Micah Noelle Lewellen v. Covenant Health ( 2015 )


Menu:
  •                IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    April 13, 2015 Session
    MICAH NOELLE LEWELLEN, ET AL. v. COVENANT HEALTH, ET AL.
    Appeal from the Circuit Court for Anderson County
    No. B4LA0018      Donald R. Elledge, Judge
    No. E2014-01410-COA-R3-CV-FILED-JUNE 9, 2015
    This appeal arises from a construction negligence case. Micah Noelle Lewellen,
    individually, and, Cale Ryan Lewellen, a minor by Micah Noelle Lewellen (“Plaintiffs”),
    sued Covenant Health, Rentenbach Engineering Company, and TEG Architects, LLC,
    (“Defendants,” collectively) in the Circuit Court for Anderson County (“the Trial
    Court”). Plaintiffs alleged that the absence of shielding in a portion of the radiology
    facilities in the new emergency department at Methodist Hospital caused Plaintiffs to
    suffer damages from excessive radiation exposure. Defendants filed motions for
    summary judgment asserting the statute of repose, Tenn. Code Ann. § 28-3-202 (2000),
    as a complete defense. The Trial Court granted Defendants‟ motions for summary
    judgment. Plaintiffs appeal to this Court arguing, in part, that the statute of repose did
    not run because the absence of the required shielding in the radiology facilities meant the
    project was not substantially completed on the date as found by the Trial Court. We hold,
    inter alia, that the radiology facilities, while perhaps defective, were used for their
    intended purpose and were substantially complete as found by the Trial Court. The
    construction statute of repose expired and serves to defeat Plaintiffs‟ claims. We affirm
    the Trial Court.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court Affirmed;
    Case Remanded
    D. MICHAEL SWINEY, J., delivered the opinion of the court, in which JOHN W.
    MCCLARTY and THOMAS R. FRIERSON, II, JJ., joined.
    John D. Agee, Clinton, Tennessee, for the appellants, Micah Noelle Lewellen,
    individually and Cale Ryan Lewellen, a minor by Micah Noelle Lewellen.
    F. Michael Fitzpatrick and Rachel Park Hurt, Knoxville, Tennessee, for the appellee,
    Covenant Health.
    Howard E. Jarvis, Dean T. Howell, and April A. Carr, Knoxville, Tennessee, for the
    appellee, Rentenbach Engineering Company.
    R. Loy Waldrop, Jr., W. Paul Whitt, and Janet S. Hayes, Knoxville, Tennessee, for the
    appellee, TEG Architects, LLC.
    OPINION
    Background
    The background facts of this case are relatively straightforward. Plaintiffs,
    along with several other similarly situated parties, filed a complaint in January 2014
    against Defendants alleging that they were exposed to excessive radiation from the
    radiology facilities at Methodist Hospital. Defendants were involved with the
    construction project at Methodist Hospital, including the radiology facilities, in some
    capacity. Micah Noelle Lewellen alleged that portions of walls lacked the necessary lead
    shielding, and that this defect led to her and her gestating child‟s exposure to excessive
    radiation while she worked at the hospital. Defendants filed answers in opposition.
    Certain of Defendants raised comparative fault against Methodist Medical Center of Oak
    Ridge (“MMC”), or, alternatively, that Covenant Health owned the facilities. Defendants
    later filed motions for summary judgment in which they asserted that the construction
    statute of repose was a complete defense. Plaintiffs filed a Motion for Leave to File
    Amended Complaint and Motion to Quash Notices of Hearing. Plaintiffs sought to add
    MMC as a Defendant to the complaint. The Trial Court granted Plaintiffs‟ Motion to
    Quash, allowing additional time to take discovery on the issues of substantial completion
    and the statute of repose.
    In June 2014, the Trial Court heard Defendants‟ motions for summary
    judgment as well as Plaintiffs‟ motion to add MMC as a party. The Trial Court granted
    Defendants‟ motions for summary judgment and denied Plaintiffs‟ Motion to Amend.
    The Trial Court incorporated its oral ruling into its order, which we quote from:
    We‟re here today on the case of Michael Phillips, Case No.
