LTF Real Estate Company, Inc. and Travelers Casualty and Surety Company of America v. D&D Utility Supply, LLC ( 2013 )


Menu:
  • Opinion issued March 21, 2013
    In The
    Court of Appeals
    For The
    First District of Texas
    ————————————
    NO. 01-11-00244-CV
    ———————————
    LTF REAL ESTATE COMPANY, INC. AND TRAVELERS CASUALTY
    AND SURETY COMPANY OF AMERICA, Appellants
    V.
    D&D UTILITY SUPPLY, LLC, Appellee
    On Appeal from the 164th District Court
    Harris County, Texas
    Trial Court Case No. 2009-03413
    MEMORANDUM OPINION
    Appellants, LTF Real Estate Company, Inc. (“LTF”) and Travelers Casualty
    and Surety Company of America (“Travelers”), challenge the trial court’s rendition
    of summary judgment in favor of appellee, D&D Utility Supply, LLC (“D&D”),
    and denial of their summary-judgment motion in D&D’s suit against LTF and
    Travelers for foreclosure and enforcement of D&D’s liens. In three issues, LTF
    and Travelers contend that the trial court erred in granting D&D summary-
    judgment, denying them summary judgment, and awarding D&D damages and
    attorney’s fees.
    We reverse and render judgment in favor of LTF and Travelers.
    Background
    In its seventh amended petition, D&D, a vendor of materials, alleged that
    FCA Construction Company, LLC (“FCA”), which was an entity “controlled by”
    Lifetime Fitness, served as a general contractor for the construction of a Lifetime
    Fitness facility in Humble, Texas (“the project”). FCA contracted with Houston
    Earthworks Resources, Inc. (“Houston Earthworks”), a plumbing subcontractor, to
    provide labor and materials for the project, and D&D provided to Houston
    Earthworks materials that were incorporated into the project. FCA later terminated
    its contract with Houston Earthworks and retained J&G Plumbing Services, LLC
    (“J&G”) as a replacement.     D&D then provided to J&G materials that were
    incorporated into the project. FCA subsequently terminated its contract with J&G.
    D&D further alleged that it did not receive payment for some of the
    materials that it had provided to both Houston Earthworks and J&G. In an effort to
    secure payment for its materials, D&D filed two separate “Affidavits Claiming
    2
    Liens” against the Lifetime Fitness property: (1) for an outstanding balance of
    $34,088.49 for materials it had provided to Houston Earthworks (the “Houston
    Earthworks lien”) and (2) for an outstanding balance of $90,414.12 for materials it
    had provided to J&G (the “J&G lien”). 1 LTF and its surety, Travelers, filed
    separate bonds to indemnify against the liens.2
    Finally, D&D alleged that LTF was a managing member of and controlled
    FCA, the contract between FCA and LTF was a “sham contract,” and D&D was in
    a “direct contractual relationship with the owner and [had] a lien as an original
    contractor.” D&D sought to recover from LTF and Travelers “all amounts due and
    owing to D&D” resulting from the perfection of the liens and its attorney’s fees. 3
    In its motion for partial summary judgment, D&D asked the trial court to
    rule that both of its liens “substantially compl[ied]” with the Texas Property Code
    and were “valid and enforceable.” In their summary-judgment motion, LTF and
    Travelers asked the trial court to rule that D&D had failed to perfect its liens in
    accordance with the Property Code. The trial court denied LTF and Travelers’
    summary-judgment motions and granted D&D’s Motion for Partial Summary
    Judgment, concluding that D&D’s liens were “valid perfected liens as a matter of
    1
    See TEX. PROP. CODE ANN. §§ 53.001–.260 (Vernon 2007 & Supp. 2011).
    2
    See 
    id. § 53.171
    (Vernon 2007).
    3
    See 
    id. § 53.156
    (Vernon Supp. 2011).
    3
    law.” D&D then filed a Motion for Final Summary Judgment in which it asked the
    trial court to award it damages as provided for in the liens and its reasonable
    attorney’s fees. D&D sought, after certain reductions, damages in the amount of
    $123,777.82 and attorney’s fees “related to only the proceedings to foreclose the
    liens.”
    The trial court granted D&D’s Motion for Final Summary Judgment,
    ordering that D&D recover from LTF and Travelers “principal damages” in the
    amount of $123,777.82, attorney’s fees in the amount of $181,055.91, and pre- and
    post-judgment interest.
    Standard of Review
    To prevail on a summary-judgment motion, a movant has the burden of
    proving that it is entitled to judgment as a matter of law and there is no genuine
    issue of material fact. TEX. R. CIV. P. 166a(c); Cathey v. Booth, 
    900 S.W.2d 339
    ,
    341 (Tex. 1995). A plaintiff moving for summary judgment on its claim must
    establish its right to summary judgment by conclusively proving all the elements of
    its cause of action as a matter of law. Rhone–Poulenc, Inc. v. Steel, 
    997 S.W.2d 217
    , 223 (Tex. 1999). When a defendant moves for summary judgment, it must
    either (1) disprove at least one essential element of the plaintiff’s cause of action or
    (2) plead and conclusively establish each essential element of its affirmative
    defense, thereby defeating the plaintiff’s cause of action. 
    Cathey, 900 S.W.2d at 4
    341. When both parties move for summary judgment and the trial court grants one
    motion and denies the other, the reviewing court should review the summary-
    judgment evidence presented by both sides, determine all questions presented, and
    render the judgment that the trial court should have rendered. Tex. Workers’
    Comp. Comm’n v. Patient Advocates of Tex., 
    136 S.W.3d 643
    , 648 (Tex. 2004).
    When deciding whether there is a disputed, material fact issue precluding summary
    judgment, evidence favorable to the non-movant will be taken as true. Nixon v.
    Mr. Prop. Mgmt. Co., 
    690 S.W.2d 546
    , 548–49 (Tex. 1985). Every reasonable
    inference must be indulged in favor of the non-movant and any doubts must be
    resolved in its favor. 
    Id. at 549.
    Liens
    In their first and second issues, LTF and Travelers argue that the trial court
    erred in granting D&D summary judgment and denying them summary judgment
    because D&D failed to perfect both of its mechanic’s liens as a matter of law.
