classic-century-inc-fka-classic-century-homes-inc-v-deer-creek ( 2008 )


Menu:
  •                         COURT OF APPEALS
    SECOND DISTRICT OF TEXAS
    FORT WORTH
    NO. 2-07-289-CV
    INIMITABLE GROUP, L.P.                                           APPELLANTS
    AND SOITIS, L.L.C.
    V.
    WESTWOOD GROUP
    DEVELOPMENT II, LTD.                                                APPELLEE
    ------------
    FROM THE 48TH DISTRICT COURT OF TARRANT COUNTY
    ------------
    OPINION
    ------------
    Introduction
    This case involves a dispute over whether a contract for the construction
    and sale of an office and warehouse building was validly terminated by the
    purchaser before closing. In five issues, appellants Inimitable Group, L.P. and
    Soitis, L.L.C. challenge (1) the trial court’s determination that they did not
    validly terminate the contract and, consequently, (2) the trial court’s final
    judgment awarding damages to appellee Westwood Group Development II, Ltd.
    for breach of contract. We affirm.
    Background
    In February 2005, Soitis and Westwood entered into an Agreement of
    Purchase and Sale (Agreement) “to provide for the construction by”
    Westwood—and the subsequent sale to Soitis—of an office and warehouse
    building in Grapevine, Texas. The Agreement provided for the building to be
    constructed according to certain plans and specifications, which were attached
    as exhibits. The initial closing date was to be October 30, 2005. The date the
    building was to be substantially completed as defined in the Agreement was
    October 15, 2005, “as adjusted from time to time as expressly provided” in the
    Agreement. The Agreement further (1) provided that “[t]ime is of the essence,”
    (2) required Westwood to construct the building with due diligence on or before
    the substantial completion date, “as extended by Excusable Delays and/or
    Purchaser Delays,” both defined in the Agreement,1 and (3) allowed Soitis to
    terminate the agreement by written notice to Westwood if substantial
    1
    … “Excusable Delay” is defined as delay in substantial completion for
    reasons “beyond the reasonable control of Seller,” such as delay because of
    strikes, governmental regulatory orders, weather, or changes to the project
    made by the purchaser. “Purchaser Delay” is defined as delay in substantial
    completion “due to any act or omission” of the purchaser, including delay
    because of any changes to the project made by the purchaser.
    2
    completion had not occurred by December 31, 2005 “as extended by Purchaser
    Delays only and Excusable Delays.”
    The construction plans attached to the Agreement provided only for the
    construction of the exterior of the building; Soitis was responsible for its own
    interior finish-out. Construction on the building began in late March 2005. In
    April 2005, Soitis and Westwood agreed that Westwood would assist Soitis in
    designing the interior finish-out of the building. Westwood hired an architect
    to assist with the interior finish-out plans.
    From April through November 2005, Tony Robertson, Soitis’s president,
    and Nicole Meadors, a Westwood employee, corresponded by phone and email
    regarding various aspects of the interior and exterior design and construction
    of the building. Al Burtin, Westwood’s chief operating officer, also participated
    in the process.   Soitis requested several alterations to the original exterior
    design, including the relocation of a truck ramp, the addition of a window, and
    the addition of a hard coat texture to the exterior. After reviewing and making
    several changes to the architect’s proposed drawings, Robertson approved the
    initial interior finish-out plans on June 21, 2005.      He approved the final
    construction documents for the interior on September 14, 2005, which
    Westwood then sent out for bids on the construction costs.
    3
    On November 7, 2005, the day Westwood received at least one of the
    bids for the interior construction, Robertson and Meadors had a phone
    conversation about the project, after which Meadors sent Robertson an email
    stating, “I was curious to hear if you had found anything else out? We have
    put your building on hold, but need to know ASAP exactly what direction we
    are going to be heading in.” Two days later, on November 9, 2005, Robertson,
    Burtin, and Meadors met regarding the project, and Robertson informed
    Meadors and Burtin that Soitis did not intend to occupy the building. They
    discussed options for the project, including having Soitis continue with the
    purchase and lease or sell the building. In addition, Robertson asked Meadors
    to investigate whether a different buyer could be found for the project.
