Preston McNees Specialty Woodworking, Inc. v. The Daniel Co. (Danco), Inc. ( 2015 )


Menu:
  •                 IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    November 24, 2014 Session
    PRESTON MCNEES SPECIALTY WOODWORKING, INC. ET AL. v.
    THE DANIEL CO. (DANCO), INC.
    Appeal from the Circuit Court for Washington County
    No. 30781     Thomas J. Seeley, Jr., Judge
    No. E2014-01004-COA-R3-CV - Filed February 13, 2015
    This case involves the proper interpretation of a contract between a general contractor and
    a subcontractor. The trial court determined that the subcontractor was entitled to recover
    additional sums above the original contract price based on the doctrine of equitable estoppel.
    The general contractor timely appealed. Having determined that the scope of the parties’
    contract covered the work in question and that the doctrine of equitable estoppel does not
    apply in this matter, we vacate the trial court’s judgment.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court
    Vacated; Case Remanded
    T HOMAS R. F RIERSON, II, J., delivered the opinion of the Court, in which D. M ICHAEL
    S WINEY and J OHN W. M CC LARTY, JJ., joined.
    Bill W. Petty and Micha Buffington, Knoxville, Tennessee, for the appellant, The Daniel Co.
    (DANCO), Inc.
    Thomas D. Dossett, Kingsport, Tennessee, for the appellee, Preston McNees Specialty
    Woodworking, Inc. d/b/a Preston Woodworking.
    OPINION
    I. Factual and Procedural Background
    The plaintiff, Preston McNees Specialty Woodworking, Inc. d/b/a Preston
    Woodworking (“Preston”), filed the present action against The Daniel Co. (DANCO), Inc.
    (“DANCO”), seeking compensation for work that Preston performed on a construction
    project wherein DANCO was the general contractor and Preston was a subcontractor. In
    2010, Preston submitted a bid to supply certain woodwork regarding a project for the College
    of Medicine Student Center at East Tennessee State University. When preparing its bid,
    Preston relied in part upon the project manual (“Manual”) that had been prepared by Fisher
    + Associates (“Fisher”), the project architect and designer.
    The Manual expressly provided for “[s]hop finishing of all natural finish interior
    woodwork” and stated that “fabrication, including assembly, finishing, and hardware
    application” should be complete before shipment to the project site. In a section entitled
    “Shop Finishing,” the Manual provided in pertinent part:
    B.         General: Finish architectural woodwork at fabrication shop as
    specified in this Section. Defer only final touchup, cleaning, and
    polishing until after installation.
    C.         General: Shop finish transparent-finished interior architectural
    woodwork at fabrication shop as specified in this Section.
    ***
    E.         Transparent Finish: Comply with requirements indicated below for
    grade, finish system, staining, and sheen, with sheen measured on 60-
    degree gloss meter per ASTM D 523.
    ***
    4.      Staining: Match Architect’s sample.
    Preston prepared and submitted its bid, which consisted of a base amount of $82,961,
    with an additional $12,605 to be added for three bays of study rooms. Preston’s bid stated
    that “All wood items are sent to field unfinished, ready to stain by others prior to
    installation.” DANCO selected Preston as the subcontractor for the aforementioned work.
    On November 22, 2010, Preston and DANCO executed a “Standard Form of
    Agreement Between Contractor and Subcontractor,” otherwise identified as AIA 1 Document
    A401-1997 (“Subcontract”). This Subcontract provides that Preston will perform the
    casework and millwork for the project for a total price of $95,566. The Subcontract also
    provides that the work will be performed “as specified in the Project Manual dated June 18,
    2010, Drawings, and addenda thereto, prepared by Fisher + Associates . . . .” The
    1
    American Institute of Architects.
