Stewart & Stevenson, LLC v. Brady Foret ( 2013 )


Menu:
  • Opinion issued August 15, 2013
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-11-01032-CV
    ———————————
    STEWART & STEVENSON, LLC, Appellant
    V.
    BRADY FORET, Appellee
    On Appeal from the 80th District Court
    Harris County, Texas
    Trial Court Case No. 2009-80709
    MEMORANDUM OPINION
    Appellant, Stewart & Stevenson, LLC, challenges the trial court’s judgment,
    entered after a jury trial, in favor of appellee, Brady Foret, in Foret’s suit against
    Stewart & Stevenson for negligence.         In three issues, Stewart & Stevenson
    contends that the trial court erred in not including in its jury charge an instruction
    on the law of responsible third parties,1 awarding excessive future damages, and
    admitting Foret’s late-filed evidence.
    We affirm.
    Background
    In his fourth amended petition, Foret alleged that on January 11, 2009, while
    he was working as a “derrick man” for Key Energy Services, LLC (“Key Energy”)
    on a 112-foot land-based oil drilling rig (“Rig 65”), the mast collapsed, causing
    him to fall over eighty feet to the ground and suffer severe injuries. Rig 65 had
    previously been refurbished and inspected by Stewart & Stevenson at its facility in
    Odessa, Texas. However, Rig 65 collapsed because it was missing at least two
    “safety pins and retainer pins” and “critical safety equipment” that should have
    been provided by Stewart & Stevenson during the refurbishment. Foret, who was
    twenty-three years old at the time of Rig 65’s collapse, “sustained severe bodily
    injuries, including orthopedic injuries and a traumatic brain injury, which have
    resulted in physical pain, mental anguish and other medical problems, including
    1
    See TEX. CIV. PRAC. & REM. CODE ANN. § 33.004 (Vernon 2012).
    2
    disfigurement and impairment.”         Foret sought to recover from Stewart &
    Stevenson $10,702,459.52 in damages.2
    In its second amended answer, Stewart & Stevenson generally denied
    Foret’s allegations, asserting that Foret’s injuries were caused by his own
    negligence or the negligence of “third parties over whom [Stewart & Stevenson]
    had no control or right of control.” Before trial, Stewart & Stevenson filed its
    “Motion to Designate Responsible Third Parties,” seeking to designate Apache
    Corporation (“Apache”), Robert McLemore, and Key Energy as responsible third
    parties. Apache was the well site owner and operator at the time of Rig 65’s
    collapse, and McLemore was the “company man,” working for Apache and
    responsible for overseeing the operation.       Stewart & Stevenson alleged that
    Apache and McLemore were negligent in “improperly using a foundation/pad that
    was designed and constructed for use by a different drilling rig”; failing to “design
    and construct a foundation/pad for the drilling rig”; “ensure that the drilling rig was
    properly equipped with all safety devices”; “adequately inspect the drilling rig”;
    and “provide a safe workplace.”
    After the trial court granted Stewart & Stevenson’s motion, Foret filed a
    “Motion to Strike Designated Responsible Third Parties,” arguing that the collapse
    2
    In his original petition, Foret also brought claims against T.K. Stanley, Inc.,
    alleging that T.K. Stanley was negligent in constructing the foundation on which
    the rig stood. However, Foret later non-suited his claims against T.K. Stanley.
    3
    of Rig 65 occurred solely because “the derrick was missing critical pins for support
    and essential for safety.” Foret asserted that Rig 65’s collapse occurred on its first
    use after being refurbished by Stewart & Stevenson, which had produced no
    evidence to indicate that Apache, McLemore, or Key Energy were responsible for
    his injuries. Foret also noted that Apache was found not liable for Rig 65’s
    collapse in a companion case filed in the United States District Court for the
    Eastern District of Louisiana.
    Stewart & Stevenson later filed a “Motion to Strike [Foret’s] Late-Filed
    Discovery,” asserting that Foret had produced to Stewart & Stevenson, after the
    July 1, 2011 discovery deadline, among other evidence, a medical report from Dr.
    Paul J. Hubbell, III on July 7, 2011 and an expert report from Terry Arnold on July
    11, 2011. In her report, Arnold produced a “Life Care Plan” for Foret, opining that
    Foret would incur $679,296 in future medical and related needs.           Stewart &
    Stevenson alleged that Arnold’s report was based, in part, on the late-filed medical
    report of Hubbell, who estimated that Foret would require $259,710 in pain-
    management treatment.
    Foret testified that on January 11, 2009, he was assigned as a ‘derrickman”
    on Rig 65, which was then located in Golden Meadow, Louisiana.                  As a
    derrickman, Foret stood on a platform, referred to as a “monkey board,” hanging
    off the side of Rig 65’s mast, approximately eighty feet off of the ground. It was
    4
    his job to stand on the platform and “rack” the drill pipes on the mast, change the
    pipes, and ensure that they were aligned correctly. When Foret began work on Rig
    65, it was “flagged,” meaning that another derrickman had set up the rig to be
    worked on.      He explained that before Rig 65 collapsed, he did not see any
    indication that it was tipping one way or another. And, as he was working on the
    monkey board, Foret suddenly heard “a loud pop” from above and felt the rig “start
    to collapse.”
    Foret’s next memory was of waking up the next day in a hospital with a
    ventilator hooked up to his throat and his jaw wired shut because he had undergone
    jaw surgery while unconscious.        His head, face, and right eye were swollen,
    making it difficult for him to see out of the eye. Foret also suffered a broken
    shoulder blade, a torn rotator cuff, a torn tricep, several rib fractures, a torn
    posterior cruciate ligament in his left knee, a collapsed lung, and several spinal
    fractures. At the time of trial, Foret still felt back pain, suffered from recurring
    knee problems, and had short-term memory loss. And he explained that he would
    have to undergo cognitive rehabilitation therapy for his injuries for the rest of his
    life.
    Foret offered, and the trial court admitted, into evidence a report prepared by
    Francisco Godoy and Roger Craddock of Engineering Systems Incorporated
    (“ESI”), analyzing the cause of Rig 65’s collapse. In their report, Godoy and
    5
    Craddock explained that Rig 65’s mast consisted of a lower and an upper section,
    which are connected at four sets of “pawls.” When the upper mast was extended,
    the pawls were simultaneously lifted, transferring the weight of the upper mast to
    the lower mast through the pawls.        The pawls each contained a “link lock
    mechanism” that secured them to the mast with a locking, or safety, pin. Each set
    of pawls required its own locking pin; so, properly constructed, Rig 65 should have
    contained four locking pins for each set of pawls.