    Robertson told Meadors and Burtin that he wanted to get a new appraisal on
    the building.   Robertson’s notes from that meeting indicate, “Anticipate a
    closing on December 1st,” and contain a notation that appears to state that the
    architect’s costs were approximately $25,000. The meeting notes also appear
    to contain calculations of the costs to either lease or sell the building in both
    improved and unimproved condition.
    Despite Robertson’s November 7, 2005 instruction to stop work on the
    building, Westwood’s contractor continued construction according to its
    contract with Westwood. As of December 13, 2005, the only item remaining
    4
    to be completed was the addition of an exterior wall light, needed to replace a
    planned but not installed light pole that the architect had inadvertently located
    over a gas line.
    On December 14, 2005, Meadors sent Robertson an email stating,
    We are still trying to sell your building[;] our prospect cannot meet
    until after the first of the year . . . so I will keep you informed. As
    far as closing on your building, we want to close after Christmas
    but before the New Year. Can you have all of your financing in
    place by this time?
    Robertson responded, “Having the financing in place is not a problem.
    Organizing our side for a closing in the middle of the holiday week is going to
    be a problem. The way things stand now, we are all out on vacation. We can
    try to figure something out this afternoon.” Meadors sent Robertson an email
    on January 9, 2006 inquiring whether Soitis “had gotten anything scheduled
    for [the] building” and asking him to email her “an update so we can get a
    closing date set.” Robertson responded,
    I forwarded the information to Chase last Thursday. My contact
    assured me they would evaluate the appraiser to determine if they
    could use him in our situation. I think you are correct, that this
    would be the most effective way to get us the appraisal we want
    in the shortest time. . . . I will be talking with Chase tomorrow at
    the latest.
    Burtin finally sent Robertson an email on January 27, 2006, stating that
    Westwood wanted to schedule closing for February 6, 2006. Burtin went on
    5
    to state that the building had been substantially completed on November 30,
    2005 and that the construction had run over schedule because of the changes
    to the exterior plans requested by Soitis, “none of which [according to Burtin]
    pertained to the seller’s actions.” Soitis did not challenge Burtin’s contention
    that it was the cause of the construction delay.
    On January 31, 2006, Meadors sent Robertson an email noting that he
    had told her Soitis was “changing the name on the [Agreement] from Soitis to
    another entity” and asking the name so that an assignment could be drafted.
    Soitis formed Inimitable in February 2006 and assigned its rights under the
    Agreement to Inimitable. According to Steve Staneff, Soitis’s former president
    and an equity holder, Inimitable was formed for the sole purpose of purchasing
    the building as an investment with the intent to lease it back to Soitis.2
    Robertson and Meadors continued to correspond regarding closing, with
    Meadors attempting to schedule a February 15, 2006 closing. Robertson told
    her that he would “make every effort for 2:00 on the 15th, [but] the 16th
    would be easier.” He also stated that he “would like to wrap this up as well.”
    Meadors met with the new appraiser on February 6, 2006.               However,
    unbeknownst to Westwood, Robertson, had already begun looking at the
    2
    … Robertson testified at trial, however, that after November 9, 2005,
    Soitis never intended to occupy the building.
    6
    Agreement to determine if Inimitable could terminate the transaction.
    Accordingly, sometime during the time he was discussing closing with Meadors,
    Robertson was discussing termination options with counsel. After confirming
    that the City had not issued a certificate of occupancy for the building exterior
    because the wall light had not been installed, appellants’ counsel sent a letter
    to Westwood terminating the Agreement under section 6.3, which allowed the
    buyer to terminate if the building had not been substantially completed by
    December 31, 2005. In the letter, counsel also demanded that Westwood
    return the $50,000 earnest money Soitis had paid into escrow when it first
    entered into the Agreement.