    B4LA0014, Connie Raby, B4LA0015, Mary Ridenour, et al., B4LA0016,
    Keith Gillis, B4LA0017, and Micah Lewellen, et al., B4LA0018, all versus
    Covenant Health, Rentenbach Engineering, doing business as Rentenbach
    Constructors, Inc., and TEG Architects, LLC.
    We‟re here as a result of a motion for summary judgment being filed
    under Rule 56 and, would advise counsel, under Rule TCA 20-16-101,
    which basically reversed the finding in Hanna[n] vs. Alltel, where the
    -2-
    parties who do not bear the burden of proof, it reversed - - it went from
    putting it on - - or reversing it to trial. And I was a part of that. Martin vs.
    Southern Railroad and Hanna[n] vs. Alltel were both debated on the floor.
    But it takes us back to what it was before Hanna[n] vs. Alltel. It‟s back to
    “put up or shut up.” That‟s the language that‟s used in the discussion.
    It is uncontroverted that litigation in each of these cases was filed on
    or about January 13, 2014, or thereafter. It is uncontroverted that in each of
    these litigations, specifically in paragraph 9, that the emergency department
    was substantially completed and opened in February of 2006.
    I read the complaint again twice yesterday, and nowhere in the
    complaint could I find any allegation of fraud or wrongful concealment. It
    is undisputed that this is a construction lawsuit, and when you read the
    allegations set out in the complaint, it‟s a construction lawsuit. It‟s an
    errors and omissions lawsuit, where one panel of lead-lined Sheetrock was
    left out of the x-ray room.
    And it‟s uncontroverted and undisputed that the imaging center was
    substantially complete to the point of making it available for its intended
    use as an emergency room no later than March 23, 2006. That‟s the
    affidavit of Anthony Pettitt that attached the Certificate of Compliance
    under Exhibit A. It‟s undisputed that the code enforcement supervisor,
    Danny Boss, for the City of Oak Ridge issued a use permit for the
    emergency room on or about April 4, 2006. But, factually, the emergency
    room was in fact being used at the end of March through December of
    2013, at which time the lead-lined wall was then constructed. December
    2013, they added lead shielding that was omitted. That‟s in the deposition
    of David Newman, page 11, line 3 through 6, page 15, line 5 through 9.
    I have read the report of Roy Osborne. I find that that report and
    several of the items submitted by Plaintiff in response to the statement of
    facts and their allegations of additional statements of facts do not comply
    with Tennessee Rules of Civil Procedure 56.06. But even taking into
    consideration Roy Osborne‟s report, it does not set out and does not
    mention the absence of any lead-lined wall or knowledge - - and that‟s
    important, knowledge - - that the lead-lined wall was not appropriately
    built. To the contrary, it said it had adequate lead-lined shielding. So even
    if I took it into consideration, it doesn‟t rise to the effect of fraud or
    concealment, which hasn‟t been pled.
    -3-
    We‟re here on the statute of repose, and I‟ll remind counsel, and it
    becomes a part of my ruling today, that under 28-3-201 under
    “Definitions,” “Substantial completion means that degree of completion of
    a project, improvement, or a specified area or portion thereof (in
    accordance with the contract documents, as modified by any change orders
    agreed to by the parties) upon attainment of which the owner can use the
    same for the purpose for which it was intended.” It also says, “The date of
    substantial completion may be established by written agreement between
    the contractor and owner.”
    We had a notification, pursuant to the statute, that was filed and is
    considered by the Court a notice of substantial completion on March 23,
    2006, between the contractor and the owner. We had the fact that from
    March of 2006 till December of 2013, it was used for the purpose for which
    it was intended. It was an x-ray room, it was a CT room, and that‟s what it
    was used for.
    Then we look at “Limitation of Actions,” and this is where the
    statute of repose comes in, TCA 28-3-202. “All actions to recover damages
    for any deficiency in the design, planning, supervision, observation of
    construction, or construction of an improvement to real property must be” -
    - it goes on - - “must be brought against the person performing or
    furnishing the design, planning, supervision, construction within four years
    after substantial completion of such an improvement.”
    TCA 28-3-203 says if you suffer the injury in the fourth year, then,
    of course, it adds a year to it.
