Allen Butler Construction, Inc. v. DHD Concrete, LLC, American Economy Insurance Company and Bituminous Casualty Corporation ( 2011 )


Menu:
  •                                NO. 07-10-0490-CV
    IN THE COURT OF APPEALS
    FOR THE SEVENTH DISTRICT OF TEXAS
    AT AMARILLO
    PANEL A
    DECEMBER 13, 2011
    ______________________________
    ALLEN BUTLER CONSTRUCTION, INC., APPELLANT
    V.
    AMERICAN ECONOMY INSURANCE COMPANY, APPELLEE
    _________________________________
    FROM THE 99[TH] DISTRICT COURT OF LUBBOCK COUNTY;
    NO. 2009-548,665; HONORABLE WILLIAM C. SOWDER, JUDGE
    _______________________________
    Before CAMPBELL and HANCOCK and PIRTLE, JJ.
    MEMORANDUM OPINION
    Appellant, Allen Butler Construction, Inc. (ABC), appeals from entry of summary judgment in favor of Appellee, American Economy Insurance Company (AEIC), in ABC's action seeking to collect damages for negligent construction on a commercial general liability policy issued by AEIC to DHD Concrete, LLC (DHD).  In two issues, ABC asserts the trial court erred in granting AEIC's cross-motion for summary judgment because ABC established as a matter of law that insurance coverage exists for ABC's claim.  We affirm.
    Background
    In June 2007, the City of Lubbock (City) entered into a contract with Lee Lewis Construction (LLC) to build Phase I of the Lubbock Youth Sports Complex (the "project").  LLC, in turn, entered into a subcontract with ABC to handle site clearing, excavation, grading, paving, sidewalks and concrete pads for the project.  Similarly, ABC entered into a subcontract with DHD to construct the concrete apron and sidewalks.
    The ABC subcontract with DHD required, among other things, that DHD's work be free from defects and conform to the project's plans.  The subcontract also required that DHD procure a commercial general liability policy naming ABC as an additional insured.  In compliance with that provision, DHD procured Commercial General Liability Policy No. 02-CE-158341-2 from AEIC (the "policy").
    In March 2008, DHD began work on the concrete apron and sidewalks.  In September 2008, the City discovered that the concrete apron, poured by DHD, was cracking and the rebar was at the bottom of the apron rather than in the center as required by the project plans.  The City's concerns were passed down to the responsible party and in a letter from ABC to LLC dated October 2, 2008, ABC acknowledged DHD had incorrectly installed rebar in the apron for quad one and offered a full refund in lieu of removing the concrete paving to correct the situation.  Four days later, on October 6, ABC sent a second letter to LLC admitting DHD incorrectly installed rebar in the concrete apron for all four quads and proposed a refund of $6.00 per square foot or $281,808.00 in lieu of replacing the concrete.  ABC also offered to grout and seal all cracks in the concrete.
    Within a week to ten days, the City responded to ABC's offer by demanding that the concrete paving in all four quads be removed and that the apron be replaced.  Thereafter, ABC waited for optimal weather conditions before replacing the apron.  In December, DHD agreed to pay ABC $2,000 a week to cover the cost of the apron's replacement.
    In January 2009, ABC began tearing out and replacing the apron using DHD's services.  This process was completed in March.  On January 21, DHD gave AEIC notice of ABC's claim against it for the defective concrete.  In a letter dated February 4, AEIC responded that it was still investigating DHD's claim and asked for additional information.  In late February, AEIC denied DHD's claim.
    In a letter dated March 4, ABC, as an additional insured on DHD's policy, requested a defense and indemnification from AEIC for a claim by the City and LLC for DHD's concrete services "that were performed negligently or not in conformity with standard construction practices."   ABC sought reimbursement for the cost of removing and then replacing the concrete apron, $300,000.  In a letter dated March 12, AEIC responded that it understood that no lawsuit had been filed and requested information regarding the claim and any information regarding any lawsuit.  In a letter dated April 15, AEIC denied ABC's request for coverage citing several policy exclusions.
    On August 18, ABC filed suit against DHD, AEIC and Bituminous.  DHD did not file an answer and, on October 30, ABC took a default judgment against DHD.  The trial court's Final Default Judgment found, in part, that:  (1) ABC made a demand for payment from DHD on or about March 19, 2009, (2) DHD failed to perform its work in a good and workmanlike manner, (3) DHD's work was not complete when the defect in its work was discovered, and (4) DHD breached its contract with ABC, breached its warranty to ABC, was negligent in its construction of the aprons and proximately caused damages to ABC of $332,378.57.  The trial court awarded ABC $332,378.57 in replacement costs, prejudgment interest of $3,277.80, and attorney's fees of $1,500.00 for a total of $337,156.37 in damages.  On December 18, 2009, ABC acquired any claims belonging to DHD in ABC's suit against AEIC through a turnover order.