    Godoy and Craddock opined that when the pawls were lifted on Rig 65 on
    the date of the collapse, it was “highly likely” that a locking pin became loose due
    to “mechanical vibrations or other mechanical operations.” When the locking pin
    became loose, the “entire upper mast load, which was supported evenly on both
    sides, suddenly became supported” on only the “‘Off Driller’ side left leg” of Rig
    65. As a result, the weight placed on the Off Driller side of the left leg “exceeded
    the maximum allowable” and caused Rig 65 to begin to buckle. Eventually, the
    upper pawl on the Off Driller side “slipped or skidded” off the lower pawl, the
    upper mast started to lean towards the left, eventually causing it to detach from the
    lower mast and collapse Rig 65. Godoy and Craddock concluded that: (1) if Rig
    65 “had been provided with the four locking pins, it is unlikely that the collapse
    would have occurred”; (2) Stewart & Stevenson should have, but did not, provide
    Rig 65 with four locking pins during repair; (3) Stewart & Stevenson’s inspectors
    6
    “were not well enough trained and knowledgeable”; and (4) because “the rig was
    able to accommodate the extra forces applied by the tautening of the guy-wires,”
    the tautening “could not have been the cause of the buckling that caused the final
    collapse of the rig.” At trial, Godoy testified to the same facts and conclusions.
    Mark Henderson testified that he was the general manager of Stewart &
    Stevenson’s Odessa facility beginning in November 2008.           He estimated that
    Stewart & Stevenson finished its refurbishment of Rig 65 between April and July
    2008. After Rig 65 had been shipped for on-site work in Louisiana, Stewart &
    Stevenson received a call from Key Energy requesting a technician to provide a
    “replacement pin” for Rig 65. Henderson noted that after refurbishing a mast,
    Stewart & Stevenson would have a quality-control technician test and certify the
    mast before it left the Odessa facility.
    Roy Mendoza, a Stewart & Stevenson quality-control technician, testified
    that he conducted the final inspection of Rig 65. He noted that, if he had noticed
    any missing locking pins, he would have reported it on the final inspection
    checklist. Mendoza did not recall whether the technician made sure the locking
    pins fit where they were supposed to fit. He was also not aware of how many
    locking pins Rig 65 required, but he agreed that a Stewart & Stevenson employee
    must have been responsible for ensuring that all of the locking pins were in place.
    7
    Mendoza marked on his checklist that the mast was sufficient even though he had
    only seen two locking pins on it.
    Jose Barron, the Stewart & Stevenson refurbishment manager in July 2008,
    testified that he was responsible for the employees who refurbished and certified
    Rig 65. He performed his own inspection, an “AESC Category 4 Inspection,” of
    Rig 65 after the refurbishment work had been completed. Barron noted that one of
    the purposes of an AESC Category 4 Inspection is to ensure that the locking
    system is working adequately. He admitted that if Rig 65 was missing two locking
    pins, it would not have met industry standards. However, Barron further testified
    that, even with only two locking pins, the rig should have been able to carry the
    maximum load of 300,000 pounds, as represented by Stewart & Stevenson.
    John Michael Garber, an environmental, health, and safety coordinator with
    Apache, testified that Apache did not perform a safety audit on Rig 65 prior to its
    use. After the collapse of Rig 65, he interviewed the Key Energy employees who
    were at the site, and they told him that there was nothing “abnormal” about the site,
    except that the pollution pans, which had been attached to the rig’s foundation so
    as to store contaminated pipe segments, had begun sinking about “six to seven
    inches.” Garber noted that Apache, through McLemore, had been informed of the
    sinkage the day before the collapse, and McLemore decided to take the pipes out of
    the pollution pans and place them back into the well.
    8
    Tracy Lee Duhon, a floor hand at the time of the collapse, testified that on
    January 8 and 9, Key Energy realized that the rig had a “misalignment problem,”
    which it attempted to fix by using hydraulic jacks. And, on January 10, Duhon
    was told to go back into the well because the pollution pans had started to sink.
    Joshua Matthews, who worked on Rig 65 with Foret, testified that on their
    first day working on the rig, they experienced some problems with the derrick
    “leaning too far.” The problem could not be fixed with hydraulic rams, and a later
    attempt was made to fix the problem by pulling on the pipe with “chain and cable”
    in an effort to properly align it, which also did not work. By the second day,
    Matthews noticed some movement in the foundation of Rig 65, but he did not think
    that it was behaving abnormally. On the third day, January 10, Matthews was told
    that pipes were being moved out of the pollution pan and back into the well so
    “they could fix the area where the [pollution] pans were sitting.” When they were
    down to thirty-three segments of pipe to place back into the well, Rig 65 collapsed.
    Roland Duhon, a foreman for Apache, testified that after the collapse,
    Apache contacted T.K. Stanley, Inc., which had constructed the foundation of Rig
    65, to remediate the foundation. Duhon noted that, if Rig 65 was having “pole
    alignment problems,” he would have relied on McLemore to “shut the operation
    down” until “things [were] safe.” He opined that Key Energy was “ultimately
    responsible” for inspecting Rig 65 and its foundation, and he explained that the
    9
    sinkage problem had to be addressed before another rig was placed on the
    foundation.
    Clyde Ned, the “rig supervisor” of Rig 65, testified that had he known that
    the rig was missing its safety pins, they would have welded their own pins to the
    rig. However, he thought a rig with two out of four pins would be “safe to use.”
    Ned explained that adjusting guy wires, wires which were attached to the top of
    Rig 65’s mast to help keep it stable, should not be used to correct alignment
    problems. And Casey Trahan, a driller floorhand on Rig 65, testified that the crew
    had tried to “tighten up” the guy wires to correct the alignment problem.
    Timothy Popik, Stewart & Stevenson’s engineering manager, testified that
    Rig 65 was “having an issue with the settling from the pollution pans,” which
    caused alignment problems and made the pipe strike the side of the foundation.
    Key Energy then decided to fix the alignment using hydraulic jacks and tightening
    the guy wires, which was not “a proper way to proceed.” Tightening the guy wires
    produced “extra stress and tension on the mast,” eventually causing the mast to tip
    over.
    In questions one and two of its charge, the trial court asked the jury to
    determine whether the negligence of Stewart & Stevenson and Key Energy
    proximately caused Foret’s injuries and, if so, to apportion a percentage of
    responsibility to each. At the charge conference, Stewart & Stevenson objected to
    10
    questions one and two because they did not include Apache or McLemore “as
    potentially responsible parties.” Specifically, Stewart & Stevenson asserted that
    “the testimony from the experts essentially is that . . . an improper use of the guy-
    wires . . . led to the [collapse].” However, the trial court concluded that “it doesn’t
    appear from the expert testimony that Apache was opined to have caused in whole
    or in part the collapse of the mast due to something that they did negligently,” and
    it overruled Stewart & Stevenson’s objection.
