Eleuterio Fuentes v. San Anastacio Development Ltd., Oscar Corona, and Mauricio Gonzalez ( 2010 )


Menu:
  •                              NUMBER 13-08-00743-CV
    COURT OF APPEALS
    THIRTEENTH DISTRICT OF TEXAS
    CORPUS CHRISTI - EDINBURG
    ELEUTERIO FUENTES,                                                           Appellant,
    v.
    SAN ANASTACIO DEVELOPMENT LTD.,
    OSCAR CORONA, AND MAURICIO GONZALEZ,                                        Appellees.
    On appeal from the 398th District Court
    of Hidalgo County, Texas.
    MEMORANDUM OPINION
    Before Chief Justice Valdez and Justices Garza and Benavides
    Memorandum Opinion by Chief Justice Valdez
    This appeal involves a dispute regarding a construction contract in which appellees,
    San Anastacio Development Ltd., Oscar Corona, and Mauricio Gonzalez (collectively
    referred to as “San Anastacio”), contracted with appellant, Eleuterio Fuentes, to construct
    a water distribution system, a sanitary sewer system, storm drainage, and paving and
    parking lot improvements at a subdivision being developed by Fuentes. After a jury trial,
    judgment was rendered in favor of San Anastacio. San Anastacio was awarded $89,300
    in damages and $7,000 in attorney’s fees. By four issues, Fuentes contends that the trial
    court erred by: (1) granting judgment for San Anastacio because the jury did not make a
    substantial performance finding; (2) rendering judgment for Cordova and Gonzalez
    because “these parties did not submit a damage question”; (3) granting judgment for San
    Anastacio because San Anastacio “failed to meet [a] condition precedent to payment”; and
    (4) awarding attorney’s fees. We affirm.
    I. BACKGROUND
    On November 2, 2004, San Anastacio and Fuentes entered into a construction
    contract in which San Anastacio contracted to construct a water distribution system, a
    sanitary sewer system, storm drainage, and paving and parking lot improvements on the
    Adams Crossing Subdivision for $212,000. The contract provided that San Anastacio
    would complete the project within fifty working days of receiving a “notice to proceed” from
    the City of Mission, Texas. The contract provided, in part, “The Owner [Fuentes] agrees
    to pay the Contractor [San Anastacio] in current funds for the performance of the contract,
    as provided in the proposal, and to make payments on account thereof.” The contract also
    provided that San Anastacio’s payment requests were to be processed through Fuentes’s
    agent, engineer Jaime Enriquez.
    On July 1, 2005, San Anastacio filed suit against Fuentes for breach of contract for
    failing to make payments on the agreement, and Fuentes counterclaimed that San
    Anastacio failed to perform its obligations under the contract. A jury trial commenced on
    May 13, 2008. At trial, Gonzalez testified that he owns San Anastacio Development Ltd.
    2
    and that he and Corona, another contractor, entered into a joint venture to complete the
    construction project at the Adams Crossing Subdivision. Corona testified that he and
    Gonzalez began construction on the Adams Crossing project in mid-November 2005, and
    believed that they could complete the project within fifty working days of receiving the
    “notice to proceed” by combining their workforces.
    Under the terms of the contract, San Anastacio submitted invoices to Enriquez for
    approval. Upon receiving the invoices, Enriquez verified that the materials represented in
    the invoices had been installed at the Adams Crossing Subdivision and then prepared a
    “certificate for payment” that was submitted to Fuentes for payment. Three certificates for
    payment were entered into evidence.          The first certificate for payment was dated
    December 9, 2004, and requested payment of $61,664.85. The second certificate for
    payment was dated December 23, 2004, reflected that no payments had been made, and
    requested payment of $88,086.60. The third certificate for payment was dated January 21,
    2005; it reflected a $61,664.85 payment by Fuentes, presumably in response to the
    December 9, 2004 request, and requested payment of $54,932.31. San Anastacio
    contends that it continued to perform work and incur expenses after the January 21, 2005
    certificate for payment was prepared.
