City of Elizabethton, Tennessee v. North American Fibers, Inc. ( 2004 )


Menu:
  •                  IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    September 20, 2004 Session
    CITY OF ELIZABETHTON, TENNESSEE v. NORTH AMERICAN
    FIBERS, INC., et al.
    Appeal from the Chancery Court for Carter County
    No. 24908 G. Richard Johnson, Chancellor
    No. E2003-02930-COA-R3-CV - FILED NOVEMBER 19, 2004
    This appeal arises out of a cause of action filed by a municipality against a corporate landowner for
    breach of a sewer easement which the municipality purchased as a path for its underground sewer
    line. The municipality alleged that after construction of the sewer line, the landowner’s long-
    standing practice of depositing fly ash and cinders over the area of the easement rendered the line
    inaccessible and necessitated the construction of an alternate sewage system for which the
    municipality requested compensation. The municipality also sought to hold the landowner’s
    president and chief executive officer liable as the alter ego of the landowner. The trial court decreed
    that the landowner had unreasonably burdened the easement, awarded the municipality compensatory
    damages, and decreed that although the landowner’s president was an alter ego of the landowner,
    he was not personally liable. On appeal the landowner argues that the municipality’s cause of action
    was barred under the statute of limitations and equitable doctrines of estoppel and laches, that under
    the rule of practical construction the easement allowed the landowner to dump material over the
    sewer line, that the trial court erred in its award of damages, and that the court erred in refusing to
    strike findings with respect to the landowner’s president. We affirm the judgment of the trial court
    as rendered and remand.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; Cause
    Remanded
    SHARON G. LEE , J., delivered the opinion of the court, in which HERSCHEL P. FRANKS, P.J. and
    CHARLES D. SUSANO , JR., J., joined.
    Stephen G. Anderson, Knoxville, Tennessee, for the Appellant, North American Fibers, Inc.
    Charlton R. Devault, Jr., Knoxville, Tennessee, for the Appellee, City of Elizabethton, Tennessee.
    OPINION
    I.
    Appellee, the City of Elizabethton (hereinafter "the City"), purchased in 1957 an easement
    from Beaunit Mills and North American Rayon Corporation, Inc., predecessors in title to Appellant,
    North American Fibers, Inc. (hereinafter "NAFI"). The easement ran approximately 1,700 feet
    across an open field and provided the City with a path for placement of one of two 24 inch diameter
    gravity sewer interceptor lines. The line which is the subject of this case, designated "the west
    interceptor line", served as a conduit for seventy percent of the City’s total sewage. It began at a
    collection point in the City and extended through NAFI’s property to the bank of the Watauga River
    at which point sewage was siphoned under the river to the sewage treatment plant located on the
    other side.
    At times relevant to the instant matter, NAFI operated a coal-fired power plant in the vicinity
    of the sewer easement. For a number of years NAFI and its predecessors had dumped cinders and
    fly ash produced by the power plant in settling ponds and waste piles in the area through which the
    easement ran. This practice continued after construction of the subject sewer line such that the
    surface elevation over the line progressively and substantially increased and manholes to the line
    were buried.
    In the mid-1980's, the Tennessee Department of Conservation and Environment (hereinafter
    "DCE") categorized the dumping area as a "private landfill" and ordered that the dumping cease.
    In 1988, DCE, which had not been advised of the City’s sewer line easement, mandated that NAFI
    place a clay "cap", or cover layer, over the dumping area. As a consequence of the accumulated ash,
    cinders and other debris and the clay cap, manhole covers, which had been at ground level when the
    line was constructed in 1958, were now buried twelve to twenty feet underground and the sewer line,
    which had been approximately fifteen feet underground in 1958, was now more than thirty feet
    underground.
