Satterfield & Pontikes Construction, Inc. v. Texas Southern University, Jim McShan, and Greg Williams , 472 S.W.3d 426 ( 2015 )


Menu:
  • Opinion issued August 13, 2015
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-14-00596-CV
    ———————————
    SATTERFIELD & PONTIKES CONSTRUCTION, INC., Appellant
    V.
    TEXAS SOUTHERN UNIVERSITY, JIM MCSHAN, AND GREG
    WILLIAMS, Appellees
    On Appeal from the 334th District Court
    Harris County, Texas
    Trial Court Case No. 2014-12277
    OPINION
    Appellant, Satterfield & Pontikes Construction, Inc. (“S&P”), sued
    appellees, Texas Southern University (“TSU”), Jim McShan, and Greg Williams,
    for alleged inconsistencies in the administration of a competitive bidding process.
    The trial court granted TSU’s plea to the jurisdiction and dismissed all of S&P’s
    claims against TSU, McShan, and Williams. In two issues, S&P argues that the
    trial court erred (1) in granting TSU’s plea to the jurisdiction on immunity grounds
    and (2) in dismissing its claims against McShan and Williams in their official
    capacities.
    We affirm.
    Background
    In January 2014, TSU solicited bids for the construction of a student housing
    facility by issuing a Request for Competitive Sealed Proposals pursuant to Texas
    Education Code section 51.783. Five companies, including S&P and Pepper-
    Lawson Horizon International Group (“Pepper-Lawson”) provided sealed bids.
    After engaging in post-proposal discussions with Pepper-Lawson, TSU accepted
    Pepper-Lawson’s bid and executed a construction contract with that firm.
    S&P sent a protest letter to TSU complaining of deficiencies in TSU’s
    administration of the bidding process, and it attempted to obtain documents related
    to the bidding process from TSU. However, TSU proceeded with construction
    using Pepper-Lawson as its contractor.
    On March 7, 2014, S&P filed suit against TSU, Jim McShan, who is TSU’s
    Vice President of Finance and CFO, and Greg Williams, who is TSU’s Executive
    Director of Procurement Services. S&P alleged that TSU, McShan, and Williams,
    acting in their official capacities, violated various sections of the Government
    2
    Code and Education Code governing the solicitation and acceptance of competitive
    bids for construction projects. S&P asked the trial court to enter a declaratory
    judgment declaring that the contract between TSU and Pepper-Lawson was void
    and to order TSU to award the project to S&P. It also sought a temporary and
    permanent injunction preventing TSU from proceeding with construction until the
    project could be properly bid and awarded.
    The trial court conducted hearings on S&P’s application for a temporary
    injunction, but the court did not grant a temporary injunction, and work on the
    construction project proceeded.
    TSU subsequently filed an amended answer, asserting sovereign immunity
    as an affirmative defense and alleging that S&P lacked standing to pursue its
    claims. No amended answer was filed for McShan or Williams. TSU then filed a
    plea to the jurisdiction, asserting that S&P’s claims were barred by sovereign
    immunity, that S&P lacked standing to bring them, and that S&P failed to state a
    cause of action. McShan and Williams did not join TSU’s plea to the jurisdiction.
    S&P responded to the plea to the jurisdiction, arguing that TSU’s sovereign
    immunity was waived by Education Code sections 51.783(f) and 51.778(a) and
    that it had standing to pursue its claims.
    The trial court held a hearing and granted TSU’s plea to the jurisdiction,
    hodling that Education Code sections 51.783(f) and 51.778(a) do not constitute a
    3
    waiver of sovereign immunity. The trial court order dismissed all claims against
    all parties. This appeal followed.
    TSU’s Plea to the Jurisdiction
    In its first issue, S&P argues that the trial court erred in granting TSU’s plea
    to the jurisdiction. In this regard, it makes three arguments. First, S&P argues that
    TSU “did not meet its burden to prove that sovereign immunity bars S&P’s
    claims.” It asserts that TSU, as the defendant, “carries the initial burden to meet
    the summary-judgment proof standard for its assertion that the trial court lacks
    jurisdiction.” Second, S&P argues that TSU never established that governmental
    immunity applies to this case because S&P is seeking to void a contract between a
    state entity and a third party, rather than seeking to uphold a contract between itself
    and a state entity, and it contends that governmental entities are not immune to
    suits, like its own, that seek to void a contract, because such suits do not seek to
    control state action. Third, S&P argues that Education Code sections 51.778 and
    51.783 waived TSU’s governmental immunity. These arguments, however, are not
    supported by the law governing the assertion of governmental immunity.