    Chapter 53 of the Texas Property Code provides a mechanism by which a
    subcontractor that furnishes materials for the construction of a building on real
    property may secure payment for those materials by imposing a lien on the
    property. TEX. PROP. CODE ANN. §§ 53.001–53.260 (Vernon Supp. 2011). To
    perfect a lien, the subcontractor “must,” among other things, timely provide written
    notice, by registered or certified mail, of the unpaid balance to the original
    5
    contractor and the “owner or reputed owner.” 4 See 
    id. §§ 53.051,
    53.056 (Vernon
    2007). A subcontractor “must” also timely file an affidavit 5 signed by the person
    claiming the lien, or another person on the claimant’s behalf, and the affidavit
    “must contain substantially” a number of statutorily enumerated items. 
    Id. §§ 53.051,
    53.052, 53.054 (Vernon 2007) and 53.053 (Vernon Supp. 2011). The
    subcontractor must also timely provide notice of the filing of the affidavit by
    sending a copy of the affidavit via certified or registered mail to the “owner or
    reputed owner” and the “original contractor.” 
    Id. §§ 53.051,
    53.055.
    Texas courts have generally recognized that certain statutory requirements
    pertaining to the securing of a lien under chapter 53 are to be reviewed for
    substantial compliance. See Mustang Tractor & Equip. Co. v. Hartford Accident
    & Indem. Co., 
    263 S.W.3d 437
    , 440 (Tex. App.—Austin 2008, pet. denied) (“The
    mechanic’s and materialman’s lien statutes, as well as the relevant case law,
    mandate that a lien affidavit should not be judged by a strict standard but by
    4
    Chapter 53 of the Texas Property Code does not define “owner” or “reputed
    owner.” The term “reputed” is defined as to “be generally said or believed to exist
    or be of a particular type, despite not being so.” THE NEW OXFORD AMERICAN
    ENGLISH DICTIONARY 1447 (2001).
    5
    A person claiming a lien must file the affidavit with the county clerk of the county
    in which the property is located not later than the 15th day of the fourth calendar
    month after the day on which the “indebtedness accrues.” TEX. PROP. CODE ANN.
    § 53.052(a) (Vernon 2007). For purposes of the timely filing of the affidavit,
    “[i]ndebtedness to a subcontractor . . . who has furnished labor or material to an
    original contractor or to another subcontractor accrues on the last day of the last
    month in which labor was performed or the material furnished.” 
    Id. § 53.053(c).
                                               6
    whether the claimant substantially complied with the statutory requirements.”);
    Occidental Neb. Fed. Sav. Bank v. East End Glass Co., 
    773 S.W.2d 687
    , 688 (Tex.
    App.—San Antonio 1989, no writ) (“For purposes of perfection, only substantial
    compliance is required in order to fulfill the requirements of the mechanic’s and
    materialman’s lien statutes.”); see also First Nat’l Bank in Dallas v. Whirlpool
    Corp., 
    517 S.W.2d 262
    , 269 (Tex. 1974) (“It is well settled that the mechanic’s and
    materialman’s lien statutes of this State will be liberally construed for the purpose
    of protecting laborers and materialmen.”).
    The J&G Lien
    LTF and Travelers argue that the J&G lien is not valid and enforceable
    because (1) D&D failed to timely provide FCA, by registered or certified mail,
    with notice concerning the unpaid balances for materials provided to J&G, see
    TEX. PROP. CODE ANN. § 53.056 (referred to herein as the “pre-lien notice”); (2)
    D&D failed to timely record its Affidavit Claiming Lien, see 
    id. § 53.052;
    (3)
    D&D’s Affidavit Claiming Lien failed to provide the name and last known address
    of the owner or reputed owner of the property in question, the name and last
    known address of the person to whom D&D furnished the materials, the
    description of the materials sold to J&G, and a statement of each month in which
    the materials were allegedly sold for which payment is requested, see 
    id. § 53.054;
    7
    and (4) D&D failed to timely provide LTF and FCA, by registered or certified
    mail, with a copy of its Affidavit Claiming Lien, see 
    id. § 53.055.
    Pre-Lien Notice
    Section 53.056 provides that in order for a lien to be valid, a claimant other
    than an original contractor must provide a pre-lien notice of unpaid balances by
    registered or certified mail to the “owner or reputed owner” of the property in
    question and “the original contractor,” as applicable, at their last known addresses.
    See 
    id. The section
    further provides,
    If the lien claim arises from a debt incurred by a subcontractor, the
    claimant must give to the original contractor written notice of the
    unpaid balance. The claimant must give the notice not later than the
    15th day of the second month following each month in which all or
    part of the claimant’s labor was performed or material delivered. The
    claimant must give the same notice to the owner or reputed owner and
    the original contractor not later than the 15th day of the third month
    following each month in which all or part of the claimant’s labor was
    performed or material or specially fabricated material was delivered.
    
    Id. § 53.056(b).
    6 A copy of a statement or billing in the usual and customary form
    is sufficient as notice under this section. 
    Id. § 53.056(f).
    D&D presented summary-judgment evidence that on September 11, 2008, it
    sent a letter addressed to “Owner” Lifetime Fitness/FCA, 2902 Corporate Place,
    Chanhassen, Minnesota 55317, and “General Contractor” FCA, at the same
    6
    The parties refer to the notices required by section 53.056 as the “pre-lien notice,”
    the “60-day notice,” and the “90-day notice.”
