Kay & Kay Contracting, LLC v. Tennessee Department of Transportation ( 2010 )


Menu:
  •                IN THE COURT OF APPEALS OF TENNESSEE
    AT KNOXVILLE
    May 19, 2010 Session
    KAY AND KAY CONTRACTING, LLC v.
    TENNESSEE DEPARTMENT OF TRANSPORTATION
    Appeal from the Claims Commission for the State of Tennessee
    No. 20081364-I     William O. Shults, Commissioner
    No. E2009-01769-COA-R9-CV - FILED JUNE 25, 2010
    Kay and Kay Contracting, LLC (“Contractor”) entered into a contract with the Tennessee
    Department of Transportation (“TDOT”) to build a bridge in Campbell County, Tennessee.
    Contractor subsequently entered into a subcontract with Whitley County Stone, LLC
    (“Subcontractor”) to provide the excavation and grading work on the project. Subcontractor
    does not have a written contract with TDOT. Both Contractor and Subcontractor filed claims
    with the Claims Commission alleging they were owed money by TDOT. Subcontractor was
    dismissed as a party because it did not have a written contract with TDOT, as required by
    Tenn. Code Ann. § 9-8-307(a)(1)(L). The Commissioner, however, determined that
    Contractor was allowed to prosecute Subcontractor’s claim as a “pass-through” claim. The
    sole issue on this interlocutory appeal is whether Tenn. Code Ann. § 9-8-307(a)(1)(L)
    removes the State’s sovereign immunity such that Contractor can assert a “pass-through”
    claim against TDOT on Subcontractor’s behalf. We conclude that sovereign immunity from
    such a claim is not removed, and we reverse the judgment of the Claims Commission.
    Tenn. R. App. P. 9 Interlocutory Appeal by Permission;
    Judgment of the Claims Commission Reversed; Case Remanded
    D. M ICHAEL S WINEY, J., delivered the opinion of the court, in which H ERSCHEL P. F RANKS,
    P.J., and J OHN W. M CC LARTY, J., joined.
    Robert E. Cooper, Jr., Attorney General and Reporter, Michael E. Moore, Solicitor General,
    and Steven B. McCloud, Senior Counsel, Nashville, Tennessee, for the Appellant, Tennessee
    Department of Transportation.
    Spencer D. Noe and Timothy C. Wills, Lexington, Kentucky, and Laurie H. Hallenberg,
    Knoxville, Tennessee, for the Appellee, Kay and Kay Contracting, LLC.
    OPINION
    Background
    The relevant facts for purposes of resolving this interlocutory appeal are
    undisputed. Contractor entered into a written contract with TDOT for the grading, drainage,
    and construction of a concrete Bulb-Tee beam bridge on Interstate 75 in Campbell County,
    Tennessee. The initial estimated cost of the project was in excess of $10.2 million.
    Subsequently, Contractor entered into a separate contract with Subcontractor for the
    excavation and grade work on the project. The estimated cost of the excavation and grading
    work was in excess of $3.1 million.
    According to Contractor, problems developed during the construction of the
    bridge, resulting in several adjustments to the contract price. After TDOT allegedly
    defaulted on payment for various portions of the project, both Contractor and Subcontractor
    filed a claim with the State of Tennessee, Division of Claims Administration. In September
    2008, the claim was transferred to the Tennessee Claims Commission. Approximately one
    month later, Contractor and Subcontractor filed a complaint with the Claims Commission
    against TDOT. According to the complaint, Contractor was owed $298,751.41, and
    Subcontractor was owed $199,746.63.1
    TDOT filed an answer and denied any liability to either Contractor or
    Subcontractor. TDOT also filed a motion to dismiss Subcontractor’s claims on the basis that
    the Claims Commission did not have subject matter jurisdiction over Subcontractor’s claim
    because there was no written contract between TDOT and Subcontractor.
    Although the Commission agreed that Subcontractor was not a proper party to
    the lawsuit in the Claims Commission, the Commission nevertheless concluded that
    Contractor could pursue Subcontractor’s claim by asserting what is referred to as a “pass-
    through” claim. According to the Commission:
    The legal issue is whether or not a general contractor
    involved in a large state highway construction project can assert
    a claim on behalf of one of its subcontractors against the State.
