gibbs-brothers-construction-inc-v-brook-hollow-green-llc-national ( 2005 )


Menu:
  •               IN THE COURT OF APPEALS OF TENNESSEE
    AT JACKSON
    August 4, 2004 Session
    GIBBS BROTHERS CONSTRUCTION, INC. v. BROOK HOLLOW
    GREEN, LLC, NATIONAL GRANGE MUTUAL INSURANCE
    COMPANY, CONTINENTAL DEVELOPMENT AND
    CONSTRUCTION, INC., NICHOLAS S. PSILLAS, AND MARSHALL
    COLLIER, INDIVIDUALLY AND D/B/A P&C CONTRACTORS
    An Appeal from the Chancery Court for Williamson County
    No. 27249    R. E. Lee Davies, Chancellor
    No. M2003-01698-COA-R3-CV - Filed April 19, 2005
    This case is about a construction lien. A real estate developer hired a contractor to perform
    paving work on new roads in a subdivision. After the work was completed, the contractor sent
    the developer an invoice for the work done, but the developer did not pay. Eventually, the
    developer paid a portion of the invoice. When no further payments were made, the contractor
    filed a lien on the developer’s roadway. The contractor then sued the developer to enforce the
    lien. After the suit was filed, the developer asserted that the contractor’s workmanship was poor
    and that, as a result, the pavement on the roadway was defective. The trial court found that the
    contractor had a valid lien and awarded a judgment against the developer and the developer’s
    surety. The trial court also awarded the contractor prejudgment interest. The developer appeals,
    asserting that the road was public and not subject to lien, that the trial court made erroneous
    evidentiary rulings, that the trial court erred in finding that a variance from the listed
    measurements was permissible under the contract, that it should have been awarded a setoff
    against the contractor’s judgment, and that the contractor should not have been awarded
    prejudgment interest. We affirm, finding that the contractor’s lien was valid and enforceable,
    that the trial court did not err in its evidentiary rulings, that the developer failed to prove
    damages to setoff, and that the trial court did not abuse his discretion in the award of
    prejudgment interest.
    Rule 3 Appeal; Judgment of the Chancery Court is affirmed
    HOLLY M. KIRBY , J., delivered the opinion of the court, in which W. FRANK CRAWFORD , P.J.,
    W.S. and DAVID R. FARMER , J., joined.
    David M. Smythe, Nashville, for the Plaintiff/Appellee Gibbs Brothers Construction, Inc.
    R. Francene Kavin, Brentwood, for Defendant/Appellants Brook Hollow Green, LLC, National
    Grange Mutual Insurance Company, Continental Development, and Defendant Nicholas Psillas.
    Defendant Marshall Collier, pro se.
    OPINION
    Plaintiff/Appellee Gibbs Brothers Construction, Inc. (“Gibbs”) is a construction company
    located in Nashville, Tennessee. Defendant/Appellant Brook Hollow Green, LLC (“Brook
    Hollow”) is a limited liability company in the business of developing real estate. Brook Hollow
    owned and developed the real property at issue in this case, located in the City of Fairview in
    Williamson County, Tennessee. The managing member of Brook Hollow is Defendant
    Continental Development & Construction, Inc. (“Continental”). Defendant Nicholas Psillas
    (“Psillas”) is the president of Continental. Psillas is also a partner with Defendant Marshall
    Collier (“Collier”) in a separate entity, Defendant P&C Contractors (“P&C”).1
    Brook Hollow planned to build a subdivision on the property. Toward that end, Brook
    Hollow hired Gibbs to put in roads for the subdivision. Constructing the roads was comprised of
    four phases: base stone work, asphalt binder work, concrete curb construction, and asphalt
    topcoat work. The contract between Gibbs and Brook Hollow specified that Gibbs would
    construct an 8-inch deep limestone base and a layer of asphalt binder 2 inches deep. The fourth
    step, an asphalt topcoat, was to be added after construction on the subdivision was complete.
    The contract stated that “[i]nvoices not paid when due are subject to late charges of 1.5% per
    month.”