    -2-
    Subcontract further states:
    1.1    The Subcontract Documents consist of (1) this Agreement; (2) the
    Prime Contract, consisting of the Agreement between the Owner and
    Contractor and the other Contract Documents enumerated therein; (3)
    Modifications issued subsequent to the execution of the Agreement
    between the Owner and Contractor, whether before or after the
    execution of this Agreement; (4) other documents listed in Article 16
    of this Agreement; and (5) Modifications to this Subcontract issued
    after execution of this Agreement. These form the Subcontract, and are
    as fully a part of the Subcontract as if attached to this Agreement or
    repeated herein. The Subcontract represents the entire and integrated
    agreement between the parties hereto and supersedes prior negotiations,
    representations or agreements, either written or oral. An enumeration
    of the Subcontract Documents, other than Modifications issued
    subsequent to the execution of this Agreement, appears in Article 16.
    Article 16 lists no additional documents.
    Following execution of the Subcontract, Preston prepared shop drawings, which set
    out the details regarding the work Preston was to perform. The front page of the shop
    drawings contains a typed statement by Preston that “trim and plywood to be stained as per
    provided sample. (Stain sample to follow).” This front page additionally bears the approval
    stamp of DANCO as well as the approval stamp of Fisher. There also appears a handwritten
    note, signed by Mr. Fisher, which states: “Wood stain to match approved door sample.”
    DANCO returned the shop drawings to Preston on June 6, 2011, with a transmittal sheet
    stating, “Wood stain to match enclosed door sample.”
    Sam Preston, President of Preston Woodworking, testified that when the shop
    drawings were returned with the notations regarding stain color, he contacted Tom Daniel
    at DANCO and reminded him that Preston’s bid was for unfinished wood. According to Mr.
    Preston, Mr. Daniel explained that the architect required the woodwork to be shop-finished;
    Mr. Preston claimed he was previously unaware of this fact. Mr. Preston related that he
    subsequently submitted a price for this finish work of $13,994, with no negative response
    from Mr. Daniel. Mr. Preston stated that Preston had not yet begun finishing of the
    woodwork, such that Mr. Daniel could have opted to accept the additional cost or allow the
    woodwork to be delivered unfinished for the original contract price.
    Preston sent a change request to DANCO on August 21, 2011, wherein Mr. Preston
    detailed the additional cost of $13,994 to stain and finish the woodwork. Mr. Preston
    -3-
    explained that he discussed this additional cost with Mr. Daniel in great detail. He admitted,
    however, that the change order was never signed by anyone at DANCO. Preston submitted
    a stain sample to the architect and received approval for same. Although Preston was
    instructed to begin installation on August 22, 2011, it was unable to comply due to conditions
    at the job site. Eventually, Preston’s on-site work began on August 29, 2011.
    Preston submitted a pay application on August 25, 2011, which included the original
    contract price of $95,556, plus an addition of $13,994 for the submitted change order.2 As
    such, the pay application reflected a total revised contract price of $109,550. Through that
    pay application, Preston requested a partial payment for its work, which Preston indicated
    was thirty-eight percent complete. Preston submitted a subsequent pay application on
    September 23, 2011, demonstrating the original contract price plus additional costs of
    $21,639 and claiming a total revised contract price in the amount of $117,195. Two
    subsequent pay applications were sent on October 25, 2011, and November 8, 2011, also
    reflecting the “revised” contract sum of $117,195. Mr. Preston testified that DANCO was
    slow in making payments and never questioned the extra charges until approximately
    November 8, 2011, after Preston’s work was substantially complete. Consequently, Mr.
    Preston sent a memo to DANCO and Mr. Fisher on that date, explaining the additional
    charges in detail.
    Subsequently, on November 15, 2011, Mr. Daniel sent a letter to Mr. Preston, which
    states:
    This letter is in response to your November 7th letter.
    As you are aware, none of the change orders you are requesting was approved
    either verbally or in writing by anyone from our company. The items listed are
    all within the scope of the work specified in your contract. Therefore, no
    additional payment beyond the original contract amount will be approved.
    DANCO ultimately paid Preston the original contract price. Preston then filed the instant
    action on August 23, 2012, seeking to recover the unpaid sum of $21,639.
