Lyle B. Murphey, Trustee of the Lyle Bernhardt Murphey Trust Under Agreement Dated May 2, 2002 And Lyle B. Murphey, Individually v. Old Dollar Properties, LLC ( 2021 )


Menu:
  •                              NUMBER 13-19-00530-CV
    COURT OF APPEALS
    THIRTEENTH DISTRICT OF TEXAS
    CORPUS CHRISTI – EDINBURG
    LYLE B. MURPHEY, TRUSTEE OF THE
    LYLE BERNHARDT MURPHEY TRUST
    UNDER AGREEMENT DATED MAY 2, 2002;
    AND LYLE B. MURPHEY, INDIVIDUALLY,                                                    Appellant,
    v.
    OLD DOLLAR PROPERTIES, LLC,                                                            Appellee.
    On appeal from the 126th District Court
    of Travis County, Texas.
    MEMORANDUM OPINION
    Before Chief Justice Contreras and Justices Hinojosa and Silva
    Memorandum Opinion by Justice Hinojosa
    Appellee/cross-appellant Old Dollar Properties, LLC                 1   (Old Dollar) sued
    1 Richard Smith, the owner of Old Dollar, is also named as a plaintiff in the suit. However, he
    nonsuited his individual claims, and he is not named in the trial court’s judgment.
    appellant/cross-appellee Lyle B. Murphey, individually and as trustee of the Lyle
    Bernhardt Murphey Trust under agreement dated May 2, 2002, for fraud, breach of
    contract, and violations of the Texas Deceptive Trade Practices Act (DTPA), alleging that
    Murphey failed to disclose various issues with the septic system when selling a mobile
    home park to Old Dollar. Following a jury trial, the trial court signed a final judgment
    awarding $195,500 in damages on Old Dollar’s breach of contract claim. In four issues,
    which we treat as five, Murphey argues: there was insufficient evidence establishing the
    (1) breach, (2) causation, and (3) damage elements of Old Dollar’s contract claim; (4) the
    trial court’s breach of contract instruction was erroneous; and (5) the trial court erred in
    not awarding Murphey attorney’s fees.
    In two cross-issues, Old Dollar argues that the trial court erred in failing to: (1) enter
    judgment on its DTPA claim; and (2) award Old Dollar attorney’s fees. We reverse and
    remand in part and affirm in part. 2
    I.      BACKGROUND
    A.      Pleadings
    Murphey sold a mobile home park (property) located in Travis County, Texas to
    Old Dollar. Old Dollar and its owner Richard Smith later sued Murphey alleging that
    Murphey failed to disclose “that the septic system serving the subject property lacked
    sufficient capacity to accommodate the mobile homes and feed store” on the property.
    The case proceeded to a jury trial.
    2 The Texas Supreme Court transferred this case from the Third Court of Appeals in Austin to this
    Court pursuant to a docket equalization order. See TEX. GOV’T CODE ANN. § 73.001.
    2
    B.     Trial
    Trial evidence showed that, in December of 2015, Smith contacted Murphey about
    purchasing the property, a four-acre tract of land with sites for eighteen mobile homes
    and a feed store. The property generated revenue from monthly rental payments from the
    mobile home owners and the proprietor of the feed store. The property contained private
    water and septic systems.
    During negotiations, Smith asked several questions regarding the septic system,
    which treated the sewage for the property. Murphey provided Smith with the design for
    the septic system which was built in 1982. The system contains eleven cascading tanks
    in which solids settle from the sewage permitting the liquid to flow to a final tank, called
    the effluent tank. The effluent tank then pumps the liquid sewage underneath the surface
    of the property’s drain field, where the liquids are absorbed in the soil. Murphey informed
    Smith that he spent approximately $4,500 a year to repair and maintain the septic system.
    He also told Smith that he paid $12,000 annually for a maintenance man, whose duties
    included maintaining the septic system. Murphey stated that he cleaned the lines in the
    drain field every three months, conducted a high-pressure cleaning of the system every
    two years, and had a vacuum truck remove solid waste from the system every two to
    three years, a process the parties refer to as “pumping” the septic system.
    Following negotiations, Smith and Murphey agreed on a $1 million purchase price.
    At Smith’s request, the sale was divided into two transactions for tax purposes: a
    $700,000 transaction for the land, and a $300,000 transaction for the water and septic
    systems. The contracts were executed on February 1, 2016.
