Signature Industrial Services, LLC and Jeffry Ogden v. International Paper Company ( 2022 )


Menu:
  •          Supreme Court of Texas
    ══════════
    No. 20-0396
    ══════════
    Signature Industrial Services, LLC and Jeffry Ogden,
    Petitioners,
    v.
    International Paper Company,
    Respondent
    ═══════════════════════════════════════
    On Petition for Review from the
    Court of Appeals for the Thirteenth District of Texas
    ═══════════════════════════════════════
    Argued September 16, 2021
    JUSTICE BLACKLOCK delivered the opinion of the Court.
    Justice Huddle and Justice Young did not participate in the
    decision.
    The principal question in this breach-of-contract case is how to
    measure consequential damages.         A jury found that the defendant
    breached by failing to pay $2.4 million as promised. The jury awarded
    the $2.4 million as direct damages, but it also added more than twenty
    times that amount in consequential damages. The plaintiff’s primary
    theory of consequential damages was that the defendant’s failure to pay
    the $2.4 million caused the abandonment of a deal in which the plaintiff
    company would have been sold for $42 million.             According to the
    plaintiff, its “company value” on the open market declined to zero after
    the breach. The court of appeals rejected this basis for consequential
    damages. 
    628 S.W.3d 541
    , 578 (Tex. App.—Corpus Christi–Edinburg
    2020).      It nevertheless accepted another theory under which a
    precipitous decline in the plaintiff company’s “book value” following the
    breach authorized consequential damages of $12.4 million. 
    Id. at 579
    .
    In this Court, the plaintiff seeks reinstatement of the jury’s award
    of $56.3 million in consequential damages, while the defendant argues
    that none of the proffered theories of consequential damages is valid.
    The parties also dispute the direct damages. Texas law requires that
    consequential damages be both (1) foreseeable at the time of contracting,
    and (2) calculable with reasonable certainty. Phillips v. Carlton Energy
    Grp., LLC, 
    475 S.W.3d 265
    , 279 (Tex. 2015); Stuart v. Bayless, 
    964 S.W.2d 920
    , 921 (Tex. 1998).        Applying these bedrock principles of
    contract law, we conclude that neither the jury’s award of $56.3 million
    nor the court of appeals’ reduced allowance of $12.4 million can stand.
    A catastrophic decline in the plaintiff company’s overall market value
    was not, at the time of contracting, a consequence of breach foreseeable
    to the defendant. Nor was a decline in the accounting measure of the
    plaintiff company’s “book value” a reasonably certain way to measure its
    damages.
    Because legally insufficient evidence supported the award of
    consequential damages and the plaintiff advances no valid theory of
    consequential damages in this Court, we render judgment against the
    plaintiff on that point. As for the direct damages, we affirm a portion of
    2
    the award.    We also affirm the court of appeals’ rejection of the
    defendant’s indemnification claim and its rendition of judgment against
    co-plaintiff Jeffry Ogden.     The judgment of the court of appeals is
    reversed in part and affirmed in part. Judgment is rendered consistent
    with this opinion, and the case is remanded to the district court for any
    further proceedings that may be necessary.
    I.      Background
    Founded in 2010, Signature Industrial Services, LLC (SIS)
    performed maintenance, construction, and other tasks for International
    Paper Company (IP) and other industrial clients. SIS and IP contracted
    in March 2014 for SIS to upgrade a slaker—a large vessel that recycles
    chemicals used to make paper—at IP’s mill in Orange, Texas. The
    initial agreement obligated IP to pay just over $775,000. Other costs
    could be billed to IP as they arose.
    Following a series of delays and disputes, including a chemical
    spill that prevented work on the slaker, the cost of the project exceeded
    initial expectations. IP instructed SIS that it could complete the work
    and bill IP at the end. After SIS finished the work, the parties disputed
    the amount IP owed. IP thought its previous payment of $1.1 million
    would suffice, but SIS wanted another $2.4 million. The parties failed
    to reach an agreement.
    SIS sued IP, alleging fraud and breach of contract.          After
    litigation began, SIS submitted two invoices intended to cover the
    remaining $2.4 million it believed it was owed. Jeffry Ogden, SIS’s
    President, intervened as a plaintiff in his personal capacity, raising
    essentially the same fraud and breach-of-contract claims as SIS.
    3
    Meanwhile, SIS had planned to be acquired by a third party,
    Primoris Services Corporation. Before litigation began, SIS received an
    offer from Primoris of $42 million. The negotiations were confidential.
    After IP refused to pay the amount SIS demanded, the negotiations
    between SIS and Primoris foundered. Facing a cash-flow crunch, SIS
    failed to fully pay its federal payroll tax, for which the IRS imposed
    penalties. The penalties led to more debt, and SIS then began to lose
    customers. Ogden, who had personally guaranteed much of SIS’s debt,
    faced mounting financial difficulty. The company all but collapsed. The
    contract for work on the slaker was worth, at most, $3.5 million. SIS
    sued IP for $56.3 million.
    Primoris made another offer to buy SIS after the lawsuit began.
    The offer price remained $42 million, though with less cash up front.
    SIS declined the offer. It later turned down two more offers, both for
    around $10 million.
    At trial, an SIS expert witness testified about the company’s lost
    value. The expert’s testimony consisted of three components: the lost
    Primoris offer, the company’s lost book value, and the tax penalties SIS
    incurred after its IRS trouble began. First, the expert calculated $42
    million in damage to the company because, in his view, the $42 million
    Primoris offer was lost due to the breach. Second, he demonstrated that
    SIS’s “book value” dropped by $12.4 million after the breach. He did this
    by looking at balance sheets from before and after the breach and
    subtracting SIS’s liabilities from its assets to arrive at a bottom-line
    measure of its pre- and post-breach book value. He attributed the drop
    in book value to IP’s non-payment, but he did not specifically analyze
    4
    any particular devalued asset or increased liability. Other witnesses
    testified that SIS lost contracting opportunities because of its precarious
    financial situation, which rendered the company’s value “less than zero”
    by the time of trial. Finally, the expert opined that IP was responsible
    for $1.9 million in penalties incurred by SIS for non-payment of payroll
    taxes. The expert added the three figures—$42 million, $12.4 million,
    and $1.9 million—to arrive at a total damages figure of $56.3 million.
