Carl Wayne Hixson v. American Towers, LLC ( 2019 )


Menu:
  •                                                                                                      11/07/2019
    IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    August 20, 2019 Session
    CARL WAYNE HIXSON ET AL. v. AMERICAN TOWERS, LLC
    Appeal from the Chancery Court for Hamilton County
    No. 16-0804       Jeffrey M. Atherton, Chancellor
    ___________________________________
    No. E2019-00335-COA-R3-CV
    ___________________________________
    Wayne Hixson and Eric Hixson (the Hixsons) granted a perpetual, exclusive easement to
    American Towers, LLC (ATC)1 to operate a telecommunications system at the top of a
    hill on their property. For many years, the hill experienced progressive slope failures. A
    recent mudslide caused thousands of dollars in property damage to the Hixsons and All
    Things Fast Motorsports, LLC (All Things Fast), a metal fabrication business owned by
    Wayne Hixson’s grandson. ATC spent thousands of dollars to move a generator away
    from the slope failure. The parties fear that the cell tower could collapse. In the trial
    court, the Hixsons and All Things Fast filed a complaint seeking a declaratory judgment
    regarding the parties’ respective maintenance responsibilities under the easement
    agreement. They also sought damages arising from ATC’s alleged breach of the
    easement agreement and other tortious conduct. ATC filed a counterclaim alleging
    similar causes of action. After a bench trial, the court ruled that ATC has a duty to
    maintain the easement and that the Hixsons have a duty to maintain the surrounding
    hillside for the benefit of ATC. Because the court found that the Hixsons and ATC were
    equally at fault for failing to prevent the recent mudslide, the court rejected their claims
    of negligence and breach of the easement agreement. However, the court awarded
    $1,245.20 to All Things Fast on its negligence claim. The court also awarded $179.99 to
    the Hixsons on their trespass claim. Finally, the court ordered the Hixsons and ATC to
    pay half of the costs necessary to stabilize the hill in accordance with the remediation
    plan proposed by the Hixsons. ATC appeals. We modify the trial court’s declaratory
    judgment, vacate the award of damages to All Things Fast, and remand for further
    proceedings. The judgment is affirmed in all other respects.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court
    Affirmed as Modified; Case Remanded
    1
    ATC was the abbreviation used in the proceedings below. From the record, it appears that ATC
    is the surviving entity of American Towers, Inc. Its parent corporation is American Towers Corporation.
    CHARLES D. SUSANO, JR., J., delivered the opinion of the court, in which THOMAS R.
    FRIERSON, II, and KENNY W. ARMSTRONG, JJ., joined.
    Marc H. Harwell, Chattanooga, Tennessee, for the appellant, American Towers, LLC.
    Andrew F. Tucker, Dayton, Tennessee, for the appellees, Carl Wayne Hixson, Michael
    Eric Hixson, and All Things Fast Motorsports, LLC.
    OPINION
    I.
    Wayne Hixson and his son, Eric Hixson, are licensed general contractors. They
    reside in Hamilton County. In 1996, the Hixsons decided to get involved in ARCA
    racing.2 They purchased real property in Soddy-Daisy and built a racecar shop. The
    racecar shop is situated at the foot of a large hill that runs along the eastern edge of the
    property.
    In February 1998, the Hixsons entered into a lease agreement with Chase
    Telecommunications, Inc. (Chase). The lease agreement gave Chase the exclusive right
    to use a portion of the hill on the Hixsons’ property to “provid[e] communication
    services.” A few months later, Specialty Constructors, Inc. (Specialty Constructors)
    constructed a cell tower and installed other related equipment on top of the hill.3 An
    access road leading to the cell tower was also constructed. From the public highway, the
    access road is steeply uphill; then, after a dogleg to the left, the access road slopes
    downhill toward the cell tower for approximately 190 yards.
    For the purposes of this appeal, it is undisputed that the builder of the cell tower
    dug approximately thirty feet into the hill and left between six and nine feet of extracted
    fill dirt on top of the hill. Excess dirt from construction of the access road was also
    placed on top of the hill or thrown over the edge. Wayne Hixson claims that he
    expressed concerns about erosion and water runoff during the initial construction of the
    cell tower. In the end, nothing was done about the fill dirt. The builder leveled off the
    hill, constructed the cell tower, and installed other related equipment. Sometime between
    1998 and 2000, ATC took over this telecommunications system by sub-lease from Chase
    or from one of its successors-in-interest.
    2
    “ARCA” stands for Automobile Racing Club of America.
    3
    Throughout this litigation, the parties repeatedly stated that Chase constructed the cell tower.
    On the last day of trial, however, ATC identified Specialty Constructors as the builder of the tower. In a
    post-trial motion, the Hixsons produced evidence that ATC later merged with OmniAmerica, Inc., the
    parent company of Specialty Constructors.
    -2-
    Eric Hixson testified that, in late 1999 or early 2000, part of the hill “broke off”
    and slid toward the racecar shop. He testified that “another mudslide” occurred in 2001.
    According to Wayne Hixson, “every time there was a big rain,” the Hixsons would “have
    mud coming down through there on the rest of [their] property[.]” According to the
    Hixsons, water flows down the access road toward the cell tower and causes erosion of
    the hill. Wayne Hixson claims that he called ATC numerous times asking for their help,
    but he did not submit those requests in writing. According to the Hixsons, ATC was not
    responsive.
    In 2003, the Hixsons attempted to take remedial action. They began constructing
    an RV garage directly below the cell tower, where the worst mudslides were occurring.
    They designed the rear wall of the RV garage to serve as a retaining wall. The Hixsons
    also installed a French drain around the perimeter of the RV garage to divert water
    runoff. The first four bays of the RV garage were completed in 2004.
    Despite these efforts, the mud kept coming. In 2007, the Hixsons constructed
    another four bays adjacent to the existing RV garage. The Hixsons testified that they
    used a “skid steer Bobcat” to remove about four feet of dirt from the area in order to build
    the second part of the garage. The Hixsons insisted that they only excavated loose dirt
    that had eroded down the hillside and that they did not dig into the toe of the hill, which,
    they said, was marked by several large boulders. Over the next few years, mud continued
    sliding down the hill and piling up behind the RV garage.
    In July 2010, the Hixsons and ATC executed an easement acquisition agreement.
    In that agreement, ATC promised to pay the Hixsons $496,500 in exchange for two
    easements: (1) a “perpetual, exclusive easement” to use the land beneath and around the
    cell tower; and (2) an “access and utility easement” to use the road leading to the cell
    tower. The Hixsons also promised to assign ATC all of their rights and obligations as
    landlords under the 1998 lease agreement. After closing, the parties recorded an
    easement agreement in the Register’s Office of Hamilton County. The easement
    agreement sets forth the parties’ rights and responsibilities in greater detail.
    In 2013, ATC received complaints from its customers about ruts in the access
    road. In response, ATC construction manager Dale Melton sent ATC field operations
    technician Curtis Utz to inspect the property. Mr. Utz testified that he had inspected the
    property once per year since 2004 and had taken about fifty photographs of the cell tower
    and access road. Mr. Melton also hired a third-party company to inspect the property.