    3
    The sales contract for the land included several disclosures in which Murphey
    indicated that the septic system was operational and that there were no known defects in
    the system. Murphey further indicated that no systems on the property needed repair.
    Murphey agreed to “pump all septic tanks and replace pressure tanks” prior to closing.
    An addendum to the sales contract provided that Murphey would convey the water and
    septic systems to Old Dollar for $300,000.
    The parties executed a separate “Bill of Sale,” for the purchase of the personal
    property affixed or attached to the real property, including the water and septic systems.
    The bill of sale specified that Old Dollar was taking the property “as is” subject to the
    representations and warranties contained in the purchase contract.
    In March of 2016, Travis Hausmann, a neighboring property owner, discovered
    sewage on his property that was originating from the mobile home park. Hausmann
    contacted Murphey believing that he still owned the property. Murphey notified Smith of
    the concern. During their conversation, Murphey told Smith that there was a sump pump
    located in the effluent tank and that Smith should turn it off. Murphey testified that he told
    Smith about the pump during one of their meetings prior to the sale and that he only used
    the pump when necessary to remove rainwater that had accumulated in the tank. Smith
    denied that such a conversation occurred, stating that he did not learn of the pump until
    after sewage was discovered on the neighboring property.
    When Smith arrived at the property, he discovered the sump pump, which was
    connected to a hose. The hose directed the waste from the effluent tank toward a ravine
    which led to the neighboring property. Concerned that he was directing sewage onto his
    4
    neighbor’s property, Smith had someone remove the pump.
    Hausmann testified that he discovered sewage on his property a year prior while
    Murphey owned the property. He stated that on both occasions that there had been no
    recent rainfall.
    Gary Platzer was called as an expert witness in septic system repairs. He has
    repaired septic systems for thirty-three years. Both Murphey and Smith were customers
    of Platzer, who has visited the property around six to seven times. Months before Old
    Dollar purchased the property, Platzer addressed a backup in the septic system. Platzer
    stated that the drain field was clogged, preventing sewage from being absorbed by the
    field. Platzer pulled the caps on the lines in the drain field to release the backed-up
    sewage. He noticed that a lot of grease and “sludge” came out. Platzer flushed each of
    the drain field lines, pressurized them, and added treatments. Platzer testified that there
    was sludge and grease pooling on top of the drain field which indicated that the system
    was “overfilled.” Platzer testified that the septic system was not working properly. He
    informed Murphey at the time that he had a “grease problem.” He also stated that the
    septic system was undersized for the number of occupants of the property. Platzer
    explained that with so many residents, the grease and solid waste did not have time to
    settle as it passed through the septic system. Platzer opined that the drain field needed
    to be at least double its current size.
    Smith contacted Platzer after discovering the sump pump in the effluent tank.
    Platzer went to the property and observed that the pump was directing sewage from the
    tank to the Hausmann’s property, which Platzer believed to be illegal. He stated that a
    5
    hose was directed down into a “gully.” Platzer maintained that any fluid coming from the
    tank constituted sewage. Platzer stated that Smith must now pump waste from the septic
    system twice a month to prevent the system from backing up. This costs Smith $1,100
    per month. Platzer testified that it would cost $75,000 to expand the drain field to the
    appropriate size, which he believed to be a reasonable expense.
    Wayne Dolezal was called as an expert witness concerning septic systems in
    general. Dolezal has been installing septic systems since 1984. He testified that if a septic
    system is working properly, there would never be a need to pump fluid from the effluent
    tank onto the surface. He stated that the tank should be watertight and should never have
    rainwater within it. Dolezal stated that rainwater can saturate the drain field preventing it
    from absorbing sewage. Dolezal recommended that Smith build a berm around the field
    to prevent runoff. Dolezal agreed that the drain field needed to be doubled in size for the
    septic system to be operational. He stated that pumping the system twice a month was
    only a temporary remedy.
    Smith testified that, in addition to incurring expenses for pumping, he has spent
    money to build a berm next to the drain field as recommended by Dolezal. Smith stated
    that he plans to expand the drain field, which would require that he remove two mobile
    home sites and reduce his monthly revenue by $930. Smith testified that if he expands
    the drain field he would suffer $233,315 in damages over the ten years he plans to own
    the property. This calculation includes the cost to expand the drain field, the accumulated
    expenses to keep the system operational, and the lost revenue from removing two mobile
    home sites. Smith stated that it would cost him $210,415 over the next ten years to
    6
    maintain the septic system without expanding the drain field. Smith introduced checks
    and invoices to demonstrate the expenses he had incurred to date. Smith also speculated
    that the septic issues reduced the property’s market value by 20%.
