state-v-public-utility-commission-of-texas-represented-by-the-office-of ( 2008 )


Menu:
  •       TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN
    NO. 03-06-00503-CV
    The State of Texas, appearing by and through the Office of the Attorney General,
    Consumer Protection and Public Health Division, Public Agency Representation
    Section; Cities of Dickinson, Friendswood, La Marque, League City, Lewisville
    and Texas City; Texas-New Mexico Power Company; First Choice Power, Inc.;
    and Texas Generating Co., L.P., Appellants
    v.
    Public Utility Commission of Texas, represented by the Office of the Attorney General,
    Natural Resources Division; and Texas Industrial Energy Consumers, Appellees
    FROM THE DISTRICT COURT OF TRAVIS COUNTY, 53RD JUDICIAL DISTRICT
    NO. D-1-GN-05-003499, HONORABLE SCOTT H. JENKINS, JUDGE PRESIDING
    OPINION
    This appeal arises from the district court’s judgment affirming the final order of the
    Public Utility Commission in the true-up proceeding to finalize “stranded costs” for Texas-New
    Mexico Power Company, First Choice Power, Inc., and Texas Generating Company, L.P.
    (collectively “TNMP”) under section 39.262 of the Public Utility Regulatory Act (“PURA”)1 and
    PUC Substantive Rule 25.263. Because we conclude the Commission’s final order was consistent
    with the plain language of the relevant statutes and was supported by substantial evidence, we affirm
    the judgment of the district court affirming the Commission’s final order.
    1
    Tex. Util. Code Ann. §§ 11.001-64.158 (West 2007).
    FACTUAL AND PROCEDURAL BACKGROUND
    In 1999, the legislature enacted Senate Bill 7 (“SB 7”), which amended the PURA
    to restructure and partially deregulate the Texas retail electric power industry. See Act of May 27,
    1999, 76th Leg., R.S., ch. 405, 1999 Tex. Gen. Laws 2543; see also CenterPoint Energy Houston
    Electric, LLC v. Gulf Coast Coalition of Cities, No. 03-05-00557-CV, 2007 Tex. App. LEXIS 9919,
    at *3-*18 (Tex. App.—Austin Dec. 20, 2007, no pet. h.) (describing statutory framework for
    transition to competitive retail electric market) (hereafter “CenterPoint”). As part of the transition
    from regulation to retail competition, the legislature authorized each electric utility to recover “all
    of its net, verifiable, nonmitigable stranded costs incurred in purchasing power and providing electric
    generation service.” Tex. Util. Code Ann. § 39.252(a) (West 2007). The term “stranded costs” is
    defined in section 39.251 of the PURA2 but, generally speaking, stranded costs represent prudently
    incurred expenditures made by the utilities in a regulated environment—previously recoverable over
    time through regulated rates paid by consumers—that have become unrecoverable in a competitive
    2
    Section 39.251(7) defines the term “stranded costs” as:
    the positive excess of the net book value of generation assets over the market value
    of the assets, taking into account all of the electric utility’s generation assets, any
    above market purchased power costs, and any deferred debit related to a utility’s
    discontinuance of the application of Statement of Financial Accounting Standards
    No. 71 (“Accounting for the Effects of Certain Types of Regulation”) for
    generation-related assets if required by the provisions of this chapter. For purposes
    of Section 39.262, book value shall be established as of December 31, 2001, or the
    date a market value is established through a market valuation method under Section
    39.262(h), whichever is earlier, and shall include stranded costs incurred under
    Section 39.263.
    
    Id. § 39.251(7).
    2
    market. See Reliant Energy, Inc. v. Public Util. Comm’n, 
    101 S.W.3d 129
    , 132 (Tex. App.—Austin
    2003), rev’d on other grounds, CenterPoint Energy, Inc. v. Public Util. Comm’n, 
    143 S.W.3d 81
    (Tex. 2004) (op. on reh’g). Recovery of stranded costs is one of the final steps in the transition from
    traditional cost-of-service regulation to retail competition.
    TNMP filed an application with the Commission seeking to recover $266,487,442
    in total stranded costs. TNMP also sought recovery of $106,573,973 for the capacity auction true-up.
    See Tex. Util. Code Ann. §§ 39.153, .262(d) (West 2007). As a preliminary matter, the Commission
    determined that TNMP was not entitled to a capacity auction true-up as a matter of law. See 
    id. § 39.153;
    PUC Subst. R. 25.381(d).3 Thereafter, the Commission referred TNMP’s application to
    the State Office of Administrative Hearings for a contested case hearing.
    After conducting a hearing and reviewing the evidence submitted by the parties, the
    administrative law judges issued a proposal for decision on May 28, 2004, including findings of fact
    and conclusions of law. The Commission adopted the PFD in part and modified the ALJs’ findings
    with respect to the following issues: 1) whether the sale of TNP One—TNMP’s sole generating
    plant—was a bona fide, third-party transaction under a competitive offering;4 2) whether TNMP
    pursued commercially reasonable efforts to mitigate stranded costs; 3) the gross-up of stranded-cost
    disallowances; and 4) the interest rate for calculating carrying costs on TNMP’s final fuel balance.
    3
    See also Supplemental Preliminary Order, PUC Docket No. 29206 (Public Util. Comm’n
    Mar. 3, 2004), available at http://interchange.puc.state.tx.us/WebApp/Interchange/Documents/
    29206_156_429330.PDF.
    4
    TNMP sold TNP One to Twin Oaks Power, LLP, an affiliate of Sempra Energy Resources.
    3
    The Commission rejected the ALJs’ recommendation and determined that TNMP’s
    sale of its TNP One generating plant was not a bona fide, third-party transaction under a competitive
    offering within the meaning of section 39.262(h) of the PURA. The Commission concluded that
    TNMP failed to comply with section 39.262(h) and failed to carry its burden of proving the market
    value of TNP One. Based on the evidence in the record, the Commission determined that the market
    value of TNP One was $180 million. The Commission used this market value to determine what
    it referred to as TNMP’s primary stranded cost balance.
    Alternatively, the Commission found that, even if it accepted the ALJs’
    recommendation that TNMP’s sale of TNP One was a bona fide, third-party transaction under a
    competitive offering within the meaning of section 39.262(h), TNMP failed to use commercially
    reasonable means to mitigate its stranded costs as required under section 39.252(d). Under this
    alternative finding, the Commission adopted the ALJs’ proposed market valuation of TNP One and
    the ALJs’ proposed adjustments, with modifications, to TNMP’s book value to reflect the lack of
    commercial reasonableness. Using this approach, the Commission determined what it referred to
    as TNMP’s alternative stranded cost balance.
    Less than two months after the Commission rendered its final order, the Texas
    Supreme Court issued its opinion in CenterPoint Energy, Inc. v. Public Utility Commission,
    
