E Solutions For Buildings, LLC v. Knestrick Contractor, Inc. ( 2019 )


Menu:
  •                                                                                           10/30/2019
    IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    August 13, 2019 Session
    E SOLUTIONS FOR BUILDINGS, LLC v. KNESTRICK CONTRACTOR,
    INC., ET AL.
    Appeal from the Chancery Court for Davidson County
    No. 15-62-IV      Russell T. Perkins, Chancellor
    ___________________________________
    No. M2018-02028-COA-R3-CV
    ___________________________________
    This appeal involves payment disputes arising out of a public construction project.
    Among other things, the case involves claims made by an equipment supplier against a
    subcontractor, the project’s general contractor, and the general contractor’s bonding
    company, and claims made by the same subcontractor against the general contractor.
    Following a trial, the trial court granted the supplier a judgment against the subcontractor
    and granted the subcontractor a judgment against the general contractor. The supplier’s
    claim against the general contractor and its bonding company was denied. The propriety
    of these rulings and numerous other issues are now before this Court. Having reviewed
    the record transmitted to us on appeal, we affirm in part, affirm in part as modified,
    reverse in part, and remand the case for such further proceedings as are necessary and
    consistent with this Opinion.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed
    in Part; Modified in Part; Reversed in Part and Remanded
    ARNOLD B. GOLDIN, J., delivered the opinion of the Court, in which J. STEVEN
    STAFFORD, P.J., W.S., and CARMA DENNIS MCGEE, J., joined.
    Paul T. Housch, Nashville, Tennessee, for the appellant, Air Comfort Heating and
    Cooling, LLC.
    Timothy H. Nichols, Nashville, Tennessee, for the appellee, E Solutions for Buildings,
    LLC.
    Adam G. LaFevor, Nashville, Tennessee, for the appellees, Knestrick Contractor, Inc.,
    and Berkley Regional Insurance Company.
    OPINION
    BACKGROUND AND PROCEDURAL HISTORY
    This case stems from the construction of the Centennial Sportsplex Indoor Fitness
    Expansion Building by the Metropolitan Government of Nashville and Davidson County
    (“Metro”). In April 2013, Metro entered into a contract with Knestrick Contractor Inc.
    (“Knestrick”), pursuant to which Knestrick agreed to construct the Centennial Sportsplex
    expansion. Under the contract, Knestrick was obligated to accomplish substantial
    completion of the project by December 2, 2013,1 and if it failed to do so, Metro was
    entitled to assess “the sum of $1,000.00 for each calendar day of delay until the Project is
    Substantially Complete.” Knestrick, as principal, and Berkley Regional Insurance
    Company (“Berkley”), as surety, provided a payment bond in connection with the
    project.
    Following its agreement to serve as a general contractor for the Centennial
    Sportsplex expansion, Knestrick entered into a subcontract with Air Comfort Heating &
    Cooling, LLC (“Air Comfort”) with respect to the HVAC work required for the project.
    This subcontract, which was entered into in July 2013, specifically provided that the
    work must be performed on or before November 27, 2013. Moreover, similar to the
    prime contract between Metro and Knestrick, the subcontract involving Air Comfort
    provided that $1,000.00 in liquidated damages could be assessed “for each day that the
    work remains uncompleted beyond the specified date period.”
    In furtherance of its required work under the subcontract, Air Comfort sought to
    purchase certain HVAC equipment. To this end, Air Comfort engaged in negotiations
    with E Solutions for Buildings, LLC (“E Solutions”). E Solutions sent Air Comfort a
    proposal regarding the needed HVAC equipment on November 11, 2013, and on
    November 13, 2013, Air Comfort submitted a purchase order for the equipment. The
    purchase order recited December 13, 2013 as the delivery date, but in the terms and
    conditions attached to the purchase order, the following was provided: “Shipment dates
    are estimates only. No valid contract may be made to ship within or at a specified time
    unless in writing, signed by an authorized signatory of Seller.” There was no liquidated
    damages provision provided for in the contract between Air Comfort and E Solutions,
    and the attached terms and conditions further stated that the seller, E Solutions, would
    “IN NO EVENT . . . BE LIABLE FOR ANY INCIDENTAL, CONSEQUENTIAL, OR
    PUNITIVE DAMAGES.” Moreover, the terms and conditions provided that E
    Solutions’ duty to perform was subject to, among other things, the “inability to procure
    1
    Per an email sent in May 2013, a representative with Metro communicated that a revised construction
    schedule, establishing a substantial completion date of December 6, 2013, was appropriate based on the
    time it took Metro to process Knestrick’s final contract.
    -2-
    materials from the usual sources of supply” and other causes beyond its “reasonable
    control.”
    When the original deadline for completion of the project proved untenable, Metro
    and Knestrick entered into an amendment whereby the substantial completion date was
    extended to January 26, 2014. Although no corresponding amendment was formally
    made regarding the completion date of Air Comfort’s work under its subcontract with
    Knestrick, a Knestrick officer testified that an extension was also passed on to
    subcontractors. Nonetheless, the ultimate delay accompanying the project’s completion
    has engendered substantial controversy among the parties concerning their respective
    claims for payment. The project was eventually certified as substantially complete on
    May 8, 2014.
    Litigation subsequently ensued as a result of the construction project. The
    initiating complaint in this matter, which was filed by E Solutions in the Davidson
    County Chancery Court (“the trial court”) on January 15, 2015, alleged that E Solutions
    had not been paid for the materials, equipment, and services it provided on the project. In
    addition to asserting a bond claim against Knestrick and Berkley, E Solutions sued Air
    Comfort for breach of contract. Further, E Solutions pled an unjust enrichment/quantum
    meruit claim against Air Comfort and Knestrick.
    On February 20, 2015, Air Comfort filed an answer to E Solutions’ complaint and
    also asserted a counterclaim and cross-claim. In its defense to E Solutions’ action, Air
    Comfort asserted, among other things, that E Solutions had materially breached the
    purchase order with Air Comfort by delaying delivery of the specified HVAC equipment.
    Air Comfort claimed that it had been damaged by E Solutions’ alleged failure to timely
    deliver the ordered equipment, and it asserted several theories of liability in its cross-
    claim against Knestrick. Air Comfort alleged that Knestrick was liable for breach of
    contract by failing to pay it sums owed under the subcontract, and according to Air
    Comfort, Knestrick should also be held liable for conversion and in violation of the
    Prompt Pay Act. A bond claim, a claim for unjust enrichment/quantum meruit, and a
    claim for contribution were also asserted against Knestrick.2
    On February 24, 2015, Knestrick and Berkley filed an answer to E Solutions’
    complaint, wherein they prayed that the claims against them be dismissed, and within the
    same filing, Knestrick separately asserted a cross-claim against Air Comfort. In the
    cross-claim, Knestrick averred it was entitled to recover $72,000.00 in liquidated
    damages and alleged that it was entitled to indemnification regarding the action filed
    against it by E Solutions. Answers to the cross-claims and counterclaim were thereafter
    filed, and a bench trial was held in the fall of 2016.
    2
    The bond claim was asserted against Knestrick and Berkley.
    -3-
    On March 17, 2017, the trial court entered its “Memorandum and Final
    Judgment,” wherein it determined that Air Comfort was entitled to a judgment for breach
    of contract against Knestrick in the amount of $15,000.00. According to the trial court,
    this was the full extent of Knestrick’s liability, and the court declined to award Air
    Comfort prejudgment interest. Further, the trial court dismissed Air Comfort’s claims
    against E Solutions and E Solutions’ claims against Knestrick and Berkley. As for E
    Solutions’ requested relief against Air Comfort, the court awarded it a judgment in the
    amount of $42,847.98, plus prejudgment interest. Notably, the court’s order stated that it
    was reserving any determination about attorney’s fees, expenses, and discretionary costs
    until appeals in the case concluded.
    Several post-trial motions were thereafter filed, and on July 7, 2017, the trial court
    entered an order addressing them. The court noted that, notwithstanding its previous
    reservation of certain issues, it had decided to entertain previously stayed issues “[a]t the
    urging of certain of the parties.” In addition to addressing the parties’ requests for
    discretionary costs, the trial court denied Air Comfort’s request for attorney’s fees.