    On SIS’s breach-of-contract claim, the jury awarded the $56.3
    million recommended by SIS’s expert for “[d]amages to [SIS]’s company
    value.” It also awarded $2.4 million in direct damages.          The jury
    awarded identical amounts to SIS on its fraud claim. As for Ogden, the
    jury awarded a total of $4.2 million in breach-of-contract damages. It
    also awarded $63 million for mental anguish to Ogden on his fraud
    claim. All told, the jury awarded over $125 million due to IP’s failure to
    pay $2.4 million.     The district court rendered judgment for both
    plaintiffs on both the breach-of-contract and fraud claims.
    The court of appeals reversed the district court’s judgment as to
    all the fraud claims. As for SIS’s breach-of-contract claim, the court of
    appeals reduced the consequential damages award from $56.3 million to
    $12.4 million, excising the damages for the lost $42 million sale and for
    SIS’s tax penalties. The court of appeals upheld the $2.4 million in
    direct damages to SIS and $12.4 million in consequential damages for
    lost book value.      It rendered judgment against Ogden on his
    breach-of-contract claim because it found he was not authorized to sue
    in his individual capacity for breach of a contract between SIS and IP.
    The court of appeals rejected IP’s claim that SIS was contractually
    5
    bound to indemnify IP for its defense of Ogden’s claims. 628 S.W.3d at
    580.
    All three parties petitioned for review in this Court. Neither SIS
    nor Ogden attempts to revive its fraud claim. SIS seeks reinstatement
    of $42 million in consequential damages, which it calculates based on
    the amount of Primoris’s offer. IP argues that none of the consequential
    damages can stand, including the $12.4 million allowed by the court of
    appeals. IP also challenges the award of direct damages and contends
    that SIS is contractually obligated to indemnify IP for expenses incurred
    defending against Ogden’s suit.      Ogden seeks reinstatement of his
    breach-of-contract recovery. We address each of these issues in turn.
    II.    Consequential Damages
    At issue are two proffered methods of calculating SIS’s
    consequential damages. First is the decline in the company’s market
    value from the $42 million offered by Primoris to the “less than zero”
    value proffered at trial. Second is the $12.4 million decline in book value
    testified to by SIS’s expert and upheld by the court of appeals. SIS asks
    this Court to reinstate the former, while IP contends that neither can
    stand. As explained below, we agree with IP.
    A.    Legal Standards
    Damages for breach of contract may include both direct and
    consequential damages. Dallas/Fort Worth Int’l Airport Bd. v. Vizant
    Techs., LLC, 
    576 S.W.3d 362
    , 373 (Tex. 2019). Direct damages often
    include restoration of “the benefit of a plaintiff’s bargain.” Quigley v.
    Bennett, 
    227 S.W.3d 51
    , 56 (Tex. 2007) (Brister, J., concurring).
    Consequential damages, on the other hand, compensate the plaintiff for
    6
    foreseeable losses that were caused by the breach but were not a
    necessary consequence of it. Stuart v. Bayless, 
    964 S.W.2d 920
    , 921
    (Tex. 1998). 1
    From at least the time of Hadley v. Baxendale, 9 Exch. 341, 156
    Eng. Rep. 145 (1854), the widely recognized rule has been that
    consequential damages “are not recoverable unless the parties
    contemplated at the time they made the contract that such damages
    would be a probable result of the breach.” Stuart, 964 S.W.2d at 921.
    We call this requirement “foreseeability.” Basic Cap. Mgmt., Inc. v.
    Dynex Com., Inc., 
    348 S.W.3d 894
    , 901 (Tex. 2011). A foreseeable loss
    may either follow predictably from the breach “in the ordinary course of
    events” or arise from “special circumstances” that the party in breach
    “had reason to know.” Id. at 902. A loss that is not the “probable”
    consequence of the breach, from the breaching party’s perspective at the
    time of contracting, is not foreseeable. Mead v. Johnson Grp., Inc., 
    615 S.W.2d 685
    , 687 (Tex. 1981); see also 24 RICHARD A. LORD, WILLISTON ON
    CONTRACTS § 64:17 (4th ed.) (“Consequential damages include those
    damages that were reasonably foreseeable or contemplated by the
    parties at the time the contract was entered into as the probable result
    of a breach.”).
    1  See also W. Union Tel. Co. v. McKinney, 2 Willison 562, 566 (Tex. Ct.
    App. 1885) (“Ordinarily, such damages would not result from the breach of
    such a contract, and cannot, therefore, be said to be direct, natural and
    proximate; but are special and consequential, and such as are recoverable only
    where the party breaching the contract had notice, when he made the contract,
    of the facts which would render such damages reasonably probable in the event
    of a breach.”).
    7
    Apart from foreseeability, consequential damages must also be
    “proved with reasonable certainty.” Phillips v. Carlton Energy Grp.,
    LLC, 
    475 S.W.3d 265
    , 278 (Tex. 2015). “Proof need not be exact, but
    neither can it be speculative.” 
    Id.
     The losses must be “susceptible of
    being established by proof to that degree of certainty which the law
    demands.” Sw. Battery Corp. v. Owen, 
    115 S.W.2d 1097
    , 1099 (Tex.
    1938).     If a loss was “too remote and depended upon too many
    contingencies, and was too speculative in its character to have
    authorized its reception as evidence of any specific and certain loss,”
    Hope v. Alley, 
    9 Tex. 394
    , 395 (1853), then it cannot be recovered. The
    reasonable-certainty rule acknowledges the limited competence of
    courts to track the complex effects of a breach of contract in an
    interdependent marketplace. Parties must prove damages such that
    courts and juries can discern the extent of the losses actually caused by
    the breach, rather than by other factors. Thus, we have called on parties
    to provide “objective facts, figures, or data” to show their lost profits and
    other consequential damages. Phillips, 475 S.W.3d at 279.
    “The proper measure of damages is a question of law,” which we
    review de novo. Allied Vista, Inc. v. Holt, 
    987 S.W.2d 138
    , 141 (Tex.
    App.—Houston [14th Dist.] 1999, pet. denied); Int’l-Great N.R. Co. v.
    Casey, 
    46 S.W.2d 669
    , 671 (Tex. Comm’n App. 1932, holding approved).
    If the legal theories underlying the damages awarded do not conform to
    the law governing damages, we may reverse the award as a matter of
    law. Whiteside v. Trentman, 
    170 S.W.2d 195
    , 196 (Tex. 1943).