    Fuentes testified that the contract did not require that he make any payment to San
    Anastacio before the completion of the Adams Crossing Project. However, Fuentes
    confirmed that he satisfied payment under the first certificate for payment but none
    thereafter. Fuentes testified that he ceased making payments because he learned that
    San Anastacio had failed to pay various subcontractors who had worked on the Adams
    Crossing project. Fuentes also testified that, after he paid the first certificate of payment,
    3
    San Anastacio had twenty-one working days left under the contract to complete the project
    but performed little work. Fuentes stated that, after the fifty working days under the
    contract expired, he allowed San Anastacio to continue working on the project for two
    additional months before terminating the contract in March 2005. After terminating his
    contract with San Anastacio, Fuentes contracted with another construction company to
    complete the project for approximately $70,000.
    Fuentes’s testimony was hotly disputed by Corona and Gonzalez. According to
    Corona and Gonzalez, when the parties contracted with Fuentes, they were told to turn in
    their requests for payment on the 25th of each month and that they would be paid on the
    10th of the following month. Moreover, Enriquez opined that a provision found within the
    contract required Fuentes to make payments as the work progressed in accordance with
    the work reflected in the certificates of payment. Corona admitted that San Anastacio was
    unable to complete the Adams Crossing project but insisted that its failure to complete the
    project resulted from Fuentes’s failure to make the requested payments. Corona testified
    that Fuentes owes San Anastacio $37,000 for work performed under Corona’s portion of
    the San Anastacio joint venture. Additionally, Gonzalez testified that Fuentes owes San
    Anastacio a total of $89,300 for work performed under the contract. Gonzalez stated that
    the $89,300 is comprised of $37,000 for work performed under Corona’s portion of the joint
    venture, as well as $52,000 for work performed under Gonzalez’s portion.
    The jury found that both San Anastacio and Fuentes failed to comply with the
    November 2, 2004 contract.       The jury awarded $89,300 to San Anastacio after it
    determined that Fuentes was the first to breach the contract and that his breach was not
    excused. The trial court entered a final judgment providing that San Anastacio evelopment
    4
    Ltd., Oscar Corona, and Mauricio Gonzalez recover $89,300 in actual damages, pre- and
    post-judgment interest, attorney’s fees, and court costs. Fuentes filed a “Motion for
    Judgment Notwithstanding the Verdict” and a “Motion for New Trial or in the Alternative
    Motion to Modify Final Judgment”; however, the trial court denied these motions. This
    appeal ensued.
    II. SUBSTANTIAL PERFORMANCE
    By his first issue, Fuentes contends that the trial court erred in awarding damages
    to San Anastacio because San Anastacio failed to plead and obtain a jury finding on
    whether it substantially performed under the contract. “Substantial performance is a
    doctrine that allows breaching parties who have substantially completed their obligations
    to recover on a contract.” Tips v. Hartland Developers, Inc., 
    961 S.W.2d 618
    , 623 (Tex.
    App.–San Antonio 1998, no pet.). Thus, Fuentes asserts that San Anastacio’s failure to
    obtain a jury finding on whether it substantially completed the requirements of the
    construction contract precludes it from collecting damages. We disagree.
