Granite Re Inc. v. Jay Mills Contracting Inc. ( 2015 )


Menu:
  •                          COURT OF APPEALS
    SECOND DISTRICT OF TEXAS
    FORT WORTH
    NO. 02-14-00357-CV
    GRANITE RE INC.                                                   APPELLANT
    V.
    JAY MILLS CONTRACTING INC.                                         APPELLEE
    ----------
    FROM THE 355TH DISTRICT COURT OF HOOD COUNTY
    TRIAL COURT NO. C2014036
    ----------
    MEMORANDUM OPINION 1 ON REHEARING
    ----------
    On April 10, 2015, appellant Granite Re Inc. (Granite) filed a motion for
    rehearing directed to our March 26, 2015 memorandum opinion and judgment.
    We deny the motion for rehearing but withdraw our prior opinion and judgment
    and substitute the following. See Tex. R. App. P. 49.3.
    1
    See Tex. R. App. P. 47.4.
    Granite appeals from the trial court’s order denying its motion to compel
    arbitration. We reverse the trial court’s order and remand for entry of an order
    compelling arbitration.
    I. BACKGROUND
    A. UNDERLYING AGREEMENTS
    The City of Granbury (the city) hired appellee Jay Mills Contracting, Inc.
    (JMC) to design and build a recreational boardwalk, boat dock, and fishing dock
    (the project). JMC then subcontracted with North American Marine Industries
    (NAMI) to perform the required work. JMC and NAMI entered into a “Blanket
    Agreement . . . between the Contractor and the Design/Build Subcontractor” (the
    blanket agreement). NAMI signed the blanket agreement on June 19, 2012, and
    JMC signed it on June 28, 2012. The blanket agreement included an arbitration
    clause, which provided that “all claims, disputes and controversies arising out of
    or relating to this Blanket Agreement and any Work Orders issued hereunder,
    including claims for extra work or changed conditions to or related to the
    Subcontract Work, shall be decided by arbitration.” The arbitration clause further
    stated that the “claimant” in any such arbitration proceeding could be either “the
    Contractor”—JMC—or the “Design/Build Subcontractor”—NAMI. Similarly, the
    blanket agreement provided that “[n]othing contained in this Blanket Agreement
    shall create a contractual relationship with, or create a cause of action in favor of,
    a third party which is neither the Contractor [JMC] nor Design/Build
    Subcontractor [NAMI]. [JMC] and [NAMI] agree that there are no third party
    2
    beneficiaries to the Blanket Agreement.” The blanket agreement further provided
    that NAMI would furnish a performance bond “in a form satisfactory to [JMC],” if
    JMC required such a bond.       It is uncontradicted that JMC required NAMI to
    furnish a performance bond.
    On the same dates that JMC and NAMI signed the blanket agreement,
    they also signed a “Work Order to Blanket Agreement” (the work order),
    incorporating the terms of the blanket agreement. The work order required NAMI
    to “provide bonding for the project for an additional $8,730.00.”                On
    June 21, 2012—before JMC signed the blanket agreement and work order but
    after NAMI did so—NAMI executed a performance bond, with Granite acting as
    the surety, in the amount of $291,719. 2 The performance bond stated that the
    work order between JMC and NAMI was “incorporated by reference and made a
    part of this [performance bond] for all purposes.”
    B. UNDERLYING DISPUTE 3
    JMC alleged that by October 2012, NAMI had abandoned the project,
    defaulted on the blanket agreement and work order, and “clos[ed] shop.” On
    2
    The performance bond was not a statutory performance bond because it
    was not executed by JMC as the city’s contractor. See Tex. Gov’t Code Ann.
    § 2253.021 (West Supp. 2014).
    3
    Our factual statements regarding the parties’ underlying dispute merely
    provide context for our discussion of the enforceability of the arbitration clause at
    issue and, of course, are not a comment on the merits of JMC’s claims, the
    merits of Granite’s defenses to those claims, or the legal import of the contracts
    between JMC and NAMI. Indeed, these issues are not before us in this appeal.
    3
    March 10, 2014, JMC sued NAMI and Granite, as NAMI’s surety, for breach of
    contract—the blanket agreement, the work order, and the performance bond—
    and sought damages arising from JMC’s efforts to complete the project and from
