TXU Portfolio Management Company, L.P. N/K/A Luninant Energy Company, L.L.C. v. FPL Energy, LLC FPL Energy Pecos Wind I, LP FPL Energy Pecos Wind IIL ( 2016 )


Menu:
  • Affirmed in part; Reverse and Remand in part; and Opinion Filed August 18, 2016
    Court of Appeals
    S     In The
    Fifth District of Texas at Dallas
    No. 05-08-01584-CV
    TXU PORTFOLIO MANAGEMENT COMPANY, L.P. N/K/A LUMINANT ENERGY
    COMPANY, L.L.C., Appellant
    V.
    FPL ENERGY, LLC; FPL ENERGY PECOS WIND I, LP; FPL ENERGY PECOS WIND
    II, AND INDIAN MESA WIND FARM, L.P., Appellees
    On Appeal from the 116th Judicial District Court
    Dallas County, Texas
    Trial Court Cause No. 04-10314
    OPINION ON REMAND
    Before Justices Francis, Evans,1 and Whitehill2
    Opinion by Justice Whitehill
    This contract dispute between TXU Portfolio Management Company, L.P. n/k/a
    Luminant Energy Company, L.L.C. (TXUPM) and FPL Energy, LLC, FPL Energy Pecos Wind
    I, L.P., FPL Energy Pecos Wind II, L.P., and Indian Mesa Wind Farm, L.P. (Wind Farms) is
    before us on remand from the Supreme Court of Texas. The case concerns three contracts
    requiring the Wind Farms to supply TXUPM with annual quantities of wind generated electricity
    and related renewable energy credits (the Agreements). The Wind Farms, however, did not meet
    their delivery obligations.
    1
    The Honorable Justice David Evans succeeded the Honorable Justice Joseph B. Morris, a member of the original panel and author of the
    original opinion in this case, upon Justice Morris’s retirement.
    2
    The Honorable Justice Bill Whitehill succeeded the Honorable Justice Kerry P. FitzGerald, a member of the original panel, upon Justice
    FitzGerald’s retirement.
    The supreme court affirmed our previous holding that TXUPM was not responsible for
    ensuring transmission capacity under those Agreements, but concluded that the Agreements’
    liquidated damages provisions were unenforceable as a penalty and thus reversed our ruling that
    TXUPM was entitled to damages based on those provisions. FPL Energy, L.L.C. v. TXU
    Portfolio Mgmt. Co. L.P., 
    426 S.W.3d 59
    , 72–73 (Tex. 2014). The supreme court then remanded
    the case to us “to determine damages consistent with [its] opinion.” 
    Id. at 73.
    The parties
    provided supplemental briefs on the remaining damages issues.
    Our damages analysis turns on two questions the trial court submitted to the jury:
              Question 4 asked the jury to determine TXUPM’s market damages for failing to
    deliver “Renewable Energy,” which consists of both wind power generated
    electricity and its corresponding renewable energy credits; and
              Question 5 asked whether TXUPM covered for the electricity the Wind Farms
    failed to provide under the Agreements.
    Based on the “yes” answer to Question 5, the trial court ruled that TXUPM was
    precluded from recovering market price based damages. Therefore, the trial court disregarded
    the $8,900,000 answer to Question 4 and entered a take nothing judgment against TXUPM,
    which adduced no evidence of damages calculated on a cover basis. TXUPM argues that the
    trial court erred in doing so because the undisputed facts show that the Wind Farms’ defensive
    cover theory does not apply.
    For the reasons discussed below, we sustain TXUPM’s fourth point of error3 and hold
    that business and commerce code § 2.712(a) requires post-breach conduct taken for the purpose
    of effecting statutory cover, and, as a matter of law, TXUPM’s non-contractual, daily supply and
    demand balancing activities were not evidence of § 2.712(a) covering transactions. Accordingly,
    3
    We use the “point of error” nomenclature because that is what TXUPM used in its opening brief.
    –2–
    the trial court erred both by submitting Question 5 over TXUPM’s objection and by not
    disregarding the answer to that question as TXUPM requested.
    Because the trial court erroneously relied on the Question 5 answer to ignore the jury’s
    Question 4 market damages finding, and because no party challenged the jury’s Question 4
    answer in the trial court on legal or factual sufficiency grounds, TXUPM is entitled to recover
    the $8,900,000 the jury awarded. However, we reject TXUPM’s new argument on remand that
    the market damages award should be increased.
    We further conclude that, because TXUPM is entitled to market damages, the trial court
    erred by concluding that TXUPM was not entitled to retain the $3,075,000 it accessed under the
    letters of credit the Wind Farms provided to secure their performance under the Agreements.
    And TXUPM is entitled to recover its attorney’s fees because it is the prevailing party on its
    breach of contract claim.
    I. ISSUES
    We address only those issues preserved in the trial court, raised in the original briefs, and
    that remained after the supreme court opinion. Those issues are whether: (i) the trial court erred
    by submitting the cover question to the jury and refusing to disregard the corresponding answer;
    (ii) TXUPM should recover market value damages; (iii) TXUPM is entitled to retain the amounts
    collected under the letters of credit; and (iv) TXUPM is entitled to recover civil practice and
    remedies code Chapter 38 attorney’s fees.4
    4
    TXUPM acknowledges, and the Wind Farms agree, that, given the supreme court’s rulings, we need not consider the following issues
    previously raised: (1) the trial court’s denial of TXUPM’s trial amendment; (2) the admission of Dr. Baughman’s testimony; (3) the denial of the
    Wind Farms’ motion for JNOV and motion for new trial on their counterclaim; (4) the admission of Dr. Siddiqi’s testimony; and (5) the exclusion
    of evidence in support of the Wind Farms’ counterclaim. Although we granted the parties’ request to provide supplemental briefing on the
    remand issues, the parties did not request, nor did we grant, leave to raise new issues.
    –3–
    II. BACKGROUND
    A detailed recital of this case’s factual and procedural background is provided in our
    prior opinion. See TXU Portfolio Mgmt. Co., L.P. v. FPL Energy, LLC, 
    328 S.W.3d 580
    , 581–85
    (Tex. App.—Dallas 2010), aff’d in part, rev’d in part, 
    426 S.W.3d 59
    (Tex. 2014). Here, we
    limit our discussion to the matters needed to resolve the issues before us.
    TXUPM sued the Wind Farms alleging that they failed to deliver the contractually
    required minimum annual quantities of wind generated electric energy (electricity) and related
    renewable energy credits (RECs) due under the Agreements, and the trial court instructed the
    jury that the Wind Farms breached the Agreements as TXUPM alleged. The Wind Farms,
    however, contested TXUPM’s legal ability to recover market damages for those breaches by
    arguing that (i) market price damages under business and commerce code § 2.713(a) are not
    allowed if the buyer covered for the seller’s breaches and (ii) TXUPM covered for the Wind
    Farms’ annual deficiencies within the meaning of business and commerce code § 2.712(a) when
    it daily replaced from other sources any electricity the Wind Farms did not deliver as projected.5
    The Wind Farms’ argument was based on undisputed evidence of TXUPM’s real-time
    “balancing activities.” The parties agree that electricity cannot be stored and therefore, once
    generated, must be immediately transmitted to its destination. According to TXUPM, real-time
    balancing refers to the constant adjustments it makes to its electricity supply to ensure that it
    meets its demand for energy at every given moment, without regard to the Wind Farms’ annual
    deficiencies.
