the-metropolitan-gov-of-nashville-and-davidison-county-tennessee-and-the ( 1995 )


Menu:
  • THE METROPOLITAN GOVERNMENT OF   )
    NASHVILLE and DAVIDSON COUNTY,   )
    TENNESSEE, and                   )
    THE METROPOLITAN NASHVILLE       )
    AIRPORT AUTHORITY,               )
    )
    Petitioners/Appellants,     )   Appeal No.
    )   01-A-01-9503-CV-00089
    v.                               )
    )   Davidson Circuit
    OVERNITE TRANSPORTATION          )   No. 87C-181
    COMPANY, a Virginia              )
    Corporation of Nashville and
    Davidson County, Tennessee,
    )
    )
    )
    FILED
    Respondent/Appellee.        )                       Oct. 19, 1995
    Cecil Crowson, Jr.
    Appellate Court Clerk
    COURT OF APPEALS OF TENNESSEE
    MIDDLE SECTION AT NASHVILLE
    APPEAL FROM THE CIRCUIT COURT FOR DAVIDSON COUNTY
    AT NASHVILLE, TENNESSEE
    THE HONORABLE HAMILTON GAYDEN, JUDGE
    CHARLES W. BURSON
    Attorney General and Reporter
    MICHAEL E. MOORE
    Solicitor General
    MICHAEL W. CATALANO
    Associate Solicitor General
    Office of the Attorney General and Reporter
    Executive Offices
    500 Charlotte Avenue
    Nashville, Tennessee 37243-0497
    ATTORNEYS FOR PETITIONERS/APPELLANTS
    HARWELL HOWARD HYNE
    Gabbert & Manner, P.C.
    Jonathan Harwell
    C. Mark Pickrell
    1800 First American Center
    Nashville, Tennessee 37238
    ATTORNEYS FOR RESPONDENT/APPELLEE
    VACATED AND REMANDED
    SAMUEL L. LEWIS, JUDGE
    O   P I N I O N
    This is an appeal by the petitioners/appellants, Tennessee
    State    Department   of   Transportation    ("TDOT")   and   Metropolitan
    Nashville Airport Authority ("MNAA"), from a jury verdict and
    judgment valuing four acres of condemned property owned by the
    respondent/appellee, Overnite Transportation Company ("Overnite"),
    at $1,759,578.10.
    ISSUES
    The petitioners/appellants raise two issues on appeal:
    1) Whether the evidence preponderates against
    the trial court's finding that the petitioner's
    property, which was condemned as part of the
    discrete access road connecting Interstate 40 to
    the   new   airport   terminal  complex   of   the
    Metropolitan Nashville Airport, was not within the
    scope of the project?
    2) If so, whether the petitioner is entitled to
    a new trial on the grounds that evidence was
    introduced to the jury by the [respondent], which
    included the enhanced value of the property taken
    for the discrete access road, based upon the
    relocation of the new terminal complex?
    In April 1979, MNAA began the Metropolitan Airport Master
    Plan Update, a study       of the development of a new terminal complex
    at the Metropolitan Nashville Airport.          The Update included five
    alternatives for the construction of a discrete access road to
    serve the airport from Interstate 40.           Of the alternatives, two
    required the taking of Overnite's property and two did not.            The
    fifth alternative did not specifically mention Overnite's property,
    but MNAA's Director of Planning and Programming testified that it
    did not require the taking of Overnite's property.             The Update
    recommended the fifth alternative.         MNAA's Board of Commissioners
    approved the study and incorporated it into the Board's resolution
    verbatim.    In December 1980, the Board announced to the public its
    plans to construct the new terminal.
    -2-
    In August 1981, the original grading plans for the new
    terminal project showed that MNAA might need a small portion of
    Overnite's property to build the discreet access road.                  In 1982,
    the Metropolitan Planning Commission approved MNAA's plans for the
    construction of the new terminal, including the construction of the
    discreet access road.      The project required that MNAA obtain a
    zoning variance.     The Metropolitan Board of Zoning Appeals sent
    hearing notices to all neighboring and affected property owners,
    including Overnite, and approved the variance in June 1982.                    Also
    in 1982, the Department of Public Works issued a letter approving
    the grading, drainage, and erosion control plans for the entire
    project.     Those plans showed the discrete access road crossing
    through Overnite's property. The trial record, however, is unclear
    as to whether the grading plans showing the taking of Overnite’s
    property became part of the public record through the zoning appeal
    or through the letter issued by the Department of Public Works.