    1
    Contractor also requested additional relief, including an order granting Contractor “329 days of
    additional time under the Contract and to terminate TDOT’s assessment of liquidated damages” against
    Contractor.
    -2-
    In contracts involving the federal government, as well as
    nineteen (19) states which have addressed such a problem, this
    sort of issue has been denominated as a “pass-through” claim.
    *   *     *
    According to the State’s position, the Commission lacks
    jurisdiction here over [Subcontractor’s] claim since the General
    Assembly of Tennessee, per the waiver of the State’s sovereign
    immunity against contractor suits, has limited the right to
    institute such causes of actions to those entities having a written
    contract with the State.        Here, so the argument goes,
    [Subcontractor] does not have a written contract with the State
    and therefore its claim for work it claims it performed, but for
    which it has not been paid in full, cannot proceed before the
    Commission. Additionally, the State argues that the general
    contractor cannot assert such a claim - a so called “pass-through
    claim” - on behalf of [Subcontractor]. Rather, the State
    contended . . . [that Subcontractor should sue Contractor and] if
    a final judgment is rendered . . . against [Contractor], it could,
    in turn, file a claim with the Commission.
    In its Response to the Motion to Dismiss, [Contractor]
    concedes that under the Tennessee Claims Commission Act,
    [Subcontractor] is not a proper party to this action.
    Nevertheless, [Contractor] says it should be able to pursue, on
    behalf of its subcontractor, a claim for work done which was an
    important part of its overall contract on the . . . project. Such a
    procedure would constitute utilization of the “pass-through”
    theory recognized in federal government contracts and
    apparently by at least eighteen of the states. In support of its
    position, [Contractor] cites the United States Supreme Court
    decision in United States v. Blair, 
    321 U.S. 730
     (1944) and
    quotes language from that opinion describing the general
    contractor there as “. . . the only person legally bound to perform
    [the] contract with the Government.” Id. at 737-738. . . .
    Both parties informed the Commission that they have
    been unable to find any precedent directly on point in Tennessee
    -3-
    either permitting or disallowing a so-called “pass-through”
    claim by a general contractor for one of its subcontractors.
    The Commission then discussed federal law and law from other states, the vast
    majority of which permit “pass-through” claims. After reviewing the law from other
    jurisdictions, the Commission concluded that there clearly was a written contract between
    TDOT and Contractor, and allowing Contractor to pursue a claim on behalf of Subcontractor
    would not offend “the concept of sovereign immunity in Tennessee since the Tennessee
    Claims Commission Act . . . [was amended] to direct a liberal application of its provisions
    in order that its remedial purposes might be accomplished.” The Commission then
    concluded:
    Therefore, the Commission FINDS that although
    [Subcontractor] is not a proper party to this litigation and
    therefore, will be DISMISSED, the issue of [Contractor’s]
    liability for nearly Two Hundred Thousand Dollars
    ($200,000.00) in payments allegedly owed to [Subcontractor] is
    ripe for resolution now and may be prosecuted by [Contractor].
    The State’s Motion to Dismiss [Contractor’s] claim on
    behalf of [Subcontractor] must be respectfully DENIED. . . .
    After entry of the above Order, TDOT filed a motion requesting permission to
    file an interlocutory appeal to this Court on the issue of whether Tenn. Code Ann. § 9-8-
    307(a)(1)(L) removes the State’s sovereign immunity for pass-through claims. The
    Commission granted TDOT’s request for a Tenn. R. App. P. Rule 9 interlocutory appeal, as
    did this Court. As stated, the sole issue on appeal is whether Tenn. Code Ann. § 9-8-
    307(a)(1)(L) removes the State’s sovereign immunity such that Contractor can assert a “pass-
    through” claim against the State on Subcontractor’s behalf.
    Discussion
    Since the relevant facts are undisputed, this appeal presents a question of law.
    We review legal issues “under a pure de novo standard of review, according no deference to
    the conclusions of law made by the lower courts.” Southern Constructors, Inc. v. Loudon
    County Bd. of Educ., 
    58 S.W.3d 706
    , 710 (Tenn. 2001).
    In Stewart v. State, 
    33 S.W.3d 785
     (Tenn. 2000), our Supreme Court gave a
    very thorough analysis of the subject matter jurisdiction of the Claims Commission.