    According to Mr. Melton, the third-party company notified him in May 2014 that the hill
    appeared to be failing. ATC claims this was its first notice of the hill failure, despite the
    Hixsons’ claims to the contrary and despite the fact that Mr. Utz had conducted annual
    inspections of the property for about a decade.
    ATC retained GEOServices, LLC (GEOServices) to perform a geotechnical
    -3-
    exploration “to characterize the subsurface conditions for the existing slope[.]” On
    August 5, 2014, GEOServices published a report of its findings and recommendations.
    The report confirmed that the hill was failing. It recommended the use of soil nails to
    stabilize the hill. Shortly thereafter, ATC asked GEOServices to provide a design for a
    soil nail remediation plan that ATC could send to potential contractors. On August 27,
    2014, GEOServices published a report of its soil nail remediation plan.
    In December 2015, Soddy-Daisy experienced an extraordinary amount of rainfall.
    According to Wayne Hixson, it rained “four or five days in a row” leading up to
    Christmas. He testified that “the total rainfall was about seven inches” and that it rained
    “about two inches” on Christmas eve. On Christmas day, the Hixsons discovered that
    there had been another mudslide. This time, a tree and “about two loads of chert”
    crashed through the roof of the RV garage. This damaged the RV garage and equipment
    owned by the Hixsons and All Things Fast. As a precaution, ATC spent about $25,000 to
    move a generator away from the slope failure. ATC also placed a tarp over part of the
    slope.
    In 2016, ATC finally got around to repairing the access road. Patrick Barry,
    ATC’s Director of Architectural Engineering, supervised this project. Mr. Barry testified
    that ATC graded the access road using crusher run, which is designed to withstand
    erosion. Mr. Barry also testified that ATC dug a ditch along the eastern side of the road
    and “pitched” the road from west to east so that water would run into the ditch. Finally,
    ATC constructed a “level spreader” at the end of the access road near the cell tower. The
    level spreader was designed to collect water from the ditch and discharge it to the east of
    the Hixsons’ property. Dr. James Smoot, a hydrologist, testified that ATC’s 2016
    improvements were properly designed to direct water away from the Hixsons’ property.
    On December 7, 2016, the Hixsons and All Things Fast filed their complaint.
    They sought: a declaratory judgment regarding the parties’ maintenance responsibilities
    under the easement agreement; $40,000 in damages arising from ATC’s alleged breach of
    the easement agreement and other tortious conduct4; punitive damages; “[a] yet
    undetermined sum to correct the erosion and water runoff issues”; attorney’s fees and
    costs; and “[a]ll other general relief deemed just and proper[.]”
    In its “Answer and Verified Counterclaim,” ATC denied responsibility for the hill
    failure and asserted a variety of defenses, including: failure to state a claim upon which
    relief can be granted; comparative fault; and “all applicable statute[s] of limitations and
    statutes of repose[.]” ATC also sought: an unspecified amount of damages arising from
    the counter-defendants’ alleged negligence and breach of the easement agreement; “an
    Order compelling the [Hixsons] to take immediate measures and corrective action to
    4
    Specifically, the Hixsons and All Things Fast alleged the following torts: negligence, trespass,
    fraudulent inducement, intentional misrepresentation, negligent misrepresentation, and nuisance.
    -4-
    provide stabilization to the slope/hillside”; attorney’s fees and costs; and “all other
    general relief deemed just and proper[.]”
    In May 2017, the court held a hearing on ATC’s request for injunctive relief. The
    court heard testimony from several witnesses and received twenty-one exhibits into
    evidence. Ultimately, the court denied ATC’s request for injunctive relief and ordered
    the parties to attend mediation. When mediation was unsuccessful, both parties filed
    motions for summary judgment. The court denied both motions and set the case for trial.
    A three-day trial took place from January 30, 2018 to February 1, 2018. The court
    heard testimony from ten witnesses, including the Hixsons, ATC representatives, and
    multiple expert witnesses. Pursuant to Tenn. R. Civ. P. 65.04(7), the court also
    considered the testimony and exhibits entered into evidence during the May 2017
    hearing. The court set forth its findings of fact and conclusions of law in a twenty-page
    memorandum opinion and order filed on August 6, 2018.
    The court “found the testimony of Wayne Hixson to be generally credible, though
    not always in the Hixsons’ favor.” On the other hand, the court found the testimony of
    Dale Melton and Patrick Berry to be “somewhat unpersuasive.” For example, the court
    disbelieved Mr. Melton’s testimony that ATC first received notice of the hill failure in
    May 2014. Instead, the court found that Curtis Utz, who conducted annual inspections of
    the property, “had almost as much of an opportunity as the Hixsons to observe the open
    and obvious erosion taking place on the hillside.”
    The court also made factual findings regarding the cause of the hill failure:
    [T]he original construction of the tower and tower pad in
    close proximity to the edge of the hill likely caused and
    contributed to the erosion. The proof at trial showed that,
    during the construction of the tower and tower pad, the
    builder dug down approximately thirty feet and left the
    extracted fill dirt on top of the hill, much of which was within
    the Easement area. This was specifically supported by the
    testimony of Mr. Hodnett, stating that the failure of [the] hill
    occurred at the top, rather than at the toe. That fill dirt has
    caused an excess of earth moving down the hill over the years
    since construction.
    Although the court found that the original construction of the cell tower led to the
    instability of the hill, the court ruled that the Hixsons and ATC were equally at fault for
    failing to properly maintain their respective areas of the property. For example, the court
    found that ATC failed “to secure the dirt next to the concrete pad and within the
    Easement” and failed “to control water on the tower pad from running down the hillside
    -5-
    above the RV Garage[.]”5 On the other hand, the court found that the Hixsons failed to
    cover the bare hillside or promote the growth of vegetation on the hill, which, according
    to Dr. Smoot, would have prevented erosion. To their credit, however, the court found
    that the Hixsons did not cut into the toe of the hill during the construction of the RV
    garage.
    The court ruled that most of the parties’ claims were without merit. Relevant to
    this appeal, the court awarded $1,245.20 to All Things Fast on its negligence claim. The
    court also awarded nominal damages to the Hixsons after finding that ATC trespassed on
    their property during ATC’s 2016 improvements to the access road. The court rejected
    ATC’s claim against the Hixsons for breach of the easement agreement. The court also
    ruled that the doctrine of comparative fault barred ATC from recovering on its negligence
    claim against the Hixsons. Finally, the court rejected ATC’s claims against All Things
    Fast because All Things Fast was not a party to the easement agreement and did not owe
    ATC a duty of care.6
    In December 2018, the court held a third hearing on the issue of remediation.
    Jimmy Mason, a general contractor, testified on behalf of the Hixsons. He recommended
    the construction of a larger retaining wall at the bottom of the hill, which he estimated
    would cost $332,480. Mr. Mason’s remediation plan had not been approved by a
    professional engineer at the time of the hearing. Derek Kilday, the Vice-President and
    Senior Geotechnical Engineer at GEOServices, testified on behalf of ATC. Mr. Kilday
    recommended the installation of soil nails at the top of the hill, which he estimated would
    cost $615,000. Mr. Kilday believed that the installation of soil nails would be much safer
    for the construction workers. However, he admitted that his remediation plan would not
    involve removal of the dirt that has piled up behind the RV garage. At the conclusion of
    the hearing, the court stated the following:
    Although less sophisticated, the testimony provided by Mr.