    For roads such as those at issue in this case, the City of Fairview’s specifications were a
    minimum of eight inches of crush rock, two inches of binder asphalt, and one and a half inches
    of topcoat. Plans for the subdivision were drawn up by an engineer with defendant Continental,
    and were approved by the City of Fairview. The plans indicated an eight-inch stone base and a
    two-inch asphalt binder, with the notation “+/-” with the measurement requirements. These
    plans were given to Gibbs for Gibbs’ use in submitting a bid for the roadwork. The bid was
    submitted in August 1999 and was accepted by Brook Hollow in September 1999. The plans
    were referenced in the contract between Gibbs and Brook Hollow.
    Defendant P&C was responsible for the utility and subgrade work, putting in the roadbed
    and the preparation for utilities such as sewers and water drainage. This work was necessary to
    prepare for the base stone and asphalt work by Gibbs. In October 1999, in a separate transaction,
    P&C hired Gibbs to finish the grading of the roadways. On October 30, 1999, Gibbs invoiced
    P&C $5,975.00 for this subgrade work. Collier forwarded this invoice to defendant Continental.
    It was not paid.
    1
    Continental, Psillas, Collier and P&C were named as defendants in the litigation below, but the trial court ultimately
    dismissed Gibbs’ claims against them, and that decision was not appealed.
    -2-
    Thereafter, Gibbs commenced work on the first three phases of laying the roadway, that
    is, the base stone work, the asphalt binder, and construction of the concrete curbs. These first
    three steps were completed in early November 1999. On November 11, 1999, Gibbs sent
    Continental an invoice for $107,649.30 for the work completed to that point. This invoice
    likewise was not paid.
    Gibbs’s bookkeeper at the time, James Potts, made a number of telephone calls to
    Continental in an attempt to collect the invoices. In May 2000, Gibbs received a $50,000.00
    check from Brook Hollow. No further payments were received.
    In June 2000, Gibbs filed a Notice of Lien for $63,624.30, which represented the balance
    from two unpaid invoices on the roadwork for the subdivision, minus the $50,000.00 partial
    payment.2 The Notice of Lien named Brook Hollow as the owner of the property.
    On July 31, 2000, Gibbs filed suit against Brook Hollow to enforce the lien and for
    money damages against Brook Hollow. In October 2000, Gibbs amended the complaint to add
    defendant National Grange Mutual Insurance Company, as surety for Brook Hollow. In its
    answer to Gibbs’ first amended complaint, Brook Hollow denied liability and asserted as an
    affirmative defense that Gibbs’ work was of poor quality. Brook Hollow asserted a claim for the
    cost of correcting or redoing Gibbs’ work as a setoff against any damages for which it might be
    held liable.
    In April 2001, Gibbs filed a motion to file a second amended complaint, adding as
    defendants Continental, P&C Contractors, and Psillas and Collier individually. This amendment
    was permitted by consent. In July 2001, Gibbs filed a motion to amend the complaint again. In
    the motion, Gibbs alleged that it had inadvertently failed to invoice Brook Hollow for work done
    on a model home at the site and sought to amend to include a claim for payment for this work, in
    the amount of $8,793.14. This amendment was likewise permitted by consent.
    During the pendency of the litigation, the thickness of the base and the asphalt binder was
    tested by core drilling on the roadway, performed by Professional Services Industries, Inc.
    (“PSI”), an engineering and testing facility located in Nashville, Tennessee. PSI was hired by
    the City of Fairview. PSI submitted a report dated January 13, 2003.
    In addition, Brook Hollow hired Dr. Louis Mishu, a geotechnical engineer, to test the
    paving work done by Gibbs. By letter dated May 22, 2002, Brook Hollow notified Gibbs that it
    intended to call Dr. Mishu as an expert witness at the trial, scheduled for June 3, 2002. Gibbs
    filed a motion in limine to exclude Dr. Mishu’s expert testimony. The motion was granted on
    the basis that Brook Hollow failed to timely supplement its response to Gibbs’ discovery request
    seeking the identity of all experts.
    2
    The invoices and Notice of Lien did not include late charges. The trial court awarded prejudgment interest in lieu
    of late charges. The late charge issue was not raised on appeal.
