84 Lumber Company v. R. Bryan Smith ( 2010 )


Menu:
  •                 IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    September 1, 2010 Session
    84 LUMBER COMPANY v. R. BRYAN SMITH, ET AL.
    Appeal from the Circuit Court for Washington County
    No. 27548    Jean A. Stanley, Judge
    No. E2010-00292-COA-R3-CV - FILED OCTOBER 28, 2010
    84 Lumber Company (“84 Lumber”) sued R. Bryan Smith (“Smith”) and Allstates Building
    Systems, LLC (“Allstates”) for a balance owed on an open account. Both sides filed motions
    for summary judgment. The Circuit Court granted 84 Lumber summary judgment, and
    entered a judgment against Smith and Allstates in the amount of $27,611.31 plus attorney’s
    fees and costs in the amount of $6,500.00. Smith appeals to this Court. We find that Smith
    did not sign the credit application in his personal capacity and, therefore, did not guarantee
    Allstates’ debt. We reverse the grant of summary judgment against Smith, and grant
    summary judgment to Smith. We affirm the grant of summary judgment against Allstates.
    Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Circuit Court
    Reversed, in part; Affirmed, in part; Case Remanded
    D. M ICHAEL S WINEY, J., delivered the opinion of the Court, in which J OHN W. M CC LARTY,
    J. joined. C HARLES D. S USANO, J R., J. separate concurring and dissenting opinion.
    Rick J. Bearfield, Johnson City, Tennessee, for the appellant, R. Bryan Smith.
    John M. Neal, Knoxville, Tennessee, for the appellee, 84 Lumber Company.
    OPINION
    Background
    84 Lumber sued Smith and Allstates in the General Sessions Court for
    Washington County alleging that Smith and Allstates were indebted to 84 Lumber for
    approximately $23,000 on an open account that was past due and owing. The General
    Sessions Court dismissed the claims against both defendants after a trial.
    84 Lumber then appealed to the Circuit Court (“Trial Court”) for Washington
    County. Both 84 Lumber and Smith filed motions for summary judgment. The operative
    document in this case is the commercial credit application, which provides, in pertinent part:
    BY SIGNING BELOW I HEREBY CERTIFY THAT I AM THE OWNER,
    GENERAL PARTNER OR PRESIDENT OF THE ABOVE BUSINESS,
    AND I DO UNCONDITIONALLY AND IRREVOCABLY PERSONALLY
    GUARANTEE THIS CREDIT ACCOUNT AND PAYMENTS OF ANY
    AND ALL AMOUNTS DUE BY THE ABOVE BUSINESS. AND THAT I
    HAVE READ ALL OF THE TERMS AND CONDITIONS ON THE
    REVERSE SIDE OF THIS APPLICATION AND UNDERSTAND AND
    AGREE TO THE SAME. AND THAT ALL OF THE INFORMATION
    CONTAINED IN THIS APPLICATION IS TRUE AND CORRECT TO THE
    BEST OF MY KNOWLEDGE.
    Below the above quoted paragraph there is a line for the “Applicant” to sign, which Smith
    executed as “R. Bryan Smith, President.” The “Applicant” is identified at the top of the
    credit application as Allstate Building System, LLC.
    After a hearing on the motions for summary judgment, the Trial Court entered
    its order on December 16, 2009 finding and holding that Smith had personally guaranteed
    Allstates’ debt. The Trial Court granted summary judgment to 84 Lumber and entered a
    judgment against Smith and Allstates in the amount of $27,611.31 plus attorney’s fees and
    costs in the amount of $6,500.00. Smith appeals to this Court.
    Discussion
    Although not stated exactly as such, Smith raises one issue on appeal: whether
    the Trial Court erred in granting summary judgment to 84 Lumber against Smith and not
    granting summary judgment to Smith.
    -2-
    Our Supreme Court reiterated the standard of review in summary judgment
    cases as follows:
    The scope of review of a grant of summary judgment is well
    established. Because our inquiry involves a question of law, no presumption
    of correctness attaches to the judgment, and our task is to review the record to
    determine whether the requirements of Rule 56 of the Tennessee Rules of Civil
    Procedure have been satisfied. Hunter v. Brown, 
    955 S.W.2d 49
    , 50-51 (Tenn.
    1997); Cowden v. Sovran Bank/Cent. S., 
    816 S.W.2d 741
    , 744 (Tenn. 1991).
