Southern Green Builders, LP and Sam Seidel v. Jaime Cleveland and Jennifer Cleveland ( 2018 )


Menu:
  • Reversed and Remanded and Majority and Dissenting Opinions filed August 9,
    2018.
    In The
    Fourteenth Court of Appeals
    NO. 14-17-00483-CV
    NO. 14-17-00540-CV
    SOUTHERN GREEN BUILDERS, LP AND SAM SEIDEL, Appellants
    V.
    JAIME CLEVELAND, Appellee
    On Appeal from the 215th District Court
    Harris County, Texas
    Trial Court Cause No. 2017-13499
    DISSENTING OPINION
    Because I believe that the arbitration clause is not mandatory, I respectfully
    dissent.
    1.    The Negotiations
    Southern Green sent Cleveland a form boilerplate construction contract.
    Cleveland modified Southern Green’s boilerplate contract by removing nearly the
    entirety of the mandatory arbitration clause and changing the words “shall be
    submitted to binding arbitration” to “may be submitted to binding arbitration.” He
    also added the language that both parties “shall have the right to seek other legal
    remedies as they see fit and the law allows.”
    This is what Cleveland did to the arbitration clause—he struck through most
    of the provision and added the underlined words:
    (c) Mediation-Binding Arbitration/Waiver of Jury Trial. The
    Owner and Builder agree that all controversies, claims (and any related
    settlements), or matters in question arising out of or relating to (i) this
    Contract, (ii) any breach or termination of this Contract, (iii) the
    construction of the Home and/or its repairs, (iv) any acts or omissions
    by the Builder (and its officers, directors or agents), and/or (v) any
    actual or purported representations or warranties, express or implied,
    relating to the Property and/or the Home (herein referred to collectively
    as a “Dispute”) shall may be submitted to binding arbitration, but both
    parties shall also have the right to seek other legal remedies as they see
    fit and the law allows. The Parties will attempt to resolve any Dispute
    through informal discussions and the dispute may be submitted to non-
    binding mediation under the Contraction Industry Mediation Rules of
    the American Arbitration Association (“AAA”). In the event that one
    or both parties do not desire to mediate, or the Dispute it not resolved
    by direct discussions and/or mediation, the Dispute shall be submitted
    to the AAA for binding arbitration in accordance with the Construction
    Industry Arbitration Rules of the AAA. The Parties will share equally
    all filing fees and administrative costs of the arbitration, however, any
    Award rendered may equitably reallocate those costs. The arbitration
    shall be governed by Texas law and the U.S. Arbitration Act, 9 U.S.C.
    1-16, to the exclusion of any provisions of state law that are inconsistent
    with the application of the Federal Act.
    In rendering the Award, the arbitrator shall state the reasons
    therefor, including any computations of actual damages or offsets, if
    applicable. The Parties agree to abide by and fully perform in
    accordance with any Award rendered by the arbitration. If the non-
    prevailing Party fails to comply with all aspects of the Award within
    thirty (30) days following issuance of the Award, then the prevailing
    Party shall be entitled to seek enforcement of the Award in any court of
    2
    competent jurisdiction. If such enforcement becomes necessary, the
    prevailing Party in such proceeding shall recover its necessary and
    reasonable attorney’s fees, in addition to any other relief to which that
    Party is entitled.
    Southern Green agreed to the changes.
    2.    Under Texas Supreme Court case law, we can consider deletions.
    In Houston Exploration Co. v Wellington Underwriting Agencies, LTD, 
    352 S.W.3d 462
    (Tex. 2011), the Supreme Court considered the deletion of certain
    paragraphs from a form contract to determine the intent of the parties. The court
    noted that it had twice before considered deletions from a form contract in
    determining the meaning of a contract. 
    Id. at 470–71
    (citing Gibson v. Turner, 
    294 S.W.2d 781
    (Tex. 1956) and Houston Pipe Line Co. v. Dwyer, 
    374 S.W.2d 662
    (Tex.
    1964)).
    And the Supreme Court has also considered deletions from a form contract in
    determining the scope of an arbitration contract. See G.T. Leach Builders, LLC v.
    Sapphire V.P., LP, 
    458 S.W.3d 502
    , 526 (Tex. 2015). This rule of construction is
    not limited to where a party contends a contract is ambiguous. 
    Id. 3. Generally,
    “may” is permissive, and “shall” is mandatory.
    Under both the ordinary meaning of words and case law, may is permissive
    while shall is mandatory. See New Oxford American Dictionary 1082, 1604 (Angus
    Stevenson & Christine Lindberg eds., 3d ed. 2010) (defining “may” as “expressing
    permission” and “shall” as “expressing an instruction or command”); Dallas Cnty.