    143 S.W.3d 81
    (Tex. 2004) (hereafter “CenterPoint Energy”). In its opinion, the supreme court held
    that interest on stranded costs must accrue from January 1, 2002, not from the date of the utility’s
    final true-up case as provided in PUC Substantive Rule 25.263(l)(3). 
    Id. at 84.
    Accordingly, the
    4
    Commission granted rehearing and remanded the case to SOAH for the ALJs to recalculate and
    quantify the interest due TNMP in light of the supreme court’s opinion.
    The ALJs issued a Remand PFD on March 11, 2005, and recommended interest in
    the amount of $41,736,027 on the Commission’s primary stranded cost balance and $45,304,441 on
    the Commission’s alternative stranded cost balance. In its final order, entitled “Second Order on
    Rehearing,” the Commission adopted the Remand PFD in part, modified the ALJs’ findings with
    respect to the appropriate interest rate to be applied to TNMP’s stranded cost balance, and
    recalculated the total interest due TNMP.
    After recalculating the interest amount due, the Commission approved a primary
    stranded cost balance of $128,820,365. This amount was further offset by TNMP’s final fuel
    balance of $41,504,474 and carrying costs on the additional TNP One depreciation, plus interest due
    on stranded costs of $39,166,214. The net amount of stranded cost recovery authorized by the
    Commission was $110,603,855.5
    Several parties sought judicial review in the Travis County District Court of the
    Commission’s Second Order on Rehearing as permitted under section 2001.171 of the
    Administrative Procedure Act. See Tex. Gov’t Code Ann. § 2001.171 (West 2000). The district
    court consolidated all of these appeals into one proceeding and rendered judgment affirming the
    5
    Based on its finding that TNMP failed to take commercially reasonable steps to mitigate
    stranded costs, the Commission approved an alternative stranded cost balance of $139,834,457.
    Like the primary stranded cost balance, this amount was further offset by TNMP’s final fuel balance
    of $41,504,474 and carrying costs on the additional TNP One depreciation, plus interest due on
    stranded costs of $42,514,910. The net amount of stranded cost recovery authorized by the
    Commission under this alternative approach was $124,966,643.
    5
    Commission’s order in all respects on July 24, 2006. TNMP, as well as the Cities of Dickinson,
    Friendswood, La Marque, League City, and Lewisville (collectively “Cities”), and the State of Texas,
    on behalf of all state entities and institutions that are electricity consumers (“State Agencies”), appeal
    from the district court’s judgment.
    DISCUSSION
    On appeal, the parties raise various issues challenging the Commission’s final order.
    The Cities and State Agencies argue that the Commission erred in determining the market value
    of TNMP’s assets when TNMP failed to carry its burden of proof on this issue.6 In two additional
    issues, the Cities argue that the Commission erred in failing to effectuate TNMP’s prior agreement
    to reduce stranded costs and in calculating the interest owed on TNMP’s final true-up balance. For
    its part, TNMP raises three issues on appeal, arguing that the Commission erred in denying TNMP’s
    capacity auction true-up, in “grossing up” disallowances for alleged federal income tax benefits,
    and in reducing the net book value of TNMP’s assets for investment tax credits. The Commission
    responds that there was no error in its final order and the order was supported by substantial
    evidence.
    Standard of Review
    In their challenges to the Commission’s final order, the parties have raised a variety
    of issues, which we review under different standards of review. We briefly summarize these
    6
    The Texas Industrial Energy Consumers (TIEC) support the Cities and State Agencies in
    this issue, but TIEC did not file a separate appeal.
    6
    different standards. As a general matter, we review the Commission’s final order under the
    substantial evidence rule. See Tex. Util. Code Ann. § 15.001 (West 2007); Tex. Gov’t Code Ann.
    § 2001.174 (West 2000). Under the substantial evidence rule, we give significant deference to the
    agency in its field of expertise. Railroad Comm’n v. Torch Operating Co., 
    912 S.W.2d 790
    , 792
    (Tex. 1995); Texas Health Facilities Comm’n v. Charter Med.-Dallas, Inc., 
    665 S.W.2d 446
    , 452
    (Tex. 1984). We presume that the agency’s order is valid and that its findings, inferences,
    conclusions, and decisions are supported by substantial evidence. City of El Paso v. Public Util.
    Comm’n, 
    883 S.W.2d 179
    , 185 (Tex. 1994); Charter 
    Med., 665 S.W.2d at 452
    . The complaining
    party has the burden to overcome this presumption. City of El 
    Paso, 883 S.W.2d at 185
    ; Hammack
    v. Public Util. Comm’n, 
    131 S.W.3d 713
    , 725 (Tex. App.—Austin 2004, pet. denied). In conducting
    a substantial evidence review, we evaluate the entire record to determine whether the evidence as
    a whole is such that reasonable minds could have reached the conclusion the agency must
    have reached in order to take the disputed action. Texas State Bd. of Dental Exam’rs v. Sizemore,
    
    759 S.W.2d 114
    , 116 (Tex. 1988); Suburban Util. Corp. v. Public Util. Comm’n, 
    652 S.W.2d 358
    ,
    364 (Tex. 1983). We may not substitute our judgment for that of the agency on the weight of the
    evidence on questions committed to the agency’s discretion. Tex. Gov’t Code Ann. § 2001.174;
    Charter 
    Med., 665 S.W.2d at 452
    ; H.G. Sledge, Inc. v. Prospective Inv. & Trading Co., 
    36 S.W.3d 597
    , 602 (Tex. App.—Austin 2000, pet. denied).
    Under a substantial evidence review, the issue for the reviewing court is not whether
    the agency’s decision was correct, but whether the record demonstrates some reasonable basis for
    the agency’s action. Charter 
    Med., 665 S.W.2d at 452
    ; Central Power & Light Co. v. Public Util.
    7
    Comm’n, 
    36 S.W.3d 547
    , 561 (Tex. App.—Austin 2000, pet. denied). The evidence in the record
    may preponderate against the decision of the agency and nevertheless amount to substantial
    evidence. Charter 
    Med., 665 S.W.2d at 452
    ; Meier Infinity v. Motor Vehicle Bd., 
    918 S.W.2d 95
    ,
    98 (Tex. App.—Austin 1996, writ denied). We will sustain the agency’s order if the evidence is
    such that reasonable minds could have reached the conclusion that the agency must have reached in
    order to justify its action. Charter 
    Medical, 665 S.W.2d at 453
    ; Suburban Util. 
    Corp., 652 S.W.2d at 364
    . We will reverse the agency’s order if the decision is not reasonably supported by substantial
    evidence, in violation of a constitutional or statutory provision, in excess of the agency’s statutory
    authority, made through unlawful procedure, affected by other error of law, arbitrary or capricious,
    or characterized by an abuse of discretion. See Tex. Gov’t Code Ann. § 2001.174(2)(A)-(F).
    Several issues raised by the parties involve questions of statutory construction, which
    we review de novo. When construing a statute, our primary goal is to determine and give effect to
    the legislature’s intent. City of San Antonio v. City of Boerne, 
    111 S.W.3d 22
    , 25 (Tex. 2003). To
    determine legislative intent, we look to the statute as a whole, as opposed to isolated provisions.
    State v. Gonzalez, 
    82 S.W.3d 322
    , 327 (Tex. 2002). We begin with the plain language of the statute
    at issue and apply its common meaning. City of San 
    Antonio, 111 S.W.3d at 25
    . Where the statutory
    text is unambiguous, we adopt a construction supported by the statute’s plain language, unless that
    construction would lead to an absurd result. Fleming Foods of Tex., Inc. v. Rylander, 
    6 S.W.3d 278
    ,
    284 (Tex. 1999). We give serious consideration to an agency’s interpretation of the statutes it is
    charged with enforcing, so long as that interpretation is reasonable and consistent with the statutory
    language. Tarrant Appraisal Dist. v. Moore, 
    845 S.W.2d 820
    , 823 (Tex. 1993); Steering Comms.
    8
    for the Cities Served by TXU Elec. v. PUC, 
    42 S.W.3d 296
    , 300 (Tex. App.—Austin 2001, no pet.).
    This is particularly true when the statute involves a complex subject matter. Steering Comms.
    for 
    Cities, 42 S.W.3d at 300
    . Courts, however, “do not defer to administrative interpretation in
    regard to questions which do not lie within administrative expertise, or deal with a nontechnical
    question of law.” Rylander v. Fisher Controls Int’l, Inc., 
    45 S.W.3d 291
    , 302 (Tex. App.—Austin
    2001, no pet.).
    Additionally, several issues raised by the parties challenge the Commission’s
    authority. The Public Utility Commission “is a creature of the Legislature and has no inherent
    authority.” Public Util. Comm’n v. GTE-SW Corp., 
    901 S.W.2d 401
    , 407 (Tex. 1995). Like other
    state administrative agencies, the Commission “has only those powers that the Legislature expressly
    confers upon it” and “any implied powers that are necessary to carry out the express responsibilities
    given to it by the Legislature.” Public Util. Comm’n v. City Pub. Serv. Bd., 
    53 S.W.3d 310
    , 316
    (Tex. 2001). It is not enough that the power claimed by the Commission be reasonably useful to the
    Commission in discharging its duties; the power must be either expressly conferred or necessarily
    implied by statute. The agency may not “exercise what is effectively a new power, or a power
    contradictory to the statute, on the theory that such a power is expedient for administrative
    purposes.” 
    Id. The statutory
    scheme
    Before addressing the issues raised by the parties, we provide a brief overview of the
    statutory scheme allowing for recovery of stranded costs. See also CenterPoint, 2007 Tex. App.
    LEXIS 9919, at *3-*18 (for discussion of statutory framework). In 1999, the legislature determined
    9
    it was in the public interest to partially deregulate the electric power industry. See generally
    Tex. Util. Code Ann. §§ 39.001-.910 (West 2007). When the legislature mandated the transition
    from traditional cost-of-service regulation to retail competition, it recognized that many utility
    companies had made very large investments to build power generation plants and that while the
    costs of these power plants might be recoverable from ratepayers in a regulated environment, these
    same costs “might well become uneconomic and thus unrecoverable in a competitive, deregulated
    power market.” CenterPoint 
    Energy, 143 S.W.3d at 82
    ; see also City of Corpus Christi v. Public
    Util. Comm’n, 
    51 S.W.3d 231
    , 237-38 (Tex. 2001). The legislature called these uneconomic
    assets “stranded costs.” CenterPoint 
    Energy, 143 S.W.3d at 82
    ; see also Tex. Util. Code Ann.
    §§ 39.001(b)(2), .251(7). As part of the transition to retail competition, the legislature made an
    express finding that it was in the public interest to allow utility companies to recover their stranded
    costs. See Tex. Util. Code Ann. § 39.001(b)(2). The legislature thus “set forth a comprehensive
    scheme for estimating, finalizing, and recovering those costs.” CenterPoint 
    Energy, 143 S.W.3d at 83
    ; see Tex. Util. Code Ann. §§ 39.201, .251-.254, .256-.265, .301-.313 (West 2007).
    The legislature provided a mechanism in section 39.262 of the PURA for each utility
    to recover its stranded costs. See Tex. Util. Code Ann. § 39.262. This mechanism requires each
    transmission and distribution utility, its affiliated retail electric provider, and its affiliated power
    generation company to jointly file an application with the Commission to finalize stranded costs.7
    7
    As part of the transition to retail competition, each existing utility was required to
    “unbundle” the services it provided and separate its business activities into three distinct units: a
    power generation company, a transmission and distribution utility, and a retail electric provider.
    Tex. Util. Code Ann. § 39.051; see City of Corpus Christi v. Public Util. Comm’n, 
    51 S.W.3d 231
    ,
    237 (Tex. 2001).
    10
    
