Howard Michael Lauderback, Individually, and D/ B/A New Era Contract Services v. FMWB Inc. ( 2016 )


Menu:
  •                        COURT OF APPEALS
    SECOND DISTRICT OF TEXAS
    FORT WORTH
    NO. 02-16-00057-CV
    HOWARD MICHAEL                                                  APPELLANT
    LAUDERBACK, INDIVIDUALLY
    AND D/B/A NEW ERA CONTRACT
    SERVICES
    V.
    FMWB, INC.                                                        APPELLEE
    ----------
    FROM THE 16TH DISTRICT COURT OF DENTON COUNTY
    TRIAL COURT NO. 15-06246-16
    ----------
    MEMORANDUM OPINION1
    ----------
    Appellant Howard Michael Lauderback, individually and d/b/a New Era
    Contract Services, appeals from the trial court’s summary judgment entered in
    favor of appellee FMWB, Inc. Because FMWB conclusively established its right
    1
    See Tex. R. App. P. 47.4.
    to judgment on its claim for breach of contract, we affirm the trial court’s
    judgment.
    I. BACKGROUND
    The relevant facts are largely undisputed. Lauderback contracted with the
    Texas Department of Transportation (TDOT) to provide mowing services along
    various roadways located in Cooke County (the contract). The contract included
    several “special provisions,” one of which required Lauderback and any
    subcontractor to provide to TDOT a “Certificate of Insurance,” verifying that either
    Lauderback or the subcontractor provided workers’ compensation insurance in
    an amount “Not Less Than: Statutory.”
    On June 4, 2013, Lauderback and FMWB entered into a subcontract under
    which FMWB agreed to perform these mowing services along a particular Cooke
    County highway (the subcontract). FMWB was to finish the project in 57 working
    days.       In exchange, Lauderback agreed to pay FMWB $100,159.26.                     The
    subcontract     apparently   incorporated       the   special   provisions   included    in
    Lauderback’s contract with TDOT.2 FMWB provided a certificate of insurance.
    During a “preaudit review of subcontractor documentation,” Lauderback’s
    insurance carrier informed him that FMWB’s certificate of insurance “was
    2
    FMWB argues that the special provisions in the contract between TDOT
    and Lauderback were not incorporated into its subcontract with Lauderback;
    however, the subcontract reflects that FMWB agreed to perform the services “as
    shown and described in the plans and in accordance with the provisions of the
    referenced specifications and special provisions which are a part of this contract.”
    [Emphasis added.]
    2
    inadequate, inaccurate, and did not provide the minimum amount of coverage of
    Workers’ Compensation Insurance as required by the contract.” As a result,
    Lauderback withheld the last payment he owed FMWB on the subcontract—
    $42,951.64—“in lieu of the charges that [Lauderback] will have to pay to provide
    workers[’] comp insurance.” FMWB asserts, and Lauderback does not dispute,
    that it performed the mowing services within the 57-day deadline.
    On May 27, 2015, FMWB sent written notice of its claim for the unpaid
    portion of the subcontract to Lauderback and his insurer (the demand letter).
    Lauderback never paid the amount requested in the demand letter: $42,951.64
    plus $1,000 in incurred attorney’s fees. On July 27, 2015, FMWB filed a verified
    petition against Lauderback, alleging a suit on a sworn account and a claim for
    breach of contract. See Tex. R. Civ. P. 185. FMWB also alternatively asserted a
    quantum-meruit claim.      FMWB attached to its petition the affidavit of Shawn
    Sloan, FMWB’s president. In turn, Sloan attached to his affidavit a “Statement of
    Claim,” reflecting the total amount Lauderback owed FMWB on the subcontract,
    and the demand letter.
    Lauderback filed a verified denial, denying the account and denying that
    “all just and lawful offsets, payments, and credits have been given or allowed.”
    See Tex. R. Civ. P. 93(10), 185.         Lauderback also alleged the following
    affirmative defenses: waiver, equitable estoppel, discharge, justification, offset,
    credit, laches, failure to meet conditions precedent, and fraud. See Tex. R. Civ.
