Rebound Care Corp. v. Universal Constructors ( 2000 )


Menu:
  •                     IN THE COURT OF APPEALS OF TENNESSEE
    AT NASHVILLE
    REBOUND CARE CORPORATION, ET AL. v. UNIVERSAL
    CONSTRUCTORS, INC.
    A Direct Appeal from the Chancery Court for Davidson County
    No. 94-444-I  The Honorable Irvin H. Kilcrease, Jr., Chancellor
    No. M1999-00868-COA-R3-CV - Decided June 13, 2000
    This case involves a dispute under a construction contract between the owner and the
    contractor. The owner sued the contractor in chancery court, and the contractor’s answer, among
    other things, asserted that plaintiff’s claim was subject to arbitration. Neither party demanded
    arbitration, and the case continued in chancery court with discovery and other proceedings for
    approximately three years, when the contractor filed a motion to dismiss or for summary judgment
    premised on the owner’s failure to comply with conditions precedent in the contract. Alternatively,
    the contractor moved to stay the proceedings until plaintiff submitted the claim to arbitration
    pursuant to the contract. The trial court found that the contract provided for arbitration and that the
    contractor had not waived its right to arbitration. The court granted the motion for summary
    judgment to the extent that the proceedings in the case were stayed until the owner’s compliance
    with the conditions precedent in the contract. In compliance with the court’s order, the owner
    submitted the case to arbitration which resulted in an award for the contractor. Subsequently, the
    trial court granted Universal’s motion to confirm the arbitration award and dismissed the owner’s
    complaint with prejudice. The owner has appealed.
    Tenn.R.App.P. 3, Appeal as of Right; Judgment of the Chancery Court is Vacated in Part,
    Affirmed in Part and Remanded
    CRAWFORD , P.J., W.S., delivered the opinion of the court, in which HIGHERS , J., and FARMER , J.,
    joined.
    Paul C. Ney, Jr., Gregory Mitchell, Nashville, For Appellant
    Darrell G. Townsend, Derrick C. Smith, Nashville, For Appellee
    OPINION
    Plaintiff, Rebound Care Corporation, d/b/a Open Arms Care Corporation (Rebound), appeals
    -1-
    from the order1 of the chancery court dismissing its complaint against defendant, Universal
    Constructors, Inc.(Universal).
    On January 3, 1994, Rebound filed its complaint against Universal.2 The complaint alleges
    that in 1989 and 1990, Rebound contracted with Universal in four separate contracts for Universal
    to act as the general contractor for the construction of thirty-two intermediate care facilities and four
    day program service centers in several areas in Tennessee. The contracts are attached as exhibits to
    the complaint and incorporated therein. The complaint avers that in July, 1991, Rebound started
    learning about problems with various parts of the Nashville facility and notified Universal and others
    of the problems and sought repairs. Further problems developed, and each time Universal was
    notified of the problems. It was represented to Rebound that the construction was not defective, but
    that Universal would investigate and recommend solutions. The complaint further avers that because
    of the many problems, Rebound retained the services of a construction consultant in 1993, and in
    January, 1994, the consultant completed the investigation and issued his report which detailed
    construction and design deficiencies. The complaint lists substantial defects that were discovered.
    The complaint alleges that Universal became aware of numerous, unauthorized deviations, allowed
    same to exist, and had defects that were, in fact, concealed from Rebound, resulting in
    misrepresentations and fraud on the part of Universal. The complaint further avers that Universal
    took actions and made representations that caused Rebound to delay in the filing of the suit.
    Rebound further alleges that Universal breached its contract by, among other things:
    a. Failing to construct the Facilities in accordance with the plans and
    specifications for the project;
    b. Failing to employ subcontractors with adequate skills and
    knowledge to execute and perform work on the Facilities in a skillful
    and workmanlike fashion and otherwise failing to ensure that the
    work was done in a skillful and workmanlike fashion;
    c. Failing to correct nonconforming work performed by Universal
    and by subcontractors under Universal’s supervision; and
    1
    The order was made final pursuant to Tenn.R.Civ.P. 54.02, since the case against one other
    defendant is still pending.