    In 1995, the City's wastewater plant manager found that the sewer line and manholes located
    within the easement area were buried under the above described debris and clay cap and were
    inaccessible. The City asked NAFI if it could borrow a bulldozer to remove the accumulation over
    its sewer line and was advised that it would need DCE’s permission before proceeding. The City
    subsequently determined that the process of getting DCE’s approval and accessing the line by
    bulldozing was both impractical and cost prohibitive. Thereafter, the City entered into discussions
    with NAFI in an effort to resolve the problem, but a mutually acceptable solution was not realized
    and, on August 16, 2000, the City filed a complaint against North American Fibers, Inc., North
    American Corporation; and Charles K. Green, individually and as ‘alter ego’ of North American
    Fibers, Inc. The complaint demands that NAFI “remove the existing burden on the plaintiff’s sanitary
    sewer line easement” and “restore complete and regular access” to the line. After the complaint was
    filed, negotiations between the parties continued without resolution and, in July of 2001, the City
    completed construction of a bypass system consisting of two parallel pressurized sewer lines and a
    -2-
    pump station. This system eliminated the City’s dependence upon both the inaccessible west
    interceptor line and the east interceptor line and both of those lines were abandoned.
    On February 14, 2002, the City filed an amended complaint which notes the futility of
    negotiations between itself and NAFI and, inter alia, recites as follows:
    Since the filing of its original complaint, the plaintiff constructed and
    placed in service in July 2001, a forced-main sewer line which bypasses that
    portion of its sanitary sewer line system which has been illegally burdened and
    obstructed by defendant. Plaintiff avers that the construction of the sewer line
    bypass and accompanying pump-stations were necessary to preserve the integrity
    of the municipal sanitary sewer system and to protect the health and safety of the
    inhabitants of the City and of the community in general. Plaintiff avers the costs
    incurred in the construction of the forced-main bypass were $1,102,754.00 and
    were reasonable.
    The complaint demands that the City be awarded the $1,102,754.00 incurred in construction
    of the bypass system and an amount adequate to reimburse it “for the increased debt service which
    it has incurred in order to finance the construction of its sewer line bypass.”
    Trial of the City’s complaint was held in December of 2002 after which the trial court entered
    its memorandum opinion and final order decreeing that NAFI “unreasonably and substantially
    burdened” the City’s sewer line easement and awarding the City damages in the amount of
    $3,414,985.00, consisting of $1,102,754.00, attributable to the construction of the bypass system,
    plus $2,312,231.00 in interest. In response to post judgment motions filed by NAFI, the trial court
    reduced its judgment to $3,215,270.00 and further reduced that amount to its present value of
    $1,187,581.49. Thereafter, NAFI timely filed the instant appeal.
    II.
    The following issues are presented for our review in this case:
    1) Was the City’s cause of action against NAFI barred under either the statute of limitations
    or the equitable doctrines of laches and estoppel?
    2) Did the trial court err in its award of damages?
    3) Did the trial court err in failing to find that NAFI was authorized to dump waste material
    on the land over the City’s sewer line based upon the parties’ practical construction of the easement?
    4) Did the trial court err in refusing to strike from the record its findings with respect to
    Charles K. Green?
    -3-
    III.
    Our standard of review in this non-jury case is de novo upon the record of the proceedings
    below and there is no presumption of correctness with respect to the trial court’s conclusions of law.
    Campbell v. Florida Steel Corp., 
    919 S.W.2d 26
    , 35 (Tenn. 1996) and T.R.A.P. 13(d). The trial
    court's factual findings are, however, presumed to be correct and we must affirm such findings
    absent evidence preponderating to the contrary. Union Carbide Corp. v. Huddleston, 
    854 S.W.2d 87
    , 91 (Tenn. 1993). “On an issue which hinges on the credibility of witnesses, the trial court will
    not be reversed unless there is found in the record clear, concrete, and convincing evidence other
    than the oral testimony of witnesses which contradict the trial court’s findings.” Galbreath v. Harris,
    
    811 S.W.2d 88
    , 91 (Tenn. Ct. App. 1990), citing Tennessee Valley Kaolin Corp. v. Perry, 
    526 S.W.2d 488
    , 490 (Tenn. Ct. App. 1974).
    IV.
    The first issue we address is whether the City’s cause of action in this case was barred under
    either the statute of limitations or the equitable doctrines of laches and estoppel.