    The jury found that the negligence of both Stewart & Stevenson and Key
    Energy caused Foret’s injuries, and it apportioned 85% of the responsibility to
    Stewart & Stevenson and 15% to Key Energy.              The jury further found that
    $135,145 would compensate Foret for his loss of past earning capacity, $2,000,000
    for his loss of future earning capacity, $1,000,000 for his past physical pain and
    mental anguish, $5,000,000 for his future physical pain and mental anguish,
    $850,000 for his physical impairment, $1,000,000 for his future physical
    impairment, $69,678.53 for his past medical expenses, and $647,636 for his future
    medical expenses. The trial court then entered judgment on the jury’s verdict,
    ordering Stewart & Stevenson liable for the entire damage award.
    Jury Charge
    In its first issue, Stewart & Stevenson argues that the trial court erred in not
    asking the jury to determine whether Apache and McLemore were also responsible
    11
    for Foret’s injuries because “the evidence and pleadings show” that their
    negligence caused or contributed to his injuries.
    We review a trial court’s decision to submit or refuse a particular jury
    question or instruction for an abuse of discretion. See La.-Pac. Corp. v. Knighten,
    
    976 S.W.2d 674
    , 676 (Tex. 1998) (per curiam). When a trial court refuses to
    submit a requested jury question or instruction on an issue raised by the pleadings
    and evidence, the question on appeal is whether the request was reasonably
    necessary to enable the jury to render a proper verdict. Tex. Workers’ Comp. Ins.
    Fund v. Mandlbauer, 
    34 S.W.3d 909
    , 912 (Tex. 2000) (per curiam) (citing TEX. R.
    CIV. P. 277, 278).
    A trial court must submit to a jury questions, instructions, and definitions
    that the pleadings and evidence raise. See TEX. R. CIV. P. 278; Elbaor v. Smith,
    
    845 S.W.2d 240
    , 243 (Tex. 1992). A trial court may refuse to submit a jury
    question only if no evidence exists to warrant its submission. See 
    Elbaor, 845 S.W.2d at 243
    ; Brown v. Goldstein, 
    685 S.W.2d 640
    , 641 (Tex. 1985) (citing
    Garza v. Alviar, 
    395 S.W.2d 821
    , 824 (Tex. 1965)). That is, a trial court is
    obligated to submit to the jury an issue if the evidence on the issue “amounts to
    more than a scintilla.” Roy v. Howard-Glendale Funeral Home, 
    820 S.W.2d 844
    ,
    846 (Tex. App.—Houston [1st Dist.] 1991, writ denied). To rise above a scintilla,
    the evidence offered to prove a vital fact must do more than create a mere surmise
    12
    or suspicion of its existence. See Kindred v. Con/Chem, Inc., 
    650 S.W.2d 61
    , 63
    (Tex. 1983). More than a scintilla of evidence exists when the evidence, as a
    whole, rises to a level that would enable reasonable and fair-minded people to
    differ in their conclusions. See Burroughs Wellcome Co. v. Crye, 
    907 S.W.2d 497
    ,
    499 (Tex. 1995). Conflicting evidence presents a fact question for the jury to
    decide. Gunn Infiniti, Inc. v. O’Byrne, 
    996 S.W.2d 854
    , 862 (Tex. 1999) (Baker,
    J., dissenting); 
    Brown, 685 S.W.2d at 641
    –42; Phillips Pipeline Co. v. Richardson,
    
    680 S.W.2d 43
    , 48 (Tex. App.—El Paso 1984, no writ).
    The Texas Civil Practice and Remedies Code provides that,
    (a)   The trier of fact, as to each cause of action asserted, shall
    determine the percentage of responsibility, stated in whole
    numbers, for the following persons with respect to each
    person’s causing or contributing to cause in any way the harm
    for which recovery of damages is sought, whether by negligent
    act or omission, by any defective or unreasonably dangerous
    product, by other conduct or activity that violates an applicable
    legal standard, or by any combination of these:
    (1)   each claimant;
    (2)   each defendant;
    (3)   each settling person; and
    (4)   each responsible third party who has been designated
    under Section 33.004.
    13
    (b)    This section does not allow a submission to the jury of a
    question regarding conduct by any person without sufficient
    evidence to support the submission.
    TEX. CIV. PRAC. & REM. CODE ANN. § 33.003 (Vernon 2012) (emphasis added).
    A responsible third party is “any person who is alleged to have caused or
    contributed to causing in any way the harm for which recovery of damages is
    sought, whether by negligent act or omission, by any defective or unreasonably
    dangerous product, by other conduct or activity that violates an applicable legal
    standard, or by any combination of these.”         
    Id. § 33.011(6)
    (Vernon 2012).
    Therefore, a party is entitled, upon request, to a jury charge that includes a
    responsible third party in apportioning responsibility if sufficient evidence supports
    its submission. See F.F.P. Operating Partners, L.P. v. Duenez, 
    237 S.W.3d 680
    ,
    694 (Tex. 2007). Evidence is insufficient to support submission of a jury question
    when (1) there is a complete absence of evidence establishing a vital fact, (2) the
    court is barred by rules of law or of evidence from giving weight to the only
    evidence of a vital fact, (3) the evidence offered to prove a vital fact is no more
    than a mere scintilla, or (4) the evidence conclusively establishes the opposite of a
    vital fact. See City of Keller v. Wilson, 
    168 S.W.3d 802
    , 810 (Tex. 2005).
    Stewart & Stevenson argues that because there is evidence that Apache and
    McLemore were negligent in not shutting down Rig 65’s operations before its
    collapse, supplying a faulty foundation for Rig 65, and permitting Key Energy to
    14
    attempt to fix the alignment problems in Rig 65 by tightening the guy wires, there
    is more than a scintilla of evidence that Apache and McLemore’s negligence
    caused or contributed to the cause of Rig 65’s collapse.
    Foret argues that the trial court did not err in not including in its jury charge
    Apache and McLemore as responsible third parties because there is no evidence
    that Apache, McLemore’s employer, “retained a contractual right of control over
    the work performed by subcontractors, including Key [Energy].” In support of its
    argument, Foret cites section 95.003 of the Texas Civil Practice and Remedies
    Code, which provides:
    A property owner is not liable for personal injury, death, or property
    damage to a contractor, subcontractor, or an employee of a contractor
    or subcontractor who constructs, repairs, renovates, or modifies an
    improvement to real property, including personal injury, death, or
    property damage arising from the failure to provide a safe workplace
    unless:
    (1)   the property owner exercises or retains some control over
    the manner in which the work is performed, other than
    the right to order the work to start or stop or to inspect
    progress or receive reports; and
    (2)   the property owner had actual knowledge of the danger
    or condition resulting in the personal injury, death, or
    property damage and failed to adequately warn.
