Addison Urban Development Partners, LLC v. Alan Ritchey Materials Company, LC , 437 S.W.3d 597 ( 2014 )


Menu:
  • Affirmed and Opinion Filed July 1, 2014
    S   In The
    Court of Appeals
    Fifth District of Texas at Dallas
    No. 05-13-00122-CV
    ADDISON URBAN DEVELOPMENT PARTNERS, LLC, Appellant
    V.
    ALAN RITCHEY MATERIALS COMPANY, LC, Appellee
    On Appeal from the County Court at Law No. 3
    Dallas County, Texas
    Trial Court Cause No. CC-10-03902-C
    OPINION
    Before Justices FitzGerald, Fillmore, and Evans
    Opinion by Justice FitzGerald
    This appeal follows a bench trial involving a dispute over a statutory construction
    materials lien. In eight issues, Addison Urban Development Partners, LLC (“Addison”) asserts
    the trial court erred in awarding judgment to Alan Ritchey Materials Company, LC (“Ritchey”).
    We affirm the trial court’s judgment.
    BACKGROUND
    Addison owns the real property known as the Meridian Square Project (the “Property”), a
    subdivision development in Addison, Texas. Addison contracted with ForceCon Services, LLC
    (“ForceCon”) for paving, excavation, street lights, and other work in constructing improvements
    on the Property (the “Project”). Pursuant to its contract with Addison, ForceCon provided
    concrete for use on the Project.
    Concrete consists of several materials, including sand and gravel. ForceCon ordered
    ingredients for concrete from several materialmen, and prepared the concrete for use in the
    Project through a process called “batching.” ForceCon was forced to batch concrete for the
    Project at an off-site batch plant because Addison limited ForceCon’s workspace in its paving
    subcontract. Addison knew its concrete was not being batched on the Project site.
    Ritchey is one of the materialmen that contracted with ForceCon to supply materials to
    make concrete for the Project. The materials to be provided included concrete sand and 1” and 1
    1/2” rock gravel.1 Pursuant to the contract, ForceCon was to pay a unit price per ton of material
    delivered for the Project. This unit price included a fuel surcharge that was tied to a price index
    related to diesel fuel. Variations in the fuel surcharge would cause the final per-ton price of the
    delivered material to increase or decrease.
    ForceCon ordered materials from Ritchey from July 22, 2009 through September 11,
    2009 for a total price of $114,470.66. Despite demands for payment, Ritchey was not paid for
    any of these materials. Therefore, Ritchey provided statutory notice to ForceCon and Addison
    concerning ForceCon’s failure to pay. Ritchey then filed a lien in the total amount of
    $114,470.66, and notified Addison of the filing.
    Addison initiated this lawsuit against Ritchey, ForceCon, and another subcontractor.
    With regard to Ritchey, Addison claimed that the total value of the materials used on the Project
    had a total contract value of $65,155.67, and Ritchey’s $114,470.66 lien on the Project exceeded
    that amount. Ritchey answered and counterclaimed against Addison for foreclosure of the lien
    and cross-claimed against ForceCon for breach of contract and a sworn account. The parties
    were subsequently realigned, with Ritchey designated as plaintiff and Addison as defendant. The
    1
    As do the parties, in this opinion we use the terms “rock,” “rock gravel,” and “gravel” interchangeably to refer to the aggregate Ricthey
    provided for the Project.
    claims between the other subcontractor and Addison were settled at mediation, and the court
    granted a default judgment in favor of Ritchey against ForceCon. Thus, only Ritchey’s claims
    against Addison remained.
    The parties filed a joint trial stipulation of facts and a stipulation of evidence. The parties
    also filed a document entitled “Agreed Motion for Procedure for Resolution Based Upon Joint
    Trial Stipulations.” The motion requested that the court admit the stipulated evidence, and set
    deadlines for briefing on the stipulated evidence and the submission of attorney’s fees affidavits.
    The trial court granted the motion and admitted the stipulated evidence.
    The court signed a final judgment on October 31, 2012. The judgment incorporates the
    interlocutory default judgment awarding Ritchey judgment against ForceCon, and awards
    Ritchey attorney’s fees against ForceCon. The judgment further awards Ritchey $114,470.66,
    plus pre- and post-judgment interest jointly and severally against Addison and ForceCon, and
    attorney’s fees against Addsion. The judgment concludes that Ritchey’s lien against the Property
    is valid and enforceable, and decrees that judgment foreclosing the lien is granted. Addison
    moved for a new trial, and the trial court made findings of fact and conclusions of law.
    STANDARD OF REVIEW
    Before we begin our analysis, we must first determine the standard of review. Addison
    asserts this case was submitted to the trial court as an agreed case under rule 263. See TEX. R.
    CIV. P. 263. Ritchey disagrees, arguing that the parties did not agree to all the facts. Ritchey
    relies on two items that purportedly support its position; a single sentence from the stipulation
    that states “Ritchey contends that . . . materials were ordered and delivered for use on the
    project” and the fact that Addison raises factual sufficiency points on appeal. We are not
    persuaded by Ritchey’s argument. The case was submitted to the court on the parties’ joint trial
    stipulation and the stipulated evidence. The joint trial stipulation presented to the court states, in
    pertinent part, “[w]ith these stipulations, Alan Ritchey Materials and Addison believe that all that
    remain are issues of law.” In addition, the parties’ agreed motion for resolution based on joint
    trial stipulations states, “[with the exception of attorney’s fees, to be submitted at a later date],
    the parties believe that all evidence . . . needed for adjudication of this matter is now before the
    Court.”
    “An agreed statement of facts under rule 263 is similar to a special verdict; it is the
    parties’ request for judgment under the applicable law.” State Farm Lloyds v. Kessler, 
    932 S.W.2d 732
    , 735 (Tex. App.—Fort Worth 1996, writ denied) (citing Chiles v. Chubb Lloyds Ins.
    Co., 
    858 S.W.2d 633
    , 634 (Tex. App.—Houston [1st Dist.] 1993, writ denied)). In a rule 263
    agreed case, the only issue on appeal is whether the district court properly applied the law to the
    agreed facts. See id.; 
    Chiles, 858 S.W.2d at 635