    Tenn. Code Ann. § 28-2-103(a) provides as follows:
    (a) No person or anyone claiming under such person shall have any action, either
    at law or in equity, for the recovery of any lands, tenements or hereditaments, but
    within seven (7) years after the right of action accrued.
    Ordinarily, a suit to abate an adverse use of an easement under this section must be brought
    within seven years from the time the cause of action arose. Shearer v. Vandergriff, 661, 
    682 S.W.2d 680
     (Tenn. 1983). And, as acknowledged by this Court in Moffitt v. Meeks, 
    199 S.W.2d 463
    , 465
    (Tenn. Ct. App. 1946), this statute of limitations begins to run from the time the adverse action
    commences. However, Tenn. Code Ann. §28-1-113 provides that the provisions of Title 28 are not
    applicable to actions brought by the state “unless otherwise expressly provided for.” The City’s
    action is not asserted to be an action “otherwise expressly provided for.”
    In Hamilton County Board of Education v. Asbestospray Corporation, 
    909 S.W.2d 783
    , 785
    (Tenn. 1995) the Tennessee Supreme Court discussed the origin and applicability of Tenn. Code
    Ann. § 28-1-113 as follows:
    The common law doctrine of nullum tempus occurit regi, which is literally
    translated as “time does not run against the king,” prevents an action brought by
    the State from being dismissed due to the expiration of the statutory period of
    limitations normally applicable to the specific type of action. This doctrine has
    been justified on the ground “that the public should not suffer because of the
    negligence of its officers and agents ...” State ex rel. Board of University &
    School Lands v. Andrus, 
    671 F.2d 271
    , 274 (8th Cir. 1982). Tennessee’s version
    -4-
    of this doctrine, found at § 28-1-113, provides as follows: “The provision of this
    title [pertaining to statutes of limitation] do not apply to actions brought by the
    State of Tennessee, unless otherwise expressly provided.” This doctrine is not to
    be lightly regarded, as we have repeatedly stated that statutes of limitation are
    looked upon with disfavor in actions brought by the State, and will not be
    enforced in the absence of clear and explicit statutory authority to do so. Dunn v.
    W.F. Jameson & Sons, Inc., 
    569 S.W.2d 799
    , 802 (Tenn. 1978); Anderson v.
    Security Mills, 
    175 Tenn. 197
    , 
    133 S.W.2d 478
     (1939).
    Moreover, it is settled that the nullum tempus doctrine applies, in certain
    cases, to subordinate organs of the state, such as counties or municipalities. The
    basic rule regarding the application of nullum tempus to actions brought by
    subordinate bodies is set forth in Wood v. Cannon County, 
    25 Tenn. App. 600
    ,
    
    166 S.W.2d 399
     (1942), where we stated:
    The statute of limitations does not run against the sovereign or the state, or
    against a county, when [the county is seeking] to enforce a demand arising
    out of, or dependent upon, the exercise of its governmental functions as an
    arm of the state. But the statute does run against a county or municipality
    in respect of its rights or claims which are of a private or corporate nature
    and in which only its local citizens are interested, as distinguished from a
    public or governmental matter in which all the people of the state are
    interested.
    Wood, 166 S.W.2d at 401 [citations omitted]. See also Jennings v. Davidson
    County, 
    208 Tenn. 134
    , 
    344 S.W.2d 359
    , 361-362 (1961).
    Pursuant to the standard indicated by the Court in Hamilton County, we are required to
    determine whether the City’s breach of easement case against NAFI is “of a private or corporate
    nature and is a matter in which only its local citizens are interested, as distinguished from a public
    or governmental matter in which all the people of the State are interested.”
    NAFI apparently argues that the breach of easement suit filed by the City was of a private
    nature because, in filing the suit, the City “was seeking to reduce costs of sewer improvements
    undertaken by the City for the benefit of local citizens and ratepayers.” We disagree with this
    conclusion.
