the City of San Antonio, (Appellant/Cross-Appellee) v. Kopplow Development, Inc., (Appellee/Cross-Appellant) , 441 S.W.3d 436 ( 2014 )


Menu:
  •                               Fourth Court of Appeals
    San Antonio, Texas
    OPINION ON REMAND
    No. 04-09-00403-CV
    THE CITY OF SAN ANTONIO,
    Appellant/Cross-Appellee
    v.
    Kopplow Development, Inc., (Appellee/Cross-Appellant
    KOPPLOW DEVELOPMENT, INC.,
    Appellee/Cross-Appellant
    From the 131st Judicial District Court, Bexar County, Texas
    Trial Court No. 2004-CI-08167
    Honorable John D. Gabriel, Jr., Judge Presiding
    Opinion by:      Rebeca C. Martinez, Justice
    Sitting:         Karen Angelini, Justice
    Rebeca C. Martinez, Justice
    Patricia O. Alvarez, Justice
    Delivered and Filed: February 5, 2014
    REVERSED AND REMANDED
    This case is before us on remand from the Supreme Court of Texas. See Kopplow Dev.,
    Inc. v. City of San Antonio, 
    399 S.W.3d 532
    (Tex. 2013). The underlying lawsuit involves an issue
    of statutory condemnation. See City of San Antonio v. Kopplow Dev., Inc., 
    335 S.W.3d 288
    (Tex.
    App.—San Antonio 2010). The City of San Antonio embarked on a project to reduce downstream
    flooding. As part of this particular project, the City built a permanent, concrete inflow wall across
    an easement owned by Kopplow Development. Kopplow, therefore, sued the City for a taking.
    The City counterclaimed for condemnation of Kopplow’s easement. Prior to trial, the parties
    04-09-00403-CV
    presented opposing motions concerning admissibility of evidence on the effect to be given the
    vested rights established for the Kopplow property before the taking. The trial court denied
    Kopplow’s request to admit evidence regarding its vested rights status, and ruled that testimony
    from Kopplow’s experts could not include consideration of the benefit of being vested from the
    requirements of the City’s new stormwater standards. The jury ultimately found that the value of
    the part taken was $4,600, the use of the part taken was a proximate cause of damages to the
    remainder, and the remainder was damaged in the amount of $690,000. The City and Kopplow
    both appealed.
    On original submission, a panel of this court affirmed the damage award for the part taken
    under the statutory takings 
    claim. 335 S.W.3d at 296
    . We reversed the award of remainder
    damages under the statutory takings theory, holding that the inflow wall would not inundate
    Kopplow’s property, even during a 100-year flood. 
    Id. at 294-95.
    We additionally held the
    remainder damages unrecoverable under Kopplow’s inverse condemnation theory because the
    property had not yet flooded and the inverse condemnation claim was therefore premature. 
    Id. at 296.
    In light of our holding, we did not reach Kopplow’s cross-appeal point that its vested right
    to develop the property meant that the trial court erred in excluding evidence of the value of the
    entire property. 
    Id. at 296-97.
    That is the issue currently before us. Because we hold that the trial
    court erred in excluding evidence of Kopplow’s vested rights status, we reverse the judgment of
    the trial court, and remand the case to the trial court for a new trial on the issue of damages
    consistent with this opinion.
    FACTUAL AND PROCEDURAL BACKGROUND
    In 1996, Kopplow purchased 18.451 acres of land adjoining Loop 410 in San Antonio.
    
    Kopplow, 399 S.W.3d at 534
    . After retaining an engineering firm, Kopplow filed a plat application
    in November 1996 and obtained utility and construction easements on the adjoining tract south of
    -2-
    04-09-00403-CV
    its property to connect sewer service. 
    Id. Because Kopplow’s
    property was below the 100-year
    floodplain elevation of 741 feet above mean sea level, as established by the Federal Emergency
    Management Agency (FEMA), Kopplow obtained a floodplain permit from the City and filled
    most of the property to 741 feet in 2000. 
    Id. About one
    fourth of the property still fell within the
    100-year floodplain, and Kopplow dedicated a drainage easement over this area. 
    Id. In 2004,
    the
    City granted Kopplow a vested rights permit, allowing it to develop the property under the rules
    in effect in November 1996. 