    P. 94.
    3
    FMWB moved for a traditional summary judgment on its claim on a sworn
    account, arguing that it had established as a matter of law “its sworn account
    based upon a written contract or founded on business dealings between the
    parties on which a systematic record has been kept; that the account is just and
    true; and that all lawful offsets, payments, and credits have been allowed,”
    resulting in damage to FMWB “in the sum of $42,951.64.” FMWB also moved for
    summary judgment on its breach-of-contract claim, contending that it had
    established as a matter of law the existence of an enforceable contract between
    the parties and Lauderback’s breach by his failure to pay all amounts owed under
    the subcontract, which resulted in $42,951.64 in damages.       In support of its
    motion, FMWB attached Sloan’s affidavit, the demand letter, and portions of the
    subcontract. Sloan’s affidavit again included as attachments the demand letter
    and the “Statement of Claim.” FMWB also argued it was entitled to attorney’s
    fees and attached its attorney’s affidavit, reflecting the attorney’s fees it had
    incurred.
    Lauderback responded to the motion, arguing that summary judgment
    would be inappropriate because he had filed a verified denial and because
    genuine issues of material fact existed on FMWB’s breach-of-contract and
    sworn-account claims. Lauderback also argued that he was entitled to an offset.
    Lauderback’s attached summary-judgment evidence consisted of his affidavit, his
    business records regarding the subcontract, and the subcontract. Neither FMWB
    4
    nor Lauderback objected to the other’s proffered summary-judgment evidence.
    See Tex. R. Civ. P. 166a(f).
    The trial court granted FMWB’s motion “in its entirety” and entered a final
    judgment awarding FMWB $42,951.64, prejudgment and postjudgment interest,
    attorney’s fees, and court costs. In its judgment, the trial court denied all other
    claims for relief. Lauderback appeals from the trial court’s judgment and argues
    in five issues that the trial court erred by granting summary judgment on FMWB’s
    claims.3
    II. DISCUSSION
    A. STANDARD OF REVIEW
    We review a summary judgment de novo. Travelers Ins. Co. v. Joachim,
    
    315 S.W.3d 860
    , 862 (Tex. 2010). We consider the evidence presented in the
    light most favorable to the nonmovant—Lauderback—crediting evidence
    favorable to him if reasonable jurors could and disregarding contrary evidence
    unless reasonable jurors could not. See Mann Frankfort Stein & Lipp Advisors,
    Inc. v. Fielding, 
    289 S.W.3d 844
    , 848 (Tex. 2009). We indulge every reasonable
    inference and resolve any doubts in Lauderback’s favor.       See 20801, Inc. v.
    3
    Although Lauderback asserts that summary judgment on FMWB’s claim
    for quantum meruit was in error, FMWB did not move for and the trial court did
    not grant summary judgment on that claim. FMWB raised quantum meruit solely
    in the alternative to its contractual claims. See generally Arias v. Brookstone,
    L.P., 
    265 S.W.3d 459
    , 469 (Tex. App.―Houston [1st Dist.] 2007, pet. denied)
    (recognizing party may plead quantum meruit in the alternative to contractual
    claims but noting recovery may not be had on both). Thus, we will not address
    Lauderback’s fourth issue and that portion of issue five directed to this claim.
    5
    Parker, 
    249 S.W.3d 392
    , 399 (Tex. 2008). A plaintiff is entitled to summary
    judgment on a cause of action if it conclusively proves all essential elements of
    the claim. See Tex. R. Civ. P. 166a(a), (c); MMP, Ltd. v. Jones, 
    710 S.W.2d 59
    ,
    60 (Tex. 1986). Once a movant produces summary-judgment evidence entitling
    it to summary judgment, the burden shifts to the nonmovant to present evidence
    raising a fact issue on at least one of those elements. See Amedisys, Inc. v.
    Kingwood Home Health Care, LLC, 
    437 S.W.3d 507
    , 511 (Tex. 2014). We must
    affirm a summary judgment if any of the grounds presented to the trial court are
    meritorious. Provident Life & Accident Ins. Co. v. Knott, 
    128 S.W.3d 211
    , 216
    (Tex. 2003).
    B. BREACH OF CONTRACT
    In its summary-judgment motion, FMWB argued that it had conclusively
    established that Lauderback breached the subcontract “by failing to pay [FMWB]
    for the labor and equipment provided to [Lauderback] under the terms of the
    contract.” In his third issue and part of his fifth issue, Lauderback asserts that the
    trial court erred by granting summary judgment on FMWB’s breach-of-contract
    claim because there were genuine issues of material fact regarding FMWB’s
    performance and whether Lauderback was entitled to an offset based on
    FMWB’s alleged failure to carry the required insurance. Lauderback raised these
    arguments in response to FMWB’s summary-judgment motion as well.