    At a pretrial hearing, the parties and the trial court discussed the competing damage
    theories and the Wind Farms’ argument that TXUPM had not produced in discovery, and
    5
    Section 2.712(a) provides: “After a breach within the preceding section the buyer may ‘cover’ by making in good faith and without
    unreasonable delay any reasonable purchase of or contract to purchase goods in substitution for those due from the seller.” TEX. BUS. & COM.
    CODE § 2.712(a).
    –4–
    therefore could not present at trial, evidence of its cover costs. The Wind Farms contended that
    the parties had a factual dispute regarding whether TXUPM’s conduct constituted cover that
    should be submitted to the jury. TXUPM, however, argued that cover did not apply because its
    daily balancing activities did not occur post-breach. The trial court then said that whether
    TXUPM covered was likely a fact question for the jury and that TXUPM would receive a take-
    nothing judgment if the jury answered that TXUPM had covered and TXUPM had no evidence
    of the costs to cover.
    Consistent with its prior position regarding cover, TXUPM at trial adduced evidence of
    only market damages measured at the time TXUPM learned of the breaches. At the close of
    evidence, the trial court submitted the two damages related questions at issue. Question 4
    instructed the jury to answer a market price damages question for combined electricity and RECs
    (together, Renewable Energy) independent of its answer to the cover question:
    What sum of money, if any, if paid now in cash, would fairly and reasonably
    compensate [TXUPM] for its damages, if any, that resulted from the Wind Farm’s
    [sic] failure to pay [TXUPM] for the Renewable Energy not provided?
    . . . [T]he amount of damages that you determine must be based on the market
    value of the Renewable Energy the Wind Farms failed to provide to [TXUPM],
    and this market value should be the market value as of the time that [TXUPM]
    learned of the Wind Farms’ failure to comply with the Agreements.
    Consider the following element of damages, if any, and none other.
    The difference between the market value of the Renewable Energy not delivered
    and the contract price for the Renewable Energy provided in the Agreements.
    In response, the jury found $8,900,000 in damages.
    At the Wind Farms’ request, the trial court also submitted Question 5 to the jury, which
    asked: “Did [TXUPM] ‘cover’ for the electricity that the Wind Farms failed to provide under the
    Agreements?”      In connection with that question, the trial court instructed the jurors that,
    “‘Cover’ means purchasing or producing electricity as a substitute for the electricity promised
    but not delivered under the Agreements.” Because the charge defined “Agreements” to be the
    –5–
    three contracts at issue, the jury was required to answer this question in light of the Agreements’
    terms.
    TXUPM objected to submitting Question 5 concerning the Wind Farms’ defensive cover
    theory, arguing that there was no evidence of cover and the question was a comment on the
    weight of the evidence. For support, TXUPM directed the trial court to our sister court’s holding
    in Jon-T Farms, Inc. v. Goodpasture, Inc., 
    554 S.W.2d 743
    , 750 (Tex. Civ. App.—Amarillo
    1977, writ ref’d n.r.e.), disapproved on other grounds by McKinley v. Drozd, 
    685 S.W.2d 7
    , 10–
    11 (Tex. 1985), which we discuss below. TXUPM, however, did not object to that instruction
    for not including § 2.712(a)’s “After a breach” language.6 The trial court overruled TXUPM’s
    objections and submitted the question to the jury, which found that TXUPM had covered the
    Wind Farms’ failure to provide the electricity due under the Agreements.
    Following the verdict, TXUPM moved the trial court to disregard the Question 5 answer
    and to enter judgment based on the $8,900,000 Question 4 damages answer. To that end,
    TXUPM argued that Question 5 should not have been submitted since there was no evidence of
    post-breach replacement electricity purchases.                              TXUPM, however, did not challenge the
    Question 4 answer under legal or factual sufficiency grounds as being too low. The trial court
    denied TXUPM’s motion.
    Conversely, the Wind Farms moved the trial court to enter judgment that TXUPM take
    nothing based on the Question 5 answer. The Wind Farms, however, did not alternatively ask
    the trial court to disregard Question 4 based on legally insufficient evidence to support the
    $8,900,000 answer to that question. Nor did they ask the trial court to grant a new trial because
    the evidence was factually insufficient to support that answer.
    6
    TXUPM objected to the instruction on the basis that the instruction (and the question) should refer to renewable energy instead of just
    electricity. It did not otherwise object to the instruction’s content.
    –6–
    Based on the jury’s cover finding, the trial court entered judgment that TXUPM take
    nothing on its breach of contract claims. The trial court reasoned that the jury’s cover finding
    precluded TXUPM from recovering the damages the jury found because that award was based on
    an incorrect market price damages measure and there was no evidence of the correct damages
    measure (cover costs).7 Consequently, the trial court also declared that TXUPM had to return the
    $3,075,000 TXUPM accessed as the beneficiary of letters of credit that the Wind Farms posted
    as security for payments owed to TXUPM under the Agreements. The trial court thus entered
    judgment that TXUPM take nothing, and denied both parties’ request for attorney’s fees under
    the declaratory judgment statute.
    TXUPM timely appealed. As noted above, we reversed and rendered judgment for
    TXUPM based on the Agreements’ liquidated damages provisions. The supreme court affirmed
    in part but reversed our liquidated damages decision, remanding to us the damages issues we
    discuss below.
    III. ANALYSIS
    A.          Controlling Facts
    The controlling facts are few and straightforward:
         Electricity is a fungible, non-segregable product.
         The Agreements required the Wind Farms to deliver specific minimum annual
    quantities of electricity.
         The Wind Farms failed to meet their annual electricity quotas for the years in
    question.
    7
    The trial court had previously held as a matter of law that TXUPM could not recover liquidated damages, which constituted a penalty.
    –7–
       Generated electricity cannot be stored for future use. Thus, TXUPM must
    simultaneously match the amount of electricity its customers demand with the
    amount of electricity its suppliers provide.
       TXUPM daily balanced its customer demands with electricity it acquired from
    its sources, including electricity it acquired from the Wind Farms.
       The Agreements required the Wind Farms to provide TXUPM on a daily basis
    a document projecting the amount of electricity that the Wind Farm would
    deliver to TXUPM the next day.
       But no Agreement contractually required a Wind Farm to deliver electricity
    according to its prior day’s estimate. That is, no Wind Farm ever had a
    contractual duty to deliver its daily projection amount, and thus no Wind Farm
    ever breached its Agreement by failing to meet its prior day’s estimate.
