C&F International, Inc. v. Interoil Services, LLC ( 2020 )


Menu:
  • Affirmed and Memorandum Opinion filed April 2, 2020.
    In The
    Fourteenth Court of Appeals
    NO. 14-18-00698-CV
    C&F INTERNATIONAL, INC., Appellant / Cross-Appellee
    V.
    INTEROIL SERVICES, LLC, Appellee / Cross-Appellant
    On Appeal from the 151st District Court
    Harris County, Texas
    Trial Court Cause No. 2015-33978
    MEMORANDUM OPINION
    Interoil Services, LLC sued C&F International, Inc. (CFI) for breach of an
    oral contract and quantum meruit for commissions that CFI owed to Interoil
    resulting from the companies’ business transactions with a third party (Schahin)
    after Schahin failed to pay its debts. CFI counterclaimed for breach of a written
    contract, claiming indemnity for losses from the Schahin transactions. A jury
    found that the written contract applied, awarded CFI damages of $1,044,910.02,
    and awarded Interoil damages of $1,140,991.65. Each party moved for entry of a
    judgment, claiming attorney’s fees, pre- and post-judgment interest, and costs.
    Each party disputed the other party’s claims for attorney’s fees and interest. The
    trial court signed a final judgment awarding Interoil $96,081.63 in damages,
    $95,200.00 in attorney’s fees, pre- and post-judgment interest, and costs.
    Each party appealed. In four issues, Interoil contends that the trial court
    erred by (1) failing to construe the written contract as a matter of law to exclude
    the Schahin transactions from being covered by the indemnity clause, and (2)
    enforcing the indemnity clause. In two issues, CFI contends that the trial court
    erred by (1) awarding attorney’s fees, interest, and costs to Interoil because Interoil
    did not prevail on any claim, and (2) denying CFI’s request for attorney’s fees.
    We affirm.
    I.     BACKGROUND
    For more than a decade, Schahin was CFI’s customer.                Schahin was
    involved in oil drilling and would use CFI to source and purchase equipment.
    Schahin would inform CFI what products Schahin needed, CFI would present
    quotes to Schahin, and CFI would purchase equipment and sell it to Schahin. CFI
    would finance the sales for up to 360 days.
    David Haese was the head of the oil and gas department at CFI, which did
    the purchasing and sales for Schahin. CFI’s Chief Financial Officer Matthias
    Lietsch testified that Haese “brought that business. He was the connection to that
    business. He was the lifeline to this. He was basically the know-how carrier.”
    Lietsch testified that Schahin was Haese’s customer and nobody at CFI “really
    understood this business besides David Haese and his team.”
    In 2003, CFI informed Haese and the rest of the employees in his
    department that CFI was terminating their employment because CFI no longer
    2
    wanted to be in the oil field supply business. However, Haese and his department
    were “spun out” to form Interoil, which continued to do “all the work” for Schahin.
    Haese was the president of Interoil.
    CFI and Interoil entered into services agreements in 2003 and 2009,
    whereby Interoil leased office space from CFI and would receive administrative
    and back-office support from CFI, among other services. Sections 1(a) and 4 of
    the 2009 agreement provided for profit-sharing and indemnity to CFI regarding
    sales to “customers of Interoil”:
    1. Services. To support the activities of Interoil in the United States,
    and in accordance with the instructions of Interoil, but subject to
    the terms of this Agreement, CFI shall provide the following
    services (the “Services”):
    a. CFI may, in its discretion and as agreed upon by CFI and
    Interoil on a case-by-case basis, accept orders from customers
    of Interoil, and such transactions shall be conducted under
    CFI’s risk management guidelines, and CFI shall perform such
    transactions in accordance with the terms thereof (singularly, a
    “CFI Sale”, and collectively, the “CFI Sales”);
    ....
    4. CFI Sales. For each CFI Sale, CFI and Interoil shall agree, on a
    case-by-case basis, on a profit share which shall be payable by CFI
    to Interoil once all payments for the CFI Sale have been collected
    by CFI from the customer. . . . Interoil hereby indemnifies and
    holds CFI harmless from and against any losses or damages arising
    from or relating to the failure of any customer to pay any amounts
    due and owing under any of the CFI Sales which are not
    reimbursed by export credit insurance.
    Lietsch testified that CFI acted “like a bank” for Interoil, providing a line of
    credit and obtaining credit insurance for the Schahin transactions. Lietsch testified
    that the 2009 agreement applied to “basically, again, only Schahin business.”      In
    negotiations for the 2009 agreement, Lietsch wrote to Haese and others that the
    3
    agreement was “a mutually agreeable profit sharing agreement on business that is
    routed via CFI’s books, in order to secure financing and risk management (credit
    insurance) on certain business (Shahin) [sic], which could be extended to other
    customers.”