    TEX. CIV. PRAC. & REM. CODE ANN. § 95.003 (Vernon 2012). In response, Stewart
    & Stevenson asserts that Foret has waived his argument by not raising it at the trial
    court’s charge conference, Louisiana law would apply instead of section 95.003,
    15
    and a property owner’s liability under section 95.003 is irrelevant to the
    designation of Apache and McLemore as a responsible third parties under section
    33.003.
    Regardless of Chapter 95,3 Chapter 33 requires a responsible third party to
    have committed a “negligent act or omission” that “caused or contributed to
    causing in any way the harm for which recovery of damages is sought.” TEX. CIV.
    PRAC. & REM. CODE ANN. § 33.011(6).             And the common law doctrine of
    negligence consists of three elements: (1) a legal duty owed by one person to
    another; (2) a breach of that duty; and (3) damages proximately resulting from the
    breach. El Chico Corp. v. Poole, 
    732 S.W.2d 306
    , 311 (Tex. 1987); Rosas v.
    Buddie’s Food Store, 
    518 S.W.2d 534
    , 536 (Tex. 1975). The threshold inquiry in a
    negligence case is duty. El 
    Chico, 732 S.W.2d at 311
    . A duty “is a legally
    enforceable obligation to comply with a certain standard of conduct.”4 Hand v.
    Dean Witter Reynolds Inc., 
    889 S.W.2d 483
    , 491 (Tex. App.—Houston [14th
    3
    We note that Chapter 95 simply served to codify Texas’s common-law approach
    to premises-owner liability set out in Redinger v. Living, Inc., 
    689 S.W.2d 415
    ,
    418 (Tex. 1985). See also Johnston v. Oiltanking Hous., L.P., 
    367 S.W.3d 412
    ,
    416 (Tex. App.—Houston [14th Dist.] 2012, no pet.). Chapter 95 further limited
    a premises owner’s liability by requiring a plaintiff to prove that the owner had
    knowledge of a dangerous condition on the premises, an issue not presented in this
    case. See 
    Johnson, 367 S.W.3d at 416
    .
    4
    Stewart & Stevenson does not contend that Louisiana law on the issue of duty in
    negligence cases is any different than Texas law.
    16
    Dist.] 1994, writ denied) (citing Way v. Boy Scouts of Am., 
    856 S.W.2d 230
    , 233
    (Tex. App.—Dallas 1993, writ denied)).
    Generally, a premises owner or general contractor does not have a duty to
    see that a subcontractor performs work in a safe manner.5 Abarca v. Scott Morgan
    Residential, Inc., 
    305 S.W.3d 110
    , 126 (Tex. App.—Houston [1st Dist.] 2009, pet.
    denied) (citing Redinger v. Living, Inc., 
    689 S.W.2d 415
    , 418 (Tex. 1985)).
    However, a limited duty arises if a premises owner or general contractor retains
    control over a subcontractor’s methods of work or operative details to the point
    that the subcontractor is not entirely free to do the work in his own way. 
    Abarca, 305 S.W.3d at 126
    (citing Koch Ref. Co. v. Chapa, 
    11 S.W.3d 153
    , 154 (Tex.
    1999)). The premises owner or general contractor’s “duty of reasonable care is
    commensurate with the control it retains” over the subcontractor.            Hoechst–
    Celanese Corp. v. Mendez, 
    967 S.W.2d 354
    , 355 (Tex. 1998) (per curiam).
    General supervisory control that does not relate to the activity causing the injury is
    not sufficient to create a duty.     
    Abarca, 305 S.W.3d at 126
    . However, “an
    employer who gives on-site orders or provides detailed instructions on the means
    or methods to carry out a work order owes the independent contractor employee a
    5
    A premises owner and a general contractor both owe the same duties to an
    independent contractor’s employees; therefore, cases considering these duties are
    used interchangeably. Koch Ref. Co. v. Chapa, 
    11 S.W.3d 153
    , 155 n.1 (Tex.
    1999) (per curiam).
    17
    duty of reasonable care to protect him from work-related hazards.” Hoechst–
    
    Celanese, 967 S.W.2d at 357
    .
    “Control can be established in two ways: by (1) a contractual right of control
    or (2) an exercise of actual control.” 
    Abarca, 305 S.W.3d at 122
    (citing Ellwood
    Tex. Forge Corp. v. Jones, 
    214 S.W.3d 693
    , 700 (Tex. App.—Houston [14th Dist.]
    2007, pet. denied)). To be liable for exercising actual control, a premises owner or
    general contractor must have had the right to control the means, methods, or details
    of the independent contractor’s work to the extent that the independent contractor
    was not entirely free to do the work its own way. 
    Abarca, 305 S.W.3d at 124
    . The
    control must relate to the injury that the negligence causes. 
    Id. It is
    not enough
    that the owner has the right to order the work to stop and start or to inspect
    progress or receive reports. 
    Id. Nor is
    it enough to recommend a safe manner for
    the independent contractor’s employees to perform the work. 
    Id. Stewart &
    Stevenson first asserts that Apache and McLemore were negligent
    in “refus[ing] to shut down the operations when [they] should have,” and it cites a
    manual, which was admitted into evidence, entitled, “Recommended Practice for
    Use and Procedures for Inspection, Maintenance, and Repair of Drilling and Well
    Servicing Structures,” authored by the American Petroleum Institute (“API”).
    Among recommended practices, API states,
    18
    Rig foundations and guywire tensions should be checked daily. The
    following conditions are reason to discontinue operations until the
    cause of the discrepancy is located and corrected:
    a.    There is large relative movement between the mast
    support structure and the rotary/setback support structure
    when the slips are set and the load is removed from the
    mast, or vice versa.
    b.    The empty traveling block does not hang over or near the
    well center and/or the mast support structure is not level.
    c.    The mast support structure or substructure subsides more
    on one side than the other with the application of load,
    and/or the guywire on one side becomes noticeably
    tighter when the tension in the guywire on the opposite
    side becomes noticeably less.
    Stewart & Stevenson also refers to a University of Texas textbook entitled, “Safety
    on the Rig,” which states, “The service companies have their own safety rules that
    must be observed by rig employees, but it is the operator’s responsibility to ensure
    that the service company’s operations do not endanger the drilling operation or
    personnel.” And there is evidence that McLemore had the ability to shut down
    operations at the rig if he deemed them unsafe. For example, Robert Duhon,
    Apache’s foreman, testified that McLemore, as the “company man,” was expected
    to ensure that the project would not proceed “until things [were] safe.”
