Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc. , 518 S.W.3d 432 ( 2017 )


Menu:
  •                 IN THE SUPREME COURT OF TEXAS
    ══════════
    No. 16-0054
    ══════════
    BARTUSH-SCHNITZIUS FOODS CO., PETITIONER,
    v.
    CIMCO REFRIGERATION, INC., RESPONDENT
    ══════════════════════════════════════════
    ON PETITION FOR REVIEW FROM THE
    COURT OF APPEALS FOR THE SECOND DISTRICT OF TEXAS
    ══════════════════════════════════════════
    PER CURIAM
    This contract dispute involves competing breach claims by a food-product manufacturer,
    Bartush-Schnitzius Foods Co. (Bartush), and a refrigeration contractor, Cimco Refrigeration, Inc.
    (Cimco). The jury found that both parties failed to comply with their agreement and assessed
    damages accordingly, but the trial court rendered judgment solely for Bartush. The court of
    appeals reversed and remanded for entry of judgment solely in Cimco’s favor. We hold that neither
    the trial court nor the court of appeals properly effectuated the jury’s verdict. We reverse the court
    of appeals’ judgment and remand the case to that court to consider unaddressed issues.
    In 2010, Bartush planned to expand its line of food products to include seafood dips.
    Manufacturing the dips required Bartush’s production facilities to maintain a constant temperature
    no higher than thirty-eight degrees—lower than Bartush’s existing refrigeration system could
    sustain. Bartush therefore contracted with Cimco to install a new system. Cimco sent Bartush an
    offer letter with three quoted options. The offer letter did not reference a particular temperature
    range. Bartush orally selected the most expensive of the three options, confirming the selection
    via email. Bartush then began paying Cimco in agreed-upon installments.
    After installation, Bartush started to operate the new system at a temperature setting of
    thirty-five degrees. However, this resulted in ice forming on the fan motors because the system’s
    defrost unit was not designed to support operation at such a low temperature. The ice caused the
    motors to overheat and fail, leading to higher temperatures that at times climbed into the 50s and
    60s. When Bartush discovered the problem, it had already paid Cimco $306,758 on the contract
    but still owed $113,400. Bartush communicated with Cimco about a repair, but after several weeks
    without receiving what it considered a workable plan, Bartush withheld further payment and
    contacted an independent refrigeration engineer. The engineer recommended a warm-glycol
    defrost unit, and Bartush contracted with Jax Refrigeration, Inc. to install the unit at a cost of
    $168,079. After the warm-glycol defrost unit was installed, the system was able to maintain the
    target temperature of thirty-five degrees.
    In response to Bartush’s nonpayment, Cimco sued Bartush to recover the balance owed on
    the contract.1 Bartush counterclaimed for breach of contract, seeking damages for, among other
    things, the costs associated with the warm-glycol defrost unit.2 Bartush also alleged that its failure
    to pay was justified by Cimco’s prior material breach. Cimco asserted that the equipment it
    installed was exactly as described in the accepted purchase order and denied that it had made any
    guarantee regarding the equipment’s capacity to maintain a specific temperature.
    1
    Cimco brought an alternative claim for quantum meruit and also asserted claims for violation of the Prompt
    Pay Act and foreclosure of a mechanic’s and materialmen’s lien. Only the contract claim was submitted to the jury.
    2
    Bartush also brought several tort claims against Cimco. The jury found in Cimco’s favor on those claims,
    and Bartush did not challenge the findings on appeal.
    2
    The parties’ claims were tried to a jury. The jury answered the relevant liability portions
    of the charge as follows: “YES” to Question 1, which asked whether Bartush failed to comply with
    the agreement; “YES” to Question 2, which asked whether Cimco failed to comply with the
    agreement; “CIMCO” to Question 3, which asked who failed to comply with the agreement first;
    and “NO” to Question 4, which asked whether Bartush’s failure to comply was excused. The jury
    awarded Bartush $168,079 in damages (the cost of installing the warm-glycol defrost unit), plus
    $215,000 in trial and conditional appellate attorney’s fees. The jury also awarded Cimco $113,400
    (the balance due on the contract). The jury did not answer the question regarding Cimco’s
    attorney’s fees because the question was conditioned in part on a finding that Bartush breached
    first.
