this defect
    needs further repair.
    20. Another area of disagreement is the waterproofing of the basement under
    the front porch. [Appellants] claim there is none, as was the case under the
    garage that was excavated. [Appellee] claims that it was waterproofed, but
    offered no testimony or other proof to show that it was done. The court is of
    the opinion that the testimony of [Appellants] together with other
    circumstantial evidence in this case supports the conclusion that the
    basement foundation wall under the porch must be waterproofed. This repair
    will require shoring up the porch roof, removal of the front porch and
    landscaping to accomplish this repair.
    Neither party disputes the foregoing findings concerning the defects that the parties agreed
    on and those they did not. Nonetheless, we have reviewed the testimony of the parties’
    respective experts, and we conclude that the evidence does not preponderate against the
    trial court’s findings concerning the building defects. As such, Appellants are entitled to
    damages for the foregoing defects. In other words, the existence of damages in this case
    is certain, and Appellants were entitled to damages in this case.
    As to the amount of damages, “[w]hen there is substantial evidence in the record
    and reasonable inferences may be drawn from the evidence[,] mathematical certainty [as
    to the amount of damages] is not required.” Cummins, 
    667 S.W.2d at 765
    . In breach of
    contract cases, such as this, the purpose of assessing damages is to place the plaintiff in the
    same position as he or she would have been in had the contract been properly performed.
    Wilhite v. Brownsville Concrete Co., 
    798 S.W.2d 772
     (Tenn. Ct. App. 1990). Damages
    for breach of contract may be awarded even where it is impossible to prove the exact
    amount of damages. Moore Constr. Co., Inc. v. Clarksville Dept. of Electricity, 
    707 S.W. 2d 1
     (Tenn. Ct. App. 1985). All that is required is proof with a reasonable degree of
    certainty. Id. at 15. Uncertain or speculative damages are prohibited only when the
    existence of damages is uncertain, not when the amount of damages is uncertain. See
    Redbud Coop. v. Clayton, 
    700 S.W.2d 551
     (Tenn. Ct. App. 1985). In its December 19,
    2019 order, the trial court arrived at its award of damages as follows:
    22. Regarding the framing defects identified in paragraph 13, supra,
    [Appellants’] expert claims that these repairs will cost $18,000.00. It is
    unclear whether 30% OH&P [i.e., overhead and profit,] is included in this
    figure. [Appellee’s] expert testified that these repairs should cost
    $22,000.00. . . . [Appellee’s] expert was not questioned on whether OH&P
    was included in this figure. The court is of the opinion that 15% OH&P
    should be added to [Appellee’s] expert’s opinion for a total of $23,300.00 to
    make the framing repairs.
    -5-
    Turning to the record, as noted by the trial court, Appellee’s expert testified, in relevant
    part, that
    [a]n LVL beam needed to be installed in the kitchen area of the home.
    Placing the LVL beam, inclusive of demolition of the kitchen would cost
    $4,000.00, plus $1,000.00 to repair the sag in the floor resulting from the
    LVL beam . . . . Further, he recommended a load bearing beam underneath
    the kitchen which would cost $2,000.00 to $3,000.00 . . . . Additionally,
    repairing the holes would cost $3,000.00 each for a total of $6,000.00 . . . .
    Further, to repair all four holes would cost between $5,000.00 and $8,000.00
    ....
    From our review of the record, the evidence does not preponderate against the trial court’s
    findings regarding the range of costs for the necessary repairs due to framing defects. As
    such, we affirm the award of $23,300.00 for such repairs.
    Concerning the other agreed upon building defects, the trial court awarded damages
    for those defects as follows:
    23. Regarding the brick/deck defect identified in paragraph 14, supra, and
    as previously noted by this court in paragraph 18, supra, [Appellants’] expert
    calls for the removal of all brick on the rear of the [H]ome, while [Appellee’s]
    expert calls for the installation of a lintel and tuck-pointing the cracks. The
    court is of the opinion that the brick on the rear of the [H]ome does not need
    to be removed, and that this defect can be repaired in the method suggested
    by [Appellee’s] expert. The cost of the repair, according to [Appellee’s]
    expert, is $5,000.00. Adding 15% OH&P to this figure will allow $5,750.00
    to remedy this defect.
    24. Regarding the foundation defect(s) identified in paragraph 15, supra, the
    experts agree that steel piers need to be installed under the right rear of the
    house to remedy this defect. [Appellee’s] expert testified that this repair
    should cost $9,000.00. Adding 15% OH&P to this figure will allow
    $10,350.00 to repair this defect. (Masonry repair is added into the damage
    calculation in paragraph 27, infra).