    Gary Hoffman, the owner of the feed store on the property, testified that during the
    period Murphey owned the property he observed sewage on the surface of the drain field
    every two or three months. Hoffman stated that he had to shut the doors of the feed store
    because of the smell.
    Murphey testified that he only used the sump pump in the effluent tank three times
    in the twenty years he owned the property. Murphey maintained that he showed the sump
    pump to Smith and explained its purpose. Murphey testified that it was important to
    encourage residents to limit their water usage so that the septic system would not be
    overburdened. Murphey stated that he pumped the entire system annually unless there
    was a lot of rainfall. He believed that the septic system worked properly for him while he
    owned the property.
    C.    Jury Charge & Verdict
    At the charge conference, Murphey objected to Question 1 which asked: “Did
    [Murphey] fail to comply with the agreement(s) for the purchase of the Property, if any?”
    Murphey further objected to the following definition in the charge: “The ‘Property’ means
    the mobile home park located at 21120 West S.H. 71, Spicewood, Texas.” Murphey
    argued that the definition and the question were “inadequate because [they were] overly
    broad in taking the two transactions . . . and combining them into one transaction by the
    interplay between [the defined term] and the use of the term ‘agreements’. . . .” The trial
    7
    court overruled the objection.
    The jury answered yes to Question 1, thereby finding that Murphey failed to comply
    with the agreements for the purchase of the property. The jury also answered yes to
    Question 2 which asked whether Murphey “engage[d] in any false, misleading, or
    deceptive act or practice that [Old Dollar] relied on to its detriment and that was a
    producing cause of damages to [Old Dollar].” However, it found that Murphey did not
    engage in such conduct knowingly or intentionally. The jury also found that Murphey did
    not commit statutory fraud. The jury found that Old Dollar sustained $24,500 in past
    damages “to address the septic system problems,” and that Old Dollar would in
    reasonable probability sustain $171,000 in damages “in the future to address the septic
    system problems[.]” The jury assessed no damages due to the diminution of the market
    value of the property as the result of the septic system problems.
    D.     Bench Trial—Attorney’s Fees
    Next, the trial court held a bench trial on the parties’ competing claims for attorney’s
    fees. Old Dollar’s counsel, Gary A. Calabrese, requested that the trial court award
    $69,000 in attorney’s fees as well as conditional appellate attorney’s fees, and testified in
    support of his request. Murphey’s attorney, Kim Brown, submitted an affidavit detailing
    his time on the case supported by his resume and itemized billing statements.
    The trial court took the matter under advisement. It later issued findings of fact and
    conclusions of law, stating that “[t]he evidence is insufficient to support an award of
    attorney’s fees in any amount.”
    8
    E.      Post-Trial Motions & Judgment
    Murphey filed a motion for judgment on the verdict, or in the alternative,
    notwithstanding the verdict, arguing that Old Dollar should take nothing on its claims
    based on the jury’s findings. The trial court signed a final judgment awarding Old Dollar
    $195,500.00 for its breach of contract claim; however, the judgment stated that Old Dollar
    “shall take nothing” on its DTPA claim. The trial court did not award attorney’s fees. Old
    Dollar filed a motion for new trial and to modify or reform the judgment, arguing that the
    trial court erred in failing to award attorney’s fees. Murphey filed a motion to modify the
    judgment or, in the alternative, for a new trial, raising various challenges to the sufficiency
    of the evidence, and arguing that Murphey was entitled to attorney’s fees. The motions
    were overruled by operation of law. This appeal followed.
    II.     LEGAL SUFFICIENCY
    In his first three issues, Murphey challenges the legal sufficiency 3 of the evidence
    supporting the jury’s breach of contract finding.
    A.      Standard of Review
    Evidence is legally sufficient if it would enable reasonable and fair-minded people
    to reach the verdict under review. City of Keller v. Wilson, 
    168 S.W.3d 802
    , 827 (Tex.
    2005). We view the evidence in the light most favorable to the challenged finding,
    indulging every reasonable inference that would support it and disregarding contrary
    evidence unless a reasonable factfinder could not. 
