Geo-Tech Foundation Repair v. Terry Leggett ( 2017 )


Menu:
  •                           COURT OF APPEALS
    SECOND DISTRICT OF TEXAS
    FORT WORTH
    NO. 02-16-00289-CV
    GEO-TECH FOUNDATION REPAIR                                           APPELLANT
    V.
    TERRY LEGGETT                                                          APPELLEE
    ----------
    FROM COUNTY COURT AT LAW NO. 2 OF TARRANT COUNTY
    TRIAL COURT NO. 2015-006367-2
    ----------
    MEMORANDUM OPINION1
    ----------
    In one issue, appellant Geo-Tech Foundation Repair (Geo-Tech) appeals
    the trial court’s interlocutory order denying a motion to compel arbitration.2 Geo-
    Tech contends that it seeks to enforce a mandatory arbitration provision
    contained in the parties’ contract and that appellee Terry Leggett cannot show
    1
    See Tex. R. App. P. 47.4.
    2
    See Tex. Civ. Prac. & Rem. Code Ann. §§ 171.021(a), .098(a)(1) (West
    2011).
    that Geo-Tech has waived its entitlement to arbitration. Leggett contends that
    the record does not include any competent evidence of a valid agreement to
    arbitrate and that Geo-Tech’s delay in demanding arbitration justified the trial
    court’s denial of the motion to compel arbitration. We reverse and remand.
    Background Facts
    In November 2015, Leggett sued Geo-Tech for breach of contract. Leggett
    alleged that in April 2011, the parties had entered into an agreement for Geo-
    Tech to perform foundation work on Leggett’s Fort Worth home. Leggett alleged
    that Geo-Tech had performed the work improperly and had attempted, but had
    failed, to correct problems that resulted from the deficient performance. Leggett
    asserted that Geo-Tech had “breached its contract . . . for the performance of
    services, to-wit, repair to the foundation of [Leggett’s] home.” In his petition,
    Leggett sought damages of $40,000 plus attorney’s fees under the civil practice
    and remedies code. See Tex. Civ. Prac. & Rem. Code Ann. § 38.001 (West
    2015). Geo-Tech filed an answer in which it asserted a general denial and pled
    for costs and attorney’s fees.
    Six months after filing its answer, in May 2016, Geo-Tech filed a motion to
    compel arbitration under section 171.021 of the civil practice and remedies code.
    See 
    id. § 171.021(a).
    In the motion, Geo-Tech contended that the parties had
    entered into a contract for foundation repair of Leggett’s home in April 2011 and
    that the contract had the following clauses:
    2
    Owner and Contractor agree that any dispute, or lawsuit related in
    any way to this agreement or the work related thereto, shall be
    resolved by mandatory and binding arbitration administered by the
    American Arbitration Association (AAA) in accordance with this
    arbitration agreement and under the commercial arbitration rules of
    the AAA . . . .
    ....
    In the event that the Owner and Contractor cannot agree that
    the movement in the foundation has been controlled and settlement
    is within the tolerances specified above, it is specifically agreed by
    acceptance of this warranty that the matter shall be determined by
    binding arbitration administered by the American Arbitration
    Association (AAA) in accordance with this arbitration agreement and
    under the commercial arbitration rules of the AAA . . . .
    To the motion, Geo-Tech attached a copy of the parties’ contract that contains
    the provisions above and represented that the attachment was a “true copy,”
    although Geo-Tech’s motion was not sworn.          The contract recites Leggett’s
    name, address, and signature; states an amount that Leggett agreed to pay Geo-
    Tech; includes a date; and illustrates the proposed foundation repair.
    Leggett responded to Geo-Tech’s motion to compel arbitration. He argued
    that Geo-Tech had waived its right to demand arbitration because of its delay in
    doing so and because of his prejudice caused by the delay. He conceded that
    the arbitration clause in the parties’ contract “purport[ed] to allow [Geo-Tech]
    to . . . arbitrate the complaints raised by [Leggett].” He argued, however, that the
    trial court should not reward Geo-Tech’s “dilatory tactics” by granting arbitration.
