concept-general-contracting-inc-dba-concept-builders-bw-affordable ( 2011 )


Menu:
  •                                   NO. 07-10-00332-CV
    IN THE COURT OF APPEALS
    FOR THE SEVENTH DISTRICT OF TEXAS
    AT AMARILLO
    PANEL A
    JULY 18, 2011
    CONCEPT GENERAL CONTRACTING, INC., D/B/A
    CONCEPT BUILDERS, BW AFFORDABLE HOUSING, L.P.,
    AND CAPITOL INDEMNITY CORP., APPELLANTS
    v.
    ASBESTOS MAINTENANCE SERVICES, INC., APPELLEE
    FROM THE 222ND DISTRICT COURT OF DEAF SMITH COUNTY;
    NO. CI-05H-106; HONORABLE ROLAND D. SAUL, JUDGE
    Before CAMPBELL and HANCOCK and PIRTLE, JJ.
    OPINION
    Appellants, Concept General Contracting, Inc. (Concept) and Capitol Indemnity
    Corp. (Capitol), appeal a judgment awarding damages to appellee, Asbestos
    Maintenance Services, Inc. (AMS), in an amount of $120,883.95.       We affirm the
    judgment of the trial court.
    Background
    On May 27, 2004, BW Affordable Housing, L.P. (BW), contracted with Concept to
    renovate certain apartment units owned by BW in Hereford, Texas.           Concept, as
    general contractor for the project, executed and filed a payment bond issued by Capitol.
    As part of this project, Concept and AMS entered into a subcontract for AMS to provide
    asbestos abatement for restricted areas within 125 apartment units.       This contract
    specifically limited the areas to be abated in a manner that would allow AMS to utilize
    an abatement method that is less intrusive and less costly than a full abatement. Soon
    after AMS began work on the project, Concept requested some additional remediation.
    AMS gave Concept a quote for this additional work, performed this additional work, and
    Concept paid AMS for this additional work.
    While AMS was performing the work identified in these two contracts, Jack
    Scheuerer, construction superintendent for Concept, requested AMS perform additional
    abatement in certain units. Concept began performing this additional work, but the
    additions were so numerous that they dramatically enlarged the scope of the project,
    and altered the means by which the abatement could be performed.1 This extra work
    was billed to Concept as it was performed by AMS. For the first four invoices, Concept
    paid for the extra work without objection. However, somewhere around the fifth invoice,
    Concept stopped paying for the extra work that AMS had performed. For approximately
    1
    According to the testimony of Glen Ashton, a third-party air maintenance
    consultant employed for this project, the additional work requested by Scheuerer more
    than doubled the scope of the work that was covered by the first two contracts, and
    altered the manner of performing the work by requiring area containment and the
    donning of hazmat suits.
    2
    eleven invoices, AMS continued to do the extra work that was marked at the job site by
    Scheuerer, but AMS eventually ceased doing this work when it determined that Concept
    was not going to pay for this extra work. However, AMS continued to perform the work
    delineated in the two contracts for some time.       At some point in the project, AMS
    ceased working and left the work site but stood ready to complete the contract work if
    and when recalled to the site by Concept. However, Concept did not call AMS back to
    the work site. Rather, Concept contracted with another asbestos abatement company
    to complete the work under the contracts as well as additional work that needed to be
    done.
    On the basis of the unpaid extra work, AMS brought suit against Concept and
    Capitol (collectively “appellants”). After a two-day trial, the trial court took the case
    under advisement.      Nearly three years later, the trial court entered its judgment
    awarding AMS $120,883.95 in damages, post-judgment interest, and $25,000 in
    attorney’s fees. Concept and Capitol then filed a motion for new trial, which was denied
    after hearing.   Concept and Capitol also filed a request for findings of fact and
    conclusions of law. The trial court entered findings of fact and conclusions of law.
    Appellants present fifteen issues by this appeal.       By their first two issues,
    appellants contend that the trial court erred in awarding AMS recovery for quantum
    meruit because this was an undisclosed theory of recovery. By their third and fourth
    issues, appellants contend that the trial court abused its discretion in admitting
    documentary exhibits and photographs as business records.             By their fifth issue,
    appellants contend that the trial court erred in finding appellants liable under a theory of
    3
    quantum meruit when AMS dismissed the proper party, the owner of the benefited
    property. By their sixth, seventh, eighth, and tenth issues, appellants contend that the
    evidence was factually insufficient to support the trial court’s judgment. By their ninth
    issue, appellants contend that liability under the theory of quantum meruit was error
    because of the existence of express contracts covering the work performed. By their
    eleventh and fifteenth issues, appellants contend that the trial court erred by failing to
    comply with the requirements of Texas Government Code section 74.059(c)(2). By their
    twelfth issue, appellants appear to contend that the evidence established their
    affirmative defenses of waiver or estoppel as a matter of law. By their thirteenth and
    fourteenth issues, appellants contend that they established their counterclaim as a
    matter of law and should, therefore, have been awarded these damages and attorney’s
    fees. We will overrule each of these issues, and affirm the judgment of the trial court.