    2
    The original complaint was filed against Universal and David, Stokes, Chilton
    Collaborative, P.C., an architectural firm. The complaint states that the action is related to a
    previously filed case in chancery court, Rebound Care Corporation, d/b/a Open Arms Care
    Corporation versus Barge, Wagonner, Sumner & Cannon, et al. The trial court consolidated the
    action, and on August 25, 1995, Rebound filed a Consolidated Amended Complaint against
    Universal and the other named defendants in the two actions. Our references in the Opinion to the
    complaint and the answer will refer to the Consolidated Amended Complaint and Universal’s answer
    thereto.
    -2-
    d. Failing to identify and bring to Rebound’s and/or the Project
    Architect’s attention problems with the site and construction design
    of one or more Facilities;
    e. Failing to construct the Facilities in a good faith and reasonable
    manner and in accordance with industry standards and legal
    requirements;
    f. Breaching express warranties;
    g. Breaching implied warranties of good workmanship and materials
    and of habitability;
    h. Failing to oversee and inspect construction of the Facilities in a
    good faith manner and in accordance with reasonable construction
    practices;
    i. Failing to fulfill its duty to remedy the defects made known to it;
    j. Failing to obtain written or other approval for changes to plans and
    specifications;
    k. Failing to give monetary credit to Rebound for labor, material, and
    other changes resulting in cost reductions; and
    l. Submitting false and incorrect applications for payment.
    The complaint further alleges that Universal along with the other defendants were negligent
    in the work performed which resulted in damages to Rebound. The complaint also avers that
    Universal was guilty of promissory fraud and fraudulent misrepresentations in commercial
    transactions in the various particulars set out in the complaint. Rebound also relies upon a violation
    of the Consumer Protection Act on the part of Universal.
    Universal’s answer to the complaint denies the material allegations against it and joins issue
    thereon. As an affirmative defense, Universal avers that the contract between the parties provides
    that any dispute should be submitted to arbitration, and that therefore the complaint should be
    dismissed. Universal further relies upon the applicable statute of limitations, T.C.A. § 28-3-201 et
    seq. and § 28-3-105.
    On December 16, 1997, Universal filed a motion to dismiss or for summary judgment
    premised on the failure of Rebound to comply with the conditions precedent in the contracts between
    the parties and the bar of the statute of limitations. In the alternative, Universal moved the court to
    stay the proceedings until plaintiff properly invokes the procedure of Article 4 of the general
    -3-
    conditions of the contract, including submission of the matter to arbitration. The trial court entered
    its order on Universal’s motion on May 20, 1998, which states in pertinent part:
    [Rebound] entered into contracts with Universal for Universal
    to construct eight (8) group homes. The construction contracts
    between the parties were put on American Institute of Architect’s
    (“AIA”) contract forms. (AIA Form 101). Incorporated in the
    contract forms were AIA general Conditions, Document A201.
    The AIA General Conditions, Document A201, contain a
    procedure for the resolution of disputes before suit may be filed in
    court. Ultimately, any claims must be submitted to arbitration. The
    Court finds that Rebound/MSC failed to submit the claims against
    Universal to arbitration, which is a condition precedent to pursuing
    the instant litigation against Universal, and finds that Universal has
    not waived its right to have the dispute submitted to arbitration. The
    Court makes no other findings of fact or conclusions of law in this
    matter.
    As an alternative remedy, Universal seeks to have this case
    stayed pending plaintiff Rebound’s compliance with the conditions
    precedent set forth in the AIA contract documents.
    On consideration of the record and Rule 56, Tenn. R. C. P.,
    the court finds that Universal’s motion for Summary Judgment is
    granted to the extent that the proceedings in the case are stayed until
    plaintiff’s Rebound’s compliance with the conditions precedent as
    provided in the AIA contract documents. The court finds it
    unnecessary to consider the remainder of Universal’s motion.
    Universal’s motion to dismiss Rebound’s Complaint, as
    amended, is denied.
    Although objecting to arbitration, Rebound, in compliance with the trial court’s order
    submitted the matter to arbitration. The arbitration resulted in an award in favor of Universal. By
    order entered June 2, 1999, the trial court denied Rebound’s motion to vacate the arbitration award
    and granted Universal’s motion to confirm the award and dismissed Rebound’s complaint. The
    order was made final pursuant to Tenn.R.Civ.P. 54.02. Rebound has appealed and presents two
    issues for review. The first issue for review as stated in Rebound’s brief is:
    1. Whether the Chancery Court erred in resolving factual disputes in
    favor of Universal, the party moving for summary judgment, and
    finding (a) that the contract between Rebound and Universal
    -4-
    contained an arbitration clause and (b) that Universal did not waive
    any arbitration rights it might have had.