    Id. at 822
    . Evidence is legally
    3Murphey also purports to challenge the factual sufficiency of the evidence. However, he does not
    discuss the standard of review for factual sufficiency or apply that standard. Rather, his sufficiency
    arguments raise only “no evidence” or legal sufficiency points. See TEX. R. APP. P. 38.1(i).
    9
    insufficient to support a disputed fact finding when (1) evidence of a vital fact is absent,
    (2) rules of law or evidence bar the court from giving weight to the only evidence offered
    to prove a vital fact, (3) the evidence offered to prove a vital fact is no more than a mere
    scintilla, or (4) the evidence conclusively establishes the opposite of the vital fact. 
    Id. at 810
    .
    B.      Applicable Law
    To prove a breach of contract claim, a plaintiff must establish (1) the existence of
    a valid contract, (2) performance or tendered performance by the plaintiff, (3) the
    defendant breached that contract, and (4) damages resulting from the breach. Dixie
    Carpet Installations, Inc. v. Residences at Riverdale, LP, 
    599 S.W.3d 618
    , 625 (Tex.
    App.—Dallas 2020, no pet.). The damages element for this claim includes a causation
    requirement. Houle v. Casillas, 
    594 S.W.3d 524
    , 556 (Tex. App.—El Paso 2019, no pet.).
    C.      Breach
    In his first issue, Murphey argues that there is legally insufficient evidence that
    Murphey breached the disclosure provisions of the parties’ agreements based on the
    jury’s findings that Murphey did not commit fraud and did not knowingly or intentionally
    deceive Old Dollar. As argued by Murphey, the seller’s disclosures in the agreement are
    limited to what a seller is “aware of.” Therefore, Murphey maintains that there can be no
    breach of the contract’s disclosure requirements based on the jury’s findings that there
    was no purposeful deception. 4
    4 Pursuant to the contracts, Murphey agreed to take the property in its present condition or “as is.”
    However, an “as is” clause that is induced by specific misrepresentations about the condition of property
    will not shield the seller from liability. Williams v. Dardenne, 
    345 S.W.3d 118
    , 124 (Tex. App.—Houston [1st
    Dist.] 2011, pet. denied); see Prudential Ins. Co. of Am. v. Jefferson Assocs., Ltd., 
    896 S.W.2d 156
    , 162
    10
    Although couched as a sufficiency issue, Murphey complains about a conflict in
    the jury’s answers. Particularly, Murphey maintains that the jury’s affirmative breach of
    contract finding conflicts with its negative findings regarding fraud and whether his
    deception was knowing or intentional. Texas Rule of Civil Procedure 295, entitled
    “Correction of Verdict,” provides that if a jury’s answers “are in conflict,” the trial court
    must give the jury written instructions regarding the nature of the conflict “and retire the
    jury for further deliberations.” TEX. R. CIV. P. 295. But to preserve error in this regard, “the
    appellant must object to the conflict or inconsistency before the jury is discharged.”
    Norwest Mortgage, Inc. v. Salinas, 
    999 S.W.2d 846
    , 865 (Tex. App.—Corpus Christi–
    Edinburg 1999, pet. denied); see USAA Tex. Lloyds Co. v. Menchaca, 
    545 S.W.3d 479
    ,
    516–17 (Tex. 2018); see also TEX. R. APP. P. 33.1(a). Because Murphey failed to object
    to the jury’s inconsistent findings in the trial court before the jury was discharged, he has
    failed to preserve this argument. Other than pointing out the alleged conflict in the jury’s
    verdict, Murphey does not argue that there is no evidence supporting a finding that
    Murphey knew of, but failed to disclose, issues with the septic system. Further, because
    such a finding supports the jury’s breach of contract verdict, we need not address
    Murphey’s arguments that there is legally insufficient evidence that he breached the
    agreements by other means. See TEX. R. APP. P. 47.1 (“The court of appeals must hand
    down a written opinion that is as brief as practicable but that addresses every issue raised
    (Tex. 1995); (“A seller cannot have it both ways: he cannot assure the buyer of the condition of a thing to
    obtain the buyer’s agreement to purchase ‘as is,’ and then disavow the assurance which procured the ‘as
    is’ agreement.”); see also Pairett v. Gutierrez, 
    969 S.W.2d 512
    , 517 (Tex. App.—Austin 1998, pet. denied)
    (reversing summary judgment on basis of “as is” clause when there was evidence that seller knew of home’s
    foundation problems but affirmatively represented to buyer that they were not aware of any foundation
    problems).