    . In such a case, this Court is limited to
    consideration of those agreed facts. See Taylor v. First Cmty. Credit Union, 
    316 S.W.3d 863
    , 866
    (Tex. App.—Houston 2010, no pet.). Such a review is less deferential to the trial court, because a
    “trial court has no discretion in deciding what the law is or in properly applying it.” 
    Kessler, 932 S.W.2d at 735
    (citing Walker v. Packer, 
    827 S.W.2d 833
    , 840 (Tex. 1992)). If the trial court files
    findings of fact in an agreed case, they are disregarded by the appellate court. Davis v. State, 
    904 S.W.2d 946
    , 950 (Tex. App.—Austin 1995, no writ). Rule 263 provides in its entirety:
    Parties may submit matters in controversy to the court upon an agreed
    statement of facts filed with the clerk, upon which judgment shall be
    rendered as in other cases; and such agreed statement signed and certified
    by the court to be correct and the judgment rendered thereon shall
    constitute the record of the cause.
    TEX. R. CIV. P. 263. Although the record does not contain an “agreed statement signed and
    certified by the [district] court to be correct,” courts have concluded that strict compliance with
    rule 263 is not a prerequisite for an agreed case. See Lambda Constr. Co. v. Chamberlin
    Waterproofing & Roofing Sys., Inc., 
    784 S.W.2d 122
    , 125 (Tex. App.—Austin 1990, writ
    denied) (citing Reed v. Valley Fed. Sav. & Loan Co., 
    655 S.W.2d 259
    , 264 (Tex. App.—Corpus
    Christi 1983, writ ref’d n.r.e.)); Henry S. Miller Co. v. Wood, 
    584 S.W.2d 302
    , 303 (Tex. Civ.
    App.—Texarkana 1979), aff’d, 
    597 S.W.2d 332
    (Tex. 1980); see also 
    Kessler, 932 S.W.2d at 735
    (stating appellate court may treat case as involving an agreed statement of facts if the record
    indicates the trial court heard the case on stipulated facts).
    The record before us reflects that this case was submitted as an agreed case. We structure
    our review accordingly.
    ANALYSIS
    Addison raises eight issues challenging the trial court’s judgment. Specifically, Addison
    asserts: (1) the evidence is legally and factually insufficient to establish that material was
    furnished; (2) the lien was limited to sand and does not include a fuel surcharge, and therefore
    Ritchey failed to establish that its lien affidavit created a valid lien; (3) the evidence is legally
    and factually insufficient to establish that Addison did not comply with its obligation for
    retainage; (4 & 5) Ritchey’s lien claim was not enforceable as to the freight charges or any item
    other than concrete sand; (6) the judgment cannot be upheld on the theory that ForceCon was
    Addison’s agent or had apparent authority or that Addison failed to pay Ritchey’s demand after
    thirty days; (7) because the judgment should be reversed, it is not equitable and just to award
    attorney’s fees; and (8) the trial court erred in denying Addison’s motion to remove the invalid
    lien. Because issues 1, 2, 4, and 5 all pertain to the validity of the lien, we consider these issues
    together.
    The Validity of the Lien
    Ritchy claimed it was entitled to a statutory mechanic’s or materialman’s lien under
    section 53.021 of the property code because it furnished labor or materials for construction of
    improvements pursuant to a contract with Addison’s subcontractor, ForceCon. Section 53.021
    provides:
    Persons Entitled to a Lien.
    (a) A person has a lien if:
    (1) the person labors, specially fabricates material, or furnishes labor or
    materials for construction and repair in this state of:
    (A) a house, building, or improvement . . . and
    (2) the person labors, specially fabricates the material, or furnishes the
    labor or materials under or by virtue of a contract with the owner or the
    owner’s agent, trustee, receiver, contractor, or subcontractor.
    TEX. PROP. CODE ANN. § 53.021 (West Supp. 2013) (emphasis added). A claimant is required to
    provide a pre-lien notice of unpaid balances to the original owner or reputed owner and the
    original contractor. See TEX. PROP. CODE ANN. § 53.056 (West 2007). When a supplier notifies
    an owner that it has not been paid, the owner may protect itself by withholding payments due to
    the contractor in an amount sufficient to pay the supplier’s claim. TEX. PROP. CODE ANN. §
    53.081 (West 2007); Page v. Marton Roofing, Inc., 
    102 S.W.3d 733
    , 734 (Tex. 2003). If the
    owner elects to withhold funds due to the contractor (called “trapped funds”), it must hold the
    funds until the time for filing a lien is passed, or, if a lien is filed, until the lien has been satisfied
    or released. See TEX. PROP. CODE ANN. § 53.082 (West 2007); Raymond v. Rahme, 
    78 S.W.3d 552
    , 559–60 (Tex. App.—Austin 2002, no pet.) (discussing trapped and retained funds). If the
    owner fails to withhold funds from the contractor, “the owner is liable and the owner’s property
    is subject to a claim for any money paid to the original contractor after the owner was authorized
    to withhold funds.” TEX. PROP. CODE ANN § 53.084(b) (West 2007); 
    Page, 102 S.W.3d at 734
    –
    35.
    After giving notice of the claim, to obtain a valid lien, a party must file an affidavit
    within the statutorily prescribed period. See TEX. PROP. CODE ANN. §§ 53.052, 53.056. The
    required contents of a lien affidavit are prescribed in section 53.054(a) of the property code. See
    TEX. PROP. CODE ANN. § 53.054(a) (West 2007). Under section 53.054, an affidavit must contain
    substantially:
    (1) a sworn statement of the amount of the claim;
    (2) the name and last known address of the owner or reputed owner;
    (3) a general statement of the kind of work done and materials furnished
    by the claimant and, for a claimant other than an original contractor, a
    statement of each month in which the work was done and materials
    furnished for which payment is requested;
    (4) the name and last known address of the person by whom the claimant
    was employed or to whom the claimant furnished the materials or labor;
    (5) the name and last known address of the original contractor;
    (6) a description, legally sufficient for identification, of the property
    sought to be charged with the lien;
    (7) the claimant’s name, mailing address, and, if different, physical
    address; and
    (8) for a claimant other than an original contractor, a statement identifying
    the date each notice of the claim was sent to the owner and the method by
    which the notice was sent.
    