    Leggett did not object to the contract that Geo-Tech attached to its motion to
    compel or contest Geo-Tech’s assertions that the parties had entered into a
    3
    contract and that the contract had contained the arbitration provisions quoted
    above.
    After Geo-Tech replied to Leggett’s response, the trial court denied Geo-
    Tech’s motion to compel arbitration. Geo-Tech brought this appeal.
    Motion to Compel Arbitration
    Geo-Tech contends that the trial court erred by denying the motion to
    compel arbitration.    In their briefing to this court, the parties focus on two
    disputes: (1) whether Geo-Tech was required to authenticate the contract that it
    attached to its motion to compel in the trial court (and whether Leggett was
    required to object to any failure to authenticate the contract as a prerequisite to
    arguing lack of authentication on appeal), and (2) whether Geo-Tech’s delay in
    seeking arbitration resulted in a waiver of its right to do so.
    A written agreement to arbitrate a controversy that arises between parties
    after the date of the agreement is generally valid and enforceable. See Tex. Civ.
    Prac. & Rem. Code Ann. § 171.001(a)(2) (West 2011); Jabri v. Qaddura, 
    108 S.W.3d 404
    , 410 (Tex. App.—Fort Worth 2003, no pet.). A party to such an
    agreement may file a motion to compel arbitration of a dispute, and the trial court
    “shall order” the parties to arbitrate on a showing of an agreement to arbitrate
    and the opposing party’s refusal to do so. Tex. Civ. Prac. & Rem. Code Ann.
    § 171.021(a); 
    Jabri, 108 S.W.3d at 410
    . If a party opposing arbitration “denies
    the existence of the agreement,” the court “shall summarily determine that issue.”
    
    4 Tex. Civ
    . Prac. & Rem. Code Ann. § 171.021(b). When a trial court denies a
    motion to compel arbitration, the party seeking arbitration may bring an
    interlocutory appeal. 
    Id. § 171.098(a)(1).
    We review a trial court’s denial of a motion to compel arbitration for an
    abuse of discretion, but we review whether there is a valid and enforceable
    arbitration agreement de novo. Watts Regulator Co. v. Tex. Farmers Ins. Co.,
    
    498 S.W.3d 643
    , 646 (Tex. App.—Fort Worth 2016, pets. abated); BBVA
    Compass Inv. Solutions, Inc. v. Brooks, 
    456 S.W.3d 711
    , 723 (Tex. App.—Fort
    Worth 2015, no pet.); Brand FX, LLC v. Rhine, 
    458 S.W.3d 195
    , 203 (Tex.
    App.—Fort Worth 2015, no pet.). A party seeking to compel arbitration must
    show that the claims at issue are subject to a valid arbitration agreement and fall
    within the scope of that agreement. Watts Regulator 
    Co., 498 S.W.3d at 646
    –47.
    Federal and state law strongly favor arbitration.     BBVA Compass Inv.
    Sols., 
    Inc., 456 S.W.3d at 717
    . “[A] trial court that refuses to compel arbitration
    under a valid and enforceable arbitration agreement has abused its discretion.”
    Brand FX, 
    LLC, 458 S.W.3d at 204
    .
    Authentication
    On appeal, Geo-Tech contends that the contract attached to its motion to
    compel contains valid and binding arbitration provisions.         Leggett argues,
    however, that the attachment cannot serve as competent evidence of a valid
    agreement to arbitrate because it is not authenticated. Leggett does not deny
    that the parties entered into a contract (indeed, he has brought a claim for breach
    5
    of that contract), but he contends that the contract that appears in the record was
    not properly authenticated.
    Leggett did not raise this argument in the trial court. On appeal, he cites
    two cases for the proposition that an unauthenticated contract cannot serve as
    competent evidence of an agreement to arbitrate. See In the Estate of Guerrero,
    
    465 S.W.3d 693
    , 705 (Tex. App.—Houston [14th Dist.] 2015, pet. denied)
    (en banc) (“Because Champion has not authenticated the Arbitration Agreement
    or any of the sales documents it attached to its motions to compel arbitration,
    there is no competent evidence of an agreement to arbitrate.”); In re Universal
    Fins. Consulting Grp., No. 14-08-00226-CV, 
    2008 WL 2133186
    , at *2 (Tex.