    11
    and necessary to final disposition of the appeal.”). We overrule Murphey’s first issue.
    D.    Causation & Damages
    We address Murphey’s second and third issues together. In his second issue,
    Murphey argues that there is legally insufficient evidence that any breach by Murphey
    caused Old Dollar damages. Specifically, Murphey maintains that there is no evidence
    that Old Dollar suffered any pecuniary loss as a result of purchasing the property. In his
    third issue, Murphey argues that there is legally insufficient evidence to support the
    amount of damages awarded by the jury. Murphey asserts that Old Dollar failed to show
    that the repair expenses were reasonable and necessary and that such expenses cannot
    be awarded as damages because they exceed the diminution in property value.
    1.     Applicable Law
    As noted previously, the damages element for a breach of contract action includes
    a causation requirement. Houle, 594 S.W.3d at 556. Specifically, the evidence must show
    that the damages are the “natural, probable, and foreseeable consequence” of the
    defendant’s conduct. Id. “A plaintiff may not recover breach-of-contract damages if those
    damages are remote, contingent, speculative, or conjectural.” AZZ Inc. v. Morgan, 
    462 S.W.3d 284
    , 289 (Tex. App.—Fort Worth 2015, no pet.). The absence of a causal
    connection between the alleged breach and the damages sought will preclude recovery.
    
    Id.
    The normal measure of damages in a breach of contract case is the expectancy
    or benefit of the bargain measure. Mays v. Pierce, 
    203 S.W.3d 564
    , 577 (Tex. App.—
    Houston [14th Dist.] 2006, pet. denied). The purpose of this measure of damages is to
    12
    restore the injured party to the economic position it would have occupied had the contract
    been performed. Clear Lake City Water Auth. v. Friendswood Dev. Co., 
    344 S.W.3d 514
    ,
    523 (Tex. App.—Houston [14th Dist.] 2011, pet. denied); Mays, 
    203 S.W.3d at 577
    .
    “Under the benefit of the bargain measure, lost profits on the bargain may be
    recovered if they are proved through competent evidence with reasonable certainty.”
    Sharifi v. Steen Auto., LLC, 
    370 S.W.3d 126
    , 148–49 (Tex. App.—Dallas 2012, no pet.).
    Opinions or estimates of lost profits must be based on objectives facts and data. 
    Id.
     “[T]o
    recover damages for the costs of repairs to property, a plaintiff must show that the cost
    of repairs was reasonable and necessary.” Lakeside Vill. Homeowners Ass’n, Inc. v.
    Belanger, 
    545 S.W.3d 15
    , 42 (Tex. App.—El Paso 2017, pet. denied).
    2.     Analysis
    Old Dollar presented evidence that it expected a functioning septic system based
    on the seller’s disclosures in the contract. Old Dollar’s expenditures to ensure the septic
    system was working properly are a natural, probable, and foreseeable consequence of
    Murphey’s failure to disclose the system’s defects. See Houle, 594 S.W.3d at 556.
    Furthermore, the damages found by the jury were necessary to restore Old Dollar to the
    economic position it would have occupied had it purchased the property with a functioning
    septic system. See Mays, 
    203 S.W.3d at 577
    . For instance, the jury’s award of $24,500
    in past damages is supported by evidence that Old Dollar was required to pump the septic
    system twice monthly and build a berm to prevent rain runoff from flowing into the drain
    field. These costs were supported by checks, invoices, as well as the testimony of Old
    Dollar’s experts that these were reasonable and necessary expenditures to prevent the
    13
    septic system from backing up. See Belanger, 545 S.W.3d at 42.
    The jury’s award of $171,000 was supported by evidence that Old Dollar must
    expand the drain field at the cost of $75,000 to permanently address the septic system
    deficiencies, which Old Dollar’s experts deemed to be a reasonable and necessary
    solution. See id. This expansion will result in the removal of two mobile home sites and
    lost revenue of $111,600 over the ten years Smith intends Old Dollar to hold the property.
    This calculation is based on objective data regarding the expected monthly rental
    payments from the two sites. See Sharifi, 
    370 S.W.3d at 148
    –49.