    Id. A vested
    rights permit insulates pending development from most
    future ordinance changes, although certain floodplain regulation changes apply retroactively even
    against vested rights holders. 
    Id. (citing TEX.
    LOC. GOV’T CODE ANN. §§ 245.002, 245.004(9)
    (West 2005)).
    San Antonio experienced 100-year floods in 1998 and 2002. 
    Kopplow, 399 S.W.3d at 534
    .
    
    Id. The City
    then planned a regional storm water detention facility for the Leon Creek watershed
    south of Kopplow’s property to mitigate downstream flooding. 
    Id. It determined
    in 2002 that the
    project would inundate portions of Kopplow’s property and the tract south of Kopplow’s property.
    
    Id. The City
    asked Kopplow in late 2003 to donate an easement that the City planned to inundate
    as part of the project. Kopplow refused. 
    Id. The City
    obtained a 207-acre drainage easement from
    the owner of the property south of the Kopplow tract in January 2004 and then built a concrete in-
    flow wall on the portion of the adjoining tract that includes Kopplow’s easements. 
    Id. By this
    time, the City had changed its regulatory 100-year floodplain to account for future,
    upstream development. 
    Id. The City
    ’s new minimum flood plain elevation was 745.16 feet msl.
    FEMA’s 100-year floodplain of 741 feet, by contrast, accounts for only existing conditions.
    Ultimately, Kopplow must fill the portion of its property to be developed from the existing 741-
    foot level to 745.16 feet: two feet due to the new detention facility and two feet due to the City’s
    ordinance change. 
    Id. at 535.
                                                    -3-
    04-09-00403-CV
    In May 2004, Kopplow sued the City for a taking while it was constructing the facility. 
    Id. The City
    counterclaimed for condemnation of Kopplow’s easement. 
    Id. Before trial,
    the trial
    court granted the City’s motion that Kopplow’s vested rights permit was not effective against
    subsequent floodplain ordinances and excluded Kopplow’s evidence pertaining to two of the four
    feet of additional fill needed to develop the property. 
    Id. (citing TEX.
    LOC. GOV’T CODE ANN.
    § 245.004(9) (West 2005)). As a result, Kopplow was not permitted to present evidence regarding
    the cost to fill the property from 741 feet to 743 feet. Kopplow’s experts testified in a bill of
    exception regarding the cost to fill the entire property. The jury found that: (1) the value of the
    part taken was $4,600; (2) the City’s use of the part taken proximately caused damages to the
    remainder; and (3) Kopplow’s remainder damages were $690,000. 
    Id. The City
    and Kopplow both appealed. 
    Id. As stated
    earlier, this court affirmed the damage
    award for the part taken under the statutory takings claim, but reversed the award of remainder
    damages. 
    Kopplow, 335 S.W.3d at 294-96
    . We also held the remainder damages unrecoverable
    under Kopplow’s inverse condemnation theory because the property had not yet flooded and the
    inverse condemnation claim was therefore premature. 
    Id. at 296.
    In light of our holding, we did
    not reach Kopplow’s cross-appeal point that its vested right to develop the property meant that the
    trial court erred in excluding some of the evidence of the cost required to fill the property from
    741 feet to 743 feet. 
    Id. at 296-97.
    Petition for review was granted by the Supreme Court of Texas. The Supreme Court held
    that the fact that flooding has not yet occurred does not render Kopplow’s inverse condemnation
    claim premature because the claim is based on the thwarting of approved development, not
    flooding. 
    Kopplow, 399 S.W.3d at 540
    . It thus concluded the award of remainder damages was
    recoverable under Kopplow’s inverse condemnation claim. 
    Id. The Supreme
    Court remanded the
    -4-
    04-09-00403-CV
    case to us solely for consideration of Kopplow’s cross-appeal point that the trial court erred in
    excluding some of the evidence of the cost of the fill. 
    Id. Upon remand,
    Kopplow contends the jury would have awarded it more damages had it
    heard evidence that the Kopplow property was subject to less onerous development regulations
    before the taking by the City, i.e., Kopplow would have presented to the jury evidence regarding
    the cost to fill the property from 741 feet to 743 feet. Kopplow asks that we reverse the trial court’s
    judgment and remand the case for a new trial on the issue of damages only.
