National Oilwell Varco, L.P. v. Flowserve Corporation, Flowserve U.S., Inc., and Flowserve S. De R.L. De C v. ( 2015 )


Menu:
  • Opinion issued April 30, 2015
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-13-00388-CV
    ———————————
    NATIONAL OILWELL VARCO, L.P., Appellant
    V.
    FLOWSERVE CORPORATION, FLOWSERVE US INC., AND
    FLOWSERVE S. DE R.L. DE C.V., Appellees
    On Appeal from the 270th District Court
    Harris County, Texas
    Trial Court Case No. 2010-76473
    MEMORANDUM OPINION
    Flowserve Corporation, Flowserve US Inc., and Flowserve S. de R.L. de
    C.V. (collectively “Flowserve”) sued National Oilwell Varco, L.P. (“NOV”) for
    breach of contract and fraud after two motors that NOV sold to Flowserve for use
    in a client’s water treatment plant leaked oil. Flowserve sought to recover from
    NOV the money that it spent to acquire replacement motors. NOV contended that
    Flowserve rejected its motors not because they leaked oil, but because they were
    not designed to start on a lower voltage, which was a requirement that Flowserve’s
    client initially failed to disclose to Flowserve or NOV. The jury returned a verdict
    in favor of Flowserve on both theories, and the trial court entered judgment on the
    jury’s verdict for breach of contract. NOV appeals, arguing that the trial court
    erred in (1) refusing to submit instructions regarding NOV’s defenses and
    (2) denying NOV’s motions for new trial and judgment notwithstanding the
    verdict. We affirm.
    Background
    A.    The Corbalis Water Treatment Plant expansion project
    In 2002, the Fairfax County Water Authority in Herndon, Virginia,
    commenced an expansion project at its Corbalis Water Treatment Plant. The
    project was significant; the value of Fairfax’s contract with its general contractor,
    Pizzagalli Construction Company, exceeded $160 million.
    Among other things, the Corbalis project required the installation of two
    large pumps.     Pizzagalli contracted with Flowserve to supply the pumps.
    Flowserve, in turn, contracted to purchase from NOV two vertical synchronous
    motors to drive the pumps. Fairfax provided the motor specifications, which
    2
    detailed the required design and provided that the bearing housing of the motors
    “shall be designed to prevent leakage of oil and excessive aeration of the oil.”
    B.    Oil leakage and repairs
    NOV concedes that the motors had “significant” oil leaks, shortly after they
    were delivered in the spring of 2009. Soon after the oil leaks were discovered,
    Fairfax issued a defective-work notice to Pizzagalli, indicating that the motors
    must be repaired to eliminate the leaks, and NOV was informed of the problem.
    The next month, Flowserve told NOV that it was concerned that its emails about
    the leaks were being “dramatically ignored,” and requested “immediate input”
    regarding repairs. NOV responded, stating that it had not ignored the emails and
    had tried various unsuccessful remedies on site.
    NOV engineers traveled to Virginia in June and July 2009 and attempted
    various fixes, but could not repair the leaks. They concluded that the motors
    would need to be removed for repair, but Fairfax could not release the motors
    during the peak-demand summer months, even though they continued to leak oil.
    In December 2009, NOV informed Flowserve that it had decided to send the
    motors to Texas for repair, and that it would send a detailed repair schedule in a
    week. Flowserve responded that a week was too long when a schedule had been
    expected earlier. Flowserve also told NOV that Pizzagalli was refusing to pay a
    “tremendous amount of money” that it owed to Flowserve because the motor issue
    3
    had not yet been corrected. Flowserve noted that Pizzagalli thought that NOV was
    “unresponsive” and had supplied motors of “terrible quality,” and was holding
    Flowserve accountable for NOV’s deficiencies.
    NOV prepared a schedule: the motors were to be removed one at a time,
    beginning in January 2010, and the repairs were to be completed by early April
    2010. The repair proposal included the addition of a lip seal to keep oil inside the
    lower bearing housings.