    Nevertheless, Murphey argues that Old Dollar should not be able to recover
    damages related to the septic system because there was no evidence of a loss in the
    market value to the property. Murphey relies on the “economic feasibility exception” which
    provides that the cost to repair a temporary injury to real property cannot be recovered as
    damages when the cost exceeds the loss in the land’s value due to the injury. ExxonMobil
    Corp. v. Lazy R Ranch, LP, 
    511 S.W.3d 538
    , 540 (Tex. 2017). However, the damages
    awarded by the jury were not based on a temporary injury to real property but were
    contract damages in the form of lost profits and other expectancy damages. Therefore,
    the economic feasibility exception does not apply.
    For the foregoing reasons, we conclude that the evidence would enable
    reasonable and fair-minded people to find damages in the amount awarded by the jury
    and that those damages were the result of Murphey’s breach of the agreements. See City
    of Keller, 168 S.W.3d at 827. We overrule Murphey’s second and third issues.
    14
    III.   CHARGE ERROR
    In his fourth issue, Murphey argues that the jury charge erroneously failed to
    distinguish between the the sales contract and the bill of sale.
    A.     Standard of Review & Applicable Law
    “A trial court has considerable discretion to determine proper jury instructions, and
    we review a trial court’s decision to submit or refuse a particular instruction for an abuse
    of discretion.” Gunn v. McCoy, 
    554 S.W.3d 645
    , 675 (Tex. 2018). A trial court must submit
    jury questions, instructions, and definitions that “are raised by the written pleadings and
    the evidence.” TEX. R. CIV. P. 278; United Scaffolding, Inc. v. Levine, 
    537 S.W.3d 463
    ,
    469 (Tex. 2017). When we review alleged error in a jury submission, we consider “the
    pleadings of the parties and the nature of the case, the evidence presented at trial, and
    the charge in its entirety.” United Scaffolding, 537 S.W.3d at 469 (quoting Columbia Rio
    Grande Healthcare, L.P. v. Hawley, 
    284 S.W.3d 851
    , 862 (Tex. 2009)).
    B.     Analysis
    Murphey argues that the terms of the two contracts are materially different;
    therefore, the trial court erred in submitting a single breach question. We disagree.
    As noted above, the purchase of the property was governed by two contracts—the
    sales contract and the bill of sale. However, the sales contract and the bill of sale each
    incorporate the other. For instance, the sales contract provides in an addendum that
    Murphey will convey the water and septic systems for $300,000 and that the sale would
    “close in conjunction with said property.” The contract’s disclosures specifically reference
    the sewage and septic systems, and the bill of sale incorporates those disclosures. In
    15
    particular, the bill of sale provides that Old Dollar is not relying on any information “other
    than [Old Dollar’s] inspection and the representations and warranties expressly contained
    in the purchase contract[.]” “When a document is incorporated into another by reference,
    both instruments must be read and construed together.” Bob Montgomery Chevrolet, Inc.
    v. Dent Zone Cos., 
    409 S.W.3d 181
    , 189 (Tex. App.—Dallas 2013, no pet.). Because the
    bill of sale incorporates the land contract’s disclosure provisions, the contracts must be
    read and construed together. See 
    id.
     Therefore, we conclude that the trial court did not
    abuse its discretion in overruling Murphey’s objection to the jury charge. See McCoy, 554
    S.W.3d at 675. We overrule Murphey’s fourth issue.
    IV.    DTPA
    In its first cross-issue, Old Dollar argues that the trial court erred in failing to enter
    judgment on the jury’s finding that Murphey violated the DTPA. Murphey responds that
    Old Dollar was not entitled to recover on its DTPA claim as a matter of law because the
    total consideration of the parties’ transaction exceeded $500,000, an argument Murphey
    raised in his motion for judgment notwithstanding the verdict. In declining to enter
    judgment on the jury’s DTPA finding, the trial court implicitly granted Murphey’s motion
    for judgment notwithstanding the verdict.