       TXUPM never made a post-year-end electricity purchase to replace electricity
    that a Wind Farm did not deliver during the prior year.
    B.     TXUPM’s Fourth Point of Error: Did the trial court err by (i) submitting Question
    5, (ii) not disregarding the jury’s answer to Question 5, and (iii) not entering
    judgment based on the Question 4 answer?
    1.      Introduction
    In light of the dissenting opinion’s analysis, we begin by discussing the relationship
    between error preservation and standard of review principles as concerns TXUPM’s fourth point
    of error, which presented the following issue:
    ISSUE PRESENTED: Did the trial court err in: 1) submitting to the jury the
    question of whether TXUPM’s undisputed continuous “balancing” of energy
    supplies to energy demands constituted cover as a matter of law; 2) refusing to
    disregard the jury’s incorrect answer to that legal question; and 3) voiding the
    jury’s award of actual damages to TXUPM on the ground that TXUPM failed to
    submit evidence of “cover” damages when, in fact, TXUPM did not cover as a
    matter of law?
    –8–
    Under that point of error, TXUPM argues that the undisputed facts established that its
    daily balancing activities as a matter of law were not covering activities within the meaning of
    business and commerce code § 2.712(a) because (i) that statute’s words “After a breach” mean
    that, “Cover is a remedy available to a buyer that necessarily first requires the seller’s breach of
    contract[,]” and (ii) “Courts hold that a buyer’s purchases to meet its own commitments that
    occur before the seller’s breach are not cover.”
    As we understand it, TXUPM’s position is that as a matter of law cover does not apply
    here because the undisputed facts establish that it did not make any post-breach electricity
    purchases to replace the electricity that the Wind Farms failed to provide as their Agreements
    required.   Therefore, the argument goes, whether the Wind Farms’ defensive cover theory
    applied was a pure question of law for the trial court to decide and should not have been
    submitted to the jury. And, according to TXUPM, had the trial court decided that legal question
    correctly, it should have entered judgment for TXUPM based on the $8,900,000 answer to
    Question 4. Because the facts regarding the Wind Farms’ performance and TXUPM’s balancing
    activities are undisputed, the key to TXUPM’s argument, and the disposition of this point of
    error, is whether, as a matter of statutory construction, the words “After a breach” in § 2.712(a)
    constitute an element of the cover remedy.
    Thus, regardless of the preservation method TXUPM asserted in the trial court, be it an
    objection that Question 5 should not be submitted or that the jury’s answer should be
    disregarded, its legal argument comes to us in the context of a no evidence scenario. Therefore,
    before we can address the merits of TXUPM’s fourth point of error we must first determine
    whether and, if so, how it preserved those arguments in the trial court because the answer to
    those questions determines the legal framework against which a “no evidence” standard of
    review applies.
    –9–
    Here, the standard of review framework is intertwined with the statutory construction
    issue regarding § 2.712(a)’s “After a breach” words. If those words constitute an element of the
    Wind Farms’ defensive cover theory that were omitted from the charge and TXUPM preserved
    its statutory construction argument in the trial court, the no evidence standard of review is
    performed under Rule 279’s omitted element framework. But, if TXUPM did not preserve its
    statutory construction argument, then the no evidence review would, as the dissent posits, be
    performed against the question and instruction as submitted. Accordingly, our first step requires
    us to first decide the nature and extent of TXUPM’s trial court error preservation.
    2.      Error Preservation Under Appellate Procedure Rule 33.1
    Our ability to resolve substantive legal questions, like the statutory interpretation
    argument that TXUPM presents in this case, ordinarily turns on whether that argument was first
    preserved in the trial court. See TEX. R. APP. P. 33.1(a)(2) (error preservation is “a prerequisite
    to presenting a complaint for appellate review”).       Error preservation can occur in several
    different ways. See 
    id. 33.1(a)(1) (preservation
    can be accomplished by “request, objection, or
    motion”); see also TEX. R. CIV. P. 273–74, 276 (rules specific to jury charge error preservation);
    T.O. Stanley Boot Co., Inc. v. Bank of El Paso, 
    847 S.W.2d 218
    , 220 (Tex. 1992) (listing ways to
    preserve no evidence point). The common characteristic, however, is that the party seeking to
    preserve a legal argument for our review usually must invoke a procedure that apprises the trial
    court of the argument in a way that calls for the trial court to decide that issue. See TEX. R. APP.
    P. 33.1(a) (preservation requires either a ruling or a refusal to rule); Burbage v. Burbage, 
    447 S.W.3d 249
    , 257 (Tex. 2014) (“[T]he objection must apprise the trial court of the error alleged
    such that the court has the opportunity to correct the problem.”); In re S.H.V., 
    434 S.W.3d 792
    ,
    801 (Tex. App.—Dallas 2014, no pet.) (party must both “take proper action to make the trial
    judge aware of the complaint and obtain a ruling, either express or implied”).
    –10–
    Here, TXUPM presented its no evidence of cover argument to the trial court both by
    objecting to the submission of Question 5 and by later asking the trial court to disregard the
    answer to that question. For the following reasons, we conclude that TXUPM preserved its
    fourth point of error arguments for our review. See TEX. R. APP. P. 33.1(a)–(b).
    Had TXUPM moved for a directed verdict against the Wind Farms’ cover theory because
    there was no evidence of any post-breach replacement purchases, the language of Question 5’s
    instruction would not matter and it would be beyond debate that TXUPM preserved its case
    dispositive statutory construction argument. See First Nat’l Collection Bureau, Inc. v. Walker,
    
    348 S.W.3d 329
    , 337 (Tex. App.—Dallas 2011, pet. denied) (discussing legal sufficiency
    preservation in a jury trial). There is no logical difference between preserving the legal argument
    that way and doing so by objecting to an instruction for the same reason. In both instances, the
    challenging party apprises the trial court of the purported legal error in time for the trial court to
    correct it. In both instances, the challenge is that as a matter of controlling law there is no
    question for the jury to decide, not whether the jury is being given a technically correct question
    to decide.8 The same analysis and result also apply where, as here, the challenging party presents
    its legal argument in a motion to disregard the answer to that question.
    Accordingly, by objecting to the submission of Question 5 about whether it effected
    cover or by asking the trial court to disregard the answer to that question, TXUPM preserved its
    legal argument that § 2.712(a) requires post-breach conduct taken for the purpose of effecting
    cover before that remedy applies.
    8
    Whether a particular statutory remedy is available is a legal question for the court to decide. See Wal-Mart Stores, Inc. v. McKenzie, 
    997 S.W.2d 278
    , 280 (Tex. 1999).
    –11–
    3.       Osterberg v. Peca
    This is not a situation like Osterberg v. Peca where there was no prior objection to the
    question or any other basis for preserving the appellants’ legal argument to the trial court in the
    first instance. See 
    12 S.W.3d 31
    , 54–56 (Tex. 2000) (issue of correct statutory requirements not
    preserved because the issue was not presented to trial court by motion or charge objection).