    A.    Standard of Review
    A plea to the jurisdiction challenges the trial court’s subject-matter
    jurisdiction to hear the case. Bland Indep. Sch. Dist. v. Blue, 
    34 S.W.3d 547
    , 554
    (Tex. 2000). Subject-matter jurisdiction is essential to the authority of a court to
    4
    decide a case and is never presumed. Tex. Ass’n of Bus. v. Tex. Air Control Bd.,
    
    852 S.W.2d 440
    , 443–44 (Tex. 1993). The plaintiff has the burden to allege facts
    affirmatively demonstrating that the trial court has subject-matter jurisdiction. 
    Id. at 446;
    see also Weir Bros., Inc. v. Longview Econ. Dev. Corp., 
    373 S.W.3d 841
    ,
    847 (Tex. App.—Dallas 2012, no pet.) (“[The plaintiff] had the burden to plead
    facts that affirmatively demonstrate a waiver of governmental immunity and that
    the court has subject matter jurisdiction.”).
    We review a trial court’s ruling on a plea to the jurisdiction de novo. See
    Tex. Dep’t of Parks & Wildlife v. Miranda, 
    133 S.W.3d 217
    , 226 (Tex. 2004). In
    reviewing the ruling, an appellate court must determine whether facts have been
    alleged that affirmatively demonstrate jurisdiction in the trial court. City of Waco
    v. Lopez, 
    259 S.W.3d 147
    , 150 (Tex. 2008).
    When reviewing a trial court’s ruling on a jurisdictional plea, “we first look
    to the pleadings to determine if jurisdiction is proper, construing them liberally in
    favor of the plaintiffs and looking to the pleader’s intent,” and “we consider
    relevant evidence submitted by the parties when necessary to resolve the
    jurisdictional issues raised.” City of Waco v. Kirwan, 
    298 S.W.3d 618
    , 621–22
    (Tex. 2009). We do not adjudicate the substance of the case but instead determine
    whether a court has the power to reach the merits of the claim. Bland Indep. Sch.
    5
    
    Dist., 34 S.W.3d at 554
    ; Bd. of Trs. of Galveston Wharves v. O’Rourke, 
    405 S.W.3d 228
    , 233 (Tex. App.—Houston [1st Dist.] 2013, no pet.).
    If the pleadings affirmatively negate the existence of jurisdiction, the plea
    may be granted without allowing the plaintiff an opportunity to amend its
    pleadings. 
    Miranda, 133 S.W.3d at 227
    . If the relevant evidence is undisputed or
    fails to raise a fact issue as to jurisdiction, the trial court rules on the plea as a
    matter of law. 
    Id. at 228.
    B.    Burden of Proof
    As a preliminary matter, S&P argues that TSU had the burden of proof in
    showing that S&P’s claims should be dismissed. It is well-established, however,
    that a court’s determination of whether it has subject-matter jurisdiction begins
    with the pleadings, and the pleader has the initial burden of alleging facts that
    affirmatively demonstrate the court’s jurisdiction to hear the cause. 
    Miranda, 133 S.W.3d at 226
    ; Tex. Logos, L.P. v. Tex. Dep’t of Transp., 
    241 S.W.3d 105
    , 110
    (Tex. App.—Austin 2007, no pet.). Here, S&P sued TSU, which is undisputedly a
    governmental entity. As such, TSU is entitled to immunity from suit unless S&P,
    as the plaintiff, has established either that sovereign immunity does not apply or
    that the State consented to suit. See Tex. Natural Res. Comm’n v. IT-Davy, 
    74 S.W.3d 849
    , 855 (Tex. 2002).