    JMC’s settlement of the city’s claims against it. JMC’s breach-of-contract claim
    against Granite solely encompassed Granite’s alleged breach of the performance
    bond, not any breach of the blanket agreement or the work order. At some point
    in 2014, NAMI filed for bankruptcy protection. After the bankruptcy court granted
    NAMI a discharge, JMC filed a notice of nonsuit as to its claims against NAMI,
    and the trial court entered a dismissal order as to those claims.            See
    Tex. R. Civ. P. 162; Epps v. Fowler, 
    351 S.W.3d 862
    , 868 (Tex. 2011).
    Granite then filed a motion to compel arbitration under the arbitration
    clause contained in the blanket agreement, arguing that the clause in the blanket
    agreement was incorporated into the performance bond through the work order.
    Thus, Granite argued that the performance bond incorporated the valid
    arbitration clause and that JMC’s claims fell within the scope of the clause.
    Granite’s argument was analogous to the children’s song “There Was an Old
    Lady Who Swallowed a Fly”:          Because the work order swallowed the
    performance bond and the blanket agreement swallowed the work order, the
    blanket agreement necessarily swallowed the performance bond contained in the
    work order. 4
    4
    This is shown by Granite’s argument that “[JMC] does have an
    enforceable arbitration agreement with [Granite] by virtue of the Bond, which
    4
    Granite also asserted that even if the arbitration clause in the blanket
    agreement could not be found to have been incorporated into the performance
    bond such that it applied to JMC’s claims against Granite, JMC’s claims were
    subject to the arbitration clause based on direct-benefits estoppel and JMC’s
    status as a third-party beneficiary of the performance bond. In other words,
    Granite argued that if the performance bond that Granite signed was not
    incorporated into the blanket agreement such that the performance bond did not
    contain an arbitration clause, Granite could enforce the clause against JMC
    under equitable-estoppel theories. 5 JMC responded that the performance bond
    did not contain an arbitration clause and that even if the performance bond were
    deemed to include an arbitration clause, its indemnity claim against Granite did
    not fall within the clause’s scope.
    After holding a nonevidentiary hearing, the trial court denied Granite’s
    motion to compel without entering findings of fact or conclusions of law. Granite
    filed an accelerated appeal and argues that the trial court erred by denying its
    motion because a valid arbitration clause existed that governed JMC’s claims.
    incorporates the Work Order, which incorporates the Blanket Agreement, which
    contains an arbitration agreement.”
    5
    At the hearing on Granite’s motion, Granite stated that its “argument is
    you can’t have the breach of contract claim under the performance bond, which
    incorporates the work order, which incorporates the blanket agreement, without
    taking out all subject to the arbitration. . . . The entire concept of incorporation by
    reference, the doctrine of equitable estoppel . . . all come into play when [JMC]
    can’t sue Granite based on the supposed default under a binding contract and
    escape the arbitration clause.”
    5
    See Tex. Civ. Prac. & Rem. Code Ann. § 51.016 (West 2015) (allowing
    interlocutory appeal from denial of motion to compel arbitration under the FAA).
    In its motion to compel, Granite asserted the Federal Arbitration Act
    applied “because the parties have engaged in interstate commerce.”            See
    9 U.S.C.A. § 2 (West 2009) (providing FAA governs contracts relating to
    interstate commerce). JMC did not object to the application of the FAA and the
    only argument raised in the trial court was that the FAA applied; thus, we apply
    the FAA.    See IKON Office Solutions, Inc. v. Eifert, 
    2 S.W.3d 688
    , 696
    (Tex. App.—Houston [14th Dist.] 1999, orig. proceeding & no pet.) (holding
    burden is on party seeking to compel arbitration to show FAA applies).
    II. STANDARD OF REVIEW, BURDENS, AND PRESUMPTIONS
    We review the trial court’s denial of a motion to compel arbitration for an
    abuse of discretion but we review de novo a trial court’s determination regarding
    whether a valid agreement to arbitrate exists. See In re Labatt Food Serv., L.P.,
    