    “We review a trial court’s decision to grant or deny a motion for a directed verdict
    and a motion for JNOV under the legal sufficiency standard of review.” Mikob Props., Inc.
    v. Joachim, 
    468 S.W.3d 587
    , 594 (Tex. App.—Dallas 2015, pet. denied). The DTPA
    generally allows a consumer to sue for damages caused by certain “false, misleading, or
    deceptive act[s] or practice[s].” TEX. BUS. & COM. CODE ANN. § 17.50(a)(1). However, the
    16
    statute does not apply to “a cause of action arising from a transaction, a project, or set of
    transactions relating to the same project, involving the total consideration by the
    consumer of more than $500,000.” Id. § 17.49(g). The purpose of this exemption is to
    maintain the DTPA as a viable source of relief for consumers in small transactions and to
    remove litigation between businesses over large transactions from the scope of the
    DTPA. Citizens Nat’l Bank v. Allen Rae Invs., Inc., 
    142 S.W.3d 459
    , 473–74 (Tex. App.—
    Fort Worth 2004, no pet.); see also AES Valves, LLC v. Kobi Int’l, Inc., No. 01-18-00081-
    CV, 
    2020 WL 1880781
    , at *5 (Tex. App.—Houston [1st Dist.] Apr. 16, 2020, pet. filed)
    (mem. op.).
    Old Dollar’s $1 million purchase exceeds the $500,000 limit imposed by the DTPA.
    See TEX. BUS. & COM. CODE ANN. § 17.49(g). As such, the statutory claim is unavailable
    to Old Dollar as a matter of law. Therefore, the trial court did not err in granting Murphey’s
    motion for judgment notwithstanding the verdict. See Joachim, 468 S.W.3d at 594; East
    Hill Marine, Inc. v. Rinker Boat Co., 
    229 S.W.3d 813
    , 821 (Tex. App.—Fort Worth 2007,
    pet. denied) (holding that trial court did not err in granting summary judgment when
    transaction exceeded $500,000 limit of DTPA). We overrule Old Dollar’s first cross-issue.
    V.     ATTORNEY’S FEES
    A.     Murphey
    In his fifth issue, Murphey argues that if he prevails in this appeal and we render
    judgment in Murphey’s favor, then he is entitled to attorney’s fees. However, we have not
    sustained any of Murphey’s issues. Therefore, we must necessarily overrule Murphey’s
    fifth issue.
    17
    B.     Old Dollar
    In its second cross-issue, Old Dollar argues that the trial court erred in failing to
    award attorney’s fees because it presented sufficient evidence that its requested fees
    were reasonable and necessary.
    1.     Standard of Review & Applicable Law
    To secure an award of attorney’s fees, the prevailing party must prove that:
    “(1) recovery of attorney’s fees is legally authorized, and (2) the requested attorney’s fees
    are reasonable and necessary for the legal representation, so that such an award will
    compensate the prevailing party generally for its losses resulting from the litigation
    process.” Rohrmoos Venture v. UTSW DVA Healthcare, LLP, 
    578 S.W.3d 469
    , 487 (Tex.
    2019). Here, the sales contract provided that if a party prevailed “in any legal proceeding
    brought under or with relation to this contract or this transaction, such party is entitled to
    recover from the non-prevailing parties . . . reasonable attorney’s fees.”
    The Texas Supreme Court has instructed that “the lodestar analysis [should] apply
    to any situation in which an objective calculation of reasonable hours worked times a
    reasonable rate can be employed.” 
    Id. at 498
    . Under this analysis, “the fact finder’s
    starting point for calculating an attorney’s fee award is determining the reasonable hours
    worked multiplied by a reasonable hourly rate, and the fee claimant bears the burden of
    providing sufficient evidence on both counts.” 
    Id.
     The fee applicant at a minimum must
    present evidence of: “(1) [the] particular services performed, (2) who performed those
    services, (3) approximately when the services were performed, (4) the reasonable
    amount of time required to perform the services, and (5) the reasonable hourly rate for
    18
    each person performing such services.” 
    Id.
     “[T]here is a presumption that the base
    lodestar calculation, when supported by sufficient evidence, reflects the reasonable and
    necessary attorney’s fees that can be shifted to the non-prevailing party.” 
    Id. at 499
    .
    “[O]ther considerations may justify an enhancement or reduction to the base lodestar;
    accordingly, the fact finder must then determine whether evidence of those considerations
    overcomes the presumption and necessitates an adjustment to reach a reasonable fee.”
    
    Id. at 501
    . “[B]illing records are strongly encouraged to prove the reasonableness and
    necessity of requested fees when those elements are contested.” 
    Id. at 502
     (emphasis in
    original). “General, conclusory testimony devoid of any real substance will not support a
    fee award.” 
    Id. at 501
    .