    After Westwood refused to return the earnest money, appellants sued
    Westwood in March 2006, claiming that Inimitable had validly terminated the
    Agreement and seeking return of the earnest money as damages for breach of
    contract.   They also sought a declaratory judgment that the Agreem ent is
    “terminated, invalid, void, and/or unenforceable.”         Westwood asserted
    counterclaims for breach of contract, negligence, and quantum meruit. In its
    Third Amended Original Answer, Westwood also included specific denials,
    claiming, among other things, that all conditions precedent to appellants’ right
    to relief had not occurred: specifically, that appellants prevented Westwood
    from performing the Agreement by instructing it to stop construction on the
    7
    building. Westwood also pled the affirmative defenses of appellants’ breach
    and failure to perform, anticipatory repudiation, waiver, promissory and
    equitable estoppel, laches and unclean hands, and impossibility or impracticality
    of performance.
    After a bench trial on January 16, 2007, the trial court ruled in favor of
    Westwood, awarding it damages of $157,946 plus prejudgment interest of
    $13,209.05—a total of $171,155.05—for breach of contract. It also awarded
    Westwood $65,000 in trial attorney’s fees and conditional attorney’s fees on
    appeal for $20,000 each to an appeal to the court of appeals and a fully briefed
    appeal in the supreme court. It also split costs between Inimitable and Soitis.
    The trial court signed findings of fact and conclusions of law on October 18,
    2007.
    Issues on Appeal
    Appellants bring five issues on appeal, in which they challenge the
    following findings and conclusions of the trial court:         (1) that Soitis and
    Westwood entered into a second, oral agreement for Westwood to coordinate
    the interior design of the building, (2) that Soitis either anticipatorily repudiated
    or breached the second, oral agreement, or both, by failing to execute change
    orders incorporating the interior design work into the Agreement, (3) that
    Westwood was excused from performance under the Agreement after Soitis’s
    8
    anticipatory repudiation, breach, or both of the second, oral agreement, (4) that
    Soitis should be estopped from claiming Westwood breached the Agreement,
    and (5) that Soitis waived any failure by Westwood to comply with the
    Agreement.
    Standard of Review
    Findings of fact entered in a case tried to the court have the same force
    and dignity as a jury’s answers to jury questions. Anderson v. City of Seven
    Points, 
    806 S.W.2d 791
    , 794 (Tex. 1991). The trial court’s findings of fact are
    reviewable for legal and factual sufficiency of the evidence to support them by
    the same standards that are applied in reviewing evidence supporting a jury’s
    answer. Ortiz v. Jones, 
    917 S.W.2d 770
    , 772 (Tex. 1996); Catalina v. Blasdel,
    
    881 S.W.2d 295
    , 297 (Tex. 1994). A court of appeals cannot make original
    findings of fact; it can only “unfind” facts. Tex. Nat’l Bank v. Karnes, 
    717 S.W.2d 901
    , 903 (Tex. 1986); Zeptner v. Zeptner, 
    111 S.W.3d 727
    , 734 (Tex.
    App.—Fort Worth 2003, no pet.) (op. on reh’g).
    Conclusions of law may not be challenged for factual sufficiency, but
    they may be reviewed to determine their correctness based upon the facts.
    Citizens Nat’l Bank v. City of Rhome, 
    201 S.W.3d 254
    , 256 (Tex. App.—Fort
    Worth 2006, no pet.); Dominey v. Unknown Heirs and Legal Representatives
    of Lokomski, 
    172 S.W.3d 67
    , 71 (Tex. App.—Fort Worth 2005, no pet.).
    9
    Existence of Oral Agreement for Interior Finish-out
    In their first issue, appellants contend that the trial court incorrectly
    concluded that Soitis and Westwood entered into a valid, binding second
    agreement for the interior finish-out of the building because there is no evidence
    that the terms of such an agreement were sufficiently definite so as to be
    enforceable. In their second issue, appellants contend that because there is no
    evidence of an enforceable second agreement, they cannot have anticipatorily
    repudiated it.