    -3-
    The three-day bench trial was held on June 3, 2002, and March 13-14, 2003. At trial,
    Gibbs’ representative, Kenneth Brown (“Brown”), testified that Gibbs did not receive
    notification of any perceived defects in its work until after Gibbs filed suit to enforce the lien
    against Brook Hollow. To address alleged defects in workmanship, Brown said, a one year
    implied warranty for labor and materials was customary for this type of construction work.
    Brown noted, however, that Brook Hollow’s first mention of any defects in Gibbs’ workmanship
    came well over a year after Gibbs completed the invoiced work.
    As to the alleged defects in Gibbs’ work, Brown testified that any failures in the paving
    work was caused by subgrade failure or abuse, not by Gibbs’s workmanship. Brown stated that a
    plus or minus tolerance or variance was customary in the paving industry in this geographical
    area.
    Collier testified on behalf of Brook Hollow. Collier noted that the City of Fairview’s
    specifications required a minimum of eight inches of stone and two inches of binder. He stated
    that he was not familiar with a plus or minus tolerance level. However, he acknowledged that
    the plans on which Gibbs based its bid indicated a plus or minus variance in the thickness
    measurements. Collier also said that a quarter to a half an inch of tolerance would be acceptable
    on the asphalt binder and less than one inch of tolerance would be acceptable on the base stone.
    Despite the grant of Gibbs’ motion in limine, Dr. Mishu was permitted to testify on
    Brook Hollow’s behalf on some issues. Mishu testified that he could not approximate the
    amount of the pavement that was bad at the time he tested Gibbs’ paving work. Dr. Mishu
    alleged that the primary reason for problems with the pavement was that the paving material
    contained too many fine particles. Mishu stated that the secondary reason for the pavement
    problems was that the paving was not thick enough.
    PSI’s representative, Wayne Haranack (“Haranack”), testified on the results of PSI’s
    testing of core samples of the pavement. Haranack found that the average of the core samples
    for the binder coat was 1.83 inches, or .17 inches short of the required two inches. Haranack
    testified that PSI also found that the average of stone base samples was 8.09 inches, or .09 more
    than required. PSI’s report stated that, in general, the binder was performing adequately, with
    relatively isolated problem areas.
    At the conclusion of the trial, the learned trial judge issued an oral ruling. The trial court
    found that Gibbs completed the work according to the contract between the parties. The trial
    court also found that Brook Hollow did not complain of any defects in the workmanship until
    after Gibbs filed a lien on the property for the amount owed. The trial judge noted that the
    experts disagreed about the extent of problems with the pavement, but accepted the testimony of
    PSI’s representative, Haranack. The trial court found that Gibbs’ paving work was within the
    tolerance levels accepted in custom and practice and within the provisions of the plans, which
    noted a “+/-” on the measurements.
    -4-
    The trial judge found that any needed repairs should have been addressed pursuant to
    applicable warranties, but noted that Brook Hollow could not reasonably ask Gibbs to make
    warranty repairs when Gibbs had not been paid for the work. The trial court found no evidence
    of a specific request that Gibbs make any repairs. Regardless, the trial court noted that no proof
    was submitted at trial of any amount needed to make such repairs. Consequently, the trial court
    held that it was impossible to determine any setoff amount or recoupment amount.
    As a result of these findings, the trial court entered a judgment against Brook Hollow in
    favor of Gibbs for $72,417.44. Of that amount, $57,649.30 was awarded against National
    Grange Mutual on the surety bond. In addition, the trial court awarded prejudgment interest of
    10 per cent per annum from December 11, 1999 to June 30, 2002. The claims against the
    remaining defendants were dismissed. From this order, Brook Hollow and National Grange
    Mutual appeal.
    On appeal, Brook Hollow argues that the trial court erred in ruling that Gibbs had a valid
    lien. Brook Hollow further contends that the trial court erred in ruling that Gibbs was not
    obligated to honor an implied warranty and in finding that the roads constructed by Gibbs were
    private roads instead of public roads. Brook Hollow also asserts that the trial court erred in
    limiting Dr. Mishu’s testimony, in finding that a variance in thickness was permissible under the
    contract, in finding that Gibbs’ paving work was within acceptable tolerance levels, in refusing
    to permit Brook Hollow to setoff the cost of repairs to the roadway, and in the award of the
    prejudgment interest against Brook Hollow.