    In its interlocutory order leading to the arbitration proceeding, the trial court found that the
    contracts between Rebound and Universal provided for arbitration of the dispute, and that Universal
    had not waived that requirement. This finding by the trial court was pursuant to Universal’s motion
    to dismiss or for summary judgment and was found without an evidentiary hearing. A motion for
    summary judgment should be granted when the movant demonstrates that there are no genuine issues
    of material fact and that the moving party is entitled to a judgment as a matter of law. Tenn. R. Civ.
    P. 56.04. The party moving for summary judgment bears the burden of demonstrating that no
    genuine issue of material fact exists. Bain v. Wells, 
    936 S.W.2d 618
    , 622 (Tenn. 1997). On a
    motion for summary judgment, the court must take the strongest legitimate view of the evidence in
    favor of the nonmoving party, allow all reasonable inferences in favor of that party, and discard all
    countervailing evidence. 
    Id.
     In Byrd v. Hall, 
    847 S.W.2d 208
     (Tenn. 1993), our Supreme Court
    stated:
    Once it is shown by the moving party that there is no genuine issue
    of material fact, the nonmoving party must then demonstrate, by
    affidavits or discovery materials, that there is a genuine, material fact
    dispute to warrant a trial. In this regard, Rule 56.05 [now Rule 56.06]
    provides that the nonmoving party cannot simply rely upon his
    pleadings but must set forth specific facts showing that there is a
    genuine issue of material fact for trial.
    
    Id.
     at 21l (citations omitted) (emphasis in original).
    Summary judgment is only appropriate when the facts and the legal conclusions drawn from
    the facts reasonably permit only one conclusion. Carvell v. Bottoms, 
    900 S.W.2d 23
    , 26 (Tenn.
    1995). Since only questions of law are involved, there is no presumption of correctness regarding
    a trial court's grant of summary judgment. Bain, 
    936 S.W.2d at 622
    . Therefore, our review of the
    trial court’s grant of summary judgment is de novo on the record before this Court. Warren v. Estate
    of Kirk, 
    954 S.W.2d 722
    , 723 (Tenn. 1997).
    Rebound asserts that the contract is ambiguous and there is no proof that the parties intended
    for the general condition to be a part of the contract. Rebound states in its brief: “given the
    extensiveness and potential significance of so many of the provisions of the General Conditions –
    and the lack of necessity of these provisions, the redundancy, and the conflicts with the other terms
    of the contract – it is unreasonable for the Chancery Court to assume that the parties intended such
    a substantial modification of the contracts absent negotiation and absent Universal’s supplying the
    document as part of the contract documents. At minimum, a jury question was presented as to
    whether the parties intended to incorporate into their contracts none, all, or part of the General
    Conditions and, if not, whether such incorporation would have been reasonable under the
    circumstances.”
    -5-
    In Warren v. Metropolitan Gov’t of Nashville & Davidson County, 
    955 S.W.2d 618
     (Tenn.
    Ct. App. 1997), this Court discussed the role of a court in interpreting a contract:
    Courts are to interpret and enforce the contract as written, according
    to its plain terms. Petty v. Sloan, 
    197 Tenn. 630
    , 
    277 S.W.2d 355
    ,
    358 (1955); Home Beneficial Ass’n v. White, 
    180 Tenn. 585
    , 
    177 S.W.2d 545
    , 546 (1944). We are precluded from making new
    contracts for the parties by adding or deleting provisions. Central
    Adjustment Bureau, Inc. v. Ingram, 
    678 S.W.2d 28
    , 37 (Tenn.
    1984); Shell Oil Co. v. Prescott, 
    398 F.2d 592
     (6th Cir. 1968). When
    clear contract language reveals the intent of the parties, there is no
    need to apply rules of construction. An ambiguity does not arise in
    a contract merely because the parties may differ as to interpretation
    of certain of its provisions. Oman Construction Co. v. Tennessee
    Valley Auth., 
    486 F.Supp. 375
     (M.D. Tenn. 1979). A contract is
    ambiguous only when it is of uncertain meaning and may fairly be
    understood in more ways than one; a strained construction may not
    be placed on the language used to find an ambiguity where none
    exists. Empress Health and Beauty Spa, Inc. v. Turner, 
    503 S.W.2d 188
    , 190-91 (Tenn. 1973). We are to consider the agreement as a
    whole in determining whether the meaning of the contract is clear or
    ambiguous. Gredig v. Tennessee Farmers Mut. Ins. Co., 
    891 S.W.2d 909
    , 912 (Tenn. Ct. App. 1994). If a contract is plain and
    unambiguous, the meaning thereof is a question of law for the court.