    2.     Analysis
    Old Dollar’s counsel, Gary A. Calabrese, testified that he has been practicing
    primarily in general litigation since 1983. He stated that he was retained by Old Dollar at
    the hourly rate of $275, which he maintained was a reasonable rate based on his
    experience. Calabrese testified that he was retained before litigation commenced and
    engaged in presuit mediation which was unsuccessful. Calabrese estimated that he had
    spent “just a little over 250 hours of time” on the case since its inception, which Calabrese
    maintained were necessary. Calabrese testified that in preparing for trial, he had many
    interviews with his client, reviewed hundreds of pages of exhibits, reviewed and
    propounded discovery, drafted pleadings, took depositions, and interviewed witnesses.
    Old Dollar did not submit any billing or time-keeping records detailing these tasks. Old
    Dollar requested that the trial court award $69,000 in attorney’s fees through trial as well
    19
    as conditional appellate attorney’s fees. The trial court concluded as a matter of law that
    Old Dollar’s evidence was legally insufficient to support an award of attorney’s fees.
    In Rohrmoos and its predecessor cases, testimony regarding attorney’s fees was
    deemed too general because the attorneys provided the amount of time spent on the
    case in the aggregate but did not indicate how the aggregated time was “devoted to any
    particular task or category of tasks.” 
    Id. at 495
     (quoting El Apple I, Ltd. v. Olivas, 
    370 S.W.3d 757
    , 763 (Tex. 2012)); see, e.g., City of Laredo v. Montano, 
    414 S.W.3d 731
    , 736
    (Tex. 2013) (per curiam) (reiterating basic proof required for lodestar calculation). In El
    Apple, for example, the attorneys did not present time records or other documentary
    evidence, instead basing their time estimates “on generalities such as the amount of
    discovery in the case, the number of pleadings filed, the number of witnesses questioned,
    and the length of the trial.” 
    370 S.W.3d at 763
    . The supreme court determined that
    because the trial court lacked evidence of how many hours each task required, it could
    not determine whether that time was reasonable, concluding that “[w]ithout at least some
    indication of the time spent on various parts of the case, a court has little basis upon which
    to conduct a meaningful review of the fee award.” 
    Id.
     Old Dollar’s testimony is similarly
    defective in that, although Calabrese gave an overall estimate of hours worked, there is
    no evidence regarding how many hours various tasks required. See 
    id.
     Therefore, the
    trial court did not err in concluding that there was insufficient evidence to support an award
    of attorney’s fees.
    However, “an award of no fees [is] improper in the absence of evidence
    affirmatively showing that no attorney’s services were needed or that any services
    20
    provided were of no value.” Midland W. Bldg. L.L.C. v. First Serv. Air Conditioning
    Contractors, Inc., 
    300 S.W.3d 738
    , 739 (Tex. 2009) (per curiam). Although the evidence
    was legally insufficient to establish an award of fees under the lodestar method, the
    evidence did establish that the attorney’s services were needed and of some value. See
    
    id.
     Further, where evidence fails to satisfy the lodestar standard regarding the details of
    the work performed, the proper remedy is to remand the issue for a redetermination of
    fees. See Rohrmoos, 578 S.W.3d at 505 (reversing and remanding for redetermination
    of attorney’s fees where evidence was legally insufficient to establish amount of fees);
    Long v. Griffin, 
    442 S.W.3d 253
    , 256 (Tex. 2014) (per curiam) (reversing and remanding
    where “no legally sufficient information support[ed] the amount of attorney’s fees the trial
    court awarded”); Montano, 414 S.W.3d at 736–37 (Tex. 2013) (per curiam) (reversing and
    remanding where party’s attorney’s fee testimony lacked the level of detail required by El
    Apple); El Apple, 
    370 S.W.3d at 764
     (“Because the affidavits and other evidence in this
    case did not provide [legally] sufficient information for a lodestar calculation, we must
    reverse and remand.”). Therefore, we must reverse that part of the trial court’s judgment
    awarding no attorney’s fees and remand for a redetermination of fees consistent with this
    Court’s opinion. We sustain in part Old Dollar’s second cross-issue.
    21
    VI.    CONCLUSION
    We reverse that part of the trial court’s judgment awarding no attorney’s fees to
    Old Dollar and remand the cause to the trial court for a redetermination of fees. We affirm
    the remainder of the trial court’s judgment.
    LETICIA HINOJOSA
    Justice
    Delivered and filed on the
    21st day of October, 2021.
    22