    Id. A party
    must comply with chapter 53 to perfect a lien under the statute. See Morrell Masonry
    Supply, Inc. v. Lupe’s Shenandoah Reserve, LLC, 
    363 S.W.3d 901
    (Tex. App.—Beaumont 2012,
    no pet.); see also TEX. PROP. CODE ANN. §§ 53.01–.058. Substantial compliance, however, is
    sufficient. See First Nat’l Bank v. Sledge, 
    653 S.W.2d 283
    , 285 (Tex. 1983); Hammons v. Tex.
    Pride Landscape, No. 05-99-00980-CV, 
    2000 WL 567108
    , at *6 (Tex. App.—Dallas May 10,
    2000, pet. denied) (not designated for publication).
    In the stipulated facts, Addison admits that it received and does not dispute the timeliness
    or contents of the notices (of the unpaid balances) or the timeliness of the filing of the liens and
    notices of the liens. Addison further admits that Ritchey properly trapped funds for the full
    amount of its $114,470.66 claim. The stipulated facts also provide that if Ritchey’s notices and
    liens were sufficient to perfect a claim, in whole or in part, Addison is liable to Ritchey and
    Addison’s property is subject to Ritchey’s claim for the amount claimed in the lien or such lesser
    amount that may be perfected plus interest and attorney’s fees. In addition, the stipulated facts
    state:
    By way of example, and for avoidance of doubt, if [Ritchey] is entitled to
    a lien for all of the materials set forth in the Invoices marked Exhibit No.
    17, [Ritchey] is entitled to recover that full amount from Addison and
    Addison’s property is subject to the full amount of the claim. On the other
    hand, to the extent any of the materials set forth in the Invoices . . . are not
    properly the subject of a lien . . . Addison is not liable and its property is
    not subject to the lien to such extent.
    Therefore, as Addison observes, while “there is no dispute as to notice . . . the parties left open
    the question of how much of the account debt was enforceable as a lien.” In other words, the
    crux of the legal determination made by the trial court and the basis of our review concerns the
    validity and perfection of the lien.
    Addison advances two challenges to the validity and perfection of the lien. First, Addison
    contends the lien is not valid because materials were not “furnished” for the Project. Next,
    Addison argues that the lien is not valid because it was perfected only as to concrete sand and
    should not include the rock gravel or associated freight and fuel charges Ritchey included in its
    claim.
    Were Materials Furnished for the Project?
    Addison’s argument that materials were not furnished for the Project is premised on the
    fact that more materials were delivered than were required to complete the job. Addison notes
    that the quantity of materials supplied exceeded the amounts required by the job by a factor of
    nearly four times. This excess is not in dispute. According to Addison, the excess materials
    cannot reasonably be described as surplus or the result of imprecise estimates. Instead, Addison
    posits that ForceCon used the account to benefit from a fixed price on the materials, and suggests
    that the excess materials “must have been used on some other project . . . or remained unused at
    the location where they were delivered.”
    The parties differ on whether this delivery of excess materials defeats the conclusion that
    the materials were “furnished” for the Project. The statute does not define the term “furnished”
    or the phrase “furnished for construction.” See TEX. PROP. CODE ANN. § 53.001 (West 2007).
    There is well-established authority, however, that the statute requires a materialman to prove he
    “furnished goods . . . for a specific job.” See Lexicon, Inc. v. Gray, 
    740 S.W.2d 83
    , 86 (Tex.
    App.—Dallas 1987, no writ); Houston Fire & Cas. Ins. Co. v. Hales, 
    279 S.W.2d 389
    , 392 (Tex.
    Civ. App.—Eastland 1955, writ ref’d n.r.e.). The question is whether the stipulated facts show
    this standard was met.
    In Lexicon, the trial court held that a roofing company was entitled to a lien on a recently
    constructed hotel based upon unpaid bills from the roofing subcontractor for the builder of the
    hotel. 
    Lexicon, 740 S.W.2d at 86
    . The trial court did not make any findings of fact or conclusions
    of law. 
    Id. This Court
    noted that the burden of proof is on the materialman to prove delivery of
    the goods to the construction site or that he furnished the goods to the builder for a specific job.
    