    In 2010, CFI and Schahin entered into a procurement agreement, which
    provided that Schahin “hereby appoints CFI as [Schahin]’s exclusive procurement
    representative, to globally source products, machinery and equipment in
    accordance with specifications issued by [Schahin].” Lietsch testified that the
    purpose of the procurement agreement, and CFI’s practice of invoicing and
    accepting payment from Schahin, was so that the transactions could be covered by
    CFI’s credit insurance. Haese testified that Interoil did “all of the work” on the
    Schahin transactions and retained a majority of the profits from those transactions.
    In emails, Interoil employees repeatedly referred to Schahin as “our customer.”
    In 2013 or 2014, Schahin stopped paying its bills, and CFI stopped paying
    commissions owed to Interoil under the 2009 services agreement because their
    exposure on the Schahin transactions exceeded the amount of commissions owed
    to Interoil. CFI relied on the indemnity clause of Section 4 of the agreement. CFI
    acknowledged that the unpaid commissions amounted to $1,140,991.65. Haese,
    citing Section 4 of the agreement, made multiple demands for payment of the
    commissions owed.
    Interoil sued CFI for the unpaid commissions, asserting claims for breach of
    an oral agreement and quantum meruit. CFI counterclaimed for breach of the 2009
    services agreement, relying on the indemnity clause in Section 4. At trial, CFI
    admitted through its evidence and through arguments that it owed Interoil
    $1,140,991.65 in unpaid commissions, but CFI asked the jury to award CFI the
    amount of its losses on the Schahin transactions. CFI claimed $3,879,860.25 in
    4
    “total Schahin loss” after accounting for its credit insurance and mitigation of
    damages, as follows:
    Unpaid balance from Schahin:                 $1,014,820.79
    Order backlog (equipment CFI purchased):        $30,089.23
    Interest:                                    $2,816,914.81
    Travel expenses for collection efforts:         $18,035.42
    Neither party objected to the first three questions in the jury charge, which
    asked:
    Question 1
    Were the Schahin transactions in question “CFI Sales” as that term is
    used in Paragraph 1(a) of the 2009 agreement?
    Answer “Yes” or “No.”
    Answer: ______________
    Question 2
    For the Schahin transactions in Question 1 that you found to be “CFI
    Sales” under the 2009 Services Agreement, what sum of money
    should be paid to Interoil?
    Do not add any amount for interest on damages, if any.
    Answer separately in dollars and cents for damages, if any.
    Consider the following elements of damages, if any, and none other:
    Profit share based on the gross profit (sales minus (a) cost of
    goods sold, (b) interest expenses and (c) export credit
    insurance).
    Answer: ______________
    Question 3
    For the Schahin transactions in question 1 that you found to be “CFI
    Sales” under the 2009 Services Agreement, what sum of money
    should be paid to C&F International, Inc.?
    Do not add any amount for interest on damages, if any.
    5
    Answer separately in dollars and cents for damages, if any.
    Consider the following elements of damages, if any, and none other:
    Losses or damages arising from or relating to the failure of any
    customer to pay any amounts due and owing under any of the
    CFI Sales which are not reimbursed by export credit insurance.
    Answer: ______________
    The remaining questions concerned Interoil’s claims for breach of an oral contract
    and quantum meruit. The parties stipulated to the amounts of reasonable and
    necessary attorney’s fees: $113,356.00 for CFI and $95,200.00 for Interoil. The
    parties did not stipulate regarding the legal availability of fees, which depended on
    the verdict from the jury.
    Interoil argued to the jury that Schahin was not “Interoil’s customer,” and
    therefore, the Schahin transactions were not “CFI Sales.” Interoil asked the jury,
    nonetheless, to award Interoil $1,140,991.65 in damages under Question No. 2 if
    the jury believed the 2009 services agreement applied to the Schahin transactions.
    The jury answered the questions as follows: (1) Yes; (2) $1,140,991.65; and
    (3) $1,044,910.02. The jury did not answer the remaining questions because they
    were predicated on a “no” answer to Question No. 1.