    Whether an agreement is legally enforceable or binding is a question of
    law. Searcy v. DDA, Inc., 
    201 S.W.3d 319
    , 322 (Tex. App.—Dallas 2006, no
    pet.); Oakrock Exploration Co. v. Killam, 
    87 S.W.3d 685
    , 690 (Tex. App.—San
    Antonio 2002, pet. denied). To be enforceable, a contract must be sufficiently
    definite in its material terms so as to enable the court to ascertain the parties’
    intentions. Fort Worth ISD v. City of Fort Worth, 
    22 S.W.3d 831
    , 846 (Tex.
    2000); T.O. Stanley Boot Co. v. Bank of El Paso, 
    847 S.W.2d 218
    , 221 (Tex.
    1992). What terms are “material” to a contract should be determined on an
    agreement-by-agreement basis. T.O. Stanley Boot 
    Co., 847 S.W.2d at 221
    (“Each contract should be considered separately to determine its material
    terms.”). When an essential term is left open for future negotiation, there is no
    binding contract. 
    Id. 10 The
    terms of an oral agreement may be established by direct or
    circumstantial evidence. Harris v. Balderas, 
    27 S.W.3d 71
    , 77 (Tex. App.—San
    Antonio 2000, pet. denied). In determining whether an oral contract exists, we
    “look to the communications between the parties and to the acts and
    circumstances surrounding those communications.” 
    Id. Appellants contend
    that they cannot have entered into an enforceable
    agreement for the interior finish-out because there was no agreed upon fee for
    Westwood’s services—and thus no way to determine the final cost of the
    agreement—a0nd no agreed upon due date for the finished product.
    When a contract does not set forth a definite price but all other elements
    of a contract have been met, the trial court may imply a reasonable price. KW
    Constr. v. Stephens & Sons Concrete Contractors, Inc., 
    165 S.W.3d 874
    ,
    883–84 (Tex. App.—Texarkana 2005, pet. denied); Buxani v. Nussbaum, 
    940 S.W.2d 350
    , 353 (Tex. App.—San Antonio 1997, no writ). Thus, when the
    parties have done everything else necessary to make a binding agreement for
    services, their failure to specify a price does not leave the contract so
    incomplete that it cannot be enforced.     KW 
    Constr., 165 S.W.3d at 884
    ;
    Burnside Air Conditioning & Heating, Inc. v. T.S. Young Corp., 
    113 S.W.3d 889
    , 894–95 (Tex. App.—Dallas 2003, no pet.); Pennington v. Jerry F.
    11
    Gurkoff, D.O., P.A., 
    899 S.W.2d 767
    , 770 (Tex. App.—Fort Worth 1995, writ
    denied).
    Additionally, the absence of a duration term for a contract “does not
    necessarily suggest that the parties did not enter into an enforceable
    agreement.”    Cytogenix, Inc. v. Waldroff, 
    213 S.W.3d 479
    , 486 (Tex.
    App.—Houston [1st Dist.] 2006, pet. denied); Avila v. Gonzalez, 
    974 S.W.2d 237
    , 244 (Tex. App.—San Antonio 1998, pet. denied) (noting that, “[w]hen the
    duration of a contract is not expressly dictated by the agreement, courts will
    frequently presume that the parties intended the agreement to last for a
    reasonable time”). If no time for performance is stated in the contract, the law
    may imply a reasonable one if the contract is “sufficiently definite for a court
    to be able to fix the time when it can be enforced.” Moore v. Dilworth, 
    142 Tex. 538
    , 
    179 S.W.2d 940
    , 942 (1944); 
    Cytogenix, 213 S.W.3d at 486
    ; 
    Avila, 974 S.W.2d at 245
    (noting that reasonable duration may be implied “in cases
    where the agreement contemplates that one party will make substantial
    expenditures or other investments in accordance with performance”).