    Issues 1 & 2: Failure to Disclose Theories of Recovery
    By their first two issues, appellants contend that the trial court abused its
    discretion in admitting evidence to support AMS’s quantum meruit and payment bond
    theories of recovery because AMS failed to expressly disclose these theories in
    response to a request for disclosure. Appellants contend that, under Texas Rule of Civil
    Procedure 193.6(a), AMS’s failure to specifically identify these theories of recovery in its
    disclosure prevents AMS from introducing evidence to support these theories. AMS
    responds that each of its three petitions, including its live pleading, included claims for
    quantum meruit damages and recovery from the payment bond, and that pleading these
    theories of recovery is sufficient.
    4
    The appellants’ contention is premised entirely on AMS’s failure to specifically
    disclose the theories of recovery under quantum meruit and the payment bond in
    response to appellants’ request for disclosure of “[t]he legal theories and, in general, the
    factual bases of your claims or defenses.” AMS responded to this request by disclosing
    that,
    Plaintiff contracted with Concept General Contracting, Inc. to perform
    asbestos abatement services, and performed all services requested until it
    became apparent that Concept was refusing to pay for same, at which
    time work was suspended pending resolution of outstanding receivables.
    Thereafter, Concept requested that plaintiff remove its remaining materials
    from the job.
    Appellants contend that AMS’s failure to explicitly disclose that it was seeking recovery
    under the theory of quantum meruit and the payment bond provided by Capitol triggers
    the exclusionary provision of Texas Rule of Civil Procedure 193.6 to prevent AMS from
    offering any evidence to support these theories of recovery.          See TEX. R. CIV. P.
    193.6(a).
    This Court finds it extremely significant that the record reflects that both theories
    of recovery were always pled by AMS as theories upon which it sought recovery from
    appellants. Notice that a plaintiff is pursuing a particular theory of recovery generally
    must come from the pleadings. See Cunningham v. Parkdale Bank, 
    660 S.W.2d 810
    ,
    812 (Tex. 1983) (pleadings define the issues at trial and give opposing party sufficient
    information to enable him to prepare a defense). Appellants do not contest that each of
    these theories of recovery were properly pled by AMS nor did they file any special
    exceptions to AMS’s pleadings. Thus, appellants were afforded appropriate notice that
    5
    AMS intended to pursue theories of recovery in quantum meruit and under the payment
    bond.
    Further, while failures to comply with requests for disclosure result in automatic
    exclusion of the non-disclosed evidence, absent proof of good cause or lack of unfair
    surprise or unfair prejudice, see TEX. R. CIV. P. 193.6(a); Phan v. Addison Spectrum,
    L.P., 
    244 S.W.3d 892
    , 899 (Tex.App.—Dallas 2008, no pet.), properly pled claims for
    affirmative relief, as opposed to withheld evidence, are not abandoned or waived by a
    party’s failure to expressly identify those claims in a response to a request for
    disclosure.2   See Killam Ranch Props., Ltd. v. Webb County, No. 04-08-00105-CV,
    2008 Tex.App. LEXIS 8682, at *3-*5 (Tex.App.—San Antonio Nov. 19, 2008, no pet.)
    (mem. op.) (holding failure to respond to discovery request not an abandonment of
    properly pled claim for attorney’s fees).
    Because the live pleadings of AMS provide notice of its intent to pursue recovery
    under the theories of both quantum meruit and the payment bond and because its
    failure to expressly identify those theories in its responses to discovery requests are not
    an abandonment of those claims, we overrule appellants’ first two issues.
    2
    In fact, this distinction between the failure to disclose evidence in response to a
    discovery request as opposed to the failure to disclose properly pled theories of
    recovery is precisely why the trial court’s ruling excluding the testimony of appellants’
    untimely disclosed expert was proper. The withholding of evidence that is necessary to
    respond to a discovery request properly results in the exclusion of that evidence under
    Rule 193.6(a).
    6
    Issues 3 & 4: Business Records
    By their third and fourth issues, appellants contend that the trial court abused its
    discretion by admitting certain documents and photographs as unauthenticated
    business records. The documents constitute AMS’s Exhibits Five through Nineteen and
    appear to be records relating to the work that AMS’s employees performed on the BW
    project.    The photographs, AMS’s Exhibit Twenty, portray various stages of work
    performed in unidentified apartment units.        Appellants contend that the challenged
    evidence was not properly authenticated and constitutes hearsay for which AMS has
    failed to establish any applicable exception to the hearsay rule. AMS responds that the
    testimony of Jack Coiner, an owner of AMS, established each of the requisites to qualify
    the challenged evidence as business records, which are excepted from the hearsay
    rule. See TEX. R. EVID. 803(6).