    In April 2010, ABC filed its First Amended Original Petition against AEIC and Bituminous seeking to recover damages awarded by the default judgment alleging that both insurers failed to defend and indemnify DHD and ABC, as an additional insured.  ABC and AEIC subsequently filed cross motions for summary judgment.  In November, the trial court granted AEIC's motion, denied ABC's motion and entered its final judgment in favor of AEIC.  This appeal followed.
    Discussion
    ABC asserts the trial court erred by granting summary judgment in AEIC's favor because ABC established, as a matter of law, that ABC and DHD met all conditions precedent to establishing coverage for DHD's allegedly defective work on the project and AEIC breached its contract by failing to defend and indemnify ABC and/or DHD.
    Standard of Review
    We review the trial court's summary judgment de novo.  Valence Operating Co. v. Dorsett, 
    164 S.W.3d 656
    , 661 (Tex. 2005).  Traditional summary judgment is proper only if the movant establishes there is no genuine issue of material fact and that the movant is entitled to judgment as a matter of law.  Tex. R. Civ. P. 166a(c); Diversicare General Partner, Inc. v. Rubio, 
    185 S.W.3d 842
    , 846 (Tex. 2003).  In our review of a trial court's grant of summary judgment, we take as true all evidence favorable to the nonmovant and indulge every reasonable inference and resolve any doubts in the nonmovant's favor.  
    Dorsett, 164 S.W.3d at 661
    ; Provident Life and Accident Ins. Co. v. Knott, 
    128 S.W.3d 211
    , 215 (Tex. 2003).
    A defendant moving for traditional summary judgment must conclusively negate at least one essential element of each of the plaintiff's causes of action or conclusively establish each element of an affirmative defense; Frost Nat. Bank v. Fernandez, 
    315 S.W.3d 494
    , 508 (Tex. 2010); Sci. Spectrum Inc. v. Martinez, 
    941 S.W.2d 910
    , 911 (Tex. 1997), and the trial court is required to grant the motion unless the nonmovant produces summary judgment evidence that raises a genuine issue of material fact.  Tex. R. Civ. P. 166a(b).  Moreover, if, as here, a trial court's granting of summary judgment does not specify the basis for the trial court's ruling, the summary judgment will be affirmed if any of the theories advanced by the movant are meritorious.  Joe v. Two Thirty Nine JV, 
    145 S.W.3d 150
    , 157 (Tex. 2004).
    An insurer's claimed exception to coverage constitutes an avoidance or an affirmative defense.  See Tex. Ins. Code Ann. § 554.002 (West 2009).  Although an insured bears the initial burden of showing there is coverage under an insurance policy, the insurer bears the burden of proving the applicability of an exclusion that permits it to deny coverage.  Venture Encoding Service, Inc. v. Atlantic Mut. Ins. Co., 
    107 S.W.3d 729
    , 733 (Tex.App. -- Fort Worth 2003, pet. denied).  When the insurer proves the applicability of an exclusion; Tex. Ins. Code Ann. § 554.002 (West 2009), the burden then shifts to the insured who must demonstrate that coverage exists under an exception to the exclusion.  Venture Encoding Service, 
    Inc., 107 S.W.3d at 733
    .
    Voluntary Assumption Provision
    Section IV.2.d., the "voluntary assumption provision," also known as the "consent-to-settlement provision," requires that an insured give prompt notice of a proposed settlement and/or tender a proposed settlement to the insurer before entering into any settlement with a claimant.  See Motiva Enterprises Co. v. St. Paul Fire and Marine Ins. Co., 
    445 F.3d 381
    , 383 n.1 (5[th] Cir. 2006) (interpreting Texas law); Maryland Casualty Co. v. American Home Assurance Co., 
    277 S.W.3d 107
    , 110, 113 (Tex.App. -- Houston [1[st] Dist.] 2009, no pet.).  If an insured breaches this provision by settling an underlying claim or liability case without the insurer's consent and the insurer is prejudiced thereby, coverage will be denied.  See Hernandez v. Gulf Group Lloyds, 
    875 S.W.2d 691
    , 693-94 (Tex. 1994); Coastal Ref. & Mktg., Inc. v. U.S. Fid. & Guar. Co., 
    218 S.W.3d 279
    , 295 (Tex.App. -- Houston [14[th] Dist.] 2007, pet. denied).  By demanding that an insurer prove prejudice, Texas law recognizes that only a material breach of this provision excuses performance.  See 
    Hernandez, 875 S.W.2d at 693
    .
