  •                    IN THE COURT OF APPEALS OF TENNESSEE,
    AT KNOXVILLE
    FILED
    _______________________________________________________
    May 1, 1998
    )
    POTTER’S HOME CENTER, INC.,         )     Anderson County Chancery Court
    Cecil Crowson, Jr.
    d/b/a POTTER’S HOME CENTER,         )     No. 95CH3775     Appellate C ourt Clerk
    )
    Plaintiff/Appellant.             )
    )
    VS.                                 )     C.A. No. 03A01-9710-CH-00467
    )
    LAUREN DALE TUCKER, and,            )
    WILBURN R. VILES, SR. and wife,     )
    MILDRED E. VILES, and the           )
    GUARANTY TITLE COMPANY, and )
    FIRST AMERICAN NATIONAL BANK )
    )
    Defendants/Appellees.            )
    )
    ______________________________________________________________________________
    From the Chancery Court of Anderson County at Clinton.
    Honorable William E. Lantrip, Judge
    Thomas C. Coleman, Jr., Jamestown, Tennessee
    Attorney for Plaintiff/Appellant.
    Dail R. Cantrell, CANTRELL, PRATT & VARSALONA, Clinton, Tennessee
    Attorney for Defendants/Appellees.
    OPINION FILED:
    AFFIRMED AND REMANDED
    FARMER, J.
    HIGHERS, J.: (Concurs)
    LILLARD, J.: (Concurs)
    Potter’s Home Center appeals the trial court’s summary judgment which dismissed
    its suit to enforce a materialman’s lien against Defendants/Appellees Wilburn R. Viles, Sr., and
    Mildred E. Viles. We affirm the trial court’s judgment based on our conclusion that Potter’s failed
    to comply with the applicable notice requirements of the mechanics’ and materialmen’s lien statutes.
    For purposes of these summary judgment proceedings, the following facts were
    undisputed. Defendant Lauren Dale Tucker purchased building materials and supplies from Potter’s
    for use on property owned by the Viles in Anderson County. The subject property was known as the
    “old Dairy Queen” property and was located within the city limits of Clinton, Tennessee. Tucker
    subsequently did not pay for many of the items he purchased from Potter’s for use on the Viles’
    property. Potter’s, therefore, sought to establish a materialman’s lien against the property by
    providing the statutorily- required notice of nonpayment to the owners of the property, the Viles.
    See T.C.A. § 66-11-115(a) (1993). Instead of serving the notice of nonpayment by registered or
    certified mail as required by statute, two of Potter’s employees hand delivered the notice to Mr.
    Viles’ office. See T.C.A. § 66-11-145(a) (1993). Both employees gave the same account of their
    delivery of the notice:
    I returned to the office of Wilburn R. Viles, Sr. and left a copy with
    his secretary on her desk. She was very busy and Mr. Viles was not
    available because he was supposedly very busy also, as I was so
    informed by his Secretary.
    Potter’s thereafter filed this lawsuit against the Viles to enforce the materialman’s
    lien. The Viles responded by filing a motion for summary judgment in which they contended that
    Potter’s could not enforce the materialman’s lien because Potter’s failed to comply with the notice
    of nonpayment requirements as set forth in the mechanics’ and materialmen’s lien statutes. The trial
    court granted the motion, and this appeal followed.1
    In order to establish a lien on property on which work is done or labor and materials
    are furnished, a claimant must provide a notice of nonpayment to the landowner in accordance with
    1
    Potter’s lawsuit also named Lauren Dale Tucker, the Guaranty Title Company, and First
    American National Bank as defendants; however, the trial court’s order indicates that it disposed
    of any claims against these defendants in a prior order.
    the mechanics’ and materialmen’s lien statutes. T.C.A. § 66-11-115(a) (1993).2 As pertinent, the
    mechanics’ and materialmen’s lien statutes contain the following notice of nonpayment
    requirements:3
    Every subcontractor, laborer or materialman contracted with
    or employed to work on buildings, fixtures, machinery, or
    improvements, or to furnish materials for the same, except one-
    family, two-family, three-family and four-family residential units,
    whether such subcontractor, laborer or materialman was employed by
    or contracted with the person who originally contracted with the
    owner of the premises or by an immediate or remote subcontractor
    acting under contract with the original contractor, or any
    subcontractor, shall provide, within sixty (60) days of the last day of
    the month within which work, services or materials were provided,
    a notice of nonpayment for such work, services or materials to the
    owner and contractor contracting with the owner if its account is, in
    fact, unpaid. The notice, which shall be served by registered or
    certified mail, return receipt requested, shall contain: . . . .
    T.C.A. § 66-11-145(a) (1993) (emphasis added).
    At the outset, we note that the foregoing provisions do not permit a supplier claiming
    a materialman’s lien to hand deliver the required notice of nonpayment. The provisions instead
    require the claimant to serve the notice “by registered or certified mail, return receipt requested.”
    T.C.A. § 66-11-145(a) (1993). In the present case, the evidence shows that Potter’s employees hand
    delivered the required notice of nonpayment to Mr. Viles’ office but that Potter’s did not serve the
    notice by registered or certified mail as required by the mechanics’ and materialmen’s statutes.