    Id. In reviewing
    the trial court’s implied findings in support of the judgment, we centered our
    analysis on whether the evidence supported a finding that the roofing company furnished
    materials for the construction of the hotel. 
    Id. Because invoices
    showing the deliveries of
    materials to the job site were admitted into evidence, we concluded the trial court did not err in
    holding the owner of the property liable for the materials sold by the roofing company and
    delivered to the job site. 
    Id. at 85–86.
    In so concluding, we noted that the Texas Supreme Court
    has stated:
    The language of the statute does not require . . . that the material should
    actually enter into the construction of the improvement. To furnish
    materials for the construction of a house and to furnish materials which
    enter into its construction are very different things. To give our statute the
    latter construction is to strain its words beyond their usual meaning, and
    this should not be done for the purpose of depriving mechanics and others
    of the protection which the statute was evidently designed to give them.
    We rather incline to a liberal construction in their favor.
    
    Id. at 85
    (citing Trammel v. Mount, 
    4 S.W. 377
    , 378 (Tex. 1887)).
    Similarly, in Hales, the Eastland court concluded that a materialman’s lien arises even if
    the material does not actually enter into the construction, unless the builder actually “turns back”
    the material to the materialman. 
    Hales, 279 S.W.2d at 392
    –93; see also Brick & Tile, Inc. v.
    Parker, 
    186 S.W.2d 66
    , 67 (Tex. 1945) (stating materialman’s lien cannot be defeated by proof
    the buyer used part of the material for other purposes); Sheldon Pollack Corp. v. Pioneer
    Concrete, 
    765 S.W.2d 843
    , 846 (Tex. App.—Dallas 1989, writ denied) (concluding materialman
    not required to prove actual consumption of materials on private project to recover against
    general contractor on indemnity bond).
    Addison advances an application of the statute requiring proof that the materials were
    actually used for the Project. To this end, Addison argues that our determination should be
    guided by the decision in Morrell Masonry Supply, Inc. v. Scott Griffin & Assocs., Inc., No. 01-
    09–01147-CV, 
    2011 WL 2089677
    , at *6 (Tex. App.—Houston [1st Dist.] 2011, no pet.) (mem.
    op.).2 In Morrell, the owner, SGA, hired a contractor, Ruiz, to install stucco on two houses, one
    at 10 Oak Cove Lane, and the other at 30 Oak Cove Lane. 
    Id. at *1.
    At the time, Ruiz was doing
    work on three other projects for another owner, all on Oak Cove Lane. An issue arose with
    regard to Ruiz not paying the supplier for stucco that was used for 30 Oak Cove Lane. 
    Id. The parties
    resolved this dispute. But as a result of these problems, SGA required that the supplier
    contact it for approval before supplying material that Ruiz claimed was for SGA job sites. 
    Id. 2 In
    its reply brief, Addison offers an alternative application, urging that when the quantity of materials provided “grossly exceeds”
    the usable quantity, materials should be deemed “furnished” to the extent the materials are delivered to the contractor or the job site in “quantities
    reasonably necessary for the ordering contractor’s performance.” Addison offers no support for this interpretation of “furnished” under the
    statute, and we reject it. Such a construction engrafts an additional burden for a materialman to prove quantities necessary for performance and
    exceeds the proof required under the statute.
    Another dispute subsequently arose, and the supplier claimed Ruiz had not paid for materials
    used on the project at 10 Oak Cove Lane. The supplier filed a lien on the property and filed suit
    to foreclose the lien. 
    Id. The trial
    court concluded, inter alia, that the supplier did not prove that the materials
    furnished to the contractor were delivered to a particular builder for a particular construction job.
    