    Despite the grading plans, evidence presented at trial
    indicated that in 1982 and for some years thereafter MNAA had not
    decided the exact location of the discrete access road.                 In 1983,
    TDOT agreed to purchase the right-of-way for the discrete access
    road in exchange for a conveyance of airport property.                 MNAA asked
    TDOT to acquire property for the discrete access road because MNAA
    did not have the power to exercise eminent domain. Though ultimate
    design   questions   had   not   been    answered,        by   1986,    TDOT    was
    appraising   Overnite's    property     so   it   could    make   an    offer    to
    purchase     land for the discrete access road.                TDOT based its
    appraisals of Overnite's property on the property's proximity to
    the airport and reported that in the rapidly expanding airport
    commercial area the highest and best use of the property was
    intense hotel/motel commercial development.                TDOT hired another
    appraiser in 1993 who also considered the location of the new
    terminal in valuing Overnite's property.
    -3-
    In January 1987, TDOT filed a petition for condemnation of
    4.257 acres of Overnite's land and tendered $741,980.00 to the
    Davidson County Circuit Court Clerk.            This amount represented
    TDOT's estimation of Overnite's damages.            The Davidson County
    Circuit Court entered an order of possession in February 1987.
    Overnite filed an answer denying that $741,980.00 represented the
    fair market value of the property TDOT sought to condemn.                In
    answer to interrogatories from Overnite concerning the valuation of
    the property, TDOT provided Overnite with the appraisals conducted
    in 1986 which valued the property based on its proximity to the new
    terminal. TDOT never updated its answers to these interrogatories.
    The case was originally set for trial on 6 December 1993,
    but the court continued the case and eventually set it for 20 June
    1994.    On 6 May 1994, TDOT filed a motion requesting that the
    court not allow Overnite to introduce evidence of the value of its
    property based on its proximity to the new terminal.              On 26 May
    1994, TDOT filed a notice that its appraisers could present a
    valuation of the property excluding the effect of the new terminal
    before trial.     TDOT also said that it would submit the valuation
    and its basis to Overnite; however, Overnite never received such a
    submission.
    On 4 June 1994, the trial judge denied TDOT's motion. The
    judge found that TDOT's request to change its legal theory of just
    compensation came "too late" and that TDOT failed to show that the
    taking of Overnite's property was probably necessary in 1980.
    Consequently, the judge held that Overnite could offer evidence of
    the value of its property based on its proximity to the new
    terminal,   and   at   trial,   he   issued   instructions   to   the   jury
    reflecting that holding.
    Regarding the valuation of the property, the jury returned
    -4-
    a verdict of $1,759,578.10.         The trial judge entered a judgment to
    that effect which also provided for the payment of interest on
    $1,017,778.10, the difference between the jury award and the amount
    deposited with the court clerk.          The trial court denied a motion
    filed by TDOT requesting a judgment not withstanding the verdict
    and a new trial.         On 28 November 1994, TDOT filed a notice of
    appeal.
    We will address appellants' issues together by discussing
    the proper formulation of the scope of the project rule and its
    application to the case at bar.
    (I)
    Under the most recent formulation of the scope
    of the project rule, the state need not compensate
    condemnees for any enhancement in the value of
    their property caused by the project which makes
    condemnation necessary if, at the time the state
    committed to the project, it was reasonably
    foreseeable that the government might take the
    condemnees' property.
    The   United     States    Constitution    and    the    Tennessee
    Constitution mandate that landowners be paid "just compensation"
    when their property is taken for public use.         U.S. Const. amend. V;
    Tenn. Const. art. I, § 21.          Traditionally, just compensation was
    the market value of the property to be taken.              United States v.
    Reynolds, 
    397 U.S. 14
    , 16-17, 
    90 S. Ct. 803
    , 805, 
    25 L. Ed. 2d 12
    ,
    16 (1970).      When the market value of the property rises solely
    because of governmental demand for the property, however, it is not
    just to require the public to pay the above normal market value.1
    1.
    United States v. Reynolds, 
    397 U.S. 14
    , 16-17, 
    90 S. Ct. 803
    , 805, 25 L.
    Ed. 2d 12, 16 (1970).   Three considerations support this proposition.  United
    States v. 320.0 Acres of Land, 
    605 F.2d 762
    , 782 (5th Cir. 1979).    First, by
    entering the market as a purchaser with a unique and pressing demand, the
    Government has distorted the market. Thus, the selling price is not the actual
    fair market value. Second, forcing "the Government to pay ... a premium over
    that which the property would bring on the open market absent the Government's
    demand would increase the cost of public projects and perhaps frustrate some
    public objectives."   