    Evidentiary rulings are committed to the sound discretion of the trial court. Bay
    Area Healthcare Group, Ltd. v. McShane, 
    239 S.W.3d 231
    , 234 (Tex. 2007). A trial
    court abuses its discretion when it acts without reference to any guiding rules and
    principles.    Downer v. Aquamarine Operators, Inc., 
    701 S.W.2d 238
    , 241-42 (Tex.
    1985).     However, even if a trial court abuses its discretion by improperly admitting
    evidence, reversal is warranted only if the error probably caused the rendition of an
    improper judgment. See TEX. R. APP. P. 44.1; Bay Area 
    Healthcare, 239 S.W.3d at 234
    .
    In such an instance, an appellate court reviews the entire record and requires the
    complaining party to demonstrate that the judgment turns on the particular evidence
    admitted. Bay Area 
    Healthcare, 239 S.W.3d at 234
    .
    7
    Evidence is authenticated by proof that the challenged evidence is what its
    proponent claims it to be.       See TEX. R. EVID. 901(a).3      Hearsay is defined as a
    statement, other than one made by the declarant while testifying at trial or hearing,
    offered in evidence to prove the truth of the matter asserted. Rule 801(d). Generally,
    hearsay is not admissible in evidence. Rule 802. However, there are a number of
    exceptions to this general rule, including the “business records” exception found in Rule
    803(6). For evidence to be admissible as a business record, the record must have been
    made at or near the time that the recorded event occurred by a person with knowledge
    of the event if the record was kept in the course of a regularly conducted business
    activity as shown by the testimony of a custodian of the record or other qualified
    witness. See Rule 803(6).
    In the present case, appellants objected to the challenged evidence as not
    having been properly authenticated by a person with personal knowledge of the
    contents of the evidence and as violating the hearsay rule. AMS presented testimony
    from Coiner that the evidence was made at or near the time that the work was
    performed by a person with knowledge of the work performed and that these records
    were kept in the ordinary course of business. Further, Coiner testified that he was the
    custodian of the challenged records.
    Coiner, during voir dire, identified each document in Plaintiff’s Exhibit Five, which
    appellants treated as representative of Exhibits Five through Nineteen, as well as
    identifying what the photographs contained in Exhibit Twenty portrayed.               Coiner’s
    3
    Further reference to the Texas Rules of Evidence will be by “Rule ___.”
    8
    testimony that the evidence accurately portrays what AMS claims it portrays, which is
    the records and photographs from the BW project that were compiled during work on
    the project, is sufficient evidence to satisfy the authentication requirement of Rule
    901(a), regardless of whether Coiner had personal knowledge of the contents of this
    evidence. See Kirwan v. City of Waco, 
    249 S.W.3d 544
    , 549 (Tex.App.—Waco 2008),
    rev’d on other grounds, 
    298 S.W.3d 618
    (Tex. 2009). Thus, we find the challenged
    evidence to have been properly authenticated and that the trial court did not abuse its
    discretion in admitting the evidence over appellants’ authentication objection.
    In regard to appellants’ challenge to whether AMS established the business
    records exception to the hearsay rule, Coiner testified to each of the requisites to
    establish the evidence as business records under Rule 803(6). However, appellants
    again contend that Coiner did not have personal knowledge of the information contained
    in the records. But, for a witness to establish the business record exception, he need
    not have been the record’s creator or have any personal knowledge of the contents of
    the record; rather, the witness need only have personal knowledge of the manner in
    which the records were prepared. Brooks v. State, 
    901 S.W.2d 742
    , 746 (Tex.App.—
    Fort Worth 1995, pet. ref’d).    We conclude that Coiner’s testimony established the
    requisites for application of the business records exception, and, therefore, that the trial
    court did not abuse its discretion in admitting the evidence over appellants’ hearsay
    objection.
    9
    Because the trial court did not abuse its discretion in admitting AMS’s Exhibits
    Five through Twenty over appellants’ authentication and hearsay objections, we
    overrule appellants’ third and fourth issues.
    Issue 5: Proper Party
    By their fifth issue, appellants contend that the trial court erred in awarding
    damages to AMS against Concept and Capitol because neither appellant owned the
    apartment units and, therefore, could not be liable for quantum meruit damages. AMS
    responds contending that Concept is the proper party against whom quantum meruit
    damages should be assessed because it was Concept, rather than the owner of the
    apartment complex, that requested the extra work.