    According to the Supreme Court:
    -4-
    It is a well-settled principle of constitutional and statutory
    law in this state that “[t]he State of Tennessee, as a sovereign,
    is immune from suit except as it consents to be sued.”
    Brewington v. Brewington, 
    215 Tenn. 475
    , 480, 
    387 S.W.2d 777
    , 779 (1965). This doctrine of sovereign immunity “has been
    a part of the common law of Tennessee for more than a century
    and [it] provides that suit may not be brought against a
    governmental entity unless that governmental entity has
    consented to be sued.” Hawks v. City of Westmoreland, 
    960 S.W.2d 10
    , 14 (Tenn. 1997). Despite this general grant of
    immunity, however, the courts of this state have frequently
    recognized that the Tennessee Constitution has modified this
    rule of absolute sovereign immunity by providing that “[s]uits
    may be brought against the State in such manner and in such
    courts as the Legislature may by law direct.” Tenn. Const. art.
    I, § 17; see also Kirby v. Macon County, 
    892 S.W.2d 403
    , 406
    (Tenn. 1994).
    Pursuant to its constitutional power to provide for suits
    against the state, the legislature created the Tennessee Claims
    Commission in 1984 to hear and adjudicate certain monetary
    claims against the State of Tennessee. See Tenn. Code Ann.
    §§ 9-8-301 to 307 (1999). While the Claims Commission has
    exclusive jurisdiction to hear claims arising against the state, cf.
    Tenn. Code Ann. § 20-13-102(a) (1994), this jurisdiction is
    limited only to those claims specified in Tennessee Code
    Annotated section 9-8-307(a). If a claim falls outside of the
    categories specified in section 9-8-307(a), then the state retains
    its immunity from suit, and a claimant may not seek relief from
    the state. Cf. Hill v. Beeler, 
    199 Tenn. 325
    , 329, 
    286 S.W.2d 868
    , 869 (1956) (stating that “except as the Legislature of the
    State consents there is no jurisdiction in this Board of Claims to
    entertain suits against the State”).
    The courts of this state have traditionally held that any
    statute granting jurisdiction to hear a claim against the state
    must be strictly construed, as any such statute is in derogation of
    the common law rule of sovereign immunity. See, e.g., Norman
    v. Tennessee State Bd. of Claims, 
    533 S.W.2d 719
    , 722 (Tenn.
    1975) (“We further recognize that the statutory provisions
    -5-
    governing the Board of Claims have been strictly construed, in
    view of the fact that they do represent an encroachment upon the
    sovereign immunity and upon the assets of the State.”); State ex
    rel. Allen v. Cook, 
    171 Tenn. 605
    , 609, 
    106 S.W.2d 858
    , 860
    (1937) (“Statutes passed by the Legislature, under the authority
    of article 1, section 17, of the Constitution, permitting suits
    against the state, being in derogation of the sovereign’s
    exemption from suits, must be strictly construed.”).
    Nevertheless, in 1985, the General Assembly amended section
    9-8-307(a) to express its intention as to the jurisdictional reach
    of the Claims Commission: “It is the intent of the general
    assembly that the jurisdiction of the claims commission be
    liberally construed to implement the remedial purposes of this
    legislation.” Tenn. Code Ann. § 9-8-307(a)(3).
    Hence, although we have traditionally given a strict
    construction to the scope of the Commission’s jurisdiction, we
    also recognize that our primary goal in interpreting statutes is
    “to ascertain and give effect to the intention and purpose of the
    legislature.” Gleaves v. Checker Cab Transit Corp., Inc., 
    15 S.W.3d 799
    , 802 (Tenn. 2000) (citing Carson Creek Vacation
    Resorts, Inc. v. State Dep’t of Revenue, 
    865 S.W.2d 1
    , 2 (Tenn.
    1993)). If the legislature intends that its statutes waiving
    sovereign immunity are to “be liberally construed,” then the
    courts should generally defer to this expressed intention in cases
    where the statutory language legitimately admits of various
    interpretations. A policy of liberal construction of statutes,
    however, only requires this Court to give “the most favorable
    view in support of the petitioner's claim,” Brady v. Reed, 
    186 Tenn. 556
    , 563, 
    212 S.W.2d 378
    , 381 (1948), and such a policy
    “does not authorize the amendment, alteration or extension of its
    provisions beyond [the statute’s] obvious meaning.” Pollard v.