    Further, regarding attorney’s fees sought by E Solutions, Knestrick, and Berkley, the
    court held that:
    E Solutions is a prevailing party and is entitled to an award of reasonable
    attorneys’ fees under the contract entered with Air Comfort. The Court,
    however, hereby DENIES E Solutions application for attorneys’ fees,
    without prejudice, because it is not accompanied by a sworn detailed
    itemization of the services rendered and the time expended for those
    particular services as required under Local Rule § 5.05 and Tenn. Sup. Ct.
    R. 8, RPC 1.5(a)(1). This denial is without prejudice. E Solutions may
    renew its request for attorneys’ fees in this Court after all appeals are
    exhausted.
    ....
    Knestrick and Berkley are prevailing parties. Knestrick is generally entitled
    to attorneys’ fees under the indemnification provisions[] of the parties’
    subcontract due to Air Comfort’s decision to withhold payment to E
    Solutions when Air Comfort had no contractual right to do so. The Court,
    however, hereby DENIES, without prejudice, Knestrick and Berkley’s
    application for attorneys’ fees because it lacks the specific itemization
    required by Local Rule Sec. 5.05 and Tenn. Sup. Ct. R. 8, RPC 1.5,
    pending the outcome of the appeals.
    Although the order was certified as final pursuant to Rule 54.02 of the Tennessee
    Rules of Civil Procedure and an appeal was thereafter pursued in this Court, a different
    -4-
    panel of this Court dismissed the previous appeal for lack of subject matter jurisdiction,
    stating in relevant part as follows:
    Here, the trial court resolved the parties’ breach of contract claims
    and found that E Solutions, Knestrick, and Berkley are contractually
    entitled to recover their attorney’s fees, but the court granted in part and
    denied in part the request for contractual attorney’s fees, without prejudice,
    directing the parties to re-submit their requests after this appeal. This order
    was improvidently certified as final. Rule 54.02 “does not allow a trial
    court to certify an order[ ] that disposes of only some, but not all, elements
    of damages, as final and appealable.” Cooper v. Powers, No. E2011–
    01065–COA–R9–CV, 
    2011 WL 5925062
    , at *6 (Tenn. Ct. App. Nov. 29,
    2011). “Notably absent from Rule 54.02 is any mention of allowing the
    certification as final of an order which disposes of certain elements of a
    claim for damages but leaves the claim pending as to other elements.” 
    Id. See, e.g.,
    Johnson v. Tanner–Peck, L.L.C., No. W2009–02454–COA–R3–
    CV, 
    2011 WL 1330777
    , at *6 n.8 (Tenn. Ct. App. Apr. 8, 2011) (explaining
    that an order was not appropriate for certification as final under Rule 54.02
    because it did not dispose of a request for treble damages, punitive
    damages, attorney’s fees and the like arising out of the same claim); Cates,
    
    1991 WL 168620
    , at *4 (“Bifurcation of damages is fatal to a 54.02
    certification.... While it is proper for the trial court to bifurcate the
    eviden[t]iary hearings on these damages, it cannot bifurcate the appeal of
    it.”). An award as to only one facet of the total damages is not properly
    certifiable. Cates, 
    1991 WL 168620
    , at *4.
    We reached the same conclusion on facts similar to those before us
    in Toyos v. Hammock, No. W2011–01649–COA–R3–JV, 
    2013 WL 177417
    , at *16–17 (Tenn. Ct. App. Jan. 17, 2013). The trial court had
    certified its judgment as final pursuant to Rule 54.02 in “an attempt to
    finalize the judgment” even though the issue of attorney’s fees had not been
    resolved. This Court entered a per curiam opinion finding that we lacked
    jurisdiction in the matter because the trial court’s order failed to adjudicate
    the request for attorney fees. We likewise find that this Court lacks
    jurisdiction over the appeal in this matter.
    E Sols. for Bldgs., LLC v. Knestrick Contractor, Inc., No. M2017-00732-COA-R3-CV,
    
    2018 WL 1831116
    , at *4 (Tenn. Ct. App. Apr. 17, 2018) (footnote omitted), perm. app.
    denied (Tenn. Aug. 9, 2018).
    Following the remand of the case, the trial court addressed the outstanding issues.
    In an order entered on October 16, 2018, the trial court ruled on the amount of attorney’s
    fees, discretionary costs, and prejudgment interest owed to E Solutions and awarded
    -5-
    Knestrick and Berkley attorneys’ fees and discretionary costs against Air Comfort. A
    timely notice of appeal was filed by Air Comfort on November 8, 2018, leading to the
    present appeal.
    ISSUES PRESENTED
    This appeal concerns a variety of issues by both Air Comfort and E Solutions. In
    Air Comfort’s brief, the issues presented for our review are as follows:
    1. Whether the trial court erred in dismissing Air Comfort’s claim of conversion of
    construction proceeds and Prompt Pay Act claim against Knestrick.
    2. Whether the trial court erred in finding that Knestrick was entitled to assess
    liquidated damages against Air Comfort and only awarding Air Comfort a
    judgment for $15,000.00 against Knestrick for breach of contract.
    3. Whether the trial court erred in awarding E Solutions a judgment for $42,847.98
    against Air Comfort.
    4. Whether the trial court erred in denying Air Comfort attorney fees under the
    Prompt Pay Act against Knestrick for withholding a contract payment and
    retainage payment.
    5. Whether the trial court erred in denying Air Comfort discretionary costs against
    Knestrick.
    6. Whether the trial court erred in denying Air Comfort prejudgment interest against
    Knestrick.
    7. Whether the trial court erred in awarding E Solutions Attorney Fees, and
    Prejudgment interest against Air Comfort.
    8. Whether the trial court erred in awarding Knestrick attorney fees and discretionary
    costs against Air Comfort.
    For its part, E Solutions raises the following issues in its appellate brief:
    1. Whether the trial court erred in awarding E Solutions a judgment for [only]
    $42,847.98 against Air Comfort.
    2. Whether the trial court erred in awarding E Solutions attorney’s fees and
    prejudgment interest against Air Comfort.
    3. Whether E Solutions is entitled to an award of additional attorney’s fees on appeal.
    4. Whether the trial court erred in not awarding E Solutions a judgment against
    Knestrick, as principal, and Berkley, as surety, on the payment bond claim.
    Knestrick and Berkley have no “Statement of the Issues” section in their brief.
    -6-
    STANDARD OF REVIEW
    This appeal arises from a bench trial. Pursuant to Rule 13(d) of the Tennessee
    Rules of Appellate Procedure, “review of findings of fact by the trial court in civil actions
    shall be de novo upon the record of the trial court, accompanied by a presumption of the
    correctness of the finding, unless the preponderance of the evidence is otherwise.” Tenn.
    R. App. P. 13(d). We review a trial court’s conclusions on questions of law de novo, but
    no presumption of correctness attaches to the trial court’s legal conclusions. Bowden v.
    Ward, 
    27 S.W.3d 913
    , 916 (Tenn. 2000). With respect to a discretionary decision made
    by a trial court, we review for an abuse of discretion. An abuse of discretion occurs when
    a court “has applied an incorrect legal standard, has reached a decision that is illogical,
    has based its decision on a clearly erroneous assessment of the evidence, or has employed
    reasoning that causes an injustice to the complaining party.” Boyd v. Comdata Network,
    Inc., 
    88 S.W.3d 203
    , 211-12 (Tenn. Ct. App. 2002).
    DISCUSSION
    As indicated above, a host of issues are presented for our review in this appeal. To
    begin our discussion, we will examine the monetary judgment Air Comfort received
    against Knestrick. In connection therewith, we will explore whether the amount of the
    judgment was proper and whether Knestrick was entitled to apply liquidated damages to
    Air Comfort’s claims for payment. Further, we will discuss whether Air Comfort’s
    remedies are limited to breach of contract and examine whether other legal theories, or
    other specific relief such as attorney’s fees, are properly implicated in this case.