    Our review of this case is governed by T.R.A.P. 13(d), which provides that review of
    findings of fact by the trial court shall be de novo upon the record of the trial court, accompanied
    by a presumption of correctness of the factual findings, unless the evidence preponderates
    otherwise. T.R.A.P. 13(d); Union Carbide Corp. v. Huddleston, 
    854 S.W.2d 87
    , 91 (Tenn.
    1993). The trial court is afforded discretion to determine the “admissibility, qualifications,
    relevancy and competency of expert testimony.” McDaniel v. CSX Transp., Inc., 
    955 S.W.2d 257
    , 263 (Tenn. 1997). The trial court’s rulings in this regard will be upheld except upon a
    showing of an abuse of this discretion. Id. at 263-64. “Resolving the conflicting testimony of
    experts falls within the province of the trier of fact[,]” Atkins v. State, 
    2004 WL 787166
    , *5
    (Tenn. Ct. App. Apr. 14, 2004) (citing State v. Flake, 
    88 S.W.3d 540
     (Tenn. 2002)), “and where
    an expert witness’s testimony is supported by the evidence and the trier of fact credits that
    testimony over others, there is no basis to reverse the court’s findings.” Id. (citing Balsinger v.
    Town of Madisonville, 
    435 S.W.2d 803
     (Tenn. 1968)).
    Brook Hollow first argues that Gibbs’s lien was invalid because the roads constructed by
    Gibbs were public roads rather than private roadways, and thus are not subject to lien under
    Tennessee Code Annotated §§ 66-11-101 and 102. The relevant portion of Section 66-1-102
    provides: “There shall be a lien upon any lot of ground or tract of land upon which . . .
    improvements [are] made, by special contract with the owner or the owner’s agent, in favor of
    the contractor, mechanic, laborer.” Section 66-11-101 (7) defines the term “improvement” as
    follows:
    -5-
    Improvement means any building, structure, erection, alteration,
    demolition, excavation, or any part thereof, including . . . private
    roadways, on real property for its permanent benefit, whether there
    is existing at the time of such work, any building, structure or other
    improvements upon the real property.
    Tenn. Code Ann. § 66-11-101(7) (2004). Thus, improvements regarding a roadway may be
    subject to lien, so long as the roadway is private.
    Brook Hollow asserts that the roads in the subdivision were not private roadways because
    the City of Fairview gave plat approval to Brook Hollow before the roads were built, making
    them public roads. Tennessee statutes, however, are contrary to Brook Hollow’s position.
    Tennessee Code Annotated § 13-3-405 states expressly that plat approval does not constitute
    public acceptance of the road. T.C.A. § 13-3-405 (1999). Moreover, in Hackett v. Smith
    County, 
    807 S.W.2d 695
     (Tenn. Ct. App. 1990), this Court explained that a road becomes public
    after there has been an offer of dedication of the road and an acceptance of its dedication to
    public use. Id. at 699. Acceptance of a road to public use may be implied through ongoing
    public use. Id. Here, the facts are inconsistent with any acceptance of the roads to public use.
    It is undisputed that Brook Hollow remained the owner of the property on which the roads were
    located. Therefore, there could be no acceptance of the roads’ dedication to public use.
    Moreover, at the time Gibbs filed the lien, the final layer of asphalt had not yet been put on the
    roads; therefore, there could be no implied acceptance of the roads to public use through ongoing
    public use. Consequently, the roadways on which Gibbs performed work remained “private
    roadways” within the meaning of Section 66-11-101(7), and the work performed by Gibbs would
    be deemed an “improvement” within the meaning of Section 66-11-102, and subject to lien on
    the land owned by Brook Hollow. Accordingly, the trial court is affirmed on this issue.