    However, as noted above, the law is clear that the right of a general
    contractor or premises owner to order work to start or stop, inspect progress, or
    receive reports is insufficient to create a duty under either the common law or
    19
    Chapter 95. See, e.g., Redinger, 
    689 S.W.2d 418
    ; Johnston v. Oiltanking Hous.,
    L.P., 
    367 S.W.3d 412
    , 417, 419 (Tex. App.—Houston [14th Dist.] 2012, no pet.);
    see also Yeager v. Drillers, Inc., 
    930 S.W.2d 112
    , 115–17 (Tex. App.—Houston
    [1st Dist.] 1996, no writ) (holding company man and employer entitled to
    summary judgment on independent contractor’s negligent claim where company
    man “did not direct [the independent contractor’s] work”). Thus, Apache and
    McLemore’s general right to shut down operations at Rig 65 could not have given
    rise to a duty, and this cannot constitute a basis for considering them as responsible
    third parties. See TEX. CIV. PRAC. & REM. CODE ANN. § 33.003(b).
    Stewart & Stevenson next asserts that Apache and McLemore were
    negligent in “suppl[ying] a faulty foundation” for Rig 65.         Clyde Ned, Key
    Energy’s “rig supervisor” at the site, did testify that it was the company man’s
    responsibility, “or the company [he was] working for,” to ensure that Rig 65’s
    foundation was safe. And there is evidence that the pollution pans sunk, which
    possibly contributed to causing Rig 65 to lean. For example, McLemore testified
    that he told Garber, Apache’s environmental, health, and safety coordinator, that he
    was “having an issue with [the] pollution pans” because “they were sinking.”
    However, it is undisputed that another independent contractor, T.K. Stanley, built
    the foundation for Rig 65.
    20
    Furthermore, an independent contractor is generally expected “to take into
    account any open and obvious premises defects in deciding how the work should
    be done, what equipment to use in doing it, and whether its workers need any
    warning.” See, e.g., Gen. Elec. Co. v. Moritz, 
    257 S.W.3d 211
    , 215–16 (Tex.
    2008). As asserted in Stewart & Stevenson’s brief, Key Energy was aware “that
    the foundation was sinking, particularly around the pollution pans.” Ned testified
    that he noticed “a little sinkage” in the foundation, and Damian McGee, a Key
    Energy employee, testified that he had “noticed some sinking where the tubing
    pans were.” Duhon testified that she could see the pollution pans sinking “about a
    foot,” causing the rig to move “a little bit.” And Mathews testified that he could
    also see that the pollution pans were sinking.         Finally, Garber testified that
    McLemore decided “together” with Joe Vale, Key Energy’s superintendent, to pull
    pipes out of the pollution pans in an attempt to remediate the sinking problem.
    However, such an awareness and agreement did not give rise to a duty on the part
    of Apache and McLemore. See 
    id. And the
    evidence conclusively establishes that
    Apache did not construct the foundation for Rig 65 and any problem with the
    foundation sinking was obvious to Key Energy, which was included in the trial
    court’s charge as a potentially responsible third party.
    Finally, Stewart & Stevenson asserts that Apache and McLemore were
    negligent in “lett[ing] Key [Energy] misuse the guy wires in a boneheaded
    21
    response to the leaning rig.” A general contractor’s right of control must relate to
    the injury the negligence causes. 
    Abarca, 305 S.W.3d at 124
    . To prove that the
    general contractor breached an applicable duty of care, a nexus must be shown
    between the general contractor’s retained control and the condition or activity that
    caused the injury. See Shell Oil Co. v. Khan, 
    138 S.W.3d 288
    , 294 (Tex. 2004);
    Hoechst-
    Celanese, 967 S.W.2d at 357
    ; see also Clayton W. Williams, Jr., Inc. v.
    Olivo, 
    952 S.W.2d 523
    , 528 (Tex. 1997).           Stated another way, a general
    contractor’s duty is commensurate with the control it retains over the independent
    contractor’s work. Hoechst-
    Celanese, 967 S.W.2d at 357
    ; 
    Mendez, 967 S.W.2d at 357
    . It is not enough to show that the general contractor controlled one aspect of
    the independent contractor’s activities if its employee’s injury arose from another.
    
    Khan, 138 S.W.3d at 294
    .
    Here, although several witnesses testified that it was improper to adjust the
    guy wires to correct a rig misalignment, there is no evidence in the record that
    Apache and McLemore directed or controlled Key Energy’s use of the guy wires.
    Stewart & Stevenson cites us only to Little’s testimony that McLemore “knew
    what was going on with regard to this guy wire movement.”            However, this
    testimony does establish that Apache and McLemore had control over the
    “operative details” surrounding Key Energy’s use of the guy wires. See, e.g,
    
    Johnston, 367 S.W.3d at 419
    –20 (holding employer’s right to control timing and
    22
    sequence of work had no relation with plaintiff’s injuries); Painter v. Momentum
    Energy Corp., 
    271 S.W.3d 388
    , 406–07 (Tex. App.—El Paso 2008, pet. denied)
    (holding no evidence company man had control over independent contractor’s
    activities in removing “rotating head” from rig, which caused plaintiff’s injuries).
    In sum, for the trial court to have asked the jury to determine whether
    Apache and McLemore were also responsible for Foret’s injuries, there must be
    evidence that Apache and McLemore committed a “negligent act or omission” that
    “caused or contributed to causing in any way the harm for which recovery of
    damages is sought.” TEX. CIV. PRAC. & REM. CODE ANN. § 33.011(6). There is no
    evidence in the record that Apache and McLemore breached a duty to Foret by not
    stopping operations, by “suppl[ying] a faulty foundation,” or by allowing Key
    Energy to misuse the guy wires. Thus, there is no evidence that Apache and
    McLemore committed a “negligent act or omission” that caused Foret’s damages.
    See El 
    Chico, 732 S.W.2d at 311
    (stating that threshold inquiry in any negligence
    case is duty). Accordingly, we hold that the trial court did not err in not including
    in its jury charge the issue of whether Apache or McLemore were possible
    responsible third parties under Chapter 33.
    We overrule Stewart & Stevenson’s first issue.
    23
    Damages
    In its second issue, Stewart & Stevenson argues that the jury’s awards of
    $5,000,000 for future pain and mental anguish, $1,000,000 for future physical
    impairment, and $2,000,000 for future earning capacity are excessive and “far
    exceed the norm for this kind of case” because it “does not involve burns, lost
    limbs, or the kinds of injuries that often generate very high verdicts.”
    Standard of Review
    We review a claim that a damages award is excessive for factual sufficiency
    of the evidence. See Mar. Overseas Corp. v. Ellis, 
    971 S.W.2d 402
    , 406 (Tex.