    It is true that the damages which were awarded in this case do benefit the local citizenry in
    that the costs of the new sewer system will now be paid for by NAFI and not from municipal
    revenue. However, the problem which resulted in the award of damages - the problem which
    prompted the prosecution of this case - was the fact that a significant portion of the City’s sewage
    system was rendered inaccessible as a result of the overburden placed upon it by NAFI. The
    -5-
    potential consequences of this situation were attested to by the City’s wastewater manager, Johann
    Coettzee, as follows:
    Q. What would you, as the wastewater manager, have had to do in the event that
    there had been any type of blockage or collapse in the line under the landfill?
    A. I would be in a very bad position. Because of the length of the pipe that is
    covered, one would have no idea where to dig; and digging in itself would be a
    lengthy and time-consuming operation. So, the risk that we have there was that
    you could have an environmental catastrophe with millions of gallons of
    wastewater going into the Watauga River and spilling into the fields upstream of
    the landfill during the time it would take to locate where exactly is the problem
    in the landfill, which is a monumental undertaking considering the length of the
    area that this covered and the depth that the pipe was at.
    The Water Quality Control Act, codified at Tenn. Code Ann. Title 69, provides at § 69-3-
    102(a):
    Recognizing that the waters of Tennessee are the property of the state and are held
    in public trust for the use of the people of the state, it is declared to be the public
    policy of Tennessee that the people of Tennessee as beneficiaries of this trust,
    have a right to unpolluted waters. In the exercise of its public trust over the waters
    of the state, the government of Tennessee has an obligation to take all prudent
    steps to secure, protect, and preserve this right.
    If for no other reason, resolution of the problem which caused the City to file its complaint
    in this case benefits not only the citizens of Elizabethton, but the general population of this state by
    securing, protecting and preserving the “right to unpolluted waters.” The City was engaged in the
    exercise of a governmental function as an arm of the state in this case and, accordingly, the City is
    not subject to the indicated statute of limitations.
    NAFI also argues that the City is equitably estopped from pursuing its cause of action under
    the doctrine of laches, arguing that the City unreasonably delayed in asserting its rights. In its brief,
    NAFI alleges that the City was aware that NAFI was dumping material over its sewer line for more
    than thirty years and yet “the City watched and said nothing”and, thereby, acquiesced in the
    dumping.
    Laches is a defense peculiar to courts of equity and is usually applied in the absence of a
    statute of limitations. Clark v. American National Bank and Trust Company of Chattanooga, 
    531 S.W.2d 563
    , 572 (Tenn. Ct. App. 1974). It is based upon the doctrine of estoppel which provides
    “that one may not enforce rights against another when that other has materially relied on some
    conduct of the moving party which is in conflict with his asserted rights.” Hannewald v. Fairfield
    Communities, Inc., 
    651 S.W.2d 222
    , 228 (Tenn. Ct. App. 1983). Laches provides that equity will
    -6-
    not intervene on behalf of a plaintiff who has unreasonably delayed in pursuing his rights,
    Hannewald, id. However, as the Tennessee Supreme Court stated in Bledsoe County v. McReynolds,
    
    703 S.W.2d 123
    , 124,125 (Tenn. 1985), the doctrine of estoppel generally does not apply to the acts
    of public authorities:
    Public agencies are not subject to equitable estoppel or estoppel in pais to the
    same extent as private parties and very exceptional circumstances are required to
    invoke the doctrine against the State and its governmental subdivisions.
    ...
    It is significant to observe that in those Tennessee cases where estoppel was
    applied, or could have been applied, the public body took affirmative action that
    clearly induced a private party to act to his or her detriment, as distinguished
    from silence, non-action or acquiescence. In the instant case the defendants have
    nothing upon which to predicate the essential element of inducement, except
    silence and inaction. (Emphasis added)
    In the matter before us, NAFI references no evidence in the record which shows that the City
    “took affirmative action that clearly induced” NAFI to place the overburden on the City’s easement
    and, accordingly, the doctrine of equitable estoppel and laches do not apply.
    The next issue we address is whether the trial court erred in its award of damages.