    Brook Hollow asserts that the trial court erred in refusing to permit some of Dr. Mishu’s
    testimony. Initially, the trial court refused to allow Dr. Mishu’s testimony as an expert, because
    Brook Hollow failed to timely supplement its discovery responses to disclose Dr. Mishu as an
    expert who would testify on behalf of Brook Hollow at trial. During the trial, however, the trial
    court allowed Dr. Mishu to testify, primarily as a fact witness, but also as an expert on some
    topics. As noted above, the trial court is afforded wide discretion to determine the admissibility
    and competency of expert testimony, the decision of a trial court regarding an expert will be
    upheld unless it is shown to be an abuse of discretion. Atkins v. State, 
    2004 WL 787166
    , *5
    (Tenn. Ct. App. Apr. 14, 2004). Further, Tennessee Rules of Civil Procedure provide specific
    discovery sanctions, which include preventing a party from introducing certain matters into
    evidence. Tenn. R. Civ. P. 37.02(B); Kuehne & Nagel, Inc. v. Preston, Skahan & Smith
    Intern., Inc., 
    2002 WL 1389615
    , *4 (Tenn. Ct. App. June 27, 2002). To the extent that the trial
    court excluded Dr. Mishu’s expert testimony, we find no error in this decision, and it is affirmed.
    Brook Hollow also asserts that the trial court erred in finding that a variance from the
    listed measurements was acceptable under the contract between the parties. Brook Hollow relies
    on Estate of Jessee v. White, 
    633 S.W.2d 767
     (Tenn. Ct. App. 1982) in support of its position
    -6-
    that a deviation from the contractual specifications constitutes a material breach of contract.
    White, however, does not stand for this proposition. In White, the defendant contractor was
    hired to pave a parking lot. Id. at 768. The contract called for a minimum base of no less than
    four inches, and required the contractor to upgrade the specifications as required to meet the
    recommendations of the Asphalt Association and the State Highway Department. Id. at 768.
    The contractor hired a subcontractor to do the paving work. Id. The subcontractor did not
    comply with minimum standards and made no effort to ascertain the recommendations of the
    Asphalt Association or the State Highway Department. Id. Under the contract, the contractor
    remained liable for the subcontractor’s breach of the contractual duties. Id. at 769.
    Consequently, the contractor in White was held liable under the agreement. Id. In contrast, in
    this case, the trial court held that a variance was acceptable under the contract in light of the
    explicit provision in the plans, referenced in the contract, and in light of testimony regarding
    industry custom and practice.
    In the case at bar, Brook Hollow’s witness, Collier, testified that the original plans for the
    pavement allowed for a variance and that the plans were drawn up by an engineer hired for
    Continental. Collier acknowledged that these plans were approved by the City of Fairview, were
    referenced in the contract, and were given to Gibbs in order for Gibbs to rely on them in
    submitting a bid. Under these circumstances, we must affirm the trial court’s decision on this
    issue.
    Brook Hollow argues on appeal that the trial court erred in crediting Haranack’s
    testimony over the testimony of Dr. Mishu on the amount of variance in the paving and the
    reason for any problems in the pavement. The appellate court accords great deference to the
    credibility determinations of the trial court, since the trial judge has the opportunity to observe
    the manner and demeanor of the witnesses while testifying. Bowman v. Bowman, 
    836 S.W.2d 563
    , 566 (Tenn. Ct. App. 1991). Brook Hollow notes that the trial court, in its oral ruling,
    erroneously described Haranack as having been selected by both Gibbs and Brook Hollow. We
    find this to be harmless error; the fact is simply that the trial court apparently credited
    Haranack’s testimony over that of Dr. Mishu. We find no basis in the record for reversing this
    credibility determination.
    Brook Hollow argues on appeal that it is entitled to recoupment—a setoff of the amount
    of necessary repairs from the judgment in favor of Gibbs. In its ruling, the trial court stated
    there does not appear to be any evidence of a specific request to
    make repairs articulated either in writing . . . or even orally by
    [Brook Hollow]. Instead, it appears that [Brook Hollow] latched
    on to these problems as a reason to not pay anything else. The
    Court finds that to be unacceptable. Likewise, there is no proof of
    any amount needed to make repairs. Therefore, it’s impossible to
    determine setoff or recoupment in this case.