    Id. § 39.262(c).
    The legislature provided a formula to calculate the utility’s stranded costs. 
    Id. § 39.251(7).
    Under this formula, a utility’s stranded costs equal the excess amount of the net book
    value of generation assets minus the market value of those assets—i.e., SC = NBV – MV. 
    Id. Each utility
    has the burden of quantifying its stranded costs using one of four statutory
    methods. 
    Id. § 39.262(h).
    These methods are sale-of-assets, stock valuation, partial stock valuation,
    or exchange of assets. 
    Id. § 39.262(h)(1)-(4).
    TNMP chose to establish its stranded costs using
    the sale-of-assets method. Under this method, TNMP was required to demonstrate that it sold
    its generating assets in a “bona fide third-party transaction under a competitive offering.” 
    Id. § 39.262(h)(1).
    Once this showing has been made, the total net value realized from the sale will
    establish the market value of the generation assets sold. 
    Id. The legislature
    recognized, however, that during the transition from regulation to
    retail competition, utilities would not have a business incentive to reduce their potential stranded
    costs. Accordingly, the legislature provided a statutory incentive—the legislature required each
    utility to “pursue commercially reasonable means to reduce its potential stranded costs, including
    good faith attempts to renegotiate above-cost fuel and purchased power contracts or the exercise of
    normal business practices to protect the value of its assets.” 
    Id. § 39.252(d).
    The legislature also
    required the Commission to consider each utility’s efforts to mitigate potential stranded costs when
    determining the utility’s final stranded cost balance. 
    Id. In addition,
    the legislature required the
    Commission to ensure that each utility does not overrecover stranded costs. 
    Id. § 39.262(a);
    see also
    CenterPoint 
    Energy, 143 S.W.3d at 98-99
    . With this statutory scheme in mind, we turn to the
    parties’ complaints regarding the Commission’s determination of TNMP’s stranded costs.
    11
    The Commission’s determination of TNMP’s stranded costs
    Through various issues asserted on appeal, the parties raise two general challenges
    to the Commission’s final order. First, the Cities and State Agencies attack the Commission’s
    determinations regarding the market value of TNMP’s generation assets. Second, the Cities and
    TNMP challenge certain calculations and adjustments to the book value of TNMP’s generation
    assets. In addition to these general challenges, the Cities argue that the Commission erred in its
    calculation of interest on TNMP’s stranded cost balance.          TNMP also complains that the
    Commission erroneously denied its capacity auction true-up and that the Commission erred in
    “grossing up” disallowances to capture alleged federal income tax benefits.
    1.      Market value of TNMP’s generation assets
    We turn first to the Cities’ and State Agencies’ arguments that the Commission erred
    in awarding stranded costs to TNMP because TNMP failed to prove the market value of TNP One.
    Specifically, the Cities and State Agencies argue that the Commission erred in devising its own
    valuation method to quantify TNMP’s stranded costs. The State Agencies further argue that because
    TNMP failed to prove the market value of TNP One in a “bona fide third-party transaction under a
    competitive offering” as required under section 39.262(h)(1) of the PURA, the Commission was not
    permitted to devise an extra-statutory method of stranded cost recovery and, in doing so, the
    Commission violated the parties’ due process rights. Because we conclude the Commission acted
    within its statutory authority in determining the market value of TNMP’s generation assets, we reject
    the Cities’ and State Agencies’ contentions.
    Chapter 39 provides four specific methods that a utility may choose from to establish
    12
    the market value of its generation assets. See Tex. Util. Code Ann. § 39.262(h). TNMP chose to
    use the “sale-of-assets” method under section 39.262(h)(1). See 
    id. § 39.262(h)(1).
    Under the sale-
    of-assets method, the market value is defined as the total value realized from a sale if, any time after
    December 31, 1999, the utility sells some or all of its generation assets in a “bona fide third-party
    transaction under a competitive offering.” 
    Id. Having sold
    its only generation asset, TNP One, to
    Sempra Energy Resources, TNMP asserted that the $120 million sales price of TNP One established
    the market value of its generation assets as required in section 39.262(h)(1). The ALJs agreed with
    TNMP that the sales price of TNP One established the market value of that asset as required under
    the statute, but the Commission disagreed. The Commission concluded that TNMP failed to
    establish market value through the sale of TNP One because TNMP failed to prove that the sale was
    a “bona fide third-party transaction under a competitive offering” as required in section
    39.262(h)(1).8
    TNMP’s failure to establish market value through an asset sale left the Commission
    with the difficult task of quantifying TNMP’s stranded costs without a demonstrated, bona fide asset
    sale to a third party. As TNP One had been sold, it was impossible for TNMP to use another method
    in section 39.262(h) to value the plant. The Commission concluded, however, that denying all
    recovery to TNMP would be contrary to the legislature’s deregulation transition plan—of which
    stranded cost recovery is an integral part. See Tex. Util. Code Ann. § 39.252(a) (allowing utilities
    to recover net verifiable, nonmitigable stranded costs). The Cities and State Agencies argue that the
    8
    None of the parties dispute this conclusion on appeal.
    13
    Commission lacked statutory authority to determine the market value of TNP One when the method
    selected by the utility fails to produce a proper market value. We disagree.
    To determine the scope of the Commission’s authority, we must read the PURA as
    a whole to determine the legislature’s intent. State v. Public Util. Comm’n, 
    883 S.W.3d 190
    , 196
    (Tex. 1994). The contemporaneous construction of a statute by the administrative agency charged
    with enforcing it is entitled to great weight. Id.; see also Dodd v. Meno, 
    870 S.W.2d 4
    , 7
    (Tex. 1994); Tarrant Appraisal 
    Dist., 845 S.W.2d at 823
    . The legislature set forth a comprehensive
    scheme through which it has charged the Commission with authority to determine each utility’s final
    stranded cost balance. See generally Tex. Util. Code Ann. §§ 39.001-.910. The legislature provided
    that each utility “is allowed to recover all of its net, verifiable, nonmitigable stranded costs.”
    Tex. Util. Code Ann. § 39.252(a).
    In this Court’s recent CenterPoint decision, we considered a similar situation. See
    CenterPoint, 2007 Tex. App. LEXIS 9919, at *35-*52 (discussing CenterPoint’s failure to satisfy
    requirements of partial stock valuation method). In that case, CenterPoint attempted to establish the
    market value of its generation assets using the partial stock valuation method in section 39.262(h)(3).
    