    Petty v. Sloan, 
    277 S.W.2d at 358
    .
    Id. at 622-23.
    Each of the four AIA contracts at issue is entitled “Standard Form of Agreement Between
    Owner and Contractor” and provides on page 1: “[t]he 1987 edition of AIA Document A201,
    General Conditions of the Contract for Construction, is adopted in this document by reference. Do
    not use with other general conditions unless this document is modified.”
    The General Conditions of the Contract for Construction - 1987 Edition states in paragraph
    3 Arbitration: “[t]he A201 document incorporates ARBITRATION according to the Construction
    Industry Arbitration Rules of the American Arbitration Association.” In addition, in article 9 of the
    contracts, the General Conditions are specified as the General Conditions for Construction, AIA
    Document A201, 1987 Edition.
    The contracts on which Rebound has filed suit clearly and specifically state that the General
    Conditions form a part of the contract and there appears to be no ambiguity in the provision for
    arbitration and the other provisions of the contract. The chancery court correctly found that the
    contracts involved in this case provide for arbitration.
    In this interlocutory order, the trial court also ruled that Universal had not waived the
    -6-
    arbitration provisions of the contracts. Tennessee courts have recognized the value of arbitrating as
    an alternative to litigation. In Arnold v. Morgan Keegan & Co., 
    914 S.W. 2d 445
     (Tenn. 1996), our
    Supreme Court stated:
    [a]rbitration is attractive because it is a more expeditious and final
    alternative to litigation.
    The very purpose of arbitration is to avoid the courts insofar
    as the resolution of the dispute is concerned. The object is to avoid
    what some feel to be the formalities, the delay, the expense and
    vexation of ordinary litigation. Immediate settlement of controversies
    by arbitration removes the necessity of waiting out a crowded court
    docket....
    Arnold, 
    914 S.W.2d at 449
     (quoting Boyd v. Davis, 
    127 Wash.2d 256
    , 
    897 P.2d 1239
    , 1242
    (1995)(en banc) (citation omitted)).
    T.C.A. § 29-5-303 (1999 Supp.) enables courts to make a summary determination in certain
    instances as to whether a party is entitled to arbitration. Upon the application of a party for a
    determination of whether there is an agreement to arbitrate, T.C.A. § 29-5-303 (a) provides that
    from the denial of an existence of an agreement to arbitrate, the court shall proceed summarily to a
    determination of the issue so raised. T.C.A. § 29-5-303 (b) provides that the court may stay an
    arbitration proceeding when there is no agreement to arbitrate and may try such an issue summarily.
    The trial court in the instant case found on motions presented that there was an agreement to
    arbitrate, and we have noted that the trial court correctly made this determination in the summary
    proceeding. The trial court also determined summarily that there had been no waiver of this
    contractual provision.
    Waiver is an intentional relinquishment of a known right. Baird v. Fidelity-Phenix Fire Ins.
    Co., 
    178 Tenn. 653
    , 
    162 S.W.2d 384
     (1942). In Baird, the Court said:
    In the opinion of the Supreme Court of Massachusetts, in
    Farlow v. Ellis et al., 
    15 Gray 229
    , 
    81 Mass. 229
    , at page 231,
    dealing with a contract of sale, occurs this pertinent statement of the
    doctrine of waiver:
    When there is a condition made at [or in] the
    contract of sale favorable to the vendor, and solely for
    his benefit, he may, if he choose, [or elect], waive it,
    and treat the contract as if no such condition had been
    embraced in it. Waiver is a voluntary relinquishment
    or renunciation of some right, a foregoing or giving up
    of some benefit or advantage, which, but for such
    waiver, he would have enjoyed. It may be proved by
    -7-
    express declaration; or by acts and declarations
    manifesting an intent and purpose not to claim the
    supposed advantage; or by a course of acts and
    conduct, or by so neglecting and failing to act, as to
    induce a belief that it was his intention and purpose to
    waive.
    Id. at 389.