    And then 28-3-205 specifically sets out “Limitation not defense for
    party in possession, guilty of fraud, who conceals cause of action.” Under
    subparagraph (b), “The limitation provided shall not be available as a
    defense to any person who shall have been guilty of fraud in performing or
    furnishing the design, planning, supervision, observation of construction,
    construction of” - - and then it goes on about land - - “who shall wrongfully
    conceal any such action.”
    As mentioned before, that‟s not an issue before the Court, but even if
    it were, there is nothing that this Court can find of any allegation of
    wrongful concealment.
    -4-
    The Court finds that the case that most appropriately matches, to the
    Court - - and I know intelligent minds differ frequently on what a case says,
    but that‟s why we have courts of appeals, and this came out of the Court of
    Appeals. Counts Company vs. Praters, Inc., 
    392 S.W.3d 80
    , goes through
    case after case that specifically addresses each of the issues that we have
    here.
    And let me first go over substantial completion, and it defines
    substantial completion on page 84. It defines it under TCA 28-3-201, just
    as I have. And in this case, it argued about the flooring was installed in
    2006, and they resurfaced it in 2007. It talks about two different
    incidences, just as we‟ve talked about here. But the Counts court recites
    Watts v. Putnam County, where it says that TCA 28-3-202 “explained that
    it was a statute that was designed to create an „outer limit‟” - - quotations,
    their quotations, not mine - - “of liability to all potential actions based on
    injury to the property, „without regard to the date of the discovery.‟ 28-3-
    202 did not extend any statute of limitations, but rather was „superimposed‟
    on existing statutes, and was unrelated to the accrual of any cause of action
    since it expressly stated that it began to run on the date of substantial
    completion rather than the date of injury or damage. The Court agreed with
    the decision from the Federal Court for the Eastern District of Tennessee,
    wherein it was held that the legislative intent in passing 28-3-202 was to
    „insulate contractors, architects, engineers and the like from liability for
    their defective construction or design of improvements to property where
    either the occurrence giving rise to the cause of action or injury happens
    more than four years after substantial completion of the improvement.‟”
    So as it pertains to fraud and concealment, the plaintiff in this case, it
    was     argued      that     “defendant    was     guilty    of      fraudulent
    concealment/concealment sufficient to toll TCA 28-3-202,” pursuant to, of
    course, TCA 28-3-205, and it cites Cunha and Conley. “However, plaintiff
    failed to properly plead this claim. Plaintiff did allege in its amended
    complaint that they „led parties to believe that the repair work it performed
    in 2007‟” - - that‟s where we go to the two different dates - - “ „had
    resolved the problem. Praters knew or should have known that these
    representations were false as the floor cupping did not correct itself after
    moisture problems,‟” etcetera. It says, “In order to toll the statute, plaintiff
    must allege „the cause of action was known to the defendant and
    fraudulently concealed by him.‟”
    -5-
    I have nothing in the record, nothing, that says that, not in the
    pleadings, not in the affidavits, not in the depositions that have been filed.
    “Tennessee Rules of Civil Procedure 9.02 requires that „in pleadings
    averring fraud, the circumstances constituting fraud „shall be stated with
    particularity‟.‟   Plaintiff failed to state circumstances constituting
    fraudulent concealment with particularity, as the only circumstances alleged
    by the plaintiff was the problem did not resolve as defendant said it would.”
    Again, it goes on.
    It‟s a good case. I researched it and couldn‟t find where it‟s been
    modified as it pertains to the issues before the Court today. I think Counts
    Company vs. Prater hits on all four corners on this case.
    I think and I so find that as set out, I have nothing that contradicts
    the date of completion, of substantial completion, as defined by statute and
    case law being on or about March 23, 2006. I find nothing, nothing, in the
    record that contradicts the fact that none of the defendants in this case knew
    or attempted to fraudulently conceal any cause of injury that is allegedly
    suffered by the plaintiffs in each of these five cases.