    Id. Third, permitting "recovery
    of value that is not
    created by fair, open market conditions would be to award a few private
    -5-
    Consequently, courts created the scope of the project rule.             Lands
    situated near public improvement projects tend to increase in
    value.   United States v. Miller, 
    317 U.S. 369
    , 376, 
    63 S. Ct. 276
    ,
    281, 
    87 L. Ed. 336
    , 344 (1943).          Courts designed the scope of the
    project rule to allow landowners to benefit from enhancement in the
    market value of their land caused by its being close to a public
    improvement.    Simultaneously, the rule prevents speculation on the
    government's activities at the public's expense by landowners or
    prospective purchasers.      See Layne v. Speight, 
    529 S.W.2d 209
    , 212
    (Tenn. 1975) (quoting 
    Miller, 317 U.S. at 376-77
    ).
    The scope of the project rule, formulated by the United
    States Supreme Court in Miller and later adopted by the Tennessee
    Supreme Court in Layne, is easy to state:               If the property being
    condemned was "probably within the scope of the governmental
    project from the time the Government was committed to it," the
    landowner is not entitled to compensation for any increase in value
    caused by the project.           
    Miller, 317 U.S. at 376-77
    .       The rule,
    however, is not so easy to apply.          United States v. 320.0 Acres of
    Land, 
    605 F.2d 762
    ,   782    (5th   Cir.   1979)    [hereinafter   Monroe
    County].    Consequently, the Court clarified the federal scope of
    the project rule in United States v. Reynolds. Although dicta, the
    Court restated Miller's rule and noted the following:
    As with any test that deals in probabilities, its
    application to any particular set of facts requires
    discriminating judgment. The rule does not require
    a showing that the land ultimately taken was
    actually specified in the original plans for the
    project.   It need only be shown that during the
    course of the planning or original construction it
    became evident that land so situated would probably
    be needed for the public use.
    
    Reynolds, 397 U.S. at 21
    (footnote omitted).
    propertyholders windfall gains solely because of public needs and exigencies."
    
    Id. -6- The Tennessee
      Supreme    Court       has   cited    the   Reynolds'
    clarification of the federal scope of the project rule. 
    Layne, 529 S.W.2d at 212-13
    .     In Layne, the court noted that Reynolds had
    "merely restated the crux of Miller," but the court also seemed to
    cite with approval the additional Reynolds' clarification quoted
    above.   
    Id. In a later
    case, the Court of Appeals of Tennessee,
    Eastern Section, adopted the Reynolds' clarification.                  State v.
    Hodges, 
    552 S.W.2d 400
    , 402 (Tenn. App. 1977).                   In Hodges, the
    State condemned 57 acres of the defendant landowner's property for
    a highway construction project in 1971.            Three years later, after
    the State had completed part of the project, the State discovered
    that it would need an additional 1.75 acres of the defendant
    landowner's property to maintain a stable slope.              
    Id. at 400. The
    trial judge, relying on Miller, held that the additional 1.75 acres
    was outside the scope of the original project.                  
    Id. at 401. In
    light of Reynolds, the court reversed the trial court, but limited
    its holding to the particular facts of the case.                    
    Id. at 402. Since
    Layne and Hodges, only one other case in Tennessee has dealt
    with a scope of the project rule issue.                 State Ex rel. Comm'r,
    Dep't of Transp. v. Veglio, 
    786 S.W.2d 944
    (Tenn. App. 1989)
    (affirming the trial court's finding that interchange upgrade and
    road widening projects were distinct).            Veglio did not explicitly
    adopt,    renounce,   or    mention        the    Reynolds'      clarification.
    Nevertheless,     based    on   Layne       and    Hodges,       the   Reynolds'
    clarification seems to be part of the scope of the project rule as
    adopted in Tennessee.
    Since Reynolds, courts have refined the federal scope of the
    project rule to reflect landowners' and prospective purchasers'
    reasonable expectations as to whether a piece of property will be
    -7-
    taken.2
    In anticipation of a proposed project, real
    property adjacent to or near land to be taken
    frequently increases in value; however, the land
    which is expected to be taken does not legitimately
    share in this enhancement because its inclusion in
    the project will make it unavailable for private
    development. Any enhancement in the value of the
    land necessarily would result from speculation that
    the Government might be compelled to pay an
    artificially inflated price.
    United States v. 2,353.28 Acres of Land, 
    414 F.2d 965
    , 967-68 (5th
    Cir. 1969) [hereinafter Brevard County].
    As a result, land is within the scope of the project when a buyer
    in the real estate market could reasonably expect that the property
    in question might become part of the project and when the increase
    in value of the property is attributable to speculation on the
    government's activities.        See Monroe 
    County, 605 F.2d at 791
    .