    Cmty. Coll. Dist. v. Bolton, 
    185 S.W.3d 868
    , 873–74 (Tex. 2005) (“may” grants
    permission to); Helena Chem. Co. v. Wilkins, 
    47 S.W.3d 486
    , 493 (Tex. 2001)
    (“shall” is mandatory, creating a duty or obligation). This is also true under the Code
    3
    Construction Act—“may” creates discretionary authority or grants permission or a
    power while “shall” imposes a duty. See Tex. Gov’t Code 311.016.
    4.    Contracts should not be interpreted to render a part of the contract
    meaningless.
    Courts are to examine and consider the entire writing to harmonize and give
    effect to all of the provisions of a contract so that “none will be rendered
    meaningless.” See Coker v. Coker, 
    650 S.W.2d 391
    , 393 (Tex. 1983); see also FPL
    Energy, LLC v. TXU Portfolio Mgmt. Co., 
    426 S.W.3d 59
    , 69 (Tex. 2014)
    (interpreting a contract, as a matter of law, to avoid rendering a provision of the
    contract meaningless).
    5.    Using these rules, the agreement does not mandate arbitration.
    The deletion of the mandatory arbitration provision from a form contract
    indicates the intent of the parties to not make arbitration mandatory. The agreement
    provides that the parties may arbitrate and also provides that the parties shall have
    the right to seek other legal remedies as they see fit. Construing the contract to
    require mandatory arbitration would make the remainder of the sentence
    meaningless—what other legal remedies could the sentence refer to if arbitration
    was mandatory? The arbitration provision is not mandatory.
    6.    Neither U.S. Home Corp. nor Feldman/Matz compels a different result.
    In In re U.S. Home Corp., 
    236 S.W.3d 761
    (Tex. 2007) (orig. proceeding) (per
    curiam), the Supreme Court construed two contracts in connection with the sale of a
    home. The sales contract stated that any claim “shall be determined by mediation or
    by binding arbitration.” The warranty book said that either party “may request”
    arbitration. The court concluded this did not render the contracts ambiguous. “While
    the warranty’s clause allowed either party to request arbitration, nothing in it
    4
    suggests that arbitration was optional if either did . . . .” 
    Id. at 765.
    By contrast, the
    clause in this case does suggest that arbitration was optional for two reasons as noted
    above—the deletion of the mandatory language and the addition of a provision that
    the parties shall have the right to seek other legal remedies.
    Similarly, the contract language in Feldman/Matz is quite different from the
    contract language in this case. See Feldman/Matz Interests, L.L.P. v. Settlement
    Capital Corp., 
    140 S.W.3d 879
    , 888 (Tex. App.—Houston [14th Dist.] 2004, no
    pet.). The contract provided in pertinent part:
    With respect to any and all other disputes or claims between us
    whatsoever related to or arising out of our services, we agree that either
    of us may submit the same to a nationally recognized, neutral,
    arbitration association (eg., AAA, JAMS, etc.) for final, binding and
    nonappealable resolution pursuant to its single arbitrator, expedited
    arbitration rules. . . If the first arbitration organization which receives a
    written demand for arbitration of the dispute from either of us does not
    complete the arbitration to finality within four months of the written
    demand, either party then may file a written demand for arbitration of
    the dispute with another nationally recognized, neutral, arbitration
    association, with the prior arbitration association then being
    immediately divested of jurisdiction, subject to a decision being
    rendered by the replacement arbitration association within four months
    of the written demand being filed with the replacement arbitration
    association. The decision of the arbitrators shall be final in all respects
    and shall be non-appealable. Any person may have a court of competent
    jurisdiction enter into its record the findings of such arbitrators for all
    purposes including for the enforcement of such award.
    This contract language evidences an intent that “may submit” is
    mandatory, because it did not provide for any opt out of the arbitration, nor
    did it provide that the parties shall retain other legal remedies. In fact, it
    specifically references a request for arbitration by only one party (demand
    from either of us). Under this agreement, arbitration was the only remedy.
    5
    “May” does not take on a special meaning in an arbitration contract. As
    always, the entire contract must reviewed to see if it is mandatory or
    permissive. See G.T. Leach 
    Builders, 458 S.W.3d at 525
    (concluding that a
    joinder provision in an arbitration contract that used the word “may” was
    permissive rather than mandatory).
    7.    Conclusion
    The arbitration requirement in this contract is permissive, not
    mandatory. The trial court correctly denied the motion to compel arbitration.
    Because the majority holds otherwise, I respectfully dissent.
    /s/       Tracy Christopher
    Justice
    Panel consists of Justices Christopher, Donovan, and Jewell. (Donovan, J.,
    majority).
    6