    In the present case, the jury found that: (1) both parties failed to comply with the
    construction contract; (2) Fuentes was the first party to fail to comply; and (3) Fuentes’s
    failure to comply was not excused.        Texas law permits builders to recover under
    construction contracts upon substantial performance, even if they have breached the
    building contract. See Vance v. My Apartment Steak House of San Antonio, Inc., 
    677 S.W.2d 480
    , 481 (Tex. 1984). However, under the present facts, substantial performance
    is irrelevant. “In the standard contract dispute, one party cancels the contract or refuses
    to pay due to alleged breaches by the other; in such circumstances, jurors will often find
    both parties failed to comply with the contract . . . unless instructed that they must decide
    5
    who committed the first material breach.” Mustang Pipeline Co. v. Driver Pipeline Co., 
    134 S.W.3d 195
    , 200 (Tex. 2004) (citing Mead v. Johnson Group, Inc., 
    615 S.W.2d 685
    , 689
    (Tex. 1981) (default by one contracting party excuses performance by the other); see also
    Lake LBJ Mun. Util. Dist. v. Coulson, 
    692 S.W.2d 897
    , 908 (Tex. App.–Austin 1985), rev’d
    on other grounds, 
    734 S.W.2d 649
    (Tex. 1987) (suggesting disjunctive submission in such
    cases)). Although the jury found that both parties failed to comply with the contract, the
    jury’s finding that Fuentes was the first to fail to comply excused San Anastacio from
    further performance. See 
    id. at 196
    (“It is a fundamental principal of contract law that when
    one party commits a material breach of that contract, the other party is discharged or
    excused from further performance.”). Moreover, the jury found that damages resulted from
    Fuentes’s breach. Accordingly, San Anastacio is not precluded from collecting damages
    by failing to obtain a jury finding on substantial performance, and the trial court did not err
    by rendering judgment in favor of San Anastacio. Fuentes’s first issue is overruled.
    III. JURY CHARGE
    By his second issue, Fuentes contends that the trial court erred in rendering
    judgment for Cordova and Gonzalez because “these parties did not submit a damage
    question.” Fuentes argues that charge error exists because the jury was asked:
    What sum of money, if any, if paid now in cash, would fairly and reasonably
    compensate SAN ANASTACIO DEVELOPMENT, LTD for its damages, if
    any, that resulted from ELEUTERIO FUENTES[‘S] failure to comply with the
    construction contract dated November 2, 2004?
    Fuentes asserts that this question did not allow the jury to consider “the correct measure
    of damages.”1
    1
    Texas Rule of Civil Procedure 301 provides that “[t]he judgm ent of the court shall conform to the
    pleadings, the nature of the case proved and the verdict . . . .” T EX . R. C IV . P. 301. Although an argum ent m ay
    be m ade that the trial court’s judgm ent does not conform to the jury’s verdict, this issue is not raised by
    6
    “[A]ny complaint to a jury charge is waived unless specifically included in an
    objection.” In re B.L.D., 
    113 S.W.3d 340
    , 349 (Tex. 2003) (citing TEX . R. CIV. P. 274; TEX .
    R. APP. P. 33.1(a)(1)). “A party must make the trial court aware of the complaint, timely
    and plainly, and obtain a ruling.” 
    Id. (citing State
    Dep’t of Highways & Pub. Transp. v.
    Payne, 
    838 S.W.2d 235
    , 241 (Tex. 1992)). Fuentes did not object to the jury charge during
    trial or in any post-trial motion. We therefore conclude that Fuentes has waived his second
    issue. See TEX . R. CIV. P. 274; TEX . R. APP. P. 33.1(a)(1); see also In re 
    B.L.D., 113 S.W.3d at 349
    .
    IV. CONDITION PRECEDENT
    By his third issue, Fuentes contends that the trial court erred in granting judgment
    for San Anastacio because San Anastacio “failed to meet [a] condition precedent to
    payment.” The contract between Fuentes and San Anastacio provides:
    Either the “Owner” [Fuentes] of [sic] the “Contractor” [San Anastacio] may
    terminate this agreement for any reason at any time by giving notice in
    writing to the other. Upon notice of termination by either party, th[e]
    “Contractor” shall discontinue all services in connection with this agreement.
    Within thirty (30) days after notice of termination, the “Contractor” shall
    submit an invoice showing in detail the services under this agreement to the
    date of termination to the “Engineer” for approval. The “Owner” shall then
    pay the “Contractor” as per invoice approved by the “Engineer.” [Enriquez].