    (II)
    To apply the scope of the project rule to the case at bar,
    the court must decide two issues.            The first is when did          MNAA
    commit to the new terminal project.          The second is whether, on that
    date, Overnite or a prospective purchaser could have reasonably
    expected that Overnite's property might become part of the new
    terminal project.        The burden of proving whether the condemned
    property was probably within the scope of the project is on the
    State.     
    Layne, 529 S.W.2d at 213
    .          We review the trial court's
    2.
    See, e.g., United States v. 49.01 Acres of Land,    
    669 F.2d 1364
    , 1367
    (10th Cir. 1982) (holding that the scope of the project rule, as enunciated by
    Miller and Reynolds, requires the Government to pay the enhanced value of the
    land if "the landowner reasonably believed that subsequent government action
    removed the property from the project's scope." United States v. 320.0 Acres of
    Land, 
    605 F.2d 762
    , 793 (5th Cir. 1979) (noting that the "crucial inquiry" is
    whether a landowner or a private purchaser could reasonably anticipate that he
    would be able to devote the property to its highest and best economic use without
    serious fear that the government would soon condemn the land); United States v.
    31.43 Acres of Land, 
    547 F.2d 479
    , 481-82 (9th Cir. 1976) (finding no error in
    the trial court's finding that property lay within the scope of the project where
    no public information existed that could lead a property owner to believe that
    his land would not be a probable object of condemnation); United States v. 172.80
    Acres of Land, 
    350 F.2d 957
    , 959 (3rd Cir. 1965) (holding that a landowner was
    entitled to the enhanced value of his property because a purchaser contemplating
    acquisition and development of the property could have reasonably anticipated
    that, at the time the Government committed to the project, he would be able to
    devote that land to its highest economic use without serious apprehension of
    condemnation); United States v. Eastman, 
    528 F. Supp. 1177
    , 1182 (holding that
    the Fifth Circuit's reasonable-expectations test requires that the enhanced value
    be an element of a landowner's condemnation award).
    -8-
    finding on the scope of the project de novo accompanied by a
    presumption that the finding is correct unless the preponderance of
    the evidence is otherwise.        Tenn. R. App. P.     13(d).
    (A)
    As of 1980, after the State funded and
    announced the project to the public, the prospect
    of the project becoming a reality became
    sufficiently definite such that, at that time,
    MNAA can be said to have committed to the new
    terminal.
    According to the reasonable expectations formulation of the
    scope of the project rule, the commitment date is the date on which
    the   prospect    of   imminent    condemnation      becomes    "sufficiently
    definite"   or,   in   other   words,   when   the   prospect    of   imminent
    condemnation would be a "major factor in the decision of any
    reasonable person to buy or develop the property." Baylin v. State
    Roads Comm’n, 
    475 A.2d 1155
    , 1161 (Md. 1984) (quoting Monroe
    
    County, 605 F.2d at 807
    ).         In Baylin, the State Roads Commission
    developed a plan for the construction of an expressway in 1948.
    The State   budgeted funds for the project as of 1954.           
    Id. at 1156. Nevertheless,
    construction on the expressway did not begin as
    planned because the State transferred the funds to another highway
    project.    In the early 1970s, the State proposed a plan to combine
    the expressway project with a mass transit project.              The addition
    of the mass transit project required the taking of additional acres
    of the appellant landowner’s property.         
    Id. at 1157. In
    1981, the
    State commenced condemnation proceedings against 137 acres of the
    appellant landowner’s property, 118 acres more than originally
    planned.    
    Id. at 1158. On
    appeal, the court cited the trial court’s finding that
    the State committed to the project in 1954 with approval.                 The
    court found that the State announced the project to the public and
    -9-
    funded it in 1954.     As of this time, people were familiar with the
    expressway's planned location and its general path.            Consequently,
    the   court   found   that   as   of    1954   landowners   and   prospective
    purchasers could not expect to devote their property to its highest
    and best use.    
    Id. at 1161. In
    the instant case, the trial court found that MNAA
    committed to the new terminal project in 1980.              Appellants argue
    that MNAA had not committed to the project until 7 June 1982 when
    the Metropolitan Board of Zoning Appeals granted MNAA a conditional
    use permit.     Without such approval, appellants argue, MNAA could
    not have built the new terminal project.           The date of commitment,
    however, is not the date on which the occurrence of the project
    becomes a legal certainty, but is the date on which the probability
    that the project will occur becomes a major factor in a person's
    decision to buy or develop the property.              Id. (quoting Monroe
    
    County, 605 F.2d at 807
    ).