    App.—Houston [14th Dist.] May 20, 2008, orig. proceeding) (mem. op.) (“Here,
    no affidavit was submitted with either the motion to compel or the amended
    motion to compel authenticating the escrow agreement or the asset purchase
    agreement. We conclude that there is no competent evidence of an agreement
    to arbitrate.”).
    The plain language of section 171.021(b) requires a trial court to
    “determine [the] issue” of the existence of an arbitration agreement when the
    party opposing arbitration “denies the existence of the agreement.” Tex. Civ.
    Prac. & Rem. Code Ann. § 171.021(b); see BCCA Appeal Grp. v. City of
    Houston, 
    496 S.W.3d 1
    , 8 (Tex. 2016) (explaining that we must “initially look to
    the plain meaning of the text as the sole expression of legislative intent”); see
    also ANCO Ins. Servs. of Houston, Inc. v. Romero, 
    27 S.W.3d 1
    , 5 (Tex. App.—
    6
    San Antonio 2000, pet. denied) (“If a party opposes an application to arbitrate by
    denying the existence of an agreement, the trial court must summarily determine
    that issue.”). Leggett never denied the existence of an agreement. Instead, he
    pled in his original petition that he had entered into an agreement in April 2011
    with Geo-Tech for foundation repair at a particular Fort Worth address, and the
    foundation repair contract that Geo-Tech attached to its motion to compel
    contains that date and that address along with detailed terms, Geo-Tech’s
    letterhead, and Leggett’s signature.     Furthermore, Leggett’s sole response to
    Geo-Tech’s motion to compel arbitration—that Geo-Tech had waived its right to
    demand arbitration—assumed that Geo-Tech at one point had the right to
    compel arbitration under the parties’ contract. Leggett’s response acknowledged
    the existence of the “arbitration clause” that “purport[ed] to allow [Geo-Tech] . . .
    to arbitrate the complaints raised by [Leggett] as early as April of 2011.” Leggett
    quoted part of the arbitration clause in his response and referred to arbitration as
    “relief [that Geo-Tech was] capable of requesting five years ago.” [Emphasis
    added.] The response assumed that Geo-Tech once enjoyed an “entitlement to
    seek to arbitrate this . . . dispute.”
    Under these specific circumstances, because Leggett never denied in the
    trial court that an arbitration agreement existed and assumed or acknowledged
    that one existed, we cannot affirm the trial court’s order on the basis of Geo-
    Tech’s failure to present competent evidence of an agreement to arbitrate, as
    Leggett argues. See Tex. Civ. Prac. & Rem. Code Ann. § 171.021(b); see also
    7
    Bell v. Koch Foods of Miss., LLC, 358 Fed. Appx. 498, 501 (5th Cir. 2009)
    (overruling an appellate complaint concerning an alleged lack of authentication of
    arbitration agreements when the party opposing arbitration did not object to
    authenticity in the trial court and did not argue that the agreements had not been
    properly signed); In re Whitfield, 
    115 S.W.3d 753
    , 755 (Tex. App.—Beaumont
    2003, no pet.) (relying on a party’s admission that arbitration agreements
    existed).
    Our conclusion in this regard receives support from three principles that
    generally undergird the requirement of preservation of error. See Tex. R. App. P.
    33.1(a). First, “requiring that parties initially raise complaints in the trial court
    conserves judicial resources by providing trial courts the opportunity to correct
    errors before appeal.” Mansions in the Forest, L.P. v. Montgomery Cty., 
    365 S.W.3d 314
    , 317 (Tex. 2012).         Second, “judicial decision-making is more
    accurate when trial courts have the first opportunity to consider and rule on
    error.” 
    Id. Third, and
    most pertinent to the issue presented here, a party should
    not be “permitted to waive, consent to, or neglect to complain about an error at
    trial and then surprise his opponent on appeal by stating his complaint for the first
    time.” 