    Each party moved for entry of a judgment in its favor. CFI calculated the
    judgment it sought by adding pre-judgment interest to its damages award, then
    subtracting Interoil’s damages, and adding CFI’s attorney’s fees. Interoil sought a
    judgment for the net difference in damages awarded by the jury, $96,081.62, plus
    attorney’s fees and pre-judgment interest. Interoil also filed a motion for judgment
    notwithstanding the verdict, asserting that the indemnity clause failed “fair notice”
    requirements, so CFI was not entitled to any damages (and Interoil was entitled to
    the full $1,140,991.65 in damages plus fees and interest).
    6
    The trial court signed a final judgment awarding Interoil $96,081.62 in
    damages, $95,200.00 in attorney’s fees, $13,939.00 in pre-judgment interest, post-
    judgment interest, and costs. Both parties appealed.
    II.   INTEROIL’S APPEAL
    In its first two issues, Interoil contends that the “unambiguous language of
    the underlying contracts is a legal issue to be decided by the trial court as a matter
    of law” and that “[p]ursuant to the plain language of the underlying contracts, the
    Schahin Entities were the direct customer of [CFI] as a matter of law.” In its third
    and fourth issues, Interoil contends that CFI “was not entitled to indemnification as
    awarded by the jury as a matter of law” and the “indemnification clause relied on
    by [CFI] is unenforceable as a matter of law.”
    A.    Contractual Interpretation Issues Not Preserved
    Under the first two issues, Interoil contends that the Schahin transactions
    were not “CFI Sales” as a matter of law, contrary to the jury’s finding, and that the
    trial court was required to rule on the plain meaning of the 2009 services
    agreement and the 2010 procurement agreement as a matter of law.              Interoil
    contends that it made three attempts to obtain rulings from the trial court based on
    the language of the underlying contracts and to enforce the plain and unambiguous
    meaning of the contracts: (1) motion for summary judgment; (2) request for a
    directed verdict; and (3) motion for judgment notwithstanding the verdict.
    When a trial court denies a motion for summary judgment and the case is
    tried on the merits, the order denying the summary judgment cannot be reviewed
    on appeal. United Parcel Serv., Inc. v. Tasdemiroglu, 
    25 S.W.3d 914
    , 916 (Tex.
    App.—Houston [14th Dist.] 2000, pet. denied). The party’s remedy is to assign
    error to the trial court’s judgment ultimately rendered following the trial on the
    7
    merits.
    Id. To preserve
    error for a “matter of law” challenge to the trial court’s
    judgment following a jury trial, an appellant must raise the issue through one of the
    following means: (1) a motion for directed verdict; (2) a motion for judgment
    notwithstanding the verdict; (3) an objection to the submission of the question to
    the jury; (4) a motion to disregard the jury’s answer to a vital fact question; or (5) a
    motion for new trial. See, e.g., Ginn v. Pierce, No. 14-17-00742-CV, 
    2019 WL 4511328
    , at *1 (Tex. App.—Houston [14th Dist.] Sept. 19, 2019, no pet. h.);
    
    Tasdemiroglu, 25 S.W.3d at 916
    .
    Although Interoil raised its contractual-interpretation issues in a motion for
    summary judgment, Interoil did not request a directed verdict at trial, nor did it
    raise this issue in its motion for judgment notwithstanding the verdict. Interoil did
    not object to the submission of Question No. 1, move to disregard the jury’s
    answer, or move for a new trial. Accordingly, Interoil failed to preserve error for
    its “matter of law” issues regarding whether the Schahin transactions were “CFI
    Sales” under the 2009 services agreement. See 
    Tasdemiroglu, 25 S.W.3d at 916
    .
    Interoil’s first two issues are overruled.
    B.    Fair Notice Not Required
    In its third and fourth issues, Interoil contends that the indemnity clause is
    unenforceable because it provides indemnification for CFI’s “negligent credit
    decisions” and is not conspicuous.
    To be enforceable, “extra-ordinary risk shifting clauses must meet certain
    fair notice requirements.” Green Int’l, Inc. v. Solis, 
    951 S.W.2d 384
    , 386 (Tex.
    1997). Such clauses must be “conspicuous” as defined by Texas’s version of the
    Uniform Commercial Code.
    Id. Extraordinary risk-shifting
    clauses include
    8
    “releases and indemnity clauses in which one party exculpates itself from its own
    future negligence.”
    Id. at 387.
    In Solis, the supreme court rejected an argument that the fair-notice
    requirements should apply to a no-damages-for-delay clause.
    Id. The court
    distinguished its prior cases concerning the shifting of tort and negligence
    damages, whereas the clause in Solis shifted only “economic damages resulting
    from a breach of contract.”