    Despite the jury’s findings that both parties failed to comply and Bartush’s failure to
    comply was not excused, the trial court stated in its final judgment that “it appears to the Court
    that the verdict of the jury was for [Bartush] and against [Cimco],” and rendered judgment in
    Bartush’s favor for $168,079 in damages, plus pre- and post-judgment interest, costs, and
    attorney’s fees. The judgment awarded nothing to Cimco, and Cimco appealed.
    The court of appeals reversed and remanded to the trial court for entry of judgment that
    Bartush take nothing and that Cimco recover $113,400 in damages, plus interest and costs. ___
    S.W.3d ___ (Tex. App.—Fort Worth 2015). The court of appeals held that the jury’s express
    finding that Bartush’s failure to comply was not excused necessarily included an implied finding
    that Cimco’s prior breach was nonmaterial. Id. at ___. The court further held that Bartush’s failure
    to pay the balance due was a material breach of the contract as a matter of law, which rendered
    irrelevant the jury’s finding that Cimco breached first and precluded Bartush’s recovery. 
    Id. 3 Finally,
    the court of appeals held that Cimco waived its challenge to the jury’s failure to award
    attorney’s fees. Id. at ___ n.9.
    Both parties filed petitions for review. Bartush argues the trial court’s judgment should be
    reinstated because Cimco’s “first” breach was material as a matter of law and thus excused
    Bartush’s subsequent failure to comply with the agreement. Alternatively, Bartush argues that
    both damages awards should be given effect, resulting in Bartush’s net recovery of $54,679 in
    compensatory damages. Cimco responds that the court of appeals correctly concluded that
    Bartush’s material breach excused Cimco’s nonmaterial breach.3 In a cross-petition, Cimco
    challenges the court of appeals’ holding that Cimco waived error regarding the jury’s failure to
    award attorney’s fees.
    We first address Bartush’s argument that the trial court properly rendered judgment entirely
    in its favor because Bartush’s failure to comply (i.e., nonpayment) was excused as a matter of law
    by Cimco’s prior material breach. “It is a fundamental principle of contract law that when one
    party to a contract commits a material breach of that contract, the other party is discharged or
    excused from further performance.” Mustang Pipeline Co. v. Driver Pipeline Co., 
    134 S.W.3d 195
    , 196 (Tex. 2004) (citing Hernandez v. Gulf Grp. Lloyds, 
    875 S.W.2d 691
    , 692 (Tex. 1994)).
    By contrast, when a party commits a nonmaterial breach, the other party “is not excused from
    future performance but may sue for the damages caused by the breach.” Levine v. Steve Scharn
    3
    As an alternative basis to affirm the court of appeals’ judgment, Cimco argues that no evidence supports
    the jury’s finding that it failed to comply with the parties’ agreement because the parol evidence rule bars enforcement
    of the disputed term regarding temperature. Cimco also made this argument in the court of appeals, but because that
    court reversed the trial court’s judgment on other grounds, it did not reach the issue. We will leave it to the court of
    appeals to address the issue in the first instance on remand.
    4
    Custom Homes, Inc., 
    448 S.W.3d 637
    , 654 (Tex. App.—Houston [1st Dist.] 2014, pet. denied).4
    The latter principle is consistent with settled Texas law regarding the elements of a contract claim.
    The claim requires a finding of breach, not a finding of material breach. See, e.g., Mays v. Pierce,
    
    203 S.W.3d 564
    , 575 (Tex. App.—Houston [14th Dist.] 2006, pet. denied) (“A breach of contract
    occurs when a party fails or refuses to do something he has promised to do.”). Accordingly, a
    material breach by Cimco would have excused Bartush from making further contractual payments,
    while a nonmaterial breach would have simply given rise to a claim for damages.
    In this case, as noted, the jury found that both parties failed to comply with the agreement.
    The jury was instructed that Bartush’s failure to comply was excused if Cimco previously “failed
    to comply with a material obligation of the same agreement,” and listed five nonexclusive
    “circumstances to consider in determining whether a failure to comply is material.” Although the
    jury found that Cimco failed to comply first, it also found that Bartush’s breach was not excused.