    Inasmuch as Potter’s did not satisfy the requirements of section 66-11-145(a), Potter’s is not entitled
    2
    Section 66-11-115(a) contains the following provisions:
    Every journeyman or other person contracted with or
    employed to work on the buildings, fixtures, machinery, or
    improvements, or to furnish materials for the same, whether such
    journeyman, furnisher, or other person was employed or contracted
    with by the person who originally contracted with the owner of the
    premises, or by an immediate or remote subcontractor acting under
    contract with the original contractor, or any subcontractor, shall
    have this lien for such work or material; provided, that the
    subcontractor, laborer or materialman satisfies all of the
    requirements set forth in § 66-11-145, if applicable.
    T.C.A. § 66-11-115(a) (1993) (emphasis added).
    3
    The legislature enacted these new requirements in 1990. See 1990 Tenn. Pub. Acts. 854.
    to a materialman’s lien on the property.
    Despite the foregoing statutory requirements, Potter’s argues on appeal that its
    employees’ hand delivery of the notice of nonpayment constituted sufficient service of the notice as
    required by section 66-11-145(a) because the Viles thereby received actual notice of nonpayment.
    This court considered and, ultimately, rejected a similar argument in Don Wood Plumbing Co. v.
    Tri-Pi, Ltd., No. 01A01-9304-CH-00162, 
    1993 WL 350114
     (Tenn. App. Sept. 15, 1993). There,
    the plaintiff failed to comply with the notice of nonpayment requirements of section 66-11-145(a)
    in that the plaintiff’s notice did not show the last date the plaintiff performed work or provided
    materials in connection with the improvements to the real property. See T.C.A. § 66-11-145(a)(3)
    (Supp. 1990) (providing that notice shall contain, inter alia, a “statement of the last date the claimant
    performed work and/or provided services or materials in connection with the improvements”). In
    urging this court to affirm the trial court’s judgment enforcing the lien, the plaintiff argued that the
    landowner had actual notice of the last date the work was performed and that the plaintiff
    substantially complied with the notice provisions of the mechanics’ and materialmen’s lien statutes.
    Don Wood Plumbing, 
    1993 WL 350114
    , at *2.
    In rejecting the plaintiff’s argument, this court reasoned that:
    The courts have uniformly held that strict compliance with the
    mechanics’ and materialmen’s lien statutes is required in order to
    establish a subcontractor’s lien against the owner. See D.T.
    McCall & Sons v. Seagraves, 
    796 S.W.2d 457
     (Tenn. App. 1990)
    (defective oath on the complaint seeking to enforce the lien);
    Sequatchie Concrete Service v. Cutter Labs, 
    616 S.W.2d 162
     (Tenn.
    App. 1980) (improper description of the property in the notice to the
    owner); Pulaski Lumber Co., Inc. v. Harpeth South, Inc., 
    501 S.W.2d 275
     (Tenn. 1973) (notice of liens not sworn to in compliance
    with the statutes); Chattanooga Lumber & Coal Corp. v. Phillips,
    
    202 Tenn. 266
    , 
    304 S.W.2d 82
     (1957) (notice to the owner must be
    registered and authenticated as provided by statute).
    The reasoning behind all of these decisions was expressed by
    the Supreme Court in McDonnell v. Amo, 
    162 Tenn. 36
    , 
    34 S.W.2d 212
     (1931):
    A materialman’s lien is [altogether] statutory,
    and, when the lawmaking body prescribes the terms
    upon which it may be asserted, it is beyond the power
    of this court to waive its provisions or substitute
    others.
    162 Tenn. at 41, 34 S.W.2d at 213.
    We find that the plaintiff in this case failed to strictly comply
    with the requirements of the notice of nonpayment. Failure to comply
    results in the denial of any lien to the plaintiff.
    The plaintiff insists that the landowner had actual notice of the
    date the last work was performed on the project by the plaintiff. We
    can find no provision in the statute that dispenses with the obligation
    to provide the statutory notice where the landowner has actual
    knowledge of the facts contained in the notice. Therefore, we think
    that fact is irrelevant to the legal question involved here.
    Unless we are willing to depart from the long standing rules
    set out in the cases in this state and hold that substantial compliance
    with the mechanics’ and materialmen’s lien statutes is sufficient, the
    plaintiff’s claim in this case must fail. We are not persuaded to do so.
    Don Wood Plumbing, 
    1993 WL 350114
    , at **1-2 (emphasis in original).
    In accordance with this court’s reasoning in Don Wood Plumbing, we hold that the
    trial court properly dismissed Potter’s action to enforce the lien because Potter’s failed to strictly
    comply with the notice of nonpayment provisions of the mechanics’ and materialmen’s lien statutes.
    Even if, as Potter’s contends, the Viles had actual knowledge of the notice of nonpayment, such
    knowledge is irrelevant to the issue before this court. As in Don Wood Plumbing, Potter’s failure
    to strictly comply with the statutory requirements of the notice of nonpayment must result in the
    denial of any lien to Potter’s.
    The trial court’s judgment is affirmed, and this cause is remanded for further
    proceedings. Costs of this appeal are taxed to Appellant, for which execution may issue if necessary.
    ____________________________________
    FARMER, J.
    ______________________________
    HIGHERS, J. (Concurs)
    ______________________________
    LILLARD, J. (Concurs)