    6
    C.    Dismissal of S&P’s Suit on Immunity Grounds
    First, S&P argues that the trial court erred in granting TSU’s plea to the
    jurisdiction on immunity grounds. It argues that TSU is not immune from its suit
    because its suit is not a “suit against the State” that attempts to control a state
    action and that, therefore, would implicate immunity principles. Second, it argues
    that TSU consented to suit. Third, it argues that even if failed to establish a waiver
    of TSU’s immunity from suit, it should be allowed an opportunity amend its
    pleadings.
    1.     Applicability of Immunity to “Suit Against the State”
    S&P argues that governmental immunity does not apply to its claims.
    “Governmental immunity is comprised of immunity from both suit and liability.”
    City of Dallas v. Albert, 
    354 S.W.3d 368
    , 373 (Tex. 2011). “Immunity from
    liability protects entities from judgments while immunity from suit deprives courts
    of jurisdiction over suits against entities unless the Legislature has expressly
    consented.” 
    Id. Sovereign immunity
    and its counterpart for political subdivisions
    of the State, governmental immunity, exist to protect the State and its political
    subdivisions from lawsuits and liability for money damages. Mission Consol.
    Indep. Sch. Dist. v. Garcia, 
    253 S.W.3d 653
    , 655 (Tex. 2008); Reata Constr. Corp.
    v. City of Dallas, 
    197 S.W.3d 371
    , 374 (Tex. 2006); Harris Cnty. v. Luna-
    Prudencio, 
    294 S.W.3d 690
    , 696 (Tex. App.—Houston [1st Dist.] 2009, no pet.).
    7
    In addition to barring suits for “money damages,” governmental immunity
    protects state entities against suits to “control state action.” 
    IT-Davy, 74 S.W.3d at 855
    –56; 
    O’Rourke, 405 S.W.3d at 234
    (holding that State is immune from suits to
    “control state action,” i.e. when trial court’s judgment would “effectively direct or
    control a government official in the exercise of his or her statutory authority”);
    Tex. Logos, 
    L.P., 241 S.W.3d at 118
    ; see also TEX. CIV. PRAC. & REM. CODE ANN.
    § 101.056 (Vernon 2011) (providing that waiver of immunity in Texas Tort Claims
    Act does not apply to governmental unit’s exercise of discretionary powers).
    Claims, including those for declaratory judgment, that seek “to establish a
    contract’s validity, to enforce performance under a contract, or to impose
    contractual liabilities are suits against the State” that attempt to “control[] state
    action,” and from which the state is therefore protected from liability by sovereign
    immunity. 
    IT-Davy, 74 S.W.3d at 855
    –56 (characterizing such claims as form of
    “controlling state action”); Tex. Logos, 
    L.P., 241 S.W.3d at 119
    (quoting 
    IT-Davy, 74 S.W.3d at 855
    -556).
    Texas courts have also “regarded these immunity principles as . . . barring
    suits to cancel or nullify a contract made for the benefit of the state.” Tex. Logos,
    
    L.P., 241 S.W.3d at 120
    (citing W.D. Haden Co. v. Dodgen, 
    308 S.W.2d 838
    , 840–
    41 (Tex. 1958)); see also Mustang Special Util. Dist. v. Providence Vill., 
    392 S.W.3d 311
    , 317 (Tex. App.—Fort Worth 2012, pet. denied) (rejecting argument
    8
    that suit to invalidate contract is not barred by immunity); Tex. S. Univ. v. State St.
    Bank & Trust Co., 
    212 S.W.3d 893
    , 908–09 (Tex. App.—Houston [1st Dist.] 2007,
    pet. denied) (holding that companies’ request for declaratory judgment on validity
    of contract, including party’s claim seeking declaration that contract was “void and
    unenforceable,” was barred by immunity principles). Finally, the Texas Supreme
    Court has repeatedly held that, absent a legislative waiver, governmental immunity
    bars suits seeking declaratory and injunctive relief against governmental entities, as
    S&P does here. See Tex. Dept. of Transp. v. Sefzik, 
    355 S.W.3d 618
    , 620 (Tex.
    2011); City of El Paso v. Heinrich, 
    284 S.W.3d 366
    , 380 (Tex. 2009); Tex. Logos,
    
    L.P., 241 S.W.3d at 115
    –16, 121.