    8
    Minnesota address. In the letter, entitled “Notice of Claim Demand for Payment
    regarding the Lifetime Fitness located in Humble, Texas,” D&D stated that it was
    providing the notice, in compliance with sections 53.055 and 53.066, and
    “Lifetime Fitness” was indebted to D&D in the amount of $81,757.73 for the sale
    and delivery of “underground utility products.” D&D attached to this letter a
    “sworn statement of account” and a statement reflecting outstanding invoices for
    materials delivered for the project in August and September 2008. It also attached
    to the letter a certified mail receipt signed by an “agent” of the recipient on
    September 18, 2008 with the addressee identified as “Lifetime Fitness/FCA” at
    2902 Corporate Place, Chanhassen, Minnesota 55317.
    D&D also presented summary-judgment evidence that on October 15, 2008,
    it sent another letter, entitled “90 Day Fund Trapping Notice (Texas Property Code
    53.056),” to “Lifetime Fitness/FCA” at 2902 Corporate Place, Chanhassen,
    Minnesota 55317. In this letter, D&D stated that it had furnished materials to J&G
    for the “Lifetime Fitness” project and there remained “due and owing $102,264.66
    for materials furnished to your subcontractor in July.” 7 D&D attached to this letter
    7
    LTF and Travelers assert that, despite all the other evidence demonstrating that
    D&D provided materials for the project in several months in 2008, the mere
    reference to “July” in the letter is controlling and constitutes an admission by
    D&D that it provided materials only in July. LTF and Travelers further assert that
    this admission constitutes a fatal defect to D&D’s case in regard to outstanding
    balances for materials provided to J&G. LTF and Travelers do not present any
    9
    a “sworn statement of account” referencing amounts owed by J&G and a statement
    reflecting outstanding invoices for the months of June, July, August, September,
    and October 2008. Also attached to this letter is a certified mail receipt signed by
    an “agent” of the recipient on October 20, 2008 with the addressee identified as
    “Lifetime Fitness” at 2902 Corporate Place, Chanhassen, Minnesota 55317.
    In addition to these notices, D&D presented summary-judgment evidence
    that on October 29, 2008, it sent a fax to telephone number “(952) 914-9523” with
    attached documents and invoices for the materials it had provided for the project.
    In her affidavit, Donna Ortego, custodian of records for D&D, testified that she
    “personally sent or caused to be sent” this fax on October 29, 2008. Although she
    did not testify to whom specifically the fax was sent, the fax cover sheet reflects
    that it was sent by D&D, the transmission result of the fax was “OK,” and the fax
    was sent to the above number. Other summary-judgment evidence establishes that
    this is the fax number for Sanaz Samie, an accounts payable clerk for “FCA
    Construction/Lifetime Fitness” who served as D&D’s contact regarding payment
    matters on the project. Attached to the fax cover sheet are numerous invoices
    pertaining to the materials that D&D provided to J&G and Houston Earthworks.
    Also attached is a handwritten notation by “Donna,” which states, “These are the
    evidence controverting the documentary evidence that establishes that D&D
    actually provided materials to J&G in months other than July.
    10
    invoices/statements for [Houston Earthworks] and J&G. Please get us paid.” The
    attached invoices reflect due dates for materials supplied to both J&G and Houston
    Earthworks from August to November 2008. And a statement summarizing the
    outstanding invoices for J&G indicates an “open balance” of $93,962.86 and
    reflects “due dates” for billing amounts from August to November 2008.
    D&D also cites an October 1, 2008 fax with attached invoices, which reflect
    “due dates” for balances accruing from July to September 2008. The fax cover
    sheet reflects that it was sent by D&D to the fax number for Sanz at “FCA
    Construction/Lifetime Fitness” and the result of the fax was “OK.” These invoices
    reflect an outstanding balance of $89,585.85. In her affidavit, Ortego testified that
    she “personally sent or caused to be sent” this fax on October 1, 2008.
    By its plain terms, section 53.056 required D&D to provide written notice to
    (1) “the original contractor” of the “unpaid balance not later than the 15th day of
    the second month following each month in which all or part of” D&D’s material
    was delivered and (2) “the owner or reputed owner” and “the original contractor
    not later than the 15th day of the third month following each month in which all or
    part of” D&D’s material was delivered. See 
    id. § 53.056.
    8
    8
    D&D was required to send the “same notice” to the “owner or reputed owner” and
    the “original contractor not later than the 15th day of the third month following
    each month in which all or part of” D&D’s material was delivered. See 
    id. § 53.056
    (Vernon 2007). However, on appeal, LTF and Travelers’ only specific
    complaint in regard to the pre-lien notice requirements related to amounts claimed
    11
    Initially, we must address the parties’ dispute concerning whether there is
    any material distinction, for purposes of determining substantial compliance with
    the pre-lien notice requirements of chapter 53, to be made between notices directed
    by D&D to LTF, Lifetime Fitness, FCA, or any other Lifetime Fitness entity. LTF
    complains that D&D did not send any of its notices specifically to “LTF Real
    Estate Company, Inc.,” which all parties now agree is the corporate entity that
    owns the property on which the project was constructed. LTF asserts on appeal
    that D&D sent required notices to FCA, which is an entity that is not a party to this
    appeal.   LTF asks that we recognize a distinction, for purposes of reviewing
    substantial compliance with Chapter 53, between it, any other Lifetime Fitness
    entity that is located at the same Minnesota address, and FCA, which is also
    located at that same address.
    It is undisputed that all of the Lifetime Fitness corporate entities discussed in
    the record (LTF, Lifetime Fitness, and others), as well as FCA, are located at the
    same street address in Chanhassen, Minnesota. Although it is undisputed that LTF
    is the entity that owns the property in question, the summary-judgment record
    indicates that, during the lifetime of the project, the parties generally referred to the
    owner of the property as “Life Time Fitness” or “Lifetime Fitness.” In fact, the
    for materials provided by D&D to J&G is that D&D failed to timely provide FCA
    notice by registered or certified mail concerning the unpaid materials. See 
    id. LTF and
    Travelers have waived any other challenge.
    12
    general contract identifies the “owner” of the property as “Life Time Fitness,” a
    corporate entity located at 2902 Corporate Place, Chanhassen, Minnesota 55317.
    There is no mention of LTF in this contract. The contract also identifies the
    contractor as FCA, located at the same “Lifetime Fitness” address in Minnesota.
    The summary-judgment record demonstrates that “Lifetime Fitness” and
    FCA represented themselves to D&D as a single entity in regard to payment
    matters for the project. Neither LTF nor any other Lifetime Fitness entity made
    any effort to delineate that only one particular Lifetime Fitness entity or FCA was
    the appropriate contact for such matters pertaining to the project. Rather, the
    letterhead on correspondence that was directed to D&D regarding the project
    identified the relevant corporate contact as “FCA Construction Lifetime Fitness.”
    Additionally, the signature line for the “Lifetime Fitness” representative who
    engaged in significant correspondence regarding the disputed payment matters
    with D&D, Sanaz Samie, identified Samie as an accounts payable clerk for “FCA
    Construction/Lifetime Fitness.” Samie and other Lifetime Fitness representatives
    directed D&D to send correspondence to “FCA Construction/Lifetime Fitness.”