    In Koontz v. Fleming, 
    117 Tenn. App. 1
    , 
    65 S.W.2d 821
     (1933), this Court stated:
    “Evidence of Waiver –1. In General. Waiver is a matter of
    fact to be shown by the evidence. It may be shown by express
    declarations manifesting an intent and purpose not to claim the
    supposed advantage, or it may be shown by a course of acts and
    conduct, and in some cases will be implied therefrom. It may also be
    shown by so neglecting and failing to act as to induce a belief that
    there is an intention or purpose to waive. Proof of express words is
    not necessary, but the waiver may be shown by circumstances, or by
    a course of acts and conduct which amounts to an estoppel.
    “2. Burden of Proof. The burden is upon the party claiming
    the waiver to prove it by such evidence as does not leave the matter
    doubtful or uncertain; but he is only required to prove it by the
    preponderance of evidence, as in other civil actions.
    “3. Weight and Sufficiency. It is also necessary that the acts,
    conduct, or circumstance relied upon should make out a clear case of
    waiver.”
    
    Id. at 824-825
     (quoting 40 Cyc.., 267).
    In Prewitt v. Bunch, 
    101 Tenn. 722
    , 
    50 S.W. 748
     (1899), our Supreme Court stated:
    To constitute an abandonment or waiver, there must be a clear,
    unequivocal, and decisive act of the party, showing a determination
    not to have the benefit in question, with a full knowledge of his rights
    in the premises. Gentry v. Gentry, 
    1 Sneed, 87
    ; Traynor v. Johnson,
    1 Head. 52; Masson v. Anderson, 
    3 Bax., 290
    ; Schouler’s Dom. Rel.,
    Sec. 189.
    
    Id. at 742
    .
    -8-
    Our Supreme Court has noted that the right to arbitration can be waived under the equitable
    principles of estoppel, laches, or waiver. See Cavalier Ins. Corp. v. Osmond, 
    538 S.W.2d 399
    , 405
    (Tenn. 1976).
    Rebound has cited in his brief numerous cases holding that under the specific facts involved,
    the waiver of the right to arbitrate has been shown. On the other hand, Universal has cited in its brief
    numerous cases holding that under the specific facts involved, the waiver of the right to arbitrate has
    not been shown, or, in some case, if there has been an waiver, there was no prejudice to the other
    party. We see no use or purpose in prolonging this opinion to discuss these particular cases, since
    each case must be decided on the basis of its particular facts. In Annotation, Defendant’s
    Participation in Action as Waiver of Right to Arbitration of Dispute Involved Therein, 98 ALR3d
    771, it is stated:
    In general, even in those jurisdictions where a contract for
    arbitration is irrevocable, the right to arbitration under the contract
    may be waived either by express words or by necessary implication,
    for example, where the conduct of a party clearly indicates an intent
    to waive the right to arbitrate. In those cases involving the issue of
    whether the defendant’s participation in an action constitutes a waiver
    of the right to arbitrate the dispute involved therein, no general rules
    are readily apparent for determining waiver other than the general
    adherence by the courts to the principle that waiver is to be
    determined from the particular facts and circumstances of each case,
    or other than the rule, applied by the courts in some recent cases, that
    it is the presence or absence of prejudice, and not the inconsistency
    of the defendant’s conduct, which is determinative of the issue of
    waiver of the right to arbitration.
    In the instant case, there are disputes as to material facts and disputes as to inferences to be
    drawn from the material facts. Rebound’s initial complaint was filed in 1994. While Univeral’s
    answer stated that the contract required arbitration, there was no demand made for arbitration at that
    time. A demand for arbitration was finally made alternatively to a motion for summary judgment
    filed December 16, 1997. In the meantime, Universal participated in the litigation process. The
    record reflects that Universal did not demand arbitration, but merely included that as an affirmative
    defense in its answer and then proceeded to answer the complaint in its entirety. Universal
    participated in the discovery proceedings and responded to discovery requests from Rebound.
    Universal benefitted from the production of documents and other discovery proceedings and
    participated in the scheduling orders of the court. Universal only sought to compel arbitration after
    the litigation had been going on for over three years. When the matter was submitted to arbitration
    pursuant to the court’s order, Universal’s primary defense was the untimeliness of the arbitration
    proceeding brought about by Rebound’s failure to file the arbitration at an earlier date. Of particular
    significance is that in April of 1995, Universal’s attorney requested an extension of time within
    which to respond to Rebound’s discovery request. There is evidence that a request for an extension
    -9-
    of time was for the express purpose of making the determination of whether Universal would
    demand arbitration or not. A letter dated April 28, 1995, from Universal’s counsel to one of
    Rebound’s lawyers, states:
    Gregory Mitchell
    Doramus & Trauger
    The Southern Turf Bldg.