    To be entitled to summary judgment on its breach-of-contract claim,
    FMWB had to conclusively establish (1) the existence of a valid contract,
    6
    (2) FMWB’s performance or tender of performance, (3) Lauderback’s breach of
    contract, and (4) FMWB’s damages as a result of the breach. See Schum v.
    Munck Wilson Mandala, LLP, No. 06-16-00006-CV, 
    2016 WL 3197159
    , at *2
    (Tex. App.—Texarkana June 9, 2016, no pet.); Triton 88, L.P. v. Star Elec.,
    L.L.C., 
    411 S.W.3d 42
    , 56 (Tex. App.—Houston [1st Dist.] 2013, no pet.). No
    party disputed that Lauderback and FMWB had entered into a valid contract or
    that Lauderback had failed to pay FMWB the final installment payment of
    $42,951.64 for the mowing services it timely performed under the subcontract.
    Lauderback argues that summary judgment was improper because FMWB failed
    to conclusively establish that it had fully performed under the subcontract
    because it had failed to provide sufficient workers’ compensation insurance―the
    second element of FMWB’s claim.
    The subcontract incorporated the TDOT special provisions from the
    contract, including the provision requiring subcontractors to provide workers’
    compensation insurance in a statutorily required amount through its own
    coverage or through Lauderback’s coverage. On appeal, both Lauderback and
    FMWB point solely to section 505.013 of the labor code as the source of this
    statutory duty. See Tex. Lab. Code Ann. § 505.013 (West 2015). That section
    provides that an individual employed by a subcontractor is not considered an
    employee of TDOT for the purposes of insurance unless the subcontractor
    leases “a tractor, a truck, mowing or cutting machinery, or other equipment to
    [TDOT] and us[es] the equipment to perform work under a contract with [TDOT].”
    7
    Id.; see also 
    id. § 406.002(a)
    (West 2015) (providing that employers’ participation
    in state’s workers’ compensation scheme is voluntary “except for public
    employees and as otherwise provided by law”). Here, Lauderback did not assert
    that FMWB had leased equipment to TDOT to perform the subcontract. Indeed,
    the subcontract recognized that FMWB was “fully equipped” and that it had
    agreed to perform all of its contractual work “at its own proper cost and expense.”
    Therefore, under the terms of section 505.013―the sole statute identified by the
    parties as defining the applicability and scope of a subcontractor’s workers’
    compensation obligations―FMWB was not under a duty to provide a certificate
    of insurance under the subcontract even though the TDOT special provision was
    incorporated into the subcontract.
    Lauderback’s assertion in his affidavit that his insurer informed him that
    FMWB’s certificate of insurance was “inadequate” and “inaccurate” failed to raise
    a fact issue regarding FMWB’s performance in light of the limits of section
    505.013.   Similarly, Lauderback’s assertion that it was entitled to an offset,
    thereby raising a fact issue regarding FMWB’s performance and damages, is
    unavailing. First, this argument rests on Lauderback’s contention that FMWB
    failed to provide the insurance required under the subcontract.       As we have
    concluded, the special provision incorporated into the subcontract did not require
    FMWB to provide a certificate of insurance to TDOT. Second, Lauderback failed
    to conclusively establish the affirmative defense of offset upon which he had the
    8
    burden of proof.4    To establish offset, Lauderback had to produce conclusive
    evidence of the existence and amount of damages caused by FMWB’s alleged
    failure. See Mathis v. Benavides, No. 04-15-00555-CV, 
    2016 WL 3020893
    , at *5
    (Tex. App.―San Antonio May 25, 2016, pet. filed) (mem. op.). In Lauderback’s
    January 14, 2016 affidavit, which was prepared more than two years after
    Lauderback withheld his final payment to FMWB, he could not state the damages
    he had incurred as a result of FMWB’s alleged failure to provide a sufficient
    certificate of insurance to TDOT:
    I paid FMWB for all of their work on all of the contracts, with the
    exception of the last payment due. . . . The money that is being
    withheld is in lieu of the charges that I will have to pay to provide
    workers[’] comp insurance.