    The primary dispute between Air Comfort and Knestrick concerns whether
    Knestrick paid all amounts owed to Air Comfort under the subcontract entered into
    between the two parties. We address this matter not only in connection with Air
    Comfort’s breach of contract claim, but also with respect to Air Comfort’s request for
    relief pursuant to the Prompt Pay Act, see Tenn. Code Ann. § 66-34-101 et seq. Of
    considerable importance to the discussion is Knestrick’s contention that it had the right to
    withhold payments and assess liquidated damages. The proof at trial showed that
    Knestrick assessed $72,000.00 in liquidated damages against Air Comfort due to delayed
    performance regarding the HVAC work for the project.
    Curiously, although the trial court awarded Air Comfort a judgment for breach of
    contract upon finding that it should receive a credit for certain of the liquidated damages
    that had been assessed against it by Knestrick for delayed performance, the court did not
    find that any violation of the Prompt Pay Act had been committed. It reached this
    conclusion notwithstanding the fact that Air Comfort had made applications for payment,
    provided Knestrick notice of nonpayment, and Knestrick had not paid all the amounts
    owed. The trial court reasoned that a claim under the Prompt Pay Act was “not
    established” given its “conclusion that the . . . liquidated damages provisions were legally
    -7-
    enforceable.” In our view, there is a lack of cohesion between the trial court’s factual
    findings and its legal conclusions. Indeed, even assuming that Knestrick was entitled to
    assess some amount of liquidated damages against Air Comfort, the trial court itself
    clearly held that not all of the funds owed to Air Comfort had been paid, as it refused to
    sanction the entirety of Knestrick’s $72,000.00 liquidated damages assessment. As the
    trial court’s order confirms that additional payment was owed to Air Comfort for its work
    under the subcontract, and the record reflects that this payment was not made despite
    applications for payment3 and notice of nonpayment submitted to Knestrick, the
    conclusion that there was no Prompt Pay Act violation is untenable.
    Knestrick vigorously maintains there was no Prompt Pay Act violation because it
    was entitled to withhold payment from Air Comfort. It notes that under Tennessee Code
    Annotated section 66-34-303, a contractor may withhold a portion of payment provided
    that such withheld payment is in accordance with the contract between the contractor and
    subcontractor, see Tenn. Code Ann. § 66-34-303, and here, Knestrick notes that the
    subcontract at issue allowed for a withholding of liquidated damages. No doubt, the
    Knestrick-Air Comfort subcontract did provide for liquidated damages, but as already
    noted, the trial court concluded that Knestrick withheld certain liquidated damages to
    which it was not entitled. Inasmuch as Knestrick has not challenged the trial court’s
    determination that a credit, and resulting judgment, was owed to Air Comfort regarding
    the withheld liquidated damages, there is no reasonable dispute that money was owed to
    Air Comfort when it sought payment from Knestrick in its renewed payment application.
    Moreover, even assuming that Knestrick had properly withheld the entirety of the
    originally assessed $72,000.00 in liquidated damages, the record reflects that additional
    sums were still owed to Air Comfort. In this vein, we note that Knestrick actually
    withheld more than $72,000.00 from the balance owed Air Comfort. In a renewed
    payment application submitted to Knestrick after the project was completed, Air Comfort
    requested a sum totaling $85,960.50 for unpaid HVAC work on the project. Absent any
    application of liquidated damages, which is a subject of controversy on appeal, there does
    not appear to be any reasonable dispute that Air Comfort earned this amount with respect
    to its performance on the Centennial Sportsplex expansion. The proof readily showed
    that the HVAC equipment was installed and that the project reached substantial
    completion. Having performed the contracted work, Air Comfort was owed the balance
    of its subcontract amount absent a valid application of offsetting damages. Yet, when
    pressed by this Court at oral argument how some amount was not owed to Air Comfort
    considering $85,960.50 in work under the contract had not been paid and only
    $72,000.00 in liquidated damages had been assessed, counsel for Knestrick argued that
    3
    In its brief on appeal, Knestrick remarks that applications for payment were made when Air Comfort’s
    work was not complete, specifically claiming that certain evidence at trial showed that all conditions
    precedent to final payment were not technically satisfied until May 12, 2014. This argument aside, we
    note that the record contains evidence that a renewed payment application regarding the amount sought
    by Air Comfort was made after that date.
    -8-
    his client could have assessed 102 days of liquidated damages. Although such an
    assessment, if permissible, would have clearly vitiated any right to payment in Air
    Comfort’s favor, Knestrick of course did not assess 102 days of liquidated damages.
    Moreover, Knestrick has not objected to the trial court’s finding that the assessment of 72
    days of liquidated damages was itself improper.
    In light of the above, although we certainly agree with the trial court that Air
    Comfort is entitled to a judgment for breach of contract, we respectfully disagree that the
    Prompt Pay Act was not violated. Simply put, Air Comfort was owed money when it
    submitted a renewed payment application after the completion of the project, and
    Knestrick never made payment after receiving notice of nonpayment. This failure to pay
    not only makes Knestrick liable under the contract, but pursuant to the Prompt Pay Act,
    makes Knestrick potentially subject to an assessment of attorney’s fees. See Tenn. Code
    Ann. § 66-34-602 (providing that where payment is not made after notice of nonpayment,
    the notifying party may seek relief in chancery court, where reasonable attorney’s fees
    “may be awarded against the nonprevailing party”).
    Before addressing the matter of attorney’s fees under the Prompt Pay Act, we will
    first review the propriety of the specific contractual amount that the trial court awarded to
    Air Comfort. As noted earlier, the trial court concluded that Air Comfort was entitled to
    a judgment in the amount of $15,000.00. Although we can ascertain from where the trial
    court arrived at this number, see infra, the trial court’s ruling on this issue has still
    confused both this Court and the parties4 on appeal. As further detailed herein, we
    respectfully conclude that the evidence preponderates in favor of a higher breach of
    contract judgment than that awarded by the trial court.
    The current judgment of $15,000.00 clearly follows from the trial court’s effective
    conclusion that 57 days of liquidated damages, which is 15 days less than 72 days, was
    the outer limit of a permissible assessment of liquidated damages under the subcontract.
    In relevant portion, the trial court’s order stated as follows:
    [T]he Court determines that Air Comfort is . . . entitled to a fifteen-day
    credit toward the seventy-two day liquidated damages assessment made by
    Knestrick against Air Comfort.
    ....
    Air Comfort, therefore, is entitled to a breach of contract judgment
    against Knestrick in the base amount of $15,000.00.
    4
    We note that at oral argument, upon questioning by the panel, counsel for Air Comfort and counsel for
    Knestrick both articulated some confusion as to how the trial court arrived at a judgment of $15,000.00.
    -9-
    Although the court’s order therefore unmistakably sets out its basis of Air Comfort’s
    specific $15,000.00 judgment against Knestrick, we fail to comprehend how the
    judgment is an accurate one based upon the record. Indeed, if an assessment for only 57
    days of liquidated damages was proper and the unpaid balance for completed work on Air
    Comfort’s subcontract was over $85,000.00, the judgment should have been higher than
    $15,000.00. Specifically, assuming that Knestrick was entitled to assess 57 days’ worth
    of liquidated damages, the evidence preponderates in favor of a finding that the judgment
    should have been $28,960.50 ($85,960.50-$57,000.00).
    The propriety of such a modified judgment is itself dependent upon reaching a
    conclusion that an assessment of liquidated damages for 57 days was even proper. This
    issue requires our review herein, because perhaps not unsurprisingly, Air Comfort argues
    that Knestrick was not entitled to assess any liquidated damages against it. For the
    reasons set forth below, we are in agreement with Air Comfort’s position on this issue.5
    As Air Comfort has pointed out, a party is not allowed to recover liquidated
    damages “where he is responsible for or has contributed to the delay or nonperformance
    alleged as breach.” V.L. Nicholson Co. v. Transcon Inv. & Financial Ltd., Inc., 
    595 S.W.2d 474
    , 484 (Tenn. 1980). Applying this principle in Airline Construction, Inc. v.
