Shawn Shamaei v. Keith Conway ( 2015 )


Menu:
  •                         COURT OF APPEALS
    SECOND DISTRICT OF TEXAS
    FORT WORTH
    NO. 02-14-00358-CV
    SHAWN SHAMAEI                                                     APPELLANT
    V.
    KEITH CONWAY                                                       APPELLEE
    ----------
    FROM COUNTY COURT AT LAW NO. 3 OF TARRANT COUNTY
    TRIAL COURT NO. 2013-005639-3
    ----------
    MEMORANDUM OPINION1
    ----------
    I. Introduction
    In a single issue, appellant Shawn Shamaei appeals from the trial court’s
    judgment awarding recovery to appellee Keith Conway on his breach of contract
    claim. We affirm.
    1
    See Tex. R. App. P. 47.4.
    II. Facts
    In December 2012, Shamaei and Conway entered into an oral contract
    whereby Conway, a licensed architect, would prepare architectural plans to
    remodel a building owned by Shamaei. Shamaei needed the renovation work to
    prevent the City of Euless from demolishing his building.
    Although both parties agreed that Conway’s compensation rate was $50
    per hour, the parties disagreed as to the total amount that was agreed to be paid
    under the contract. Conway testified that they agreed he would receive $50 per
    hour until the architectural work was completed, but Shamaei testified that
    Conway would receive $50 per hour, not to exceed $5,000, representing no more
    than 100 total hours of work.2
    Conway worked on the project from mid-December 2012 until the end of
    February 2013 and submitted periodic invoices to Shamaei totaling $15,450.
    2
    Shamaei testified as follows:
    A: [H]e told me that he’s going to charge me $50 per hour.
    And I ask him how long does it take him to do -- how long -- how
    does he charge. He says he does by the hour. And I told him by
    measurement and the design that he has, how long is [it] going to
    take him to do it? He said maximum a hundred hours. I knew it was
    too much for that, you know, 1300 square feet building, but I did it for
    100 hours maximum for $50 per hour.
    Q: So that’s $5,000?
    A: $5,000 his fee exactly.
    2
    Shamaei paid some, but not all, of the invoices, leaving an unpaid balance of
    $9,450.     Shamaei did not complain about any of the amounts billed until
    approximately a month after the final invoice had been submitted, by which time
    Shamaei had used the architectural services provided by Conway, the
    remodeling work had been completed, and the building had been saved from
    demolition. Conway sued Shamaei for breach of contract after Shamaei refused
    to pay his final invoice.
    The trial court awarded $7,8503 to Conway on the contract claim, plus
    attorney’s fees, prejudgment interest, post judgment interest, and costs. Neither
    party requested findings of fact and conclusions of law, and none were made by
    the trial court.
    III. Analysis
    In his single issue, Shamaei complains that the trial court erred by finding
    that a contract existed because an essential term was missing, i.e., the maximum
    amount of hours it would take to complete the work, and because Conway failed
    to present any evidence of the reasonable value for the architectural services
    rendered.
    3
    This figure took into account Conway’s testimony that he had mistakenly
    over-billed Shamaei in the amount of $1,000, along with a subtraction of $600
    that Conway billed for a “site visit” and that the trial court apparently found not to
    be part of the agreement.
    3
    A. Standard of Review
    In a trial to the court in which no findings of fact or conclusions of law are
    filed, the trial court’s judgment implies all findings of fact necessary to support it.
    Rosemond v. Al-Lahiq, 
    331 S.W.3d 764
    , 766–67 (Tex. 2011); Wood v. Tex. Dep’t
    of Pub. Safety, 
    331 S.W.3d 78
    , 79 (Tex. App.—Fort Worth 2010, no pet.). When
    a reporter’s record is filed, however, these implied findings are not conclusive,
    and an appellant may challenge them by raising both legal and factual sufficiency
    of the evidence issues. When such issues are raised, the applicable standard of
    review is the same as that to be applied in the review of jury findings or a trial
    court’s findings of fact.   Roberson v. Robinson, 
    768 S.W.2d 280
    , 281 (Tex.
    1989); Liberty Mut. Ins. Co. v. Burk, 
    295 S.W.3d 771
    , 777 (Tex. App.—Fort
    Worth 2009, no pet.). The judgment must be affirmed if it can be upheld on any
    legal theory that finds support in the record. 
    Rosemond, 331 S.W.3d at 767
    ;
    Liberty 
    Mut., 295 S.W.3d at 777
    .
    We may sustain a legal sufficiency challenge only when (1) the record
    discloses a complete absence of evidence of a vital fact; (2) the court is barred
    by rules of law or of evidence from giving weight to the only evidence offered to
    prove a vital fact; (3) the evidence offered to prove a vital fact is no more than a
    mere scintilla; or (4) the evidence establishes conclusively the opposite of a vital
    fact. Uniroyal Goodrich Tire Co. v. Martinez, 
    977 S.W.2d 328
    , 334 (Tex. 1998),
    cert. denied, 
    526 U.S. 1040
    (1999); Robert W. Calvert, “No Evidence” and
    “Insufficient Evidence” Points of Error, 
    38 Tex. L. Rev. 361
    , 362–63 (1960). In
    4
    determining whether there is legally sufficient evidence to support the finding
    under review, we must consider evidence favorable to the finding if a reasonable
    factfinder could and disregard evidence contrary to the finding unless a
    reasonable factfinder could not. Cent. Ready Mix Concrete Co. v. Islas, 
    228 S.W.3d 649
    , 651 (Tex. 2007); City of Keller v. Wilson, 
    168 S.W.3d 802
    , 807, 827
    (Tex. 2005).