    Mason provides a more comprehensive approach to the
    retention of the hillside. I heard Mr. Kilday testify, and I
    even followed it up, [his] primary concern with regard to the
    poured wall approach dealt with the safety of the workers, not
    with the efficacy of the structure.
    5
    We assume the latter finding is limited to ATC’s pre-2016 conduct, because the court credited
    Dr. Smoot’s testimony that ATC’s 2016 improvements to the access road were properly designed to
    direct water away from the Hixsons’ property.
    6
    The memorandum opinion and order also states that “[a]ny matters not otherwise addressed in
    this Memorandum Opinion and Order are hereby denied and/or dismissed.” We interpret this as a denial
    of the Hixsons’ request for punitive damages and both parties’ request for attorney’s fees and costs.
    -6-
    Under the circumstances, based upon the proof presented to
    me, and we’re looking for a long term comprehensive fix,
    rather than the somewhat more narrow approach that the soil
    nails would provide, the testimony provided to the Court
    persuades this Court that the poured wall approach presented
    and suggested by Mr. Mason at the cost of $332,480 is the
    most appropriate mechanism to effect the security of this
    hillside.7
    The court ordered the Hixsons and ATC to pay half of the costs necessary to stabilize the
    hill in accordance with the remediation plan proposed by the Hixsons. ATC appealed.
    Later, upon motion of the parties, the court entered an agreed order staying enforcement
    of its judgment pending the resolution of this appeal.
    II.
    Although not stated as such, ATC raises the following issues:
    Whether the Hixsons’ claims are barred by the three-year
    statute of limitations set forth in Tenn. Code Ann. § 28-3-105.
    Whether the trial court erred by declaring that ATC has a duty
    under the easement agreement to maintain the easement on
    top of the hill.
    Whether the trial court erred by rejecting ATC’s claim against
    the Hixsons for breach of the easement agreement.
    Whether the trial court erred by rejecting ATC’s negligence
    claim against the Hixsons.
    Whether the trial court erred by awarding $1,245.20 to All
    Things Fast on its negligence claim.
    Whether the trial court erred by ordering the parties to repair
    the hill in accordance with the Hixsons’ remediation plan.
    Whether the trial court erred by ordering ATC to pay half of
    the costs necessary to implement the remediation plan.
    7
    This oral ruling was incorporated by reference in the court’s January 23, 2019 “Final Order of
    Remediation.”
    -7-
    The Hixsons raise one additional issue:
    Whether the prevailing party in this appeal is entitled to an
    award of reasonable attorney’s fees and costs.
    Although the trial court rejected most of the Hixsons’ claims, the Hixsons do not
    challenge those rulings in this appeal. Nor do the Hixsons challenge the court’s ruling
    that they must pay for half of the costs of remediation.
    III.
    This case comes to us after a bench trial. Therefore, our review of the trial court’s
    factual findings “shall be de novo upon the record” and “accompanied by a presumption
    of the correctness of the finding[s], unless the preponderance of the evidence is
    otherwise.” Tenn. R. App. P. 13(b). “For the evidence to preponderate against a trial
    court’s finding of fact, it must support another finding of fact with greater convincing
    effect.” Dorning v. Bailey, 
    223 S.W.3d 269
    , 272 (Tenn. Ct. App. 2007) (citations
    omitted). We give great weight to credibility determinations made by the trial court. 
    Id. On the
    other hand, we review questions of law de novo, without affording a presumption
    of correctness to the conclusions of the court below. 
    Id. IV. The
    first issue raised by ATC is whether the Hixsons’ claims are barred by the
    three-year statute of limitations set forth in Tenn. Code Ann. § 28-3-105. We decline to
    chase that rabbit. The trial court ruled against the Hixsons on all but one of their claims.
    Because the Hixsons are not challenging any aspect of the trial court’s decision, the
    statute-of-limitations issue is moot with respect to the Hixsons’ unsuccessful claims. The
    Hixsons were successful on their trespass claim, but ATC’s brief does not include facts or
    argument relevant to that claim. Therefore, ATC waived the statute-of-limitations
    defense with respect to that claim. See Hodge v. Craig, 
    382 S.W.3d 325
    , 335 (Tenn.
    2012) (citations omitted) (“An issue may be deemed waived, even when it has been
    specifically raised as an issue, when the brief fails to include an argument satisfying the
    requirements of Tenn. R. App. P. 27(a)(7).”).8
    V.
    The second issue raised by ATC concerns the trial court’s declaratory judgment
    regarding the parties’ maintenance responsibilities under the easement agreement. We
    8
    ATC also waived the statute-of-limitations defense with respect to All Things Fast’s negligence
    claim. See 
    Hodge, 382 S.W.3d at 335
    (“[A]n issue may be deemed waived when it is argued in the brief
    but is not designated as an issue in accordance with Tenn. R. App. P. 27(a)(4).”).
    -8-
    begin by discussing common law principles that will inform our analysis of this issue.
    Then we will turn to the easement agreement itself.
    A.
    “An easement is an interest in another’s real property that confers on the
    easement’s holder an enforceable right to use that real property for a specific purpose.”
    Shew v. Bawgus, 
    227 S.W.3d 569
    , 578 (Tenn. Ct. App. 2007) (citations omitted). “[A]n
    easement carries rights and restrictions applicable to the owner of the easement (the
    dominant estate) and the owner of the property underlying and adjoining the easement
    (the servient estate).” Rogers v. Roach, No. M2011–00794–COA–R3–CV, 
    2012 WL 2337616
    , at *8 (Tenn. Ct. App., filed June 19, 2012):
    [T]he rights of the easement owner and of the landowner are
    not absolute, irrelative, and uncontrolled, but are so limited,
    each by the other, that there may be a due and reasonable
    enjoyment of both the easement and the servient estate.
    
    Id. (quoting Carroll
    v. Belcher, No. 01A01-9802-CH-00106, 
    1999 WL 58597
    , at *1
    (Tenn. Ct. App., filed Feb. 9, 1999)). Thus, “[t]he owner of an easement cannot
    materially increase the burden of it upon the servient estate[.]” Mize v. Ownby, 
    225 S.W.2d 33
    , 35 (Tenn. 1949) (citations omitted); see also Rogers, 
    2012 WL 2337616
    , at
    *8. Likewise, “[t]he owner of the servient estate has no legal right to interfere with an
    easement holder’s enjoyment and use of the easement.” Rogers, 
    2012 WL 2337616
    , at
    *9 (citing Charles v. Latham, No. E2003-00852-COA-R3-CV, 
    2004 WL 1898261
    (Tenn. Ct. App., filed Aug. 25, 2004)); see also Cox v. East Tenn. Natural Gas Co., 
    136 S.W.3d 626
    , 628 (Tenn. Ct. App. 2003).
    Absent an agreement to the contrary, an easement holder “has both a right and the
    duty to maintain an easement so that it can be used for its granted purpose[.]” 28A C.J.S.