    S&P argues, however, that its suit to invalidate the contract between TSU
    and Pepper-Lawson does not attempt “to control state action” but instead seeks to
    invalidate a contract, and, thus, TSU is not immune from suit. See 
    IT-Davy, 74 S.W.3d at 855
    –56.
    S&P relies on Texas Highway Commission v. Texas Association of Steel
    Importers to support its argument. See 
    372 S.W.2d 525
    (Tex. 1963). In that case,
    the Association of Steel Importers sought to invalidate an administrative order of
    the Texas Highway Commission that prohibited the award of contracts to entities
    that used foreign-sourced 
    materials. 372 S.W.2d at 526
    , 530. The court held that
    the proceeding seeking to nullify the administrative order “cannot be classed as a
    9
    suit against the state” because it was a proceeding to declare an agency order void
    as exceeding the agency’s statutory authority, not a suit complaining about a state
    entity’s exercise of its statutory authority to contract. See 
    id. at 530.
    Here, the
    opposite is the case. S&P has expressly brought suit against a state entity—TSU—
    seeking to declare a state-awarded contract invalid, to enjoin its enforcement after
    the fact, and to obtain damages from the state entity that awarded the contract to
    another bidder in the exercise of authority expressly granted the state entity by the
    Texas Education Code.
    In Texas Logos, the Austin Court of Appeals analyzed Steel Importers in
    circumstances similar to those of the present case. In Texas Logos, as here, a
    company (Texas Logos) sued a governmental entity (the Texas Department of
    Transportation, or “TxDOT”) seeking a declaratory judgment that the entity had
    exceeded its statutory authority by violating provisions regarding procurement of a
    contract with a third party (Media 
    Choice). 241 S.W.3d at 109
    , 111–13. As S&P
    does here, Texas Logos equated its claims with the claim in Steel Importers and
    argued that the precedent in Steel Importers compelled a conclusion that Texas
    Logos’ claim against TxDOT was not a “suit against the state” that implicated
    principles of governmental immunity because it did not seek to control state action
    but instead sought to void a contract. 
    Id. at 116,
    120.
    10
    The court in Texas Logos distinguished Steel Importers and held that Texas
    Logos’ claim against TxDOT did seek to control state action on a contract and
    therefore did implicate principles of governmental immunity. It cited the supreme
    court’s precedents in W.D. Haden Co. and IT-Davy regarding suits that seek to
    control state action and held that “[s]uits to nullify a contract made for the benefit
    of the state would likewise implicate sovereign immunity principles as currently
    articulated by the Texas Supreme Court.” 
    Id. at 120.
    The court added, “Even if
    sovereign immunity would not otherwise have barred Texas Logos’s declaratory
    claims if it had alleged ongoing statutory violations in the logo sign procurement
    and sought to make TxDOT comply with these statutes, Texas Logos alleges only
    past statutory violations, the ‘only plausible remedy’ for which is the invalidation
    of the contract. Such a remedy . . . implicates sovereign immunity and bars Texas
    Logos’s UDJA claims challenging the logo sign contract and procurement.” Tex.
    Logos, 
    L.P., 241 S.W.3d at 122
    –23.
    We conclude, as did the court in Texas Logos, that the reasoning from Steel
    Importers is not applicable here. S&P does not seek to declare an agency order
    void as unauthorized by law. It seeks a declaratory judgment voiding a specific
    contract between TSU, a governmental entity, and a third party, Pepper-Lawson,
    and it seeks a court order enjoining further work on the now-completed project and
    awarding the project to itself. Thus, S&P’s suit ultimately seeks to “nullify a
    11
    contract made for the benefit of the state” and “to compel non-performance of
    once-binding contractual obligations,” implicating governmental immunity
    principles. See W.D. 
    Haden, 308 S.W.2d at 841
    ; Providence 
    Vill., 392 S.W.3d at 317
    ; see also Tex. Logos, 
    L.P., 241 S.W.3d at 119
    –20 (relying on W.D. Haden and
    IT-Davy in concluding that “[s]uits to nullify a contract made for the benefit of the
    state . . . implicate sovereign immunity principles as currently articulated by the
    Texas Supreme Court”).