    Id. We note
    that in each of the cases relied on by Leggett, the party opposing
    arbitration objected in the trial court to the lack of authentication and therefore
    appeared to deny the existence of the agreement in accordance with section
    171.021(b). See 
    Guerrero, 465 S.W.3d at 704
    ; Universal Fins. Consulting Grp.,
    8
    
    2008 WL 2133186
    , at *1; see also Tex. Civ. Prac. & Rem. Code Ann.
    § 171.021(b). Thus, we conclude that those cases are distinguishable.        See
    
    Guerrero, 465 S.W.3d at 704
    (noting that the facts in that case concerning the
    arbitration agreement were “disputed” and acknowledging that a “trial court may
    summarily decide whether to compel arbitration on the basis of affidavits,
    pleadings, discovery, and stipulations if the material facts are not controverted”
    (emphasis added)); see also Jack B. Anglin Co. v. Tipps, 
    842 S.W.2d 266
    , 269
    (Tex. 1992) (“[W]e hold that the trial court may summarily decide whether to
    compel arbitration on the basis of affidavits, pleadings, discovery, and
    stipulations.”). To the extent that the courts’ decisions in the cases cited by
    appellant may be construed to hold that a party may challenge authentication of
    an arbitration agreement for the first time on appeal even when the party never
    challenged the agreement in the trial court and affirmatively acknowledged the
    agreement’s existence there, we disagree.
    We conclude that the totality of the record establishes the existence of a
    valid arbitration agreement, especially in light of Leggett’s failure to deny the
    existence of that agreement and his assumption that the agreement existed. See
    Watts Regulator 
    Co., 498 S.W.3d at 646
    .
    Alleged waiver
    Given our conclusion that the record establishes the existence of an
    arbitration agreement between Geo-Tech and Leggett, arbitration must occur
    unless Geo-Tech’s delay in seeking arbitration resulted in waiver, as Leggett
    9
    contends.   See Tex. Civ. Prac. & Rem. Code Ann. §§ 171.001(a), .021(a).
    Leggett argues that Geo-Tech waived its right to demand arbitration because it
    first made the demand months before the date set for trial and years after the
    parties had entered the agreement for foundation repairs and after Geo-Tech had
    failed to make the repairs. Geo-Tech contends that the lapse of time between
    Leggett’s November 2015 original petition and Geo-Tech’s May 2016 demand for
    arbitration is insufficient to establish waiver, that Geo-Tech has not substantially
    invoked the judicial process to cause waiver, and that Leggett has not shown any
    prejudice caused by Geo-Tech’s delay in requesting arbitration.
    As the Texas Supreme Court recently explained,
    A party’s right to arbitrate may be waived by its substantially
    invoking the judicial process to the other party’s detriment. To effect
    such an implied waiver, however, the conduct that substantially
    invoked the judicial process must have prejudiced the other party to
    the arbitration agreement. When courts consider allegations of such
    a waiver, “[t]here is a strong presumption” against it . . . . The
    presumption governs in close cases. . . .
    Where facts are undisputed, whether the right to arbitrate has
    been waived is a matter of law subject to de novo review on appeal.
    The party asserting waiver bears a heavy burden of proof to show
    the party seeking arbitration has waived its arbitration right. Whether
    waiver has occurred depends on the totality of the circumstances.
    The analysis involves numerous factors, including whether the party
    asserting the right to arbitrate was plaintiff or defendant in the
    lawsuit, how long the party waited before seeking arbitration, the
    reasons for any delay in seeking to arbitrate, how much discovery
    and other pretrial activity the party seeking to arbitrate conducted
    before seeking arbitration, whether the party seeking to arbitrate
    requested the court to dispose of claims on the merits, whether the
    party seeking to arbitrate asserted affirmative claims for relief in
    court, the amount of time and expense the parties have expended in
    10
    litigation, and whether the discovery conducted would be unavailable
    or useful in arbitration.