    Barr, 
    807 S.W.2d 247
    (Tenn. Ct. App. 1990), this Court held that the trial court in that
    case should not have awarded liquidated damages to a party that had “at the very least
    contributed to some of the delays” on a construction project. 
    Id. at 262.
    As we
    explained:
    Although Barr and the trial court have both pointed to numerous
    delays that were attributable to Airline, we cannot hold the plaintiff liable
    for all the delays merely because Airline’s delays may have outweighed
    those occasioned by Barr. The law in Tennessee is contrary to this
    conclusion. Liquidated damages will not be awarded to one that has
    contributed to or mutually caused the delay or breach. V.L. Nicholson
    Company v. Transcon Investment and Financial Ltd., 
    Inc., 595 S.W.2d at 484
    , citing Glassman Const. Co., Inc. v. Maryland City Plaza, Inc., 
    371 F. Supp. 1154
    (D.C. Md. 1974), aff’d, 
    530 F.2d 968
    (4th Cir. 1975); 9
    Tennessee Jurisprudence, Damages, § 29 (1983).
    5
    Although we agree with Air Comfort’s position that Knestrick should not be allowed to recover
    liquidated damages in connection with this case, we do not find favor in its specific argument that
    liquidated damages are unavailable due to a withdrawal of a liquidated damages claim. To the extent that
    Knestrick “withdrew” its claim for liquidated damages, Knestrick merely withdrew a request for a
    monetary judgment. Indeed, whereas a monetary claim for liquidated damages had clearly been asserted,
    counsel for Knestrick clarified at trial that Knestrick was not actually seeking a specific monetary
    judgment for such damages. Instead, counsel made clear that Knestrick was simply seeking confirmation
    that it had been entitled to previously withhold such funds based on a right to liquidated damages.
    - 10 -
    The defendant in this case could have recovered “actual” delay
    damages, See Mayo, Tennessee Law of Damages, § 15-5 (1988). However,
    absent proof of such damages there can be no award.
    
    Id. After Knestrick
    raised the propriety of its right to assess liquidated damages in its
    cross-claim against Air Comfort,6 Air Comfort filed an answer denying that it was
    responsible for liquidated damages. Among other things, it asserted that Knestrick had
    delayed the project and construction of the building at the Centennial Sportsplex
    expansion. This argument is not without substantial support in the record. Similar to the
    Airline case, the party claiming liquidated damages here—Knestrick—clearly contributed
    to a portion of the delay on the project. The evidence at trial showed that the completion
    of Air Comfort’s HVAC installation work was dependent on the existence of a building,
    and roof, at the project site. The evidence at trial reflected that Knestrick was responsible
    for delay relative to the construction of the building that impacted Air Comfort’s ability
    to perform. Indeed, when Knestrick’s owner, William Knestrick, was asked at trial
    whether any causes of delay on the project were Knestrick’s responsibility, he responded,
    “Now I realize that to be the case.” Regarding the sequence of activities on the project,
    we note that several of Air Comfort’s tasks on the project were scheduled to start in the
    fall of 2013. For example, Knestrick’s Vice President of Operations, Jerry Thurman,
    testified specifically concerning two activities, noting that there had been scheduled start
    dates of September 30, 2013 and October 21, 2013. Air Comfort’s ability to complete its
    work, however, was hindered given the lack of a building on the site. When asked at trial
    if a building had been erected as of October 2013 for Air Comfort to install mechanical
    equipment, Mr. Thurman responded, “I would doubt that since the slabs [were] not
    poured until the 4th of November.” Mr. Thurman’s testimony further indicated that
    although Knestrick had not completed the slab until November 4, 2013, such work had
    originally been scheduled for completion many months earlier, in July 2013. Mr.
    Thurman testified that the pouring of the slab was a critical path activity, confirming that
    the building on the site could not be built in the absence of a slab on which to put the
    building. Necessarily, therefore, the delay in the slab pouring caused delays in the
    construction of the building, thereby contributing to delayed performance of Air Comfort.
    According to Mr. Thurman’s testimony, it was a “fair statement” that the building may
    have “been up” by early December 2013 but not all “dried in.” For a building to be
    considered “dried in,” Mr. Thurman indicated that it would need, among other things, a
    roof.
    6
    Although the cross-claim specifically sought a judgment for $72,000.00 against Air Comfort, Knestrick,
    as we detailed in a previous footnote, clarified at trial that it was not actually seeking a judgment for that
    amount in liquidated damages, but rather, confirmation that the previous withholding of that amount as
    liquidated damages had been proper.
    - 11 -
    The proof at trial showed that delays on the project were evident fairly early on in
    the process. Charles Lampley, a senior project manager at Air Comfort, testified that in
    July 2013, after the subcontract had been signed, he went to the project site. Regarding
    the status of construction by Knestrick at that time, he stated, “Basically, there was no
    work done on site.” Timeline notes made by Chris Koster, Special Projects Manager
    with Metro’s Board of Parks and Recreation, detailed several aspects of the delay on the
    project. A note regarding the project status on July 23, 2013 indicated as follows:
    MP demands a recovery action plan from KNI to make up time on the
    schedule. MP requests KNI to increase needed manpower on site, increase
    hours and/or weekends, cut float time from the schedule and look at critical
    path activities to show a method of making up time on the schedule. MP
    informs KNI that this request has been outstanding for 2 months now and
    expects it to be delivered to MP by close of business 8.2.13.
    A subsequent note regarding August 2, 2013 indicated that the requested recovery plan
    had not been delivered. Another note regarding a time period spanning from July 2013 to
    August 2013 indicated as follows: “3 weeks passed without demo of site being
    completed despite assurances from KNI that this would be a 2 day project.”
    Included among the many detailed project delays, Mr. Koster’s notes have several
    entries regarding the delayed slab pouring for the project. A note regarding September
    17, 2013 stated that “KNI indicates slab pour will now occur at the end of the month.”
    Several subsequent notes for October 2013 detail the slab pouring not having been
    completed. Given the delays on the project, Metro expressed its concern to Knestrick. In
    an email sent on October 9, 2013, the Director of the Parks Department noted the
    “significant contractor delay” and stated that whereas the project should have then been
    past 50% completion, payment applications indicated it was only at about 10%
    completion. The email was critical of Knestrick’s attention to the matter, noting in
    relevant part as follows:
    Our project manager has been requesting a Recovery Plan from
    Knestrick since June demonstrating how you intend to devote resources and
    manage the construction to get back on schedule. As of this month we still
    have not seen an effort to provide a recovery plan or devote the resources
    on site to make up lost time. At this time, this department finds the
    response by your company to these requests and effort to recover time to be
    insufficient and unacceptable.
    Therefore, the Metro Purchasing director and I would like to meet
    with you, or whoever is most appropriate within the Knestrick
    administration, to discuss these and other issues related to performance on
    this contract and what options are available moving forward.
    - 12 -
    Knestrick eventually received an extension from Metro to reach substantial
    completion, and although no formal amendment was reached between Knestrick and Air
    Comfort, Mr. Thurman testified that the awarded 55-day extension was passed on to
    subcontractors. The proof showed that the extension was not necessitated by Air
    Comfort in any way. Moreover, the proof showed that measuring Air Comfort’s
    performance relative to such an extension was improper. Whereas Knestrick had
    originally sought an 84-day extension, it was untimely in seeking this request from
    Metro. The trial court itself noted that there were “delays attendant to Knestrick’s failure
    to obtain a full 84-day extension of the original Project schedule,” and therefore, the court
    was of the opinion that a full measure of liquidated damages was improper. In discussing
    the insufficiency of the awarded extension and taking note of delays attributable solely to
    Knestrick, the trial court stated as follows:
    The Court concludes that adding 55 days was an insufficient extension for
    delays that cannot be attributable to any party to this lawsuit, except
    Knestrick. Because of this delay, the pouring of the slab, for example, was
    delayed from a completion date of on or about July 1, 2013 (as originally
    scheduled) until November 4, 2013 (as completed). Knestrick asked for 84
    days from Metro but was only awarded 55 days, in part, because Knestrick
    did not request the extension within the 21-day period for such requests
    prescribed by the Construction Contract. Similarly, Knestrick did not
    challenge Metro’s award of 55 days or bring Metro into this litigation
    because it apparently wanted to keep its good business relationship with
    Metro. Unfortunately, this desire to keep a good business relationship with
    Metro should not allow Knestrick to summarily pass on all of the liquidated
    damages it sought to pass on to Air Comfort.