    The trial court conducted a hearing on the merits on January 31, 2014, wherein Mr.
    Preston and Mr. Daniel were the only witnesses to testify. At trial, Mr. Daniel maintained
    that he orally informed Mr. Preston on several occasions that Preston would not be paid any
    sums in excess of the contract price. Mr. Daniel therefore did not feel the need to deny the
    2
    Preston erroneously listed the original contract price as $95,556 rather than $95,566 on all pay
    applications.
    -4-
    charges in writing. According to Mr. Daniel, all of the work requested of Preston was
    included in the Manual and was part of the original contract. Mr. Daniel pointed to specific
    provisions in the Manual that included stain as a part of the transparent finish and stated that
    the stain sample referenced therein was to match the wood doors at the job site. Mr. Daniel
    indicated that he told Mr. Preston as early as December 2010 that if Preston did not shop-
    finish the woodwork, Preston would not keep the job and DANCO would hire someone else.
    Mr. Preston denied ever being told by Mr. Daniel that the additional charges would
    not be paid. According to Mr. Preston, he understood transparent finish to be without any
    stain. He also maintained that there was no stain sample attached to the project manual.
    At the conclusion of the trial, the court rendered its opinion from the bench, finding
    that Mr. Daniel’s letter dated November 15, 2011, denying the additional charges, was sent
    two months after the first change order on August 21, 2011. The court noted that although
    Mr. Daniel testified he did not feel the need to document DANCO’s denial of the change
    orders in writing because he had conveyed this denial to Preston orally, “the best proof is
    always documentation . . . .” The court invoked the equitable doctrine of estoppel, finding
    that it was unfair for DANCO to wait until the work was completed to provide notice that the
    extra charges would be denied. The trial court accordingly granted judgment to Preston in
    the amount of $21,639. DANCO timely appealed.
    II. Issue Presented
    DANCO presents a single issue for our review:
    Whether the trial court erred by applying the doctrine of equitable
    estoppel to modify a fully integrated contract.
    III. Standard of Review
    Our standard of review is de novo with a presumption of correctness as to the trial
    court’s findings of fact unless the preponderance of the evidence is otherwise. Tenn. R. App.
    P. 13(d); McCarty v. McCarty, 
    863 S.W.2d 716
    , 719 (Tenn. Ct. App. 1992). No presumption
    of correctness attaches to the trial court’s legal conclusions. Union Carbide Corp. v.
    Huddleston, 
    854 S.W.2d 87
    , 91 (Tenn. 1993).
    We review issues of contract interpretation de novo. See Dick Broad. Co., Inc. of
    Tenn. v. Oak Ridge FM, Inc., 
    395 S.W.3d 653
    , 659 (Tenn. 2013). As this Court has
    previously explained:
    -5-
    In resolving a dispute concerning contract interpretation, our task is to
    ascertain the intention of the parties based upon the usual, natural, and
    ordinary meaning of the contract language. Planters Gin Co. v. Fed.
    Compress & Warehouse Co., Inc., 
    78 S.W.3d 885
    , 889-90 (Tenn. 2002) (citing
    Guiliano v. Cleo, Inc., 
    995 S.W.2d 88
    , 95 (Tenn. 1999)). A determination of
    the intention of the parties “is generally treated as a question of law because
    the words of the contract are definite and undisputed, and in deciding the legal
    effect of the words, there is no genuine factual issue left for a jury to decide.”
    Planters Gin 
    Co., 78 S.W.3d at 890
    (citing 5 Joseph M. Perillo, Corbin on
    Contracts, § 24.30 (rev. ed. 1998); Doe v. HCA Health Servs. of Tenn., Inc.,
    
    46 S.W.3d 191
    , 196 (Tenn. 2001)). The central tenet of contract construction
    is that the intent of the contracting parties at the time of executing the
    agreement should govern. Planters Gin 
    Co., 78 S.W.3d at 890
    . The parties’
    intent is presumed to be that specifically expressed in the body of the contract.