    Id. at *7.
    On appeal, the supplier relied on Lexicon to argue that the trial court erred in shifting
    the burden of proof to the supplier by requiring it to prove that the materials were delivered,
    used, and signed for by the owner at the 10 Oak Cove job site. 
    Id. at *4.
    SGA argued that
    Lexicon was distinguishable because it did not involve alternative job sites where the materials
    could have been used by the contractor. 
    Id. The Houston
    Court of Appeals agreed with SGA, stating with regard to Lexicon, that “the
    posture of this case is different.” 
    Id. at *6.
    The court observed, “[h]ere, the question is whether
    ‘some evidence’ supports the trial court’s conclusion that [the supplier] was not entitled to a lien
    because [the supplier] did not establish that (1) materials were delivered to [the specific job site]
    or (2) materials were furnished for use in the job at [the specific job site].” 
    Id. (emphasis in
    original). The court concluded that there was some evidence to support the trial court’s
    conclusion that the supplier was not entitled to a lien. 
    Id. In reaching
    its conclusion, the court noted that the supplier relied on invoices, delivery
    tickets, and the testimony of its officer manager to support its contention that it was entitled to a
    lien. But the court noted that many of the delivery tickets listed “will call” as the shipment
    method, several had no signature as being received, and many had illegible signatures or
    markings. 
    Id. The office
    manager could not identify any of the signatures as belonging to Ruiz or
    SGA, and stated that the orders were confirmed as being for the 10 Oak Cove project “a majority
    of the time.” Conversely, the owner testified that he only received confirmation calls between
    three and five times, and only two of the delivery tickets indicated that the owner was contacted.
    
    Id. This conflicting
    evidence was critical to the court’s determination. Significantly, the court
    stated:
    We do not hold that delivery tickets and invoices indicating materials
    were for a particular job site is not some evidence to support a lien.
    But such evidence is not conclusive in the face of contradicting
    evidence. Here the trial court was presented with evidence casting real
    doubt about where the material went, as well as testimony that [the
    supplier] was on notice of SGA’s contention that Ruiz was erroneously
    designating SGA’s job sites and that [the supplier] had agreed not to
    accept Ruiz’s word that materials were to be used at an SGA site without
    verifying that fact with SGA.
    