    The first motor was removed and arrived at NOV’s facility in January 2010.
    As the repairs progressed, NOV decided not to install the proposed lip seal, telling
    Flowserve and Pizzagalli that it was unnecessary and would cause further delays.
    Pizzagalli asked Fairfax for approval to ship the motor back to Virginia, and
    Fairfax agreed, noting that it was “very disappointed and concerned” that the
    originally proposed repair procedures were not followed.           Pizzagalli then
    authorized Flowserve to ship the motor, but reminded Flowserve that it bore all
    risks if the repairs were unsuccessful.
    The motor was reinstalled at Corbalis in March 2010, but it showed signs of
    leaking the next day. Internally, NOV continued to attempt to find a way to
    resolve the oil leaks. But one engineer noted in an internal email that NOV was
    “looking very stupid in front of this customer!!” The NOV engineer responsible
    for the design of the motors’ lower bearing housing reported internally that he
    4
    “suspect[ed] that if we do not get this [oil leak issue] turned around really fast . . .
    they might end up using our[] [motors] until they get someone else to build some[,]
    then tell us they don’t want them . . . .”
    On March 19, 2010, Fairfax inspected the repaired motor and was displeased
    to see that it was running hotter than it had previously and that there was a
    “remarkable amount of oil residue.” Fairfax sent a letter to Pizzagalli, requesting
    an immediate plan of action, telling it that “[w]ith this ongoing oil leakage problem
    and new high bearing temperature problem we still consider this equipment
    defective,” and stating that it was “very concerned” that the motors could not be
    repaired. Pizzagalli responded by notifying Flowserve: “due to the repeated and
    continuing problems . . . we will formally and finally reject the motors and require
    that Flowserve act immediately to provide new motors” unless certain repair
    conditions were met. In response, Flowserve and NOV prepared a written repair
    plan. Based on NOV’s analysis, Flowserve informed Pizzagalli that the oil on the
    repaired motor was merely residual and proposed that the second motor be repaired
    as the first one had.
    After the second motor was repaired, it was returned to Corbalis on Friday,
    May 21, 2010. Before it was started, a Fairfax inspector put his hand inside the
    motor and found that it came away “covered in oil.” Pizzagalli immediately
    contacted NOV and Flowserve and requested that a representative from Flowserve
    5
    inspect the second motor. NOV responded that it had tested the motor for 36 hours
    with no leak and that it believed that the oil was merely residual. But it also
    admitted that the motors had been steam-cleaned and baked to remove any residual
    oil before they were shipped back to Corbalis.
    On June 2, 2010, Pizzagalli formally rejected the two motors due to the
    “persistent and substantial oil leaks,” which it noted had been ongoing since April
    2009. Pizzagalli noted that “[t]he opportunity for Flowserve and NOV to cure the
    oil leak defect by repair of these motors is now long past,” and it demanded that
    Flowserve agree in writing by June 11, 2010 to provide contractually-compliant
    motors manufactured by someone other than NOV.
    On June 9, 2010, Flowserve demanded that NOV “provide Flowserve with a
    detailed proposal outlining the steps NOV will take to immediately and finally
    resolve the motor issues” by June 16, 2010. On June 10, 2010, Flowserve notified
    Pizzagalli that it had demanded that NOV provide a proposal for final resolution of
    the leaks, and that Flowserve was also evaluating alternative motor vendors. On
    June 11, 2010, NOV wrote Flowserve to propose several additional repairs, and
    concluded that, though they were “unsure of [the] origin” of the oil on the motors,
    the “tiny amounts” “if . . . indeed residual” should taper off to zero after four to six
    weeks.
    6
    On June 25, 2010, Flowserve told NOV that NOV’s “inability to resolve the
    oil leak problem after several attempts over many months” left Flowserve with
    “little choice but to attempt to mitigate the damages caused by the . . . motors” by
    “sourcing replacement motors from a different motor supplier,” and that NOV “is
    welcome to participate in this effort.” Five days later, Flowserve notified NOV
    that Pizzagalli would not accept further repair attempts and that the motors would
    be replaced.