    Here, Robertson testified that Soitis and Westwood had an oral
    agreement for Westwood to engage the architect to provide interior design
    services for the project. Robertson signed off on initial drawings and on final
    construction documents prepared by the architect for that purpose. He was
    12
    actively engaged in the design process, making comments to the drawings and
    suggesting revisions based on Soitis’s specific needs.          When Westwood’s
    counsel asked him at trial whether he had agreed to pay Westwood for its
    expenses in engaging the architect, Robertson said, “Yes.”
    Burtin testified about the process by which Westwood and Soitis entered
    into their oral agreement regarding the interior finish-out of the building. He
    explained as follows:
    Here’s how the process works: We . . . talked about okay,
    yes, our willingness to fill that role. And then what we typically do
    with every person, with every client, is we go through the process
    of design.
    Then after design is signed off on, then we go through the
    process of obtaining construction documents. And then after the
    construction documents are acquired, then they have to be bid out.
    And then we go through the selection of the bidding process to get
    the best contractor. And then that is awarded to that best
    contractor, and then we know a price at that point in time.
    He explained that it is impossible to determine a final price for the interior finish-
    out until the entire process is complete. However, he did testify regarding
    expenses that
    we would go through this process and get to a point where we
    have a number. And then at that point in time, we will add a
    margin on top of the best bid number. And then that is the number
    that we will use to add to the different expanded scope of work
    which was requested of us.
    13
    Thus, Burtin’s testimony corroborates Robertson’s that Soitis agreed to at least
    reimburse Westwood for its expenses related to providing the interior design
    services. Accordingly, we do not believe that the agreement was indefinite for
    failure to provide a final, agreed upon price for those services. See 
    Buxani, 940 S.W.2d at 353
    .
    Moreover, we do not believe that the agreement is unenforceable for lack
    of a specific term for completion of the services.          Burtin testified that
    Westwood representatives explained the interior design and construction
    process to Soitis, and the parties were actively engaged in the design process
    throughout the summer while the exterior shell construction was ongoing. The
    trial court found that Soitis initially intended to occupy the building and that it
    could save time and money by working on the interior finish-out during
    construction of the exterior as opposed to waiting until the exterior was
    completed before beginning the interior finish-out; appellants do not challenge
    that finding. Thus, the trial court impliedly found that Soitis intended for the
    interior finish-out to be completed within a reasonable time after construction
    of, and closing on, the exterior part of the building, so as to provide Soitis with
    the maximum savings of time and money.
    Based on the foregoing, we conclude and hold that the trial court did not
    err by determining that Soitis and Westwood entered into an enforceable oral
    14
    agreement for the interior finish-out of the building. We overrule appellants’
    first issue. Because appellants’ second issue—whether the trial court erred by
    determining that appellants anticipatorily repudiated the interior finish-out
    agreement—is contingent upon their argument that the oral agreement was
    unenforceable, we overrule their second issue as well.
    Whether Westwood Excused from Performing Under
    Agreement of Purchase and Sale
    In their third issue, appellants contend that the trial court erred by
    concluding that Westwood was excused from performing under the Agreement
    after appellants either anticipatorily repudiated or breached the second
    agreement for interior design services, or both.
    If, after a party breaches a contract, the other party continues to insist
    on performance by the defaulting party, the nondefaulting party is not excused
    from performing its part of the contract as a result of the defaulting party’s
    breach; the contract continues in force for the benefit of both parties. Kennedy
    Ship & Repair L.P. v. Pham, 
    210 S.W.3d 11
    , 25 (Tex. App.—Houston [14th
    Dist.] 2006, no pet.); Houston Belt & Terminal Ry. v. J. Weingarten, Inc., 
    421 S.W.2d 431
    , 435 (Tex. Civ. App.—Houston [1st Dist.] 1967, writ ref’d n.r.e.).