    The trial court nonetheless sanctioned the assessment of liquidated damages by
    Knestrick against Air Comfort. In light of the court’s own findings about Knestrick’s
    delay and the proof that Knestrick had contributed to the delay on the project and Air
    Comfort’s performance, we hold that Knestrick’s assessment of liquidated damages
    against Air Comfort was improper. Again, a party is not allowed to recover liquidated
    damages “where he is responsible for or has contributed to the delay or nonperformance
    alleged as breach.” V.L. Nicholson 
    Co., 595 S.W.2d at 484
    . Actual delay damages could
    have been pursued against Air Comfort, see Airline Constr., 
    Inc., 807 S.W.2d at 262
    , but
    the trial court’s approval of Knestrick’s assessment of liquidated damages was improper
    in light of Knestrick’s clear contribution to the delay. Moreover, case law instructs that it
    would matter not if Air Comfort had been responsible for delays that outweighed those
    occasioned by Knestrick. See 
    id. (“Although Barr
    and the trial court have both pointed
    to numerous delays that were attributable to Airline, we cannot hold the plaintiff liable
    for all the delays merely because Airline’s delays may have outweighed those occasioned
    by Barr. The law in Tennessee is contrary to this conclusion. Liquidated damages will
    not be awarded to one that has contributed to or mutually caused the delay or breach.”).
    - 13 -
    We, therefore, conclude that the evidence preponderates in favor of a finding that the
    amount owed to Air Comfort is $85,960.50. We hereby modify Air Comfort’s judgment
    against Knestrick in this amount.7
    Turning to the question of attorney’s fees, and as mentioned earlier herein,
    Knestrick’s failure to pay Air Comfort following Air Comfort’s notice of nonpayment
    makes it potentially subject to an assessment of attorney’s fees under the Prompt Pay Act.
    See Tenn. Code Ann. § 66-34-602 (providing that where payment is not made after notice
    of nonpayment, the notifying party may seek relief in chancery court, where reasonable
    attorney’s fees “may be awarded against the nonprevailing party”). Specifically, the
    statute provides that fees may be awarded if the nonprevailing party has acted in bad
    faith. Classic City Mech., Inc. v. Potter S. E., LLC, No. E2015-01890-COA-R3-CV,
    
    2016 WL 5956616
    , at *17 (Tenn. Ct. App. Oct. 14, 2016) (quoting Tenn. Code Ann. §
    66-34-602(b)). In discussing what constitutes bad faith, a previous panel of this Court
    stated as follows:
    Although a finding of bad faith is a prerequisite to an award of
    attorney’s fees under the statute, what constitutes bad faith is not statutorily
    defined. Previous courts have determined that “acts taken in bad faith
    involve knowing or reckless disregard for contractual rights or duties.”
    Madden Phillips Constr., 
    Inc., 315 S.W.3d at 829
    (citation omitted).
    Moreover, in Trinity Industries, Inc. v. McKinnon Bridge Co., Inc., 
    77 S.W.3d 159
    (Tenn. Ct. App. 2001), we affirmed a trial court’s finding that a
    company had not acted in bad faith when we concluded that we had “no
    doubt that [the company’s] principals honestly believed that their company
    did not owe the money claimed by [the plaintiff].” 
    Id. at 181.
    Id.
    On appeal, 
    Knestrick argues that attorney’s fees are improper for two reasons.
    First, it argues that it cannot have liability for attorney’s fees because it is a prevailing
    party concerning the Prompt Pay Act claim asserted. Second, it argues that certain
    7
    In addition to pursuing a contractual claim and seeking relief under the Prompt Pay Act, Air Comfort
    has advanced a separate common law conversion claim. We find no basis to disturb the trial court’s
    rejection of this claim. As one court has noted, “[a] tort action only arises when the act constituting the
    contract breach also constitutes a breach of a common law duty independent of the contractual
    relationship.” Yinghong Mach. Int’l Ltd. v. Wholesale Equip., Co., No. 2:13-cv-02671-JTF-cgc, 
    2014 WL 12887673
    , at *4 (W.D. Tenn. Oct. 17, 2014) (citing Green v. Moore, No. M2000-03035-COA-R3-CV,
    
    2001 WL 1660828
    , at *3 (Tenn. Ct. App. 2001)). Here, the alleged conversion is predicated on
    Knestrick’s failure to pay sums allegedly owed in accordance with the subcontract. Being necessarily
    founded upon a breach of contract, we are of the opinion that the claim fails. See 
    id. (dismissing conversion
    claim for failure to state a claim when the plaintiff alleged breach of contract and failed to
    show a duty separate and apart from a contractual obligation).
    - 14 -
    findings by the trial court demonstrate that it acted in good faith. We have already
    dispensed with the first argument and have concluded that the Prompt Pay Act was
    violated. Thus, attorney’s fees may be awarded if there was bad faith on the part of
    Knestrick. This requires us to confront Knestrick’s second argument concerning the trial
    court’s findings. Although the trial court appeared to dismiss Air Comfort’s claim for
    attorney’s fees on the basis that the Prompt Pay Act was not violated, the court also made
    a number of findings that pertain to the issue of Knestrick’s bad faith, or lack thereof.
    Indeed, Knestrick correctly acknowledges that the trial court held that the parties “had a
    good faith dispute.” Moreover, we observe that the court held that Knestrick’s
    withholding of money was “not wrongful” and “was accomplished in keeping with a
    claim of right provided under an enforceable contract between the parties.” Respectfully,
    based on our review of this voluminous record, we are of the opinion that the evidence
    preponderates in favor of a finding that Knestrick did act in bad faith. Indeed, acts in bad
    faith can include those that involve a “reckless disregard” for contractual rights. 
    Id. We are
    of the opinion that the evidence readily establishes such a standard here, because
    again, even though $72,000.00 in liquidated damages was assessed, Knestrick failed to
    pay for completed work under the subcontract that it acknowledged totaled $85,960.50.
    The amount withheld was thus undeniably several thousand dollars more than the
    claimed liquidated damages. At a minimum, the evidence supports a conclusion that
    Knestrick acted in reckless disregard with regard to its withholding of the difference
    between the balance of the unpaid work completed by Air Comfort and the assessed
    liquidated damages.8 In light of our determination that the Prompt Pay Act was violated
    and our conclusion that the evidence preponderates in favor of a finding that Knestrick
    acted in bad faith, we hereby remand the case to the trial court for a reconsideration of
    Air Comfort’s request for attorney’s fees. See Tenn. Code Ann. § 66-34-602(b)
    (emphasis added) (“Reasonable attorney’s fees may be awarded against the nonprevailing
    party; provided, that such nonprevailing party has acted in bad faith.”).
    Regarding the discretionary costs and attorney’s fees awarded against Air
    Comfort, we hereby reverse these awards. As to the issue of discretionary costs, which is
    governed by Rule 54.04 of the Tennessee Rules of Civil Procedure, this Court has
    previously outlined when such costs may be awarded and what factors should accompany
    a trial court’s ruling on the matter:
    A “prevailing party” may request discretionary costs, such as
    “reasonable and necessary court reporter expenses for depositions or trials,
    [and] reasonable and necessary expert witness fees for depositions (or
    stipulated reports) and for trials.” Tenn. R. Civ. P. 54.04(2). The purpose
    of     awarding      discretionary     costs    is     to    help    “make
    8
    Although Knestrick advances the argument that it could have assessed more than $72,000.00 in
    liquidated damages, we note again that it did not do so. Moreover, as mentioned earlier in this Opinion, it
    has not challenged the trial court’s determination that the liquidated damages it did assess were excessive.
    - 15 -
    the prevailing party whole,” not to punish the losing party. Owens v.