    25. Regarding the waterproofing defect(s) identified in paragraph 16, supra,
    [Appellee’s] expert testified that this repair should cost $5,000.00. Adding
    OH&P to this figure will allow $5,750.00 to repair this defect.
    In reaching the amount of damages for brick/deck defects, foundation defects, and
    waterproofing defects, the trial court relied solely on the evidence of Reda’s own expert.
    Furthermore, in contesting the award of damages, Reda does not specifically address the
    trial court’s addition of OH&P expenses to the repair amounts stated by their expert. As
    -6-
    such, we conclude that the evidence does not preponderate against the trial court’s award
    of $21,850.00 for the foregoing repairs.
    Finally, the trial court addressed incidental and ancillary repair costs:
    26. Regarding the lack of footer drain defect identified in paragraph 17,
    supra, [Appellants’] contractor includes in his estimate $18,450.00 for
    excavation and waterproofing; $10,920.00 for landscaping; $1,400.00 for
    foundation drain; and, $2,050.00 for gravel. Several of these costs are
    associated with repair of other defects, but must be incurred to install a proper
    physical footer drain. Because the court allowed $5,000.00 in paragraph 25
    above to excavate and waterproof the right rear of the [H]ome, the court is
    of the opinion that this amount for excavation included in [Appellant’s]
    request should be reduced by this amount ($18,450.00 - $5,000.00 =
    $13,450). Therefore, adding 15% OH&P for excavation and waterproofing;
    landscaping; foundation drain; and, gravel, the sum of $31,993.00 will be
    allowed to repair this defect(s), and other, infra.
    27. Regarding the waterproofing defect identified in paragraph 20, supra,
    and the court’s opinion that this defect needs repairs, the court is of the
    opinion that the costs of repair included in paragraph 26, supra, includes
    costs necessary to make this repair. However, there appears to be no proof
    in the record on the cost necessary to replace the front porch following the
    installation of the footer drain and waterproofing. There is a subcontractor
    bid, See Trial Exhibit 59, which includes some costs associated with the
    demolition of the front porch, but not replacement. [Appellants’] contractor
    did have the sum of $36,800.00 for masonry, but this court has held that the
    bricks on the rear of the house do not need to be removed and replaced, but
    the cracks in the brick need repair.
    As noted above, this court is not precluded from awarding a sum to
    compensate a homeowner for a defect that is certain . . . . Therefore, the
    court will award an additional $15,000.00, inclusive of OH&P, for the
    removal and replacement of the front porch as well as for masonry repair to
    remedy the cracks in the brick caused by settlement of the foundation.
    28. [Appellants] have requested other items of damages, some of which
    should be awarded, and some of which should not. The court finds that
    [Appellants] have failed to carry their burden of proof on the following items
    of damages: fish tank removal; moving; monthly storage and unpacking;
    HVAC; polyurethane injection; downspouts; and, framing not awarded
    elsewhere in this opinion.
    29. The court is of the opinion that there will be some electrical work and
    interior finish work required to repair the home properly. Trial Exhibit 59 is
    a subcontractor bid for $52,027.87 for various work, some of which has been
    awarded elsewhere in this opinion, to include front porch repairs; framing
    -7-
    repairs; and kitchen repairs. Some of the items included in Exhibit 59 are for
    items the court declines to award, to include deck repair and removal and
    replacement of tile in the basement. However, many of the costs contained
    in Exhibit 59 will be necessary to compensate [Appellants], to include
    removal and replacement of drywall in basement; drywall repair; baseboard
    and ¼ round in basement; painting; floor repair and reset carpet. The court
    is of the opinion that 60% of the amount requested in Exhibit 59, inclusive
    of OH&P, ($31,200.00) is an amount that will compensate [Appellants] for
    the additional items identified in this paragraph.
    Based on the foregoing, the trial court awarded a total judgment in the amount of
    $125,343.00. From our review of the record, including the testimony of the experts and
    the trial exhibits, we conclude that the trial court’s reasoning is sound and its award of
    damages in the amount of $125,343.00 is within the range of reasonableness given the
    extent of the building defects, the known costs of necessary repairs, and the likely
    incidental and ancillary costs that will arise as those repairs are made. As discussed above,
    damages are certain in this case as Appellee concedes numerous defects in its construction
    of the Home. Although the amount of damages is not certain, there is sufficient evidence
    to support the trial court’s reasoning and ultimate entry of judgment in the amount of
    $125,343.00. As such, we affirm the trial court’s award of damages in the amount of
    $125,343.00.