    Moreover, as in Texas Logos, S&P has alleged only past violations of the
    competitive bidding provisions in the Education Code on a now-completed
    contract, not the ongoing violations at issue in Steel Importers that would permit a
    remedy under the statute. 
    See 372 S.W.2d at 526
    , 530; Tex. Logos, 
    L.P., 241 S.W.3d at 122
    –23. Thus, the only plausible remedy would be invalidation of the
    contract between TSU and Pepper-Lawson—a remedy implicating principles of
    sovereign immunity. See Tex. Logos, 
    L.P., 241 S.W.3d at 122
    –23.
    We conclude that, contrary to S&P’s argument, its suit against TSU does
    implicate principles of governmental immunity, and, therefore, as the plaintiff, it
    was required to establish the state’s consent to its suit.
    2.     Consent to Suit
    Regardless of general principles of governmental immunity, “a party may
    establish consent to sue by referencing a legislative statute or a resolution granting
    12
    express legislative permission” to sue a governmental entity. Gen. Servs. Comm’n
    v. Little-Tex Insulation Co., 
    39 S.W.3d 591
    , 594 (Tex. 2001). Legislative consent
    to sue the State must be expressed in “clear and unambiguous language.” 
    Id. S&P argues
    that Education Code sections 51.778(a) and 51.783(f) waived
    TSU’s governmental immunity, thereby establishing consent to suit.
    Education Code section 51.778 addresses competitive bidding on contracts
    generally. It provides:
    Except as otherwise provided by this subchapter, all contracts for the
    construction or erection of permanent improvements at an institution
    are void unless made after advertising for bids for the contracts in a
    manner prescribed by the institution’s board, receiving sealed
    competitive bids, and awarding of the contract to the lowest
    responsible bidder by the board.
    TEX. EDUC. CODE ANN. § 51.778(a) (Vernon 2012). Section 51.778(b) provides
    that if a contract is awarded to someone other than the lowest bidder, the lowest
    bidder “shall be notified of the recommendation for award and shall be allowed an
    opportunity before the award to present evidence” of its responsibility.       
    Id. § 51.778(b).
    Education Code section 51.783—the specific provision under which TSU
    solicited bids for the construction here—provides the process for selecting
    contractors for construction services through competitive sealed proposals. 
    Id. § 51.783
    (Vernon 2012). Section 51.783 sets out the method for preparing a
    13
    request for competitive sealed proposals, the documents required, and notice
    requirements. 
    Id. Section 51.783(f)
    provides:
    The board [responsible for administering the selection process] shall
    receive, publicly open, and read aloud the names of the offerors and,
    if any are required to be stated, all prices stated in each proposal.
    Within 45 days after the date of opening the proposals the board shall
    evaluate and rank each proposal submitted in relation to the published
    selection criteria.
    
    Id. § 51.783
    (f). This section states that the school’s board “shall select the offeror
    that offers the best value for the institution based on the published selection criteria
    and on its ranking evaluation.” 
    Id. § 51.783
    (g). It allows the board to negotiate
    with the selected contractor and to “discuss . . . options for a scope or time
    modification and any price change associated with the modification.” 
    Id. Section 51.783
    further provides that “the board is not restricted to considering price alone
    but may consider any other factor stated in the selection criteria” in determining
    “best value” for the institution. 
    Id. § 51.783
    (g)–(h).
    TSU argues that section 51.778, the more general provision, does not apply
    here because its bidding was completed pursuant to section 51.783. However, this
    argument is immaterial as neither section 51.778 nor section 51.783 contains an
    express waiver of governmental immunity from a suit to declare a governmental
    entity’s contract void in “clear and unambiguous language,” and S&P points to no
    such language. See Little-Tex Insulation 
    Co., 39 S.W.3d at 594
    . Nor does S&P
    14
    refer to any other statute that serves to waive TSU’s governmental immunity in this
    case. Thus, S&P has not borne its burden of establishing TSU’s consent to suit on
    S&P’s claim. See 
    id. 3. Opportunity
    to Amend Pleadings
    Finally, S&P argues that, even if we conclude that it did not sufficiently
    establish a waiver of TSU’s immunity from suit, it should be allowed an
    opportunity to amend its pleadings. We disagree.