    In its original petition, AMS named the owner of the apartment units, BW, as a
    defendant. However, in its subsequent amended petitions, AMS dropped BW as a
    defendant. On this basis, appellants cite Truly v. Austin, 
    744 S.W.2d 934
    , 937 (Tex.
    1988), for the proposition that “[c]entral to the contractor’s right to recover in quantum
    meruit is the owner’s acceptance and retention of the benefits arising as a direct result
    of the contractor’s partial performance.” Interpreting this quoted portion of Truly as
    literally as possible, appellants contend that it is only the owner of the benefitted
    property that can be held liable under the theory of quantum meruit. However, the Truly
    court makes clear that, to recover in quantum meruit, the plaintiff must show that its
    efforts were undertaken for the person sought to be charged. 
    Id. Incidental benefits
    to
    other parties do not give rise to quantum meruit claims against those third-party
    beneficiaries. See id.; Bashara v. Baptist Mem’l Hosp. Sys., 
    685 S.W.2d 307
    , 310 (Tex.
    10
    1985); see also Sourignavong v. Methodist Healthcare Sys., 
    977 S.W.2d 382
    , 385
    (Tex.App.—Amarillo 1998, pet. denied).
    In the present case, the evidence is clear that AMS contracted with Concept, as
    general contractor, to provide specific asbestos abatement services.         The evidence
    does not establish that AMS ever dealt with BW directly. Further, all of the extra work
    that was requested was at the direction of Scheuerer, Concept’s construction
    superintendent for the project. Thus, it was Concept, rather than BW, for whom AMS
    performed the extra work. See Bearden Investigative Agency, Inc. v. Melvin, No. 2-02-
    078-CV, 2003 Tex.App. LEXIS 957, at *17-*18 (Tex.App.—Fort Worth Jan. 30, 2003, no
    pet.); Fidelity Savs. & Loan Ass’n v. Morrison & Miller, Inc., 
    764 S.W.2d 385
    , 387-88
    (Tex.App.—Beaumont 1989, no writ). Further, evidence was presented that Concept
    needed AMS’s asbestos abatement, including the extra work, in order for Concept to
    complete its general contract with BW. Therefore, the record establishes that the extra
    work performed by AMS was for the benefit of Concept, and was not an incidental
    benefit to a third-party.
    As such, we conclude that AMS could properly assert a claim of quantum meruit
    against Concept, and overrule appellants’ fifth issue.
    Issues 6, 7, 8, & 10: Factual Sufficiency of the Evidence
    By appellants’ sixth, seventh, and eighth issues, appellants contend that the
    evidence is factually insufficient to support the quantum meruit elements that AMS
    provided appellants valuable services or materials (issue six), AMS’s work benefited
    appellants (issue seven), and Concept accepted services or materials from AMS (issue
    11
    eight). By their tenth issue, appellants contend that the evidence is factually insufficient
    to support the trial court’s judgment against Capitol under the payment bond. Each of
    these issues challenge explicit factual findings made by the trial court.4
    Standard of Review
    An assertion that the evidence is factually insufficient to support a fact finding
    means that the evidence supporting the finding is so weak or the evidence to the
    contrary is so overwhelming that the answer should be set aside and a new trial
    ordered.     Garza v. Alviar, 
    395 S.W.2d 821
    , 823 (Tex. 1965).            In reviewing factual
    sufficiency, the reviewing court must consider, examine, and weigh all of the evidence in
    the record. Maritime Overseas Corp. v. Ellis, 
    971 S.W.2d 402
    , 406-07 (Tex. 1998). In
    doing so, the court does not consider the evidence in the light most favorable to the
    4
    Appellants’ issues challenge the trial court’s following findings of fact:
    5. Concept then requested substantial additional work, approximately
    equal in scope to the original job. This additional work substantially
    increased the preparation necessary, thereby actually exceeding the
    quoted scope.
    6. Plaintiff [AMS] is an asbestos contractor, and the services provided
    involve removal of asbestos contaminated material. The limited scope
    quoted could be accomplished with the use of “glove bags” that do not
    involve area containment and donning of hazmat suits. The extra work
    subsequently requested include removal of carpet, which did require these
    additional precautions.
    8. Plaintiff’s work benefitted Defendant Concept . . . .
    9. Concept accepted the extra work.
    12. Asbestos [AMS] dealt directly with Concept, and presented its invoices
    stating the basis of its claim for compensation. All notice requirements for
    recovery under the payment bond against Defendant Capitol . . . have
    occurred or been satisfied.
    12
    finding; instead, the court considers and weighs all the evidence, and sets aside the
    disputed finding only if it is so contrary to the great weight and preponderance of the
    evidence as to be clearly wrong and unjust. 