    After Flowserve sued NOV, a June 2011 inspection of the motors revealed
    leaking oil. At trial, NOV engineers admitted that the oil was not residual and had
    leaked from the lower bearing housing.
    C.    The 65% requirement
    Dominion Power, the utility company that supplied power to Corbalis,
    limited the voltage dip during startup of the pumps’ motors to a maximum of 3% in
    order to avoid interruption of service to other customers. As part of the Corbalis
    expansion, Fairfax installed a reduced voltage starter set on a 65% tap, with the
    intention that the motors start on 65% power and transition to 100% power over
    time to avoid an impermissible voltage dip. But this design feature had not been
    included in the design specifications that NOV used to design the motors.
    Accordingly, through no fault of NOV, the motors it supplied were not designed to
    start on a 65% tap.
    7
    In August 2009, after NOV had concluded that the motors would need to be
    removed to repair the oil leaks, Flowserve learned for the first time that Fairfax
    wanted the motors to start on a 65% tap. Fairfax’s engineering firm concluded that
    the motors supplied were not capable of starting on a 65% tap and would need to
    be modified or replaced in order to do so. Fairfax notified Pizzagali that the
    motors were defective because they were unable to start on a 65% tap.
    Pizzagalli, in turn, notified Flowserve. Flowserve responded that it and
    NOV “were never contracted by Pizzagalli . . . to start at 65% rated voltage.”
    Accordingly, Flowserve told Pizzagalli, “based on the fact that the 65% voltage
    start requirement is not a part of the contract between [Flowserve] and Pizzagalli,
    Flowserve and NOV will work . . . to meet this requirement, however, any changes
    to the pump or motor must be to the expenses of Pizzagalli.” Pizzagalli disputed
    this, acknowledging that the requirement had not been included in the design
    specifications, but arguing that because it had been mentioned on associated
    drawings, the expenses should be covered by Flowserve.
    Flowserve and Pizzagalli entered into a settlement agreement in July 2010.
    Pizzagalli agreed to pay Flowserve money that it was withholding on the Corbalis
    project and an unrelated project in exchange for Flowserve’s replacement of the
    motors, which, according to the agreement, had been rejected due to oil leaks. The
    8
    replacement motors Flowserve purchased were designed to comply with the 65%
    requirement.
    D.    Trial and post-trial motions
    After a three week trial, the jury found that NOV breached its contract with
    Flowserve and committed fraud against Flowserve. The jury assessed $999,000 in
    damages for the amount paid by Flowserve for replacement motors attributable to
    NOV’s breach, and $190,000 in incidental damages.
    NOV moved for judgment notwithstanding the verdict, arguing that the
    evidence conclusively established that Flowserve rejected the motors because they
    did not meet the 65% requirement, not because they leaked, and that there was no
    evidence to support the jury’s fraud finding. The trial court denied the motion and
    entered judgment on the jury’s verdict for breach of contract and the parties’
    stipulation regarding attorney’s fees.
    NOV moved for a new trial, arguing, among other things, that the evidence
    showed as a matter of law that the oil leaks were not the cause of Flowserve’s
    rejection of the motors, that the evidence was factually insufficient to support the
    jury’s fraud finding, and that the trial court erred in denying its requested
    instructions regarding its defenses. The trial court denied the motion and NOV
    appealed.
    9
    Charge Issues
    In its first and second issues, NOV argues that the trial court erred in
    refusing to submit its requested jury instructions on NOV’s affirmative defense of
    excuse. NOV argues that it was entitled to two such instructions: (1) a prior
    material breach instruction based on Flowserve’s alleged bad faith refusal to
    provide NOV a reasonable opportunity to cure the oil leaks and (2) a waiver
    instruction based on Flowserve’s alleged waiver of the right to sue NOV for
    NOV’s delivery of non-conforming motors.