    S&P was never awarded a contract that TSU failed to perform; rather, it
    seeks to invalidate a third-party’s contract with TSU based on TSU’s alleged
    failure in the past to conduct the bidding process on the contract properly and to
    award S&P the construction contract in place of Pepper-Lawson in the manner
    S&P argues was required by the Education Code.
    A governmental entity’s exercise of statutory authority, such as the authority
    to take bids and award contracts, is an exercise of the entity’s discretionary powers.
    See 
    O’Rourke, 405 S.W.3d at 234
    –35 (holding that discretionary act is one that
    requires exercise of “personal deliberation, decision and judgment”); Tex. Logos,
    
    L.P., 241 S.W.3d at 118
    (holding that state entity is immune from suit deriving
    from its exercise of statutory authority to award sign contracts). As discussed
    above, the legislature has not waived immunity for suits that seek to control state
    action by dictating the exercise of discretionary powers, such as that at issue here.
    15
    See, e.g., TEX. CIV. PRAC. & REM. CODE ANN. § 101.056 (Vernon 2011) (providing
    that waiver of immunity in Texas Tort Claims Act does not apply to governmental
    unit’s exercise of discretionary powers); 
    IT-Davy, 74 S.W.3d at 855
    –56 (holding
    that sovereign immunity protects State from suits to “control state action”);
    
    O’Rourke, 405 S.W.3d at 234
    (holding that State is immune from suits to “control
    state action,” i.e. when trial court’s judgment would “effectively direct or control a
    government official in the exercise of his or her statutory authority”). Nor has
    S&P been able to point to any express waiver of immunity from such a suit.
    Moreover, even if S&P could have sued TSU on the contract under a theory
    it did not plead, S&P’s suit for injunctive and declaratory relief seeking to halt
    construction under the contract between TSU and Pepper-Lawson and to require
    TSU to repeat the bidding process in compliance with the competitive bidding
    procedures of the Education and Government Codes is long since moot.
    Construction had already begun under TSU’s contract with Pepper-Lawson long
    before the case reached this Court—and indeed, under the terms of the contract
    was to have been completed by the fall of 2014. The trial court denied S&P’s
    motion for injunctive relief halting performance of the construction contract, and
    S&P did not appeal that decision or otherwise pursue its claim for injunctive relief.
    Accordingly, any claim by S&P seeking to require TSU to re-bid the project is now
    moot.    See Williams v. Lara, 
    52 S.W.3d 171
    , 184 (Tex. 2001) (holding that
    16
    controversy becomes moot when “the issues presented are no longer ‘live’” and
    party loses standing to maintain its claims).
    Thus, the pleadings here affirmatively negate the existence of jurisdiction.
    See 
    Miranda, 133 S.W.3d at 238
    (holding that plea may be granted without
    allowing plaintiff opportunity to amend his pleadings if pleadings affirmatively
    negate existence of jurisdiction). We conclude that the trial court did not err in
    granting TSU’s plea to the jurisdiction. We overrule S&P’s first issue.
    Dismissal of S&P’s Claims against McShan and Williams
    In its second issue, S&P argues that the trial court erred in dismissing its
    claims against McShan and Williams.
    Generally, public officials sued in their official capacity—as McShan and
    Williams were here—are protected by the same sovereign or governmental
    immunity as the governmental unit they represent. See Tex. A&M Univ. Sys. v.
    Koseoglu, 
    233 S.W.3d 835
    , 843–44 (Tex. 2007). We have already held that the
    trial court correctly determined that it lacked jurisdiction to consider the merits of
    S&P’s claims against TSU on governmental immunity grounds. Thus, the trial
    court correctly determined that it lacked jurisdiction over McShan and Williams,
    who were sued in their official capacities. See 
    id. It does
    not matter that neither
    McShan nor Williams joined TSU’s plea to the jurisdiction nor otherwise moved to
    dismiss the claims against them, as the trial court is obliged to consider its
    17
    jurisdiction over claims even if not raised by the parties themselves. See In re
    United Servs. Auto. Ass’n, 
    307 S.W.3d 299
    , 306 (Tex. 2010) (holding that not only
    may issue of subject-matter jurisdiction be raised for first time on appeal by parties
    or court, but also “a court is obliged to ascertain that subject matter jurisdiction
    exists regardless of whether the parties questioned it”).