    Specifically the relevant substantive issue in Osterberg was whether the election code’s
    campaign finance reporting requirements were met by substantial compliance with the applicable
    filing deadline. The jury found that the defendants did not file by the date specified in the
    charge.        The defendants, however, argued on appeal that the sufficiency of the evidence
    supporting that answer should be measured by a “substantial compliance” standard instead of a
    literal compliance standard.
    The supreme court affirmed the court of appeals’ decision to perform its evidentiary
    sufficiency analyses measured by the literal standard stated in the charge because, as the supreme
    court repeatedly observed, the defendants never raised their substantial compliance argument in
    the trial court:
    On appeal, the Osterbergs argued for the first time that they need only
    “substantially comply” with the Election Code’s expenditure reporting provisions,
    and they did so. They contended that because there was insufficient evidence to
    support the unrequested “substantial compliance” issue, the evidence was legally
    and factually insufficient to support the jury’s finding that they failed to report
    their expenditures.
    The court of appeals held that the Osterbergs waived their substantial compliance
    argument. The court explained:
    The Osterbergs never argued prior to, or during, trial that substantial
    compliance satisfies the filing requirements of Section 254.124. . . .
    ***
    The Osterbergs could instead be arguing that when a court submits a defective
    issue to the jury, an appellate court should review the sufficiency of the evidence
    against the question and instruction that the trial court should have submitted—
    not the one actually submitted—even if the defect was never brought to the
    –12–
    court’s attention and the question or instruction never requested. That assertion is
    misguided. Even if Peca [the plaintiff] had a burden of proof with regard to some
    substantial compliance standard—an issue we do not decide today—it is the
    court’s charge, not some other unidentified law, that measures the sufficiency of
    the evidence when the opposing party fails to object to the charge. [Citations
    omitted]. As we recently stated in Holland v. Wal–Mart Stores, Inc., 
    1 S.W.3d 91
             (1999), if the trial court has “to resolve a legal issue before the jury could properly
    perform its fact-finding role[,] . . . a party must lodge an objection in time for the
    trial court to make an appropriate ruling without having to order a new 
    trial.” 12 S.W.3d at 54-55
    (emphasis added); see State Dept. of Highways & Pub. Transp. v. Payne,
    
    838 S.W.2d 235
    , 241 (Tex. 1992) (“There should be but one test for determining if a party has
    preserved error in the jury charge, and that is whether the party made the trial court aware of the
    complaint, timely and plainly, and obtained a ruling.”).
    Here, TXUPM repeatedly apprised the trial court of TXUPM’s position. At a minimum,
    it did so when it objected to the charge. And it did so again when it moved to disregard the
    Question 5 answer. Because TXUPM told the trial court what TXUPM believed was the correct
    standard for applying the law to the undisputed facts, we conclude that it preserved its argument
    in the trial court.
    4.      Rule of Civil Procedure 279 and Omitted Elements
    Because TXUPM preserved its statutory construction argument, and assuming it is
    correct about what § 2.712(a) requires, Rule 279 would require us to perform a no evidence
    analysis compared to a deemed finding on that element which would support the trial court’s
    order.    See TEX. R. CIV. P. 279; Serv. Corp. Int’l v. Guerra, 
    348 S.W.3d 221
    , 228–29 (Tex.
    2011). Specifically, the supreme court’s Service Corp. opinion implicitly clarified the line of
    cases holding that evidentiary sufficiency is measured against the given charge if there is no
    objection to the question or instruction at issue:
    When an element of a claim is omitted from the jury charge without objection and
    no written findings are made by the trial court on that element then the omitted
    element is deemed to have been found by the court in such manner as to support
    the judgment. TEX. R. CIV. P. 279; In re J.F.C., 
    96 S.W.3d 256
    , 263 (Tex. 2002).
    –13–
    Here there was no objection to the charge on the basis that it omitted the element
    nor did the trial court make findings on it, so there is a deemed finding in support
    of the judgment. But just as with any other finding, there must be evidence to
    support a deemed finding. Thus, we next address whether legally sufficient
    evidence supports the finding here. See In re 
    J.F.C., 96 S.W.3d at 276
    ; Ramos v.
    Frito–Lay, Inc., 
    784 S.W.2d 667
    , 668 (Tex. 
    1990). 348 S.W.3d at 228
    –29.
    The supreme court so held despite the court of appeals’ express holding in that case that,
    “In the context of a jury trial, the sufficiency of the evidence is reviewed in light of the charge
    submitted if no objection is made to the charge.” Serv. Corp. Int’l v. Guerra, 
    348 S.W.3d 239
    ,
    245 (Tex. App.—Corpus Christi 2009), 
    rev’d, 348 S.W.3d at 228
    –29. It thus follows that the
    supreme court rejected the court of appeals’ “charge as given” rule for the express language in
    Rule 279 because the alleged legal error was otherwise preserved.9 See PopCap Games, Inc. v.
    MumboJumbo, LLC, 
    350 S.W.3d 699
    , 612–13 (Tex. App.—Dallas 2011, pet. denied); Alfia v.
    Overseas Serv. Haus, Inc., No. 05-11-01390-CV, 
    2013 WL 3477345
    , at *3–4 (Tex. App.—
    Dallas July 9, 2013, no pet.) (mem. op.).
    But here it is undisputed that TXUPM never made post-year-end replacement electricity
    purchases. Thus, the dispositive issue is whether § 2.712(a) imposes a post-breach purchase
    requirement as an element of proving § 2.712(a) cover. Accordingly, we address the threshold
    statutory construction question TXUPM preserved in the trial court and presented to us to decide.
    5.         The Applicable Statutes
    Given the undisputed facts, this becomes a statutory construction case. When construing
    a statute, we attempt to ascertain and effectuate the legislature’s intent. City of San Antonio v.
    City of Boerne, 
    111 S.W.3d 22
    , 25 (Tex. 2003). We start with the plain and ordinary meaning of
    the statute’s words. 
    Id. If a
    statute is unambiguous, we generally enforce it according to its
    9
    We note that the appellate briefs reflect that Service Corp. moved for a directed verdict and a JNOV on legal and factual sufficiency
    grounds.
    –14–
    plain meaning. 
    Id. We read
    the statute as a whole and interpret it so as to give effect to every
    part. Id.; see also Phillips v. Bramlett, 
    288 S.W.3d 876
    , 880 (Tex. 2009) (“We further try to give
    effect to all the words of a statute, treating none of its language as surplusage when reasonably
    possible.”).
    Here, it is undisputed that the Agreements required the Wind Farms to deliver annual
    quantities of electricity as determined by a post-year-end analysis.         Moreover, electricity’s
    fungible and ephemeral nature made it impossible for TXUPM to replace previously non-
    delivered electricity with substitute electricity days, weeks, or months later.