    A.    Standard of Review
    We review a trial court’s refusal to include an instruction in the jury charge
    for an abuse of discretion. See Tex. Dep’t of Hum. Servs. v. E.B., 
    802 S.W.2d 647
    ,
    649 (Tex. 1990); Powell Elec. Sys. v. Hewlett Packard Co., 
    356 S.W.3d 113
    , 122
    (Tex. App.—Houston [1st Dist.] 2011, no pet.). A trial court has wide discretion
    in submitting instructions and jury questions. Powell Elec. Sys., 
    356 S.W.3d at 122
    . A trial court abuses its discretion when it acts in an arbitrary or unreasonable
    manner, or if it acts without reference to any guiding rules or principles. Tex.
    Dep’t of Hum. Servs., 802 S.W.2d at 649; Powell Elec. Sys., 
    356 S.W.3d at 122
    .
    A trial court must submit to the jury all questions, instructions, and
    definitions raised by the pleadings and evidence. TEX. R. CIV. P. 278 (“The court
    shall submit the questions, instructions and definitions in the form provided by
    10
    Rule 277, which are raised by the written pleadings and the evidence.”); Hyundai
    Motor Co. v. Rodriguez, 
    995 S.W.2d 661
    , 664 (Tex. 1999). “When a trial court
    refuses to submit a requested instruction on an issue raised by the pleadings and
    evidence, the question on appeal is whether the request was reasonably necessary
    to enable a jury to render a proper verdict.” Shupe v. Lingafelter, 
    192 S.W.3d 577
    ,
    579 (Tex. 2006) (per curiam).
    B.    Did the trial court err in refusing to submit NOV’s requested
    instruction regarding Flowserve’s prior material breach?
    In its first issue, NOV contends that the trial court erred in refusing to submit
    its requested jury question on the affirmative defense of excuse based upon
    Flowserve’s prior material breach of rejecting the motors in bad faith, without
    providing NOV a reasonable opportunity to cure the oil leaks.
    1.    Applicable Law
    A party is excused from performing a contract if the other party committed a
    prior material breach of the contract. See Mustang Pipeline Co. v. Driver Pipeline
    Co., 
    134 S.W.3d 195
    , 196 (Tex. 2004) (“It is a fundamental principle of contract
    law that when one party to a contract commits a material breach of that contract,
    the other party is discharged or excused from further performance.”); Compass
    Bank v. MFP Fin. Servs., Inc., 
    152 S.W.3d 844
    , 852 (Tex. App.—Dallas 2005, pet.
    denied) (excuse based upon prior material breach is an affirmative defense). The
    11
    party asserting excuse bears the burden of proving it. See Am. Petrofina, Inc. v.
    Allen, 
    887 S.W.2d 829
    , 830 (Tex. 1994).
    Under the Uniform Commercial Code (UCC), which the parties agree is
    applicable here, each party to a contract has a duty to act in good faith in the
    performance or enforcement of the contract.      TEX. BUS. & COM. CODE ANN.
    § 1.304 (West 2009); El Paso Natural Gas Co. v. Minco Oil & Gas, 
    8 S.W.3d 309
    (Tex. 1999). “Good faith” means honesty in fact and the observance of reasonable
    commercial standards of fair dealing. TEX. BUS. & COM. CODE ANN. § 1.201(20)
    (West 2009).    When a buyer rejects non-conforming goods and the time for
    performance has not yet expired, “the seller may seasonably notify the buyer of his
    intention to cure and may then within the contract time make a conforming
    delivery.” TEX. BUS. & COM. CODE ANN. § 2.508 (West 2009).
    2.     Analysis
    NOV argues that both the UCC and the parties’ contract required Flowserve
    to provide NOV an opportunity to cure any nonconformity before Flowserve
    would be justified in replacing the motors. NOV further contends that Flowserve’s
    failure to provide NOV a good faith, reasonable opportunity to cure amounts to a
    contractual breach that preceded any material breach by NOV. Accordingly, NOV
    maintains that the trial court should have submitted NOV’s excuse defense based
    on prior material breach to the jury.