    Anything more than a scintilla of evidence is legally sufficient to support the
    finding. Cont’l Coffee Prods. Co. v. Cazarez, 
    937 S.W.2d 444
    , 450 (Tex. 1996);
    Leitch v. Hornsby, 
    935 S.W.2d 114
    , 118 (Tex. 1996). More than a scintilla of
    evidence exists if the evidence furnishes some reasonable basis for differing
    conclusions by reasonable minds about the existence of a vital fact. Rocor Int’l,
    Inc. v. Nat’l Union Fire Ins. Co., 
    77 S.W.3d 253
    , 262 (Tex. 2002).
    Any ultimate fact may be proved by circumstantial evidence. Russell v.
    Russell, 
    865 S.W.2d 929
    , 933 (Tex. 1993).              A fact is established by
    circumstantial evidence when the fact may be fairly and reasonably inferred from
    other facts proved in the case. 
    Id. B. Terms
    of the Contract
    Shamaei argues that trial court erred by permitting recovery because there
    was no agreement on the maximum number of hours it would take to complete
    the job. Without a cap on the number of hours to be worked, the total maximum
    5
    contract price cannot be calculated.4     Shamaei argues that a total maximum
    contract price is an “essential term,” without which the contract is unenforceable.
    While Shamaei is correct that essential terms of a contract must be agreed
    upon before a court can enforce it, see T.O. Stanley Boot Co. v. Bank of El Paso,
    
    847 S.W.2d 218
    , 221 (Tex. 1992), when parties have done everything else
    necessary to make a binding agreement for services, even the failure to specify a
    price will not leave the contract so incomplete that it cannot be enforced.
    Pennington v. Gurkoff, 
    899 S.W.2d 767
    , 770 (Tex. App.—Fort Worth 1995, writ
    denied).   In such a case, a presumption arises that a reasonable price was
    intended. 
    Id. (citing Bendalin
    v. Delgado, 
    406 S.W.2d 897
    , 900 (Tex. 1966);
    Polland & Cook v. Lehmann, 
    832 S.W.2d 729
    , 739–40 (Tex. App.—Houston [1st
    Dist.] 1992, writ denied)).
    In this case, Shamaei received Conway’s second invoice by email on
    February 23. This invoice billed for 110 hours of Conway’s work, an amount
    which, on its face, exceeded the 100-hour ceiling Shamaei had sought to
    impose.5 At this point, the job was still not complete. Yet Shamaei allowed
    Conway to continue work on the project without a single protest, complaint, or
    4
    We infer from the judgment that the trial court found that a 100-hour cap
    on Conway’s services was not part of the agreement. See 
    Rosemond, 331 S.W.3d at 766
    –67; 
    Wood, 331 S.W.3d at 79
    .
    5
    When combined with the January 14 invoice, by February 23 Conway had
    billed Shamaei for a total of 178 hours of work.
    6
    objection as to the number of hours Conway had expended on the project to
    date.
    Moreover, faced with invoices that exceeded 100 hours almost two-fold,
    Shamaei continued to actively engage Conway in the final push to finalize the
    plans and obtain City permits necessary for the renovation process.          Text
    communications exchanged between the parties during this critical period of time
    demonstrate a flurry of activity between Shamaei and Conway related to the
    project.6 On February 27, Shamaei specifically directed Conway’s work, asking
    him to respond to an email from a city official and to change the location of the
    dumpster on the plans in order to finalize the permit process with the City. These
    communications evidence an ongoing agreement between the parties to work
    beyond the hours already expended by Conway to get the plans approved and
    the architectural work done.
    On March 4, the permit was approved and Conway had ceased billing for
    his time. Four days later, Shamaei received the third and final invoice, which
    added another fifty hours of work for those last days leading up to final City
    approval. Rather than speak up when faced with invoices that had more than
    doubled what Shamaei claimed was the agreed-upon limit, the record reflects
    that Shamaei again remained silent. Not until almost a month later, after he had
    6
    Included were discussions regarding matters such as reviewing the City of
    Euless’s comments to the architectural plans and identifying the types of
    chemicals that would be stored on the premises.
    7
    used Conway’s architectural plans to complete his renovation project and save
    his building from demolition, did Shamaei, in response to a request for final
    payment by Conway, first claim he did not believe the invoiced time was
    reasonable.
    Given the conduct and course of dealings between the parties as reflected
    in the record, the trial court could have found that Shamaei accepted Conway’s
    ongoing work as reasonable and necessary to complete the job. Because the
    record reveals more than a scintilla of evidence to support the finding that the
    hours as billed by Conway in performing the contract were reasonable, we hold
    that the evidence is legally sufficient to support the judgment. See Tex. Delta
    Upsilon Found. v. Fehr, 
    307 S.W.2d 124
    , 131–32 (Tex. Civ. App.—Austin 1957,
    writ ref’d n.r.e.) (holding evidence sufficient to support jury finding on reasonable
    value of architects’ services under contract that had no cost limitation but only an
    estimated cost approximation and finding a duty on the part of the client to inform
    the architects that their services were no longer desired when cost became a
    factor; otherwise, a duty on the part of the architect to continue to work).
    We overrule Shamaei’s sole issue.
    IV. Conclusion
    Having overruled Shamaei’s sole issue, we affirm the trial court’s
    judgment.
    /s/ Bonnie Sudderth
    BONNIE SUDDERTH
    JUSTICE
    8
    PANEL: LIVINGSTON, C.J.; DAUPHINOT and SUDDERTH, JJ.
    DELIVERED: April 30, 2015
    9