    We may also reverse an award if the evidence of damages was
    legally insufficient. “In evaluating legal sufficiency, we are required to
    8
    determine whether the proffered evidence as a whole rises to a level that
    would enable reasonable and fair-minded people to differ in their
    conclusions.” Transp. Ins. Co. v. Moriel, 
    879 S.W.2d 10
    , 25 (Tex. 1994).
    We “view the evidence in the light favorable to the verdict, crediting
    favorable evidence if reasonable jurors could, and disregarding contrary
    evidence unless reasonable jurors could not.” City of Keller v. Wilson,
    
    168 S.W.3d 802
    , 807 (Tex. 2005).
    B.     Damages for the Company’s Lost Market Value
    Prior to the breach, SIS confidentially negotiated its sale to
    Primoris for $42 million. It is undisputed that IP knew nothing about
    the pending sale to Primoris when it agreed to the slaker contract. As a
    result, the loss of the deal cannot have been a foreseeable consequence
    of the breach. This is so even if SIS could show that the breach caused
    the deal to collapse. Foreseeability is an independent element of any
    claim for consequential damages. Basic Cap., 348 S.W.3d at 901. Even
    if caused by the breach, damages are not recoverable if they were not
    within the breaching party’s reasonable contemplation at the time of
    contracting. Stuart, 964 S.W.2d at 921. Because of IP’s undisputed lack
    of awareness of the Primoris deal at the time of contracting, the court of
    appeals rejected the lost $42 million sale as a basis for consequential
    damages. 628 S.W.3d at 578.
    In this Court, SIS acknowledges that the loss of the Primoris sale
    was not itself foreseeable to IP. SIS instead defends the $42 million
    award as a measurement of lost “company value” rather than as
    9
    damages for loss of the Primoris deal. 2 SIS contends the jury measured
    its lost “company value” as the difference between the price offered by
    Primoris ($42 million) and the company’s market value at the time of
    trial (“less than zero,” according to witnesses). After framing the award
    in this way, SIS asks us to assess whether the decline in the company’s
    market value—not loss of the sale itself—was a foreseeable consequence
    of the breach. As explained below, we conclude that it was not.
    To begin with, the court of appeals was justified in rejecting SIS’s
    argument that the $42 million lost Primoris sale is sufficient evidence
    of a decline in company value of $42 million or more. This is so for
    several reasons.     First, the jury awarded the entire amount of the
    Primoris offer (and more), not the difference between the highest offer
    and subsequent, post-breach offers. A company does not lose all its
    value by forfeiting one sale opportunity, particularly when the record
    reflects later offers. Second, treating the $42 million as reflecting a
    decline in the company’s market value would render duplicative the
    $12.4 million in lost book value, which the jury awarded on top of the
    $42 million. Third, SIS cannot use the $42 million sale price to estimate
    its pre-breach value and then use expert testimony on book value to
    estimate its post-breach value. Market value and book value are not
    interchangeable measures. 3
    2 The jury charge instructed the jury to measure “damages to
    Signature’s company value that were the natural and probable consequence of
    the failure to comply and that were foreseeable when the agreement was
    made.”
    3City of Harlingen v. Est. of Sharboneau, 
    48 S.W.3d 177
    , 187 (Tex. 2001)
    (Baker, J., concurring in the judgment) (“Market value is the price the property
    would bring ‘when it is offered for sale by one who desires, but is not obligated
    10
    SIS nevertheless asks us to consider the entire consequential
    damages award of $56.3 million as reflecting a decline in its market
    value and to view the lost Primoris sale merely as some evidence of that
    value. This way of understanding the jury’s award is consistent with
    the jury charge, which instructed the jury to award “damages to
    Signature’s company value that were the natural and probable
    consequence of the failure to comply and that were foreseeable when the
    agreement was made.”           Even assessing the award on those terms,
    however, the damages awarded cannot stand because they were not
    “foreseeable when the agreement was made.”
    Again, “[f]oreseeability is a fundamental prerequisite to the
    recovery of consequential damages for breach of contract.” Basic Cap.,
    348 S.W.3d at 901. To establish the foreseeability of the damages it
    seeks, SIS must prove that IP “contemplated at the time” it agreed to
    the slaker contract that a catastrophic collapse in SIS’s market value far
    outpacing the $2.4 million IP refused to pay “would be a probable result
    of the breach.”      Stuart, 964 S.W.2d at 921; see also RESTATEMENT
    (SECOND) OF CONTRACTS § 351. It has not done so.
    to sell, and is bought by one who is under no necessity of buying it.’”) (quoting
    State v. Windham, 
    837 S.W.2d 73
    , 77 (Tex. 1992)); JEFFREY J. HAAS,
    CORPORATE FINANCE 74 (2d ed. 2021) (“Book value (BV) is the simplest
    valuation method because it is derived directly from the numbers on the
    company’s balance sheet. The book value of a company on any given date is
    simply the value of its total assets (TA) less the value of its total liabilities (TL),
    both as reported on the balance sheet on that date. In other words, book value
    is the amount of the company’s assets that would be left after the company’s
    creditors are paid off in full. Thus, book value is also known as ‘shareholders’
    equity.’”); see id. at 24 (noting that the balance sheet approach “is limited”
    because it “requires the omission of the current fair values of most assets and
    liabilities”).
    11
    SIS attempts to show its collapse was foreseeable to IP by
    demonstrating that IP knew SIS needed payments on the slaker
    contract to fund future business opportunities.         SIS relies on our
    decision in Basic Capital, in which we held that damages for lost
    business opportunities were foreseeable on the facts of that case. Basic
    Cap., 348 S.W.3d at 903. In Basic Capital, the contract was for loans to
    fund specific capital investments by the plaintiff. The nature of the
    contract thus made it clear that withholding payment would impair the
    plaintiff’s anticipated investments. Id. We concluded that the plaintiff
    need not prove that the details of each lost real estate venture were
    known to the defendant at the time of contracting.             Because the
    defendant “clearly knew how the [money] would be used,” the plaintiff
    did not need to establish that the particulars of each lost opportunity
    were known to the defendant at the time of contracting in order for the
    lost profits predictably flowing from the breach to be recovered as
    consequential damages. Id.