    12
    In its opening brief, NOV did not identify a provision of the contract that
    gave NOV the right to cure. It relied instead on the general UCC requirement that
    each party to a contract must reject goods in good faith. Later, in its reply brief,
    NOV asserted that the contract contained a cure and limitation of remedies
    provision:
    In the event any goods manufactured by [NOV] and furnished
    hereunder are found to be defective or otherwise fail to conform to the
    conditions of this contract, Buyer’s sole and exclusive remedy shall be
    to notify [NOV] and [NOV] will at its option (1) replace the goods at
    the delivery point specified herein (2) repair the goods or (3) refund
    the purchase price. Buyer’s remedies are limited as aforesaid
    regardless of the basis of the claim. Claims must be made promptly
    after discovery but not later than one year from date of delivery.
    [NOV] must be given an opportunity to investigate.
    After oral argument, Flowserve filed a letter with this Court, asserting that the
    record contains competing purchase orders, and because of this “battle of the
    forms,” the parties agreed that they would look solely to the UCC and not to the
    competing forms to supply the terms governing available remedies. We conclude
    that we need not decide the battle of the forms issue, or whether the parties agreed
    to look only to the provisions of the UCC, because neither of those questions
    impacts our analysis.
    NOV tendered a proposed question on excuse with instructions regarding
    prior material breach and four other affirmative defenses. NOV’s tender read:
    13
    Affirmative defenses to breach of contract liability question and instructions—
    Was NOV’s failure to comply excused?
    You are instructed as follows:
    Failure to comply by NOV is excused by Flowserve’s
    previous failure to comply with a material obligation of the
    same agreement. In addition to the language of the agreement,
    the law imposes on a party to a contract a duty to enforce the
    contract in good faith. In that connection, good faith means
    honesty in fact and the observance of reasonable commercial
    standards of fair dealing. The duty of good faith applies to the
    buyer’s decision to reject the goods.
    Failure to comply by NOV is excused if compliance is
    waived by Flowserve.
    Waiver is an intentional surrender of a known right
    or intentional conduct inconsistent with claiming the
    right.
    A party’s conduct includes conduct of others that the
    party has ratified. Ratification may be express or implied.
    Implied ratification occurs if a party, though he
    may have been unaware of unauthorized conduct taken
    on his behalf at the time it occurred, retains the benefits
    of the transaction involving the unauthorized conduct
    after he acquired full knowledge of the unauthorized
    conduct. Implied ratification results in the ratification of
    the entire transaction.
    NOV’s failure to comply is excused if you find that
    Flowserve accepted the benefits of a transaction, and that
    Flowserve subsequently took an inconsistent position to avoid
    corresponding obligations or effects.
    You are instructed that NOV’s failure to comply is
    excused if you find that NOV’s performance was rendered
    14
    impracticable or impossible by the occurrence of an event the
    non-occurrence of which was a basic assumption on which the
    contract was made.
    Answer “Yes” or “No”:          ____________
    NOV’s tender commingled instructions regarding six different affirmative
    defenses, but NOV argues in its first issue that the trial court erred in refusing the
    prior material breach instruction.
    There is no evidence supporting an instruction regarding a prior material
    breach by Flowserve. It is undisputed that the motor specifications required that
    the bearing housing of the motors “be designed to prevent leakage of oil and
    excessive aeration of the oil.” NOV’s delivery of motors that leaked oil thus
    constituted a breach of the contract.      See Westech Eng’g, Inc. v. Clearwater
    Constructors, Inc., 
    835 S.W.2d 190
    , 203–04 (Tex. App.—Austin 1992, no writ.)
    (noting that failure of equipment to meet specifications warrants rejection and that
    trial court did not err in concluding that seller breached contract by failing to
    supply equipment meeting contract specifications). It is undisputed that Flowserve
    did not reject the motors and cover by buying new motors until after the oil leaks
    were discovered. NOV points to no evidence, and we have found none in the
    record, that would support a finding that Flowserve breached the contract before
    the leaks were discovered. Thus, there is no evidence that Flowserve’s alleged
    breach occurred before NOV’s—which is required, by definition, for Flowserve to
    15
    have committed a “prior material breach.” See Mustang Pipeline Co., 134 S.W.3d
    at 196.