    -7-
    Brook Hollow asserts that it could not present proof of damages because the trial court refused to
    allow testimony from its expert witness, Dr. Mishu. As noted above, we find no abuse of
    discretion in the trial court’s determination on the admissibility of Dr. Mishu as an expert
    witness. McDaniel v. CSX Transp., Inc., 
    955 S.W.2d 257
    , 263 (Tenn. 1997). Brook Hollow
    does not point to any place in the record in which it made, or sought to make, an offer of proof of
    Dr. Mishu’s testimony regarding damages. Moreover, after the trial court ruled on Gibbs’
    motion in limine regarding Dr. Mishu’s testimony, Brook Hollow was on notice that his
    testimony would be limited. After the first day of trial, June 3, 2002, the remainder of the trial
    testimony was heard on March 13-14, 2003, and Brook Hollow nevertheless did not proffer
    evidence from which the trial court could determine an amount to award as recoupment to Brook
    Hollow. We find no error in the trial court’s decision on this issue.
    Finally, Brook Hollow argues that the trial court erred in awarding prejudgment interest.
    Brook Hollow asserts that the trial court was biased and awarded prejudgment interest to punish
    Brook Hollow, rather than to fully compensate Gibbs. Brook Hollow bases this argument on the
    trial judge’s statement that “it appears that [Brook Hollow] latched onto these problems as a
    reason to not pay anything else.”
    In Myint v. Allstate Ins. Co., 
    970 S.W.2d 920
    , 927 (Tenn. 1998), the Tennessee Supreme
    Court noted that the purpose of prejudgment interest is to “fully compensate a plaintiff for the
    loss of use of funds to which he or she was legally entitled, not to penalize a defendant for
    wrongdoing.” It held that an “award of prejudgment interest is within the sound discretion of the
    trial court and the decision will not be disturbed by an appellate court unless the record reveals a
    manifest and palpable abuse of discretion.” Id. at 927 (citing Spencer v. A-1 Crane Service,
    Inc., 
    880 S.W.2d 938
    , 944 (Tenn.1994)); Otis v. Cambridge Mut. Fire Ins. Co., 
    850 S.W.2d 439
    , 446 (Tenn.1992). The Myint court observed that, “in cases where the evidence supports the
    trial court’s decision, no abuse of discretion is found.” Id. at 927.
    In the case at bar, it is undisputed that Brook Hollow did not send Gibbs any written
    communication regarding perceived defects in Gibbs’ workmanship until Brook Hollow filed its
    answer to Gibbs’ complaint to enforce its lien. Brook Hollow presented testimony from Psillas
    that he began observing failures in the paved roadways in December 1999, and that he
    mentioned these failures to Collier. In contrast, Gibbs presented testimony that, in the course of
    its efforts to collect the amount due from Brook Hollow before filing a lien, including
    discussions with Psillas, there were no assertions of defects in Gibbs’ work. Gibbs’ position was
    that it had no notice that Brook Hollow considered its workmanship defective until it received
    Brook Hollow’s answer to the complaint. The statement by the trial judge to which Brook
    Hollow objects indicates that the trial court credited the testimony presented by Gibbs on this
    issue. Again, we accord great deference to the trial court’s determinations of credibility.
    Bowman, 836 S.W.2d at 566. With appropriate deference to the trial court’s credibility
    determination, there is ample evidence in the record to support the trial court’s conclusion that
    Brook Hollow gave Gibbs no notice of perceived defects until after Gibbs filed suit to enforce its
    lien, and the resulting inference that Brook Hollow “latched onto” these defects as a reason not
    to pay Gibbs any more money for its work. Under these circumstances, we find no error by the
    -8-
    trial court in reaching this conclusion. Accordingly, we affirm the trial court’s decision to award
    prejudgment interest to Gibbs.
    The decision of the trial court is affirmed. Costs of this appeal are assessed against
    Defendant/Appellants, Brook Hollow Green, LLC, and National Grange Mutual Insurance
    Company, for which execution may issue, if necessary.
    __________________________________________
    HOLLY M. KIRBY, JUDGE
    -9-