    Id. at 407;
    Gooch v. American Sling Co.,
    
    902 S.W.2d 181
    , 184 (Tex.App.--Fort Worth 1995, no writ).
    Quantum Meruit Claim
    Quantum meruit is an equitable theory of recovery which is based on an implied
    agreement to pay for benefits received. Heldenfels Bros., Inc. v. City of Corpus Christi,
    
    832 S.W.2d 39
    , 41 (Tex. 1992); Iron Mountain Bison Ranch, Inc. v. Easley Trailer Mfg.,
    Inc., 
    42 S.W.3d 149
    , 159 (Tex.App.—Amarillo 2000, no pet.). To establish a claim for
    quantum meruit damages in Texas, a plaintiff must prove that it (1) provided valuable
    services or materials, (2) for the benefit of the defendant, (3) that were accepted by the
    defendant, and (4) the defendant had reasonable notice that the plaintiff expected
    compensation for the services or materials. Heldenfels Bros., 
    Inc., 832 S.W.2d at 41
    ;
    Iron Mountain Bison 
    Ranch, 42 S.W.3d at 159-60
    . Thus, by their sixth through eighth
    issues, appellants challenge the factual sufficiency of the evidence supporting the trial
    court’s findings of fact that AMS proved the first three elements of its quantum meruit
    claim.
    Appellants challenge the sufficiency of the evidence proving that the extra work
    performed by AMS was a valuable service or material. Appellants’ contention reiterates
    their complaints about the evidence addressed in issues three and four, and also
    contends that AMS failed to follow appropriate procedures for obtaining approval to
    perform the extra work. However, a review of appellants’ argument makes clear that
    13
    they are not disputing that AMS performed valuable work that was outside the scope of
    the contract.5   Rather, appellants’ contention relates to whether AMS is entitled to
    payment for the extra work that was performed, and the appropriate amount of value
    provided by AMS through its extra work.          The record establishes that Scheurer
    requested that AMS perform extra work that exceeded the scope of the work that AMS
    and Concept initially agreed upon. Further, while there was some dispute regarding
    exactly how much extra work was performed and the value of this extra work, there is
    no evidence that denies that AMS performed some work that exceeded the scope of the
    initial agreements and that this extra work was valuable. Thus, we cannot agree with
    appellants’ contention that the evidence was factually insufficient to establish that AMS
    provided valuable services or materials to Concept. We overrule appellants’ sixth issue.
    Appellants also challenge the factual sufficiency of the second element of AMS’s
    quantum meruit claim, that Concept benefited from AMS’s extra work. By this issue,
    appellants simply reiterate their contention presented in issue five, that any benefit from
    AMS’s extra work flowed to the owner of the property, BW, and not to appellants.
    However, as addressed above in analysis of appellants’ fifth issue, the evidence that
    Concept requested and benefitted from the extra work performed by AMS is not so
    against the great weight and preponderance of the evidence as to be clearly wrong and
    unjust. We overrule appellants’ seventh issue.
    5
    Within their argument of issue six, appellants allege that, “Finding of Fact No. 4
    includes a reference to ‘ALC,’ a flaw which is fatal to the elements of the theory of
    quantum meruit.” However, this allegation is not explained. As this Court cannot
    determine the nature of appellants’ argument, we cannot agree that the trial court’s
    reference to ALC is fatal to AMS’s quantum meruit claim. We do, however, note that
    the trial court’s finding of fact No. 4 appears to go with Finding of Fact Nos. 2 and 3 to
    identify the scope of the work covered by the express contracts.
    14
    Finally, appellants challenge the sufficiency of the evidence to establish that
    Concept accepted the extra work performed by AMS.           Appellants contend that the
    evidence establishes that, after August 18, 2004, Concept consistently refused to
    accept the extra work provided by AMS by limiting payment of invoices to only those
    charges attributable to work performed under the initial agreement. Concept contends
    that it requested “backup” documentation to support the extra work, and that it conveyed
    to AMS that this backup was required before Concept could accept the extra work.
    While the record does evidence that Concept stopped paying for extra work after
    August of 2004 and that it requested backup documentation to support AMS’s extra
    work, the evidence also shows that Scheurer continued to request AMS to perform extra
    work after August of 2004 and that the extra work performed by AMS was necessary for
    Concept to complete its contract with BW. Thus, while there is some evidence that
    appellants did not accept AMS’s work after August 18, 2004, we cannot conclude that
    the trial court’s finding that Concept accepted the extra work performed by AMS after
    August of 2004 is so against the great weight and preponderance of the evidence as to
    be clearly wrong and manifestly unjust. We overrule appellants’ eighth issue.