    1998). When faced with a factual-sufficiency challenge to a jury’s finding, we
    must consider and weigh all of the evidence, not just that evidence which supports
    the finding. See Ortiz v. Jones, 
    917 S.W.2d 770
    , 772 (Tex. 1996). Because we are
    not a fact finder, we may set aside the finding only if it is so contrary to the
    overwhelming weight of the evidence that the finding is clearly wrong and
    manifestly unjust. Mar. Overseas 
    Corp., 971 S.W.2d at 407
    .
    Due to the nature of personal injury damages, i.e., because they are
    unliquidated and incapable of measurement by any certain standard, a jury has
    broad discretion in fixing the amount of the award. See Weidner v. Sanchez, 
    14 S.W.3d 353
    , 372 (Tex. App.—Houston [14th Dist.] 2000, no pet.); J.
    Wigglesworth Co. v. Peeples, 
    985 S.W.2d 659
    , 665–66 (Tex. App.—Fort Worth
    24
    1999, pet. denied); see also Pittsburgh Corning Corp. v. Walters, 
    1 S.W.3d 759
    ,
    781 (Tex. App.—Corpus Christi 1999, pet. denied) (“[D]eterminations of pain and
    suffering damages cannot be neatly confined to mathematical certainties.”).
    However, that discretion is limited in that it must enjoy evidentiary support; in
    other words, “[j]uries cannot simply pick a number and put it in the blank.” Saenz
    v. Fid. & Guar. Ins. Underwriters, 
    925 S.W.2d 607
    , 614 (Tex. 1996).
    Future Pain and Mental Anguish
    Stewart and Stevenson first asserts that the evidence regarding future mental
    anguish is “non-existent” and the evidence regarding future pain is “limited” and
    “not nearly enough to justify” the jury’s award of $5,000,000.
    To recover damages for mental anguish, a plaintiff must produce direct
    evidence of the nature, duration, and severity of the mental anguish, establishing a
    substantial disruption in his daily routine. See City of Tyler v. Likes, 
    962 S.W.2d 489
    , 495 (Tex. 1997) (quoting Parkway Co. v. Woodruff, 
    901 S.W.2d 434
    , 444
    (Tex. 1995)); Verinakis v. Med. Profiles, Inc., 
    987 S.W.2d 90
    , 95 (Tex. App.—
    Houston [14th Dist.] 1998, pet. denied). “As a general rule, evidence to establish
    ‘adequate details to assess mental anguish claims’ can be demonstrated by ‘the
    claimants’ own testimony, that of third parties, or that of experts.’” N.N. v. Inst.
    for Rehab. & Research, 
    234 S.W.3d 1
    , 9 (Tex. App.—Houston [1st Dist.] 2006, no
    pet.) (quoting 
    Parkway, 901 S.W.2d at 444
    ).
    25
    The presence or absence of pain, either physical or mental, is an inherently
    subjective question. HCRA of Tex., Inc. v. Johnston, 
    178 S.W.3d 861
    , 871 (Tex.
    App.—Fort Worth 2005, no pet.); Dollison v. Hayes, 
    79 S.W.3d 246
    , 249 (Tex.
    App.—Texarkana 2002, no pet.). No objective measures exist for analyzing pain
    and suffering damages. 
    HCRA, 178 S.W.3d at 871
    ; see also Hicks v. Ricardo, 
    834 S.W.2d 587
    , 591 (Tex. App.—Houston [1st Dist.] 1992, no writ). Thus, once the
    existence of some pain and suffering has been established, there is no objective
    way to measure the adequacy of the amount awarded as compensation. 
    HCRA, 178 S.W.3d at 871
    ; Dawson v. Briggs, 
    107 S.W.3d 739
    , 751 (Tex. App.—Fort
    Worth 2003, no pet.).
    Here, in regard to Foret’s mental anguish, Dr. Bradley Bartholomew, a
    neurosurgeon who examined and treated Foret, testified that, as a result of falling
    from between sixty to eighty feet to the ground, Foret suffered a “closed head
    injury” that resulted in “traumatic brain injury.” Testing conducted after the fall
    revealed that Foret had performed lower than average in attention concentration
    and intellectual, language, memory, and motor functioning. And Bartholomew
    described Foret as suffering from permanent “cognitive deficits.” Dr. Richard
    Pollock, a neuropsychologist, concluded that Foret had “suffered a significant
    brain injury” and was “experiencing a significant depression.” He opined that
    Foret “has a cognitive disorder,” meaning that he has “problems with memory and
    26
    processing information,” and “very significant clinical depression.”          Pollock
    concluded that these issues would be “permanent and lifelong,” and Foret will
    “have to work with those deficits for the rest of his life.”
    Foret’s wife, Megan Foret, testified that since his injury, Foret often forgets
    where he is going when he is driving, forgets to turn off the stove after cooking,
    and cannot bathe his child because he will forget the child is in the bathtub. As a
    result, Foret feels like “he’s less than a man” because “he can’t help out as much as
    he used to.” She explained that Foret cries “a lot” and the crying “is getting
    worse.” Megan did not think it was realistic for them to have a second child
    because of the attention she now has to give to her husband. Likewise, Foret
    testified that since his injury, he is not “the man that” he “should be” for Megan,
    and he suffers from anxiety and depression.
    In regard to pain, Dr. Bartholomew testified that Foret suffered from
    fractures in his spine and kyphosis, or an abnormal “bending” of the spine that may
    “continue to cause pain.” Bartholomew opined that Foret will have “permanent
    pain” in his back with permanent restrictions on “repetitive bending, stooping,
    crawling, twisting, turning” and picking up objects weighing more than twenty-
    five pounds. Foret testified that he still suffers from knee and back pain. And
    Bartholomew opined that Foret would need “long-term pain management” for the
    rest of his life.
    27
    From this record, we conclude that Foret presented direct evidence of his
    physical pain and mental anguish from which the jury could have reasonably
    concluded that he will continue to suffer substantial disruptions in his daily
    routine.6 See City of Tyler v. 
    Likes, 962 S.W.2d at 495
    . Accordingly, we hold that
    the jury’s award of $5,000,000 dollars for future pain and mental anguish is not so
    contrary to the overwhelming weight of the evidence as to be clearly wrong and
    manifestly unjust. See Mar. Overseas Corp. v. Ellis, 
    971 S.W.2d 402
    , 407 (Tex.
    1998).
    Future Physical Impairment
    Stewart & Stevenson next argues that because the jury’s award of
    $1,000,000 in future physical impairment is excessive, this Court should suggest a
    remittitur of 90% of the award.
    “Physical impairment, sometimes called loss of enjoyment of life,
    encompasses the loss of the injured party’s former lifestyle.” Gen. Motors Corp. v.