    Accordingly, as we explain below, unambiguous statutory language compels the result
    that TXUPM’s pre-breach balancing acquisitions as a matter of law could not be evidence of
    covering transactions that would bar TXUPM from pursuing a market damages theory. That is,
    any electricity TXUPM acquired from other sources to ensure its pre-breach ability to meet its
    daily customer demands cannot be considered evidence of a cover purchase because the
    balancing transactions occurred before there was a contract breach to be remedied. See TEX.
    BUS. & COM. CODE §§ 2.711(a), 2.712(a).
    Specifically, the cover remedy is available to an aggrieved buyer who, after the seller
    breaches the contract by failing to deliver goods as required, in good faith reasonably purchases
    goods to substitute for those the seller failed to deliver:
    After a breach within the preceding section the buyer may “cover” by making in
    good faith and without unreasonable delay any reasonable purchase of or contract
    to purchase goods in substitution for those due from the seller.
    
    Id. § 2.712(a)
    (emphasis added).
    The “preceding section” is § 2.711, captioned “Buyer’s Remedies in General; . . . .” As
    its caption suggests, § 2.711 states the remedies generally available to a buyer when the seller
    breaches its contract by failing to deliver a contractually required quantity of goods.          
    Id. –15– §
    2.711(a). A buyer so situated may choose between effecting cover under § 2.712 or recovering
    market damages under § 2.713:
    Where the seller fails to make delivery . . . the buyer may . . . in addition to
    recovering so much of the price as has been paid (1) “cover” and have damages
    under the next section [§ 2.712] as to all the goods affected whether or not they
    have been identified to the contract; or (2) recover damages for non-delivery as
    provided for in this chapter (Section 2.713).
    
    Id. § 2.711(a)
    (emphasis added).
    Accordingly, cover “is not a mandatory remedy for the buyer.” 
    Id. § 2.712
    cmt. 3. That
    is, an aggrieved buyer need not minimize its damages by “covering” and not doing so does not
    bar it from pursuing a market price damages theory:
    Under § 2.712(c), upon seller’s breach the buyer is not required to cover as a
    means of minimizing damages, and his failure to effect cover does not bar him
    from any other remedy. Thus, on seller’s breach a buyer is free to choose
    between damages based upon the difference between the contract price and the
    cost of cover under § 2.712, and damages for non-delivery, consisting of the
    difference between the market price at the time when the buyer learns of the
    breach and the contract price under § 2.713(a).
    Jon-T Farms, 
    Inc., 554 S.W.2d at 750
    .
    Thus, as a matter of unambiguous statutory language, a buyer aggrieved by a seller’s
    failure to deliver the contractually required quantity of goods may either effect cover or recover
    market damages. See TEX. BUS. & COM. CODE §§ 2.711(a), 2.712(a). Likewise, also as a matter
    of plain statutory language, a buyer may effect a cover remedy only “[a]fter a breach.” See 
    id. § 2.712(a).
    Because the statutory language is unambiguous and there is no applicable precedent from
    us or the supreme court, we could end our analysis of this legal question here.
    6.      Case law
    The parties have not presented, and we have not found, a case squarely on point. But
    Jon-T Farms, Inc. is close. In that case, the buyer (Goodpasture) and the seller (Jon-T) in
    –16–
    January contracted for the seller to deliver grain to the buyer in October and November of that
    same year. Unfortunately, a railcar shortage developed and by November 30th the seller had
    delivered only slightly more than 20% of its contractual requirement. The buyer, however,
    encouraged the seller to keep delivering, exercised its right to extend the delivery period, and
    even used its own trucks to help the seller make deliveries.
    But grain prices had increased after the parties created their contract, and the seller on
    December 10th sent the buyer a letter repudiating the contract by refusing to deliver more grain
    unless the buyer agreed to a price increase. The buyer, however, declined to do so and a week
    later sued the seller for § 2.713 market damages. In response, the seller (like the Wind Farms
    here) argued that the buyer could not recover market damages because (i) the buyer covered for
    the seller’s breaches by meeting the buyer’s customers’ demand with grain that the buyer had
    otherwise previously arranged for and (ii) having “covered” for the seller’s breaches, market
    price damages were no longer an available remedy.
    The case was tried to a jury, which found that the seller breached the contract and caused
    the buyer substantial market price damages. The trial court rejected the seller’s argument that
    the buyer had used its pre-breach arrangements to effect cover, thereby precluding a market price
    damages recovery, and entered judgment for the buyer accordingly.
    On appeal, the seller argued that (i) there was no evidence supporting the damages
    finding because the buyer had used its other grain sources to cover for the seller’s delivery
    breaches; (ii) the buyer did not proffer any evidence of its cover damages; and (iii) the alleged
    covering conduct precluded a market price damages recovery.
    Our sister court in Amarillo reviewed business and commerce code §§ 2.711–2.713 in
    detail, analyzed the buyer’s inventory management practices, and rejected the seller’s argument
    –17–
    because the buyer was not required to cover and there was no evidence that it made any post-
    breach purchases for the purpose of covering for the seller’s non-delivery breaches:
    The testimony of the plaintiff’s witnesses, Long and Truitt, was that Goodpasture
    normally bought sufficient grain in order to meet its contracts for sale. There is
    no evidence that in Goodpasture’s mode of operation it makes a specific purchase
    contract in order to meet the requirements of a specific sales contract. The
    company maintains “position” records as to its overall operation which disclose
    the total amount of grain it has contracted to sell and the total amount it has
    contracted to buy, and its “position” is maintained in order to fill its sales
    contracts. The contract entered into between Jon-T and Goodpasture cannot be
    said to have been entered into to fill any particular outstanding commitment. The
    grain purchased is commingled with other grain. Although in the overall
    operation Goodpasture may have bought some grain to compensate for the
    undelivered Jon-T grain to insure an adequate supply to meet its commitments,
    there is no testimony that Goodpasture went out and bought specific grain to
    make up for the specific amount of grain undelivered by Jon-T.
    In fact, this record reveals that Goodpasture filed its suit within a week after
    learning of Jon-T’s breach and, as was its right, elected to seek the difference
    between the contract and market price, together with incidental and consequential
    damages. Goodpasture was not required to cover and there is no evidence of
    Goodpasture’s purchase of grain for the purpose of cover during that 
    week. 554 S.W.2d at 750
    (emphasis added).
    In sum, the Amarillo court rejected the seller’s argument because the buyer’s pre-breach
    purchases made to ensure its ability to meet its own customers’ demands were no evidence of
    post-breach replacement purchases for the purpose of remedying the seller’s actual breach.
    The Jon-T facts are remarkably similar to ours except that, unlike generated electricity,
    (i) grain can be held in inventory and (ii) a specific lot can be segregated and delivered to a
    particular customer. And the Wind Farms argue that there was no testimony that the buyer
    (Goodpasture) bought specific grain to replace the grain that the seller (Jon-T) breached the
    contract by failing to deliver, whereas, here there was testimony that TXUPM’s daily balancing
    practice was to take the Wind Farms’ electricity first and then, if there was a shortfall from the
    Wind Farms’ daily estimate, acquire replacement electricity from other sources to settle the
    –18–
    difference. For several reasons, however, those distinctions and that argument do not suggest a
    different result here.