    The ownership of the property is clear, but the fact is, Methodist
    Medical Center is not a party to this litigation, and if they were, it would
    apply to them also. The undisputed, verified, pursuant to Rule 56,
    information before the Court for the Court to take into consideration is
    Methodist Medical Center owned the property, Jan McNally, as president
    of the corporation, signed the contract with the engineers and the
    construction company. The deed to the property, as presented to the Court,
    is owned by Methodist Medical Center. It‟s a separate corporate entity that
    is not a party to this litigation, but, obviously, even if it were, the ruling of
    the Court would apply to them also. We have pending a motion to join
    Methodist Medical Center.
    Even in the proposed amended complaint that‟s been filed in this
    case, nowhere does it mention fraud or concealment that I can recall. And,
    again, I read it all again yesterday. I read the complaints again yesterday to
    ensure that the statutes and case law as I read them was consistent with the
    proof that had been submitted to me under Rule 56.
    For those reasons, I find that the motions for summary judgment
    filed in each of the five cases by each of the defendants in this cause of
    -6-
    action are valid, and the Court would grant the same. I would tax the cost
    to the plaintiffs.
    Plaintiffs appeal.
    Discussion
    Although not stated exactly as such, Plaintiffs raise the following issues on
    appeal: 1) whether the Trial Court erred in granting summary judgment to Defendants
    when, according to Plaintiffs, issues of fact existed concerning the substantial completion
    of the project at question and whether exceptions to the statute of repose applied; 2)
    whether the Trial Court erred in denying Plaintiffs‟ motion to amend to add MMC as a
    party; and, 3) whether the Trial Court erred in limiting discovery to the date of substantial
    completion when other relevant issues were before the Trial Court.
    With regard to summary judgments, this Court explained in Estate of Boote
    v. Roberts:
    The trial court‟s resolution of a motion for summary judgment is a
    conclusion of law, which we review de novo on appeal, according no
    deference to the trial court‟s decision. Martin v. Norfolk S. Ry. Co., 
    271 S.W.3d 76
    , 84 (Tenn. 2008). Summary judgment is appropriate only when
    the moving party can demonstrate that there is no genuine issue of material
    fact, and that it is entitled to judgment as a matter of law. Tenn. R. Civ. P.
    56.04; see Hannan v. Alltel Publ’g Co., 
    270 S.W.3d 1
    , 5 (Tenn. 2008);
    Byrd v. Hall, 
    847 S.W.2d 208
    , 214 (Tenn. 1993).
    This action was filed [after July 1, 2011]. Therefore, the trial court
    was required to apply the summary-judgment standard set forth in
    Tennessee Code Annotated § 20-16-101. That statute provides:
    In motions for summary judgment in any civil action
    in Tennessee, the moving party who does not bear the burden
    of proof at trial shall prevail on its motion for summary
    judgment if it:
    (1) Submits affirmative evidence that
    negates an essential element of the nonmoving
    party‟s claim; or
    (2) Demonstrates to the court that the
    nonmoving party‟s evidence is insufficient to
    -7-
    establish an essential element of the nonmoving
    party‟s claim.
    Tenn. Code Ann. § 20-16-101 (Supp. 2012).
    Estate of Boote v. Roberts, No. M2012-00865-COA-R3-CV, 
    2013 WL 1304493
    , at **8-9
    (Tenn. Ct. App. March 28, 2013), no appl. perm. appeal filed (footnotes omitted).
    The construction statute of repose states as follows:
    All actions to recover damages for any deficiency in the design, planning,
    supervision, observation of construction, or construction of an improvement
    to real property, for injury to property, real or personal, arising out of any
    such deficiency, or for injury to the person or for wrongful death arising out
    of any such deficiency, shall be brought against any person performing or
    furnishing the design, planning, supervision, observation of construction,
    construction of, or land surveying in connection with, such an improvement
    within four (4) years after substantial completion of such an improvement.
    Tenn. Code Ann. § 28-3-202 (2000) (emphasis added).
    Substantial completion is defined as follows:
    “Substantial completion” means that degree of completion of a project,
    improvement, or a specified area or portion thereof (in accordance with the
    contract documents, as modified by any change orders agreed to by the
    parties) upon attainment of which the owner can use the same for the
    purpose for which it was intended; the date of substantial completion may
    be established by written agreement between the contractor and the owner.
    Tenn. Code Ann. § 28-3-201(2) (2000).