    Payment bond
    By their tenth issue, appellants contend that the evidence is factually insufficient
    to support the trial court’s judgment against Capitol. Even though the trial court found
    that all notice requirements under the payment bond had been satisfied by AMS,
    appellants point to the testimony of Mark Gross, Concept’s president and owner, that
    AMS failed to provide the requisite notice to assert a claim against the payment bond.
    15
    AMS responds contending that the terms of the bond except a party in direct contract
    with Concept from being required to provide notice of suit. Thus, according to AMS,
    there was no notice requirement applicable to AMS, who was in direct contract with
    Concept, and the trial court’s finding that all notice requirements have been satisfied is
    sufficient as a matter of law.
    Reviewing the arguments of appellants in their tenth issue, it is clear that their
    factual sufficiency challenge rests on an unstated premise, that the payment bond in
    issue has a notice requirement that applies to AMS. A review of the record reveals that
    the evidence does establish that AMS did not provide Concept notice of its intent to sue.
    The terms of the payment bond provide that, “No suit or action shall be commenced
    hereunder by any claimant: . . . unless claimant, other than one having direct contract
    with the Principal, shall have given written notice to [Concept] . . . .” This payment bond
    is defined by the scope of the work that Concept was to perform in completion of the
    project for BW. As previously mentioned, while the extra work performed by AMS is
    beyond the terms of the initial agreement between AMS and Concept, the evidence
    establishes that AMS’s extra work needed to be performed for Concept to complete the
    project. Thus, the extra work was within the general scope of the payment bond. Also,
    the evidence establishes that Concept and AMS were in direct contract with regard to
    the initial asbestos abatement that Concept consistently acknowledged and accepted.
    As such, by the express terms of the payment bond, AMS was excepted from the notice
    16
    requirement6 and, therefore, the trial court’s finding that all required notice has been
    satisfied is supported by the evidence. We overrule appellant’s tenth issue.
    Issue 9: Express Contract
    Appellants contend that the trial court erred in awarding AMS damages under the
    theory of quantum meruit because there are express contracts between AMS and
    Concept that generally cover AMS’s provision of asbestos abatement services for the
    BW project. AMS responds that the express contracts did not cover the extra work
    requested by Concept and performed by AMS and, therefore, recovery under the theory
    of quantum meruit is permitted.
    The right to recover in quantum meruit is based upon a promise implied by law to
    pay for beneficial services rendered and knowingly accepted. Davidson v. Clearman,
    
    391 S.W.2d 48
    , 50 (Tex. 1965). However, when a valid express contract covers the
    services or materials upon which recovery is sought, recovery in quantum meruit will not
    be permitted. 
    Truly, 744 S.W.2d at 936
    . But, the existence of an express contract does
    not preclude recovery in quantum meruit for the reasonable value of services rendered
    and accepted which are not covered by the contract. Black Lake Pipe Line Co. v. Union
    6
    We acknowledge that AMS’s quantum meruit claim is, by definition, extra-
    contractual. However, the payment bond excepts claimants from providing notice of
    claims when in direct contract with Concept. Exceptions to coverage contained within
    an insurance policy are to be strictly construed against the insurer and in favor of
    coverage, and any intent to exclude coverage must be expressed in clear and
    unambiguous language. National Union Fire Ins. Co. of Pittsburgh, Pa. v. Hudson
    Energy Co., 
    811 S.W.2d 552
    , 555 (Tex. 1991). In the present case, the terms of the
    bond allow for a reasonable interpretation exempting AMS from the notice requirement,
    and we are therefore compelled to interpret the policy in favor of coverage.
    17
    Constr. Co., 
    538 S.W.2d 80
    , 86 (Tex. 1976), overruled on other grounds by Sterner v.
    Marathon Oil Co., 
    767 S.W.2d 686
    , 690 (Tex. 1989).
    The trial court’s findings of fact make it clear that the extra work exceeded the
    scope of the work covered by the express contracts. Specifically, the trial court found
    that the work covered by the express contracts could be performed “with the use of
    ‘glove bags’ that do not involve area containment and donning of hazmat suits.”
    However, the extra work that was requested by Scheuerer “included removal of carpet,
    which did require these extra precautions.” Appellants’ argument simply states that the
    express contracts covered “asbestos abatement to be conducted by Appellee” and that,
    because the express contracts covered asbestos abatement, AMS is precluded from
    recovery in quantum meruit based on the provision of any asbestos abatement services.
    Appellants’ argument, however, wholly fails to address the trial court’s finding that the
    scope of the asbestos abatement covered by the express contracts was exceeded by
    the extra work as evidenced by the necessity that AMS take the specified extra
    precautions. Finding that there is significant evidence in the record to support the trial
    court’s finding that the extra work exceeded the scope of the express contracts, we are
    bound by the trial court’s factual finding. See McGalliard v. Kuhlmann, 
    722 S.W.2d 694
    ,
    696 (Tex. 1986) (when a finding of fact is unchallenged, it is binding on an appellate
    court unless the contrary is established as a matter of law or there is no evidence to
    support the finding). Consequently, we overrule appellants’ ninth issue.