    One, that grain can be held in inventory, segregated, and delivered to a specific customer
    would present a more compelling argument that a purchase from a different source replaced a
    specific seller’s non-delivered grain. That difference is significant because the cover damages
    measure requires the buyer to match the replacement goods’ cost with the undelivered goods’
    contract price and to make additional adjustments related to specific matching transactions:
    The buyer may recover from the seller as damages the difference between the cost
    of cover and the contract price together with any incidental or consequential
    damages . . . but less expenses saved in consequence of the seller’s breach.
    TEX. BUS. & COM. CODE § 2.712(b). That calculus, however, would be extraordinarily difficult,
    if not impossible, where, as here, the breach occurs and is determined only after a full year of
    daily transactions, some of which were below and some of which were above the day-before
    projections, and the buyer has other supply sources simultaneously providing fungible and non-
    segregable goods.
    Two, Jon-T’s reference to “undelivered” goods is statutorily significant. Section 2.712(a)
    affords the cover remedy to compensate for a breach within § 2.711(a)’s scope. Section 2.711(a)
    in turn enumerates a buyer’s remedies, including cover, when “the seller fails to make a
    delivery.” 
    Id. § 2.711(a)
    . But not just any “non-delivery” will support the cover remedy.
    Instead, the non-delivery must first breach a contract. This principle is necessarily so because
    the code remedies apply only if there has first been a contractual failure to perform within the
    meaning of code subchapter E concerning “Performance” that produces a breach within the
    meaning of subchapter F concerning “Breach, Repudiation and Excuse.” That is, there is no
    statutory remedy unless there is a prior contract breach as statutorily defined.
    –19–
    Three, because the cover remedy is an alternative to market damages, its application
    requires an intentional decision to make a substitutionary purchase for the purpose of remedying
    a breach. That optional nature combined with § 2.713(a)’s requirement that the market contract
    price difference be measured “at the time when the buyer learned of the breach” means that the
    buyer must know of the breach and related quantity before it can decide on an informed basis
    between its cover and market price damages. See 
    id. § 2.713(a).
                                              Accordingly, the Amarillo
    court correctly focused on whether there was evidence of post-breach purchases made for the
    purpose of effecting cover as opposed to routine pre-breach purchases to meet operational
    needs.10 See Jon-T Farms, 
    Inc., 554 S.W.2d at 750
    . Thus, pre-breach balancing transactions for
    the purpose of meeting customer needs do not satisfy the statutory language or scheme.11
    Finally, we note that in another part of the charge in the present case, the trial court
    instructed the jury that the Wind Farms had breached the Agreements and the breach upon which
    TXUPM’s damages must be measured was the Wind Farms’ failure to pay TXUPM for their
    annual deficiencies. This implicitly recognizes that breach was not measured on an interim basis
    during a compliance year, but rather that performance was assessed on an annual basis.
    Therefore, we conclude that Question 5 should not have been submitted and once
    answered should have been disregarded. Thus, the trial court erred as a matter of law in both
    instances because that question was legally immaterial. See Spencer v. Eagle Star Ins. Co., 
    876 S.W.2d 154
    , 157 (Tex. 1994). We sustain the first part of TXUPM’s fourth point of error.
    10
    The seller also argued that certain grain purchases in the following spring were cover transactions, but the court rejected that argument
    because the court did “not find any evidence of such specific purchases for such alleged cover set out in the record.” Jon-T Farms, 
    Inc., 554 S.W.2d at 750
    . Thus, that holding as to those post-breach transactions reinforces the principle that specific post-breach purchases must be
    matched to specific breaching non-deliveries to be cover transactions.
    11
    The cases cited by the Wind Farms are not persuasive. Those cases involve anticipatory repudiation, which is not at issue here. See, e.g.,
    Dura-Wood Treating Co. v. Century Forest Indus., Inc., 
    675 F.2d 745
    , 748 (5th Cir. 1982) (seller advised buyer that it would not be able to honor
    its contractual obligation to sell); Commonwealth Edison Co. v. Allied Chem. Nuclear Prods., Inc., 
    684 F. Supp. 1434
    , 1437 (N.D. Ill. 1988) (fact
    issue concerning use of pre-existing contracts to cover after seller refused to provide uranium before the time of delivery claiming contract was
    void due to government action).
    –20–
    Furthermore, the trial court used the immaterial answer to Question 5 to disregard the
    jury’s answer to Question 4 in which the jury found that the Wind Farms breaches regarding
    electricity and RECs caused TXUPM to suffer $8,900,000 in market damages for failing to
    deliver Renewable Energy, which the Agreements define to include both electricity and
    Renewable Energy Credits (RECs). Doing so was harmful, and thus reversible, error if it
    probably caused the rendition of an improper judgment (or probably prevented the appellant
    from properly presenting its case on appeal). TEX. R. APP. P. 44.1(a).
    Because we conclude that the trial court should not have submitted Question 5 and should
    have disregarded the answer to it, we next consider whether TXUPM is entitled to recover the
    market damages the jury found in response to Question 4.
    C.     Should TXUPM recover market value damages, and if so, in what amount?
    1.      The Answer to Question 4
    Under § 2.713, the damages measure for a seller’s non-delivery is the difference between
    the market price at the time when the buyer learned of the breach and the contract price together
    with any incidental and consequential damages, but less expenses saved in consequence of the
    seller’s breach:
    Subject to the provisions of this chapter with respect to proof of market price
    (Section 2.723), the measure of damages for non-delivery or repudiation by the
    seller is the difference between the market price at the time when the buyer
    learned of the breach and the contract price together with any incidental and
    consequential damages provided in this chapter (Section 2.715), but less expenses
    saved in consequence of the seller’s breach.
    TEX. BUS. AND COM. CODE. § 2.713(a). The jury awarded TXUPM $8,900,000 in damages.
    The Wind Farms argue that there is no evidence to support market value damages
    because TXUPM’s expert, Manu Asthana, offered irrelevant and unreliable expert testimony.
    According to the Wind Farms, Ashthana’s models (i) do not measure the value of the Wind
    Farms’ electricity at the correct time, and (ii) rely on inapplicable and unreliable pricing reports.
    –21–
    This no evidence point, however, was not preserved for our review. A no evidence point
    is preserved through: (1) a motion for instructed verdict; (2) a motion for judgment
    notwithstanding the verdict; (3) an objection to the submission of the issue to the jury; (4) a
    motion to disregard the jury’s answer to a vital fact issue; or (5) a motion for new trial. T.O.
    Stanley Boot 
    Co., 847 S.W.2d at 220
    . Although the Wind Farms availed themselves of many of
    these procedural vehicles, every challenge to TXUPM’s market damages request rested solely on
    the ground that market damages were not available because TXUPM had covered.