    Thus, when one party materially breaches a contract, the nondefaulting party
    is forced to elect between two courses of action, i.e., continuing performance
    15
    or ceasing performance. 
    Pham, 210 S.W.3d at 25
    ; Chilton Ins. Co. v. Pate &
    Pate Enters., Inc., 
    930 S.W.2d 877
    , 887–88 (Tex. App.—San Antonio 1996,
    writ denied). Treating the contract as continuing after a breach deprives the
    nondefaulting party of any excuse for terminating its own performance. 
    Pham, 210 S.W.3d at 25
    ; Chilton 
    Ins., 930 S.W.2d at 888
    .
    According to appellants, Westwood failed to elect which remedy it
    wished to pursue against appellants:     either (1) insist on performance and
    remain bound by all terms of the Agreement or (2) treat appellants’ actions as
    a breach and eschew any performance by appellants; in other words, appellants
    contend that by continuing to seek closing on the exterior, Westwood
    consciously decided to forego the benefit of being able to claim a prior breach
    of the Agreement by appellants. Appellants’ did not raise this argument at trial
    or in their pleadings, nor did they try it by consent.3 Mastin v. Mastin, 
    70 S.W.3d 148
    , 154 (Tex. App.—San Antonio 2001, no pet.) (“Trial by consent
    is intended to cover the exceptional case where it clearly appears from the
    record as a whole that the parties tried the unplead issue.”).         Because
    3
    … Although appellants’ counsel did ask several questions related to
    Westwood’s continuing construction of the shell after Robertson instructed
    them to put the building on hold, those questions were clearly related to an
    attempt to prove that Westwood, rather than appellants, was responsible for
    the delays in substantial completion of the exterior.
    16
    appellants’ argument is in the nature of an avoidance to Westwood’s
    affirmative defense of excuse, it too is an affirmative defense that appellants
    were required to plead. T EX. R. C IV. P. 94; Compass Bank v. MFP Fin. Servs,
    Inc., 
    152 S.W.3d 844
    , 852 (Tex. App.—Dallas 2005, pet. denied). Because
    they did not do so, they are not entitled to rely on Westwood’s alleged failure
    to elect its remedies to support reversal of the judgment on appeal. Compass
    
    Bank, 152 S.W.3d at 852
    , 857.
    Moreover, appellants did not challenge paragraph 34 of the trial court’s
    findings of fact and conclusions of law, which states, “Substantial completion
    of the building was timely, and all conditions precedent were met by
    Westwood.” Thus, appellants failed to challenge an alternative finding of the
    trial court that supports its judgment: that Westwood did not fail to perform
    its obligations under the Agreement. 4 We overrule appellants’ third issue.
    4
    … When findings of fact are filed and are unchallenged, they occupy the
    same position and are entitled to the same weight as the verdict of a jury; they
    are binding on an appellate court unless the contrary is established as a matter
    of law or there is no evidence to support the finding. McGalliard v. Kuhlmann,
    
    722 S.W.2d 694
    , 696 (Tex. 1986); Raman Chandler Props., L.C. v. Caldwell’s
    Creek Homeowners Ass’n, Inc., 
    178 S.W.3d 384
    , 390 (Tex. App.—Fort Worth
    2005, pet. denied).
    17
    Whether Appellants Estopped from Claiming Westwood Breached Agreement
    In their fourth issue, appellants contend that the trial court erred by
    concluding that appellants are estopped from claiming Westwood breached the
    Agreement first.   Initially, they contend that equitable principles, such as
    estoppel, are not applicable in breach of contract cases. Such a contention is
    incorrect, however, because estoppel is routinely applied by courts in contract
    cases. See, e.g., Cal-Tex. Lumber Co. v. Owens Handle Co., 
    989 S.W.2d 802
    ,
    821 (Tex. App.—Tyler 1999, no pet.); Wright Way Constr. Co. v. Harlingen
    Mall Co., 
    799 S.W.2d 415
    , 422 (Tex. App.—Corpus Christi 1990, writ denied).