    At oral argument and in its briefing, NOV relied upon Oil Country
    Specialists, Ltd. v. Phillipp Brothers Inc., 
    762 S.W.2d 170
     (Tex. App.—Houston
    [1st Dist.] 1988, writ denied) and Printing Center of Texas, Inc. v. Supermind
    Publishing Company, Inc., 
    669 S.W.2d 779
     (Tex. App.—Houston [14th Dist.]
    1984, no writ), to argue that the oil leaks could not constitute a breach of the
    contract until after NOV was given a reasonable opportunity to cure. According to
    NOV, this means that Flowserve breached first by refusing in bad faith to allow
    NOV reasonable opportunity to cure. However, neither Oil Country Specialists
    nor Printing Center of Texas supports NOV’s position because neither involved the
    assertion of a prior material breach.
    In Oil Country Specialists, the jury answered in the affirmative a special
    issue asking whether the plaintiff rejected the goods in bad faith. See 762 S.W.2d
    at 178–79. That is different from the theory asserted by NOV here, which is that
    the alleged bad-faith refusal to allow NOV to cure by repairing the non-
    conforming goods constituted the first breach. And while Printing Center of Texas
    recognizes that a buyer may reject goods in bad faith, see 669 S.W.2d at 784, it
    does not support the proposition that a bad-faith rejection of non-conforming goods
    can constitute the first breach of a contract so as to support a prior material breach
    16
    instruction, as NOV argues here.        Thus, these cases do not support NOV’s
    argument that the evidence here supports its requested prior material breach
    instruction.   Because it was unsupported by the evidence, NOV’s tendered
    instruction on prior material breach was not proper. See Union Pac. R.R. v.
    Williams, 
    85 S.W.3d 162
    , 166 (Tex. 2002).
    In addition, the jury was instructed not to include in its damages award any
    amount that Flowserve could have avoided by the exercise of reasonable care.
    NOV argued that Flowserve did not act in a commercially reasonable manner
    when it rejected NOV’s motors and chose to cover. Thus, the trial court’s charge
    instructed the jury that Flowserve was not entitled to recover damages to the extent
    that Flowserve acted unreasonably. We hold that NOV failed to demonstrate that
    the trial court abused its discretion in rejecting its prior material breach instruction
    or that the rejection resulted in an improper verdict. See Powell Elec. Sys., 
    356 S.W.3d at 122
    ; Shupe, 192 S.W.3d at 579.
    We overrule NOV’s first issue.
    C.    Did the trial court err in refusing to submit NOV’s requested
    instruction regarding excuse based on Flowserve’s waiver?
    In its second issue, NOV contends that the trial court erred in refusing to
    submit its requested jury question on excuse based upon Flowserve’s waiver of the
    right to recover for the damages it sustained in connection with its cover.
    17
    1.     Applicable Law
    Waiver may be asserted as an affirmative defense against a party who
    “intentionally relinquishes a known right or engages in intentional conduct
    inconsistent with claiming that right.” Tenneco, Inc. v. Enter. Prods. Co., 
    925 S.W.2d 640
    , 643 (Tex. 1996); see also Robinson v. Robinson, 
    961 S.W.2d 292
    ,
    300 (Tex. App.—Houston [1st Dist.] 1997, no writ) (“The doctrine of waiver
    distinguishes between a showing of intent to waive by actual renunciation and a
    showing of intent to waive based on inference.”). When a party relies on inferred
    or implied waiver by conduct, it is that party’s burden “to produce conclusive
    evidence that the opposite party manifested its intent to no longer assert its claim.”
    Robinson, 961 S.W.2d at 300.
    2.     Analysis
    NOV requested that the trial court submit the following instruction regarding
    excuse based upon waiver:
    Failure to comply by NOV is excused if compliance is waived by
    Flowserve. Waiver is an intentional surrender of a known right or
    intentional conduct inconsistent with claiming the right.