    Owens, 
    241 S.W.3d 478
    , 496–497 (Tenn.Ct.App.2007).
    When deciding whether to award discretionary costs under Rule 54.04(2),
    the trial court should:
    (1) determine whether the party requesting the costs is the
    “prevailing party,”
    (2) limit awards to the costs specifically identified in the rule,
    (3) determine whether the requested costs are necessary and reasonable, and
    (4) determine whether the prevailing party has engaged in conduct during
    the litigation that warrants depriving it of the discretionary costs to which it
    might otherwise be entitled.
    Mass. Mut. Life Ins. Co. v. Jefferson, 
    104 S.W.3d 13
    , 35–36 (Tenn. Ct.App.
    2002) (citations omitted). The burden is on the movant to convince the trial
    court that it is entitled to discretionary costs, Carpenter v. Klepper, 
    205 S.W.3d 474
    , 490 (Tenn. Ct. App. 2006); however, as a general matter,
    courts should “award discretionary costs to a prevailing party if the costs
    are reasonable and necessary and if the prevailing party has filed a timely
    and properly supported motion.” Mass. Mut. Life Ins. 
    Co., 104 S.W.3d at 35
    .
    Rule 54.04(2) costs expressly address themselves to the sound discretion of
    the trial court. Stalsworth v. Grummons, 
    36 S.W.3d 832
    , 835
    (Tenn.Ct.App.2000). Accordingly, trial courts are free to apportion the
    costs between the parties as “the equities of each case demand.” Sanders v.
    Gray, 
    989 S.W.2d 343
    , 345 (Tenn. Ct. App. 1998). Therefore, on appeal,
    this Court will not substitute our own discretion for that of the trial
    court. State ex rel. Vaughn v. Kaatrude, 
    21 S.W.3d 244
    , 248 (Tenn. Ct.
    App. 2000).
    Freeman v. CSX Transp., Inc., 
    359 S.W.3d 171
    , 179–80 (Tenn. Ct. App. 2010).
    In this case, the trial court concluded that Knestrick, not Air Comfort, was entitled
    to discretionary costs. In so ruling, the court held that Air Comfort was not a prevailing
    party and noted that it had not established a Prompt Pay Act claim. In contrast, the trial
    court concluded that Knestrick was a prevailing party. Given our previous discussion and
    the relief awarded herein in Air Comfort’s favor, we are of the opinion that Air Comfort
    should properly be considered the prevailing party as to its claims against Knestrick.
    Consequently, upon remand of this case, the trial court is directed to consider whether Air
    Comfort, as the prevailing party, is entitled to discretionary costs, provided Air Comfort
    files a new motion for discretionary costs within thirty days after the filing of the
    - 16 -
    mandate by this Court. See Tenn. R. Civ. P. 54.04(2) (“In the event an appeal results in
    the final disposition of the case, under which there is a different prevailing party than the
    prevailing party under the trial court’s judgment, the new prevailing party may request
    discretionary costs by filing a motion in the trial court, which motion shall be filed and
    served within thirty (30) days after filing of the appellate court’s mandate in the trial
    court.”).
    Also at issue is Air Comfort’s request for prejudgment interest. In denying
    prejudgment interest to Air Comfort, the trial court held as follows: “Given that
    Knestrick withheld the liquidated damages against Air Comfort under a claim of right
    under an enforceable liquidated damages provision and given that the amount of potential
    damages was not necessarily liquidated or ascertainable, the Court declines to award Air
    Comfort prejudgment interest against Knestrick.” According to Air Comfort, this ruling
    should be reversed. For the reasons that follow, we agree.
    As pointed out by Air Comfort, trial courts are authorized to award prejudgment
    interest pursuant to Tennessee Code Annotated section 47-14-123.9 Although the
    decision to make such an award is discretionary, see Story v. Lanier, 
    166 S.W.3d 167
    ,
    181 (Tenn. Ct. App. 2004) (noting that a trial court “is vested with considerable
    discretion when determining whether prejudgment interest is warranted”), a trial court’s
    action is not immunized from challenge on appeal. Indeed, “appellate deference is not
    synonymous with rubber stamping a trial court’s decision.” Scholz v. S.B. Int’l, Inc., 
    40 S.W.3d 78
    , 82 (Tenn. Ct. App. 2000).
    In discussing the relevant considerations that must be taken into account regarding
    a claim for prejudgment interest, the Tennessee Supreme Court stated as follows in Myint
    v. Allstate Insurance Co.:
    Several principles guide trial courts in exercising their discretion to
    award or deny prejudgment interest. Foremost are the principles of equity.
    Tenn. Code Ann. § 47–14–123. Simply stated, the court must decide
    whether the award of prejudgment interest is fair, given the particular
    circumstances of the case. In reaching an equitable decision, a court must
    keep in mind that the purpose of awarding the interest is to fully
    compensate a plaintiff for the loss of the use of funds to which he or she
    was legally entitled, not to penalize a defendant for wrongdoing. Mitchell v.
    Mitchell, 
    876 S.W.2d 830
    , 832 (Tenn.1994); 
    Otis, 850 S.W.2d at 446
    .
    9
    We recognize that inasmuch as we have determined that a violation of the Prompt Pay Act occurred,
    there appears to be an argument that some interest should have been awarded as a matter of right. Indeed,
    the Prompt Pay Act provides that “[a]ny payment not made in accordance with this chapter shall accrue
    interest.” Tenn. Code Ann. § 66-34-601. However, no such issue was advanced by Air Comfort, who
    limited its argument regarding interest to the interest available under Tennessee Code Annotated section
    47-14-123.
    - 17 -
    In addition to the principles of equity, two other criteria have
    emerged from Tennessee common law. The first criterion provides that
    prejudgment interest is allowed when the amount of the obligation is
    certain, or can be ascertained by a proper accounting, and the amount is not
    disputed on reasonable grounds. 
    Mitchell, 876 S.W.2d at 832
    . The second
    provides that interest is allowed when the existence of the obligation itself
    is not disputed on reasonable grounds. 
    Id. (citing Textile
    Workers Union v.
    Brookside Mills, Inc., 
    205 Tenn. 394
    , 402, 
    326 S.W.2d 671
    , 675 (1959)).
    We note that these criteria, if strictly construed, could prohibit the
    recovery of prejudgment interest in the vast majority of cases. Indeed, only
    a liquidated claim, for which prejudgment interest is already recoverable as
    a matter of right under Tenn.Code Ann. § 47–14–109, can truly be
    considered an obligation of certain and indisputable amount. Further, it is
    safe to say that, at trial, defendants usually can articulate at least one good
    reason for disputing the existence of the obligation, for were it otherwise,
    defendants would rarely survive summary judgment. Finally, the focus on
    whether the defendant had a reasonable defense ignores the principle that
    prejudgment interest is not a penalty imposed on the defendant for
    indefensible conduct.
    Not surprisingly, an analysis of relevant case law reveals that these
    criteria have not been used to deny prejudgment interest in every case
    where the defendant reasonably disputed the existence or amount of an
    obligation. More typically, courts either use the certainty of a claim as
    support for an award of prejudgment interest, or they do not discuss the
    certainty of the claim at all. See, e.g., 
    Mitchell, 876 S.W.2d at 832
    (allowing the award of interest where the existence and amount of the
    obligation under a settlement agreement were not reasonably
    disputed); 
    Otis, 850 S.W.2d at 446
    (allowing the award of interest to a
    plaintiff whose right to recover under a fire insurance contract was
    reasonably      disputed     on     the      grounds     of    arson      and
    misrepresentation); Performance Systems, Inc. v. First American Nat.
    Bank, 
    554 S.W.2d 616
    , 619 (Tenn.1977) (allowing the award of interest,
    although the existence of the defendant's obligation under the lease was
    reasonably disputed); Johnson v. Tennessee Farmers Mut. Ins. Co., 
    556 S.W.2d 750
    , 752 (Tenn.1977)(allowing the award of interest, although the
    amount of recovery under the insurance claim was reasonably
    disputed); Uhlhorn v. Keltner, 
    723 S.W.2d 131
    , 138 (Tenn.App.1986)
    (allowing award of interest in a boundary dispute case, where the existence
    of any obligation to pay rent and the amount of rent due were both
    reasonably disputed); Schoen v. J.C. Bradford & Co., 
    667 S.W.2d 97
    , 101–
    - 18 -
    02 (Tenn.App.1984)(rejecting argument that prejudgment interest should
    not be imposed when defendant appealed in good faith).