    A summary judgment may be granted only when there is no genuine
    issue of material fact and the moving party is entitled to judgment as a matter
    of law. Tenn. R. Civ. P. 56.04; Byrd v. Hall, 
    847 S.W.2d 208
    , 214 (Tenn.
    1993). The party seeking the summary judgment has the ultimate burden of
    persuasion “that there are no disputed, material facts creating a genuine issue
    for trial . . . and that he is entitled to judgment as a matter of law.” 
    Id. at 215
    .
    If that motion is properly supported, the burden to establish a genuine issue of
    material fact shifts to the non-moving party. In order to shift the burden, the
    movant must either affirmatively negate an essential element of the
    nonmovant’s claim or demonstrate that the nonmoving party cannot establish
    an essential element of his case. 
    Id.
     at 215 n.5; Hannan v. Alltel Publ’g Co.,
    
    270 S.W.3d 1
    , 8-9 (Tenn. 2008). “[C]onclusory assertion[s]” are not sufficient
    to shift the burden to the non-moving party. Byrd, 
    847 S.W.2d at 215
    ; see also
    Blanchard v. Kellum, 
    975 S.W.2d 522
    , 525 (Tenn. 1998). Our state does not
    apply the federal standard for summary judgment. The standard established
    in McCarley v. West Quality Food Service, 
    960 S.W.2d 585
    , 588 (Tenn. 1998),
    sets out, in the words of one authority, “a reasonable, predictable summary
    judgment jurisprudence for our state.” Judy M. Cornett, The Legacy of Byrd
    v. Hall: Gossiping About Summary Judgment in Tennessee, 
    69 Tenn. L. Rev. 175
    , 220 (2001).
    Courts must view the evidence and all reasonable inferences therefrom
    in the light most favorable to the non-moving party. Robinson v. Omer, 
    952 S.W.2d 423
    , 426 (Tenn. 1997). A grant of summary judgment is appropriate
    only when the facts and the reasonable inferences from those facts would
    permit a reasonable person to reach only one conclusion. Staples v. CBL &
    Assocs., Inc., 
    15 S.W.3d 83
    , 89 (Tenn. 2000). In making that assessment, this
    Court must discard all countervailing evidence. Byrd, 
    847 S.W.2d at 210-11
    .
    Recently, this Court confirmed these principles in Hannan.
    -3-
    Giggers v. Memphis Housing Authority, 
    277 S.W.3d 359
    , 363-64 (Tenn. 2009).
    In resolving a dispute concerning contract interpretation, our task is to ascertain
    the intention of the parties based upon the usual, natural, and ordinary meaning of the
    contract language. Planters Gin Co. v. Fed. Compress & Warehouse Co., Inc., 
    78 S.W.3d 885
    , 889-90 (Tenn. 2002)(citing Guiliano v. Cleo, Inc., 
    995 S.W.2d 88
    , 95 (Tenn. 1999)).
    A determination of the intention of the parties “is generally treated as a question of law
    because the words of the contract are definite and undisputed, and in deciding the legal effect
    of the words, there is no genuine factual issue left for a jury to decide.” Planters Gin Co.,
    
    78 S.W.3d at
    890 (citing 5 Joseph M. Perillo, Corbin on Contracts, § 24.30 (rev. ed. 1998);
    Doe v. HCA Health Servs. of Tenn., Inc., 
    46 S.W.3d 191
    , 196 (Tenn. 2001)).
    As pertinent to this appeal, Tenn Code Ann. § 29-2-101 provides:
    29-2-101. Writing required for action. – (a) No action shall be brought:
    ***
    (2) To charge the defendant upon any special promise to answer for the debt,
    default, or miscarriage of another person;
    ***
    unless the promise or agreement, upon which such action shall be brought, or
    some memorandum or note thereof, shall be in writing, and signed by the party
    to be charged therewith, or some other person lawfully authorized by such
    party.
    
    Tenn. Code Ann. § 29-2-101
     (Supp. 2009).
    As this Court has stated:
    The general rule is that a corporate officer’s signature preceded by a
    corporation’s name and followed [by] a designation of the signature’s
    corporate capacity is evidence that the officer was acting as an agent of the
    corporation. See Bill Walker & Assoc., Inc. v. Parrish, 
    770 S.W.2d 764
    , 770
    (Tenn. App. 1988). This general rule, however, does have exceptions when
    the contract reveals a different intention. 