    ABC does not seriously dispute AEIC's contention that DHD and ABC breached the policy's voluntary assumption provision.  Rather, ABC contends that any failure to adhere to the provision's terms is excused because neither ABC's nor DHD's actions prejudiced AEIC.  Having reviewed the summary judgment record, we find that AEIC established prejudice as a matter of law.
    Section I.1.a. of the policy gave AEIC the unfettered discretion to settle any claim or suit and Section IV.2.c.(3) required its insured to "[c]ooperate with [AEIC] in the . . . settlement of the claim."  In Motiva, the United States Court of Appeals for the Fifth Circuit concluded that "[w]hen . . . the insurer is not consulted about the settlement, the settlement is not tendered to it [,] and the insurer has no opportunity to participate in or consent to the ultimate settlement decision . . . the insurer is prejudiced as a matter of law."  
    Motiva, 445 F.3d at 386
    .  This result is required in consent-to-settle exclusion cases because "[a]n insurer's right to participate in the settlement process is an essential prerequisite to its obligation to pay a settlement."  
    Id. at 242.
     Depriving the insurer of this contractual right constitutes a material breach, or prejudice.  
    Id. Here, as
    in Motiva, AEIC's summary judgment evidence establishes that AEIC was not consulted regarding ABC's and DHD's settlement of the City's and/or LLC's claims against ABC and DHD, had no settlement tendered to it by either ABC or DHD, and was not given any opportunity to participate in, or consent to, any ultimate settlement decision.  Rather, ABC and DHD unilaterally settled the City's and LLC's claim against them without any notice to AEIC.  When ABC filed suit against DHD and AEIC in August 2009, liability for the alleged defective concrete work had already been admitted by ABC and DHD, a settlement of LLC's and/or the City's claims had been struck, and the costs for remediation had been incurred.  AEIC received no benefit from the policy provisions it had bargained for in order to limit its liability.
    Furthermore, since its insureds had already admitted liability and the cost of their remediation was quantified with no opportunity for AEIC to lessen its financial exposure through the policy's provisions, the subsequent default judgment entered against DHD in ABC's suit was simply pro forma.  Prior to its entry, ABC and DHD had "wholly deprived [AEIC] of its ability to defend" against the claims asserted by the City and/or LLC.  See Maryland Casualty 
    Co., 277 S.W.3d at 117-18
    (collected cases cited therein).  See also Coastal Ref. & Mktg., 
    Inc., 218 S.W.3d at 287
    ("entry of default judgment will ordinarily constitute prejudice as a matter of law").  Under these circumstances, we find that AEIC's summary judgment evidence established AEIC suffered prejudice as a matter of law.  
    Motiva, 445 F.3d at 386
    ; Maryland Casualty 
    Co., 277 S.W.3d at 117
    .
    Because AEIC conclusively established the applicability of an exclusion that would permit it to deny coverage, the burden shifted to ABC and, in order to defeat AEIC's summary judgment motion, ABC necessarily had to adduce evidence establishing a genuine issue of material fact as to whether AEIC was prejudiced.  See Coastal Ref. & Mktg., 
    Inc., 218 S.W.3d at 295
    (no prejudice for breach of a consent-to-settle provision where insurer was aware of lawsuit and continuing settlement negotiations before the settlement but did not participate); Comsys Information Technology Services, Inc. v. Twin City Fire Insurance Co., 130 S.W.3d 181,191-92 (Tex.App. -- Houston [14[th] Dist.] 2003, pet. denied) (no prejudice for breach of a consent-to-settle provision where insurer was invited to mediation and chose not to participate in settlement negotiations).  Here, ABC produced no summary judgment evidence establishing AEIC was aware of, or invited to participate in, any ongoing settlement negotiations between ABC, DHD, the City or LLC prior to, or during, replacement of the concrete apron between January and March 2009.  Moreover, there was no "suit" regarding LLC's and/or the City's claims whatsoever until August 2009 when ABC filed suit against DHD and AEIC--nearly five months after ABC and DHD had settled with LLC and/or the City and incurred the cost of replacing the apron.        Accordingly, we find that ABC failed to raise a genuine issue of material fact as to whether ABC and DHD breached the consent-to-settle provision and/or whether an exception existed as to AEIC's exclusion of coverage affirmative defense, to-wit: whether AEIC was not prejudiced by that breach.  ABC's two issues are overruled.
    CONCLUSION
    The trial court's judgment is affirmed.
    Patrick A. Pirtle
    Justice