    Myint v. Allstate Ins. Co., 
    970 S.W.2d 920
    , 927–28 (Tenn. 1998) (footnote omitted).
    Whereas the Supreme Court noted that past decisions existed where interest was not
    allowed when there was a good faith dispute, the Supreme Court stated that such cases
    were overruled “[t]o the extent . . . [they] suggest[ed] that prejudgment interest can never
    be awarded when a claim is reasonably disputed.” 
    Id. at 928
    n.7.
    Writing for this Court, then Judge Koch explained the Supreme Court’s action in
    Myint as follows:
    As we construe the Myint decision, the Tennessee Supreme Court has
    shifted the balance to favor awarding prejudgment interest whenever doing
    so will more fully compensate plaintiffs for the loss of use of their funds.
    Fairness will, in almost all cases, require that a successful plaintiff be fully
    compensated by the defendant for all losses caused by the defendant,
    including the loss of use of money the plaintiff should have received. That
    is not to say that trial courts must grant prejudgment interest in absolutely
    every case. Prejudgment interest may at times be inappropriate such as (1)
    when the party seeking prejudgment interest has been so inexcusably
    dilatory in pursuing a claim that consideration of a claim based on loss of
    use of the money would have little weight; (2) when the party seeking
    prejudgment interest has unreasonably delayed the proceedings after suit
    was filed; or (3) when the party seeking prejudgment interest has already
    been otherwise compensated for the lost time value of its money.
    
    Scholz, 40 S.W.3d at 83
    (internal citations omitted).
    In light of the Supreme Court’s discussion in Myint and this Court’s discussion in
    Scholz, we conclude that the trial court’s denial of prejudgment interest to Air Comfort
    was in error. Initially, we fail to comprehend how the court concluded that “the amount
    of potential damages was not necessarily . . . ascertainable.” There was not any dispute
    that the HVAC work had been performed and completed, and further, it is clear that the
    work had a certain value under the subcontract. No doubt, Knestrick defended Air
    Comfort’s claim for damages by relying on its own assessment of liquidated damages,
    but it seems evident that the amount of damages was ascertainable upon resolution of the
    liquidated damages question. Indeed, the calculation of damages, properly implemented,
    could have been achieved by simply subtracting the amount of any permissible liquidated
    damages from the balance owed under the subcontract.
    Additionally, it appears that the trial court lost sight of the economic purpose of
    prejudgment interest. Awards of prejudgment interest are “based on the recognition that
    - 19 -
    a party is damaged by being forced to forego the use of its money over time.” 
    Id. at 82.
    Interest is awarded, not to punish a defendant, but to compensate the wronged party. 
    Id. Thus, whereas
    the bad faith, or lack thereof, of a defendant is not really the proper focal
    point, the trial court here appeared to place emphasis on this consideration, specifically
    noting as follows in its denial of prejudgment interest: “Given that Knestrick withheld
    the liquidated damages against Air Comfort under a claim of right under an enforceable
    liquidated damages provision . . . the Court declines to award Air Comfort prejudgment
    interest.” Knestrick’s own brief characterizes the court’s finding as determining that
    “Knestrick operated under a good faith claim of right.” This proffered justification is a
    significantly devalued one in light of the Myint and Scholz decisions, and here, we are of
    the opinion that it cannot properly be invoked to deny Air Comfort prejudgment interest.
    Again, “[f]airness will, in almost all cases, require that a successful plaintiff be fully
    compensated by the defendant for all losses caused by the defendant, including the loss of
    use of money the plaintiff should have received.” 
    Id. at 83.
    The trial court’s cited
    justifications do not survive scrutiny here, and there is no question that Air Comfort has
    been deprived of money that it should have received.10 We reverse the trial court’s denial
    of prejudgment interest to Air Comfort and remand the case with instructions to calculate
    and award Air Comfort the prejudgment interest to which it is entitled.
    To briefly recap, Air Comfort should be considered a prevailing party in its
    litigation against Knestrick, which, as noted, has resulted in a much higher modified
    judgment herein. The award of attorney’s fees against Air Comfort is reversed, as is the
    award of discretionary costs. The trial court is directed to reconsider Air Comfort’s
    request for attorney’s fees upon remand, and, if a new motion for discretionary costs is
    timely filed by Air Comfort, is directed to consider that issue as well. Further, as noted,
    we agree with Air Comfort that the trial court erred in denying it prejudgment interest.
    Having addressed the various questions between Air Comfort and Knestrick, we
    now turn to the points of dispute between E Solutions and Air Comfort. As noted earlier,
    the trial court awarded E Solutions a judgment in the amount of $42,847.98. While Air
    Comfort claims that the trial court erred in awarding E Solutions any judgment, E
    Solutions argues that the awarded judgment was insufficient. For the reasons that follow,
    we agree with E Solutions.
    The primary dispute between Air Comfort and E Solutions relates to Air
    Comfort’s failure to pay for the equipment it purchased from E Solutions. Testimony at
    trial revealed that the amount unpaid from certain invoices was $52,847.98, but, when
    awarding E Solutions a judgment, the trial court reduced this amount by $10,000.00 upon
    10
    Knestrick obviously disputes that Air Comfort is entitled to the full sum it has claimed, but as we have
    noted, even Knestrick has not challenged the trial court’s decision to award some type of monetary
    judgment to Air Comfort. Indeed, regarding the credit and resulting judgment afforded to Air Comfort by
    the trial court, Knestrick states as follows in its brief: “Knestrick avers that the assessment [of the credit]
    was a proper resolution . . . and should not be overturned on appeal.”
    - 20 -
    finding that E Solutions was responsible for ten days of delay on the project. In support
    of its position that no judgment should have been awarded to E Solutions, Air Comfort
    claims that E Solutions materially breached the contract between the two parties by
    failing to deliver equipment on or before December 13, 2013. We disagree. Although
    the purchase order recited a December 13, 2013 delivery date, the attached terms and
    conditions, as we have already noted, indicated that shipment dates were estimates only.
    Specifically, the terms of the contract provided that “[n]o valid contract may be made to
    ship within or at a specified time unless in writing, signed by an authorized signatory of
    Seller.” There was no evidence of any such authorization in this case. Moreover,
    testimony at trial, from representatives of both E Solutions and Air Comfort, revealed
    that there was no expectation that all equipment would be delivered by December 13.
    According to Brent Bill, account manager at E Solutions, his client waited to order
    equipment in order to align delivery of the equipment with the actual need for the
    equipment:
    I was waiting to be released by Air Comfort and I had conversations with
    [Mr. Lampley] asking when we should release that equipment.
    Part of the flow of the job, like we mentioned before, is delivering
    the equipment when it best suits them so they do not have to incur storage
    fees or transfer fees. So we were trying to provide it just in time for the
    delivery of the equipment.
    Although Mr. Lampley’s testimony was somewhat contradictory at places, it did indicate
    that Air Comfort did not expect delivery of the equipment before December 13 given the
    lead times. Thus, aside from the fact that the contract did not obligate E Solutions to
    deliver equipment on or before the claimed December 13 date, there was testimony on
    both sides evidencing a lack of expectation of any such delivery.
    Moreover, as previously stated, the contract between the two parties provided that
    E Solutions’ duty to perform was contingent upon, among other things, the “inability to
    procure materials from the usual sources of supply” and other causes beyond its
    “reasonable control.” Evidence at trial showed that when E Solutions ordered equipment,
    it ran into issues of equipment not being available. These manufacturing delays, the court
    found, were “on balance” outside of E Solutions’ control.