    “In other words, the object to be attained in construing a contract is to
    ascertain the meaning and intent of the parties as expressed in the language
    used and to give effect to such intent if it does not conflict with any rule of
    law, good morals, or public policy.” 
    Id. (quoting 17
    Am.Jur.2d, Contracts, §
    245).
    Kafozi v. Windward Cove, LLC, 
    184 S.W.3d 693
    , 698 (Tenn. Ct. App. 2005). “Courts must
    look at the plain meaning of the words in a contract to determine the parties’ intent. If the
    contractual language is clear and unambiguous, the literal meaning controls . . . .” Allmand
    v. Pavletic, 
    292 S.W.3d 618
    , 630 (Tenn. 2009) (internal citation omitted).
    IV. The Subcontract
    DANCO contends that the trial court erred by applying the doctrine of equitable
    estoppel to modify this fully integrated Subcontract. As noted above, the Subcontract does
    provide that it contains the entire agreement between the parties and that it is comprised of
    certain specific documents. Preston’s bid is not one of the documents listed in the
    Subcontract. Further, the Subcontract expressly provides that it “supersedes prior
    negotiations, representations or agreements, either written or oral.” Thus, the bid submitted
    by Preston prior to execution of the Subcontract, which states that the woodwork would be
    sent to the job site unfinished, is not part of the Subcontract.
    When interpreting a contract, our “initial task is to determine whether the language
    in the contract is ambiguous.” Ray Bell Cons’t Co., Inc. v. Tenn. Dep’t of Transp., 
    356 S.W.3d 384
    , 386-87 (Tenn. 2011) (citing Planters Gin Co. v. Fed. Compress & Warehouse
    Co., 
    78 S.W.3d 885
    , 890 (Tenn. 2002)). “If the contract language is unambiguous, then the
    -6-
    parties’ intent is determined from the four corners of the contract.” Ray 
    Bell, 356 S.W.3d at 387
    (citing Whitehaven Cmty. Baptist Church v. Holloway, 
    973 S.W.2d 592
    , 596 (Tenn.
    1998)). This Court has explained the principles applied to determine whether the contract
    language is clear or ambiguous as follows:
    The language in dispute must be examined in the context of the entire
    agreement. Cocke County Bd. of Highway Commrs. v. Newport Utils. Bd., 
    690 S.W.2d 231
    , 237 (Tenn. 1985). The language of a contract is ambiguous when
    its meaning is uncertain and when it can be fairly construed in more than one
    way. Farmers-Peoples Bank v. Clemmer, 
    519 S.W.2d 801
    , 805 (Tenn. 1975).
    “A strained construction may not be placed on the language used to find
    ambiguity where none exists.” 
    Id. Vanbebber v.
    Roach, 
    252 S.W.3d 279
    , 284 (Tenn. Ct. App. 2007). “The parol evidence rule
    does not permit contracting parties to ‘use extraneous evidence to alter, vary, or qualify the
    plain meaning of an unambiguous written contract.’” Staubach Retail Servs.-Se., LLC v. H.G.
    Hill Realty Co., 
    160 S.W.3d 521
    , 525 (Tenn. 2005) (quoting GRW Enters. v. Davis, 
    797 S.W.2d 606
    , 610 (Tenn. Ct. App. 1990)).
    In the case at bar, the Subcontract expressly states that the work would be performed
    by Preston “as specified in the Project Manual dated June 18, 2010, Drawings, and addenda
    thereto, prepared by Fisher + Associates . . . .” Multiple provisions within the Manual
    declared that the woodwork would be finished in the shop before being delivered to the job
    site. The Manual further explicitly provided that this finish would include stain to be
    selected by the architect. Based upon these clear and unambiguous provisions, we determine
    that the Subcontract provided that Preston would finish the woodwork in the shop before
    delivering it to the job site. We further determine that such finish was to include stain as
    specified by the architect. Any parol evidence to the contrary should not have been
    considered by the trial court.