    Id. at *6.
    (emphasis added).
    The facts in Morrell are distinguishable from the case at bar, and this distinction is
    critical to our inquiry. Here, the controlling facts are not in dispute. The parties stipulated that the
    materials made the subject of Ritchey’s claim were all delivered to a batch plant operated by
    ForceCon, and Addison knew the materials were not being batched on the Project site. The
    stipulated evidence shows that each time ForceCon ordered materials from Ritchey, it specified
    that the materials were for the Project. Addison created a dispatch sheet for each order
    documenting the type and quantity of material ordered and the project for which it was being
    provided. Ritchey assigned order numbers 1211, 1216, and 1220 to the orders placed by
    ForceCon, and these order numbers identified the materials (concrete sand, 1” and 1 1/2” rock
    gravel) and the Project. At delivery, Ritchey presented delivery tickets reflecting the types of
    materials delivered, the amount, and that the materials were for use on the Project. A ForceCon
    representative acknowledged receipt of these delivery tickets. The invoices for the materials
    ordered reference the delivery tickets and also designate the Project by name. In the present case,
    there is no evidence that the materials delivered were used at another job; Addison’s theory
    concerning ForceCon’s use of the excess materials is but conjecture. Therefore, unlike Morrell,
    there is no evidence controverting that the materials were furnished for the Project. On the facts
    in this case, the evidence demonstrates that Ritchey delivered materials to ForceCon in
    connection with the Project.
    Moreover, there is nothing to suggest the legislature intended the additional burden on
    materialmen that Addison seeks to impose. As we previously noted, the legislature did not define
    the word “furnish” as it pertains to section 53.021. Where the legislature does not provide a
    definition for a term in a statute, it is a cardinal rule of statutory construction that the words
    employed in statutes are ordinarily given their plain meaning unless a contrary meaning is
    apparent from the statute’s context. See City of Houston v. Bates, 
    406 S.W.3d 539
    , 543–44 (Tex.
    2013). Further, the legislature has stated that words and phrases used in a statute should be read
    in context and construed according to the rules of grammar and common usage. TEX. GOV’T
    CODE ANN. § 311.011(a) (West 2013).
    According to Black’s Law Dictionary, the word “furnish” means “to supply, provide, or
    equip, for accomplishment of a particular purpose.” BLACK’S LAW DICTIONARY 675 (6th ed.
    1990). Webster’s defines “furnish” as to “supply or give.” WEBSTER’S NEW COLLEGIATE
    DICTIONARY 462 (1981). It seems clear through these definitions that the plain meaning of the
    word “furnish,” in the context of furnishing materials for a specific job, involves supplying the
    materials and nothing more. The definitions in no way suggest that furnishing or supplying
    materials for a project equates to or entails actual use of such materials. See 
    Trammel, 4 S.W. at 378
    (furnishing materials for construction differs from furnishing materials that enter into
    construction). We are also mindful of the fact that the lien statute “is to be liberally construed for
    the purpose of protecting laborers and materialmen,” so as to afford “the most comprehensive
    application” without “doing violence” to the statute’s terms. Wesco Distrib., Inc. v. Westport
    Grp, Inc., 
    150 S.W.3d 553
    , 557 (Tex. App.—Austin 2004, no pet.). Limiting the word “furnish”
    and the phrase “furnished for construction” to reflect the common meaning is consistent with this
    purpose and result.
    Is the Lien Invalid Because it is Not Limited to Concrete Sand?
    Next, we consider Addison’s challenge to the perfection of the lien based on its
    contention that the lien was perfected only as to concrete sand. Ritchey’s lien affidavits stated:
    Claimant’s labor and materials furnished for construction of improvements
    on the real property described below are generally described as concrete
    sand and related freight charges (including applicable fuel surcharges).
    According to Addison, the description in the affidavit does not encompass gravel, another
    aggregate supplied by Ritchey to mix the concrete.
    Section 53.054 requires that an affidavit claiming a materialman’s lien include “a general
    statement of the kind of work done and materials furnished by the claimant.” TEX. PROP. CODE
    ANN. § 53.054. However, the statute also provides that “[t]he affidavit is not required to set forth
    the individual items of work done or material furnished or specially fabricated.” 
    Id. § 53.054(c).
    Generally, the mechanic’s and materialman’s lien statutes are liberally construed for the
    purpose of protecting laborers and materialmen. See First Nat’l Bank in Dallas v. Whirlpool
    Corp., 
    517 S.W.2d 262
    , 269 (Tex. 1974). Thus, for purposes of perfection, only substantial
    compliance with the statutes is required. See Occidental Neb. Fed. Sav. Bank v. E. End Glass
    Co., 
    773 S.W.2d 687
    , 688 (Tex. App.—San Antonio 1989, no writ); Mustang Tractor & Equip.
    Co. v. Hartford Accident & Indem. Co., 
    263 S.W.3d 437
    , 440 (Tex. App.—Austin 2008, pet.
    denied).
    The purpose of serving lien affidavits on the property owner is to give notice. Arias v.
    Brookstone, L.P., 
    265 S.W.3d 459
    , 464–65 (Tex. App.—Houston [1st Dist.] 2007, pet. denied).
    The lien is to be recorded to give fair notice to third parties of that for which a lien is claimed.
    See Haden Co., Inc. v. Mixers, Inc., 
    667 S.W.2d 316
    (Tex. App.—Dallas 1984, no writ). Cases
    interpreting the mechanic’s and materialman’s lien statutes counsel against invalidating a lien on
    a purely technical basis. Courts are more willing to excuse a mistake or omission where no party
    is prejudiced by the defect. Ready Cable, Inc. v. RJP S. Comfort Homes, Inc., 
    295 S.W.3d 763
    ,
    765 (Tex. App.—Austin 2009, no pet.). Therefore, we consider Ritchey’s lien affidavit in terms
    of whether it substantially complied with the statute.
    The evidence reflects that concrete sand and gravel are known components of prepared
    concrete, and there is no dispute that both gravel and sand were required for the concrete that
    was to be batched for the Project. The parties stipulated that ForceCon ordered sand and 1” and 1
    1/2” aggregate and these materials were delivered to ForceCon’s batch plant. Despite the general
    description in the lien affidavits, Ritchey’s notices and demands to Addison and ForceCon
    specified that Ritchey had provided both sand and gravel. These notices advised, “Claimant
    furnished concrete sand, rock, and related transportation for the Project under Claimant’s
    agreement with ForceCon . . . .”
    We conclude the trial court did not err in concluding that the affidavits substantially
    complied with the statute. There was no dispute that the aggregate materials for concrete had
    been delivered, and there is nothing to suggest that Addison or any third party was surprised or
    suffered prejudice by reason of Ritchey’s general description of the aggregate in the affidavit. As
    the Corpus Christi court aptly observed, “[t]he Legislature did not intend that the materialman
    should lose his lien through the technicalities of a warning, where the owner was not misled to
    his prejudice.” Hunt Developers, Inc. v. W. Steel Co., 
    409 S.W.2d 443
    , 449 (Tex. Civ. App.—
    Corpus Christi 1966, no writ).
    Finally, Addison contends the lien improperly included freight and fuel surcharges
    because these items are not “materials” under the property code. Section 53.001 defines
    “material” as all or part of
    (A) the material, machinery, fixtures or tools incorporated into the work,
    consumed in the direct prosecution of the work, or ordered and delivered
    for incorporation or consumption . . .
    (C) power, water, fuel, and lubricants consumed or ordered and delivered
    for consumption in the direct prosecution of the work.
    TEX. PROP. CODE ANN. § 53.001(4). Ritchey asserts that the freight or delivery was factored into
    the price of the materials sold, and it was therefore entitled to the lien price of the “material
    ordered and delivered for consumption” and “fuel consumed” in connection with the Project. We
    agree.
    The record reflects that Ritchey charged by the ton for the materials delivered to the
    Project. The invoices show the components of the final price — material, freight, and fuel
    surcharge. These components comprise the total cost per ton.
    The final price of the materials is based on the weight of the material, not the delivery
    distance. The weight is multiplied by the estimated material and freight components of the
    delivered price of the material during the bid process. The fuel charge is expressed as a
    percentage, and calculated from the freight component of the delivered price. The fuel surcharge