    Next, appellants contend that there is no evidence to support an estoppel
    finding because the evidence does not support a finding that appellants
    intentionally misled Westwood, nor a finding that Westwood relied on any such
    misrepresentation or concealment to its detriment.
    Estoppel is defined in general as conduct which causes the other party to
    materially alter his position in reliance on that conduct. Roberts v. Clark, 
    188 S.W.3d 204
    , 213 (Tex. App.—Tyler 2002, pet. denied); Braugh v. Phillips, 
    557 S.W.2d 155
    , 158 (Tex. Civ. App.—Corpus Christi 1977, writ ref’d n.r.e.). To
    invoke the doctrine of estoppel, all the necessary elements of estoppel must be
    present. 
    Roberts, 188 S.W.3d at 213
    ; Douglas v. Aztec Petroleum Corp., 
    695 S.W.2d 312
    , 317 (Tex. App.—Tyler 1985, no writ). The elements of equitable
    18
    estoppel are (1) a false representation or concealment of material facts, (2)
    made with knowledge, actual or constructive, of those facts, (3) with the
    intention that it should be acted on, (4) to a party without knowledge or means
    of obtaining knowledge of the facts, (5) who detrimentally relies on the
    representations. Johnson & Higgins of Tex., Inc. v. Kenneco Energy, Inc., 
    962 S.W.2d 507
    , 515–16 (Tex. 1998); Argyle ISD ex rel. Bd. of Trustees v. Wolf,
    
    234 S.W.3d 229
    , 241 (Tex. App.—Fort Worth 2007, no pet.).
    One of the essential requisites of estoppel is a reasonable or justified
    reliance on the conduct or statements of the person sought to be estopped by
    the person seeking the benefit of the doctrine. 
    Roberts, 188 S.W.3d at 213
    ;
    
    Douglas, 695 S.W.2d at 317
    . The purpose of estoppel is for the protection of
    those who have been misled by that which upon its face was fair. 
    Roberts, 188 S.W.3d at 213
    ; 
    Douglas, 695 S.W.2d at 317
    . A person may not assert
    estoppel for the purpose of shielding himself from the results of his own
    dereliction of duty. 
    Roberts, 188 S.W.3d at 213
    ; 
    Douglas, 695 S.W.2d at 317
    .
    Misrepresentation or Concealment
    Appellants challenge the trial court’s findings that Soitis changed its
    business plan in the summer of 2005 and concealed this fact from Westwood
    as well as its intentions with regard to the building. It also challenges the trial
    court’s finding that Soitis never intended to agree on the outstanding issues and
    19
    misled Westwood into believing that it was going to close to obtain the benefit
    of additional contract defenses.      According to appellants, the evidence
    conclusively shows that Robertson candidly informed Westwood that Soitis no
    longer intended to occupy the building and that appellants fully intended to
    close on the building up until Robertson received the email from Burtin regarding
    Purchaser Delays.
    During closing arguments, the trial court stated the following:
    What concerns me about this is I’ve never been able to figure
    out based on the evidence I’ve heard, when your client [appellants]
    said they had the money, what justification they had that they kept
    stringing out the closing.
    ....
    . . . And then we have a series of reassuring e-mails and
    meetings accommodating the purchaser as the purchaser continues
    to lead on the builder that they’re going to close until, oddly
    enough, they get just past the number of days [Westwood] pointed
    out that might be arguably in the delay.
    ....
    . . . I pretty much have reached [the] conclusion that there’s
    some credibility issues on both sides - - and I’m worming my way
    through that.
    ....
    Pretty - - pretty limited testimony whenever a client says he
    didn’t look at it [referring to Robertson’s testimony that he did not
    know there was a possibility of terminating the Agreement until
    after Burtin sent the email alleging Purchaser Delays]. He didn’t
    20
    testify that he didn’t have lawyers reviewing it. I don’t think the
    Indianapolis law firm came up with an overnight opinion on the
    contract this size without consulting with its clients. It . . . does
    beg me to ignore reality.