    Here, MNAA announced the new terminal project to the public
    in December 1980.      In some condemnation cases, a just commitment
    date is the date the state announced the project.             Monroe 
    County, 605 F.2d at 806
    ; 
    Baylin, 475 A.2d at 1161
    .                  Once the State
    announces the project, the probability of condemnation will affect
    the decisions of      ordinary investors in the real estate market.
    See United States v. Miller, 
    317 U.S. 369
    , 377 (1943).               Further,
    MNAA approved funding for the new terminal project in December
    1980.   Money approved is usually spent, and thus, the likelihood
    that a prospective project will become a reality is far greater.
    In the face of a public announcement and approved funding, the need
    for a zoning permit does not create sufficient uncertainty to
    compel this court to hold that the trial court erred in finding
    that MNAA committed to the new terminal project in 1980.
    -10-
    (B)
    At the time the MNAA committed to the new
    terminal project, the possibility of condemnation
    of Overnite's property was sufficiently serious
    such that the property can be said to be within
    the scope of the project.
    Knowing the commitment date, the court must decide
    whether, on that date, the owner of the land to be taken could
    reasonably expect to be able to devote his land to its highest
    economic use without serious apprehension that the State would
    soon condemn the property.    See Monroe County, 
    605 F.2d 762
    , 793
    & n.44 (5th Cir. 1979). Several courts consider the following
    three factors to determine if the taking was reasonably
    foreseeable: (1) the foreseeability that the government would
    change the original plans to include the property,    (2) the
    length of time between the commencement of the project and the
    taking in question, and   (3) the Government's representations
    concerning the finality of the original plans.    See, e.g., United
    States v. 62.17 Acres of Land,    
    538 F.2d 670
    , 680 (5th Cir. 1976)
    [hereinafter Jasper City];    
    Baylin, 475 A.2d at 1162-64
    ; State
    Dep't of Transp. v. Montgomery Ward Dev. Corp., 
    719 P.2d 507
    , 513
    (Or. App. 1986).
    (i)
    The foreseeability that MNAA would change the
    1980 Master Plan Update, a continuing planning
    document, to include Overnite’s property weighs in
    favor of a finding that the property was within
    the scope of the new terminal project.
    The application of    the scope of the project rule calls for
    "discriminating judgment."     Jasper 
    City, 538 F.2d at 678
    .       The
    Government need not actually specify the land ultimately taken in
    the original project for the land to come within its scope;         it
    need only be evident that the Government might take the given tract
    -11-
    for the project.       
    Id. In Jasper City,
    the Government did not
    specify    the     landowner’s     property      in   the    original     plans.
    Nevertheless, the Government's representations that it would take
    all of the property within the five year flood line and the
    probability of mistakes in surveying made it reasonably foreseeable
    that the Government would take the landowner’s property.                  
    Id. at 681. The
    court in United States v. Crance, 
    341 F.2d 161
    (8th Cir.
    1965), reached a similar result. In 1958, the Government purchased
    five acres from a landowner for a dam and reservoir project.
    
    Crance, 341 F.2d at 162
    .         From its inception, the project called
    for recreational facilities around the reservoir, but neither a
    1956 preliminary design memorandum nor a 1960 public proposal of
    sites approved by the Chief of Engineers included taking any of the
    remainder of the landowner’s tract.            
    Id. at 162-63. After
    persons
    protested the lack of recreational facilities on the landowner’s
    side of the reservoir, the engineers inspected additional sites
    including the landowner’s tract.               
    Id. at 163. After
    public
    meeting,    the   Government     took    the   remaining    35   acres    of   the
    landowner’s tract for the creation of a public use area.                 
    Id. The district court
    found that the property was not within the scope of
    the project.      Thus, it allowed evidence concerning the enhanced
    value of the property.        
    Id. at 162. On
    appeal, the circuit court reversed the judgment of the
    district court.      
    Id. at 167. The
    circuit court noted that none of
    the plans that excluded the landowner's additional property were
    final plans.      
    Id. at 164. The
    circuit court found the significant
    factor to be that "the project contemplated recreational areas from
    its very inception."         It stated as follows:
    -12-
    [C]ertainly property lying beyond a perimeter of
    the reservoir would probably be incorporated for
    recreational purposes if the land acquired for the
    reservoir alone was not also sufficient for
    recreational utilization. Since the [landowner’s]
    property abutted the reservoir line, it was within
    the sphere of probable acquisition for recreational
    use.
    
    Id. at 165. Another
    court reached a different result on similar facts.