    On appeal, NOV contends that Flowserve had the “right under the UCC to demand
    from Pizzagalli a reasonable opportunity” for NOV to repair or replace the motors.
    NOV contends that because Flowserve did not do so, and instead “chose to settle
    its differences with Pizzagalli in return for receiving Flowserve’s withheld funds,”
    18
    it “waived its rights to demand” that NOV “pay for the replacement motors.”
    NOV relies upon Section 2.711 of the Business and Commerce Code, which
    provides a buyer may “cover” at the seller’s expense if the buyer rightfully rejects
    the goods. See TEX. BUS. & COM. CODE ANN. § 2.711 (West 2009). NOV argues
    that, because Flowserve did not “rightfully” reject the motors, it may not recover
    damages from NOV for the amount it spent “covering.”
    Because NOV relies on inferred or implied waiver by conduct, it was NOV’s
    burden to adduce evidence that Flowserve manifested its intent to waive its claim
    against NOV for the cost of the cover. But NOV points to no evidence indicating
    such a waiver. See Robinson, 961 S.W.2d at 300.
    The sole case NOV relies upon in support of its waiver argument, Vera v.
    North Star Dodge Sales, Inc., 
    989 S.W.2d 13
     (Tex. App.—San Antonio 1998, no
    pet.), illustrates the type of evidence required to support a claim of waiver. In
    Vera, after a dispute arose regarding North Star’s sale of a car to Vera, North Star
    sent a check to Vera that said: “Endorsement releases North Star Dodge from any
    and   all   liability   regarding   the   purchase   of     a   1993   Mazda   Protg
    JM1B62266PO585288.” 
    Id. at 16
    . Vera endorsed and cashed the check, and
    waived his DTPA claim by doing so. 
    Id. at 18
    .
    There are no comparable facts here.                 Waiver is the intentional
    relinquishment of a known right or intentional conduct inconsistent with claiming a
    19
    right, and NOV points to no statement or action by Flowserve suggesting that
    Flowserve did not intend to assert its right to have NOV compensate Flowserve for
    damages Flowserve sustained in connection with its cover. See Tenneco, Inc., 925
    S.W.2d at 643.
    We overrule NOV’s second issue.
    Judgment Notwithstanding the Verdict
    In its third issue, NOV challenges the trial court’s denial of its motion for
    judgment notwithstanding the verdict, contending that the evidence conclusively
    established that Flowserve rejected the motors because they did not meet the 65%
    requirement, and not because they leaked.
    A.    Standard of Review
    We review the denial of a motion for judgment notwithstanding the verdict
    under a no-evidence standard. See NETCO, Inc. v. Montemayor, 
    352 S.W.3d 733
    ,
    738 (Tex. App.—Houston [1st Dist.] 2011, no pet.) (citing Tanner v. Nationwide
    Mut. Fire Ins. Co., 
    289 S.W.3d 828
    , 830 (Tex. 2009)). The evidence is sufficient
    if it “would enable reasonable and fair-minded people to reach the verdict under
    review.” City of Keller v. Wilson, 
    168 S.W.3d 802
    , 827 (Tex. 2005). We view the
    evidence “in the light most favorable to the verdict,” and we “credit evidence
    favoring the jury verdict if reasonable jurors could, and disregard contrary
    evidence unless reasonable jurors could not.” Zachry Constr. Corp. v. Port of
    20
    Houston Auth. of Harris Cnty., 449 S.W.3d. 98, 101 n.3 (Tex. 2014); Tanner, 289
    S.W.3d at 830 (quoting Cent. Ready Mix Concrete Co. v. Islas, 
    228 S.W.3d 649
    ,
    651 (Tex. 2007)). Evidence is legally insufficient if: (1) there is a complete
    absence of evidence of a vital fact; (2) the court is barred by rules of law or
    evidence from giving weight to the only evidence offered to prove a vital fact;
    (3) the evidence offered to prove a vital fact is no more than a mere scintilla; or
    (4) the evidence establishes conclusively the opposite of the vital fact. City of
    Keller, 168 S.W.3d at 810.