    is acquired from an index and is based on the variable rate of diesel fuel from the time the bid is
    placed to the time the material is ordered.
    Ritchey demonstrated that all three components (materials, freight, and fuel surcharge)
    are added together to arrive at the final invoiced price of the material. The price charged is
    calculated by multiplying the tons of material delivered by the component rates for that material
    and freight. An additional percentage is then applied to the freight portion to obtain the fuel
    surcharge. The material and freight components are broken out on the invoices so that customers
    can track the proper application of the fuel surcharge. Ritchey does not categorize the freight
    value as a shipping charge, nor is it based on mileage. This evidence establishes the components
    of that which was consumed in the direct prosecution of the work, or ordered and delivered for
    incorporation or consumption. Thus, the evidence shows that the component items of the final
    price were properly included in the lien price.
    Addison insists that freight is not an item of material or labor under the property code.
    Although the property code does not include the word freight, the statute does provide a lien for
    labor and materials consumed in providing materials. See TEX. PROP. CODE ANN. § 53.021
    (providing lien for labor furnished); TEX. PROP. CODE ANN. § 53.023 (securing payment for labor
    done or material furnished). The statue defines “labor” as “labor used in the direct prosecution of
    the work.” TEX. PROP. CODE ANN. § 53.001(3). Even if the fuel surcharge is deemed something
    other than a component of the price of the material supplied, diesel is consumed in providing the
    materials. And the delivery of these materials can be properly categorized as labor used in the
    direct prosecution of the work.
    This Court rejected a similar argument concerning the inclusion of delivery charges in a
    lien in Hammons v. Texas Pride Landscape, No. 05-99-00980-CV, 
    2000 WL 567108
    , at *6-7
    (Tex. App.—Dallas May 10, 2000, pet. denied) (not designated for publication). In Hammons, a
    subcontractor who had been hired to do landscaping on a project filed liens for the work it had
    done, including delivery charges, labor in planting the plants and the clean-up of the realty, and
    rental of a dumpster. The owner argued that the costs of labor and the dumpster rental were not
    properly costs to which a materialman’s lien might attach. 
    Id. at *8.
    Our Court disagreed, and
    concluded that these charges, including the cost of labor for delivery, were properly included in
    the lien’s total amount. Id.; see also Lyda Swinerton Builders, Inc. v. Cathay Bank, 
    409 S.W.3d 221
    , 241 (Tex. App.—Houston [14th Dist.] 2013, pet. filed) (noting that definition of materials
    does not always include actual use or consumption in direct prosecution of the work; liens also
    available when items are “delivered for” use or consumption).
    Based on the foregoing, we conclude the trial court did not err in concluding that the lien
    was valid and properly perfected. Materials were furnished for the Project, and the rock gravel
    and associated freight charges were properly included in Ritchey’s lien claim. Addison’s first,
    second, fourth, and fifth issues are overruled.
    Retainage
    In its third issue, Addison asserts the evidence is insufficient to support the conclusion
    that Addison failed to comply with its obligation for retainage.3 Although Ritchey asserted a
    cause of action based upon Addison’s breach of a duty to withhold retainage, the trial court did
    not reach this issue. The parties stipulated that Ritchey properly trapped funds and Addison was
    liable to the extent the lien was valid and perfected as to all charges claimed in the lien. We have
    concluded the trial court did not err in concluding Ritchey’s lien was valid, and that the judgment
    should be affirmed on this theory. Addison’s third issue is overruled.
    Agency and Apparent Authority
    In its sixth issue, Addison contends the judgment cannot be upheld under an agency or
    apparent authority theory or because it failed to pay Ritchey’s demand after thirty days. We have
    already concluded that the judgment should be affirmed on the theories that were actually tried.
    Therefore, we need not consider any alternative grounds challenging the judgment. Addison’s
    sixth issue is overruled.
    Attorney’s Fees
    In its seventh issue, Addison challenges the award of attorney’s fees. The only basis for
    this challenge is Addison’s assertion that the fees are not equitable and just because they are
    based on an improper judgment. We have concluded that the trial court’s judgment in favor of
    3
    “Retained” funds are funds withheld from the original contractor either under a contractual agreement or section 53.101, which requires a
    property owner to retain ten per cent of the contract price for thirty days after the project is completed. 
    Raymond, 78 S.W.3d at 560
    ; TEX. PROP.
    CODE ANN. §§ 53.025, 53.101 (West 2007).
    Ritchey is not error. Consequently, the trial court did not err in awarding Ritchey its reasonable
    attorney’s fees. See TEX. PROP. CODE ANN. § 53.156. Addison’s seventh issue is overruled.
    Summary Motion to Remove Invalid Claim
    In its eighth issue, Addison argues the trial court erred in denying its motion to remove an
    invalid claim. Section 53.160(a) of the property code provides:
    (a) In a suit brought to foreclose a lien or to declare a claim or lien invalid or
    unenforceable, a party objecting to the validity or enforceability of the claim or
    lien may file a motion to remove the claim or lien. The motion must be verified
    and state the legal and factual basis for objecting to the validity or enforceability
    of the claim or lien. The motion may be accompanied by supporting affidavits.
    TEX. PROP. CODE ANN. § 53.160(a) (West Supp. 2013). The statute further provides that “the
    grounds for objecting to the validity or enforceability of a claim or lien for purposes of the
    motion are limited to the following: (1) notice of claim was not furnished to the owner or
    original contractor . . . (2) an affidavit claiming a lien failed to comply with Section 53.054 or
    was not filed as required by Section 53.052; (3) notice of the filed affidavit was not furnished to
    the owner or original contractor as required by Section 53.055; (4) the deadlines for perfecting a
    lien claim for retainage under this chapter have expired . . . (5) all funds subject to the notice of
    the claim to the owner and a notice regarding the retainage have been deposited in the registry of
    the court . . . (6) when the lien affidavit was filed on homestead property . . . no contract was
    executed or filed . . . or the affidavit claiming a lien failed to include the notice as required . . . or
    the notice failed to include the statement required; and (7) the claimant executed a valid and
    enforceable waiver or release of the claim or lien claimed in the affidavit.” TEX. PROP. CODE
    ANN. § 53.160(b).
    Thus, the statute expressly provides authority for the trial court to hear a summary motion
    to remove a lien that is based on any one of the grounds set out in subsection (b). See 
    id. If the
    trial court determines that the movant is entitled to removal of the lien, the trial court has
    authority to “enter an order removing the lien claimed in the lien affidavit.” See § 53.160(e).
    Here, Addison’s motion asserted that Ritchey failed to comply with section 53.054
    because it failed to prove it furnished materials for the project. Addison further asserted the lien
    should be removed because Ritchey filed three duplicative lien affidavits. Filing duplicative lien
    affidavits is not a basis for removal under the statute. See 
    id. And we
    have concluded that
    Ritchey did prove it furnished materials for the project. Accordingly, the trial court did not err in
    denying Addison’s motion to remove the lien. Addison’s eighth issue is overruled.
    Having resolved all of Addison’s issues against it, we affirm the trial court’s judgment.
    130122F.P05
    /Kerry P. FitzGerald/
    KERRY P. FITZGERALD
    JUSTICE
    S
    Court of Appeals
    Fifth District of Texas at Dallas
    JUDGMENT
    ADDISON URBAN DEVELOPMENT                          On Appeal from the County Court at Law
    PARTNERS, LLC, Appellant                           No. 3, Dallas County, Texas
    Trial Court Cause No. CC-10-03902-C.
    No. 05-13-00122-CV         V.                      Opinion delivered by Justice FitzGerald.
    Justices Fillmore and Evans participating.
    ALAN RITCHEY MATERIALS
    COMPANY, LC, Appellee
    In accordance with this Court’s opinion of this date, the judgment of the trial court is
    AFFIRMED.
    It is ORDERED that appellee ALAN RITCHEY MATERIALS COMPANY, LC recover
    its costs of this appeal from appellant ADDISON URBAN DEVELOPMENT PARTNERS,
    LLC.
    Judgment entered July 1, 2014
    