    United States v. 172.80 Acres of Land, 
    350 F.2d 957
    (3d Cir. 1965)
    [hereinafter    Mercer   County].       In     this   case,   the   Government
    purchased 20 acres of a landowner’s 100 acre tract for a dam and
    reservoir    project.     
    Id. at 958. During
      negotiations,     the
    Government representative assured the landowner that the Government
    would not need other parts of his land for the project.             Though the
    original project did not call for the creation of recreational
    areas, a change in the Government's policy concerning public
    developments and the use of reservoir areas prompted a decision to
    acquire the remainder of the landowner’s property for recreational
    use.   
    Id. The circuit court
    affirmed the holding of the district
    court that the enhanced value of the property was includable in the
    condemnation award.      
    Id. at 959. Noting
    that the possibility of
    project expansion to include the property in question might have
    occurred to a perceptive landowner or prospective purchaser, the
    circuit court distinguished Mercer County from Crance based on the
    differences    between   the    Government’s      representations     and   the
    original plans of the projects.
    In the instant case, the discrete access road was part of
    the project from the time MNAA committed to it.           The Airport Master
    Plan Update specifically called for the construction of a discrete
    access road to the new terminal.             Overnite argues that it had no
    notice that appellants required its land for the discrete access
    -13-
    road.   However, MNAA’s resolution adopting the Update incorporated
    it as if MNAA had copied it verbatim.     The Update included two
    discrete access road alternatives which required the taking of
    Overnite’s property.   That MNAA considered Overnite's property for
    use in the construction of the planned discrete access road would
    likely have put Overnite on notice that MNAA might need its
    property for the project.
    Also, because the alternative chosen by      MNAA did not
    require the taking of Overnite’s property, Overnite argues it was
    reasonable for it to expect that MNAA would not take its property.
    As noted in Reynolds, the Government does not have to specify the
    land to be taken in the original plans for the land to be within
    the scope of the project.   United States v. Reynolds, 
    397 U.S. 14
    ,
    21 (1970).   "It need only be shown that during the course of the
    planning or original construction it became evident that the land
    so situated would probably be needed for the public use."   
    Id. "We cannot straightjacket
    the government in defining scope of the
    project, but on the other hand, we cannot permit global meanderings
    to enclave areas not reasonably to have been conceived as included
    at inception."   Jasper City, 
    538 F.2d 670
    , 678 (5th Cir. 1976).
    From its inception, the new terminal project contemplated
    a discrete access road.      Further, the Master Plan Update, a
    "continuing planning document" considered Overnite’s property for
    public use. According to early plans for the new terminal project,
    the discrete access road was a small part of a much larger project,
    and the plans did not schedule it for construction until MNAA had
    almost the entire project completed.      As in Jasper City, the
    possibility that MNAA would need to make some adjustments to allow
    the discrete access road to accommodate the rest of the new
    terminal construction was reasonably forseeable.    Once the court
    -14-
    accepts the possibility of adjustment as reasonably foreseeable,
    the taking of Overnite’s property, property that the State had
    already publicly considered for taking, is reasonably foreseeable
    as well.      Thus, a holding that the 1980 Update was a final
    expression    of      the   project      for      the    purposes      of   defining     the
    project’s       scope       is     unrealistic          and     would       unnecessarily
    "straightjacket" the State in the construction of public projects.
    See Jasper 
    City, 538 F.2d at 678
    . Further, a narrow interpretation
    of the scope of the project rule would encourage the State, when
    acquiring property, to obtain more land than it felt was absolutely
    necessary    to    avoid     the    risk     of     having     to    acquire   additional
    property at an enhanced value.                 State v. Hodges, 
    552 S.W.2d 400
    ,
    402 (Tenn. App. 1977).
    Overnite also argues that because TDOT, and not MNAA, took
    Overnite’s property to build the discrete access road, the discrete
    access   road     and   the      new    terminal        construction        were    separate
    projects.    In John L. Roper Lumber Company v. United States, 
    150 F.2d 329
    (4th Cir. 1945), the court addressed a similar question.
    There, the Government authorized the Secretary of the Navy to
    establish a Marine Corps Training Area.                       
    Roper, 150 F.2d at 330
    .
    The Federal Works agency condemned Roper’s property, which was
    across the      highway      from      the   training        area,    to    house    defense
    personnel.      
    Id. The original plans
    for the Marine Corp Training
    area contemplated a housing project.                       