    Id.
    It is possible for an officer of a corporation
    -4-
    to avoid personal liability by signing his name and
    adding his title and the name of the corporation.
    However such a signature does not produce the
    presumptive effect of a signature in which the
    name of the corporation appears first followed by
    the word, “by” or “per” and the name of the
    corporation. In the former case, additional
    evidence, such as test of the instrument or
    evidence of the joint intent of the parties, would
    be required to establish that only the corporation
    was to be bound. In the latter case, the intention
    of the parties is self evident from the form of the
    signature.
    Cone Oil Co., Inc. v. Green, 
    669 S.W.2d 662
    , 664 (Tenn. App. 1983).
    Fleet One, LLC v. Cook, No. M2001-03048-COA-R3-CV, 
    2002 Tenn. App. LEXIS 395
    , at
    **6-7 (Tenn. Ct. App. June 5, 2002), no appl. perm. appeal filed.
    To begin, we note that in its brief on appeal 84 Lumber cites Pennsylvania law
    in addition to Tennessee law. The contract in the instant case states that it is to be construed
    in accordance with Pennsylvania law. In the Trial Court, however, neither party raised an
    issue regarding whether Pennsylvania law should be applied. Instead, both parties cited
    Tennessee law to the Trial Court, and the Trial Court, not surprisingly, applied Tennessee
    law. Because this issue was raised for the first time on appeal, we consider it waived, and
    we will apply Tennessee law. See Crossley Const. Corp. v. Nat. Fire Ins. Co. of Hartford
    wherein we stated:
    Except for some limited exceptions not applicable here,
    we will not consider issues, let alone claims, raised for the first
    time on appeal. See City of Cookeville ex rel. Cookeville Reg’l
    Med. Ctr. v. Humphrey, 
    126 S.W.3d 897
    , 905-06 (Tenn. 2004)
    (noting the general rule that “questions not raised in the trial
    court will not be entertained on appeal.” (quoting Lawrence v.
    Stanford, 
    655 S.W.2d 927
    , 929 (Tenn. 1983))).
    Crossley Const. Corp. v. Nat. Fire Ins. Co. of Hartford, 
    237 S.W.3d 652
    , 656 (Tenn. Ct. App.
    2007).
    We next note that both parties cite to several cases that involve a guaranty
    -5-
    document containing a signature or signatures separate and apart from the contract with its
    signature or signatures that formed the underlying indebtedness. E.g., Kelso Oil Co., Inc. v.
    East West Truck Stop, Inc., 
    102 S.W.3d 655
     (Tenn. Ct. App. 2002); Kubota Tractor Corp.
    v. Fugate Implement Co., Inc., 
    1989 Tenn. App. LEXIS 398
     (Tenn. Ct. App. June 2, 1989),
    no appl. perm. appeal filed; Cone Oil Co., Inc. v. Green, 
    669 S.W.2d 662
     (Tenn. Ct. App.
    1983). In the case now before us on appeal we are faced with a situation wherein the one
    signature at issue appears only on the document which created the contractual indebtedness.
    There is no separate guaranty document and no separate signature involved in this case. As
    such we find these cited cases to be easily distinguishable from the instant case.
    84 Lumber argues on appeal, in part, that Creative Resource Management, Inc.
    v. Soskin, should control the outcome in this case because the language in the Creative
    Resource Management, Inc. contract was similar to the language contained in the contract
    in the instant case. Creative Resource Management, Inc. v. Soskin, No. 01-A-01-9808-CH-
    00016, 
    1998 Tenn. App. LEXIS 788
     (Tenn. Ct. App. Nov. 25, 1998), no appl. perm. appeal
    filed. Importantly, however, the contract in Creative Resource Management, Inc. also
    contained definitions for pronouns used within the contract and the entire contract read in
    light of those defined terms compelled the result that the signator had signed in his personal
    capacity and was personally liable for the debt.
    In contrast, the contract in the case now before us does not contain any
    definitions for the terms used within the contract. A careful reading of the contract, however,
    shows that on its second page the contract makes a distinction between the terms ‘Applicant’
    and ‘Guarantor.’ Specifically, while the majority of the contract provisions refer only to the
    ‘Applicant,’ paragraphs eight and nine contain the language: “APPLICANT AND
    PERSONAL GUARANTOR(S) AGREE …,” and “Applicant and Personal Guarantor(s)
    hereby authorize …” respectively. Smith signed the contract on the signature line labeled
    “Applicant” and added his title of “President” after his signature. Smith did not sign the
    contract in any other place.