    18
    Issues 11 & 15: Timeliness of Judgment
    Appellants contend that the trial court failed to comply with the requirements of
    Texas Government Code section 74.059(c)(2),7 when it failed to enter judgment in this
    case for more than two and a half years after the date of trial. In their analysis of the
    alleged harm caused by this delay, appellants cite Coiner’s conviction for improper
    disposal of asbestos.8 AMS responds contending that appellants failed to complain of
    the delay in the trial court, and case law requires a showing of how the delay caused
    harm before a delay is reversible. AMS contends that appellants fail to show how
    Coiner’s conviction caused appellants harm or would necessitate that they be afforded a
    new trial.
    Our review of the record does not indicate that appellants ever sought to obtain
    the trial court’s ruling in this case nor did appellants bring to the trial court’s attention its
    failure to comply with Texas Government Code section 74.059(c)(2) at any time before
    the trial court rendered its judgment. Following the trial court’s judgment, appellants did
    identify this issue in their timely filed motion for new trial.         Thus, the issue was
    preserved. See TEX. R. APP. P. 33.1(b).
    7
    Section 74.059(c)(2) provides, “(c) A district, statutory probate, or statutory
    county court judge shall: (2) rule on a case within 90 days after the case is taken under
    advisement.” TEX. GOV’T CODE ANN. § 74.059(c)(2) (West 2005).
    8
    Appellants’ issue 15 does not challenge the judgment as being untimely, but
    does challenge the trial court’s denial of appellants’ motion for new trial based on
    Coiner’s conviction. Since that issue contends that appellants are entitled to a new trial
    on the same basis upon which they contend that the trial court’s untimely judgment
    caused them harm, we will analyze the issues together.
    19
    A trial court’s failure to comply with section 74.059(c)(2) is not automatically
    reversible error.   See Smith v. Montemayor, No. 03-02-00466-CV, 2003 Tex.App.
    LEXIS 5099, at *31-*32 (Tex.App.—Austin June 19, 2003, no pet.) (mem. op.). The
    complaining party bears the burden of demonstrating that the trial court’s delay in
    rendering judgment probably caused the rendition of an improper judgment. 
    Id. at *32.
    To meet this burden, appellants contend that they were harmed by the passage
    of the three-year period after AMS’s forfeiture of its corporate charter, and by the
    intervening federal indictment and conviction of Coiner for improper disposal of
    asbestos. However, appellants in no way identify the significance of the passage of
    three years after AMS’s forfeiture of its corporate charter nor do they identify how such
    an occurrence caused them harm.          Similarly, appellants identify that Coiner was
    indicted and convicted of improper disposal of asbestos, but make no attempt to explain
    to this Court how this conviction impacts the present case. Further, evidence provided
    by appellants indicates that Coiner was convicted of negligent release of hazardous air
    pollutants, and that the actions upon which this conviction is based occurred after AMS
    had completed its work on the BW project. As such, we conclude that appellants have
    failed to meet their burden of demonstrating that the trial court’s delay in rendering
    judgment probably caused the rendition of an improper judgment.             Likewise, we
    conclude that appellants have failed to establish that Coiner’s conviction entitles
    appellants to a new trial. We overrule appellants’ eleventh and fifteenth issues.
    20
    Issue 12: Waiver and Estoppel
    Appellants contend that the evidence established their affirmative defenses of
    waiver or estoppel as a matter of law. Appellants’ contention is premised on AMS’s
    acceptance of payment for the work covered by the agreements, while Concept refused
    to pay for the extra work reflected in the invoices after August of 2004. Appellants
    contend that AMS’s silence from August of 2004, when Concept stopped paying for the
    extra work, until August of 2005, when AMS filed the present suit, constitutes a waiver
    of AMS’s right to recover on the extra work.       Alternatively, appellants contend that
    AMS’s failure to provide requested documentation to support the extra work performed
    prior to trial estops AMS from recovering on the extra work.        AMS responds that
    Concept’s request for backup documentation on the extra work was disputed and that,
    in any event, its failure to provide documentation to support its claim for payment does
    not constitute an “intentional relinquishment of a known right.”
