Stones River Utilities, Inc. v. Metropoltian Government of Nashville, Davidison County, Tennessee - Concurring ( 1995 )


Menu:
  • STONES RIVER UTILITIES, INC.,    )
    )
    Plaintiff/Appellant,      )
    )         Appeal No.
    )         01-A-01-9505-CH-00217
    VS.                              )
    )         Davidson Chancery
    )         No. 94-1665-III
    METROPOLITAN GOVERNMENT OF )
    NASHVILLE, DAVIDSON COUNTY,      )
    TENNESSEE, acting by and through
    the ELECTRIC POWER BOARD and )
    )
    FILED
    d/b/a "NASHVILLE ELECTRIC        )                             Oct. 25, 1995
    SERVICE" or "NES,"               )
    )                         Cecil Crowson, Jr.
    Defendant/Appellee.       )                             Appellate Court Clerk
    COURT OF APPEALS OF TENNESSEE
    MIDDLE SECTION AT NASHVILLE
    APPEALED FROM THE CHANCERY COURT OF DAVIDSON COUNTY
    AT NASHVILLE, TENNESSEE
    THE HONORABLE ROBERT S. BRANDT, CHANCELLOR
    STANLEY M. CHERNAU
    R. GARRY CHAFFIN
    CHERNAU, CHAFFIN & BURNSED
    424 Church Street
    Suite 1750
    Nashville, Tennessee 37219
    Attorneys for Plaintiff/Appellant
    CYRUS L. BOOKER
    CARLA G. FOX
    BOOKER & ASSOCIATES
    First American Center
    315 Deaderick Street
    Suite 1280
    Nashville, Tennessee 37238-1280
    Attorneys for Defendant/Appellee
    AFFIRMED IN PART; REVERSED IN PART;
    AND REMANDED
    BEN H. CANTRELL, JUDGE
    CONCUR:
    TODD, P.J., M.S.
    KOCH, J.
    OPINION
    This is a contract dispute in which the chancellor found that the
    uncontradicted proof showed that the plaintiff had no cause of action for the acts
    alleged in the complaint. We reverse on the single ground of estoppel and remand
    for further proceedings on that issue alone.
    I.
    In 1993 Stones River Utilities, Inc. secured a contract to supply meter
    readers to Nashville Electric Service on an as needed basis. The specifications sent
    out soliciting bids on the work stated: "The Contractor will furnish a maximum of
    fifteen (15) Contract Meter Readers with twelve (12) Contract Meter Readers normally
    being used on an as needed basis as determined by NES." Stones River was the
    successful bidder and signed an agreement including the following provisions:
    It is expressly understood that NES is not required to
    assign any amount of work or any number of projects to
    the contractor. The necessity of such work, and the
    assignment thereof to the contractor is left solely and
    exclusively to the judgment and determination of NES.
    *    *    *
    Either party may terminate this contract without cause by
    giving the other party at least thirty (30) days notice in
    writing.
    After securing the contract, Stones River sought financing to purchase
    new trucks for its meter readers but ran into difficulty because of the cancellation
    clause in the contract. NES's general counsel agreed to clarify that provision and sent
    Stones River a letter on June 9, 1993 containing the following:
    -2-
    It is standard policy of NES that all of its service
    contracts state "... NES is not required to assign any
    amount of work or any number of projects ...", and further,
    to have a 30-day notice of cancellation of the contract.
    NES is in the business of distributing electricity,
    and as such, uses meters to record the amount of
    electricity used by its customers. In order to know how
    much is used, NES has to have individuals to read these
    meters. As long as NES is in this business, the program
    of reading meters will always be utilized.
    As to the 30-day notice of cancellation, NES
    reserves this right in the event the contractor does not
    fulfill the terms of the contract.
    I hope this clarifies the matter for you.
    The letter was shown to the truck dealer, and subsequently, Stones River was able
    to finance the new vehicles.
    On January 10, 1994 NES sent a letter terminating the contract. The
    letter cited a decision of "current management at NES" to reorganize the meter
    reading function and return it to "permanent NES employees."           Stones River
    registered a protest and on February 4, 1994, NES sent another letter stating, "Due
    to recent announcements and the undetermined effects on the meter reading function,
    the action to terminate the above contract has been rescinded. The purpose of this
    action is to keep options open to handle any meter reading contingencies."