    We first address whether the Trial Court erred in granting summary
    judgment to Defendants when, according to Plaintiffs, issues of fact existed concerning
    the date of the substantial completion of the project at question and whether exceptions to
    the statute of repose applied. Plaintiffs argue that the absence of the shielding in the wall
    means that the construction project was not substantially completed until that defect was
    corrected. Therefore, according to Plaintiffs, the statute of repose did not expire because
    it never started running until the defect was corrected.
    -8-
    To resolve this issue, we must consider the definition of substantial
    completion. Substantial completion does not mean perfect completion according to the
    exact specifications. Otherwise, the qualifying word “substantial” before “completion”
    would have no meaning. Rather, as reflected in the statutory definition quoted above,
    substantial completion means that the project or improvement can be used for its intended
    purpose. The undisputed evidence in the record on appeal is that the emergency
    department, including the CT room at issue, was used from March 2006. The fact that
    the improvement allegedly was defective does not prevent that improvement from being
    substantially complete. This Court in addressing this issue has stated:
    This Court again reiterated that in Meyer, the Court rejected the
    argument that substantial completion cannot occur until all defects have
    been repaired, and stated that a building is substantially complete when it
    can be used for its intended purpose, even if it has some defects, and thus
    subsequent repairs do not affect the date of substantial completion. 
    Id. In this
    case, plaintiff‟s allegation that the attempted repairs by
    defendant would change the date of substantial completion is a conclusion,
    not accepted by the courts. The above cases make clear that the date of
    substantial completion is determined by the date upon which the
    improvement can be used for that which it was intended, and there is no
    dispute herein that these floors were completed, i.e. installed, by May 2006.
    The fact that a repair was attempted by Praters one year later does not
    change the date of substantial completion under case law. Plaintiff‟s
    attempt to characterize the work done in 2007 as “additional work” rather
    than a “repair” is misguided. There can be no serious argument that the
    additional work done in 2007 was anything more than an attempt to repair a
    floor that was unsatisfactory.
    Counts Co. v. Praters, Inc., 
    392 S.W.3d 80
    , 86 (Tenn. Ct. App. 2012).
    In our view, adopting Plaintiffs‟ argument would vitiate the very purpose of
    the construction statute of repose.          Under Plaintiffs‟ position, every defective
    construction project would be considered not substantially complete for purposes of the
    relevant statute of repose. This surely is not what our General Assembly intended.
    Rather, it is clear that our General Assembly intended through the construction statute of
    repose to set an outer limit to liability arising from defective work on improvements to
    real property. The undisputed evidence is that the CT room was, in fact, used for its
    intended purpose starting in 2006. The Trial Court did not err when it found there was no
    genuine dispute that the date of substantial completion was “on or about March 23,
    2006.”
    -9-
    Plaintiffs argue further that exceptions to the statute of repose apply. The
    exceptions are stated as follows:
    (a) The limitation provided by this part shall not be asserted as a defense by
    any person in actual possession or the control, as owner, tenant, or
    otherwise, of such an improvement at the time any deficiency in such an
    improvement constitutes the proximate cause of the injury or death for
    which it is proposed to bring an action.
    (b) The limitation hereby provided shall not be available as a defense to any
    person who shall have been guilty of fraud in performing or furnishing the
    design, planning, supervision, observation of construction, construction of,
    or land surveying, in connection with such an improvement, or to any
    person who shall wrongfully conceal any such cause of action.
    Tenn. Code Ann. § 28-3-205 (2000).
    As found by the Trial Court, no exception applies. First, it is undisputed
    from the record that Methodist Hospital was in ownership, possession, and control of the
    CT room at all relevant times in this case. Regarding fraud or wrongful concealment, we
    find, as did the Trial Court, that Plaintiffs did not plead this with sufficient particularity.
    Although Plaintiffs alleged that Defendants falsely or deceptively omitted material facts
    regarding the defect, they do not specify how. The fact that a construction defect exists
    and goes unnoticed does not in itself constitute fraud or wrongful concealment. To hold
    otherwise would mean that most every construction defect could be considered a species
    of fraud which would, once again, vitiate the intention and purpose of the construction
    statute of repose. Plaintiffs‟ argument ignores the underlying intention and purpose of
    the statute of repose and the exceptions thereto. Our General Assembly made a public
    policy decision when it enacted the improvement to real property statute of repose, as is
    its responsibility.