    Id. at 331. The
    court
    rejected Roper’s contention that because a different government
    agency condemned the property, the property was outside the scope
    of the project:
    We cannot believe that the rule set forth in the
    Miller case should be nullified by the mere chance
    that an agency of the Government different from the
    one for whose use the land is taken, should, by
    reason of the fact that it holds available funds,
    be directed to institute condemnation proceedings.
    -15-
    
    Id. Roper stands for
    the proposition that as long as the
    property in question is part of the project, the fact that the
    condemning authority is a different government agency is not
    relevant.    As a result, the fact that TDOT condemned Overnite’s
    property for MNAA does not render the discrete access road outside
    the scope of the new terminal project.
    (ii)
    Six years, during which the project was
    continuously under construction, is a relatively
    short amount of time between the commencement of
    the terminal project and the taking of Overnite’s
    property such that it weighs in favor of finding
    that Overnite could not reasonably expect to be
    able to devote its property to its highest
    economic use without serious apprehension of
    condemnation.
    Even where a condemnee's land is within the scope of the
    project at the time the state becomes committed to it, there comes
    a point in time when it would no longer be just to apply the scope
    of the project rule in the government's favor.    Monroe 
    County, 605 F.2d at 797
    .    At that time, the government's delay has removed the
    specter of condemnation created by the project's original scope.
    See Jasper 
    City, 538 F.2d at 680
    .   Because of additional factors in
    Monroe County, the court did not define the "just" limits on the
    temporal reach of the scope of the project rule, but it did warn
    the Government that eighteen years might exceed those limits.
    Monroe 
    County, 605 F.2d at 797
    .
    However, other courts have directly addressed the temporal
    reach of the scope of the project rule.        In Jasper City, the
    Government delayed the taking for ten years. Jasper 
    City, 538 F.2d at 680
    .     For the first five years, the Government was not aware
    -16-
    that an additional taking was necessary.         
    Id. at 673. For
    the
    last five years, a lack of funding delayed the taking.              
    Id. The circuit court
    noted that the delay in taking in the first five
    years was acceptable because there was a high probability of the
    need for adjustment given the nature of the project and because the
    need for adjustment would not reveal itself for five years.            
    Id. at 680. Regarding
    the second five years, the circuit court remanded
    the case to the district court to determine if the delay in the
    second five years constituted a representation to the landowner
    that additional adjustments would not be necessary.           
    Id. In addition, the
    court in Baylin addressed the temporal
    reach of the scope of the project rule.              Baylin v. State Roads
    Comm'n, 
    475 A.2d 1155
    (Md. 1981).           As previously discussed, in
    Baylin, the State committed to a highway project in 1954, but did
    not take the appellant landowner’s property until twenty-seven
    years later.     
    Id. at 1163. Plans
    for the project in the late
    1950's showed that the State would require nineteen acres of the
    appellant landowner’s property.         
    Id. at 1156. The
    final plan,
    accepted in 1976, called for significantly more than nineteen acres
    of the appellant landowner’s property.         
    Id. at 1158. At
    trial, the appellant landowner prayed for the enhanced
    value of the land above the original nineteen acres.                
    Id. The trial judge
    found that the property was part of the scope of the
    project, and the appellate court reversed.       
    Id. at 1165. The
    court
    noted that the length of time between the commencement of the
    project and the condemnation was an important factor because of the
    protracted time involved.      
    Id. at 1163. The
    court found that it
    would    be   "incompatible   with    the   principles    underlying      just
    compensation for the Government ... to announce a project and then,
    27 years later, build a substantially enlarged project and say that
    -17-
    this is one    project and one taking."          
    Id. at 1164. The
    case at bar is unlike either Jasper City or Baylin.
    First, in the present case, only six years elapsed from the
    commencement of the project to the taking while in Jasper City and
    Baylin it was eleven and twenty-seven years respectively.              Second,
    here, the delay between the commencement of the project and the
    taking was not the result of an intervening event such as a
    surveying error or a loss of funding.           Instead, it was part of the
    ongoing    process    of   construction.        As   noted   in   Jasper   City,
    "gradualism in acquisition is oft times fact and not fiction."
    Jasper 
    City, 538 F.2d at 680
    .             That the delay was part of the
    normal process of construction makes the eventual taking more
    foreseeable.    Third,     in Jasper City and Baylin, the plans that did
    not require the landowner’s property were in place for several
    years.    Here, MNAA changed the plan for the discrete access road
    requiring no taking of Overnite’s property in 1981, eight months
    after MNAA announced it.