    V. Attorney’s Fees
    The parties’ contract provides, in relevant part:
    25. Default. Should Buyer default hereunder, the Earnest Money shall be
    forfeited as damages to Seller and shall be applied as a credit against Seller’s
    damages. Seller may elect to sue, in contract or tort, for additional damages
    or specific performance of the Agreement, or both. Should Seller default,
    Buyer’s Earnest Money shall be refunded to Buyer. In addition, Buyer may
    elect to sue, in contract or tort, for damages or specific performance of this
    Agreement, or both. In the event that any party hereto shall file suit for
    breach or enforcement of this Agreement (Including suits filed after Closing
    which are based on or related to the Agreement), the prevailing party shall
    be entitled to recover all costs of such enforcement, including reasonable
    attorney’s fees.
    “A cardinal rule of contractual interpretation is to ascertain and give effect to the
    intent of the parties.” Crye-Leike, Inc. v. Carver, 
    415 S.W.3d 808
    , 816 (Tenn. Ct. App.
    2011) (quoting Allmand v. Pavletic, 
    292 S.W.3d 618
    , 630 (Tenn. 2009)). “When the
    language of the contract is plain and unambiguous, courts determine the intentions of the
    parties from the four corners of the contract, interpreting and enforcing it as written.” 
    Id.
    -8-
    (quoting Union Realty Co., Ltd. v. Family Dollar Stores of Tenn., Inc., 
    255 S.W.3d 586
    ,
    591 (Tenn. Ct. App. 2007)). “In such a case, the contract is interpreted according to its
    plain terms as written, and the language used is taken in its ‘plain, ordinary, and popular
    sense.’” 
    Id.
     (quoting Maggart v. Almany Realtors, Inc., 
    259 S.W.3d 700
    , 704 (Tenn.
    2008)). Here, the parties’ use of the term “shall,” i.e., “the prevailing party shall be entitled
    to recover all costs of such enforcement, including reasonable attorney’s fees,” indicates
    that the award of attorney’s fees to the prevailing party is mandatory. See Myers v.
    AMISUB (SFH), Inc., 
    382 S.W.3d 300
    , 308 (Tenn. 2012) (“‘When “shall” is used . . . it
    is ordinarily construed as being mandatory and not discretionary.’”) (quoting Bellamy v.
    Cracker Barrel Old Country Store, Inc., 
    302 S.W.3d 278
    , 281 (Tenn. 2009)).
    Accordingly, Appellants are entitled to an award of attorney’s fees if they are the prevailing
    party.
    Tennessee courts have defined a “prevailing party” as one who “succeeds on a
    ‘significant claim’ which affords the [party] a substantial measure of the relief sought.”
    Daron v. Dep’t of Corr., 
    44 S.W.3d 478
    , 481 (Tenn. 2001). Additionally, a “prevailing
    party” has been defined as a party “who has succeeded ‘on any significant issue in litigation
    which achieves some of the benefit the part[y] sought in bringing suit.” Fannon v. City of
    LaFollette, 
    329 S.W.3d 418
    , 431 (Tenn. 2010) (internal citations omitted). Although
    Appellants did not receive the full amount of damages they initially sought, i.e.,
    $253,810.00, they received a significant award of $125,343.00. Furthermore, as discussed
    above, Appellee conceded that there were numerous building defects in the Home. This
    fact clearly evinces that Reda, by its own admission, breached the contract and the
    warranty. Nonetheless, the trial court denied Appellants’ “motion for attorney’s fees on
    the grounds that the court’s judgment was for both breach of contract and negligence and
    attorney’s fees are not supported by the facts as found, and the causes of action alleged.”
    We disagree. Under the plain language of the parties’ contract, as the prevailing party in
    the lawsuit, Appellants are entitled to their reasonable attorney’s fees and costs. As such,
    we reverse the trial court’s denial of attorney’s fees and remand for determination of
    Appellant’s reasonable attorney’s fees and costs, including those fees and costs accrued in
    this appeal, and for entry of judgment on same. Eberbach v. Eberbach, 
    535 S.W.3d 467
    ,
    474 (Tenn. 2017) (holding that “former wife was prevailing party at trial and appellate
    levels, and thus was entitled to attorney’s fees award under mandatory fee provision in
    parties’ marital dissolution agreement.”).
    VI. Conclusion
    For the foregoing reasons, we affirm the trial court’s orders awarding Appellants
    damages in the amount of $125,343.00 and discretionary costs in the amount of $4,602.25.
    We reverse the trial court’s order denying Appellant’s motion for attorney’s fees. The case
    is remanded for determination of Appellants’ reasonable attorney’s fees, costs, and
    expenses incurred in the litigation, including on appeal, for entry of judgment on same, and
    for such other proceedings as may be necessary and are consistent with this opinion. Costs
    -9-
    of the appeal are assessed to Appellee, Reda Home Builders, Inc., for all of which execution
    may issue if necessary.
    s/ Kenny Armstrong
    KENNY ARMSTRONG, JUDGE
    - 10 -