    Our review of the record reveals that AMS continued to perform extra work for
    Concept after Concept stopped paying for the extra work, but that the period of time
    during which AMS performed extra work while not being paid was from September of
    2004 to April of 2005. This is only a period of eight months. Further, evidence was
    presented that Concept had paid for the extra work on the first four invoices. AMS
    presented evidence that it continued to perform the extra work beyond this point in good
    faith and because it thought that Concept may have been attempting to get change
    orders approved by BW which was delaying payment for the extra work. However,
    once Coiner determined that Concept was not going to pay AMS for the extra work,
    21
    AMS stopped performing the extra work. Thus, AMS did not take a course of action
    inconsistent with claiming a right to payment for extra work for such an extended period
    that it can be fairly said that AMS waived its right to payment. See Sun Exploration &
    Prod. Co. v. Benton, 
    728 S.W.2d 35
    , 37 (Tex. 1987) (waiver requires the intentional
    relinquishment of a known right or engaging in intentional conduct inconsistent with
    claiming that right).
    As to the claim of estoppel, appellants fail to cite to any authority that would
    support their contention that a failure to substantiate a claim for payment estops a
    person from seeking judicial recourse for the claim. While it was clearly incumbent
    upon AMS to establish the value of the services it provided to Concept in order to
    recover on its quantum meruit claim, nothing in the law requires that a plaintiff must
    establish that value before filing suit and substantiate that value in a manner acceptable
    to the benefitted party or else be estopped from asserting a quantum meruit claim.
    Finding no evidence to support appellants’ affirmative defenses of waiver or
    estoppel, we overrule appellants’ twelfth issue.
    Issues 13 & 14: Concept’s Breach of Contract Counterclaim
    Appellants contend that they established their counterclaim for breach of contract
    as a matter of law and that, as a result, they are entitled to at least $20,080 in actual
    damages as well as $25,000 in attorney’s fees. AMS responds that it was Concept that
    breached the contract and, therefore, the trial court did not err in denying appellants’
    counterclaim. Further, AMS contends that the $5,000 in attorney’s fees attributable to
    22
    the removal of AMS’s mechanic’s lien is being raised for the first time on appeal and is,
    therefore, waived.
    Appellants premise their contention that they are entitled to recover for their
    breach of contract counterclaim on their decision to retain a third-party asbestos
    abatement company to complete the contract work on the project that was not
    completed by AMS.      However, their argument fails to address the uncontroverted
    evidence that AMS remained ready to complete the work identified in the agreements
    upon being recalled by Concept.          However, apparently because AMS ceased
    performing the extra work for which it was not being paid, Concept did not recall AMS to
    complete the work, but rather chose to retain a third-party to complete the work on the
    project. As such, the evidence establishes that it was Concept, not AMS, that breached
    the contracts. Thus, we conclude that the trial court did not err in denying appellants’
    counterclaim.
    Having determined that appellants are not entitled to recover on their breach of
    contract counterclaim, their attorney’s fees issue is reduced to appellants’ contention
    that AMS stipulated that Concept was entitled to $5,000 in attorney’s fees relating to the
    removal of a mechanic’s lien. While the record does reflect that AMS acknowledged an
    agreement that $5,000 in attorney’s fees for appellants would be attributable to removal
    of the lien, this acknowledgement was part of a pre-trial stipulation that the parties had
    agreed “that $25,000 was a reasonable and necessary attorneys’ fee through trial for
    each side’s attorney, and agreed that of that sum, with respect to Defendants, $5,000 of
    that would be reasonably attributable to the Motion to Remove Mechanic’s Lien . . . .”
    23
    (emphasis added). Looking at the precise language used by AMS, we construe the
    agreement to simply indicate that the parties agreed as to what would constitute a
    reasonable and necessary attorney fee award, and that this agreement, as it relates to
    appellants, has factored in $5,000 for the removal of the lien. Thus, nothing in the
    agreement obligated the trial court to make a separate award of attorney’s fees to
    appellants relating to the removal of the lien.
    Further, appellants cite Texas Property Code section 53.156 as statutory support
    for their entitlement to these attorney’s fees. However, section 53.156 permits the trial
    court to award costs and reasonable attorney’s fees as would be equitable and just.
    TEX. PROP. CODE ANN. § 53.156 (West 2007). Appellants have wholly failed to show
    that the trial court abused its discretion by not awarding them $5,000 as attorney’s fees
    relating to removal of the mechanic’s lien.
    Finally, appellants failed to address the trial court’s award of attorney’s fees in
    either their motion for new trial or in their motion for reconsideration of motion for new
    trial. Thus, we conclude that appellants failed to bring their construction of the pre-trial
    stipulation regarding attorney’s fees to the trial court’s attention and, therefore, have
    waived any objection to the trial court’s award. See TEX. R. APP. P. 33.1.
    We overrule appellants’ thirteenth and fourteenth issues.
    24
    Conclusion
    Having overruled each of appellants’ fifteen issues, we affirm the judgment of the
    trial court.
    Mackey K. Hancock
    Justice
    25