    279 S.W.3d 640
    , 643 (Tex. 2009) (orig. proceeding); J.M. Davidson, Inc. v.
    Webster, 
    128 S.W.3d 223
    , 227 (Tex. 2003); Branch Law Firm, L.L.P. v. Osorn,
    
    447 S.W.3d 390
    , 395 (Tex. App.—Houston [14th Dist.] 2014, no pet.).           But
    because the trial court did not enter findings of fact or conclusions of law to
    explain its denial of the motion to compel, we must uphold the trial court’s
    decision if there is sufficient evidence to support the denial on any legal theory
    raised in the trial court.   Shamrock Foods Co. v. Munn & Assocs., Ltd.,
    
    392 S.W.3d 839
    , 844 (Tex. App.—Texarkana 2013, no pet.); In re Weeks
    6
    Marine, Inc., 
    242 S.W.3d 849
    , 854 (Tex. App.—Houston [14th Dist.] 2007, orig.
    proceeding).
    Because Granite sought to compel arbitration, it bore the burden to
    establish that (1) there is a valid arbitration agreement and (2) the claims raised
    fall within that agreement’s scope. In re Kellogg, Brown & Root, Inc., 166 SW.3d
    732, 737 (Tex. 2005) (orig. proceeding). The first inquiry is not subject to the
    FAA’s general presumption in favor of arbitration and is determined by the
    application of state-law principles of contract.     See In re Poly–Am., L.P.,
    
    262 S.W.3d 337
    , 347–48 (Tex. 2008) (orig. proceeding); 
    Kellogg, 166 S.W.3d at 737
    –38. Under such principles, we primarily must determine the parties’ intent
    as expressed in the terms of the contract.      Chrysler Ins. Co. v. Greenspoint
    Dodge of Houston, Inc., 
    297 S.W.3d 248
    , 252 (Tex. 2009). If Granite met its
    burden to show a valid arbitration agreement, then any doubts concerning the
    scope of the arbitrable issues—the second inquiry—should be resolved de novo
    in light of the policy and presumption favoring arbitration. Moses H. Cone Mem’l
    Hosp. v. Mercury Constr. Corp., 
    460 U.S. 1
    , 24–25, 
    103 S. Ct. 927
    , 941 (1983);
    accord Ellis v. Schlimmer, 
    337 S.W.3d 860
    , 861–62 (Tex. 2011); Prudential Sec.
    Inc. v. Marshall, 
    909 S.W.2d 896
    , 898–99 (Tex. 1995) (orig. proceeding); BBVA
    Compass Inv. Solutions, Inc. v. Brooks, No. 02-13-00047-CV, 
    2015 WL 595209
    ,
    at *4 (Tex. App.—Fort Worth Feb. 12, 2015, no pet. h.).
    7
    III. ENFORCEABILITY OF ARBITRATION CLAUSE
    A. EXISTENCE OF VALID ARBITRATION AGREEMENT
    Therefore, our first question is whether Granite showed, under Texas
    contract principles, that there was a valid agreement to arbitrate as between JMC
    and Granite.    Granite posited three theories by which it could enforce the
    arbitration clause in the blanket agreement against JMC: (1) incorporation by
    reference, (2) direct-benefits estoppel, and (3) third-party beneficiary.   See
    generally Rachal v. Reitz, 
    403 S.W.3d 840
    , 846 n.5 (Tex. 2013) (listing theories
    under which nonsignatories may be bound to or may enforce arbitration
    agreements). For the following reasons, we conclude that Granite carried its
    burden to show that there was a valid arbitration agreement as between JMC
    and Granite.
    As stated above, the arbitration clause Granite seeks to enforce was
    contained in the blanket agreement, not the performance bond.         Under the
    doctrine of incorporation by reference, however, where an agreement refers to a
    prior contract or instrument, the subsequent agreement may properly constitute
    part of the original contract.   Cappadonna Elec. Mgmt. v. Cameron Cnty.,
    