    Samie’s letters also identified her location as 2902 Corporate Place, Chanhassen,
    Minnesota 55317, which is the address at which the Lifetime Fitness entities and
    FCA are both located.
    13
    The corporate representative of LTF, Tim Lundgren, testified that both LTF
    and FCA are wholly owned subsidiaries of “Lifetime Fitness, Inc.” During his
    deposition, when referring to the owner of the property, he actually referred to the
    relevant corporate entity as “Lifetime Fitness Real Estate.” Lundgren agreed that
    the officers of LTF were also officers of FCA. When asked about how to properly
    identify Lifetime Fitness, he stated that it was his practice to write both “Lifetime
    Fitness” and “Life Time Fitness when describing the activity.” Lundgren also
    agreed that at the time of the construction of the project, FCA did not have to
    submit change order requests to “LTF.” Lundgren explained that FCA only builds
    “Lifetime Fitness facilities” and, to his knowledge, there had never been any
    arbitration or litigation between “FCA” or “LTF,” or a “lien filed by FCA on any
    Lifetime Fitness project.” And neither “Lifetime” nor LTF had ever required a
    payment or performance bond to be procured by FCA on any projects.
    Based upon this evidence, as well as the ample evidence that Lifetime
    Fitness and FCA represented themselves to D&D as acting as both the owner or
    original contractor, we conclude that, for the purposes of determining compliance
    with chapter 53 of the Texas Property Code, any notice provided to a Lifetime
    Fitness entity or FCA at 2902 Corporate Place, Chanhassen, Minnesota 55317
    constituted notice to both the “owner” or “reputed owner” and the “original
    14
    contractor.”9 See Occidental Neb. Fed. Sav. 
    Bank, 773 S.W.2d at 688
    (noting that
    in light of “scheme of interlocking corporate shells,” “owner and contractor were,
    as a practical matter, the same people”); Marathon Metallic Bldg. Co. v. Tex. Nat’l
    Bank of Waco, 
    534 S.W.2d 743
    , 747 (Tex. Civ. App.—Waco 1976, no writ)
    (holding that claimant had substantially complied with statute despite incorrectly
    naming corporation as property owner when actual owners were corporation’s
    officers and stockholders). 10
    We have outlined above the four sets of documents that D&D contends
    constitute pre-lien notices under section 53.056. We conclude that the September
    11, 2008 and October 15, 2008 letters, sent to Lifetime Fitness/FCA, and the fax
    communications dated October 1 and 29, 2008 constitute second notices. TEX.
    PROP. CODE ANN. § 53.056(f) (“copy of the statement or billing in the usual and
    9
    We again note that although FCA is not a party to this appeal, LTF makes
    arguments concerning lack of notice received by FCA. Because we have
    concluded that any notice provided to a Lifetime Fitness entity or FCA at the same
    Minnesota address constituted notice to both the “owner” or “reputed owner” and
    the “original contractor,” we decline to consider whether LTF would be entitled to
    complain about the lack of notice provided to FCA.
    10
    LTF and Travelers also challenge the notices provided by D&D, asserting that
    D&D’s counsel filed with the trial court three certified mail receipt cards
    “knowing them to be forged.” However, there is no evidence to substantiate the
    forgery allegations against D&D’s counsel. Although there is evidence that
    certain certified mail receipts were altered after they were received, there is no
    evidence as to who altered the cards. The evidence also demonstrates that the card
    or cards to which the allegedly forged additions were made already referred to a
    Lifetime Fitness entity or FCA at the same Minnesota address. In light of our
    conclusion that Lifetime Fitness and FCA represented themselves to be one in the
    same, LTF and Travelers’ unsubstantiated allegations of forgery are immaterial.
    15
    customary form is sufficient as notice under this section”). Thus, pursuant to
    section 53.056, which requires a subcontractor to provide notice not later than the
    15th day of the second month following each month in which all or part of the
    materials were delivered, the September 11, 2008 notice would have been timely in
    regard to any materials delivered by D&D to J&G in July, August, and September
    2008; the October 1, 2008 fax notice and the October 15, 2008 letter would have
    been timely in regard to any materials delivered by D&D to J&G in August,
    September, and October 2008; and the October 29, 2008 fax, which was provided
    after the 15th day of October, would only have been timely in regard to any
    materials delivered by D&D to J&G in September and October 2008. See 
    id. § 53.051
    (“To perfect the lien, a person must comply with this subchapter.”). Thus,
    presuming that D&D complied with the other statutory requirements, D&D would
    have been entitled to recover a judgment for the unpaid balances that it, pursuant to
    section 53.056, timely presented to Lifetime Fitness/FCA in its pre-lien notices.
    Neither party has made any substantial effort in their briefing to this Court to
    clarify the specific amounts that were timely disclosed in these pre-lien notices.
    LTF and Travelers assert that nothing was timely presented, while D&D asserts
    that amounts consistent with the amounts reflected on the lien were timely
    presented in these pre-lien notices. D&D does not cite to any affidavit testimony
    or other evidence that articulates the specific amounts timely disclosed, and our
    16
    review of the record raises fact questions that would have precluded the trial court
    from finding, as a matter of law, that D&D timely presented, in its four pre-lien
    notices, approximately $90,000 in unpaid balances pertaining to materials provided
    to J&G. This is because, in each of the pre-lien notices, there appear to be amounts
    that were not timely presented under section 53.056.
    Regarding the September 11, 2008 notice, the attached balance statement
    refers to outstanding invoices for the months of August and September 2008, and
    the statement reflects a carry-forward balance of $76,038.12.         Although the
    September 11, 2008 notice would have been timely for disclosure of unpaid
    balances for materials delivered in July, August, and September 2008, there is no
    explanation as to when the materials supporting the carry-forward balance were
    delivered. This raises the possibility that the September 11, 2008 notice presented
    amounts that were not timely disclosed pursuant to section 53.056. The October
    15, 2008 notice presents similar problems. Although the October 15, 2008 notice
    would have been timely for any materials delivered in August, September, and
    October 2008, there is a carry-forward balance in the attached statement of
    $33,868.94, with no explanation as to when the materials for the carry-forward
    balance were delivered. The notice also references outstanding invoices for the
    months of June and July 2008, which would not have been timely presented by this
    notice.   Similarly, the October 1, 2008 faxed notice, which would have been
    17
    timely for materials delivered in August, September, and October 2008, includes
    an invoice for an unpaid balance of over $9,000 for materials delivered in July
    2008, which could not have been timely presented by that notice. Finally, the
    October 29, 2008 faxed notice, which would have been timely for materials
    delivered in September and October 2008, references significant unpaid balances
    for materials delivered in July and August 2008.