    To make the latter finding, the jury must have concluded that Cimco’s prior breach was not
    material. We therefore agree with the court of appeals that the jury made such an implied finding.
    Notwithstanding the jury’s implied finding of nonmateriality, Bartush argues that Cimco’s
    failure to provide a refrigeration system capable of maintaining a temperature of thirty-five degrees
    was a material breach as a matter of law, excusing Bartush from further performance. We disagree.
    Generally, materiality is an issue “to be determined by the trier of facts.” Hudson v. Wakefield,
    
    645 S.W.2d 427
    , 430 (Tex. 1983). Like other issues of fact, materiality may be decided as a matter
    4
    Accord Gilbert v. Fitz, No. 05-16-00218-CV, 
    2016 WL 7384167
    , at *6 (Tex. App.—Dallas Dec. 21, 2016,
    no pet.); Harris Cty. Util. Dist. No. 16 v. Harris Cty. Mun. Dist. No. 36, No. 01-10-00042-CV, 
    2011 WL 3359698
    , at
    * 9 (Tex. App.—Houston [1st Dist.] Aug. 4, 2011, no pet.); DAVID R. DOW & CRAIG SMYSER, TEXAS PRACTICE:
    CONTRACT LAW § 9.3 (2005).
    5
    of law only if reasonable jurors could reach only one verdict. See City of Keller v. Wilson, 
    168 S.W.3d 802
    , 822 (Tex. 2005) (“If the evidence at trial would enable reasonable and fair-minded
    people to differ in their conclusions, then jurors must be allowed to do so.”).
    In Mustang Pipeline, we outlined several factors enumerated in the Restatement that are
    “significant in determining whether a failure to perform is 
    material.” 134 S.W.3d at 199
    (citing
    RESTATEMENT (SECOND) OF CONTRACTS § 241 (Am. Law Inst. 1981)). These factors include:
    (a)     the extent to which the injured party will be deprived of the benefit which
    he reasonably expected;
    (b)     the extent to which the injured party can be adequately compensated for the
    part of that benefit of which he will be deprived;
    (c)     the extent to which the party failing to perform or to offer to perform will
    suffer forfeiture;
    (d)     the likelihood that the party failing to perform or to offer to perform will
    cure his failure, taking account of the circumstances including any
    reasonable assurances;
    (e)     the extent to which the behavior of the party failing to perform or to offer
    to perform comports with standards of good faith and fair dealing.
    
    Id. The jury
    charge in this case listed these factors for the jury’s consideration in evaluating
    whether Cimco’s failure to comply was material. The parties presented trial evidence that could
    have led the jurors to reasonably disagree regarding the application of these factors, including
    conflicting evidence on the parties’ communications regarding temperature requirements. By
    contrast, in Mustang we held that a contractor’s failure to meet a deadline in contravention of an
    express time-is-of-the-essence clause was a material breach as a matter of law. 
    Id. at 199–200.
    No such conclusive evidence of materiality exists in this case. Because reasonable jurors could
    6
    have disagreed on whether Cimco breached a material obligation, we may not overrule the jury’s
    implied finding on that issue.
    Bartush next argues that, even accepting the jury’s finding that its failure to comply with
    the agreement was not excused, the court of appeals erred in holding that “Bartush’s unexcused
    and material breach” (failing to pay the balance due) renders irrelevant the jury’s finding that
    Cimco breached first and “precludes Bartush’s recovery under the contract.” ___ S.W.3d at ___.
    Bartush contends that the court should have given effect to the jury’s damages awards to both
    parties. We agree.
    While a party’s nonmaterial breach does not excuse further performance by the other party,
    neither does the second breach excuse the first. To the contrary, a material breach does not
    discharge a claim for damages that has already arisen. RESTATEMENT (SECOND) OF CONTRACTS §
    237 cmt. e (Am. Law Inst. 1981); see also Allied Capital Partners, LP v. Proceed Tech. Res., Inc.,
    
    313 S.W.3d 460
    , 465 (Tex. App.—Dallas 2010, no pet.) (citing the Restatement for the proposition
    that “a material breach will not discharge an obligation of the non-breaching party that arose before
    the alleged breach”). In other words, a material breach excuses future performance, not past
    performance. The court of appeals turned the doctrine on its head, effectively holding that
    Bartush’s nonpayment retroactively excused Cimco’s prior breach. This was error.