    We find this case to be factually analogous to Fleet One, LLC v. Cook, No.
    M2001-03048-COA-R3-CV, 
    2002 Tenn. App. LEXIS 395
     (Tenn. Ct. App. June 5, 2002),
    no appl. perm. appeal filed; and Topline Auto. Eng’g, Inc. v. Arney, C.A. 66, 
    1989 Tenn. App. LEXIS 28
     (Tenn. Ct. App. Jan. 20, 1989), no appl. perm. appeal filed. In Fleet One,
    LLC, the contract contained the words: “I assume personal and individual responsibility and
    liability, and guarantee payment of all charges due and payable ….” Fleet One, LLC, 
    2002 Tenn. App. LEXIS 395
     at *3. The contract in Topline Auto. Eng’g, Inc. contained the
    following language: “the undersigned does jointly and severally personally guarantee to pay
    and be responsible for payment of all sums, balances, and accounts due seller by buyer ….”
    Topline Auto. Eng’g, Inc., 
    1989 Tenn. App. LEXIS 28
     at *1.
    -6-
    Despite the personal guarantee language, in both the Fleet One, LLC contract
    and the Topline Auto. Eng’g, Inc. contract, this Court held that the signator in each case had
    signed in a representative capacity only and not in a personal capacity. Specifically, the Fleet
    One, LLC contract was found to be too vague to constitute a personal guarantee with “no
    logical variation between the debtor and guarantor.” Fleet One, LLC, 
    2002 Tenn. App. LEXIS 395
     at *10. In Topline Auto. Eng’g, Inc., this Court determined that two signatures
    were required “one, for the credit application, and another for the guaranty,” but that only one
    signature appeared on the document. Topline Auto. Eng’g, Inc., 
    1989 Tenn. App. LEXIS 28
    at *3.
    In the case now before us on appeal, a careful and thorough reading of the
    entire contract supports the conclusion that Smith signed the contract only for the
    “Applicant,” Allstates, in his capacity as the president of the “Applicant.” There is no
    question but that the “Applicant” in the contract is Allstates. It was this signature of Smith
    as president of Allstates that bound Allstates to its obligations under the contract, including
    liability for reasonable attorney fees if the “ACCOUNT IS PLACED FOR COLLECTION.”
    It is clear that the Trial Court properly found Allstates contractually liable under the contract
    signed by Smith as president of Allstates. The Trial Court granted judgment against not just
    Smith but also against Allstates “in the amount of $27,611.31, together with Plaintiff’s
    reasonable attorney’s fees and costs in the amount of $6500.00.” The only basis the Trial
    Court had for awarding attorney fees against Allstates in 84 Lumber’s judgment was the
    specific provision contained in the credit application providing for reasonable attorney fees.
    The Trial Court found that Allstates was contractually obligated for the attorney fees as
    provided in the credit application based upon Smith’s signature as president of Allstates.
    Unless Smith signed the credit application on behalf of Allstates, there would be no legal
    basis for awarding 84 Lumber its attorney fees against Allstates as the Trial Court did.
    In order for Smith also to have been personally liable under this contract, Smith
    needed to have executed the contract a second time showing that he was signing as the
    guarantor and not for the “Applicant.” This he did not do. There is no writing signed by
    Smith showing that he would answer for the debt of Allstates. We, therefore, hold that Smith
    cannot be held personally liable on this debt. We reverse the summary judgment against
    Smith.
    There are no genuine disputed issues of material fact, and, as a matter of law,
    Smith cannot be held liable for Allstate’s debt. We, therefore, grant summary judgment in
    favor of Smith. The remainder of the Trial Court’s judgment is affirmed.
    -7-
    Conclusion
    The judgment of the Trial Court granting summary judgment to 84 Lumber
    against Smith is reversed, and Smith is granted summary judgment. The remainder of the
    judgment is affirmed, and this cause is remanded to the Trial Court for collection of the costs
    below. The costs on appeal are assessed against the appellee, 84 Lumber Company.
    _________________________________
    D. MICHAEL SWINEY, JUDGE
    -8-