    DISCUSSION
    Initially, we address the City’s contention that Kopplow failed to preserve error on the
    issue of vested rights. Specifically, the City claims that Kopplow failed to appeal the trial court’s
    March 16, 2009 “Interlocutory Order on Plaintiff’s Request for Declaratory Relief,” ruling that
    Kopplow’s vested rights permit does not apply to the City’s flood plain and storm water
    regulations, and thus waived its right to complain about vested rights on appeal.
    We disagree that Kopplow failed to preserve error on this issue. First, Kopplow was not
    required to appeal the complained-of order. An interlocutory appeal was not available to Kopplow,
    and the ruling was subsumed in the final judgment. Second, Kopplow met its burden of preserving
    error. “To preserve error concerning the exclusion of evidence, the complaining party must
    actually offer the evidence and secure an adverse ruling from the court.” Perez v. Lopez, 
    74 S.W.3d 60
    , 66 (Tex. App.—El Paso 2002, no pet.). Kopplow objected to the exclusion of the vested rights
    evidence, and made an offer of proof as to damages. Thus, Kopplow properly preserved error on
    the vested rights issue. See id.; see also TEX. R. APP. P. 33.1.
    Standard of Review
    Having determined that Kopplow properly preserved error, we must first interpret section
    245.004 to determine whether the trial court erred in concluding that the exemption provided in
    -5-
    04-09-00403-CV
    section 245.004(9) mandates that the floodplain regulation changes applied retroactively and, thus,
    in excluding evidence of Kopplow’s vested rights status. See TEX. LOC. GOV’T CODE ANN.
    § 245.004(9) (West 2005). When issues involve the interpretation of a statute itself, we apply a
    de novo standard of review. MCI Sales & Serv., Inc. v. Hinton, 
    329 S.W.3d 475
    , 500 (Tex. 2010)
    (an issue of statutory construction is a legal question which we review de novo); Johnson v. City
    of Fort Worth, 
    774 S.W.2d 653
    , 656 (Tex. 1989) (holding statutory construction is a question of
    law); see also Ustanik v. Nortex Found. Designs, Inc., 
    320 S.W.3d 409
    , 412 (Tex. App.—Waco
    2010, pet. denied) (if resolution of the issue requires us to construe statutory language, we review
    under a de novo standard; once we determine the proper construction of the statute, we determine
    whether the trial court abused its discretion in the manner in which it applied the statute to the
    instant case).
    In construing a statute, our main objective is to ascertain and give effect to the intent of the
    Legislature. Horizon/CMS Healthcare Corp. v. Auld, 
    34 S.W.3d 887
    , 892 (Tex. 2000); Wickware
    v. Sullivan, 
    70 S.W.3d 214
    , 218 (Tex. App.—San Antonio 2001, no pet.). When interpreting a
    statute, we “consider the entire act, its nature and object, and the consequences that would follow
    from each construction.” Sharp v. House of Lloyd, Inc., 
    815 S.W.2d 245
    , 249 (Tex. 1991); see
    also TEX. GOV’T CODE ANN. § 311.023 (West 2013). We must “reject interpretations of a statute
    that defeat the purpose of the legislation so long as another reasonable interpretation exists.”
    Nootsie, Ltd. v. Williamson Cnty. Appraisal Dist., 
    925 S.W.2d 659
    , 662 (Tex. 1996). When a
    statute is clear and unambiguous, we need not resort to rules of construction or extrinsic evidence
    to construe it. Cail v. Service Motors, Inc., 
    660 S.W.2d 814
    , 815 (Tex. 1983). Instead, we may
    determine the intent of the Legislature from the plain and ordinary meaning of the words used
    within the statute. 
    Id. -6- 04-09-00403-CV
    ANALYSIS
    Kopplow contends that the trial court erred in excluding evidence of the damages Kopplow
    claimed for the loss of its vested development rights. Chapter 245 of the Local Government Code
    recognizes a developer’s vested rights and requires a regulatory agency to review a permit
    application based on the regulations in effect at the time the project’s first application is filed. See
    Milestone Potranco Dev., Ltd., v. City of San Antonio, 
    298 S.W.3d 242
    , 248 (Tex. App.—San
    Antonio 2009, pet. denied). Generally, “a project with vested rights is not subject to intervening
    regulations or changes after the vesting date.” City of San Antonio v. Rogers Shavano Ranch, Ltd.,
    
    383 S.W.3d 234
    , 245 (Tex. App.—San Antonio 2012, pet. denied); see also Harper Park Two, LP
    v. City of Austin, 
    359 S.W.3d 247
    , 250 (Tex. App.—Austin 2011, pet. denied) (“The obvious intent
    of chapter 245 is to prohibit land-use regulators from changing the rules governing development
    projects ‘in the middle of the game[.]’”).