    Id. The Commission
    determined that CenterPoint did not comply with the statutory requirements
    because it failed to demonstrate that at least 19% of the transferred stock had been “spun off and sold
    to public investors through a national stock exchange” as required in section 39.262(h)(3). 
    Id. The Commission
    concluded that none of the other statutory methods could be used to determine the
    market value of CenterPoint’s generation assets because CenterPoint did not meet the statutory
    requirements for any of those methods. 
    Id. at *52-*60.
    Accordingly, the Commission chose to use
    14
    the utilities code definition of “market value” to develop a substitute valuation method. 
    Id. at *62-
    *63 (citing Tex. Util. Code Ann. § 39.251(4)). In the absence of a market valuation established
    under one of the prescribed methods in section 39.262(h), we upheld the Commission’s implied
    authority to consider and use alternative methods for determining market value in order to carry out
    the “strong legislative mandate” of stranded cost recovery. 
    Id. at *63-*67.
    In addition, we rejected
    claims by OPC and the customers of CenterPoint that, having failed to meet its burden of proof,
    CenterPoint was not entitled to any stranded cost recovery at all. 
    Id. at *60-*62.
    In this case, as in CenterPoint, the Commission determined—and none of the parties
    dispute—that TNMP failed to establish the market value of TNP One because it failed to meet the
    statutory requirements of section 39.2629(h)(1). In light of TNMP’s failure to satisfy the statutory
    requirements, the Commission turned to the utilities code definition of “market value” in section
    39.251(4) to determine the appropriate valuation of TNMP’s generation assets. Section 39.251(4)
    defines “market value” as “the value the assets would have if bought and sold in a bona fide third-
    party transaction on the open market.” Tex. Util. Code Ann. § 39.251(4). Based on this definition,
    the Commission concluded that it was proper to determine the market value TNP One would have
    if TNMP had initially conducted a bona fide transaction in compliance with section 39.262(h)(1).
    Consistent with our decision in CenterPoint, we hold that the Commission properly
    considered an alternative valuation method based on the definition of market value in section
    39.251(4) when TNMP failed to establish the market value of its generation assets in compliance
    with one of the four methods in section 39.262(h). See CenterPoint, 2007 Tex. App. LEXIS 9919,
    at *52-67. Likewise, we conclude that, given TNMP’s failure to establish market value of TNP One
    15
    using one of the four methods in section 39.262(h), the Commission did not exceed its statutory
    authority when it developed an alternative valuation method based on the statutory definition of
    market value in section 39.251(4). See 
    id. at *62-*63.
    We next consider whether the Commission’s determination of market value was
    reasonable and supported by substantial evidence. In conducting a substantial evidence review, we
    must determine whether the evidence as a whole is such that reasonable minds could have reached
    the conclusion reached by the Commission—namely, that the market value of TNP One was $180
    million. City of El 
    Paso, 883 S.W.2d at 186
    ; 
    Sizemore, 759 S.W.2d at 116
    . The true test is not
    whether the agency reached the correct conclusion, but whether some reasonable basis exists in the
    record for the action taken by the agency. Charter 
    Med., 665 S.W.2d at 452
    . When weighing the
    testimony, the Commission may accept or reject part or all of each witness’s conclusions; it is
    the final judge regarding the credibility and validity of such testimony. Central Power & Light 
    Co., 36 S.W.3d at 561
    ; Southern Union Gas Co. v. Railroad Comm’n, 
    692 S.W.2d 137
    , 141-42
    (Tex. App.—Austin 1985, writ ref’d n.r.e.).
    The Commission determined that if TNMP’s flawed auction process produced a sales
    price of $120 million, then a bona fide sale would have produced a higher price for TNP One. The
    record reflects that several parties presented evidence on the value of TNP One and the sales price
    TNMP would have received if it had conducted a proper sale. See Tex. Util. Code Ann. § 39.251(4).
    In the analysis prepared by TNMP witness Patrick Bridges, and relied on by the ALJs, a recent run-
    up in the prices of natural gas showed an increasing value for TNP One and a potential value to
    bidders of approximately $174 million. The ALJs also referenced notes made by a TNMP witness,
    16
    Rhonda Lenard, during the sales negotiations with Sempra where TNMP again referred to a value
    of $180 million for TNP One—a value that TNMP repeatedly stated it held as a reasonable value for
    TNP One. The record also showed that Austpro, another potential buyer for TNP One, indicated a
    possible bid of $188 million. Although Austpro never submitted a written bid, the Commission
    considered this amount to be in the upper range of prices that a bona fide sale would have produced.
    Several parties also suggested alternative values for TNP One. TIEC witness, Steve
    Weyel, performed numerous calculations using “spark spread” discounted cash flow analysis and
    testified that these calculations suggested a range of $255 to $316 million. Cities witness, Lane
    Kollen, also provided testimony on the market value of TNP One. But these analyses also presumed
    a delayed sale of TNP One. The Commission rejected the testimony of Weyel and Kollen because
    it concluded that TNMP should not be penalized for its failure to delay the sale of TNP One. Based
    on the record evidence, the Commission concluded that a bona fide competitive offering would have
    captured the recent run-up in natural gas prices and would have produced a sales price of $180
    million, net of expenses. Accordingly, the Commission determined that the appropriate market value
    for TNP One was $180 million.
    The record before the Commission was extensive, and the Commission had ample
    evidence on which to base its determination of market value. The evidence regarding the market
    value of TNP One suggested a valuation between $174 million and $316 million. We conclude that
    the record contains substantial evidence to support a market value for TNP One within the range of
    evidence before the Commission. Given the admitted complexity of determining the market value
    of TNP One and the deference owed to the Commission in its area of expertise, we hold that there
    17
    is a reasonable basis for the Commission, in its discretion, to select a market value for TNP One
    within the range of evidence presented by the parties. See City of El 
    Paso, 883 S.W.2d at 186
    (affirming agency decision to select value within range of evidence in the record). We conclude that
    the Commission’s market valuation of TNP One is supported by substantial evidence. We further
    conclude that the Commission’s determination of market value was consistent with its statutory
    authority under the PURA and that the Commission did not create an extra-statutory method of
    stranded cost recovery. We overrule the Cities’ first issue and the State Agencies’ issues 1A and 1B.
    2.      Due Process
    The State Agencies further allege that the Commission’s creation of an extra-statutory
    method of stranded cost recovery violates Due Process. Having determined that the Commission
    did not exceed its statutory authority or create an extra-statutory method of stranded cost recovery,
    we reject the State Agencies claim that the Commission violated Due Process. We overrule the State
    Agencies’ issue 1C.
    3.      Adjustments to Book Value
    A)      Accelerated depreciation
    In their second issue, the Cities argue that the Commission failed to effectuate
    TNMP’s prior agreement to reduce stranded costs. This issue arises from TNMP’s agreement in a
    previous proceeding before the Commission to apply accelerated depreciation to the book value of
    TNP One as a means to reduce stranded costs. See Application of Texas-New Mexico Power
    Company for Approval of a Transition Plan and Statement of Intent to Decrease Rates, Docket
    18
    No. 17751 (Tex. Pub. Util. Comm’n Nov. 4, 1998) (order on reh’g). Because we conclude the
    Commission’s reduction to the net book value of TNP One by $19,340,031 for accelerated
    depreciation was reasonable and supported by substantial evidence, we reject the Cities’ argument.
    To understand the Cities’ argument on this issue, it is necessary to examine the
    Commission’s prior order and the stipulation agreed to by TNMP. In 1997, in anticipation of
    deregulation, TNMP filed an application with the Commission in Docket No. 17751 seeking
    approval of TNMP’s plan to transition to a deregulated electric market. See 
    id. The parties
    in that
    proceeding reached a stipulated agreement on TNMP’s transition plan and submitted that stipulation
    to the Commission for approval. The Commission incorporated the stipulation as part of the
    transition plan approved in its final order. See 
    id. Under the
    transition plan approved by the
    Commission in Docket No. 17751, TNMP was to apply a total of $75 million in accelerated
    depreciation to the book value of TNP One—$15 million per year from 1999 through 2002, plus an
    additional $15 million—to reduce stranded costs:
    In addition to normal depreciation, TNMP shall recover additional depreciation on
    TNP One in the amount of $15,000,000 each year for the years 1999-2002. In
    addition, TNMP shall record additional depreciation on TNP One of up to a total
    cumulative amount of $15,000,000 over the years 1998-2002, based on the amount
    available and calculated pursuant to the earnings sharing mechanism approved in this
    Order.
    