    In sum, the jury’s findings that Cimco failed to comply with the agreement first and that
    its failure to comply was not material mean that (1) Bartush remained liable for its subsequent
    failure to comply, but (2) Bartush’s claim for damages caused by Cimco’s prior breach remained
    7
    viable.5 Cimco had a preexisting duty to perform under the contract, and the jury found that Cimco
    violated that duty before Bartush breached by withholding payment.
    Accordingly, the court of appeals erred in holding that Bartush’s breach barred its recovery
    of damages for Cimco’s failure to perform a preexisting obligation, and we therefore reverse the
    court’s judgment. Because the court of appeals did not reach Cimco’s alternative argument that
    the trial court’s judgment should be reversed on the ground that no evidence supported the jury’s
    finding that Cimco failed to comply with the parties’ agreement, we remand the case to the court
    of appeals to do so.
    Finally, we address the attorney’s-fees issue raised in Cimco’s cross-petition. Cimco
    contends that, as a prevailing party on its breach-of-contract claim, it is entitled to a remand for a
    determination of its attorney’s fees. See TEX. CIV. PRAC. & REM. CODE § 38.001. Although the
    court of appeals rendered judgment in Cimco’s favor, the court held that Cimco failed to preserve
    error regarding the jury’s failure to award it attorney’s fees.
    As noted, the jury awarded Cimco damages for Bartush’s failure to comply with the
    agreement; however, the jury left blank Question 24—which asked the jury to assess Cimco’s
    attorney’s fees—because it was conditioned on the following answers: “yes” to Question 1 (did
    Bartush fail to comply); “Bartush” to Question 3 (who failed to comply first); and “no” to Question
    4 (was Bartush’s breach excused). Because the jury answered “Cimco” to Question 3, it did not
    answer Question 24 in accordance with the instruction. Cimco did not object to the conditional
    5
    A similar state of affairs often arises in the context of construction contracts, when a contractor sues for the
    balance due and owing on the contract and the property owner counterclaims for damages for incomplete or defective
    performance. See Vance v. My Apartment Steak House of San Antonio, Inc., 
    677 S.W.2d 480
    (Tex. 1984). In such
    cases, if the contractor has substantially completed performance, i.e., the contractor’s breach is not material, then the
    contractor has a claim for the unpaid balance and the owner has a claim for damages. See 
    id. at 481–82;
    RESTATEMENT
    (SECOND) OF CONTRACTS § 237 cmt. d (Am. Law Inst. 1981).
    8
    submission of Question 24, but did object to Question 3 on the ground that “there is no evidence
    that Cimco failed to comply with the agreement.”
    The court of appeals held that Cimco waived error regarding the jury’s failure to answer
    Question 24 by not objecting to its conditional submission. ___ S.W.3d at ___ n.9. Cimco argues
    that its objection to Question 3 was sufficient to preserve error on the jury’s failure to answer
    Question 24 because an objection to an invalid basis for liability “preserves error for any impact
    the wrongful inclusion has on other charge questions.” McFarland v. Boisseau, 
    365 S.W.3d 449
    ,
    454–55 (Tex. App.—Houston [1st Dist.] 2011, no pet.). Because we do not consider whether any
    evidence supports Cimco’s breach, and thus do not address whether Question 3 was an invalid
    basis for liability, we cannot say at this point whether Cimco’s objection to Question 3 was
    sufficient to preserve error on Question 24. We leave it to the court of appeals to address this issue
    on remand.
    Ultimately, although both the trial court and the court of appeals purported to render
    judgment in accordance with the jury’s verdict, neither court did so. The trial court improperly
    ignored the jury’s finding that Bartush’s failure to comply was not excused, while the court of
    appeals improperly ignored the jury’s finding that Cimco breached first. Accordingly, we grant
    the parties’ petitions for review, and, without hearing oral argument, TEX. R. APP. P. 59.1, we
    reverse the court of appeals’ judgment and remand the case to that court to consider the parties’
    unaddressed issues.
    OPINION DELIVERED: April 28, 2017
    9