    ....
    Because FMWB has not provided proper Workers[’] Comp
    Insurance documentation, I will have to purchase coverage for the time
    period of their work. I have requested information from State Farm
    regarding this and as of the date of this affidavit, I do not have the final
    information regarding how much this will cost or when it will cost you
    money.
    4
    We assume without deciding that Lauderback’s claim of “offset” is an
    affirmative defense―as Lauderback pleaded in the trial court and asserts on
    appeal―and not a counterclaim―as FMWB contends. Whether it was an
    affirmative defense or a counterclaim, Lauderback had the burden to produce
    summary-judgment evidence establishing the amount of his damages, which he
    did not do. See Davis v. Am. Express Bank, FSB, No. 03-12-00564-CV,
    
    2014 WL 4414826
    , at *4 (Tex. App.―Austin Aug. 29, 2014, no pet.) (mem. op.);
    Triton 
    88, 411 S.W.3d at 60
    ; Bellair, Inc. v. Aviall of Tex., Inc., 
    819 S.W.2d 895
    ,
    899–900 (Tex. App.―Dallas 1991, writ denied). See generally Tex. R. Civ. P. 94
    (listing affirmative defenses that must be pleaded), 97(a) (defining compulsory
    counterclaims).
    9
    There is no evidence that any claim for a work-related injury regarding the
    subcontract has been filed.
    FMWB conclusively proved all essential elements of its breach-of-contract
    claim through its summary-judgment evidence, and Lauderback failed to raise a
    fact issue on any of these established elements. See, e.g., Sw. Pipe Servs., Inc.
    v. Sunbelt Rentals, Inc., No. 01-15-00124-CV, 
    2016 WL 888780
    , at *3–5 (Tex.
    App.―Houston [1st Dist.] Mar. 8, 2016, no pet.) (mem. op.); Kleas v. Clark,
    Thomas & Winters, P.C., No. 03-12-00755-CV, 
    2013 WL 4516120
    , at *2 (Tex.
    App.―Austin Aug. 21, 2013, pet. denied) (mem. op.); Law Office of David E.
    Williams, II, P.C. v. Fort Worth Tex. Magazine Venture, LP, No. 02-10-00373-CV,
    
    2011 WL 2651865
    , at *1–2 (Tex. App.―Fort Worth July 7, 2011, no pet.) (mem.
    op.); UL, Inc. v. Pruneda, No. 01-09-00169-CV, 
    2010 WL 5060638
    , at *11–15
    (Tex. App.―Houston [1st Dist.] Dec. 9, 2010, no pet.) (mem. op.). Accordingly,
    the trial court did not err by granting judgment as a matter of law in favor of
    FMWB on its claim for breach of contract.
    III. CONCLUSION
    FMWB conclusively established each element of its claim for breach of
    contract, and Lauderback failed to raise a fact issue as to those established
    elements. We overrule issue three and that portion of issue five directed to
    FMWB’s breach-of-contract claim. We need not address issue one, issue two, or
    that portion of issue five directed to FMWB’s suit on a sworn account. See Tex.
    R. App. P. 47.1. A suit on a sworn account is not an independent cause of action
    10
    but is a procedural device by which a plaintiff may recover for certain types of
    contractual claims. See Rizk v. Fin. Guardian Ins. Agency, Inc., 
    584 S.W.2d 860
    ,
    862 (Tex. 1979). Because we have upheld the summary judgment on FMWB’s
    breach-of-contract claim, we are not required to address the propriety of the
    summary judgment on its suit on a sworn account.        See Burruss v. Citibank
    (S.D.), N.A., 
    392 S.W.3d 759
    , 762 (Tex. App.―Dallas 2012, pet. denied) (after
    affirming summary judgment on breach-of-contract claim, declining to address
    summary judgment regarding claim for account stated).         Finally and as we
    previously stated, we will not address issue four or that portion of issue five
    directed to FMWB’s quantum-meruit claim.         Accordingly, we affirm the trial
    court’s judgment. See Tex. R. App. P. 43.2(a).
    /s/ Lee Gabriel
    LEE GABRIEL
    JUSTICE
    PANEL: DAUPHINOT, GARDNER, and GABRIEL, JJ.
    DELIVERED: October 6, 2016
    11