    Many of these invoices and charges are likely reflected in multiple notices.
    Thus, we recognize that an unpaid balance that was presented untimely in one of
    the notices may have been presented timely in another. However, D&D did not
    present any evidence that established as a matter of law that it timely presented in
    its pre-lien notices unpaid balances of over $90,000 for materials delivered to
    J&G. 11    Because a portion of the trial court’s judgment awarding damages to
    D&D was based upon unpaid balances for materials delivered by D&D to J&G,
    and because D&D did not demonstrate as a matter of law that it complied with
    section 53.056 for the full amount of damages the trial court awarded regarding the
    11
    D&D presented some evidence that it timely presented unpaid balances pertaining
    to materials delivered to J&G. But, D&D did not present evidence, through
    affidavit or otherwise, to establish, as a matter of law, that the specific amount of
    damages it sought were timely disclosed in these pre-lien notices. Donna Ortego’s
    affidavit testimony related to notices that she “sent or caused to be sent,” but she
    did not offer any factual explanation as to how D&D arrived at its damages figure
    in regard to the J&G lien. And, based upon the status of the record before us, we
    simply cannot say as a matter of law what amount of unpaid balances for materials
    that D&D delivered to J&G was timely presented by D&D’s multiple pre-lien
    notices.
    18
    J&G lien, we hold that the trial court erred in granting summary judgment in favor
    of D&D for amounts related to materials delivered by D&D to J&G.
    Affidavit Claiming Lien
    A person claiming a lien must file an affidavit with the county clerk of the
    county in which the property is located not later than the 15th day of the fourth
    calendar month after the day on which the indebtedness accrues. 
    Id. § 53.052(a).
    A subcontractor must timely file an affidavit that is signed by the person claiming
    the lien or another person on the claimant’s behalf, and the affidavit “must contain
    substantially”:
    (1)    a sworn statement of the amount of the claim;
    (2)    the name and last known address of the owner or reputed
    owner;
    (3)    a general statement of the kind of work done and materials
    furnished by the claimant and, for a claimant other than an
    original contractor, a statement of each month in which the
    work was done and materials furnished for which payment is
    requested;
    (4)    the name and last known address of the person by whom the
    claimant was employed or to whom the claimant furnished the
    materials or labor;
    (5)    the name and last known address of the original contractor;
    (6)    a description, legally sufficient for identification, of the
    property sought to be charged with the lien;
    (7)    the claimant’s name, mailing address, and, if different, physical
    address; and
    19
    (8)    for a claimant other than an original contractor, a statement
    identifying the date each notice of the claim was sent to the
    owner and the method by which the notice was sent.
    
    Id. § 53.054(a).
    On November 19, 2008, D&D filed an Affidavit Claiming Lien, which D&D
    asserts pertains to its claim for materials provided to J&G. 12 In regard to the
    statutory requirements pertaining to the time of filing, D&D presented evidence
    that it delivered materials to J&G that were incorporated into the Lifetime Fitness
    project as late as November 2008. For purposes of considering the timeliness of
    the filing of the affidavit, indebtedness accrues “on the last day of the last month in
    which labor was performed or the material furnished.” See 
    id. § 53.053(c).
    Thus,
    the indebtedness pertaining to the materials provided to J&G accrued on the last
    day of November 2008. Accordingly, D&D’s November 2008 affidavit was timely
    filed to the extent that it pertained to indebtedness accruing from materials
    provided to J&G.
    We now turn to the substance of D&D’s Affidavit Claiming Lien, which was
    purportedly filed in regard to materials delivered to J&G. In the affidavit, D&D
    stated that it furnished labor and materials for an improvement located at “Life
    Time Fitness, 13600 Will Clayton Parkway, Humble, Texas 77346”; “Life Time
    12
    As explained below, we make this qualification because the affidavit itself does
    not identify J&G.
    20
    Fitness” is the owner of the land and improvements; FCA, located at 2902
    Corporate Place, Chanhassen, Minnesota 55317, was the general contractor for the
    improvement; the “kind of work furnished by D&D [was] the supplying of
    Underground Utility materials”; the “amount paid for the construction, labor and
    materials and due and owing [sic] $90,414.12 is true, correct, and just, and with all
    just and lawful offsets, payments, and credits know to the undersigned allowed”;
    and D&D “sent notices” to “FCA/Life Time Fitness” by certified mail. D&D also
    identified itself as the claimant and provided its address. Thus, D&D complied, in
    several respects, with section 53.034. See 
    id. § 53.054(a)(1),
    (2), (5), (6), and (7).
    However, D&D did not, anywhere in the affidavit, set forth “a statement of
    each month in which the work was done and materials furnished for which
    payment is requested,” the name and last known address of the person to whom the
    claimant furnished the materials or labor,” or a statement identifying the date each
    notice of the claim was sent to the owner and the method by which the notice was
    sent. See 
    id. § 53.054(a)(3),
    (4), (8). In response to these deficiencies, D&D
    argues that there was no resulting prejudice because it had already provided pre-
    lien notices that included the month and description of materials delivered. Thus,
    D&D asserts it substantially complied with chapter 53’s requirements.
    Other Texas courts that have considered substantial-compliance issues under
    chapter 53 “have distinguished between mere technical defects, which can be
    21
    excused, and those defects that are more substantive in nature and, if overlooked,
    would read a provision out of the statute or prejudice another party.” Mustang
    Tractor & Equip. 
    Co., 263 S.W.3d at 441
    . For example, in Mustang Tractor, the
    court considered an affidavit that contained all of the information required by
    section 53.054 except a statement identifying the date each notice of the claim was
    sent to the owner and the method by which the notice was sent. 