    The evidence in the record is undisputed, as found by the Trial Court, that
    the relevant CT room project was substantially completed by March 2006. Plaintiffs filed
    the present lawsuit in January 2014. The four year statute of repose had long expired,
    and this serves to defeat Plaintiffs‟ claims. We hold, as did the Trial Court, that the
    construction statute of repose applies to defeat Plaintiffs‟ claims and that none of the
    statutory exceptions apply.1
    1
    Our holding applies also to the minor appellant as minority does not toll the statute of repose. See
    Etheridge ex rel. Etheridge v. YMCA of Jackson, 
    391 S.W.3d 541
    , 547 (Tenn. Ct. App. 2012).
    -10-
    We next address whether the Trial Court erred in denying Plaintiffs‟ motion
    to amend to add MMC as a party. The abuse of discretion standard applies. Our
    Supreme Court has stated:
    The grant or denial of a motion to amend a pleading is discretionary
    with the trial court. Harris v. St. Mary’s Med. Ctr., Inc., 
    726 S.W.2d 902
    ,
    904 (Tenn. 1987). Generally, trial courts must give the proponent of a
    motion to amend a full chance to be heard on the motion and must consider
    the motion in light of the amendment policy embodied in Rule 15.01 of the
    Tennessee Rules of Civil Procedure that amendments must be freely
    allowed; and, in the event the motion to amend is denied, the trial court
    must give a reasoned explanation for its action. Henderson v. Bush Bros. &
    Co., 
    868 S.W.2d 236
    , 238 (Tenn. Workers‟ Comp. Panel 1993). Although
    permission to amend should be liberally granted, the decision “will not be
    reversed unless abuse of discretion has been shown.” Welch v. Thuan, 
    882 S.W.2d 792
    , 793 (Tenn. Ct. App. 1994). Factors the trial court should
    consider when deciding whether to allow amendments include “[u]ndue
    delay in filing; lack of notice to the opposing party; bad faith by the moving
    party, repeated failure to cure deficiencies by previous amendments, undue
    prejudice to the opposing party, and futility of amendment.” Merriman v.
    Smith, 
    599 S.W.2d 548
    , 559 (Tenn. Ct. App. 1979).
    Cumulus Broadcasting, Inc., v. Shim, 
    226 S.W.3d 366
    , 374 (Tenn. 2007).
    In Lee Medical, Inc. v. Beecher, 
    312 S.W.3d 515
    (Tenn. 2010), the
    Supreme Court discussed the abuse of discretion standard at length, stating:
    The abuse of discretion standard of review envisions a less rigorous
    review of the lower court‟s decision and a decreased likelihood that the
    decision will be reversed on appeal. Beard v. Bd. of Prof’l Responsibility,
    
    288 S.W.3d 838
    , 860 (Tenn. 2009); State ex rel. Jones v. Looper, 
    86 S.W.3d 189
    , 193 (Tenn. Ct. App. 2000). It reflects an awareness that the
    decision being reviewed involved a choice among several acceptable
    alternatives. Overstreet v. Shoney’s, Inc., 
    4 S.W.3d 694
    , 708 (Tenn. Ct.
    App. 1999). Thus, it does not permit reviewing courts to second-guess the
    court below, White v. Vanderbilt Univ., 
    21 S.W.3d 215
    , 223 (Tenn. Ct.
    App. 1999), or to substitute their discretion for the lower court‟s, Henry v.
    Goins, 
    104 S.W.3d 475
    , 479 (Tenn. 2003); Myint v. Allstate Ins. Co., 
    970 S.W.2d 920
    , 927 (Tenn. 1998). The abuse of discretion standard of review
    does not, however, immunize a lower court‟s decision from any meaningful
    -11-
    appellate scrutiny. Boyd v. Comdata Network, Inc., 
    88 S.W.3d 203
    , 211
    (Tenn. Ct. App. 2002).
    Discretionary decisions must take the applicable law and the relevant
    facts into account. Konvalinka v. Chattanooga-Hamilton County Hosp.