    Unlike in Basic Capital, however, SIS does not seek compensation
    for the loss of specific business opportunities. Recovery of the lost profits
    flowing from lost business opportunities, as in Basic Capital, has long
    been recognized as a valid theory of consequential damages. Phillips,
    475 S.W.3d at 278–79 (detailing the standards governing awards of lost
    profits).   Instead of travelling the well-worn path—calculating the
    profits it would have made from the business it lost due to IP’s breach—
    SIS pursued a novel damages model premised on a decline in the
    company’s overall market value as an asset. But SIS cites no contract
    case in which a court has upheld an award of consequential damages
    12
    premised on a drop in a company’s market value as an asset. 4 The few
    Texas courts that have addressed the question have not allowed such a
    recovery. 5 This case will not be the first.
    4  The cases cited by SIS do not support an award of consequential
    damages for reduced company value in a breach-of-contract case. In Sawyer v.
    Fitts, 
    630 S.W.2d 872
     (Tex. App.—Fort Worth 1982, no writ), the court allowed
    loss-of-value damages in a tort suit, although—unlike here—the lost value had
    been realized by a transaction that locked in the plaintiff’s actual losses. The
    same was true for Wellogix, Inc. v. Accenture, LLP, 
    823 F. Supp. 2d 555
     (S.D.
    Tex. 2011), aff’d, 
    716 F.3d 867
     (5th Cir. 2013), also a tort case. Whether a
    decline in a company’s market value could ever be an appropriate measure of
    damages in a tort suit is a question we do not address. SIS cites one contract
    case involving lost-value damages, R.G. McClung Cotton Co. v. Cotton
    Concentration Co., 
    479 S.W.2d 733
     (Tex. App.—Dallas 1972, writ ref’d n.r.e.).
    There, however, the devalued asset at issue was a commodity, not a company.
    The defendant delayed delivery of cotton, and the price dropped during the
    delay. The subject of the contract was the fluctuating commodity itself, and
    the court allowed the breaching defendant to be charged with the decline in
    market value during the delay in delivery. The case does not mention
    foreseeability. In any event, charging cotton dealers with knowledge of the
    cotton market is a far cry from charging IP with knowledge of the market for
    buying and selling companies like SIS.
    5 Transitional Entity LP v. Elder Care LP, No. 05-14-01615-CV, 
    2016 WL 3197160
    , at *8 (Tex. App.—Dallas May 27, 2016, no pet.) (reversing an
    award that “appear[ed] to compensate appellees for the loss in value of a
    business” rather than basing damages on the benefit of the bargain); Abraxas
    Petroleum Corp. v. Hornburg, 
    20 S.W.3d 741
    , 761 (Tex. App.—El Paso 2000, no
    pet.) (agreeing that lost value was an inappropriate measure and
    distinguishing lost profits from lost value); Nelson v. Data Terminal Sys., Inc.,
    
    762 S.W.2d 744
    , 747–48 (Tex. App.—San Antonio 1988, writ denied) (“DTS
    contends that diminution of value in support of Nelson’s breach of contract
    cause of action is not a proper measure of damages. We agree with DTS . . . .”);
    see also Robehr Films, Inc. v. Am. Airlines, Inc., 85 CIV. 1072 (RPP), 
    1989 WL 111079
    , at *5 (S.D.N.Y. Sept. 19, 1989) (“Under Texas law, damages for
    diminution in value of a business are not recoverable in a breach of contract
    action, but are only recoverable in tort.”), aff’d, 
    902 F.2d 1556
     (2d Cir. 1990);
    cf. Hollywood Fantasy Corp. v. Gabor, 
    151 F.3d 203
    , 214 (5th Cir. 1998)
    (“Under Texas law, the loss of goodwill or business reputation is not
    13
    It stands to reason that losing business opportunities will often
    contribute to a decline in a company’s market value, but whether this
    will be the case—and to what extent—depends on many factors typically
    beyond the reasonable contemplation of the breaching party.                 The
    market for ownership of a business is distinct from the market the
    business serves. See Henry G. Manne, Mergers and the Market for
    Corporate Control, 73 J. POL. ECON. 110, 112 (1965). Dense volumes
    detail the proper way to value companies. See, e.g., TIM KOLLER ET AL.,
    VALUATION: MEASURING AND MANAGING THE VALUE OF COMPANIES (7th
    ed. 2020). Students in business schools (and increasingly in law schools)
    ponder asset pricing models and formulas for calculating the weighted
    average cost of capital. Peter H. Huang & Michael S. Knoll, Corporate
    Finance, Corporate Law and Finance Theory, 74 S. CALIF. L. REV. 175,
    175–76 (2000).      Despite detailed knowledge of their own industry,
    companies often do not understand the market for buying and selling
    companies like themselves, much less companies in other lines of work.
    As a result, specialized bankers and consultants are frequently hired
    when companies have reason to explore either their own market value
    or that of other companies.
    SIS proffered no evidence that IP ever had any reason to concern
    itself with SIS’s market value in the eyes of those, like Primoris and its
    advisors, who buy and sell companies. That alone renders SIS’s lost
    market value unforeseeable to IP and therefore unrecoverable. Yet even
    if IP knew SIS’s market value at the time of contracting, foreseeing the
    recoverable in a breach of contract action.”); Sterling Projects, Inc. v. Fields,
    
    530 S.W.2d 602
    , 605 (Tex. Civ. App.—Waco 1975, no writ) (same).
    14
    impact of breaching a promise to pay on a company’s market value is at
    least as difficult as valuing the company in the first place. When valuing
    a business, “confounding events may be hard to disentangle.” FRANK H.
    EASTERBROOK & DANIEL R. FISCHEL, THE ECONOMIC STRUCTURE                    OF
    CORPORATE LAW 193 (1996).         Isolating the impact of the breach of
    contract from other factors contributing to investors’ reduced interest in
    a company will rarely be an easy task.
    The law does not charge contracting parties with a duty to
    understand how their actions will affect the counterparty’s market
    valuation. SIS points to no authority to the contrary, and we are aware
    of none.   We do not expect contracting parties, regardless of their
    sophistication, to study the market for acquiring their counterparties
    before entering into a contract or breaching one. As a general rule,
    neither the counterparty’s market value nor the impact of breach on that
    value will be reasonably foreseeable at the time of contracting. SIS
    offered no evidence distinguishing IP from this general rule.               It
    attempted to show that IP was intimately familiar with SIS’s business
    because of the companies’ close relationship. But again, knowledge of a
    business is not the same as knowledge of the market for buying and
    selling that business. 6
    As we said in Basic Capital, “a general knowledge of a prospective
    borrower’s business does not give a lender reason to foresee the probable
    results of its refusal to” perform. 348 S.W.3d at 902. In other words, a
    6  Even companies that know the market for buying and selling
    businesses will generally have no duty to investigate or foresee the market
    value of companies with which they contract, provided that the contract itself
    is not concerned with the market value of the counterparty.