    Easements § 227; see also 25 Am. Jur. 2d Easements and Licenses § 72. “The owner of
    the dominant estate may do whatever is reasonably necessary to the enjoyment of the
    easement and to keep it in a proper state of repair . . . .” Hager v. George, No. M2013–
    02049–COA–R3–CV, 
    2014 WL 3371680
    , at *5 (Tenn. Ct. App., filed July 8, 2014)
    (quoting 28A C.J.S. Easements § 227). The easement holder may even “enter the
    servient estate in order to maintain, repair or protect the easement” as long as such
    maintenance is “necessary” and performed “in a reasonable manner as not to increase
    needlessly the burden of the servient estate.” 
    Id. On the
    other hand, “[t]he owner of a
    servient estate generally has no duty to maintain or repair an easement for the benefit of
    the dominant tenant in the absence of an agreement requiring it.” 28A C.J.S. Easements
    § 227; see also 25 Am. Jur. 2d Easements and Licenses § 72. Instead, the owner of the
    servient estate must simply “abstain from acts that are inconsistent with the easement.”
    28A C.J.S. Easements § 191.
    -9-
    The Supreme Court has also explained the extent to which landowners have a duty
    to provide lateral support to adjoining land. XI Properties, Inc. v. RaceTrac Petroleum,
    Inc., 
    151 S.W.3d 443
    (Tenn. 2004). “[T]he traditional common law view [is] that land in
    its natural state is entitled to lateral support from the adjoining land.” 
    Id. at 447.
    However, when “a landowner alters his land by filling, thus raising the level of the land
    above its natural state, there is no right of lateral support from adjoining landowners with
    respect to the altered portion of the land.” 
    Id. at 448.
    On the contrary,
    landowners who raise their land above the natural level are
    under a duty to “keep the dirt from encroaching upon [their]
    neighbor’s land.” . . . This duty includes, if necessary, the
    building of a retaining wall or other structure to protect the
    neighbor’s land.
    
    Id. (citations omitted);
    see also 1 Am. Jur. 2d Adjoining Landowners § 45.
    B.
    With these common law principles in mind, we now turn to the easement
    agreement itself. An easement agreement is a contract, and the interpretation of a
    contract is a question of law that we review de novo. Wood v. Metro. Gov’t of Nashville
    and Davidson Co., No. M2008-02570-COA-R3-CV, 
    2009 WL 2971052
    , at *3 (Tenn. Ct.
    App., filed Sept. 16, 2009). We strive to “interpret contracts so as to ascertain and give
    effect to the intent of the contracting parties.” Individual Healthcare Specialists, Inc. v.
    BlueCross BlueShield of Tennessee, Inc., 
    566 S.W.3d 671
    , 694 (Tenn. 2019). The
    written words of a contract are “the lodestar of contract interpretation.” 
    Id. We generally
    interpret words according to “the usual, natural, and ordinary meaning of the contractual
    language[.]” 
    Id. at 691
    (citations omitted). If the words of a contract are clear and
    unambiguous, we apply their plain meaning. 
    Id. at 691
    . However, if the words of a
    contract are ambiguous (i.e., susceptible to more than one reasonable interpretation), we
    must resort to “other rules of contract construction to determine the parties’ intent.” West
    v. Shelby Cty. Healthcare Corp., 
    459 S.W.3d 33
    , 42 (Tenn. 2014) (citing Dick Broad.
    Co., Inc. of Tenn. v. Oak Ridge FM, Inc., 
    395 S.W.3d 653
    , 659 (Tenn. 2013)). If a
    contract omits “a term that is necessary to a determination of [the parties’] rights and
    duties, a term which is reasonable may be supplied by the court.” Dick Broadcasting
    Co., Inc. of Tennessee v. Oak Ridge FM, Inc., 
    395 S.W.3d 653
    , 667-68 (Tenn. 2013)
    (quoting German v. Ford, 
    300 S.W.3d 692
    , 706 (Tenn. Ct. App. 2009)).
    The trial court ruled that Sections 6 and 11 of the easement agreement require
    ATC to maintain its exclusive easement on top of the hill. The court also ruled that
    Sections 6(a), 9(a) and 10 of the easement agreement require the Hixsons to maintain the
    surrounding hillside for the benefit of ATC. In pertinent part, those sections provide as
    - 10 -
    follows:
    6. Use of Easement Areas
    (a) Exclusive Easement. . . . At all times during the Term,
    [ATC] shall have the exclusive right to use and shall have
    free access to the Easements seven (7) days a week, twenty-
    four (24) hours a day. . . . [the Hixsons] shall not have the
    right to use the Exclusive Easement for any reason and shall
    not disturb [ATC’s] right to use the Exclusive Easement in
    any manner. . . .
    (b) Access and Utility Easement. The Access and Utility
    Easement shall be used by [ATC] . . . for ingress and egress
    from and to the Exclusive Easement, as well as the
    construction, installation, operation and maintenance of
    overhead and underground [utilities]. . . . [the Hixsons] shall
    not in any manner prevent access to, and use of, the Access
    and Utility Easement by [ATC] . . . and [the Hixsons] shall
    not utilize the Access and Utility Easement in any manner
    that interferes with [ATC’s] . . . use of such area. . . .
    *      *      *
    9. Covenants and Agreements.
    (a) [The Hixsons] represent[ ] and warrant[ ] that [they are]
    the owner[s] in fee simple of the Easements, free and clear of
    all liens and encumbrances, and that [they] alone ha[ve] full
    right to grant the Easements and assign the Lease (as defined
    in Section 25 hereof). [The Hixsons] further represent[ ] and
    warrant[ ] that [ATC] shall peaceably and quietly hold and
    enjoy the Easements during the Term without any hindrance,
    molestation or ejection by any party whomsoever.
    *      *      *
    - 11 -
    10. Non-Disturbance.
    During the Term, [the Hixsons] will not improve or grant any
    other easement, ground lease, lease license, sale or other
    similar interest of or upon the Premises if such improvement
    or interest would interfere with [ATC’s] use of the
    Easements. [ATC] and its customers are currently utilizing
    the Exclusive Easement for the purpose of transmitting and
    receiving telecommunication signals, including but not
    limited to wireless telecommunications signals.            [The
    Hixsons] and [ATC] recognize that [ATC’s] use of the
    easement rights set forth in this Agreement would be
    frustrated if the telecommunications signals were blocked, if
    an obstruction were built that would cause interference with
    such transmission, or if access and/or utilities to and from the
    Exclusive Easement were partially and/or completely
    inhibited. [The Hixsons], for [themselves], [their] successors
    and assigns, hereby agree[ ] to use [their] best efforts to
    prevent the occurrence of any of the foregoing, and shall
    promptly undertake any remedial action necessary to do so.
    [ATC] shall have the express right to seek an injunction to
    prevent any of the activity prohibited by this Section 10.