    Certain types of municipal regulations are, however, exempted from Chapter 245’s
    limitations. See TEX. LOC. GOV’T CODE ANN. § 245.004 (West 2005). The exemption at issue
    here provides:
    This chapter does not apply to:
    (9) regulations to prevent imminent destruction of property or injury to persons
    from flooding that are effective only within a flood plain established by a federal
    flood control program and enacted to prevent the flooding of buildings intended for
    public occupancy[.]
    TEX. LOC. GOV’T CODE ANN. § 245.004(9) (West 2005). The parties do not cite to, and we have
    not located, any authority interpreting this particular statutory exemption.
    The City persuaded the trial court that exemption (9) bars recognition of Kopplow’s vested
    rights. On appeal, the City argues that exemption (9) applies because the City is a community
    -7-
    04-09-00403-CV
    participating in the National Flood Insurance Program (NFIP), and that the City is the local flood
    plain administrator for the NFIP. We disagree.
    The plain language of the statute indicates that cities are allowed to enforce against vested
    rights only those flooding regulations “established by a federal flood control program” (emphasis
    added). The record contains no evidence showing that the NFIP established the City’s flood plain.
    Although the City contends that it adopted federally-established flood plain ordinances, it also
    acknowledges that the NFIP encourages communities to develop more stringent flooding
    regulations, and that the City did so. Thus, the City is the entity that established the flood plain,
    not the NFIP. The record supports the distinction between the FEMA 100-year flood plain and
    the City’s ultimate development flood plain, with the City’s regulations being more onerous than
    FEMA’s.
    By specifying regulations effective in a federally-established flood plain, the Legislature
    expressed a clear intent to distinguish from non-federal, or local, flood plain regulations. See
    Comm’n for Lawyer Discipline v. Denisco, 
    132 S.W.3d 211
    , 216 (Tex. App.—Houston [14th Dist.]
    2004, no pet.) (express mention of one thing ordinarily presumed to exclude all others). It is also
    noteworthy that the Legislature chose to use the qualifier “only,” therefore indicating an intention
    to exempt federally-defined flood plains alone. Accordingly, we agree that the trial court erred in
    concluding that section 245.004(9) exempted Kopplow’s vested rights, and in excluding evidence
    of the cost to fill the property from 741 feet to 743 feet due to the City’s new flooding regulations.
    HARM
    Having determined that the trial court erred in excluding evidence of the cost of the fill
    related to Kopplow’s vested rights permit, we must now examine whether the error harmed
    Kopplow.
    -8-
    04-09-00403-CV
    Standard of Review
    Evidentiary rulings are committed to the trial court’s sound discretion.          Bay Area
    Healthcare Grp., Ltd. v. McShane, 
    239 S.W.3d 231
    , 234 (Tex. 2007) (per curiam); Interstate
    Northborough P’ship v. State, 
    66 S.W.3d 213
    , 220 (Tex. 2001). A trial court abuses this discretion
    when it acts without regard for guiding rules or principles. U-Haul Int’l, Inc. v. Waldrip, 
    380 S.W.3d 118
    , 132 (Tex. 2012); Owens–Corning Fiberglas Corp. v. Malone, 
    972 S.W.2d 35
    , 43
    (Tex. 1998). Even if a trial court errs by improperly admitting evidence, reversal is warranted only
    if the error was harmful, i.e., it probably resulted in an improper judgment. TEX. R. APP. P. 44.1;
    Nissan Motor Co. Ltd. v. Armstrong, 
    145 S.W.3d 131
    , 144 (Tex. 2004).
    In determining whether the error was harmful, we review the entire record and require the
    complaining party to demonstrate that the judgment turns on the particular evidence admitted or
    excluded. 