    180 S.W.3d 364
    , 371 (Tex. App.—Corpus Christi 2005, orig. proceeding & no
    pet.); Teal Constr. Co./Hillside Villas Ltd. v. Darren Casey Interests, Inc.,
    
    46 S.W.3d 417
    , 420 (Tex. App.—Austin 2001, pet. denied). The language in the
    subsequent agreement must plainly refer to the original contract or otherwise
    show that the parties intended for the subsequent agreement to become part of
    8
    or incorporated into the original contract. See One Beacon Ins. Co. v. Crowley
    Marine Servs., Inc., 
    648 F.3d 258
    , 267 (5th Cir. 2011); Owen v. Hendricks,
    
    433 S.W.2d 164
    , 167 (Tex. 1968); In re C & H News Co., 
    133 S.W.3d 642
    , 645
    (Tex. App.—Corpus Christi 2003, orig. proceeding); see also In re Enron Corp.
    Sec., Derivative & “ERISA” Litig., 
    391 F. Supp. 2d 541
    , 581 n.45 (S.D. Tex. 2005)
    (reciting Texas law regarding doctrine of incorporation by reference).
    Even so, the language in the work order clearly indicated that the parties to
    the bond—NAMI and Granite—intended to incorporate the terms of the work
    order and, necessarily, the blanket agreement into the performance bond.
    Additionally, the blanket agreement specified that each work order included the
    blanket agreement; thus, the work order automatically included the terms of the
    blanket agreement, including the arbitration clause. Indeed, federal courts have
    held that a surety must arbitrate disputes related to a performance bond where
    the performance bond specifically incorporated by reference a contract
    containing an arbitration clause. See U.S. Fid. & Guar. Co. v. W. Point Constr.
    Co., 
    837 F.2d 1507
    , 1508 (11th Cir. 1988); Exch. Mut. Ins. Co. v. Haskell Co.,
    