    11. Access and Utilities. To the extent not otherwise
    addressed herein . . . [the Hixsons] hereby grant[ ] and
    convey[ ] unto [ATC] . . . full, complete, uninterrupted and
    unconditional access to and from the Exclusive Easement,
    seven days a week, 24 hours a day, over and across any
    adjacent property now or hereafter owned by [the Hixsons],
    for, without limitation, ingress and egress to and from the
    Exclusive Easement, as well as the construction, installation,
    location, maintenance, relocation and repair of overhead
    and/or underground utility connections . . . provided that
    [ATC] shall repair any damages to the Premises caused by
    such access. . . .
    We respect the trial court’s effort to cobble together a coherent set of maintenance
    responsibilities from these scattered sections of the easement agreement. As we see it,
    however, the easement agreement fails to address this issue.
    First, consider sections 6 and 11. Section 6 gives ATC the exclusive right to use
    the easement area on top of the hill, but that section does not say anything about ATC’s
    duty to maintain or repair the area. At best, such a duty is implied; but in the absence of
    - 12 -
    more direct language, we find this section ambiguous. Section 11 requires ATC to
    “repair” the property, but this duty only extends to damages caused by ATC’s “ingress
    and egress to and from the Exclusive Easement, as well as the construction, installation,
    location, maintenance, relocation and repair of overhead and/or underground utility
    connections [along the access road].” The damages sustained in this case did not arise
    from such activity. For the purposes of this appeal, section 11 is irrelevant.
    Next, consider sections 6(a), 9(a), and 10. Sections 6(a) and 9(a) contain
    covenants of quiet enjoyment. In the landlord-tenant context, “[a] covenant of quiet
    enjoyment protects the lessee from any act of the lessor which destroys the quiet and
    beneficial enjoyment of the use of the property.” Couch v. Hall, 
    412 S.W.2d 635
    , 619
    (Tenn. 1969) (citations omitted). “The covenant of quiet enjoyment is breached when the
    landlord obstructs, interferes with, or takes away from the tenant in a substantial degree
    the beneficial use of the leasehold.” 49 Am. Jur. 2d Landlord and Tenant § 473. The
    parties have not cited, and we have not identified, any cases holding that a covenant of
    quiet enjoyment abrogates the common law rule that the owner of a servient estate has no
    duty to maintain his property for the benefit of an easement holder. We are also not
    aware of any cases holding that a covenant of quiet enjoyment abrogates the common law
    rule that a landowner has no duty to provide additional lateral support to adjoining land
    that has been filled or otherwise changed from its natural state.
    Finally, section 10 prohibits the Hixsons from “improv[ing] or grant[ing] any
    other easement, ground lease, lease license, sale or other similar interest of or upon the
    Premises if such improvement or interest would interfere with [ATC’s] use of the
    Easements.” According to section 10, improvements to the property could interfere with
    ATC’s use of the easement “if the telecommunications signals were blocked, if an
    obstruction were built that would cause interference with such transmission, or if access
    and/or utilities to and from the Exclusive Easement were partially and/or completely
    inhibited.” Although section 10 requires the Hixsons to use their “best efforts” to prevent
    the construction of improvements that will interfere with ATC’s use of the easement, this
    section does not speak to whether the Hixsons have a general duty to maintain the
    surrounding hillside for the benefit of ATC.
    We conclude that the easement agreement does not contain a description of the
    parties’ maintenance responsibilities. As previously discussed, if a written agreement
    omits “a term that is necessary to a determination of [the parties’] rights and duties, a
    term which is reasonable may be supplied by the court.” Dick Broadcasting Co., Inc. of
    
    Tennessee, 395 S.W.3d at 667-68
    (quoting 
    German, 300 S.W.3d at 706
    ). The authors of
    the Restatement (Third) of Property have compiled a list of supplementary terms that
    may be supplied by the court when an easement agreement omits a term necessary to a
    determination of the parties’ rights and duties. According to the Restatement,
    [u]nless the terms of a servitude . . . provide otherwise, duties
    - 13 -
    to repair and maintain the servient estate and the
    improvements used in the enjoyment of a servitude are as
    follows:
    (1) The beneficiary of an easement or profit has a duty to the
    holder of the servient estate to repair and maintain the
    portions of the servient estate and the improvements used in
    the enjoyment of the servitude that are under the beneficiary’s
    control, to the extent necessary to
    (a) prevent unreasonable interference                with    the
    enjoyment of the servient estate, or
    (b) avoid liability of the servient-estate owner to third
    parties.
    (2) Except as required by § 4.9,[9] the holder of the servient
    estate has no duty to the beneficiary of an easement or profit
    to repair or maintain the servient estate or the improvements
    used in the enjoyment of the easement or profit. . . .
    Rest. (Third) of Property: Servitudes § 4.13 (2000).
    These supplementary terms are consistent with the common law principles
    discussed in Part V(A) of this opinion. Absent an agreement to the contrary, an easement
    holder has the duty to maintain the easement so that the easement may be used for its
    intended purpose. 28A C.J.S. Easements § 227; see also 25 Am. Jur. 2d Easements and
    Licenses § 72. When reasonably necessary, the easement holder may also enter the
    servient estate to make repairs. Hager, 
    2014 WL 3371680
    , at *5. The owner of the
    servient estate generally has no duty to maintain the servient estate for the benefit of the
    easement holder; he must simply refrain from unreasonable interference with the
    easement holder’s use of the easement. Rogers, 
    2012 WL 2337616
    , at *9; 28A C.J.S.
    Easements §§ 191, 227; 25 Am. Jur. 2d Easements and Licenses § 72.
    Because the easement agreement does not directly address the parties’
    maintenance responsibilities, we hold that the supplementary terms set forth in the
    Restatement (Third) of Property: Servitudes § 4.13 are reasonable and should be supplied
    by law. Therefore, we modify the trial court’s declaratory judgment regarding the
    parties’ maintenance responsibilities. Specifically, we hold that: (1) ATC has a duty to
    9
    Section 4.9 provides that “the holder of the servient estate is entitled to make any use of the
    servient estate that does not unreasonably interfere with enjoyment of the servitude.” Rest. (Third) of
    Property: Servitudes § 4.9 (2000).
    - 14 -
    maintain the easement on top of the hill; and (2) the Hixsons do not have a duty to
    maintain the surrounding hillside for the benefit of ATC.
    Although it is not clear whether the Supreme Court would extend its lateral
    support jurisprudence to disputes between a landowner and an adjoining easement holder,
    we would reach the same result under those rules. The hill on the Hixsons’ property
    became unstable after ATC’s predecessor-in-interest “alter[ed] [the hill] by filling, thus
    raising the level of the land above its natural state.” XI Properties, 
    Inc., 151 S.W.3d at 448
    . Thus, the Hixsons would not have a duty to provide additional lateral support. See
    
    id. Instead, ATC,
    as the successor-in-interest, would have “a duty to ‘keep dirt from
    encroaching upon [the Hixsons’] land.’ ” See 
    id. VI. Next,
    we will consider whether the trial court erred by rejecting ATC’s breach of
    contract claim against the Hixsons. In order to prevail on a breach of contract claim, a
    plaintiff must prove “the existence of a valid and enforceable contract, a deficiency in the
    performance amounting to a breach, and damages caused by the breach.” Fed. Ins. Co.
    v. Winters, 
    354 S.W.3d 287
    , 291 (Tenn. 2011).