    In its memorandum opinion, the trial court stated as follows with respect to the award of
    damages in this case:
    The burden that the Defendant has placed on the city’s easement has
    reduced the value of the easement beneath the waste and cap to zero, as the city
    cannot reasonably access that portion of its sewer line. In light of all of the
    circumstances, the city chose a reasonable method of accessing its sewer line by
    having constructed a new pressurized by-pass sewer line contiguous to the cap
    covered line. The cost of construction of the new line was $1,102,754.00
    principal, plus $2,312,231.00 interest, for a total cost of $3,414,985.001. The
    investment and interest lost due to the cost of the project is not an appropriate
    element of damages, as the Plaintiff will be made whole by being reimbursed by
    the Defendant for the actual reasonable costs for accessing its sewer line, which
    costs were incurred as a result of the Defendant’s acts in making the line
    unreasonably inaccessible.
    1
    As we have noted the amount of damages awarded was subsequently reduced to a lesser amount.
    -7-
    The Defendant argues that the Plaintiff failed to mitigate its damages.
    When the record is considered as a whole, the Plaintiff has acted with reasonable
    care and diligence under the circumstances, and did not enhance its damages.
    With regard to the issue of damages NAFI first contends that “the preponderance of the
    evidence was that the West Interceptor was not damaged and that access to it could have been
    permanently restored for about $140,000.”
    NAFI’s argument that the west interceptor line was not damaged is inapposite. The trial
    court’s award of damages is based upon its finding that the line was no longer subject to reasonable
    access, not that the line was damaged. NAFI’s argument that access to the line could have been
    restored for $140,000.00 is based upon the report and testimony of E. Roberts Alley, an engineering
    expert who appeared as a witness in the case on behalf of NAFI. Apparently the fill over the City’s
    easement covers four manholes which open into the covered sewer line. Mr. Alley proposed that the
    material above the manholes be excavated which would allow for the insertion of pre-manufactured
    ten foot diameter metal cylinders as access channels to each of these manholes. Assuming that this
    solution did allow access to the covered manholes, it would not provide access to the line as a whole.
    In its reply brief, NAFI concedes that a block in the west interceptor “could be such that it could not
    be fixed from a manhole and might require a dig-down repair.” We have already referenced
    testimony of Mr. Coetzee to the effect that a dig down repair under the present circumstances would
    be a time consuming undertaking which could result in a major environmental catastrophe. This
    evidence supports the conclusion that Mr. Alley’s proposed solution of accessing the manholes was
    inadequate and unacceptable. Other evidence in the record does not preponderate to the contrary.
    NAFI next argues that the new sewage system cost the City $2,202,000.00 but that that
    money was spent in lieu of the $1,300,000.00 the City otherwise would have spent to replace a forty
    year old influent pump which was part of the replaced system. NAFI asserts that “the extra
    $900,000.00 gave the City a new modern system in place of an aging one built in the 1950's,
    eliminated the invert siphon under the Watauga River and brought the City other advantages.” NAFI
    contends that the “damages from breach of the easement cannot be more than the net additional cost
    incurred by the City as a result of the breach.”
    While it is true that the new system resulted in incidental benefits to the City, this does not
    belie the fact that the new system constituted a reasonable solution to problem caused by NAFI.
    NAFI’s alternative to the implemented solution was to gain entry to the four manholes and, as we
    have indicated, we do not agree that this would have solved the problem presented. The evidence
    does not preponderate against the finding that construction of the new system was the only proposal
    presented that constituted a reasonable solution to the overburden problem.
    NAFI also contends that the City failed to mitigate its damages in this case.