    Id. After the
    Commission approved TNMP’s transition plan in Docket No. 17751, the
    legislature passed SB 7, which deregulated the retail electric market. Chapter 39 of the utilities code
    differed from the stipulation agreed to by TNMP in Docket No. 17751. One of the primary
    19
    differences was that retail competition began in 2002, not 2003 as contemplated by the stipulation.
    See Tex. Util. Code Ann. § 39.001(b)(1) (implementing customer choice on January 1, 2002). Over
    the ensuing years, the Commission dealt with several proceedings trying to reconcile the promises
    made by TNMP in Docket No. 17751 with Chapter 39.9 In this final stranded cost true-up
    proceeding, the Commission again faced the need to reconcile the stipulation and transition plan
    approved in Docket No. 17751 with the requirements in Chapter 39.
    The issue for the Commission in this case was how to reconcile TNMP’s promises
    to apply accelerated depreciation in the transition plan with the requirement in section 39.261(c)(2)
    of the PURA to apply excess earnings from 1999-2001 to reduce the net book value of generation
    assets. See 
    id. § 39.261(c)(2).
    The record reflects that TNMP had excess earnings of $40,659,969
    for 1999-2001 and did not book the accelerated depreciation required under the stipulation and
    transition plan for these years. Based on TNMP’s stipulation in Docket No. 17751, the Commission
    determined that TNMP should apply a total of $60 million in accelerated depreciation to reduce the
    net book value of TNP One, thereby reducing its stranded costs.10 The Commission observed that
    if TNMP had actually booked the accelerated depreciation as required under the stipulation and
    transition plan approved in Docket No. 17751, TNMP would not have had $40.6 million in excess
    earnings for 1999-2001. Accordingly, the Commission subtracted the $40.6 million in excess
    9
    The Commission’s final order in Docket No. 17751 expressly states that TNMP’s 1998
    transition plan must be reconciled with any later-enacted deregulation legislation. Application of
    Texas-New Mexico Power Company for Approval of a Transition Plan and Statement of Intent to
    Decrease Rates, Docket No. 17751 (Tex. Pub. Util. Comm’n Nov. 4, 1998) (order on reh’g).
    10
    The Commission did not require TNMP to apply accelerated depreciation for 2002, since
    retail competition began January 1st of that year.
    20
    earnings that TNMP already applied to reduce its stranded costs from the $60 million total, leaving
    $19,340,031 in additional depreciation for TNMP to apply to the net book value of TNP One. This
    is the adjustment that the Commission made to the net book value of TNP One.
    Section 39.252(a) allows a utility to recover “all of its net, verifiable, nonmitigable
    stranded costs.” Tex. Util. Code Ann. § 39.252(a). However, the legislature imposed a statutory
    duty on each utility to pursue commercially reasonable means to reduce its potential stranded costs.
    
    Id. § 39.252(d).
    In addition, for those utilities identified as having positive stranded costs in
    the Commission’s 1998 ECOM Report11 to the Texas Senate Interim Committee on Electric
    Restructuring, the legislature required those utilities to take additional steps to reduce the net book
    value of, or “accelerate” the recovery of, stranded costs by returning excess earnings to their Texas
    customers. 
    Id. §§ 39.254,
    .257. Under section 39.254, these excess earnings “shall be applied to the
    net book value of generation assets.” 
    Id. § 39.254.
    Because TNMP was one of the utilities identified
    as having positive stranded costs in the 1998 ECOM Report, TNMP was required to apply its excess
    earnings from annual reports to reduce the net book value of its generation assets. 
    Id. The legislature
    charged the Commission with enforcing the utilities’ obligations to
    mitigate stranded costs. In section 39.252(a), the legislature expressly provided that a utility “may
    not be permitted to overrecover stranded costs.” 
    Id. § 39.262(a).
    Thus, the Commission was
    required to ensure that TNMP properly applied its excess earnings to reduce the net book value of
    its generation assets.
    11
    Public Utility Commission of Texas, Report to the Texas Senate Interim Committee on
    Electric Restructuring, “Potentially Strandable Investment (ECOM) Report: 1998 Update” (Apr. 30,
    1998) (hereafter “1998 ECOM Report”).
    21
    The Cities complain that the Commission should not have offset TNMP’s obligation
    to apply $60 million in accelerated depreciation with TNMP’s excess earnings mitigation because
    there is no connection between TNMP’s prior agreement to apply accelerated depreciation in Docket
    No. 17751 and the excess earnings mitigation requirement in Chapter 39 of the PURA. See 
    id. §§ 39.254,
    .257, .261. Given the Commission’s obligation to ensure that TNMP complies with
    its own obligation to apply excess earnings to reduce net book value and does not overrecover
    stranded costs, we agree with the Commission that this offset was reasonable and necessary to avoid
    “double counting.”
    The record reflects that the Commission’s order in Docket No. 17751 required it to
    reconcile TNMP’s promise to apply accelerated depreciation as a means to reduce stranded costs
    with the legislature’s deregulation plan in Chapter 39 of the PURA. The record further reflects that
    if TNMP had booked the accelerated depreciation required under the stipulation and transition plan
    approved in Docket No. 17751, TNMP would not have had $40.6 million in excess earnings with
    which it could have further mitigated stranded costs as required under section 39.254 of the PURA.
    We therefore conclude that the Commission’s decision to offset TNMP’s promise to reduce stranded
    costs by $60 million with TNMP’s $40.6 million in excess earnings for 1999-2001 was reasonable
    and comports with the Commission’s obligation to ensure that TNMP applies its excess earnings to
    reduce net book value and does not overrecover stranded costs. See Tex. Util. Code Ann. §§ 39.254,
    .252(a), (d), .262(a); see also In re Entergy, 
    142 S.W.3d 316
    , 324 (Tex. 2004) (Commission
    has exclusive jurisdiction to adjudicate disputes arising from agreements incorporated into
    22
    Commission orders); Public Util. Comm’n v. Southwestern Bell Tel. Co., 
    960 S.W.2d 116
    , 119-20
    (Tex. App.—Austin 1997, no pet.) (Commission has discretion to formulate and award remedy
    necessary to effectuate parties’ agreement). We overrule the Cities’ second issue.
    B)      Investment Tax Credits
    In its third issue, TNMP claims that the Commission erred in reducing TNMP’s net
    book value by $6,490,000 for investment tax credits. TNMP claims that the Commission lacked
    authority to make this reduction because section 39.251(7) of the PURA—the section defining
    stranded costs—fails to reference investment tax credits. Because we conclude the Commission’s
    treatment of investment tax credits was proper, we reject TNMP’s claim.
    Like accelerated depreciation, Congress created investment tax credits to spur
    economic development. See, e.g., Central Power & Light Co. v. Bullock, 
    696 S.W.2d 30
    , 31
    (Tex. App.—Austin 1984, no writ); see generally Application of Normalization Accounting Rules
    to Balances of Excess Deferred Income Taxes and Accumulated Deferred Investment Tax Credits
    of Public Utilities Whose Generation Assets Cease to be Public Utility Property, 68 Fed. Reg. 10190
    (IRS Mar. 4, 2003). Businesses were given tax credits for making certain capital investments.
    