    Overnite argues that until 1986 it had no knowledge that
    MNAA had changed the plans to include Overnite’s property, and
    thus, the changes could not have affected Overnite’s reasonable
    expectations.      The trial record is ambiguous as to whether the
    public    record     included    MNAA’s   new    plans   which    showed    that
    Overnite’s property might be taken.          Unlike Baylin, however, there
    is no evidence in the trial record that after the commencement of
    the project Overnite received representations from MNAA or TDOT
    that they would not take its property.
    In other cases, courts have found delays of much longer than
    six years insufficient to remove the condemned property from the
    scope of the project.           An Oregon appellate court found that a 14
    -18-
    year delay was insufficient to render the property outside the
    scope of the project.         State Dep't Of Transp. v. Montgomery Ward
    Dev. Corp., 
    719 P.2d 507
    , 514 (Ore. App. 1986).                  One reason for the
    courts decision was that "[a]lthough the plans changed frequently
    during the 14 years before the actual taking, most plans called for
    some kind of taking similar to that which occurred."                    
    Id. at 514. Also,
    the court relied on the fact that "[t]here was no evidence of
    government representations which misled defendants or caused them
    any prejudice."      
    Id. Similarly, the Utah
    Supreme Court held that
    an 11 year delay between the first and second condemnation was not
    so lengthy as to "constitute two separate projects."                       Board of
    County    Comm'rs    v.    Ferrebee,    
    844 P.2d 308
    ,      311   (Utah   1992).
    Specifically, the Utah Supreme Court stated that "[w]hile the
    County deserves no praise for speed, we cannot say that its actions
    constitute two separate projects, especially when it consistently
    and openly contemplated acquiring all of Ferrebee’s property." 
    Id. at 311. (iii)
    MNAA's representations as to the finality of
    the 1980 Master Update Plan were not so definite
    as to lead Overnite to believe that it could
    devote its property to its highest use without
    serious apprehension of condemnation.
    Courts    give    crucial    consideration        to   the   government's
    representations      when    determining       scope   of    the   project     cases.
    Monroe 
    County, 605 F.2d at 792
    .           If the government unequivocally
    represents to the landowner or the public that it will not need a
    certain parcel of property for a project, the government, in
    effect, assures the landowner that any enhancement in the value of
    that parcel will be based on its proximity to the government
    project.    
    Id. at 793; see
    also Mercer County, 
    350 F.2d 957
    , 958 (3d
    Cir. 1965).
    -19-
    In Brevard County, 
    414 F.2d 965
    (5th Cir. 1969), the court
    considered the effects of the Government's representations.                              In
    that case, NASA condemned over 72,000 acres of land in August 1961.
    
    Id. at 967. The
       Government      did    not    include     the    appellant
    landowner's property in the original condemnation nor was there any
    evidence at that time that the Government intended to acquire the
    property.     In September 1961, before a Senate committee, a public
    official testified that NASA would not need any additional lands
    for the project.        
    Id. at 969. Subsequently
    in 1962, the need for
    additional     launch       pads     necessitated         the   acquisition         of   an
    additional     14,800       acres    including     654.43       from   the    appellant
    landowner.     
    Id. at 966, 969-70
    & n. 12.                 The court reversed the
    judgment of the trial court which excluded evidence of the enhanced
    value of the appellant landowner's property.                      
    Id. at 972. The
    court found that the public officials testimony in 1961 destroyed
    the persuasiveness of              the Government's argument that its 1961
    plans were not conclusive.            
    Id. at 971. The
    instant case is distinguishable from both Mercer County
    and Brevard County.          In both of those cases, after the Government
    committed to the project, it made definitive representations that
    its plans were final and that the Government would not require the
    landowner's        property.        Here,    no    such    statements        were    made.
    Further, as previously noted, the nature of the document which
    marked the State’s commitment to the new terminal project, the
    importance of the discrete access road in relation to the entire
    project, and the scheduling of the construction of the discrete
    access road after MNAA completed most of the remainder of the
    project indicated that one could not reasonably expect the 1980
    Master Plan Update to be MNAA’s final expression of its plans for
    the discrete access road.
    -20-
    Consequently, the foreseeability that the State would take
    Overnite’s property, the length of time from the date the State
    committed to the new terminal project to the date of the taking,
    and the State’s representations as to the finality of the original
    plans all support a finding that Overnite's property was within the
    scope of the new terminal project.            It therefore results that the
    judgment of the trial court is vacated and the case is remanded to
    the   trial   court   for   a   new   trial    and   any   further   necessary
    proceedings.    Costs on appeal are taxed to appellee.
    ___________________________________
    SAMUEL L. LEWIS, JUDGE
    CONCUR:
    _____________________________
    HENRY F. TODD, P.J., M.S.
    _____________________________
    BEN H. CANTRELL, J.
    -21-