    A plaintiff has the duty to exercise reasonable care and diligence to avoid loss or minimize
    damages. Haynes v. Cumberland Builders, Inc., 
    546 S.W.2d 228
    , 234 (Tenn. Ct. App. 1976). But
    -8-
    only reasonable action is required of a plaintiff in this regard and a plaintiff is not required to
    mitigate damages if such action is unduly burdensome. Id. In Tampa Electric Company v. Nashville
    Coal Company, 
    214 F. Supp. 647
    , 652 (M.D. Tenn. 1963) the Court states as follows regarding
    limitations on the plaintiff’s duty to mitigate :
    The critical factor in determining fulfillment of a plaintiff’s duty to mitigate is
    whether the method which he employed to avoid consequential injury was
    reasonable under the circumstances existing at the time. The rule with respect to
    mitigation of damages may not be invoked by a contract breaker “as a basis for
    hypercritical examination of the conduct of the injured party, or merely for the
    purpose of showing that the injured person might have taken steps which seemed
    wiser or would have been more advantageous to the defaulter.” In re Kellett
    Aircraft Corp., 
    186 F.2d 197
    , 198-199 (3rd Cir. 1950). As stated in McCormick,
    Damages, Sec. 35 (1935), “a wide latitude of discretion must be allowed to the
    person who by another’s wrong has been forced into a predicament where he is
    faced with a probability of injury or loss. Only the conduct of a reasonable man
    is required of him.”
    In support of its argument that the City failed to mitigate damages, NAFI states that “[i]t is
    virtually self-evident that the problem with fly ash over the sewer line could have been avoided if
    the city had ever objected to the practice.” Contrary to this assertion that the City never objected, we
    note the following letter dated November 11, 1971, from then City Attorney, Walter Curtis, to Dan
    Laws, counsel for NAFI’s predecessor, Beaunit Corporation:
    Dear Dan:
    On August 28, 1957, Beaunit Corporation, then doing business as Beaunit
    Mills, Inc., for and in consideration of the sum of $10,000.00, executed a Deed
    conveying an Easement to the City of Elizabethton, Tennessee, for the purpose of
    installing an Interceptor Sewer Line for the City of Elizabethton, Tennessee. This
    Document is of record in Deed Book 145 at Page 43, in the Register’s office for
    Carter County, Tennessee, and a copy of same is attached hereto for your
    information.
    There is also enclosed herewith a map or survey showing the City Sanitary
    Sewer Line referred to above, in its relation to the wet basin settling ponds now
    being used by Beaunit.
    Examination of this map will show that several hundred feet of the Sewer
    Line, and Two (2) Manholes marked “A” and “B” on the map, are now completely
    covered up, and inaccessible, by reason of the wet basin settling ponds.
    -9-
    I am advised by the City Engineer that in the event of any leakage from the
    settling ponds into the Sewer Line, there would probably be damages incurred at
    our Sewer Treatment Plant in the neighborhood of a million dollars before the
    Plant could be shut down. Moreover, in the event any repair work is ever needed
    on the Line at the points in question, such repair work would be impossible under
    the present existing conditions.
    I have been directed to call this matter to your attention as Counsel for
    Beaunit Corporation with the hope that we can possibly arrange a conference on
    the matter to determine what if anything, needs to be done, or can be done to
    reduce the possible exposure to both the City and Beaunit.
    Your kind consideration of this matter would be greatly appreciated, and
    I am sure that Mr. James Clear, or Mr. John McCready or our City Manager, Mr.
    Robert P. Asbury, Jr., will be glad to answer any questions you have in regards to
    this matter.
    In light of this correspondence, we do not agree with NAFI’s assertion that the City was
    inattentive to the problem created by the constant dumping which continued despite notification.
    As we have indicated, the City’s problem of accessing its sewer line was further exacerbated by the
    capping of the already overburdened easement, an event which was mandated by the DCE in
    consequence of NAFI’s dumping of fly ash. Upon its discovery that the area over the sewer line had
    been capped and the line was no longer accessible without great expense, the City entered into
    negotiations with NAFI in an attempt to resolve the problem. The City ultimately implemented a
    reasonable solution and NAFI was apparently unable to present a viable alternative. Under these
    circumstances and our review of the record, we find no merit in NAFI’s argument that the City failed
    to take reasonable action to mitigate damages in this case.
    As a final matter with respect to the award of damages in this case ,we note that NAFI’s brief
    statement that the requirement that it pay the prospective cost of financing the new sewer system “is
    unwarranted and unprecedented.” NAFI presents no authority to support its argument that the trial
    court should not have included these financing costs in its award of damages. Accordingly, the trial
    court’s decision in this regard is affirmed.