    S&P argues, however, that McShan and Williams’s acts were not merely the
    acts of public officials but were ultra vires acts that are an exception to
    governmental immunity. Under the ultra vires exception, immunity “does not
    preclude prospective injunctive remedies in official-capacity suits against
    government actors who violate statutory or constitutional provisions.” 
    Heinrich, 284 S.W.3d at 368
    –69. For a suit to fall within the ultra vires exception to
    governmental immunity, however, the suit “must not complain of a government
    officer’s exercise of discretion, but rather must allege, and ultimately prove, that
    the officer acted without legal authority or failed to perform a purely ministerial
    act.” 
    Id. at 372;
    O’Rourke, 405 S.W.3d at 234
    .
    S&P cannot establish the ultra vires exception here.              S&P cannot
    demonstrate that McShan and Williams acted without legal authority or failed to
    perform a purely ministerial act, rather than discretionary acts, as required for the
    ultra vires exception to apply. See 
    Heinrich, 284 S.W.3d at 372
    ; 
    O’Rourke, 405 S.W.3d at 234
    . S&P does not challenge TSU’s authority to solicit competitive bids
    18
    or to enter into construction contracts, nor does it allege that McShan and Williams
    were not authorized to conduct the biding process on behalf of TSU. Moreover, as
    the language of Education Code section 51.783 indicates, the determination of
    which bid to accept was not purely ministerial, but involved the exercise of
    discretion. See TEX. EDUC. CODE ANN. § 51.783(g)–(h) (providing that board must
    determine which bid represents “the best value for the institution based on the
    published selection criteria and on [the board’s] ranking evaluation” and that “the
    board is not restricted to considering price alone but may consider any other factor
    stated in the selection criteria” in making its determination); 
    O’Rourke, 405 S.W.3d at 234
    (“A discretionary act is one that requires the exercise of personal
    deliberation, decision and judgment.”); Junemann v. Harris Cnty., 
    84 S.W.3d 689
    ,
    693 (Tex. App.—Houston [1st Dist.] 2002, pet. denied) (“Actions that involve
    personal deliberation, decision, and judgment are discretionary; actions that require
    obedience to orders or the performance of a duty to which the actor has no choice,
    are ministerial.”).
    S&P argues that McShan and Williams did not have discretion to violate
    statutory provisions in implementing the bidding process, but this argument does
    not alter the fact that S&P is complaining about McShan’s and Williams’s exercise
    of their statutory discretion, for which they have immunity. See 
    Junemann, 84 S.W.3d at 693
    . Moreover, even if their actions could somehow be characterized as
    19
    ministerial and ultra vires, S&P is seeking retrospective relief in that it is asking for
    a declaratory judgment voiding the construction contract between TSU and
    Pepper-Lawson and awarding the construction contract to S&P itself. Any such
    retrospective relief is moot because of the advanced state of the construction on the
    project and is likewise barred by immunity. See 
    O’Rourke, 405 S.W.3d at 236
    n.2
    (holding that immunity applies to suits for injunctive relief “seeking imposition of
    an affirmative duty based on a past alleged actionable wrong”).
    These deficiencies in S&P’s pleadings cannot be cured by re-pleading. See
    
    Miranda, 133 S.W.3d at 227
    . Accordingly, we conclude that the trial court lacked
    subject-matter jurisdiction and did not err in dismissing S&P’s claims against
    McShan and Williams.        See 
    O’Rourke, 405 S.W.3d at 236
    n.2 (holding that
    immunity applies to suits for injunctive relief “seeking imposition of an affirmative
    duty based on a past alleged actionable wrong”); see also 
    Heinrich, 283 S.W.3d at 372
    (holding that immunity bars suit against state official for performance of
    discretionary act). We overrule S&P’s second issue.
    Conclusion
    We affirm the judgment of the trial court.
    Evelyn V. Keyes
    Justice
    Panel consists of Justices Keyes, Higley, and Brown.
    20