    Knox County, 
    886 S.W.2d 759
    , 760 (Tenn. 1994). Moreover,
    “[w]here a right of action is dependent upon the provisions of a
    statute . . . we are not privileged to create such a right under the
    guise of a liberal interpretation of it.” Hamby v. McDaniel, 
    559 S.W.2d 774
    , 777 (Tenn. 1977).
    Accordingly, when deciding whether a claim is within the
    proper statutory scope of the Commission’s jurisdiction to hear
    -6-
    and decide claims against the State of Tennessee, we will give
    a liberal construction in favor of jurisdiction, but only so long as
    (1) the particular grant of jurisdiction is ambiguous and admits
    of several constructions, and (2) the “most favorable view in
    support of the petitioner's claim” is not clearly contrary to the
    statutory language used by the General Assembly. Cf.
    Northland Ins. Co. v. State, 
    33 S.W.3d 727
    , 730 (Tenn. 2000)
    (“The statute’s liberal construction mandate allows courts to
    more broadly and expansively interpret the concepts and
    provisions within its text.”). Furthermore, because issues of
    statutory construction are questions of law, see Wakefield v.
    Crawley, 
    6 S.W.3d 442
    , 445 (Tenn. 1999); Jordan v. Baptist
    Three Rivers Hosp., 
    984 S.W.2d 593
    , 599 (Tenn. 1999), we
    review the issues involving the jurisdiction of the Claims
    Commission de novo without any presumption that the legal
    determinations of the commissioner were correct.                See
    Northland Ins. Co., 33 S.W.3d at 729; Ardis Mobile Home Park
    v. State, 
    910 S.W.2d 863
    , 865 (Tenn. Ct. App. 1995).
    Stewart, 33 S.W.3d at 790-91 (footnote omitted)
    In reaching a conclusion that pass-through claims were permissible in
    Tennessee and consistent with Tenn. Code Ann. § 9-8-307(a)(1)(L), the Commission relied
    heavily upon the case of Interstate Contracting Corp. v. City of Dallas, 
    135 S.W.3d 605
    (Tex. 2004), wherein the Texas Supreme Court answered the following certified question in
    the affirmative: “Does Texas recognize pass-through claims, i.e., may a contractor assert a
    claim against an owner on a subcontractor’s behalf when there is no privity of contract
    between the subcontractor and the owner?” Id. at 607. In concluding that Texas did
    recognize pass-through claims, the Texas Supreme Court discussed the various policy factors
    both in support of and against allowing such claims. The Texas Supreme Court ultimately
    concluded that Texas would allow pass-through claims based on the policy reasons which
    favored allowing such claims. Id. at 619. Ironically, the Texas Supreme Court refused to
    answer the specific question that is now posed to this Court for review:
    The City argues that, before a pass-through claim against
    a governmental entity can be recognized, there must be a waiver
    of sovereign immunity. ICC responds that, to the extent the City
    asserts that ICC’s breach of contract claims are barred by
    sovereign immunity, such arguments are outside the scope of the
    question certified by the Fifth Circuit. ICC also argues that the
    -7-
    City did not mention sovereign immunity in its brief filed with
    the Fifth Circuit, nor did the City plead sovereign immunity in
    its answer filed in district court.
    Although the questions certified do not limit our answers,
    we decline to extend our answers in this case to the issue of
    sovereign immunity, which is well beyond the scope of the
    questions certified. Doing so would require us to venture into
    the facts of this particular case and analyze the merits of the
    parties’ claims at issue before the Fifth Circuit Court of
    Appeals, rather than provide answers solely as to the status of
    Texas law on the questions asked. For this reason, we confine
    our answers to the questions certified. How our answer is to be
    applied to the facts of this case is the province of the certifying
    court. See Amberboy v. Societe de Banque Privee, 
    831 S.W.2d 793
    , 798 (Tex. 1992).
    City of Dallas, 135 S.W.3d at 620.