    Auth., 
    249 S.W.3d 346
    , 358 (Tenn. 2008); Ballard v. Herzke, 
    924 S.W.2d 652
    , 661 (Tenn. 1996). An abuse of discretion occurs when a court strays
    beyond the applicable legal standards or when it fails to properly consider
    the factors customarily used to guide the particular discretionary decision.
    State v. Lewis, 
    235 S.W.3d 136
    , 141 (Tenn. 2007). A court abuses its
    discretion when it causes an injustice to the party challenging the decision
    by (1) applying an incorrect legal standard, (2) reaching an illogical or
    unreasonable decision, or (3) basing its decision on a clearly erroneous
    assessment of the evidence. State v. Ostein, 
    293 S.W.3d 519
    , 526 (Tenn.
    2009); Konvalinka v. Chattanooga-Hamilton County Hosp. 
    Auth., 249 S.W.3d at 358
    ; Doe 1 ex rel. Doe 1 v. Roman Catholic Diocese of
    
    Nashville, 154 S.W.3d at 42
    .
    To avoid result-oriented decisions or seemingly irreconcilable
    precedents, reviewing courts should review a lower court‟s discretionary
    decision to determine (1) whether the factual basis for the decision is
    properly supported by evidence in the record, (2) whether the lower court
    properly identified and applied the most appropriate legal principles
    applicable to the decision, and (3) whether the lower court‟s decision was
    within the range of acceptable alternative dispositions. Flautt & Mann v.
    Council of Memphis, 
    285 S.W.3d 856
    , 872-73 (Tenn. Ct. App. 2008)
    (quoting BIF, a Div. of Gen. Signal Controls, Inc. v. Service Constr. Co.,
    No. 87-136-II, 
    1988 WL 72409
    , at *3 (Tenn. Ct. App. July 13, 1988) (No
    Tenn. R. App. P. 11 application filed)). When called upon to review a
    lower court‟s discretionary decision, the reviewing court should review the
    underlying factual findings using the preponderance of the evidence
    standard contained in Tenn. R. App. P. 13(d) and should review the lower
    court‟s legal determinations de novo without any presumption of
    correctness. Johnson v. Nissan N. Am., Inc., 
    146 S.W.3d 600
    , 604 (Tenn.
    Ct. App. 2004); Boyd v. Comdata Network, 
    Inc., 88 S.W.3d at 212
    .
    
    Beecher, 312 S.W.3d at 524-25
    .
    In its written order, the Trial Court stated that Plaintiffs‟ motion was
    “futile.” In addition, the Trial Court elaborated on its reasoning in its oral ruling as
    quoted above. The Trial Court did not commit reversible error in declining to add MMC
    -12-
    as a party because to have granted the motion would not have altered the outcome of
    Plaintiffs‟ case against Defendants. The statute of repose still would have served to
    defeat Plaintiffs‟ claims against Defendants. We find no abuse of discretion by the Trial
    Court on this issue.
    The final issue we address is whether the Trial Court erred in limiting
    discovery to the date of substantial completion when other relevant issues were before the
    Trial Court. “Decisions concerning pretrial discovery are matters well within the
    discretion of the trial court and thus are reviewed under an abuse of discretion standard.”
    Frye v. St. Thomas Health Servs., 
    227 S.W.3d 595
    , 600 (Tenn. Ct. App. 2007). Plaintiffs
    fail to adequately articulate what additional discovery they believe was necessary for the
    resolution of this case. We also note that it appears from the record that Plaintiffs were,
    in fact, given sufficient opportunity for discovery as to the dispositive issue before the
    Trial Court, that of the date of substantial completion. We hold that the Trial Court did
    not abuse its discretion in limiting discovery thusly.
    Conclusion
    The judgment of the Trial Court is affirmed, and this cause is remanded to
    the Trial Court for collection of the costs below. The costs on appeal are assessed against
    the Appellants, Micah Noelle Lewellen, individually and Cale Ryan Lewellen, a minor
    by Micah Noelle Lewellen, and their surety, if any.
    _________________________________
    D. MICHAEL SWINEY, JUDGE
    -13-