    742 F.2d 274
    , 276 (6th Cir. 1984); Developers Sur. & Indem. Co. v. Resurrection
    Baptist Church, 
    759 F. Supp. 2d 665
    , 669–71 (D. Md. 2010); see also Greta A.
    McMorris & Lawrence Lerner, To What Extent is a Surety Bound by Arbitration
    and Forum Selection Provisions in its Principal’s Contract?, 33 Constr.
    Lawyer 22, 26–27 (2013). Such is the case here.
    9
    Therefore, we conclude the performance bond contained a valid arbitration
    clause applicable to Granite and JMC through the doctrine of incorporation by
    reference. 6 Because we so conclude, we need not address Granite’s arguments
    that the arbitration clause was enforceable through the equitable doctrines of
    direct-benefits estoppel or third-party beneficiary.
    B. CLAIMS FALL WITHIN SCOPE OF AGREEMENT
    Although Granite met its burden to show that the arbitration clause was
    valid as between Granite and JMC through incorporation by reference, it must
    also establish that JMC’s breach-of-contract claims against it fell within the scope
    of the arbitration clause and, if so, whether an exception removes JMC’s claims
    from arbitration. See 
    Ellis, 337 S.W.3d at 861
    –62. Because Granite established
    that a valid arbitration clause between it and JMC existed, we now indulge a
    strong presumption in favor of arbitration.       See 
    id. at 862;
    J.M. 
    Davidson, 128 S.W.3d at 227
    .      Necessarily, we must broadly interpret the scope of an
    arbitration clause in light of the federal policy favoring arbitration. In re NEXT
    Fin. Grp., Inc., 
    271 S.W.3d 263
    , 267 (Tex. 2008) (orig. proceeding). But when
    exceptions to the arbitration clause are raised, we construe the exceptions
    narrowly in light of the federal policy favoring arbitration and disfavoring broad
    interpretations of exceptions. 
    Id. This is
    a question of law that we review de
    6
    Although the arbitration clause limits who may be a “claimant” in any
    arbitration proceeding to NAMI or JMC, JMC is the claimant because it brought
    claims against Granite.
    10
    novo and that allows consideration of the terms of the arbitration clause and the
    factual allegations pertinent to the claim. In re FirstMerit Bank, N.A., 
    52 S.W.3d 749
    , 754 (Tex. 2001) (orig. proceeding); Associated Glass, Ltd. v. Eye Ten Oaks
    Invs., Ltd., 
    147 S.W.3d 507
    , 512 (Tex. App.—San Antonio 2004, orig. proceeding
    & no pet.).
    The arbitration clause provided that “all claims, disputes and controversies
    arising out of or relating to this Blanket Agreement and any Work Orders issued
    hereunder . . . shall be decided by arbitration.”     The clause excepted from
    arbitration “a claim for contribution or indemnity asserted by [JMC] in a suit
    against a party with whom [JMC] does not have an enforceable arbitration
    agreement” (the exemption provision). In its petition against NAMI and Granite,
    JMC alleged that Granite breached the performance bond “by refusing and failing
    to remedy the defaults of [NAMI under the blanket agreement and work
    order] . . . and failing to pay [JMC] for the portion of [NAMI’s] work [that JMC]
    completed employing such subcontractors and laborers, and furnishing such
    materials as [JMC] deemed necessary.”        In short, JMC argued that because
    NAMI breached the blanket agreement and the work order, Granite’s obligations
    under the performance bond were triggered. JMC pleaded for specific damages
    in the amount of $109,698.13, representing the amount JMC alleged it paid the
    city to settle the city’s claims against JMC based on NAMI’s alleged default and
    JMC’s attorneys’ fees defending against the city’s claims.
    11
    JMC’s breach-of-contract claim against Granite clearly relates to NAMI’s
    alleged failure to fully perform under the blanket agreement and work order,
    which triggered Granite’s obligations under the performance bond.                In other
    words, JMC could not pursue its breach-of-contract claim without reference to
    NAMI’s performance (or lack of performance) under the blanket agreement and
    work order. JMC’s breach-of-contract claim against Granite, therefore, fell within
    the scope of the clause.       See U.S. Sur. Co. v. Hanover R.S. Ltd. P’ship,
    
    543 F. Supp. 2d 492
    , 495–96 (W.D.N.C. 2008); In re Rushing, 
    443 B.R. 85
    , 95
    (Bankr. E.D. Tex. 2010); Cleveland Constr., Inc. v. Levco Constr., Inc.,
    
    359 S.W.3d 843
    , 854–55 (Tex. App.—Houston [1st Dist.] 2012, pet. dism’d);
    cf. Gloucester City Bd. of Educ. v. Am. Arbitration Ass’n, 
    755 A.2d 1256
    , 1262
    (N.J.   Super.   Ct.   App.   Div.   2000)     (holding   contractor’s   claim   against
    subcontractor’s statutory surety not subject to arbitration clause contained in
    construction contract and incorporated into performance bond because
    contractor’s claim did not involve performance of underlying construction contract
    but involved surety’s personal defenses arising from the provisions of the bond
    itself). See generally Pennzoil Exploration & Prod. Co. v. Ramco Energy Ltd.,
    