    It is undisputed that the easement agreement functions as a contract. ATC also
    presented uncontradicted evidence that it incurred “around $25,000” in damages as a
    result of moving its generator away from the slope failure. Therefore, the only issue is
    whether the Hixsons’ actions constitute “a deficiency in the performance amounting to a
    breach [of the easement agreement].” 
    Id. In ATC’s
    counterclaim, ATC alleged that the Hixsons breached Sections 9 and 10
    of the easement agreement by digging into the toe of the hill when they constructed the
    RV garage. At trial, ATC argued that the Hixsons also breached the easement agreement
    in other ways.10 For example, ATC argued that the Hixsons breached their implied duty
    of good faith and fair dealing by failing to disclose the erosion of the hillside prior to the
    parties’ execution of the easement agreement. ATC also argued that the Hixsons
    breached Sections 9 and 10 of the easement agreement by failing to cover or promote the
    growth of vegetation on the surrounding hillside, which, according to Dr. Smoot, would
    have prevented further erosion. Finally, ATC claimed that Section 25 of the easement
    10
    The Hixsons failed to object to this variance in the proof and pleadings in the trial court.
    Therefore, the issue is waived. Wheeler v. City of Maryville, 
    203 S.W.2d 924
    , 926 (Tenn. 1947); Tolliver
    v. Tellico Village Property Owners Ass’n, Inc., 
    579 S.W.3d 8
    , 26 (Tenn. 2019) (“[A] trial court may
    exclude proof of an issue not fairly within the scope of the pleadings upon the objection of the adverse
    party.”); American Trust & Banking Co. v. Parsons, 
    108 S.W.2d 187
    , 189 (Tenn. Ct. App. 1937) (“[A]
    variance between the pleadings and proof is not available upon appeal unless the variance is specifically
    pointed out at the trial . . . .”).
    - 15 -
    agreement requires the Hixsons to indemnify ATC for the damages it sustained. All of
    ATC’s arguments are without merit.
    First, the Hixsons did not breach their implied duty of good faith and fair dealing.
    Wayne Hixson testified that he informed ATC about the condition of the hill on
    numerous occasions. The court found his testimony credible. We see no reason to
    disturb that credibility determination. The court also found that ATC had notice of the
    hill failure from the annual inspections conducted by Mr. Utz. The evidence
    preponderates in favor of that finding. Accordingly, we agree with the trial court that the
    Hixsons did not breach their implied duty of good faith and fair dealing by failing to
    disclose the condition of the hill prior to the execution of the easement agreement.
    Second, the Hixsons’ construction of the RV garage does not constitute a breach
    of the easement agreement. The Hixsons completed construction of the RV garage in
    2007. The easement agreement was not executed until 2010. It is absurd to suggest that
    the Hixsons breached the easement agreement before it existed. Additionally, the
    evidence in the record preponderates in favor of the trial court’s finding that the Hixsons
    did not cut into the toe of the hill. Derek Hodnett, a professional engineer, testified that if
    the Hixsons had cut into the toe of the hill, the retaining wall would have failed or the RV
    garage would have shifted. The court found Mr. Hodnett’s testimony credible, and we
    decline to disturb that credibility determination.
    Third, the Hixsons did not breach the easement agreement by failing to cover or
    promote the growth of vegetation on the surrounding hillside. As explained in Part V(B)
    of this opinion, the Hixsons did not have a duty under the easement agreement to
    maintain the servient estate for the benefit of ATC.
    Lastly, ATC is not entitled to damages pursuant to Section 25 of the easement
    agreement. ATC argues that it is entitled to damages based on the following indemnity
    clause:
    [The Hixsons] agree[ ] to indemnify and agrees to hold
    [ATC] harmless with respect to any demands, claims, actions,
    causes of action, assessments, expenses, costs, damages,
    losses, and liabilities (including reasonable attorneys’ fees
    and costs) under the Lease which relate to costs or actions
    first arising on or before the date of this Agreement.
    (Emphasis added.) This is a red herring. Put aside the question of whether ATC’s claim
    arose “on or before” the execution of the easement agreement. Section 25 concerns the
    Hixsons’ assignment of their rights and obligations as landlords under the 1998 lease
    agreement. By its own terms, the indemnity clause cited above only applies to claims
    arising “under the Lease.” Importantly, ATC’s counterclaim is based on the Hixsons’
    - 16 -
    alleged breach of the easement agreement, not the lease agreement. For the purposes of
    this appeal, section 25 is irrelevant.
    For all of the foregoing reasons, we affirm the trial court’s ruling that ATC is not
    entitled to damages on its claim for breach of the easement agreement.
    VII.
    Now we consider whether the trial court erred by rejecting ATC’s negligence
    claim against the Hixsons.
    In order to establish a prima facie claim of negligence . . . a
    plaintiff must establish the following essential elements: “(1)
    a duty of care owed by defendant to plaintiff; (2) conduct
    below the applicable standard of care that amounts to a
    breach of that duty; (3) an injury or loss; (4) cause in fact; and
    (5) proximate, or legal, cause.” McCall v. Wilder, 
    913 S.W.2d 150
    , 153 (Tenn. 1995); see also Naifeh v. Valley
    Forge Life Ins. Co., 
    204 S.W.3d 758
    , 771 (Tenn. 2006).
    Giggers v. Memphis Housing Auth., 
    277 S.W.3d 359
    , 364 (Tenn. 2009).
    “[D]uty . . . is the legal obligation of a defendant to conform to a reasonable
    person’s standard of care in order to protect against unreasonable risks of harm.” 
    Id. (citations omitted).
    We have already explained the scope of the Hixsons’ duty of care
    under the common law. As the owners of the servient state, the Hixsons have the right to
    use their property in any manner that does not “unreasonably interfere” with ATC’s use
    of the easement. See Cox v. East Tenn. Natural Gas Co., 
    136 S.W.3d 626
    , 628 (Tenn.
    Ct. App. 2003). The Hixsons do not have an affirmative duty to maintain the servient
    estate for the benefit of ATC. 28A C.J.S. Easements § 227; 25 Am. Jur. 2d Easements
    and Licenses § 72; see also XI Properties, 
    Inc., 151 S.W.3d at 448
    (“[When] a
    landowner alters his land by filling, thus raising the level of the land above its natural
    state, there is no right of lateral support from adjoining landowners with respect to the
    altered portion of the land.”); 1 Am. Jur. 2d Adjoining Landowners § 45. Because the
    Hixsons did not have a duty to maintain the hillside for the benefit of ATC, we affirm the
    trial court’s conclusion that ATC is not entitled to damages on its negligence claim.
    VIII.
    Next we consider whether the trial court erred by awarding $1,245.20 to All
    Things Fast on its negligence claim against ATC. Although not clearly articulated by the
    parties or the trial court, All Things Fast’s negligence claim is a premises liability action.
    In order to prevail on a premises liability claim, the plaintiff
    - 17 -
    must prove the elements of a negligence claim, and in
    addition, must prove either that “the condition was caused or
    created by the owner, operator, or his agent,” or “if the
    condition was created by someone other than the owner,
    operator, or his agent, that the owner or operator had actual or
    constructive notice that the condition existed prior to the
    accident.”