    B.    Applicable Law
    To recover damages for breach of contract, a plaintiff must show that he
    suffered a pecuniary loss as a result of the breach. S. Elec. Servs., Inc. v. City of
    Houston, 
    355 S.W.3d 319
    , 323–24 (Tex. App.—Houston [1st Dist.] 2011, pet.
    denied). “Such losses must be the natural, probable, and foreseeable consequence
    of the defendant’s conduct.” 
    Id.
     at 324 (citing Mead v. Johnson Grp, Inc., 
    615 S.W.2d 685
    , 687 (Tex. 1981)). “[T]he absence of a causal connection between the
    alleged breach and the damages sought will preclude recovery.” 
    Id.
    C.    Analysis
    The jury found that Flowserve was entitled to recover damages for NOV’s
    breach of the contract. Viewing the evidence in the light most favorable to the
    21
    verdict, we conclude that the evidence at trial was legally sufficient to support the
    jury’s verdict.
    Flowserve’s witnesses testified that Flowserve did not believe that either it
    or NOV was required by their respective contracts to supply motors designed to
    start on a 65% tap. They testified that irrespective of that requirement, the motors
    were unacceptable because they continued to leak, even after NOV’s repeated
    attempts to fix them. Flowserve’s General Manager testified that Flowserve’s
    position was that it was not contractually required to supply motors that started on
    a 65% tap because that specification was not a part of the contract, but that it did
    have a contractual obligation to supply motors that did not leak oil, and that the
    motors were rejected and replaced because of the oil leaks. Documentary evidence
    showed that Flowserve informed Pizzagalli that neither it nor NOV was
    responsible for the expense of resolving the 65% tap problem because that
    requirement had not been included in the project specifications. This is some
    evidence supporting the jury’s conclusion that Flowserve’s damages were caused
    by the motors oil leaks as opposed to their failure to meet the 65% requirement.
    NOV argues that the jury should not have believed Flowserve’s witnesses
    because the evidence conclusively shows that the oil leaks were not the cause of
    Flowserve’s damages. For example, NOV points to evidence that Flowserve’s
    Post-Delivery Service Coordinator asked his manager whether they should have an
    22
    independent consultant, Armando Tovar, attend NOV’s review of the motors when
    NOV was given an opportunity to propose a final resolution after Pizzagalli
    rejected the motors in June 2010. Flowserve’s manager responded that he didn’t
    “believe [Tovar] would . . . be of much help. The problem is more political than
    technical.” NOV also points to evidence that Flowserve supplied replacement
    motors that could start on a 65% tap, arguing that this proves the 65% issue was
    the real reason that the motors were rejected.
    We disagree with NOV’s contention that this evidence conclusively showed
    that the motor leaks did not cause Flowserve’s damages. The evidence on this
    point sharply conflicted; it was the province of the jury to resolve conflicting
    evidence, to determine the credibility of the witnesses, and to weigh their
    testimony. City of Keller, 168 S.W.3d at 819. We are required to credit evidence
    favoring the jury’s conclusion that NOV’s breach caused Flowserve’s damages “if
    reasonable jurors could, and disregard contrary evidence unless reasonable jurors
    could not.” Tanner, 289 S.W.3d at 830. We conclude that there was more than a
    mere scintilla of evidence to enable reasonable and fair-minded people to conclude
    that the motors were rejected and replaced due to the oil leaks. See City of Keller,
    168 S.W.3d at 827.
    We overrule NOV’s third issue.
    23
    Because we have determined that the trial court properly rendered judgment
    on the jury’s breach of contract finding, we do not reach NOV’s remaining issues,
    which pertain to the alternate ground of recovery, fraud.
    Conclusion
    We affirm the judgment of the trial court.
    Rebeca Huddle
    Justice
    Panel consists of Chief Justice Radack and Justices Bland and Huddle.
    24