    139 F.3d 1061
    , 1067 (5th Cir. 1998) (“Broad arbitration clauses [governing
    disputes relating to the contract] are not limited to claims that literally ‘arise under
    the contract,’ but rather embrace all disputes between the parties having a
    significant relationship to the contract regardless of the label attached to the
    dispute.”).
    12
    JMC argues that its claim seeking indemnity is exempted from arbitration
    under the exemption provision. But there is an enforceable arbitration agreement
    as between JMC and Granite under the doctrine of incorporation by reference
    and because JMC’s claims fall with the broad scope of the arbitration clause.
    Therefore, the exception stated in the clause, interpreted narrowly in favor of
    arbitration, does not apply to JMC’s claims against Granite. See Choice Hotels
    Int’l, Inc. v. BSR Tropicana Resort, Inc., 
    252 F.3d 707
    , 712 (4th Cir. 2001)
    (holding breach-of-contract claim was not collection action such that claim was
    encompassed by exemption for collection actions contained in arbitration clause);
    cf. New York v. Oneida Indian Nation of N.Y., 
    90 F.3d 58
    , 62–64 (2d Cir. 1996)
    (holding claim clearly fell within exclusion to arbitration contained in clause;
    therefore, claim fell outside scope of arbitration clause and was not subject to
    arbitration). We conclude that JMC’s claim against Granite fell within the scope
    of the broad arbitration clause in the blanket agreement and was not included in
    the exemption provision.
    IV. CONCLUSION
    We conclude that a valid arbitration clause existed between JMC and
    Granite through the doctrine of incorporation by reference and that JMC’s claims
    against Granite fell within the scope of the clause. Accordingly, the arbitration
    clause was enforceable by Granite in JMC’s action against it. The trial court
    abused its discretion to conclude otherwise, and we sustain that portion of
    Granite’s first issue raising incorporation by reference. We need not address the
    13
    remaining portion of Granite’s first issue raising third-party beneficiary or
    Granite’s second issue raising direct-benefits estoppel. See Tex. R. App. P.
    47.1. Accordingly, we reverse the trial court’s order denying Granite’s motion to
    compel arbitration and remand to the trial court for entry of an order compelling
    the parties’ dispute to arbitration under the terms of the arbitration clause.
    See Tex. R. App. P. 43.2(d), 43.3(a).
    /s/ Lee Gabriel
    LEE GABRIEL
    JUSTICE
    PANEL: DAUPHINOT, GABRIEL, and SUDDERTH, JJ.
    DELIVERED: April 23, 2015
    14
    

Document Info

Docket Number: 02-14-00357-CV

Filed Date: 4/23/2015

Precedential Status: Precedential

Modified Date: 10/16/2015

Authorities (25)

United States Fidelity and Guaranty Company, a Corporation ... , 837 F.2d 1507 ( 1988 )

State of New York and George E. Pataki, as Governor of the ... , 90 F.3d 58 ( 1996 )

Exchange Mutual Insurance Company v. The Haskell Company, ... , 742 F.2d 274 ( 1984 )

Choice Hotels International, Incorporated v. Bsr Tropicana ... , 252 F.3d 707 ( 2001 )

pennzoil-exploration-and-production-company-pennzoil-international-inc , 139 F.3d 1061 ( 1998 )

Developers Surety & Indemnity Co. v. Resurrection Baptist ... , 759 F. Supp. 2d 665 ( 2010 )

In Re Poly-America, L.P. , 262 S.W.3d 337 ( 2008 )

In Re Firstmerit Bank, N.A. , 52 S.W.3d 749 ( 2001 )

In Re Labatt Food Service, L.P. , 279 S.W.3d 640 ( 2009 )

Chrysler Insurance Co. v. Greenspoint Dodge of Houston, Inc. , 297 S.W.3d 248 ( 2009 )

In Re NEXT Financial Group, Inc. , 271 S.W.3d 263 ( 2008 )

Gloucester City v. AM. ARBITRATION ASS'N. , 333 N.J. Super. 511 ( 2000 )

Moses H. Cone Memorial Hospital v. Mercury Construction ... , 103 S. Ct. 927 ( 1983 )

United States Surety Co. v. Hanover R.S. Ltd. Partnership , 543 F. Supp. 2d 492 ( 2008 )

Associated Glass, Ltd. v. Eye Ten Oaks Investments, Ltd. , 147 S.W.3d 507 ( 2004 )

Cappadonna Electrical Management v. Cameron County , 180 S.W.3d 364 ( 2005 )

Teal Construction Co. v. Darren Casey Interests, Inc. , 46 S.W.3d 417 ( 2001 )

Ellis v. Schlimmer , 337 S.W.3d 860 ( 2011 )

Prudential Securities Inc. v. Marshall , 909 S.W.2d 896 ( 1995 )

Owen v. Hendricks , 433 S.W.2d 164 ( 1968 )

View All Authorities »