    NAFI next argues that the parties’ practical construction of the easement authorized it to
    dump fly ash on the surface over the City’s sewer line because “for more than 30 years the City, as
    grantee, acted as if it had no right to stop NAFI from using the land above the sewer line as a
    landfill.”
    The rule of practical construction provides that the interpretation placed upon a contract by
    the parties thereto as evidenced by their acts will be adopted by the court. Galleria Associates, L.P
    v. Mogk, 
    34 S.W.3d 874
    , 877 (Tenn. Ct. App. 2000). However, the rule of practical construction is
    only applicable if “the language used by the parties to the contract is indefinite or ambiguous, and
    -10-
    hence of doubtful construction.” Fidelity-Phenix Fire Ins. Co. of New York v. Jackson, et al., 
    181 S.W.2d 625
     (Tenn. 1944). The easement granted to the City in the matter sub judice is neither
    ambiguous nor indefinite and states in pertinent part as follows:
    It is the intention of this instrument to convey only such rights or easements over
    said land as is reasonably necessary to construct said sewer interceptor line, and
    to maintain the same ... .
    It is beyond dispute that an overburdening of the sewer line with fly ash and other material
    interfered with the City’s clearly articulated right under the easement to maintain the line.
    Accordingly, the rule of practical construction is not applicable. Even if the rule were applicable in
    this case evidence hitherto referenced in this opinion contradicts NAFI’s assertion that the City acted
    as if it had no right to stop NAFI from dumping fly ash over its sewer line.
    The final issue presented in this appeal is whether the trial court erred in refusing to strike
    from the record findings with respect to defendant Charles K. Green.
    Charles K. Green became president and chief executive officer of North American Rayon
    Corporation, NAFI’s predecessor in title, in 1987. He subsequently became the corporation’s sole
    owner and changed its name to North American Fibers, Inc. In its complaint, the City avers that
    Charles K. Green is the alter ego of the named corporate defendants and that he “transfers property
    between his companies, loans himself money from his companies, controls the entire operations and
    employee complements of each company, and deals with each company as if it were a sole
    proprietorship.” The complaint further avers that “[t]he defendants are one and the same entity for
    purposes of this civil action.” As set forth in its memorandum opinion, the trial court agreed that
    Mr.Green was the alter ego of the defendant corporations and that the defendant corporations were
    the alter egos of each other. However, the trial court also concluded that no liability attached with
    regard to Mr. Green because the City “had not proven by a preponderance of the evidence that any
    alter ego act of Green, or any alter ego act of the corporations, legally or proximately caused the
    unreasonable and substantial burden on the Plaintiff’s sewer easement.” NAFI argues that since the
    trial court concluded that it did not matter whether Mr. Green was the alter ego of the defendant he
    should not be embarrassed by findings of the court relative to its determination in this regard.
    Accordingly, NAFI argues that the trial court erred in failing to delete from the record these
    “embarrassing” findings.
    It is our determination that the trial court did not abuse its discretion in failing to delete any
    of its findings with respect to Charles K. Green. In any event, no supporting authority is cited in
    support of this argument and, therefore, the issue is waived. As recognized in State v. Brown, 
    795 S.W.2d 689
    , 698 (Tenn. Cr. App. 1990):
    Failure of a defendant to cite authority for propositions in his argument on
    appeal constitutes waiver of the issue. State v. Houston, 
    688 S.W.2d 838
     (Tenn.
    Crim. App. 1984); Moorman v. State, 
    577 S.W.2d 473
     (Tenn. Crim. App. 1978).
    -11-
    The brief of the appellant should contain an argument setting forth the contentions
    of the appellant with respect to the issues presented with citations to the
    authorities and appropriate references to the record.
    For the foregoing reasons the judgment of the trial court is affirmed and the cause is
    remanded for further action consistent with this opinion. Costs of appeal are adjudged against North
    American Fibers, Inc.
    _________________________________________
    SHARON G. LEE, JUDGE
    -12-