    Id. Interoil argues
    that CFI’s loss was due to “its own negligent credit
    decisions.” But the pleadings in this case do not show that CFI was seeking
    indemnity for its own negligence.       Interoil did not request a fact-finding on
    whether CFI was negligent, and neither the jury nor the court made such a finding.
    The record does not conclusively establish that CFI’s loss was due to its own
    negligence. Rather, the record shows that CFI’s loss was based on economic
    damages resulting from a third-party’s breach of contract. See
    id. Because the
    record does not show that CFI was seeking indemnity from its own negligence,
    conspicuousness is not required. See DDD Energy, Inc. v. Veritas DGC Land, Inc.,
    
    60 S.W.3d 880
    , 885 (Tex. App.—Houston [14th Dist.] 2001, no pet.) (holding that
    the fair-notice requirements do “not apply where an indemnitee is seeking
    indemnification from claims not based on the negligence of the indemnitee”); cf.
    Audubon Indem. Co. v. Custom Site-Prep Inc., 
    358 S.W.3d 309
    , 320 (Tex. App.—
    Austin 2011, no pet.) (holding that fair notice was not required for a subcontractor
    to indemnify a contractor because although the indemnity provision applied to
    some negligence of the contractor, the indemnity claim arose from an arbitrator’s
    findings of negligence and breach of contract against the contractor that were
    based on the subcontractor’s negligence).
    Interoil’s third and fourth issues are overruled.
    9
    III.   CFI’S APPEAL
    In its first issue, CFI asks “[w]hether the Trial Court properly awarded
    Interoil Services LLC attorneys’ fees, pre- and post-judgment interest, and costs of
    court?” In its second issue, CFI asks, “[w]hether the Trial Court erroneously
    denied C&F International, Inc.’s request for attorneys’ fees when CFI prevailed on
    all of its claims for affirmative relief?”
    A.    Interoil’s Breach of Written Contract Claim Tried by Consent
    In its first issue, CFI contends that Interoil did not prevail on any of its
    claims—breach of an oral contract or quantum meruit. CFI argues that Interoil
    “did not seek any relief under the 2009 Services Agreement.” CFI challenges only
    the award of attorney’s fees, interest, and costs. CFI does not challenge the award
    of damages, arguing that “the judgment should be modified to reflect that CFI
    prevailed on its claims and that the most that should be awarded to Interoil is the
    net payment required under the 2009 Services Agreement.”
    CFI does not cite to any rule of procedure, statute, or case law for this issue,
    nor does CFI provide this court with a legal framework within which to resolve the
    issue. Assuming without deciding that CFI’s first issue is not waived due to
    inadequate briefing, we will address the merits of the issue as much as reasonably
    possible. See St. John Missionary Baptist Church v. Flakes, No. 18-0513, 
    2020 WL 593694
    , at *2, *4 (Tex. Feb. 7, 2020) (reaffirming that “courts of appeals
    retain their authority to deem an unbriefed point waived in lieu of requesting
    additional briefing” but noting that appellate courts should reach the merits of an
    appeal whenever reasonably possible); see also Tex. R. App. P. 38.1(i) (“The brief
    must contain a clear and concise argument for the contentions made, with
    appropriate citations to authorities and to the record.”); Alexander v. Citibank N.A.,
    No. 14-04-01087-CV, 
    2006 WL 89517
    , at *1 (Tex. App.—Houston [14th Dist.]
    10
    Jan. 17, 2006, no pet.) (mem. op.) (appellant waived both issues on appeal by
    failing to cite to legal authority other than the rules of evidence).
    A trial court’s judgment must conform to the pleadings, see Tex. R. Civ.
    P. 301, and a trial court cannot render a judgment on a theory of recovery not
    sufficiently set forth in the pleadings or otherwise tried by consent. Herrington v.
    Sandcastle Condo. Ass’n, 
    222 S.W.3d 99
    , 102 (Tex. App.—Houston [14th Dist.]
    2006, no pet.). “When issues not raised by the pleadings are tried by express or
    implied consent of the parties, they shall be treated in all respects as if they had
    been raised in the pleadings.” Tex. R. Civ. P. 67. The rule for trial by consent is
    intended to cover the exceptional case in which the record clearly shows the parties
    tried an unpleaded issue. 
    Herrington, 222 S.W.3d at 102
    .
    In Ingram v. Deere, for example, the Supreme Court of Texas held that an
    issue was tried by consent when both parties presented evidence on the subject and
    allowed the issue to be raised in the jury charge. See 
    288 S.W.3d 886
    , 893 (Tex.