    Burry, 
    203 S.W.3d 514
    , 554 (Tex. App.—Fort Worth 2006, pet. denied); see
    6
    Stewart & Stevenson cites us to several cases in which plaintiffs received lesser
    damage awards, arguing that they demonstrate that the damage awards in this case
    are excessive. However, because there is no certain standard by which personal
    injury damages can be measured, “each case must stand on its own facts and
    circumstances.” See, e.g., Star Hous., Inc. v. Shevack, 
    886 S.W.2d 414
    , 421 (Tex.
    App.—Houston [1st Dist.] 1994, writ denied). And we note that Stewart &
    Stevenson does not challenge the jury’s award of $1,000,000 dollars for two-and-
    a-half years of past physical pain and mental suffering; nor does it challenge the
    testimony of Doctors Bartholomew and Pollock, who opined that Foret will have
    “permanent” and “lifelong” issues as a result of his injuries.
    28
    Doctor v. Pardue, 
    186 S.W.3d 4
    , 18 (Tex. App.—Houston [1st Dist.] 2005, pet.
    denied) (quoting Golden Eagle Archery, Inc. v. Jackson, 
    116 S.W.3d 757
    , 772
    (Tex. 2003)).    A plaintiff generally must show that his physical-impairment
    damages are substantial and extend beyond any pain, suffering, mental anguish,
    lost wages or diminished earning capacity. 
    Burry, 203 S.W.3d at 555
    ; see Golden
    Eagle Archery, 
    Inc., 116 S.W.3d at 772
    (indicating that “it would be appropriate to
    advise the jury [by instruction] that it may consider as a factor loss of enjoyment of
    life. But the jury should be instructed that the effect of any physical impairment
    must be substantial and extend beyond any pain, suffering, mental anguish, lost
    wages or diminished earning capacity and that a claimant should not be
    compensated more than once for the same elements of loss or injury.”).
    Here, Megan testified that Foret was one of the most “lively people” she had
    known before his injuries, and he spent his spare time hunting, fishing, and helping
    his father repair their cars and homes. She noted that after he sustained his
    injuries, she sees Foret cry “because of all things that he used to be able to do that
    he can’t do now, such as helping his dad.” Foret was “very independent” before
    his injuries but now she has “to do everything” for him.         Foret testified that
    because of his chronic back pain, he is no longer “physically able to do the kinds of
    things” that he did prior to being injured. Specifically, Foret can no longer go deer
    hunting or work on cars with his father. And he can only play with his son for
    29
    short periods of time before his back begins to hurt. Foret is also unable to hold
    his son for longer than five or ten minutes, and, as his son grows, Foret will no
    longer be able to hold him at all.
    From this evidence, the jury could have reasonably concluded that Foret
    would suffer a substantial loss of enjoyment of life and loss of his former lifestyle.
    See, e.g., Figueroa v. Davis, 
    318 S.W.3d 53
    , 64–65 (Tex. App.—Houston [1st
    Dist.] 2010, no pet.) (upholding award for past and future physical impairment for
    plaintiff with dental injuries because he subsequently had to limit number and
    types of food he ate and “could not eat some of the foods that he loved” for several
    years); 
    Burry, 203 S.W.3d at 549
    –55 (upholding $3,500,000 award for future
    physical impairment for mother who suffered brain damage and could no longer
    read to her children, drive a car, or live without supervision); see also Marquette
    Transp. Co. Gulf-Inland, LLC v. Jackson, No. 01-10-01025-CV, 
    2012 WL 1454476
    , at *13–14 (Tex. App.—Houston [1st Dist.] Apr. 26, 2012, no pet.) (not
    designated for publication) (holding evidence plaintiff “permanently limited” and
    no longer “able to participate in the same activities that he pursued before he was
    injured, including everything from standing in order to cook and clean to playing
    basketball” sufficient to support jury’s award of $500,000 for future physical
    impairment). Accordingly, we hold that the jury’s award of $1,000,000 for future
    30
    physical impairment is not so contrary to the overwhelming weight of the evidence
    as to be clearly wrong and manifestly unjust.
    Future Earning Capacity
    Finally, Stewart & Stevenson asserts that the jury’s award of $2,000,000 in
    future earning capacity is excessive.
    Lost earning capacity is an assessment of a plaintiff’s capacity to earn a
    livelihood prior to injury and the extent to which that capacity is impaired by the
    injury. Scott’s Marina at Lake Grapevine, Ltd. v. Brown, 
    365 S.W.3d 146
    , 158–59
    (Tex. App.—Amarillo 2012, pet. denied). Lost earning capacity is not measured
    by what a person actually earned before an injury, but by the person’s capacity to
    earn, even if he had never worked in that capacity in the past. Id.; Gen. Motors
    Corp. v. Burry, 
    203 S.W.3d 514
    , 553 (Tex. App.—Fort Worth 2006, pet. denied).
    Proof of loss of earning capacity is always uncertain and is left largely to the
    discretion of the jury. Rigdon Marine Corp. v. Roberts, 
    270 S.W.3d 220
    , 232
    (Tex. App.—Texarkana 2008, pet. denied). Nevertheless, to support an award of
    damages for lost earning capacity, a plaintiff must present evidence sufficient to
    permit a jury to reasonably measure earning capacity in monetary terms. Tagle v.
    Galvan, 
    155 S.W.3d 510
    , 519–20 (Tex. App.—San Antonio 2004, no pet.);
    Durham Transp. Co., v. Beettner, 
    201 S.W.3d 859
    , 864 (Tex. App.—Waco 2006,
    pet. denied). Non-exclusive factors that may be considered in determining lost
    31
    earning capacity include evidence of past earnings and the plaintiff’s stamina,
    efficiency, ability to work with pain, and work-life expectancy. Big Bird Tree
    Servs. v. Gallegos, 
    365 S.W.3d 173
    , 178 (Tex. App.—Dallas 2012, pet. denied);
    
    Tagle, 155 S.W.3d at 519
    .
    Thomas Mayor, an economist, testified that he reviewed Foret’s tax returns,
    his employment and payroll records, and “a whole host of these general statistical
    studies.” Mayor interviewed Foret and noted that he “was very young” and “was
    really on track to be a high income earner for someone with his education and at
    his age.” In his expert report, entered into evidence, Mayor opined that Foret
    would lose $1,725,068 in future earning capacity, without taking into account lost
    career advancement, which would total $2,587,602 in future earning capacity. He
    further explained that “if the medical evidence indicates that he will be able to
    return to work and earn some percentage of his former pay, then that percentage
    should be subtracted in order to arrive at the appropriate mitigated loss.” In the
    case that Foret could “work in a light duty capacity,” Mayor opined that he would
    lose $1,069,542, without considering career advancement, and $1,940,702 when
    considering career advancement.