    15
    party’s mere familiarity with another company does not alone make the
    collapse of that company a foreseeable consequence of breach. Id. at
    901–02. The same is true here. IP’s familiarity with SIS’s business did
    not make SIS’s precipitous decline in attractiveness to buyers a
    foreseeable consequence of breach.
    SIS contends that, beyond general familiarity, IP was specifically
    aware that SIS needed speedy payment to fund future business and that
    an unexpected cash-flow crunch could be devastating to SIS. The only
    evidence SIS offered on this point was (1) the parties’ longstanding
    familiarity with one another, (2) the fact that IP’s employees later
    learned of SIS’s financial distress, and (3) the assertion that
    construction is a “gossipy-type industry.”         Even assuming that SIS
    established IP’s knowledge of SIS’s precarious financial position, that
    does not make the effect of breach on SIS’s market value foreseeable. As
    in Basic Capital, one traditional measure of consequential damages is
    lost profits, which must be established with reasonable certainty. 348
    S.W.3d at 898, 901. SIS could have sought such damages, but it chose
    not to. Instead, it laid its overall decline in market value—not the
    discrete injuries that caused its market value to decline—at IP’s feet.
    But even if IP should reasonably have foreseen that its breach would
    cost SIS a great deal of business, SIS’s decline in market value is a
    fundamentally different matter.             Damages for that loss were
    unforeseeable and therefore unavailable. 7
    7  In addition to arguing foreseeability, IP also argues that “company
    value” damages are not available as a matter of law because they reflect “paper
    losses” in SIS’s theoretical market value, not actual cash losses suffered by the
    time of trial. See DAN B. DOBBS & CAPRICE L. ROBERTS, LAW OF REMEDIES
    16
    Parties need not scour the balance sheets of their counterparties
    and weigh the likely consequences of breach on the counterparty’s
    attractiveness to investors. 8       Far from helping new and unstable
    § 3.4 (3d ed. 2018) (explaining that “consequential losses must have been
    realized or must be likely to be realized in the future” to be recoverable, so
    “bookkeeping losses do not count when it comes to consequential damages”).
    Because we reverse the award for lack of foreseeability, we do not consider
    whether the damages suffer from this additional defect. We also do not
    consider another potential bar to “company-value” damages. IP argued in the
    court of appeals that SIS could never recover for its decline in market value
    because those losses were suffered by the company’s owners, not by SIS itself.
    Unlike withholding payment to SIS on the slaker contract, which harms SIS
    itself, a deterioration in SIS’s value as an asset harms those who hold the
    asset—so the argument goes. After all, it is SIS’s owners, not SIS itself, who
    would be paid by a buyer like Primoris if SIS were sold. If this argument is
    correct, then SIS itself was ineligible to seek recovery for a decline in its market
    value, and the eligible entities—SIS’s owners—were not parties to the slaker
    contract and therefore could not sue for its breach. But IP does not press this
    argument here, so we do not consider it.
    8  Of course, parties can give notice of their dire financial straits at the
    time of contracting. See, e.g., W. Union Tel. Co. v. Brooks, 
    279 S.W. 443
    , 444
    (Tex. 1926). When one party has given notice of the consequences of breach at
    the time of contracting, no further inquiry into the foreseeability of those
    consequences is required. Elijah Ragira/VIP Lodging Grp., Inc. v. VIP
    Lodging Grp., Inc., 
    301 S.W.3d 747
    , 756 (Tex. App.—El Paso 2009, pet. denied)
    (“[I]f the special circumstances under which the contract was actually made
    were communicated by the plaintiffs to the defendants, and thus known to both
    parties, the damages resulting from the breach of such a contract, which they
    would reasonably contemplate, would be the amount of injury which would
    ordinarily follow from a breach of contract under these special circumstances
    so known and communicated.”) (emphasis added) (quoting Hadley, 9 Exch. at
    354–55); RESTATEMENT (SECOND) OF CONTRACTS § 351 cmt. b (“If loss results
    other than in the ordinary course of events, there can be no recovery for it
    unless it was foreseeable by the party in breach because of special
    circumstances that he had reason to know when he made the contract.”).
    Relying on this rule, a party in SIS’s position could give notice of its pending
    sale and of its expectation that a breach would scuttle the sale and drive its
    company’s value into the ground, thereby resulting in losses far exceeding the
    size of the contract. Whether anyone would contract with such a company is
    17
    businesses like SIS, such a rule would encourage parties to contract only
    with large, established companies. Few rational parties would contract
    with a fledgling company for whom a $2.4 million non-payment might
    one day be worth $56 million in “company value” damages.
    In sum, the decline in SIS’s market value reflected in the jury’s
    award was not foreseeable to IP and was therefore not available as
    consequential damages. We affirm the court of appeals’ reversal of $42
    million of the award on foreseeability grounds. The court of appeals left
    in place $12.4 million of the award, to which we now turn.
    C.   Damages for the Company’s Lost Book Value
    The jury was instructed to measure the “[d]amages to Signature’s
    company value.” 9 It awarded over $56 million. The court of appeals
    concluded that $12.4 million of that amount was supported by legally
    sufficient evidence. 628 S.W.3d at 579. The $12.4 million upheld by the
    court of appeals was derived from the calculations of SIS’s expert, who
    testified that SIS’s “book value” declined by $12.4 million as a result of
    the breach.
    While book value serves a purpose in accounting, we conclude
    that a drop in book value, without more, cannot support an award of
    consequential damages for breach of contract. Again, consequential
    another matter. And whether bars other than foreseeability would foreclose
    such damages is a question we do not address.
    9 The jury charge did not define “company value.” To the extent
    “company value” is understood to mean market value, we have already
    explained why a decline in SIS’s market value was unforeseeable and therefore
    unrecoverable. To the extent “company value” could refer also to “book value,”
    we will separately address the court of appeals’ allowance of $12.4 million in
    “book value” damages.