    Bullock, 696 S.W.2d at 31
    . Such credits were viewed as benefits to the utility that must ultimately
    be passed on to ratepayers. See 
    id. at 32.
    Because Congress wanted to ensure that public utilities
    would have those sums to invest, the IRS required each public utility to segregate investment tax
    credits into a separate account for regulatory purposes. See Application of Normalization Accounting
    23
    Rules, 68 Fed. Reg. at 10191. In a process called “normalization,” the IRS further required that the
    credit amounts be amortized for return to ratepayers over the life of the asset.12 See 
    id. at 10191-92.
    The record reflects, at the time it filed for stranded cost recovery, TNMP held slightly
    more than $15 million in its investment tax credit account. The Commission concluded that this
    amount represented benefits received by TNMP that had yet to be passed on to ratepayers. Cities
    witness, Kollen, testified that TNMP’s stranded costs should be reduced by the entire amount of
    TNMP’s investment tax credit account. In contrast, Commission staff witness, Darryl Tietjen,
    testified that TNMP’s stranded costs should only be reduced by the present value of TNMP’s
    investment tax credit balance, or $6.49 million. The Commission adopted Tietjen’s recommendation
    and reduced the book value of TNP One accordingly.
    TNMP argues that the Commission lacked authority to make this reduction because
    nothing in the definition of stranded costs references “investment tax credits.” See Tex. Util. Code
    Ann. § 39.251(7). TNMP further argues that the Commission erred in relying on section 36.059 of
    the PURA to support its reduction because that section does not apply to this stranded cost true-up
    proceeding. See 
    id. § 36.059.
    Accordingly, TNMP maintains there is no legal basis in the PURA
    to support the Commission’s reduction to book value for investment tax credits. We disagree.
    In directing the Commission to finalize and determine each utility’s stranded cost
    balance, the legislature provided that the utility shall only recover its “net, verifiable, nonmitigable
    stranded costs.” 
    Id. § 39.252(a).
    The legislature further provided that a utility shall not overrecover
    12
    None of the parties have raised the issue of a potential normalization violation; therefore,
    we do not address it. Cf. CenterPoint, 2007 Tex. App. LEXIS 9919, at *105-18 (remanding
    Commission’s final order to consider remedy for normalization violation).
    24
    its stranded costs. 
    Id. § 39.262(a).
    Cities witness, Kollen, testified that allowing TNMP to retain
    investment tax credits would allow TNMP to overrecover stranded costs.13 Based on this testimony
    and the legislative mandate that utilities shall not overrecover stranded costs, we conclude that the
    Commission acted within its authority under Chapter 39 of the PURA to reduce the net book value
    of TNMP’s generation assets by the present value of TNMP’s investment tax credit account. We
    also conclude that the Commission’s decision is supported by substantial evidence.14 See 
    id. § 39.262(a);
    Charter 
    Med., 665 S.W.2d at 452
    ; Central Power & 
    Light, 36 S.W.3d at 561
    . We
    overrule TNMP’s third issue.
    4.      Interest
    In their third issue, the Cities dispute the Commission’s calculation of interest on
    TNMP’s final stranded cost balance. The Cities argue that the Commission acted arbitrarily and
    capriciously in applying different interest rates to TNMP’s final fuel balance and final stranded cost
    balance. As a result of this alleged discrimination, the Cities argue that the Commission has allowed
    TNMP to overrecover stranded costs in violation of section 39.262 of the PURA. Because we
    conclude that the Commission’s application of different interest rates to TNMP’s final fuel balance
    13
    The Commission’s reduction to TNMP’s stranded costs is consistent with its previous
    decision in Docket 22349 in which the Commission first estimated TNMP’s stranded costs. In that
    docket, the Commission also required TNMP to include investment tax credits as a reduction to book
    value and, therefore, to stranded costs.
    14
    In light of our determination that the Commission’s reduction to book value for investment
    tax credits was within the Commission’s authority under Chapter 39 of the PURA, we reject
    TNMP’s complaint that the Commission erroneously relied on section 36.059.
    25
    and final stranded cost balance comports with the statute and Commission rules and was supported
    by substantial evidence, we reject the Cities’ arguments.
    Less than two months after the Commission issued its final order in this case,
    the supreme court released its opinion in CenterPoint Energy. The supreme court invalidated part
    of PUC Substantive Rule 25.263—the Commission’s rule governing stranded cost true-up
    
    proceedings. 143 S.W.3d at 81
    ; see 16 Tex. Admin. Code § 25.263 (2005). Specifically, the
    supreme court invalidated rule 25.263(l)(3), holding that carrying charges on a utility’s final stranded
    cost balance should be calculated from January 1, 2002—the date customer choice began—instead
    of from the date of the final true-up order, which could be two or more years later, as provided in the
    