    Id. After noting
    that the contractor had provided the owner with the requisite pre-lien notices,
    which identified the date and method by which they were sent, and after further
    noting that there was no allegation that the owner did not receive actual notice of
    the claims in a timely manner, the court held that the affidavit’s omission of the
    date and method by which the notices were sent constituted “a mere technical
    error.” 
    Id. The court
    reasoned that “because there [was] no risk that anyone was
    misled to his prejudice as a result of such omission,” the lien affidavits
    substantially complied with chapter 53. 
    Id. at 444.
    Similarly, in Richardson v. Mid–Cities Drywall, Inc., the court held that
    although the mailing address of the claimant did not appear in the sworn portion of
    the affidavit, the claimant had substantially complied with chapter 53 because the
    address appeared in the filing “as the address to which the document was to be
    returned by the clerk after it was recorded” and in “the attachment prepared by the
    county clerk as part of the official record specifying the index date and providing a
    22
    receipt.” 
    968 S.W.2d 512
    , 515 (Tex. App.—Texarkana 1998, no pet.); see also
    New AAA Apartment Plumbers, Inc. v. DPMC–Briarcliff, L.P., 
    145 S.W.3d 728
    ,
    730 (Tex. App.—Corpus Christi 2004, no pet.) (holding that claimant substantially
    complied with chapter 53 by sending copy of lien affidavit to property owner
    before, rather than after, affidavit was filed, and noting that “the purpose of the
    statute was fulfilled”).
    In contrast, in Milner v. Balcke-Durr, Inc., the court held that an affidavit
    that did not reference the months in which work was performed did not comply
    with chapter 53 and, thus, the claimant’s non-compliance precluded recovery by
    the purported lienholder. No. 03-05-00547-CV, 
    2006 WL 2190516
    , at *3 (Tex.
    App.—Austin Aug. 4, 2006, no pet.) (mem. op.). The court concluded that the
    omitted information was “essential to perfection of [the] statutory lien and to [the]
    claim against the indemnity bond. 
    Id. Similarly, in
    Mainline Industrial Services,
    Inc. v. Inland Enterprises, Inc., the court held that “the omission of the owner’s
    name and address alone” caused “the lien affidavit to fail as a matter of law.” No.
    06-00-00020-CV, 
    2001 WL 455843
    , at *3 (Tex. App.—Texarkana May 2, 2001,
    no pet.)
    Although we are mindful that mechanic’s and materialman’s statutes are to
    be liberally construed to protect laborers and materialmen, we find no support in
    the case law for concluding that the affidavit filed by D&D that pertained to the
    23
    materials it provided to J&G substantially complied with chapter 53’s
    requirements. Most significantly, the affidavit contains absolutely no reference to
    J&G, the contractor to whom D&D asserts that it furnished the materials for which
    it was seeking payment. This omission is even more significant in light of the
    additional omissions from the affidavit, including the omission of a statement of
    the months in which D&D furnished materials to J&G for which it was seeking
    payment.    We recognize that other courts have relied upon the substantial
    compliance standard to excuse the omission of the date of notice and method of
    service under chapter 53. See Mustang Tractor & Equip. 
    Co., 263 S.W.3d at 441
    .
    A court has also excused the omission of the mailing address of the claimant from
    the sworn portion of the affidavit. See 
    Richardson, 968 S.W.2d at 515
    . However,
    no court has ever excused the omission of the name of the party to whom materials
    were furnished, which is the basis for securing the lien in the first place; this
    cannot be considered a mere “technical defect.”
    D&D argues that there was no prejudice resulting from the omission because
    it had disclosed the information in its pre-lien notices. However, if we accepted
    D&D’s argument, we would be reading out a provision of the statute that, on its
    face, is of critical importance for providing, through a publicly-filed document,
    clear identification of the claim that is basis for the filing of the lien. If the
    multiple pre-lien notices and attached invoices and statements could be used to
    24
    satisfy these statutory requirements, then the obvious purpose for requiring a
    lienholder to identify both when and to whom it furnished materials for which it
    needed to be paid would be frustrated.
    In sum, the identity of the party to whom the materials were allegedly
    furnished and for which the claimant is seeking payment constitutes a material and
    “essential” component of a lien affidavit filed pursuant to section 53.054(a). 13 See
    Milner, 
    2006 WL 2190516
    , at *3. Accordingly, we hold that, by omitting this
    information, as well as the information pertaining to the months in which D&D
    furnished materials for which it claimed payment, D&D failed to substantially
    comply with chapter 53 and the trial court erred in granting D&D summary
    judgment on its claims for damages pertaining to the materials it delivered to J&G.
    We further hold that the trial court erred in denying LTF and Travelers’ summary-
    judgment motion regarding D&D’s claims against it for damages pertaining to the
    materials that it delivered to J&G.
    The Houston Earthworks Lien
    LTF and Travelers argue that the Houston Earthworks lien is not valid and
    enforceable because D&D failed to timely provide FCA, by registered or certified
    mail, notice concerning the unpaid materials provided to Houston Earthworks, see
    TEX. PROP. CODE ANN. § 53.056; D&D failed to timely provide LTF, by registered
    13
    We note that the bond itself obtained by LTF Real Estate does not identify J&G.
    25
    or certified mail, with a “90 Day Fund Trapping Notice” concerning the unpaid
    materials provided to Houston Earthworks, see id.; D&D’s Affidavit Claiming
    Lien failed to provide the name and last known address of the owner or reputed
    owner of the property in question, the description of the material sold to Houston
    Earthworks, and a statement of each month in which the material was allegedly
    sold for which payment is requested, see 
    id. § 53.054(a);
    and D&D failed to timely
    provide LTF and FCA, by registered or certified mail, a copy of its Affidavit
    Claiming Lien, see 
    id. § 53.055.
    Pre-Lien Notice
    As noted above, section 53.056 provides that in order for a lien to be valid, a
    claimant like D&D must provide a pre-lien notice of unpaid balances by registered
    or certified mail to “the original contractor” at its last known addresses no “later
    than the 15th day of the second month following each month in which all or part of
    the claimant’s labor was performed or material delivered”; it must also “give the
    same notice to the owner or reputed owner and the original contractor not later
    than the 15th day of the third month following each month in which all or part of
    the claimant’s labor was performed or material or specially fabricated material was
    delivered.” 