    McShane, 239 S.W.3d at 234
    ; Nissan 
    Motor, 145 S.W.3d at 144
    . “[I]t is not necessary
    for the complaining party to prove that ‘but for’ the exclusion of evidence, a different judgment
    would necessarily have resulted.” McCraw v. Maris, 
    828 S.W.2d 756
    , 758 (Tex. 1992). The
    complaining party must only show “that the exclusion of evidence probably resulted in the
    rendition of an improper judgment.” 
    Id. If erroneously
    excluded evidence was crucial to a key issue, the error was likely harmful.
    State v. Cent. Expressway Sign Assocs., 
    302 S.W.3d 866
    , 874 (Tex. 2009) (exclusion of evidence
    harmful because evidence was directly related to central issue in case, i.e., value of condemned
    property); Reliance Steel & Aluminum Co. v. Sevcik, 
    267 S.W.3d 867
    , 873 (Tex. 2008). By
    contrast, exclusion is likely harmless if the evidence was cumulative and not controlling on a
    material issue dispositive of the case. 
    Sevcik, 267 S.W.3d at 873
    ; Corrales v. Dept. of Family &
    Protective Servs., 
    155 S.W.3d 478
    , 487 (Tex. App.—El Paso 2004, no pet.).
    -9-
    04-09-00403-CV
    Here, the issue of Kopplow’s vested rights was a crucial question, because it bore upon the
    amount of remainder damages owed for the inverse condemnation. The jury determined that
    Kopplow was entitled to $690,000 as compensation for having to fill the property from 743 feet to
    745 feet. However, assuming that there was no exemption for Kopplow’s vested rights, Kopplow
    should have been permitted to present evidence of the additional cost to fill the property from 741
    feet to 743 feet; i.e., that the cost of the entire fill would have been more than $690,000.
    Kopplow provided, through its expert, engineer Dennis Rion, reliable and admissible
    evidence in support of its entire damages. See TEX. R. EVID. 103(a)(2) (error cannot be predicated
    on the exclusion of evidence unless the substance of the evidence was made known by offer, or
    was apparent from the context); PopCap Games, Inc. v. MumboJumbo, LLC, 
    350 S.W.3d 699
    , 719
    (Tex. App.—Dallas 2011, pet. denied) (noting reviewing court cannot determine whether
    exclusion of evidence was harmful without an offer of proof). Rion would have testified to the
    quantities and costs shown in an exhibit tendered to the trial court in a bill of exception. The
    damages model in that exhibit projects the cost for grading existing conditions on the Kopplow
    property to an elevation of 745.16 feet. The project total is estimated at $867,248. Kopplow also
    tendered a bill of exception from its appraisal expert, David Bolton. Bolton’s detailed appraisal
    report estimates that the total compensation due Kopplow is $1,115,000, i.e., market value of the
    part taken and damages to the remainder property. Had the trial court ruled in Kopplow’s favor
    on the vested rights issue, Bolton would have presented testimony consistent with the tendered
    appraisal report.
    Because the jury did not hear evidence related to the cost required to fill the entire property,
    we conclude that the exclusion harmed Kopplow. See, e.g., Caffe Ribs, Inc. v. State, 
    328 S.W.3d 919
    , 931-33 (Tex. App.—Houston [14th Dist.] 2010, no pet.); Oddo v. State, 
    912 S.W.2d 831
    ,
    833-34 (Tex. App.—Dallas 1995, writ denied) (holding exclusion of evidence related to
    - 10 -
    04-09-00403-CV
    compensable damages was harmful where it was the only evidence regarding remainder damages);
    State v. Oak Hill Joint Venture, 
    815 S.W.2d 827
    , 832 (Tex. App.—Austin 1991, no writ) (holding
    exclusion of evidence of true remainder size deprived condemnors of opportunity to present
    probative evidence regarding effect of taking on market value of designated remainder, and was
    thus harmful).
    CONCLUSION
    Based on the foregoing, we sustain Kopplow’s issue on cross-appeal. We reverse the
    judgment of the trial court awarding Kopplow damages in the amount of $690,000, and remand
    the case to the trial court for a new trial on the issue of remainder damages related to the inverse
    condemnation claim.
    Rebeca C. Martinez, Justice
    - 11 -