    In light of all the above, we find no error in the trial court’s conclusion that Air
    Comfort was responsible for paying for the equipment that E Solutions provided. We
    respectfully disagree, however, with the trial court’s decision to reduce the amount of E
    Solutions’ judgment by $10,000.00. As correctly noted by E Solutions, the trial court,
    upon stating that E Solutions was responsible for ten days of delay, essentially passed
    down to E Solutions $10,000.00 in liquidated damages that had been assessed against Air
    Comfort. We agree with E Solutions that this was error. E Solutions was not a party to
    - 21 -
    Air Comfort’s contract with Knestrick, nor did the E Solutions-Air Comfort contract
    contain a provision allowing for an assessment of liquidated damages. The damages
    assessed were not in any way foreseeable or tied to a contractual basis in the parties’
    contract. Even assuming there were delays attributable to E Solutions as the court found,
    Air Comfort did not present any proof for damages outside of what was in essence a
    liquidated damages assessment. We therefore agree with E Solutions that there was no
    basis upon which to reduce the judgment to $42,847.98. We hereby enter a modified
    judgment in favor of E Solutions against Air Comfort in the amount of $52,847.98.
    In addition to awarding E Solutions a base monetary judgment against Air
    Comfort for breach of contract, the trial court awarded E Solutions attorney’s fees and
    prejudgment interest. On appeal, Air Comfort raises a couple of specific concerns with
    respect to these awards. For the reasons that follow, we find no error on the part of the
    trial court.
    We turn first to the matter of attorney’s fees. A determination of reasonable
    attorney’s fees is a discretionary matter, and “[t]here is no fixed mathematical rule in this
    jurisdiction for determining reasonable fees.” Killingsworth v. Ted Russell Ford, Inc.,
    
    104 S.W.3d 530
    , 534 (Tenn. Ct. App. 2002). On appeal, the sole issue raised by Air
    Comfort about attorney’s fees is that the trial court, relative to a reduction of the fees
    claimed by E Solutions, estimated that the amount of fees expended in claims against
    Knestrick and Berkley were one third of the total fees claimed by E Solutions. We fail to
    discern any error by the trial court. Again, there is no fixed mathematical rule in
    determining fees, and we are of the opinion that the trial court acted appropriately in
    attempting to ascertain the amount of fees E Solutions had expended relative to its suit
    against Air Comfort, as opposed to those fees it incurred against Knestrick and Berkley.
    Moreover, we observe that the trial court took appropriate account of E Solutions’ degree
    of success when further reducing the amount of fees claimed by E Solutions. Ultimately,
    by taking these reduction factors into account, the court determined that an award of
    approximately $51,000.00 in attorney’s fees was appropriate despite an initial attorney’s
    fee claim by E Solutions of over $90,000.00. We find no abuse of discretion in the
    court’s determination that this fee was reasonable. Moreover, exercising our own
    discretion, we are of the opinion that E Solutions is entitled to additional attorney’s fees
    for pursuing its appeal against Air Comfort. The contract between these two parties
    provided that Air Comfort would be liable for all collection expenses, including
    reasonable attorney’s fees, incurred by E Solutions in attempting to collect any amount
    due. E Solutions succeeded in this Court in collecting a higher amount for the equipment
    it supplied, and we therefore remand the matter to the trial court to award E Solutions the
    reasonable attorney’s fees it incurred against Air Comfort on appeal.
    Regarding the prejudgment interest awarded to E Solutions, Air Comfort simply
    maintains that the trial court erred in determining that October 16, 2018 was the operative
    end date by which prejudgment interest should be calculated. We find no error in the
    - 22 -
    court’s conclusion. The final judgment in this case was not entered until October 16,
    2018. The court did not err in allowing prejudgment interest up until that date.
    Moreover, on remand the trial court should recalculate the award of prejudgment interest
    to take into consideration the increase in the judgment in favor of E Solutions.
    We finally turn our attention to the bond claim asserted by E Solutions. In doing
    so, we initially note that pursuant to Tennessee Code Annotated section 12-4-201 et seq.,
    the General Assembly has created provisions “to provide protection for furnishers of
    labor and material on public works because these workmen are not protected by the
    mechanics’ and materialmen’s lien laws.” Wal-Bd. Supply Co., Inc. v. Daniels, 
    629 S.W.2d 686
    , 687 (Tenn. Ct. App. 1981). These provisions “provide that no contract may
    be let for a public project until the contractor executes a bond containing provisions
    required by the statute and to the effect that he will pay for all labor and material used in
    the project.” 
    Id. As we
    have already noted, a payment bond was provided in this case in
    connection with the Centenntial Sportsplex expansion project for Metro. Knestrick was
    the principal under the bond, with Berkley serving as surety.
    As a result of E Solutions’ failure to receive payment for the equipment it
    provided for the Centennial Sportsplex expansion, E Solutions asserted a bond claim
    against Knestrick and Berkley. At trial, the proof showed that $52,847.98 was owed to E
    Solutions under unpaid invoices, and further, there was testimony from Charlene
    Leonard, one of E Solutions’ owners, establishing that E Solutions had furnished a claim
    under the payment bond. The specific notice of claim given by E Solutions was
    introduced as an exhibit at trial.
    Counsel for Knestrick and Berkley conceded at trial that the bond claim had been
    timely made, and there does not appear to be any dispute that E Solutions was not paid
    the outstanding $52,847.98 under its invoices. The trial court, however, rejected the bond
    claim and held as follows:
    The Court concludes that E Solutions is not entitled to judgment against
    Knestrick and Berkley on the bond claim because of the Court’s ruling that
    Knestrick is not liable to E Solutions and given that E Solutions’ bond
    claim is derivative; it cannot be realized unless and until Air Comfort fails
    to pay the judgment it owes to E Solutions. Alternatively, it is not clear
    from the Complaint that E Solutions was pursuing a statutory bond claim.
    As for the court’s lack of clarity about whether this case involved a statutory bond,
    we observe that the payment bond, a copy of which was attached to E Solutions’
    complaint, contains a provision expressly stating as follows:
    When this Bond has been furnished to comply with a statutory or other
    legal requirement in the location where the construction was to be
    - 23 -
    performed, any provision in this Bond conflicting with said statutory or
    legal requirement shall be deemed deleted herefrom and provisions
    conforming to such statutory or other legal requirement shall be deemed
    incorporated herein. When so furnished, the intent is that this Bond shall
    be construed as a statutory bond and not as a common law bond.
    As for the trial court’s specific conclusion that there can be no recovery on the
    bond claim until Air Comfort fails to pay the judgment it owes to E Solutions, we
    respectfully disagree. We are unaware of any such limiting requirement, and we observe
    that the statute itself simply provides that “[a]ny laborer or furnisher of labor or material
    to the contractor, or to any immediate or remote subcontractor under the contractor, may
    bring an action on the bond, and have recovery in such laborer’s or furnisher’s own
    name.” Tenn. Code Ann. § 12-4-204. Moreover, as E Solutions has illustrated in its
    appellate brief, there are a number of practical problems in holding that a bond claim is
    not available until a claimant has failed to collect from the party with whom it has
    contracted. As E Solutions argued:
    If a bond claim is not “ripe” until the claimant has failed to collect on a
    judgment against that entity it contracted with, how can the bond claimant
    also comply with the very short deadline for providing notice of the bond
    claim as required by T.C.A. § 12-4-205? If a bond claim is not “ripe” until
    the claimant has failed to collect on a judgment against that entity it
    contracted with, how can the bond claimant also comply with the six month
    statute of limitations for a bond claim set out in T.C.A. § 12-4-206?
    As it is, there is no dispute that a timely bond claim was made. Further, the proof showed
    that E Solutions was not paid $52,847.98 under its invoices. In light of the foregoing, we
    reverse the trial court on this issue and remand for the entry of a judgment allowing
    recovery on E Solutions’ bond claim including prejudgment interest and attorney’s fees.
    CONCLUSION
    For the reasons discussed above, we affirm in part, affirm in part as modified,
    reverse in part, and remand the case for such further proceedings as are necessary and
    consistent with this Opinion.
    _________________________________
    ARNOLD B. GOLDIN, JUDGE
    - 24 -