    rule. 143 S.W.3d at 84
    . In accordance with the supreme court’s decision, the Commission granted
    rehearing and remanded this case to SOAH for additional proceedings to determine the interest due
    on TNMP’s final stranded cost balance.
    A)      Interest rate for stranded costs
    The Commission’s rule requires the interest rate for stranded costs to be calculated
    based on TNMP’s weighted average cost of capital (“WACC”). See 16 Tex. Admin. Code
    § 25.263(l)(3)(A)(i). The record reflects that the Commission applied an interest rate of 10.93% to
    TNMP’s final stranded cost balance. This interest rate was within the range of evidence submitted
    by the parties. TNMP’s expert witness testified that the Commission should apply an interest rate of
    11.59% to TNMP’s final stranded cost balance. The Cities’ expert witness, Scott Norwood, testified
    that the Commission should apply a rate of 8.31%. The Office of Public Utility Counsel proposed
    an interest rate of 9.8%. And the Commission staff recommended an interest rate of 10.93%.
    26
    Because the Commission’s chosen interest rate of 10.93% falls within the range of evidence
    submitted by the parties, we conclude that there is a reasonable basis in the record to support the
    Commission’s application of an interest rate of 10.93%. See City of El 
    Paso, 883 S.W.2d at 186
    .
    Thus, we conclude the Commission’s chosen interest rate is supported by substantial evidence.
    B)     Interest rate for final fuel balance
    Section 25.263(h)(4) of the Commission’s true-up rule governs the interest rate to be
    applied to a utility’s final fuel balance.15 16 Tex. Admin. Code § 25.263(h)(4) (2005). Section
    25.263(h)(4) gives two options for the Commission to use when determining the interest rate for a
    utility’s final fuel balance. The first option requires the Commission to use the utility’s WACC
    when the period between the issuance of the utility’s final fuel reconciliation order and the date of
    the final true-up order is more than one year. Under the second option, the Commission must use
    15
    Section 25.263(h)(4) provides:
    The final fuel balance, as adjusted by paragraphs (2) and (3) of this subsection, shall
    include carrying costs on the positive or negative fuel balance equal to:
    (A)      the weighted-average cost of capital approved in the company’s unbundled
    cost of service (UCOS) proceeding, if the period until the date of the final
    true-up order is greater than one year; or
    (B)      the rate approved in § 25.236 of this title (relating to Recovery of Fuel Costs)
    if the period until the date of the final true-up order is one year or less.
    16 Tex. Admin. Code § 25.263(h)(4) (2005). This portion of the Commission’s rule was not at issue
    in the supreme court’s CenterPoint Energy decision. See generally CenterPoint Energy Inc.
    v. Public Util. Comm’n, 
    143 S.W.3d 81
    (Tex. 2004) (invalidating PUC Subst. Rule 25.263(l)(3)).
    27
    the short-term interest rate approved in PUC Substantive Rule 25.236 if the period between the final
    fuel reconciliation order and the final true-up order is one year or less.
    Because the Commission issued TNMP’s final fuel reconciliation order on February
    11, 2004, TNMP’s witness estimated that the Commission’s order in the stranded cost true-up
    proceeding would be issued within six months and proposed using the short-term interest rate of
    1.17%16 approved in PUC Substantive Rule 25.236. Although the parties disputed the interpretation
    of section 25.263(h)(4), the Commission agreed with TNMP and applied the short-term interest
    rate of 1.17%.
    The Commission’s determination was based upon its interpretation of rule
    25.263(h)(4). As the Commission explained in its order on rehearing,
    [T]he appropriate period for determining which interest rate applies is measured from
    the date the Commission issues its order in the final fuel reconciliation and can
    therefore, be different than the actual time period to which the rate applies.
    Otherwise, there would have been no reason to include the words “one year or less”
    in the rule since the period between the end of the reconciliation period and the
    earliest filing of the true-up was known to be two years when the rule was written.
    We defer to the Commission’s interpretation of its own rule unless it is plainly
    erroneous or inconsistent with the language of the rule. See Public Util. Comm’n v. Gulf States Utils.
    Co., 
    809 S.W.2d 201
    , 207 (Tex. 1991) (“Our review is limited to determining whether the
    administrative interpretation is plainly erroneous or inconsistent with the regulation.” (internal
    quotation omitted)); Gulf Coast Coalition of Cities v. Public Util. Comm’n, 
    161 S.W.3d 706
    ,
    16
    This was the short-term interest rate as of the date TNMP filed its application to finalize
    stranded costs.
    28
    712 (Tex. App.—Austin 2005, no pet.). We conclude that the Commission’s interpretation of
    section 25.263(h)(4) comports with the plain language of the rule. Under this interpretation, the
    Commission properly applied the short-term interest rate to TNMP’s final fuel balance. We further
    conclude that the Commission’s decision was supported by substantial evidence.
    To the extent the Cities complain that the Commission applied different interest rates
    to TNMP’s final stranded cost balance and final fuel balance to the disadvantage of TNMP’s
    customers, we reject that complaint. The Commission’s application of different interest rates was
    reasonable, was supported by the record, and comports with the Commission’s rules. We overrule
    the Cities’ third issue.
    5.      Capacity auction true-up
    In TNMP’s first issue, it complains that the Commission erred in summarily denying
    TNMP’s capacity auction true-up claim for $106 million. Prior to the evidentiary hearing in this
    case, the Commission issued a Supplemental Preliminary Order ruling on the threshold issue of
    whether TNMP was entitled to a capacity auction true-up. In this order, the Commission concluded
    that TNMP was not entitled to a capacity auction true-up because TNMP did not conduct a capacity
    auction. Because we conclude that the Commission’s decision was reasonable and consistent with
    the relevant statutes and Commission rules, we reject TNMP’s complaint.
    To encourage competition in the newly emerging retail market, the legislature
    required utilities with more than 400 megawatts of installed generation capacity to auction off 15%
    29
    of their capacity prior to January 1, 2002. See Tex. Util. Code Ann. § 39.153(a);17 see also
    CenterPoint, 2007 Tex. App. LEXIS 9919, at *126-*132 (describing capacity auction process and
    true-up). Because TNMP had less than 400 megawatts of installed generation capacity, TNMP was
    exempt from the capacity auction requirement in section 39.153. See Tex. Util. Code Ann.
    § 39.153(a). TNMP was the only utility to fall within the statutory exemption.18 To prevent
    any utility from exercising undue market power, the legislature, in section 39.156, also required
    certain utilities to reduce their ownership and control of installed generation capacity and file market
    mitigation plans with the Commission. See 
    id. § 39.156.
    One of the options available to those
    utilities required to reduce their capacity under section 39.156 was a capacity auction. 
    Id. § 39.156(c)(3).
    As part of the final proceeding to true-up stranded costs, section 39.262(d) of the
    17
    Section 39.153(a) provides:
    Each electric utility subject to this section shall sell at auction, at least 60 days before
    the date set for customer choice to begin, entitlements to at least 15 percent of the
    electric utility’s Texas jurisdictional installed generation capacity. For the purposes
    of this section, the term “electric utility” includes any affiliated power generation
    company that is unbundled from the electric utility in accordance with Section
    39.051, but does not include any entity owning less than 400 megawatts of installed
    generation capacity.
    Tex. Util. Code Ann. § 39.153(a) (emphases added).
    18
    The record reflects that, prior to the passage of SB 7, TNMP sought and obtained from the
    legislature an exemption from the capacity auction requirement. See Senate Special Comm. on Elec.
    Util. Restructuring, 76th Leg., R.S. 13 (Mar. 13, 1999) (transcript available from Senate Staff
    Services Office). This exemption was valuable to TNMP. In light of this exemption, TNMP did not
    have to participate in a capacity auction, and it was the only incumbent utility allowed to retain
    control of 100% of its capacity.
    30
    PURA required the Commission to true-up the capacity auction for each utility that auctioned
    capacity under section 39.153 or 39.156. 
    Id. § 39.262(d).19
    TNMP agrees that it was exempt from the capacity auction requirement in section
    39.153 and that it did not conduct a capacity auction pursuant to either section 39.153 or 39.156.
    Nevertheless, TNMP argues that the legislature’s use of the word “shall” in section 39.262(d)
    is mandatory and requires the Commission to conduct a capacity auction true-up for TNMP. We
    disagree.
    The plain language of section 39.262(d)(2) requires the Commission to reconcile the
    difference between “the price of power obtained through the capacity auctions under Sections
    39.153 and 39.156” and the power cost projections that were employed to estimate stranded costs
    in the proceeding under section 39.201. See Tex. Util. Code Ann. § 39.262(d)(2) (emphasis added).
    The plain language of this statute also presumes that TNMP participated in the required capacity
    19
    Section 39.262(d) provides:
    The affiliated power generation company shall reconcile, and either credit or bill to
    the transmission and distribution utility, the net sum of:
    (1)      the former electric utility’s final fuel balance determined under Section
    39.202(c); and
    (2)      any difference between the price of power obtained through the capacity
    auctions under Sections 39.153 and 39.156 and the power cost projections
    that were employed for the same time period in the ECOM model to estimate
    stranded costs in the proceeding under Section 39.201.
    