    For example, the Wind Farms’ motion for directed verdict argued that Asthana’s damage
    models were not competent evidence solely because he failed to account for cover and market
    damages are unavailable to a party who covers. Likewise, when the Wind Farms objected to the
    jury charge, they complained that the charge did not state the appropriate damages measure
    because the appropriate measure was cover.        Furthermore, there was no legal or factual
    sufficiency challenge to the $8,900,000 finding when the Wind Farms moved for judgment. And
    there was no motion for new trial, JNOV, or to disregard on these grounds. Consequently, the
    jury’s finding that TXUPM suffered $8,900,000 in market damages is an unchallenged finding
    that sets a damages floor. See Carbona v. CH Med. Inc., 
    266 S.W.3d 675
    , 687 (Tex. App.—
    Dallas 2008, no pet.).
    On remand, the Wind Farms rely on § 1.305(a) for the premise that TXUPM should not
    recover the damages the jury awarded because TXUPM suffered no actual economic injury. See
    TEX. BUS. & COM. CODE § 1.305(a). This section provides:
    The remedies provided by this title must be liberally administered to the end that
    the aggrieved party may be put in as good a position as if the other party had fully
    performed, but neither consequential or special damages nor penal damages may
    be had . . . .
    –22–
    
    Id. Comment 1
    to this section states that “Compensatory damages are limited to compensation.”
    
    Id. cmt. 1.
    Thus, the Wind Farms contend that we should render a take-nothing judgment
    because TXUPM suffered no actual economic injury.
    This was not raised as an objection to Question 4, nor did the Wind Farms argue that the
    trial court should disregard the Question 4 answer for that reason. And the Wind Farms did not
    make that argument in their opening brief.12 Accordingly, that argument is not properly before
    us. See TEX. R. APP. P. 33.1, 38(f).
    Therefore, on this record, TXUPM is entitled to recover at least the $8,900,000 in market
    damages the jury found in Question 4. We thus sustain the first part of TXUPM’s fourth point of
    error concerning the recovery of $8,900,000 in market damages.
    2.        TXUPM’s Request for Increased Damages
    TXUPM’s remand brief argues that TXUPM’s market damages recovery should be
    increased. Specifically, TXUPM contends that the jury “plainly” discounted the $20,900,000
    damages it requested based on the Wind Farms’ expert’s testimony that damages should be
    reduced by $10,600,000 for lack of transmission capacity. Because this Court and the supreme
    court rejected the trial court’s conclusion that TXUPM was contractually obligated to provide
    transmission capacity, TXUPM maintains that it is “entitled to the full amount of market price
    damages, untainted by the district court’s erroneous transmission capacity holding.” To this end,
    TXUPM requests that we add $10,600,000 to the jury’s $8,900,000 finding, and render judgment
    for that amount. We decline to do so.
    In the court below, TXUPM’s motion for judgment asked the court to enter judgment
    based on the $8,900,000 award. Likewise, its brief in support of its motion for judgment prayed
    12
    The Wind Farms’ opening brief cited § 1.305 as supporting its argument that TXUPM could not recover market damages because it,
    according to the Wind Farms, elected to cover for the Wind Farms’ electricity shortages.
    –23–
    for an $8,900,000 judgment.                       TXUPM’s arguments in its initial appellate briefing were
    consistent with those requests.                     TXUPM, however, never asked the trial court to enter a
    $19,500,000 judgment, nor did it initially claim that the trial court erred in not doing so. Thus,
    there is no basis preserved for our doing so now. See TEX. R. APP. P. 33.1.13
    In addition, there is no basis for us to conclude as a matter of law that absent the trial
    court’s transmission capacity holding the jury would have awarded TXUPM $19,500,000 in
    damages. TXUPM’s expert presented nine damage models and the amount of damages was
    disputed. We cannot speculate about what the jury intended when reaching a particular verdict,
    which entering the verdict TXUPM now requests would require us to do. See Houston Med.
    Testing Servs. Inc., v. Mintzer, 
    417 S.W.3d 691
    , 696 (Tex. App.—Houston [14th Dist.] 2013, no
    pet.).
    TXUPM argues that an appellate court may increase a jury award when the higher
    amount is established as a matter of law. See, e.g., Hill v. Spencer & Son, Inc., 
    973 S.W.2d 772
    ,
    775–76 (Tex. App.—Texarkana 1998, no pet.) (appellate court may render judgment if no
    evidence supports the award and undisputed evidence conclusively established the amount as a
    matter of law). Here, however, there is no undisputed amount, and it is not established as a
    matter of law. We thus resolve the second part of TXUPM’s second issue against it.
    3.         Conclusion
    For the reasons previously stated, we conclude that:
    (i) effective cover under business and commerce code § 2.712(a) requires as an element
    that the buyer make an after the breach purchase or contract to purchase goods in substitution for
    those due from the seller;
    13
    TXUPM’s remand brief also argues that the law of the case doctrine applies to foreclose all challenges to its request for a judgment “in
    excess of $20 million.” We disagree. Neither this Court nor the supreme court decided any part of TXUPM’s claim for market damages, and the
    law of the case does not apply to legal issues that were not decided in prior appeals. See Grant Thornton LLP v. Suntrust Bank, 
    133 S.W.3d 342
    ,
    363 (Tex. App.—Dallas 2004, pet. denied).
    –24–
    (ii) resolution of TXUPM’s fourth point of error requires us to conduct a no evidence
    review to determine whether the trial court erred by submitting Question 5 to the jury or by
    denying TXUPM’s motion to disregard the answer to that Question;
    (iii) because the “after a breach” element was omitted from the Question 5 instruction
    without objection but TXUPM preserved its statutory construction argument, our no evidence
    review is conducted under Rule 279 measured against that missing element;
    (iv) the trial court instructed the jury that, “It has been established that the Wind Farms
    were deficient in providing the required minimum Annual Quantity of Renewable Energy for the
    years 2002, 2003, 2004 and 2005 and failed to comply with the Agreements by failing to pay
    [TXUPM] for this deficiency[;]”
    (v) no party challenged on appeal the legal or factual sufficiency of the evidence
    supporting that instruction;
    (vi) it is undisputed that there is no evidence that TXUPM made any post-breach
    purchases of electricity to substitute for electricity that the Wind Farms failed to deliver as
    contractually required;
    (vii) the trial court erred by submitting Question 5 and by denying TXUPM’s motion to
    disregard the answer to that Question;
    (viii) no party challenged on appeal the legal or factual sufficiency of the evidence
    supporting the Question 4 answer;
    (ix) the trial court erred by denying TXUPM’s motion to enter judgment based on the
    Question 4 answer; and
    (x) the trial court’s errors caused the rendition of an improper judgment.
    –25–
    Accordingly, we reverse the trial court’s judgment that TXUPM take nothing on its
    breach of contract claim and render judgment that TXUPM recover from the Wind Farms
    damages of $8,900,000.
    D.      TXUPM’s Fifth Point of Error: Is TXUPM entitled to retain the amounts collected
    under the letters of credit in partial satisfaction of the judgment?