    18
    damages must be “proved with reasonable certainty.” Phillips, 475
    S.W.3d at 278. SIS’s use of book value as a damages measure fails to
    satisfy this requirement. The jury was asked to rely on SIS’s bottom-line
    book value without analysis of specific items on the balance sheet. SIS’s
    expert testified that before the breach, in December of 2013, the
    company had a book value of $3,322,442. After the breach, in March of
    2016, that value was underwater by $9,109,059. The difference between
    those two numbers is the $12.4 million upheld by the court of appeals.
    We cannot agree that SIS proved losses of $12.4 million with the
    requisite reasonable certainty.
    To begin with, SIS seems to have used book value as a proxy for
    the value of the company as an asset, i.e., its market value. But “[b]ook
    value and market value are not the same.” Pike v. Tex. EMC Mgmt.,
    LLC, 
    610 S.W.3d 763
    , 785 (Tex. 2020). In Pike, the plaintiff tried to
    demonstrate the value of an interest in a partnership by showing the
    book value of its cement plant.       
    Id.
       We rejected the evidence as
    insufficient to show the actual loss in value suffered because the book
    value of the asset is not its fair market value. Id. at 784. Instead, book
    value is “simply the value of [a company’s] total assets . . . less the value
    of its total liabilities”—that is, “the amount of the company’s assets that
    would be left after the company’s creditors are paid off in full.” HAAS,
    CORPORATE FINANCE 74. It is an accounting concept, the decline of which
    does not necessarily reflect actual losses to the company.
    Merely demonstrating a decline in book value, as did SIS’s expert,
    does not prove any actual losses—with reasonable certainty or
    otherwise. For this reason, Texas courts have long rejected the use of
    19
    book value as a measure of damages. “Book value is entitled to little, if
    any, weight in determining the value of corporate stock, and many other
    factors must be taken into consideration.” Bendalin v. Delgado, 
    406 S.W.2d 897
    , 900–01 (Tex. 1966). Several court of appeals decisions
    similarly criticize attempts to use book value as a proxy for the value of
    a company to its owners. 10 We see no reason to depart from these
    precedents. As an accounting measure, book value has its uses. But the
    aggregate number itself offers only a limited, big-picture view of the
    company’s financial situation.      It tells the jury nothing about the
    underlying losses actually suffered by the company that contributed to
    the drop in book value, and it tells the jury nothing about the overall
    decline in the market value of the company as an asset. The $12.4
    million in book-value damages upheld by the court of appeals must be
    reversed.
    ***
    SIS has not sought to recover lost profits as an alternative
    measure of consequential damages, nor has it offered evidence to
    support such a recovery. In some past cases where a “charge failed to
    instruct the jury on the proper measure of . . . damages,” we have
    “remand[ed] . . . for a new trial” so long as there was “some evidence”
    10Bhatia v. Woodlands N. Hous. Heart Ctr., PLLC, 
    396 S.W.3d 658
    , 667
    (Tex. App.—Houston [14th Dist.] 2013, pet. denied) (“Book value is an
    improper method for determining the value of [a business] because such values
    are mere arbitrary entries in a ledger.”); Mandell v. Mandell, 
    310 S.W.3d 531
    ,
    537 (Tex. App.—Fort Worth 2010, pet. denied) (“Book value has limited
    application, if any, in determining the value of . . . a small, closely held
    corporation.”); Lee v. Hersey, 
    223 S.W.3d 439
    , 448 (Tex. App.—Amarillo 2006,
    pet. denied) (“[F]inancial statements . . . provide no probative evidence of
    market value . . . .”).
    20
    that could support a specific amount of damages based on valid criteria.
    Arthur Andersen & Co. v. Perry Equip. Corp., 
    945 S.W.2d 812
    , 817 (Tex.
    1997); ERI Consulting Eng’rs, Inc. v. Swinnea, 
    318 S.W.3d 867
    , 880
    (Tex. 2010) (remanding because “competent evidence exists to establish
    some reasonably certain amount of lost profits” other than the amount
    awarded). If, however, no evidence supports lost profits under a proper
    theory, we have rendered judgment. See Horizon Health Corp. v. Acadia
    Healthcare Co., 
    520 S.W.3d 848
    , 866 (Tex. 2017) (rendering a
    take-nothing judgment when the evidence was legally insufficient to
    establish lost profits with the requisite certainty). Here, SIS did not
    establish with reasonable certainty the size of any particular lost profits.
    It sought only the recovery of its overall loss in company value, and such
    damages were unavailable for the reasons explained above.              Any
    evidence in the record regarding the amount of specific lost profits is
    scantier than what we rejected in Horizon Health.           
    Id.
     at 860–64.
    Accordingly, we affirm the court of appeals’ judgment rejecting the $42
    million damages for lost market value and reverse its judgment
    upholding damages based on a decline in book value.             We render
    judgment that SIS take nothing on its claim for consequential damages.
    III.   Direct Damages
    IP also appeals the award of direct damages, which the court of
    appeals affirmed. The jury awarded $2.4 million in direct damages,
    which reflect the difference between what IP paid and the amount SIS
    claimed IP owed. The court of appeals reviewed all the evidence and
    determined that it could not say there was legally insufficient evidence
    for the full $2.4 million award. 628 S.W.3d at 576–77. IP attacks two
    21
    discrete portions of the direct damages award, which are reflected in two
    invoices totaling around $1.2 million.
    Invoice #1200-6087 shows $622,560.61 in charges to IP for
    (1) overhead, (2) tax penalties, and (3) lost revenue due to non-payment.
    IP contends these charges are prohibited by the contract and are
    therefore unrecoverable as a matter of law. See Wade & Sons, Inc. v.
    Am. Standard, Inc., 
    127 S.W.3d 814
    , 824 (Tex. App.—San Antonio 2003,
    pet. denied). We agree.
    First, the contract prohibited SIS from billing IP for the “[w]ages
    of any employee in [SIS’s] home office or any employee not directly
    employed on th[is] Project,” “[i]nterest on capital employed either in
    plant or in expenditures on the Project,” or “[o]verhead or general
    expenses of any kind.” The invoice charged for back-office staffing costs
    as well as time that management spent meeting with IP about the
    project, not for labor on the slaker project itself. These are plainly
    “overhead or general expenses of any kind,” so the contract forbids SIS
    from charging IP for those costs.        Second, the contract made SIS
    responsible for “pay[ing] . . . any tax or contribution required by any
    applicable Federal, State or local laws.” As a result, the tax penalties
    reflected on the invoice were not chargeable to IP. Third, the invoice’s
    charge for “lost revenue . . . due to the loss of work from non-payment
    and suit” would be a matter of consequential damages, not direct
    payment under the contract.