    Having determined that the finishing of the woodwork was addressed and covered by
    the Subcontract, we conclude that the trial court lacked sufficient basis upon which to employ
    the doctrine of equitable estoppel. As our Supreme Court has explained:
    The doctrine of equitable estoppel requires evidence of the following elements
    with respect to the party against whom estoppel is asserted:
    (1) Conduct which amounts to a false representation or
    concealment of material facts, or, at least, which is calculated to
    convey the impression that the facts are otherwise than, and
    -7-
    inconsistent with, those which the party subsequently attempts
    to assert; (2) Intention, or at least expectation that such conduct
    shall be acted upon by the other party; (3) Knowledge, actual or
    constructive of the real facts.
    Consumer Credit Union v. Hite, 
    801 S.W.2d 822
    , 825 (Tenn. Ct. App. 1990)
    (quoting Callahan v. Town of Middleton, 
    41 Tenn. App. 21
    , 
    292 S.W.2d 501
    ,
    508 (1954) (citation omitted)). Equitable estoppel also requires the following
    elements with respect to the party asserting estoppel:
    (1) Lack of knowledge and of the means of knowledge of the
    truth as to the facts in question; (2) Reliance upon the conduct
    of the party estopped; and (3) Action based thereon of such a
    character as to change his position prejudicially.
    
    Id. Osborne v.
    Mountain Life Ins. Co., 
    130 S.W.3d 769
    , 774 (Tenn. 2004). We determine that
    several of the above-listed elements are absent in this case. There was no showing that
    DANCO falsely represented or concealed any material facts, and there was also no showing
    that Preston lacked the means of knowledge of the truth or acted in reliance upon DANCO’s
    conduct to its detriment. Mr. Preston admitted that Preston had been provided with the
    Manual when its bid was prepared, and the Manual expressly required that the woodwork be
    finished in the shop before delivery. Preston should not be permitted to complain of surprise
    or the alleged necessity of additional costs when this provision was known to it from the
    inception of this transaction.
    Further, to the extent that the trial court found the additional sums sought by Preston
    to be the result of a change in the scope of the original work required, we note that the
    Subcontract provides as follow:
    The Subcontractor may be ordered in writing by the Contractor, without
    invalidating this Subcontract, to make changes in the Work within the general
    scope of this Subcontract consisting of additions, deletions or other revisions,
    including those required by Modifications to the Prime Contract issued
    subsequent to the execution of this Agreement, the Subcontract Sum and the
    Subcontract Time being adjusted accordingly. The Subcontractor, prior to the
    commencement of such changed or revised Work, shall submit promptly to the
    Contractor written copies of a claim for adjustment to the Subcontract Sum
    -8-
    and Subcontract Time for such revised Work in a manner consistent with the
    requirements of the Subcontract Documents.
    It is undisputed that DANCO did not order in writing any changes to the Subcontract.
    Therefore, the trial court’s reliance upon a change order submitted by Preston, which
    purported to increase the contracted amount, was improper as it was not preceded by the
    requisite written order from DANCO.
    We conclude that the trial court erred in applying the doctrine of equitable estoppel
    in this situation. The trial court should have enforced the Subcontract according to its plain
    terms. See Bob Pearsall Motors, Inc. v. Regal Chrysler-Plymouth, Inc., 
    521 S.W.2d 578
    , 580
    (Tenn. 1975) (holding that it is the court’s duty to enforce contracts according to their plain
    terms). Because the finish work was required of Preston by the Subcontract, we determine
    that there was no basis for an award of additional monies to Preston.
    V. Conclusion
    For the foregoing reasons, we vacate the trial court’s judgment. Costs on appeal are
    taxed to the appellee, Preston McNees Specialty Woodworking, Inc. d/b/a Preston
    Woodworking. This case is remanded to the trial court for the collection of costs assessed
    below.
    ________________________________
    THOMAS R. FRIERSON, II, JUDGE
    -9-