    The Tennessee statute removing the State’s immunity for claims against the
    State based upon breach of contract provides, in relevant part, as follows:
    (a)(1) The commission or each commissioner sitting individually
    has exclusive jurisdiction to determine all monetary claims
    against the state based on the acts or omissions of “state
    employees,” as defined in § 8-42-101(3), falling within one (1)
    or more of the following categories:
    *   *     *
    (L) Actions for breach of a written contract
    between the claimant and the state which was executed
    by one (1) or more state officers or employees with
    authority to execute the contract . . . .
    Tenn. Code Ann. § 9-8-307(a)(1)(L) (Supp. 2009) (emphasis added).
    All parties to this appeal agree that Subcontractor does not have a written
    contract with TDOT and, therefore, it is not a proper party to this lawsuit. Thus, the
    -8-
    Commission’s dismissal of Subcontractor as a party was correct. The more difficult issue
    is whether Contractor can assert a pass-through claim on Subcontractor’s behalf.
    Tenn. Code Ann. § 9-8-307(a)(1)(L) is quite clear in requiring a written
    contract with the State before immunity from suit is removed. The statute is neither
    ambiguous nor reasonably open to several constructions. By allowing Contractor to assert
    a pass-through claim on Subcontractor’s behalf, Contractor is asserting a breach of contract
    claim on behalf of a party that everyone agrees does not have a written contract with TDOT.
    This is contrary to the plain language of the statute.
    We agree with the Commissioner that there are several sound policy reasons
    which mitigate in favor of allowing pass-through claims. It is, however, the General
    Assembly’s prerogative to determine the State’s public policy as to allowing suits against the
    State, not this Court’s, and the General Assembly has done so. If the General Assembly
    concludes that the public policy of this State is such that pass-through claims against the
    State should be allowed, then the General Assembly can amend Tenn. Code Ann. § 9-8-
    307(a)(1)(L) to permit such claims.
    We acknowledge that we must give Tenn. Code Ann. § 9-8-307(a)(1)(L) a
    liberal construction. However, in so doing we cannot amend, alter, or extend the statute
    beyond its obvious meaning. Stewart, 33 S.W.3d at 791. The obvious and ordinary meaning
    of requiring a “written contract between claimant and the state...” is not susceptible of more
    than one meaning. A contract is either written or it is not. If we allow pass-through claims,
    then we are allowing a party to sue the State and prosecute the claim of a different entity that
    has no contractual relationship with the State. This is contrary to the clear and unambiguous
    language of the statute requiring a written contract between the claimant and the State before
    the State can be sued for breach of contract. We again note that if the General Assembly
    believes that allowing pass-through claims is in the State’s best interest and public policy
    favors allowing such claims, we invite the General Assembly to amend the relevant statutory
    provisions to expressly allow such claims.
    It is important to emphasize the scope of our holding. Our opinion applies only
    to pass-through claims wherein subject matter jurisdiction is predicated on the removal of
    the State’s immunity pursuant to Tenn. Code Ann. § 9-8-307(a)(1)(L). We express no
    opinion on whether pass-through claims otherwise are permitted in Tennessee in other
    contexts.
    We also note that our holding does not allow TDOT to escape liability if
    Subcontractor has a valid claim. The scope of TDOT’s contractual liability on this project
    is controlled by its written contract with Contractor. The contract between Contractor and
    -9-
    Subcontractor cannot expand TDOT’s liability under the original contract. As noted by the
    Commission in this case:
    The actual work to be performed by [Contractor] is literally
    contained within the terms of the Prime Contract between the
    State and [Contractor]. Paragraph 1(b) of the Contract . . .
    incorporates by reference the Proposal Contract which, in turn,
    in Item D of the Contract Schedule, at page 10, includes
    precisely the work . . . which [Subcontractor] contends it
    completed but was not paid in full for doing.
    If TDOT’s liability for work performed by Subcontractor is dependent on the terms of
    TDOT’s contract with Contractor, then Contractor can sue TDOT directly for any alleged
    breach of that contract.
    Conclusion
    The judgment of the Claims Commission is reversed and this cause is
    remanded to the Claims Commission for further proceedings consistent with this Opinion and
    for collection of the costs below. Costs on appeal are taxed to the Appellee, Kay and Kay
    Contracting, LLC.
    ________________________________
    D. MICHAEL SWINEY, JUDGE
    -10-