    None of the charges reflected in Invoice #1200-6087 is allowed by
    the contract. SIS has offered no substantive defense of these charges
    beyond the assertion that the jury could consider all the invoices and
    22
    arrive at this damages award. And the court of appeals never addressed
    whether the contract expressly barred the items in Invoice #1200-6087,
    despite IP’s arguments to that effect. We conclude that the parties’
    agreement precludes these charges, and it is undisputed that the direct
    damages award includes the full amount of this invoice. The direct
    damages must be reduced by the amount of the invoice, $622,560.61.
    Invoice #1200-6088 sought $647,309.93 to compensate SIS for the
    “cost of management and field labor,” “materials,” and “equipment . . .
    not previously billed to [IP].”    The contract makes these expenses
    chargeable to IP. Moreover, a separate contract between the parties
    allows for the charges listed, and the court of appeals correctly
    determined that the jury was allowed to consider that contract as well.
    628 S.W.3d at 576.
    IP argues that because the parties had agreed to negotiate
    regarding what portion of the costs IP would pay, IP cannot be liable for
    the full amount of the invoice. But the conclusion does not follow from
    the premise. The parties did agree to negotiate if disputes arose, but
    that does not render ephemeral IP’s promise to pay amounts it owed.
    The agreement to negotiate did not preclude the jury from finding that
    IP owed the full amount of the invoice. We conclude that sufficient
    evidence supported the jury’s conclusion that IP owed SIS the amounts
    reflected in this invoice. City of Keller, 168 S.W.3d at 810.
    When a lump-sum damages award contains both compensable
    and non-compensable damages, we have remanded the entire award for
    retrial based only on the compensable portion.        County of Bexar v.
    Santikos, 
    144 S.W.3d 455
    , 464 (Tex. 2004). Here, however, we have
    23
    concluded as a matter of law that IP did not breach the parties’ contract
    by failing to pay Invoice #1200-6087, and it is undisputed that the jury
    awarded SIS damages for the full amount of that invoice—
    $622,560.61—as part of its award of direct damages for contract
    breaches. Because SIS cannot legally recover these damages, which are
    cleanly excisable from the total award, we render judgment reducing the
    award of direct damages by this amount. See TEX. R. APP. P. 60.2(c)
    (permitting the Supreme Court to render the judgment that a lower
    court should have rendered); Barker v. Eckman, 
    213 S.W.3d 306
    , 310
    (Tex. 2006) (affirming reduction in damages award for contract breaches
    where recovery for some breaches was legally barred by limitations and
    amount of damages awarded for each breach was undisputed).
    IV.    Indemnification
    IP claims that SIS must indemnify it for expenses incurred
    defending the suit brought by Ogden. The court of appeals disagreed.
    We affirm, but for a different reason than the court of appeals.
    The contract requires SIS to indemnify IP for its defense costs if
    “any person makes a claim” for “damage or injury of any kind” that is
    “caused by, resulting from, arising out of, or occurring in connection with
    the performance by [SIS]” of the contract. 11 The indemnity provision
    11   The relevant provision reads:
    6. Indemnity. [SIS] assumes the defense and the entire responsibility and
    liability for any and all damage or injury of any kind or nature (including
    resulting death) to all persons, whether employed by [SIS] or otherwise,
    including but not limited to (a) employees and agents of subcontractors of [SIS]
    or [IP], or (b) any other third party, and to all property (other than the work
    itself as set out in paragraph 7 below) caused by, resulting from, arising out of,
    or occurring in connection with the performance by [SIS], or any subcontractor
    or agent of [SIS], of this AGREEMENT. In the event the liability of [SIS] shall
    24
    has an exception, however, for when liability “arise[s] by reason of the
    sole negligence of [IP].” In such cases, SIS “shall not be liable.”
    The court of appeals understood the “sole negligence” exception to
    cover this case because the case involves only alleged wrongdoing by IP
    and no wrongdoing on the part of SIS. That was error. Under the
    language chosen by the parties, the exception is triggered when liability
    arises by reason of IP’s negligence, not its breaches of contract. See Sw.
    Bell Tel. Co. v. DeLanney, 
    809 S.W.2d 493
    , 494–95 (Tex. 1991)
    (distinguishing negligence and breach of contract). The alleged liability
    in this case does not arise from any form of negligence at all. Ogden
    sued IP for breach of contract and fraud, not negligence. The indemnity
    clause’s “sole negligence” exception therefore has no application.
    The result should nevertheless be affirmed. The Insurance Code
    forbids certain construction contracts from requiring an indemnitor to
    indemnify an indemnitee for “a claim caused by the . . . fault . . . or the
    breach of contract of the indemnitee.”             TEX. INS. CODE § 151.102
    (emphasis added). 12 Because Ogden’s claims complain of IP’s fraud and
    arise by reason of the sole negligence of [IP], then and only then, [SIS] shall
    not be liable under the provisions of this paragraph. If any person makes a
    claim for any such damage or injury (including death resulting therefrom) as
    hereinabove described, [SIS] agrees to indemnify and save harmless [IP], its
    agents, servants and employees from and against any and all loss, damage,
    injury or expense including reasonable attorney’s fees that [IP] may sustain as
    a result of any such claims . . . .
    12 This subchapter of the Insurance Code applies to construction
    contracts for “project[s] for which . . . indemnitor[s]” are “provided or procure[]
    insurance subject to” Chapter 151 or Title 10. TEX. INS. CODE § 151.101(a).
    SIS has consistently argued that section 151.102 applies to the slaker contract,
    and IP has never suggested that the statute does not cover the agreement.
    25
    breach of contract, we conclude that the statute renders the indemnity
    agreement ineffective to the extent it would require SIS to indemnify IP
    against Ogden’s suit.