    Parker v. Holiday Hospitality Franchising, Inc., 
    446 S.W.3d 341
    , 350 (Tenn. 2014)
    (emphasis in original) (footnote omitted) (quoting Blair v. West Town Mall, 
    130 S.W.3d 761
    , 764 (Tenn. 2004)).
    In premises liability cases, the owner or possessor of land has a duty “to exercise
    due care under all the circumstances.” 
    Id. (citing Blair
    v. West Town Mall, 
    130 S.W.3d 761
    , 764 (Tenn. 2004)). This duty includes “the responsibility of either removing, or
    warning against, any dangerous condition on the premises of which the property owner is
    actually aware or should be aware through the exercise of reasonable diligence.” 
    Parker, 446 S.W.3d at 350
    (quoting Eaton v. McLain, 
    891 S.W.2d 587
    , 594 (Tenn. 1994)).
    Owners and possessors of property must exercise this same standard of care with regard
    to persons off the premises when the foreseeability and gravity of harm outweigh the
    burden imposed by engaging in safer, alternative conduct. See Hale v. Ostrow, 
    166 S.W.3d 713
    , 716-18 (Tenn. 2005); Howell v. Nelson Gray Enters., No. E2019-00033-
    COA-R3-CV, 
    2019 WL 4127393
    , at *4 (Tenn. Ct. App., filed Aug. 30, 2019); Estes v.
    Peels, No. E1999-00582-COA-R3-CV, 
    2000 WL 1424808
    , at *5-7 (Tenn. Ct. App., filed
    Sept. 21, 2000); De Ark v. Nashville Stone Setting Corp., 
    279 S.W.2d 518
    , 521 (Tenn.
    Ct. App. 1955).
    Here, ATC owed a duty of reasonable care toward All Things Fast. It was
    extremely foreseeable that a major mudslide would cause significant damage to the RV
    garage where the Hixsons and All Things Fast stored their equipment. These factors
    outweighed ATC’s burden of taking steps to remedy the erosion and water runoff issues.
    ATC breached this duty by failing to take such action until after the December 2015
    mudslide. And, as previously explained, the evidence preponderates in favor of the trial
    court’s finding that the excess fill dirt and water runoff issues were the actual and
    proximate cause of the hill failure. It is undisputed that All Things Fast suffered
    $2,490.41 in damages. Finally, although the dangerous condition of the hill was created
    by someone other than ATC, the evidence preponderates in favor of the trial court’s
    finding that ATC “had actual or constructive notice that the condition existed prior to the
    accident.” 
    Parker, 446 S.W.3d at 350
    . Thus, all of the elements of a premises liability
    action are present.
    In its answer, ATC asserted the defense of comparative fault by alleging
    - 18 -
    wrongdoing on the part of the Hixsons, All Things Fast, and the original builder of the
    cell tower.11 The trial court found that the Hixsons and ATC were equally at fault for the
    December 2015 mudslide, but the court did not allocate any fault to the builder of the cell
    tower or All Things Fast. Because the court found that ATC was fifty percent at fault,
    the court ordered ATC to pay All Things Fast fifty percent of its damages – that is,
    $1,245.20.
    Our review of the trial court’s allocation of fault is de novo with a presumption of
    correctness, unless the evidence preponderates otherwise. Lindgren v. City of Johnson
    City, 
    88 S.W.3d 581
    , 584 (Tenn. Ct. App. 2002) (citing Tenn. R. App. P. 13(d); Cross v.
    City of Memphis, 
    20 S.W.3d 642
    (Tenn. 2000)). Under Tennessee’s system of modified
    comparative fault, the trier of fact “should first determine the total amount of the
    plaintiff’s damages without regard to fault, and then apportion damages on the percentage
    of fault attributable to each tortfeasor.” 
    Id. at 585
    (citing Grandstaff v. Hawks, 
    36 S.W.3d 482
    (Tenn. Ct. App. 2000)). Importantly, the trier of fact may allocate fault “to
    all persons involved in an injury-causing event[,]” including non-parties. Carroll v.
    Whitney, 
    29 S.W.3d 14
    , 21 (Tenn. 2000) (emphasis added) (footnote omitted). This
    includes non-parties that are shielded from liability by a statute of repose. Dotson v.
    Blake, 
    29 S.W.3d 26
    , 29 (Tenn. 2000) (“[T]he trier of fact should be allowed to consider
    the fault of a tortfeasor who is protected from liability due to a statute of repose.”). “[I]n
    cases of multiple tortfeasors, [the] plaintiff will be entitled to recover so long as [the]
    plaintiff’s fault is less than the combined fault of all tortfeasors.” McIntyre v. Balentine,
    
    833 S.W.2d 52
    , 58 (Tenn. 1992).
    In this case, the trial court’s own factual findings do not support the court’s
    allocation of fault. For example, the court found that “the original construction of the
    tower and tower pad in close proximity to the edge of the hill likely caused and
    contributed to the erosion.” Yet, the court did not allocate any fault to Specialty
    Constructors. It is immaterial that Specialty Constructors was not a party to this suit or
    that Specialty Constructors may be shielded from liability by the construction statute of
    repose. See 
    Dotson, 29 S.W.3d at 29
    ; 
    Carroll, 29 S.W.3d at 21
    . The court also failed to
    allocate fault to All Things Fast, despite finding that All Things Fast stored its equipment
    in close proximity to an “open and obvious” danger. See Allen v. Sulcer, 
    255 S.W.3d 51
    ,
    59 (Tenn. Ct. App. 2007) (citing Coln v. City of Savannah, 
    966 S.W.2d 34
    , 43 (Tenn.
    1998), overruled on other grounds by Cross v. City of Memphis, 
    20 S.W.3d 642
    (Tenn.
    2000)) (“If an application of the balancing test yields a duty of care on the part of the
    defendant, the facts supporting an open and obvious risk of danger remain relevant to the
    comparative fault analysis.”). Finally, the court erred by finding the Hixsons fifty percent
    11
    Although ATC did not identify Specialty Constructors as the builder, ATC alleged, “[u]pon
    information and belief, [that] Chase Telecommunications, Inc., or a company retained by Chase
    Telecommunications, Inc., designed and constructed all parts of the Easement at issue in this case[.]”
    (Emphasis added.)
    - 19 -
    at fault. As explained in Part V(B) of this opinion, it was ATC’s responsibility to
    maintain its exclusive easement to the extent necessary to “avoid liability of the servient-
    estate owner to third parties.” Rest. (Third) of Property: Servitudes § 4.13 (2000)
    (emphasis added).
    We affirm the trial court’s conclusion that ATC negligently maintained its
    easement to the detriment of All Things Fast; however, we vacate the trial court’s award
    of damages to All Things Fast. On remand, and without hearing further proof, the trial
    court should determine the percentage of fault attributable to ATC, Specialty
    Constructors, and All Things Fast. In making that determination, the court should
    consider “all the circumstances of the case,” including, but not limited to, the factors
    discussed in Eaton v. McLain, 
    891 S.W.2d 587
    , 592 (Tenn. 1994). If All Things Fast’s
    percentage of fault is less than the combined fault of all the tortfeasors, then the court
    shall order ATC to pay All Things Fast damages in direct proportion to ATC’s
    percentage of fault.