    2009); see also Sage Street Assoc. v. Northdale Const. Co., 
    863 S.W.2d 438
    , 446
    (Tex. 1993) (ambiguity of contract tried by consent because the parties allowed a
    damages question to go to the jury and there was conflicting testimony on the
    subject).
    Interoil did not assert in its live petition a claim based on CFI’s breach of the
    2009 services agreement.       But both parties adduced evidence that CFI owed
    Interoil commissions under the 2009 services agreement. The jury charge did not
    ask whether either party breached the 2009 services agreement, but it asked
    whether the Schahin transactions were “‘CFI Sales’ as that term is used in
    Paragraph 1(a) of the 2009 Services Agreement.” The charge then asked the jury
    “what sum of money should be paid to Interoil” and instructed the jury about what
    “elements of damages” to consider. CFI did not object to the jury question about
    11
    Interoil’s damages under the 2009 services agreement. CFI told the jury that it
    agreed with Interoil’s entitlement to damages under the 2009 services agreement:
    Number 2, if you answered yes [to Question No. 1], your answer here
    should be $1.1 million. In fact, I’ll give you the exact number. We
    calculated it. It’s $1,140,991.65. I agree with [counsel for Interoil]
    that that’s our number and that’s the amount that Interoil would be
    entitled to under the 2009 agreement.
    Because the parties adduced evidence about what CFI was owed under the 2009
    services agreement and then asked the jury to determine Interoil’s “damages”
    under the agreement, the issue was tried by consent. See 
    Ingram, 288 S.W.3d at 893
    .
    Interoil included in its petition a request for attorney’s fees under
    Section 38.001 of the Civil Practice and Remedies Code. See Tex. Civ. Prac. &
    Rem. Code § 38.001(8) (“A person may recover reasonable attorney’s fees from an
    individual or corporation, in addition to the amount of a valid claim and costs, if
    the claim is for: . . . an oral or written contract.”). Because Interoil recovered
    damages on a claim for a written contract, Interoil was entitled to attorney’s fees.
    See id.; see also 
    Solis, 951 S.W.2d at 390
    . And because Interoil was successful
    and obtained a money judgment, Interoil was entitled to costs, see Tex. R. Civ.
    P. 131, pre-judgment interest, see Johnson & Higgins of Tex., Inc. v. Kenneco
    Energy, Inc., 
    962 S.W.2d 507
    , 533 (Tex. 1998), and post-judgment interest, see
    Tex. Fin. Code § 304.003(a).
    CFI’s first issue is overruled.
    B.     No Attorney’s Fees for Claim Against Limited Liability Companies
    In its second issue, CFI contends that the trial court “erroneously denied
    CFI’s request for attorneys’ fees presumably on a rationale that a net recovery is
    required for a party to obtain an award for attorney’s fees,” citing McKinley v.
    12
    Drozd. See 
    685 S.W.2d 7
    , 10–11 (Tex. 1985) (holding that net recovery was not
    required under predecessor statute to Section 38.001, and the statute allowed
    recovery of attorney’s fees “even if the amount of the claim is entirely offset by an
    opposing party’s claim”).
    It is undisputed that Interoil is a limited liability company. CFI alleged in its
    live petition that Interoil is “an Ohio limited liability company.” A party cannot
    recover attorney’s fees under Section 38.001 against a limited liability company.
    Alta Mesa Holdings, L.P. v. Ives, 
    488 S.W.3d 438
    , 455 (Tex. App.—Houston [14th
    Dist.] 2016, pet. denied). Thus, the trial court did not err by overruling CFI’s
    request for attorney’s fees. See Beard v. Endeavor Nat. Gas, L.P., No. 01-08-
    00180-CV, 
    2008 WL 5392026
    , at *8 (Tex. App.—Houston [1st Dist.] Dec. 19,
    2008, pet. denied) (mem. op.) (“Here, the trial court did not reveal the basis for the
    denial of attorney’s fees, and thus we may uphold its ruling on any basis supported
    by the evidence.”); Smith v. McCarthy, 
    195 S.W.3d 301
    , 305 (Tex. App.—Fort
    Worth 2006, pet. denied) (same); Sharp v. Hobart Corp., 
    957 S.W.2d 650
    , 654
    (Tex. App.—Austin 1997, no pet.) (same).
    CFI’s second issue is overruled.
    IV.    CONCLUSION
    The parties’ issues are overruled. The trial court’s judgment is affirmed.
    /s/    Ken Wise
    Justice
    Panel consists of Chief Justice Frost and Justices Wise and Hassan.
    13