    IP argues that Ogden’s injuries were actually “caused by” SIS’s
    wrongdoing —its failure to pay payroll taxes—rather than by IP’s fraud
    or breach of contract. IP may be correct that the true cause of Ogden’s
    personal liability and the follow-on harms to his credit and reputation
    was SIS’s failure to pay taxes. But we do not understand section 151.102
    to ask who is truly at fault for the injuries complained of. Instead, it
    asks only whether the “claim” for which indemnity is sought was “caused
    by” the fault or breach of contract of the indemnitee. See Union Pac.
    R.R. v. Brown, No. 04-17-00788-CV, 
    2018 WL 6624507
    , at *5 (Tex.
    App.—San Antonio Dec. 19, 2018, no pet.) (requiring the indemnitee to
    identify pleadings alleging its liability for the fault of the indemnitor).
    Here, no one disputes that the “claim” is Ogden’s suit alleging
    fraud and breach of contract due to IP’s refusal to pay under the slaker
    contract.   For purposes of the anti-indemnity statute, IP’s alleged
    breach—which IP no longer disputes—was the cause of Ogden’s claim,
    regardless of whether SIS’s actions were also part of what truly brought
    about the injuries alleged by Ogden.       The statute does not require
    factual inquiry into the “true” cause of the plaintiff’s injuries. Absent
    fraud or some other unusual circumstance not present here, examining
    the pleadings will generally be a sufficient basis to determine whether
    Because no party argues otherwise, we will assume section 151.101(a) applies
    to the agreement.
    26
    the “claim” was “caused by” the fault or breach of contract of the party
    seeking indemnification. TEX. INS. CODE § 151.102.
    V.    Ogden’s Claims
    Jeffry Ogden, SIS’s President, also sued IP in his individual
    capacity for fraud and breach of contract. He received a $67 million
    award. The court of appeals reversed the award in its entirety and
    rendered judgment against Ogden, holding that the elements of fraud
    were not met and that Ogden had no right to sue on the contract between
    SIS and IP. 628 S.W.3d at 580–81. Ogden challenges the court of
    appeals’ decision only with respect to his breach-of-contract claim. We
    affirm.
    Ogden was neither a party to the contract nor in privity with one.
    He sued under two theories—assignment and agency—that he claims
    allow him to personally recover against IP for breach of a contract
    between IP and SIS. Both theories fail.
    First, Ogden argues that SIS assigned the right to sue under the
    contract to him. But the contract has a non-assignment clause. Such
    clauses are enforceable. Island Recreational Dev. Corp. v. Republic of
    Tex. Sav. Ass’n, 
    710 S.W.2d 551
    , 556 (Tex. 1986). Even if there were no
    such clause, Ogden has not pointed to any words or actions by SIS that
    demonstrate an intent to assign the contract to him. If anything, SIS
    demonstrated its intent not to assign its rights by suing to enforce the
    contract on its own.
    Second, Ogden argues that, as an agent of SIS with an interest in
    the contract, he can sue for breach. The law does not support Ogden’s
    agency theory. In Tinsley v. Dowell, 
    26 S.W. 946
    , 948 (Tex. 1894), we
    27
    held that the “general rule is that one who contracts as agent cannot
    maintain an action, in his own name and right, upon the contract.” We
    recognized four narrow exceptions: (1) “where the agent contracts in his
    own name”; (2) “where the agent does not disclose his principal”; (3)
    “where the agent is authorized to act as owner of the property” by “the
    usages of trade”; and (4) “where the agent has an interest in the subject-
    matter of the contract.” 
    Id.
     In that case, Dowell had attempted to sue
    on his principal’s land-sale contract. We held that his only interest in
    the contract was a percentage of the proceeds, but the subject-matter of
    the contract was the land itself. When Tinsley breached by failing to
    purchase the land, Dowell had no right to sue on the contract. Id. at
    949. 13
    Ogden has not shown that any of the exceptions articulated in
    Tinsley apply here. The jury found that Ogden had an “interest” in the
    subject-matter of the contract, but this is unsupportable as a matter of
    law. 14 The subject of the contract was work by SIS and payment by IP,
    which was owed to SIS alone. Ogden’s hope that SIS would be paid and
    would in turn pay off tax debt he had guaranteed is not a legally
    See also Cavaness v. Gen. Corp., 
    283 S.W.2d 33
    , 37 (Tex. 1955) (noting
    13
    that an agent’s personal ownership of the patent rights in a licensing contract
    “would be the kind of personal interest contemplated by the rule”); Harper v.
    Welchem, Inc., No. C14-91-00627-CV, 
    1992 WL 198620
    , at *2 (Tex. App.—
    Houston [14th Dist.] Aug. 20, 1992, writ denied) (rejecting a plaintiff’s claims
    for lack of an “in rem interest” or other interest in the contract “adequate for
    the purposes of the fourth Tinsley exception”).
    Unless underlying material facts are in dispute and therefore require
    14
    resolution by a jury, the question of whether a party has an interest in the
    subject-matter of another party’s contract sufficient to allow him to sue on the
    contract will be a question of law for the court.
    28
    cognizable “interest in the subject-matter of the contract” sufficient to
    authorize Ogden to sue in his personal capacity for injuries to his
    company. The jury may have mistakenly found otherwise based on a
    colloquial understanding of the word “interest.” But Ogden had no more
    legal interest in the slaker contract than any other officer of a closely
    held company has in his company’s contracts. To hold that he can sue
    for breach of SIS’s contracts in his personal capacity would collapse the
    distinction between corporate entities and their individual owners or
    officers. Ogden cites no authority supporting such an outcome.
    In any event, Ogden cites no case in which an individual with an
    interest in a contract has been permitted to sue as an agent or assignee
    when the principal is already suing on the same contract for the same
    breach. The resulting duplicative litigation and double recovery are
    self-evidently inappropriate. We affirm the court of appeals’ rendition
    of judgment against Ogden.
    VI.    Conclusion
    The judgment of the court of appeals is affirmed in part and
    reversed in part. Judgment is rendered that SIS take nothing on its
    claim for consequential damages. Judgment is rendered reducing SIS’s
    recovery of direct damages by $622,560.61.        As for IP’s claim for
    indemnity, the judgment of the court of appeals is affirmed. The court
    of appeals’ rendition of judgment that Ogden take nothing is likewise
    affirmed. The case is remanded to the district court for any further
    proceedings that may be necessary.
    29
    James D. Blacklock
    Justice
    OPINION DELIVERED: January 14, 2022
    30