    Id. § 39.262(d).
    31
    auctions. Because TNMP did not conduct a capacity auction pursuant to section 39.153 or 39.156,
    the Commission concluded there was nothing to reconcile in a capacity auction true-up for TNMP.
    The Commission’s interpretation of section 39.262(d) is reasonable and consistent
    with the plain language of the statute. Because the legislature expressly exempted TNMP from the
    capacity auction requirement, we are unpersuaded that the legislature intended the Commission to
    conduct a capacity auction true-up for TNMP.20 We overrule TNMP’s first issue.
    6.      “Grossing up” disallowances
    In its second issue, TNMP claims that the Commission erred in “grossing up”
    disallowances to capture tax benefits resulting from TNMP’s stranded cost recovery.21 Because we
    conclude that the Commission acted within its authority under the PURA to “gross up”
    disallowances when calculating TNMP’s stranded costs, we reject TNMP’s claim.
    Section 39.262(c) expressly requires TNMP to file its application to finalize stranded
    costs with the Commission. See Tex. Util. Code Ann. § 39.262(c). TNMP does not dispute the
    Commission’s authority to calculate TNMP’s final stranded cost balance. Rather, TNMP argues that
    the Commission lacks discretion to make adjustments to the various components that comprise
    20
    To the extent TNMP relies on PUC Substantive Rule 25.281 to support its argument, we
    are likewise unpersuaded by that argument. It is axiomatic that an agency may not enact rules
    inconsistent with its statutory authority. See, e.g., Railroad Comm’n v. Lone Star Gas, 
    844 S.W.2d 679
    , 685 (Tex. 1992); State Bd. of Ins. v. Deffebach, 
    631 S.W.2d 794
    , 798 (Tex. App.—Austin 1982,
    writ ref’d n.r.e.). The language of the rule is consistent with the statute. Having thus concluded that
    section 39.262(d) of the PURA does not require the Commission to conduct a capacity auction true-
    up, we likewise conclude there is no requirement to do so under the Commission’s rules.
    21
    TNMP does not challenge the disallowances, nor does TNMP challenge the Commission’s
    authority to disallow certain costs when finalizing TNMP’s stranded cost balance.
    32
    TNMP’s stranded cost balance. We disagree. The legislature expressly provided that a utility may
    recover all of its net, verifiable, nonmitigable stranded costs, but that a utility may not overrecover
    stranded costs. See 
    id. § 39.252(a),
    .262(a). Thus, the Commission’s authority to adjust the various
    components comprising TNMP’s stranded cost balance is grounded in its authority to ensure that
    TNMP does not overrecover stranded costs. See 
    id. § 39.262(a).
    In this case, as part of its request to recover stranded costs, TNMP sought to retain
    its account balance for accumulated deferred federal income tax (ADFIT) to cover its tax liability
    on its stranded cost recovery. As the Commission explained in its final order, the ADFIT account
    balance reflects the regulatory expectation that TNMP would eventually recover the book value of
    TNP One through depreciation. During the early years of accounting for certain assets, like TNP
    One, the ADFIT balance grows because the regulatory tax expense paid by ratepayers exceeds the
    utility’s actual tax expense. This trend reverses in later years when the utility’s actual tax expense
    exceeds its regulatory tax expense, and the ADFIT account balance will ultimately reach zero.
    Under continuing regulation, TNMP’s ADFIT account balance related to depreciation would have
    ultimately reached zero.
    But TNMP will now recover the book value of TNP One as proceeds from the sale
    of that asset and as stranded costs. If the entire book value is recovered, the ADFIT account will
    satisfy TNMP’s tax burden with respect to its stranded cost recovery and will ultimately reach zero.
    Where, as here, the Commission made adjustments to both the book value and market value of TNP
    One, TNMP will not recover the entire book value of TNP One. As a result, TNMP will not incur
    a tax liability on the amounts not recovered, and the ADFIT account balance will never reach zero.
    33
    Stated differently, without “grossing up” the disallowances made by the Commission, TNMP will
    retain the remaining balance in its ADFIT account and will therefore overrecover stranded costs.
    Section 39.262(a) expressly precludes TNMP from overrecovering stranded costs.
    Tex. Util. Code Ann. § 39.262(a). Because the Commission has disallowed recovery of certain
    costs associated with TNP One, TNMP will not owe federal income tax on those costs, and TNMP
    will not need the associated ADFIT balance. Were the Commission not to “gross up” these
    disallowances, TNMP would overrecover stranded costs. Given the express legislative command
    that a utility may not be permitted to overrecover stranded costs, see Tex. Util. Code Ann.
    § 39.262(a), we conclude that the Commission acted within its authority to “gross up” disallowances
    and thereby prevent TNMP from overrecovering stranded costs. We overrule TNMP’s third issue.
    CONCLUSION
    Having overruled the parties’ issues on appeal, we affirm the judgment of the district
    court affirming the Commission’s final order.
    __________________________________________
    Jan P. Patterson, Justice
    Before Justices Patterson, Pemberton and Waldrop
    Affirmed
    Filed: January 25, 2008
    34
    

Document Info

Docket Number: 03-06-00503-CV

Filed Date: 1/25/2008

Precedential Status: Precedential

Modified Date: 2/1/2016

Authorities (25)

Dodd v. Meno , 870 S.W.2d 4 ( 1994 )

City of San Antonio v. City of Boerne , 111 S.W.3d 22 ( 2003 )

Centerpoint Energy, Inc. v. Public Utility Commission , 143 S.W.3d 81 ( 2004 )

Texas Health Facilities Commission v. Charter Medical-... , 665 S.W.2d 446 ( 1984 )

City of Corpus Christi v. Public Utility Commission of Texas , 51 S.W.3d 231 ( 2001 )

Railroad Commission v. Torch Operating Co. , 912 S.W.2d 790 ( 1995 )

Central Power & Light Co./Cities of Alice v. Public Utility ... , 36 S.W.3d 547 ( 2001 )

Suburban Utility Corp. v. Public Utility Commission , 652 S.W.2d 358 ( 1983 )

Public Util. Com'n v. CITY PUBLIC SER. BD. , 53 S.W.3d 310 ( 2001 )

In Re Entergy Corp. , 142 S.W.3d 316 ( 2004 )

Public Utility Commission v. Gulf States Utilities Co. , 809 S.W.2d 201 ( 1991 )

Tarrant Appraisal District v. Moore , 845 S.W.2d 820 ( 1993 )

Pub. Util. Com'n v. Gte-Southwest , 901 S.W.2d 401 ( 1995 )

Fleming Foods of Texas, Inc. v. Rylander , 6 S.W.3d 278 ( 1999 )

Rylander v. Fisher Controls International, Inc. , 45 S.W.3d 291 ( 2001 )

Steering Committees for the Cities Served by TXU Electric v.... , 42 S.W.3d 296 ( 2001 )

Reliant Energy, Inc. v. Public Utility Commission , 101 S.W.3d 129 ( 2003 )

State Board of Insurance v. Deffebach , 631 S.W.2d 794 ( 1982 )

Southern Union Gas Co. v. Railroad Commission , 692 S.W.2d 137 ( 1985 )

Hammack v. Public Utility Com'n of Texas , 131 S.W.3d 713 ( 2004 )

View All Authorities »