    So in the engagement of the Indiana lawyers, it’s something
    the Court may inquire into, but I’m not . . . gonna buy into the fact
    that the Indiana lawyers were faxed the contract the night before
    they authored the termination advice and told the client to do it.
    It is clear from the trial court’s comments that the judge did not necessarily
    believe Robertson’s testimony regarding appellants’ intentions to close the
    Agreement.
    The trial court was entitled to disbelieve Robertson’s and Staneff’s
    testimony that Soitis intended to close on the building until just before the
    scheduled closing date; the trial court’s comments show that it instead
    construed Soitis’s failure to respond to Westwood’s closing inquiries with any
    firm details as an intent not to close if at all possible. As the finder of fact, the
    trial court was entitled to believe or disbelieve all or part of any witness’s
    testimony. See Shear Cuts, Inc. v. Littlejohn, 
    141 S.W.3d 264
    , 270–71 (Tex.
    App.—Fort Worth 2004, no pet.). Accordingly, there is sufficient evidence to
    support the trial court’s finding of misrepresentation, concealment, or both on
    the part of Soitis as to its intentions regarding closing.
    Reliance
    21
    Appellants also contend that Westwood cannot have relied on any
    misrepresentation or concealment because the evidence shows that Westwood
    nevertheless continued construction of the building even after Robertson’s
    November 7, 2005 instructions to stop work on the building. However, Burtin
    testified that because of Robertson’s instruction, Westwood did not press to
    obtain a certificate of occupancy for the exterior shell. According to Burtin, had
    Robertson not given that instruction, Westwood would have pressed the
    construction contractor to complete installation of the last item needed—the
    wall mounted light—so that a certificate could be issued. And if Westwood had
    been able to obtain that certificate, appellants would not have been able to
    terminate for the reason they relied on at trial—that construction of the exterior
    was not substantially complete as defined in the Agreement because a
    certificate of occupancy had not been issued for the shell. We conclude that
    this is sufficient evidence to support the trial court’s findings and conclusions
    on estoppel.
    We overrule appellants’ fourth issue.
    Whether Trial Court Correctly Concluded That Appellants Waived Right to
    Terminate Because of Westwood’s Failure to Substantially Complete
    In their fifth and final issue, appellants contend that the trial court erred
    by concluding that Soitis waived any failure by Westwood to comply with all
    22
    of its obligations under the Agreement.     According to appellants, because
    waiver requires a knowing and intentional relinquishment of a right—and
    Robertson did not know the extent of appellants’ rights under the Agreement
    until he reviewed it after receiving Burtin’s January 21 email—appellants cannot
    have waived those enforcement rights.
    However, we have already pointed out the trial court’s skepticism
    regarding Robertson’s knowledge of the extent of the contents of the
    Agreement. Moreover, a party to a contract is presumed to have read and
    understood its contents. UBS Fin. Servs., Inc. v. Branton, 
    241 S.W.3d 179
    ,
    189 (Tex. App.—Fort Worth 2007, no pet.); see Mikey’s Houses LLC v. Bank
    of Am., N.A., 
    232 S.W.3d 145
    , 167 (Tex. App.—Fort Worth 2007, no pet.
    [mand. pending]) (Livingston, J., dissenting). Accordingly, we conclude and
    hold that the trial court did not err by concluding that appellants waived any
    failure of Westwood to comply with the Agreement. We overrule appellants’
    fifth and final issue.
    Conclusion
    Having overruled appellants’ five issues, we affirm the trial court’s
    judgment.
    TERRIE LIVINGSTON
    JUSTICE
    PANEL: CAYCE, C.J.; LIVINGSTON and HOLMAN, JJ.
    DELIVERED: August 14, 2008
    23