    Generally, no one factor is, by itself, dispositive. Parties
    seeking to arbitrate have taken several different types of action
    without substantially invoking the judicial process. Examples of such
    actions include filing suit, conducting discovery, noticing depositions,
    taking depositions, agreeing to trial settings, and moving for
    procedural disposition. Additionally, asserting defensive claims . . .
    does not waive arbitration. And while delay by the party seeking
    arbitration may be a factor, we have found no waiver in cases where
    there were delays of as much as eight months and even two years.[3]
    RSL Funding, LLC v. Pippins, 
    499 S.W.3d 423
    , 430–31 (Tex. 2016) (citations
    omitted); see G.T. Leach Builders, LLC v. Sapphire V.P., LP, 
    458 S.W.3d 502
    ,
    511–12 (Tex. 2015) (stating that a party asserting waiver as a defense to
    arbitration has the “high” burden “to prove that (1) the other party has
    ‘substantially invoked the judicial process,’ which is conduct inconsistent with a
    claimed right to compel arbitration, and (2) the inconsistent conduct has caused it
    to suffer detriment or prejudice”); Richmont Holdings, Inc. v. Superior Recharge
    Sys., L.L.C., 
    455 S.W.3d 573
    , 575–76 (Tex. 2014) (stating that “mere delay in
    moving to compel arbitration is not enough for waiver” and explaining that
    whether a party has “substantially invoked the judicial process depends on . . .
    factors [such as] the reason for delay in moving to enforce arbitration, the amount
    of discovery conducted by the movant, and whether the movant sought
    disposition on the merits”); Kennedy Hodges, L.L.P. v. Gobellan, 
    433 S.W.3d 3
            The delay between when Leggett filed his original petition and when Geo-
    Tech filed its motion to compel arbitration was six months.
    11
    542, 543 (Tex. 2014) (“Proving waiver is a high hurdle due to the strong
    presumption against waiver of arbitration.”); Prudential Sec. Inc. v. Marshall, 
    909 S.W.2d 896
    , 898–99 (Tex. 1995) (orig. proceeding) (“A party does not waive a
    right to arbitration merely by delay; instead, the party urging waiver must
    establish that any delay resulted in prejudice.”).
    In the context of showing waiver of a right to arbitration, prejudice means
    “inherent unfairness in terms of delay, expense, or damage to a party’s legal
    position that occurs when the party’s opponent forces it to litigate an issue and
    later seeks to arbitrate that same issue.” Kennedy Hodges, 
    L.L.P., 433 S.W.3d at 545
    . “Any doubts regarding waiver are resolved in favor of arbitration.” Nw.
    Constr. Co. v. Oak Partners, L.P., 
    248 S.W.3d 837
    , 847 (Tex. App.—Fort Worth
    2008, pet. denied). Merely engaging in litigation, such as filing counterclaims or
    participating in discovery, is not enough to result in waiver. Branch Law Firm
    L.L.P. v. Osborn, No. 14-14-00892-CV, 
    2016 WL 444867
    , at *14 (Tex. App.—
    Houston [14th Dist.] Feb. 4, 2016, pet. denied).
    The record in this case does not contain sufficient evidence of either
    required ground for waiver:     that Geo-Tech substantially invoked the judicial
    process or that Leggett has been prejudiced. See G.T. Leach Builders, 
    LLC, 458 S.W.3d at 511
    –12. The forty-seven-page clerk’s record establishes Geo-Tech’s
    limited participation in this suit. The record contains only three documents filed
    by Geo-Tech: its original answer, its motion to compel arbitration, and its reply to
    Leggett’s response to the motion to compel arbitration. Geo-Tech’s answer—a
    12
    one-page document—asserts only a general denial and a request for costs and
    attorney’s fees. See Tex. R. Civ. P. 92. The record does not establish any
    attempt by Geo-Tech to seek disposition of Leggett’s breach of contract claim on
    its merits or otherwise.