    Fuentes alleges that he terminated the contract by letter in March 2005, and that
    San Anastacio’s last request for payment was made on January 21, 2005. As previously
    discussed, the jury found that Fuentes was the first to breach the contract. Fuentes’s
    breach excused San Anastacio from further performance. See Mustang Pipeline 
    Co., 134 S.W.3d at 196
    . Even if Fuentes attempted to terminate the contract by a letter presented
    to San Anastacio in March 2005, evidence was presented that, as of that date, Fuentes
    Fuentes. Accordingly, we consider only whether the jury charge was erroneous. See T EX . R. A PP . P. 47.1.
    7
    had already         breached the contract.   Accordingly, Fuentes’s breach excused San
    Anastacio from submitting a final invoice. See 
    id. Fuentes’s third
    issue is overruled.
    V. PRESENTMENT
    In his fourth issue, Fuentes contends that the trial court erred by awarding attorney’s
    fees to San Anastacio because there is no evidence that San Anastacio presented its
    demand for attorney’s fees to Fuentes as required by civil practice and remedies code
    section 38.002(1). See TEX . CIV. PRAC . & REM . CODE ANN . § 38.002(1) (Vernon 2008)
    (providing that “[t]o recover attorney’s fees . . . the claimant must be represented by an
    attorney . . .”).
    A party who prevails on a breach of contract claim is entitled to recover attorney’s
    fees for prosecution of the claim. 
    Id. § 38.001
    (Vernon 2008). To recover attorney’s fees,
    a claimant must have first presented the claim to the opposing party or his agent. 
    Id. § 38.002(2).
    The purpose of presentment is to allow the person against whom the claim is
    asserted an opportunity to pay a claim within thirty days after notice of the claim without
    incurring an obligation for attorney’s fees. Jones v. Kelley, 
    614 S.W.2d 95
    , 100 (Tex.
    1981). No particular form of presentment is required. 
    Id. All that
    is necessary is an
    assertion of a debt or claim and a request for compliance made to the opposing party, and
    the party’s refusal to pay. Panizo v. Young Men’s Christian Ass’n of Greater Houston Area,
    
    938 S.W.2d 163
    , 168 (Tex. App.–Houston [1st Dist.] 1996, no writ). The statute is to be
    generously construed to promote its underlying purpose. TEX . CIV . PRAC . & REM . CODE
    ANN . § 38.005 (Vernon 2008).
    Fuentes asserts that San Anastacio is not entitled to recover attorney’s fees
    because “there was no evidence in the record that established that [San Anastacio] w[as]
    8
    represented by counsel when any request for payment was made . . . .” The plain
    language of section 38.002(1) requires that in order to recover attorney’s fees “the claimant
    must be represented by an attorney”; however, it does not set forth whether or not the
    claimant must be represented by an attorney at the time of presentment. 
    Id. § 38.002(1).
    Fuentes fails to cite any authority for his argument that an attorney must be employed by
    the claimant at the time of presentment, and we find none.2 Construing section 38.002
    generously, we cannot say on this record that the trial court erred in concluding that
    presentment had been satisfied so as to allow recovery of attorney’s fees. Fuentes’s fourth
    issue is overruled.
    VI. CONCLUSION
    Having overruled all of Fuentes’s issues on appeal, we affirm the judgment of the
    trial court.
    ROGELIO VALDEZ
    Chief Justice
    Delivered and filed the
    29th day of July, 2010.
    2
    On appeal, Fuentes does not assert that San Anastacio failed to prove that: (1) it presented the
    claim to Fuentes; or (2) paym ent for the just am ount owed was not “tendered before the expiration of the 30th
    day after the claim is presented.” T EX . C IV . P RAC . & R EM . C OD E A N N . § 38.002(2), (3) (Vernon 2008).
    Accordingly, we do not reach these issues. See T EX . R. A PP . P. 38.1, 47.1.
    9