Document Info

Docket Number: 05-13-00122-CV

Citation Numbers: 437 S.W.3d 597

Filed Date: 7/1/2014

Precedential Status: Precedential

Modified Date: 1/12/2023

Authorities (24)

First National Bank in Dallas v. Whirlpool Corp. , 517 S.W.2d 262 ( 1974 )

Walker v. Packer , 827 S.W.2d 833 ( 1992 )

Page v. Marton Roofing, Inc. , 102 S.W.3d 733 ( 2003 )

First National Bank in Graham v. Sledge , 653 S.W.2d 283 ( 1983 )

Wood v. Henry S. Miller Co. , 597 S.W.2d 332 ( 1980 )

Brick Tile, Inc. v. Parker , 143 Tex. 383 ( 1945 )

Mustang Tractor & Equipment Co. v. Hartford Accident & ... , 263 S.W.3d 437 ( 2008 )

Davis v. State , 904 S.W.2d 946 ( 1995 )

Raymond v. Rahme , 78 S.W.3d 552 ( 2002 )

HOUSTON FIRE AND CASUALTY INSURANCE CO. v. Hales , 279 S.W.2d 389 ( 1955 )

Sheldon Pollack Corp. v. Pioneer Concrete of Texas, Inc. , 765 S.W.2d 843 ( 1989 )

Haden Co., Inc. v. Mixers, Inc. , 667 S.W.2d 316 ( 1984 )

Morrell Masonry Supply, Inc. v. Lupe's Shenandoah Reserve, ... , 363 S.W.3d 901 ( 2012 )

State Farm Lloyds v. Kessler , 932 S.W.2d 732 ( 1996 )

Taylor v. FIRST COMMUNITY CREDIT UNION , 316 S.W.3d 863 ( 2010 )

Lambda Construction Co. v. Chamberlin Waterproofing & ... , 784 S.W.2d 122 ( 1990 )

Reed v. Valley Federal Savings & Loan Co. , 655 S.W.2d 259 ( 1983 )

Occidental Nebraska Federal Savings Bank v. East End Glass ... , 773 S.W.2d 687 ( 1989 )

Wesco Distribution, Inc. v. Westport Group, Inc. , 150 S.W.3d 553 ( 2004 )

Arias v. Brookstone, L.P. , 265 S.W.3d 459 ( 2008 )

View All Authorities »