    222 Fourth Ave. North
    Nashville, TN 37219
    Re: Rebound Care
    Dear Greg:
    You should check with your boss before filing motions to
    compel. I spoke with Jim this morning and explained why no
    answers had been filed. I explained that we had been considering a
    motion to compel arbitration, a copy of which I was planning to file
    yesterday, but that Universal had not made the final decision on
    whether to insist on arbitration or not. Jim agreed to an extension,
    noted that he was very tied up with the Earthman matter, and
    suggested that I check with Universal and determine how much time
    was needed. He indicated he would agree to an order allowing a
    reasonable amount of additional time. Much to my surprise, someone
    hand delivered a motion to compel along with a certification that you
    had made a good faith effort to resolve the matter. To my knowledge,
    the only communication I received from you was a letter dated a week
    ago demanded answers.
    Please strike the motion. If you have any questions feel free
    to contact me.
    Very truly yours,
    BOULT, CUMMINGS, CONNERS & BERRY
    By: H. Frederick Humbracht, Jr.
    It further appears from the record that by August of 1995, the discovery requests had not been
    answered, and counsel for Rebound wrote a letter to Universal’s counsel on August 21, 1995, and
    it states:
    H. Frederick Humbracht, Jr., Esq.
    Boult, Cummings, Conners & Berry
    -10-
    414 Union Street, Suite 1600
    Nashville, TN 37219
    Re: Rebound Care Corporation d/b/a Open
    Arms Care Corporation v. Barge, Waggoner
    Sumner and Cannon, Incorporated, et al
    Docket No. 94-444-I
    Dear Rick:
    We need Universal’s answers to interrogatories to move this
    case along. As you know, these answers were due several months
    ago, but we delayed in filing a motion to compel because you
    indicated that Universal was still deciding how to proceed. We
    believe that we have provided ample time for Universal to examine
    the case, and, therefore, if Universal has not answered the
    interrogatories by September 5, 1995, we will file a motion to compel
    these answers. We cannot agree to any further extensions of time in
    which to respond.
    Please call Paul Ney or me if you have any questions.
    Sincerely yours,
    Gregory Mitchell
    The record further indicates that Universal thereafter participated in the litigation process and
    filed its motion which alternatively sought arbitration on December 16, 1997.
    We have not exhaustively related the record, because the above is sufficient to show that
    there are disputed issues of material fact or disputed inferences to be drawn from the facts as to
    whether there was a waiver of the right to arbitrate. Under these circumstances, the trial court’s
    summary disposition of the waiver was error, and the case must be remanded for further proceedings
    in that regard.
    Although the case is being remanded for further proceedings concerning the waiver issue,
    we feel that we should in the interest of judicial economy consider the second issue, which is stated:
    2. Whether the arbitration panel denied Rebound its right under
    T.C.A. § 29-5-306 to a proper evidentiary hearing on the claims and
    defenses at issue in the proceeding.
    Rebound asserts that the trial court erred in confirming the award of the arbitrators and
    -11-
    denying Rebound’s application to vacate the award. Rebound argues that the trial court should have
    vacated the award pursuant to T.C.A. § 29-5-313 (a)(4)(Supp. 1999) which states in pertinent part:
    “The arbitrators . . . refused to hear evidence material to the controversy or otherwise so conducted
    the hearing, contrary to the provisions of § 29-5-306 as to prejudice substantially the rights of a
    party.” Rebound asserts that it had witnesses to testify, and the panel refused to hear such testimony.
    Rebound does not point out in its brief, nor have we found in the record, that Rebound requested and
    was denied the right to put on any proof in the arbitration proceeding. There is simply nothing in
    the record to indicate that Rebound was denied its right. Therefore, the trial court did not err in
    confirming the award and denying Rebound’s application to vacate the award.
    Accordingly, the order of the trial court holding that Universal did not waive the right to
    arbitration dismissing Rebound’s complaint is vacated. The order of the trial court in all other
    respects is affirmed. The case is remanded to the trial court for such other proceedings as are
    necessary consistent with this Opinion. Costs of appeal are assessed one-half to Rebound Care
    Corporation and one-half to Universal Constructors, Inc.
    -12-