    Furthermore, in its reply to Leggett’s response to the motion to compel,
    Geo-Tech represented that it had not propounded any discovery, and Leggett, as
    the party bearing the burden on the waiver issue, did not present evidence to the
    contrary. Also, an e-mail that appears in the record, sent by Leggett’s counsel to
    Geo-Tech’s counsel in May 2016, indicates that Geo-Tech had not responded to
    at least some of Leggett’s discovery requests at that time. On appeal, Geo-Tech
    acknowledges that it has propounded requests for disclosure, see Tex. R. Civ. P.
    194.2, but states that it has served no other requests for discovery.
    For all of these reasons, we cannot conclude that Geo-Tech substantially
    invoked the judicial process. See G.T. Leach Builders, 
    LLC, 458 S.W.3d at 511
    –
    12.
    With regard to prejudice, although Leggett emphasizes that Geo-Tech
    sought arbitration after the case was already set for trial, the record shows that
    Geo-Tech filed the motion to compel arbitration just a few days after Leggett’s
    counsel sent an e-mail stating that he was going to set the case for trial. Further,
    Leggett stated in his response to the motion to compel that the trial date was set
    for October 2016, which is five months after Geo-Tech sought arbitration.
    13
    Therefore, the record does not suggest that Geo-Tech waited until Leggett had
    spent significant resources preparing for trial before demanding arbitration.4
    In the trial court, Leggett argued that Geo-Tech’s delay in seeking
    arbitration before Leggett filed his original petition may have caused the loss of
    certain claims under a statute of limitation.     But Leggett did not reveal what
    claims he could have brought but had not.           Furthermore, although Leggett
    argued in the trial court that Geo-Tech “str[ung him] along with hollow promises
    as his rights fade[d], [and then sought to take] away his day in [c]ourt,” 5 Leggett
    did not provide any proof of such pre-litigation conduct. Furthermore, in the e-
    mail between counsel discussed above, Leggett’s counsel stated that arbitration
    did not “trouble” Leggett because “[a]ll breach of contract remedies, including
    recovery of [counsel’s] attorney’s fees, [were] available in arbitration.”
    4
    Leggett did not provide evidence concerning any money or time he spent
    in pursuing his breach of contract claim before Geo-Tech filed its motion to
    compel arbitration.
    5
    On appeal, Leggett states,
    More than five years ago, [Leggett] sought the services of . . . Geo-
    Tech for repair of the foundation of his home. But [Geo-Tech] failed
    to resolve these foundation problems. Over the next several years,
    Geo-Tech strung [Leggett] along, always promising they would be
    able to fix both the foundation problems for which they were
    originally hired [and] the damages they . . . caused in their faulty
    attempts at repair.
    After years of promises and failed repairs, [Leggett] filed suit.
    [Footnotes omitted.]
    14
    Thus, we cannot conclude that the record establishes Leggett’s prejudice
    from Geo-Tech’s delay in seeking arbitration after the parties engaged in pre-
    litigation disputes or after Leggett filed his original petition. See id.; Nw. Constr.
    
    Co., 248 S.W.3d at 848
    .
    For all these reasons, we cannot conclude that Leggett satisfied either of
    the requirements to defeat the strong presumption against a waiver of arbitration.
    See RSL 
    Funding, 499 S.W.3d at 430
    ; G.T. Leach Builders, 
    LLC, 458 S.W.3d at 511
    –12; Nw. Constr. 
    Co., 248 S.W.3d at 848
    .
    Conclusion
    Based on the reasons stated above, we conclude that the trial court
    abused its discretion by denying Geo-Tech’s motion to compel arbitration. See
    Tex. Civ. Prac. & Rem. Code Ann. §§ 171.001(a), .021(a); BBVA Compass Invs.
    
    Solutions, 456 S.W.3d at 717
    .       We sustain Geo-Tech’s sole issue.         Having
    sustained Geo-Tech’s sole issue, we reverse the trial court’s order denying Geo-
    Tech’s motion to compel arbitration, and we remand this cause to the trial court
    for further proceedings consistent with this opinion.
    /s/ Terrie Livingston
    TERRIE LIVINGSTON
    CHIEF JUSTICE
    PANEL: LIVINGSTON, C.J.; WALKER and MEIER, JJ.
    DELIVERED: March 30, 2017
    15