    Id. § 53.056(b).
    D&D presented summary-judgment evidence that on July 15, 2008, it sent to
    “Owner” Lifetime Fitness/FCA and “General Contractor” FCA, both at the same
    26
    Minnesota address, a letter, entitled “Notice of Claim Demand for Payment.” “re:
    the Lifetime Fitness in Humble, Texas.” In the letter, D&D stated that it was
    providing notice in compliance with chapter 53 that Houston Earthworks was
    indebted to D&D in the amount of $33,634.33 “for the sale and delivery of
    underground utility products” and, in the event payment was not received by
    August 15, 2008, D&D would file an Affidavit Claiming Lien on the property.
    D&D attached to this letter a “sworn statement of account” that Houston
    Earthworks was indebted to D&D. And, attached to the sworn statement is a
    statement referencing invoices for materials delivered by D&D to Houston
    Earthworks for the months of April, May, June, and July 2008. The statement
    reflects an outstanding balance of $33,634.33. Also attached to D&D’s letter is a
    certified mail receipt signed by an “agent” on July 18, 2008 with the address
    identified as “Lifetime Fitness/FCA” at the Minnesota address.14
    D&D also presented summary-judgment evidence that on August 15, 2008,
    it sent to “Owner” Lifetime Fitness and “General Contractor” FCA, both at the
    same Minnesota address, another letter entitled “Notice of Claim Demand for
    Payment regarding the Lifetime Fitness in Humble, Texas.” In the letter, D&D
    stated that it was providing notice in compliance with chapter 53 that Houston
    14
    D&D acknowledges that it did not timely present the unpaid balances for April
    2008 and, thus, the total amount it sought pertaining to the Houston Earthworks
    lien was $33,363.70.
    27
    Earthworks was indebted to D&D in the amount of $34,088.49 “for the sale and
    delivery of underground utility products” and, in the event that payment was not
    received by September 15, 2008, D&D would file an Affidavit Claiming Lien on
    the property. D&D attached to this letter (1) a “sworn statement of account” that
    Houston Earthworks was indebted to D&D, (2) a statement referencing invoices
    for materials delivered by D&D to Houston Earthworks for the months of April,
    May, June, and July 2008, which reflected an outstanding balance of $34,088.49,
    and (3) a certified mail receipt addressed to “Lifetime Fitness/FCA” at the
    Minnesota address signed by an “agent” on August 19, 2008. 15
    D&D also presented summary-judgment evidence that on July 14, 2008, it
    faxed to Lifetime Fitness or FCA copies of invoices for materials it had delivered
    to Houston Earthworks in April, May, June, and July 2008. In her affidavit,
    Ortego testified that she personally sent or caused to be sent the fax. The fax cover
    sheet indicates that the fax was sent to a fax number that was the same as that for
    Sanaz Samie, the accounts payable clerk for “FCA Construction/Lifetime Fitness.”
    Although there is not a total provided for all of the invoices, the face of the
    invoices reflect an outstanding total amount of over $30,000. D&D also presented
    summary-judgment evidence that on September 25, 2008, Ortego faxed to the fax
    15
    Unlike the statements attached to D&D’s pre-lien notices pertaining to J&G, the
    statement attached to these notices do not reference unexplained carry-forward
    balances.
    28
    number provided for “FCA Construction/Lifetime Fitness” a copy of D&D’s
    statement detailing invoices for materials delivered to Houston Earthworks. The
    statement references materials provided from April to July 2008 and reflects a total
    outstanding balance of $33,634.33. Finally, D&D presented summary-judgment
    evidence that on October 29, 2008, it faxed to “FCA Construction/Lifetime
    Fitness” a copy of all the invoices for materials delivered to both Houston
    Earthworks and J&G. Included with this fax was a summary of the “invoices for
    Houston Earthworks Resources, Inc.: Lifetime Fitness,” which reflects a total
    “open balance” of $33,634.33, derived from invoices from April, May, June, and
    July 2008.
    As explained above, the notices provided to either a Lifetime Fitness entity
    or FCA at the same Minnesota address can be considered as constituting notice to
    the other. Moreover, the July 15, 2008 cover letter was addressed to both Lifetime
    Fitness and FCA, and we have rejected LTF’s arguments that D&D did not
    substantially comply with chapter 53 because it sent notices to Lifetime Fitness
    rather than LTF. 16 Accordingly, we hold that D&D presented summary-judgment
    16
    LTF asserts in its briefing that “D&D concedes that it failed to provide the
    requisite 60 and 90 day notices to both LTF and FCA relative to Houston
    Earthworks’ alleged unpaid materials.” (Emphasis added.) It also asserts that
    “D&D admittedly failed to provide LTF and FCA with all pre-lien notices required
    by this statute via certified or registered mail.” (Emphasis added.) LTF offers no
    citation to the record to support these alleged concessions. And our review of the
    29
    evidence establishing that, with its July 15, 2008 letter, it timely provided notice
    pursuant to section 53.056 regarding materials that D&D provided to Houston
    Earthworks in May, June, and July 2008 and D&D had an unpaid balance for these
    materials in the amount of $33,363.70. 17
    Affidavit Claiming Lien
    As noted above, a person claiming a lien must file an affidavit with the
    county clerk of the county in which the property is located not later than the 15th
    day of the fourth calendar month after the day on which the indebtedness accrues.
    See 
    id. § 53.052(a).
    And the affidavit “must contain substantially,” among other
    things, a sworn statement of the amount of the claim; the name and last known
    address of the owner or reputed owner; a general statement of the kind of work
    done and materials furnished and a statement of each month in which the work was
    done and materials furnished; the name and last known address of the person to
    whom the claimant furnished the materials or labor; the name and last known
    address of the original contractor; and a statement identifying the date each notice
    record contradicts LTF and Travelers’ assertions that such concessions have been
    made during the course of this litigation.