    Stewart & Stevenson asserts that Mayor’s conclusions “rested on the critical
    assumption that [Foret] flatly cannot work again” and such evidence “is so weak as
    to make the damage award clearly wrong and unjust.” However, as noted in his
    32
    report, Mayor calculated a loss in future earning capacity of $1,940,702, taking
    into account the possibility of future employment, a calculation not far from the
    jury’s award of $2,000,000 dollars. Furthermore, there is evidence in the record
    that Foret may be unemployable for the rest of his life. Dr. Bartholomew noted,
    The problem is he can’t do physical labor anymore because of his
    spine injuries, so that would have to put him in more of a desk-type
    job. And I don’t see how, with cognitive deficits, he’s going to be
    able to get gainful employment with these deficits. So the answer is
    no, I don’t see him being employable.”
    Likewise, Dr. Pollock opined that “the odds are against” Foret finding competitive
    employment again.
    Furthermore, Viola Lopez, a vocational rehabilitation expert, testified that
    she performed a “vocational assessment” of Foret. She concluded that because of
    Foret’s “chronic pain,” the “restrictions [doctors] have placed on him,” and “the
    neuro cognitive problems of even day-to-day activities,” she did not believe Foret
    would be able to find “competitive employment.” She also noted that Foret had
    “never done light work, work in an office or clerical.” Thus, she did not think it
    was “reasonable to think he can do that.”
    From this evidence, we cannot conclude that the jury’s award of $2,000,000
    for loss of future earning capacity is so contrary to the overwhelming weight of the
    evidence as to be clearly wrong and manifestly unjust. Accordingly, we hold that
    33
    the evidence is factually sufficient to support the jury’s award of $2,000,000 for
    loss of future earning capacity.
    Stewart & Stevenson also argues that the jury’s awards of future damages
    are “overlapping” because “all his future damages stem from the physical and
    emotional pain that will curtail his work and personal life in the future to some
    extent.” However, as established above, factually-sufficient evidence supports the
    jury’s awards individually for future pain and mental anguish, future physical
    impairment, and loss of future earning capacity. Accordingly, we further hold that
    the evidence is factually sufficient to support the jury’s entire $8,000,000 dollar
    award for future damages.
    We overrule Stewart & Stevenson’s second issue.
    Late-Filed Discovery
    In its third issue, Stewart & Stevenson argues that the trial court erred in
    admitting into evidence Foret’s late-filed discovery responses, namely, the life care
    plan by Terry Arnold, and medical information supplied by Dr. Paul Hubbell, a
    pain management specialist. Stewart & Stevenson asserts that Arnold’s life care
    plan “unexpectedly injected about $680,000 in future economic damages that Foret
    had never requested before.”
    When a party has not timely made, amended, or supplemented a discovery
    response, the party may not introduce into evidence the material or information
    34
    that was not timely disclosed unless the court finds that there was good cause for
    the failure to timely make the discovery response or the failure to timely make the
    discovery response will not unfairly surprise or unfairly prejudice the other parties.
    TEX. R. CIV. P. 193.6(a). A disclosure is presumed to be untimely if it was made
    less than thirty days before trial. 
    Id. 193.5(b). The
    party seeking to introduce the
    evidence has the burden of establishing good cause or the lack of unfair surprise or
    prejudice. 
    Id. 193.6(b). And
    the trial court has discretion to determine whether the
    party has met this burden. Alvarado v. Farah Mfg. Co., 
    830 S.W.2d 911
    , 914
    (Tex. 1992); Dolenz v. State Bar of Tex., 
    72 S.W.3d 385
    , 387 (Tex. App.—Dallas
    2001, no pet.).
    Here, on July 11, 2011, Stewart & Stevenson filed a “Motion to Strike
    [Foret’s] Late-Filed Discovery,” in which it asserted that Foret had produced to
    Stewart & Stevenson, after the July 1, 2011 discovery deadline, among other
    evidence, Hubbell’s expert report on July 7, 2011 and Arnold’s life care
    management plan on July 11, 2011. In Arnold’s “Life Care Plan,” she estimated
    that Foret would incur $679,296 in future medical and related needs. Stewart &
    Stevenson alleged that the expert report was based, in part, on the late-filed
    medical report from Dr. Hubbell, who had estimated that Foret required $259,710
    in pain management treatment. In his response to Stewart & Stevenson’s motion,
    Foret argued that Stewart & Stevenson was not unfairly prejudiced by the late
    35
    production of Hubbell’s report because he was timely designated as an expert and
    his medical records were produced upon receipt. In regard to Arnold’s report,
    Foret asserted that he timely designated Arnold and Stewart & Stevenson had
    Arnold’s report when it deposed her on July 12, 2011.
    Stewart & Stevenson argues that it was “deliberately shortchange[ed]” in its
    ability to adequately depose Dr. Hubbell and Arnold concerning the substance of
    their reports. However, we note that on July 13, 2011, two days after it had filed
    its motion to strike, and one day after it had deposed Arnold, Stewart & Stevenson
    filed a “Motion to Assign This Case to the Jury Docket, or, In the Alternative,
    Motion for Continuance.” In that motion, Stewart & Stevenson asked the trial
    court to set the jury trial start on July 18, 2011. In the alternative, Stewart &
    Stevenson requested a continuance only if the trial court denied its “request to have
    [the] matter set on the jury docket for the two-week period July 18, 2011 – July 29,
    2011.” On July 19, 2011, in response to Foret’s motion to strike its motion for
    continuance, Stewart & Stevenson again asserted that it “seeks to maintain the
    current jury trial.” Only in the alternative to the trial court’s denial of its motion to
    assign the case did Stewart & Stevenson assert a “need for additional discovery”
    due to Foret’s “barrage of late-filed discovery.”
    Here, Stewart & Stevenson was able to depose Arnold after receiving her
    report, Foret produced Dr. Hubbell’s report as soon as it became available, and,
    36
    most importantly, Stewart & Stevenson repeatedly insisted on going to trial on July
    18.   Thus, the trial court could have reasonably concluded that Stewart &
    Stevenson was not unfairly prejudiced by the late production of Arnold’s and
    Hubbell’s reports. See, e.g., Wigfall v. Tex. Dep’t of Criminal Justice, 
    137 S.W.3d 268
    , 274 (Tex. App.—Houston [1st Dist.] 2004, no pet.) (holding that trial court
    did not abuse its discretion in not excluding late-designated expert witnesses where
    movant did not request continuance or show how “delay left him unable to conduct
    his own discovery”). Accordingly, we hold that the trial court did not err in
    admitting the reports into evidence.
    We overrule Stewart & Stevenson’s third issue.
    Conclusion
    We affirm the judgment of the trial court.
    Terry Jennings
    Justice
    Panel consists of Justices Jennings, Brown, and Huddle.
    37