    TXUPM’s fifth issue argues that it is entitled to retain the amounts collected under the
    Wind Farms’ letters of credit. We agree.
    The trial court declared that TXUPM was required to return the $3,075,000 proceeds
    from the Wind Farms’ letters of credit that were posted as security for the Wind Farms’
    performance under the Agreements. That ruling rested on the trial court’s holding that TXUPM
    was not entitled to recover damages. But we have concluded that TXUPM is entitled to recover
    market damages. Therefore, the trial court erred in its conclusion, and TXUPM is entitled to
    retain the letter of credit proceeds in partial satisfaction of the judgment. We sustain TXUPM’s
    fifth issue.
    E.      Is TXUPM entitled to recover attorney’s fees?
    The district court exercised its discretion under Chapter 37 to deny both parties’
    attorney’s fees and award costs to the Wind Farms. See TEX. CIV. PRAC. & REM. CODE § 37.009.
    Because neither party challenges that ruling, a request for Chapter 37 fees is not before us.
    But TXUPM’s motion for judgment on the verdict also argued that TXUPM was entitled
    to Chapter 38 attorney’s fees and TXUPM prayed for fees in its original briefing when it asked
    this Court to render judgment on the breach of contract claim. Thus, TXUPM argues that it is
    entitled to recover Chapter 38 attorney’s fees because it established that the Wind Farms
    breached the Agreements and it is the prevailing party entitled to damages. See TEX. CIV. PRAC.
    & REM. CODE § 38.001. We agree.
    –26–
    Civil practice and remedies code Chapter 38 allows a reasonable attorney’s fees recovery
    in breach of contract cases. 
    Id. To recover
    attorney’s fees under § 38.001, a party must prevail
    on the underlying claim and recover damages. Ventling v. Johnson, 
    466 S.W.3d 143
    , 154 (Tex.
    2015); Intercontinental Grp. P’ship v. KB Home Lone Star L.P., 
    295 S.W.3d 650
    , 653 (Tex.
    2009). An award of reasonable attorney’s fees is mandatory under this section if there is proof of
    the reasonableness of the fees. 
    Ventling, 466 S.W.3d at 154
    . A request in a prayer is sufficient
    to support an attorney’s fees award. See Tull v. Tull, 
    159 S.W.3d 758
    , 762 (Tex. App.—Dallas
    2005, no pet.) (“A general request for attorney’s fees in the prayer of the pleading is itself
    sufficient to authorize the award of attorney’s fees.”).
    We thus sustain TXUPM’s request for attorney’s fees. We reverse the trial court’s
    judgment awarding costs to the Wind Farms, render judgment that TXUPM is entitled to recover
    its Chapter 38 attorney’s fees, and remand the case to the trial court to determine the amount of
    such fees.14
    IV. DISPOSITION
    We affirm the trial court’s judgment that neither party is entitled to recover Chapter 37
    attorney’s fees.
    We reverse the trial court’s judgment that: (i) TXUPM take nothing on its breach of
    contract claim; (ii) the Wind Farms recover costs; and (iii) TXUPM return the funds accessed
    under the letters of credit.
    We render judgment that TXUPM recover from the Wind Farms damages of $8,900,000
    plus pre and post judgment interest and reasonable attorney’s fees, and we further render
    14
    The parties agreed on the record that attorney’s fees and supporting evidence would be submitted to the trial court for determination after
    the verdict. Although TXUPM’s brief requests rendition of judgment for fees in a specific amount, it does not cite any authority or provide any
    record references to support rendition. Accordingly, we leave the fees issue to the trial court on remand. See Delta Steel Bldgs. Co. v. Crow, 
    633 S.W.2d 343
    , 344 (Tex. App.—Dallas 1982, no writ) (remanding for determination of reasonable attorney’s fee).
    –27–
    judgment that TXUPM is entitled to retain the $3,075,000 it accessed under the letters of credit
    in partial satisfaction of that judgment.
    We remand to the trial court solely for the purpose of calculating pre and post judgment
    interest and to determine the amount of reasonable Chapter 38 attorney’s fees and costs TXUPM
    is entitled to recover.
    /Bill Whitehill/
    BILL WHITEHILL
    JUSTICE
    Evans, J., dissenting
    081584F.P05
    –28–
    S
    Court of Appeals
    Fifth District of Texas at Dallas
    JUDGMENT
    TXU PORTFOLIO MANAGEMENT                              On Appeal from the 116th Judicial District
    COMPANY, L.P. N/K/A LUMINANT                          Court, Dallas County, Texas
    ENERGY COMPANY, L.L.C., Appellant                     Trial Court Cause No. 04-10314.
    Opinion delivered by Justice Whitehill.
    No. 05-08-01584-CV          V.                        Justices Francis and Evans participating.
    FPL ENERGY, LLC; FPL ENERGY
    PECOS WIND I, LP; FPL ENERGY
    PECOS WIND II, and INDIAN MESA
    WIND FARM, L.P., Appellees
    In accordance with this Court’s opinion of this date, the judgment of the trial court that
    neither party is entitled to Chapter 37 attorney’s fees is AFFIRMED.
    The trial court’s judgment that appellees FPL ENERGY, LLC; FPL ENERGY PECOS
    WIND I, LP; FPL ENERGY PECOS WIND II, and INDIAN MESA WIND FARM, L.P.
    recover their costs and that appellant TXU PORTFOLIO MANAGEMENT COMPANY, L.P.
    N/K/A LUMINANT ENERGY COMPANY, L.L.C. take nothing on its breach of contract claim
    and return the funds accessed under the letters of credit is REVERSED.
    We RENDER judgment that appellant TXU PORTFOLIO MANAGEMENT
    COMPANY, L.P. N/K/A LUMINANT ENERGY COMPANY, L.L.C. recover from appellees
    FPL ENERGY, LLC; FPL ENERGY PECOS WIND I, LP; FPL ENERGY PECOS WIND II,
    and INDIAN MESA WIND FARM, L.P. actual damages of $8,900,000 plus pre and post
    judgment interest and reasonable attorney’s fees, and that it is entitled to retain the funds
    accessed under the letters of credit in partial satisfaction of that judgment. We REMAND to the
    trial court for a calculation of pre and post judgment interest and for determination of the amount
    of appellant TXU PORTFOLIO MANAGEMENT COMPANY, L.P. N/K/A LUMINANT
    ENERGY COMPANY, L.L.C’s reasonable attorney’s fees.
    –29–
    It is ORDERED that appellant TXU PORTFOLIO MANAGEMENT COMPANY, L.P. N/K/A
    LUMINANT ENERGY COMPANY, L.L.C recover its costs of this appeal from appellees FPL
    ENERGY, LLC; FPL ENERGY PECOS WIND I, LP; FPL ENERGY PECOS WIND II, and
    INDIAN MESA WIND FARM, L.P.
    Judgment entered August 18, 2016.
    –30–