    17
    To the extent that LTF and Travelers complain that D&D’s July 15, 2008 letter
    could not constitute both notices referenced in section 53.056, nothing in the plain
    language of the statute would suggest support for such an argument. Rather, case
    law indicates that such notice would substantially comply with chapter 53’s notice
    requirements. See Arias v. Brookstone, L.P., 
    265 S.W.3d 459
    , 466 (Tex. App.—
    Houston [1st Dist.] 2007, pet. denied) (concluding that notification of affidavit
    required by section 53.055 could be provided before lien actually filed”).
    30
    of the claim was sent to the owner and the method by which the notice was sent.
    See 
    id. § 53.054(a).
    Here, D&D presented in the summary-judgment record a copy of its
    Affidavit Claiming Lien file-stamped on October 21, 2008. For the purpose of
    considering the timelines of the filing of the affidavit, indebtedness accrues “on the
    last day of the last month in which labor was performed or the material furnished.”
    See 
    id. § 53.053(c).
    Thus, the indebtedness pertaining to the materials provided to
    Houston Earthworks accrued on the last day of July 2008 and D&D’s October
    2008 affidavit was timely filed to the extent that it pertained to indebtedness
    accruing from materials provided to Houston Earthworks.
    We now turn to the substance of D&D’s Affidavit Claiming Lien pertaining
    to Houston Earthworks. In the affidavit, D&D stated that it furnished labor and
    materials for an improvement located at “Life Time Fitness, 13600 Will Clayton
    Parkway, Humble, Texas 77346”; “Life Time Fitness/FCA” is the owner of the
    land and improvements; “Houston Earthworks Resources Inc,” located at a stated
    address in Tomball, Texas, was the general contractor for the improvement; the
    “kind of work furnished [was] the supplying of Utility pipe materials”; the
    “amount paid for the construction, labor and materials and due and owing [sic]
    $34,088.49 is true, correct, and just, and with all just and lawful offsets, payments,
    and credits known to the undersigned allowed”; and D&D “sent notices” to “Life
    31
    Time Fitness, FCA” by certified mail at the Minnesota address.             D&D also
    identified itself as the claimant and provided its address. Thus, D&D’s Houston
    Earthworks affidavit complied, in several respects, with section 53.034.
    Additionally, LTF and Travelers’ assertion that the affidavit did not set forth the
    name and last known address of the owner or reputed owner and the description of
    the material sold to Houston Earthworks is refuted by the face of the affidavit. The
    affidavit sets forth the Minnesota address for Lifetime Fitness and is not defective
    for failing to identify LTF as the corporate entity that owned the property. The
    affidavit also provided a basic description of the kind of material that D&D
    provided.
    However, the affidavit, contrary to section 53.054(a)(3), did not set forth the
    months that D&D delivered the materials to Houston Earthworks for which it
    remained unpaid. D&D asserts that, in light of the fact that Lifetime Fitness and
    FCA had “actual notice” of this information from its pre-lien notices, LTF was
    “not prejudiced by this technical omission on the lien.” At least one court has
    addressed an affidavit’s omission of this kind of information. See Milner, 
    2006 WL 2190516
    , at *3. As noted above, in Milner, the court held that an affidavit that
    did not reference the months in which work was performed and for which payment
    was being demanded did not comply with chapter 53. 
    Id. The court
    concluded
    that such information was “essential to perfection of [the] statutory lien and to [the]
    32
    claim against the indemnity bond. 
    Id. We agree
    with the reasoning set forth in
    Milner and conclude that information pertaining to the months for which the
    claimant is seeking to recover unpaid balances for materials delivered is an
    essential part of the affidavit. Although we remain mindful of the substantial-
    compliance standard, this information, like the information identifying the party to
    whom the materials were furnished, is critical to establishing the validity of the
    lien.   Although D&D established through summary-judgment evidence that it
    provided multiple pre-lien notices with attached statements and invoices reflecting
    an outstanding balance for materials provided to Houston Earthworks, the affidavit
    itself did not indicate the specific months for which it remained unpaid.
    Accordingly, we hold that, by omitting this information, D&D failed to
    substantially comply with chapter 53 and the trial court erred in granting D&D
    summary judgment on its claims for damages pertaining to the materials it
    delivered to Houston Earthworks. We further hold that the trial court erred in
    denying LTF and Travelers’ summary-judgment motion regarding D&D’s claims
    against it for damages pertaining to the materials that it delivered to Houston
    Earthworks.
    We sustain the portions of LTF and Travelers’ first and second issues in
    which they contend that D&D did not perfect its mechanic’s and materialman’s
    liens concerning J&G and Houston Earthworks.
    33
    Attorney’s Fees
    In a portion of their third issue, LTF and Travelers argue that the trial court
    erred in awarding D&D its attorney’s fees because “D&D is precluded from
    recovering attorney’s fees on claims on which it did not prevail.”
    A trial court may award reasonable costs and attorney’s fees “in any
    proceeding to foreclose a lien or to enforce a claim against a bond” or “in any
    proceeding to declare that any lien or claim is invalid or unenforceable.” 
    Id. § 53.156
    (Vernon Supp. 2011).
    Attorney’s fees may be recovered only when they are provided for by statute
    or by contract between the parties. Dallas Cent. Appraisal Dist. v. Seven Inv. Co.,
    
    835 S.W.2d 75
    , 77 (Tex. 1992).          In order to show that attorney’s fees are
    reasonable and necessary, a plaintiff is required to show that the fees were incurred
    while suing the defendant on a claim which allows for the recovery of such fees.
    See Stewart Title Guar. Co. v. Sterling, 
    822 S.W.2d 1
    , 10 (Tex. 1991). If the
    plaintiff is unsuccessful on such a claim, it is not entitled to recover its attorney’s
    fees. See Green Int’l, Inc. v. Solis, 
    951 S.W.2d 384
    , 390 (Tex. 1997). Because
    D&D is not the prevailing party, it cannot recover on its claim for attorney’s fees.
    See Ruiz v. Stewart Mineral Corp., 
    202 S.W.3d 242
    , 250 (Tex. App.—Tyler, 2006,
    pet denied).
    34
    We sustain the portion of LTF and Travelers’ third issue in which they
    contend that the trial court erred in awarding D&D attorney’s fees.
    Conclusion
    We reverse the judgment of the trial court and render judgment that D&D
    take nothing on its claims.
    Terry Jennings
    Justice
    Panel consists of Justices Jennings, Massengale, and Huddle.
    35