    IX.
    The next issue is whether the trial court erred by ordering the parties to repair the
    hill in accordance with the remediation plan proposed by the Hixsons. A trial court has
    discretion to fashion an appropriate equitable remedy given the particular circumstances
    of each case. E.g., Winquist v. Goodwin, No. E2009–02597–COA–R3–CV, 
    2010 WL 4272703
    , at *3 (Tenn. Ct. App., filed Oct. 28, 2010); Morrow v. Jones, 
    165 S.W.3d 254
    ,
    258 (Tenn. Ct. App. 2004).
    A court abuses its discretion when it causes an injustice to the
    party challenging the decision by (1) applying an incorrect
    legal standard, (2) reaching an illogical or unreasonable
    decision, or (3) basing its decision on a clearly erroneous
    assessment of the evidence.
    “If a discretionary decision is within a range of acceptable alternatives, we will not
    substitute our judgment for that of the trial court simply because we may have chosen a
    different alternative.” Patty v. Lane, No. E2012–01787–COA–R3–CV, 
    2013 WL 3421928
    , at *5 (Tenn. Ct. App., filed July 3, 2013) (citing White v. Vanderbilt Univ., 
    21 S.W.3d 215
    , 223 (Tenn. Ct. App. 1999)).
    Here, the trial court was presented with two potential remediation plans. Jimmy
    Mason, a licensed general contractor, recommended the construction of a larger retaining
    wall at the bottom of the hill, which he estimated would cost $332,480. Mr. Mason made
    this recommendation after observing the Hixsons’ property and consulting with a
    professional engineer. He did not have access to prior slope stability studies. At the time
    of the December 2018 hearing, Mr. Mason had not obtained design drawings from a
    - 20 -
    professional engineer.
    Derek Kilday, a professional engineer at GEOSerivices, testified that “a concrete
    wall could be installed” but that “until fully analyzed, any costs associated with said wall
    means nothing essentially.” Mr. Kilday also testified that he was “primarily concerned
    about [the] safety of workers at the bottom of the slope.” Instead of a retaining wall, Mr.
    Kilday recommended the installation of soil nails at the top of the hill. Mr. Kilday claims
    that this approach is much safer for the construction workers. The estimated cost of this
    remediation plan is $615,000. Mr. Kilday testified that his plan would not involve
    excavation of the excess fill dirt that has already eroded down the hill and piled up
    around the RV garage.
    The trial court ultimately ordered the parties to repair the hill in accordance with
    Mr. Mason’s remediation plan. The court observed that Mr. Mason’s plan was “less
    sophisticated” but “more comprehensive” in nature because it would involve the
    excavation of the dirt presently surrounding the RV garage. The court also noted the
    significantly lower price of this plan. Finally, the court observed that Mr. Kilday’s
    concern with the retaining wall was the safety of the construction workers and not the
    efficacy of the structure.
    Both remediation plans presented to the trial court have their advantages and
    disadvantages. As the trial court observed, the Hixsons’ proposed plan is more
    preliminary in nature, but it is cheaper and more comprehensive. ATC’s proposed plan
    has already been approved by a professional engineer, but it is more expensive and fails
    to address the excess dirt surrounding the RV garage. It is unclear which plan would be
    safer for construction workers. Mr. Mason testified that his plan could be executed
    safely. Mr. Kilday disagrees and thinks soil nails are safer. However, Patrick Barry, an
    ATC engineer, testified in a deposition that ATC previously ruled out a soil nail
    remediation plan because he believes the use of soil nails is unsafe in this context.
    Because we think that both proposals are “within a range of acceptable
    alternatives, we will not substitute our judgment for that of the trial court simply because
    we may have chosen a different alternative.” See Patty v. Lane, 
    2013 WL 3421928
    , at
    *5. We hold that the trial court did not abuse its discretion when it ordered the parties to
    repair the hill in accordance with the plan remediation plan proposed by the Hixsons.
    X.
    The last issue raised by ATC is whether the trial court erred when it ordered ATC
    to pay for half of the costs necessary to implement the remediation plan. Given our
    holding that ATC has a duty to maintain the easement and that the Hixsons do not have a
    duty to maintain the surrounding hillside for the benefit of ATC, it follows that ATC
    should bear the entire cost of remediating the hill. The Hixsons, however, are not asking
    - 21 -
    this Court to shift the entire cost of remediation to ATC. Instead, the Hixsons ask us to
    affirm the trial court’s ruling that the parties should each pay half of the costs necessary
    to implement the Hixsons’ proposed remediation plan. We will do just that and no more.
    See Tenn. R. App. P. 36(a) (“Nothing in this rule shall be construed as requiring relief be
    granted to a party responsible for an error or who failed to take whatever action was
    reasonably available to prevent or nullify the harmful effect of an error.”).
    XI.
    Finally, the Hixsons ask us to consider whether the prevailing party is entitled to
    an award of reasonable attorney’s fees and costs resulting from this appeal. Tennessee
    courts follow the “American-Rule,” which provides that
    a party in a civil action may recover attorney’s fees only if:
    (1) a contractual or statutory provision creates a right to
    recover attorney’s fees; or (2) some other recognized
    exception to the American Rule applies, allowing for
    recovery of such fees in a particular case.
    Eberbach v. Eberbach, 
    535 S.W.3d 467
    , 474 (Tenn. 2017) (quoting Cracker Barrel Old
    Country Store, Inc. v. Epperson, 
    284 S.W.3d 303
    , 308 (Tenn. 2009)).
    In this case, section 21 of the easement agreement contains a provision regarding
    attorney’s fees:
    If there is any legal action or proceeding between Grantor or
    Grantee arising from or based on this Agreement, the
    unsuccessful party to such action or proceeding shall pay to
    the prevailing party all costs and expenses, including
    reasonable attorney’s fees and disbursements incurred by
    such prevailing party in such action or proceeding and in any
    appeal in connection therewith. If such prevailing party
    recovers a judgment in any such action, proceeding or appeal,
    such costs, expenses and attorney’s fees and disbursements
    shall be included in and as a part of such judgment.
    We find this provision of the easement agreement clear and unambiguous.
    Because the Hixsons are the prevailing parties in this appeal, we hold that ATC is
    required to pay all costs and expenses, including reasonable attorney’s fees, incurred by
    the Hixsons as a result of this appeal. However, neither the Hixsons nor ATC were
    “prevailing parties” in the trial court; therefore, the parties shall pay their own attorney’s
    fees incurred during the proceedings below.
    - 22 -
    XII.
    In conclusion, we modify the trial court’s declaratory judgment, vacate the award
    of damages to All Things Fast, and remand for further proceedings consistent with this
    opinion. The judgment is affirmed in all other respects. Pursuant to section 21 of the
    easement agreement, costs on appeal (including reasonable attorney’s fees) are taxed to
    the appellant, ATC.
    _______________________________
    CHARLES D. SUSANO, JR., JUDGE
    - 23 -