    Stones River filed this action on February 16, 1994 alleging that NES
    breached the contract and an implied covenant of fair dealing and was estopped to
    rely on the sections of the contract quoted above. Despite the breakdown in the
    parties' relations, from late February, 1994 through June, 1994, NES assigned enough
    work to Stones River to occupy two meter readers and a lead person. After that,
    although the contract remained open, NES did not assign any work to contract meter
    readers.
    -3-
    II.
    The chancellor granted summary judgment to NES. In his memorandum
    opinion the chancellor said, "Stones River may or may not have some other cause of
    action based upon representations made to it by NES after the contract was executed,
    but NES did not breach the contract." We agree that NES could not be liable on the
    original agreement because it did not obligate NES to assign any work to Stones River
    and it gave NES the right to terminate the agreement on thirty days notice.
    On appeal, however, Stones River argues waiver, estoppel, and
    modification of the contract (based on the events that took place after the agreement
    was signed). With respect to the waiver and modification contentions, we do not find
    any support for them in the record. Even if the letter issued on June 9, 1993 is
    considered as somehow altering the written agreement, it does not commit NES to
    furnishing any level of work to Stones River. Arguably, it could be taken as a
    modification of the right to terminate the contract without cause; but the paragraph
    referring to meter readers, as a matter of law, is too vague for a reasonable person
    to place any reliance on it.
    With respect to the estoppel issue, Stones River's president said in an
    affidavit filed in opposition to the motion for summary judgment that, on May 14th,
    1993, she met with members of NES's staff who strongly suggested that Stones River
    obtain new vehicles for use in performing the contract. Specifically, she said, "NES
    further assured us that we would have twelve readers every day for the duration of the
    contract, if we bought new trucks. Therefore, at the urging of NES we decided to
    purchase all new vehicles." Earlier, when she gave her deposition, she was asked if
    NES told her she had to buy new vehicles. She replied:
    No, I don't think they said you had to purchase new
    vehicles, because they couldn't say that. I had to -- when
    -4-
    the specs called for properly functioning vehicles, but they
    said we needed new vehicles. And they made that very
    clear.
    In its complaint Stones River made the following allegations:
    8.     Plaintiff would show that when it received
    the contract it was necessary to acquire thirteen vehicles.
    Plaintiff's President, one Jamie Wilson, on May 14, 1993
    met with NES representatives Melvin Bess, Tyler Mills,
    and Don Hill to discuss the start-up of the contract and the
    necessity for the purchasing of vehicles.
    *    *    *
    11.      Plaintiff alleges that at this meeting Ms.
    Wilson was advised by the NES representatives that
    Plaintiff would have twelve routes on a daily basis and
    that if Plaintiff's performance was good the contract would
    be extended or renewed, which gave further credence to
    the insistence that Plaintiff purchase new vehicles.
    An action based on estoppel may be brought where the promises of one
    party are relied on by another party to his detriment. In Foster & Creighton Co. v.
    Wilson Contracting, 
    579 S.W.2d 422
    (Tenn. App. 1979), this court said:
    [W]hen one man by his promise induces another to
    change his situation, a repudiation of the promise would
    amount to a fraud. Where one makes a promise which
    the promisor should reasonably expect to induce action or
    forbearance of a definite and substantial character on the
    part of the promisee, and where such promise does in fact
    induce such action or forebearance, it is binding if
    injustice can be avoided only by enforcement of the
    
    promise. 579 S.W.2d at 427
    .
    We are of the opinion that there are contested facts in this case that
    make summary judgment on the estoppel issue improper. See Byrd v. Hall, 
    847 S.W.2d 208
    (Tenn. 1993). Therefore, we reverse the judgment below on that point
    -5-
    and remand the cause to the trial court for further proceedings on the issue of
    estoppel only. Otherwise, the judgment is affirmed.
    Tax the costs on appeal to the appellee.
    _____________________________
    BEN H. CANTRELL, JUDGE
    CONCUR:
    _______________________________
    HENRY F. TODD, PRESIDING JUDGE
    MIDDLE SECTION
    _______________________________
    WILLIAM C. KOCH, JR., JUDGE