Bright Excavation, Inc. v. Pogue Construction Co., LP and Hartford Fire Insurance Co. ( 2020 )


Menu:
  • Affirmed and Opinion Filed April 21, 2020
    In The
    Court of Appeals
    Fifth District of Texas at Dallas
    No. 05-18-00820-CV
    BRIGHT EXCAVATION, INC., Appellant
    V.
    POGUE CONSTRUCTION CO., LP AND HARTFORD FIRE INSURANCE
    CO., Appellees
    On Appeal from the 191st Judicial District Court
    Dallas County, Texas
    Trial Court Cause No. DC-17-00591
    MEMORANDUM OPINION
    Before Justices Myers, Osborne, and Nowell
    Opinion by Justice Nowell
    This is an appeal from a final take-nothing judgment following the granting
    of a traditional and no-evidence motion for summary judgment and a motion for
    attorney’s fees. Bright Excavation, Inc., a subcontractor, sued the general contractor,
    Pogue Construction Co., LP, and its surety, Hartford Fire Insurance Co., for breach
    of contract and other causes of action seeking additional payment for excavation
    work Bright claims was beyond the scope of its contract. In seven issues, Bright
    argues the trial court erred by granting summary judgment because the subcontract
    is ambiguous and the evidence raised fact issues: on waiver and excuse defenses to
    the contractual time limits for submitting change orders; on Bright’s causes of action
    for quantum meruit, promissory estoppel; and on the bond claim against Hartford.
    We conclude the subcontract is not ambiguous, the work performed was within the
    scope of work, and Bright was not entitled to additional compensation. We also
    conclude Bright’s other causes of action fail because there is an express contract
    covering the subject matter and no breach of the subcontract to support the bond
    claim. We affirm the trial court’s judgment.
    Background
    Lancaster Independent School District hired Pogue as the general contractor
    on a project to build two new elementary schools. This dispute concerns only the
    Pleasant Run school. Bright was invited to bid on the earthwork portion of the project
    and received a bid package from Pogue containing the plans and specifications and
    other relevant documents. Attached to the specifications was a geotechnical report
    of the subsurface conditions at the site. Section 00 31 32 of the specifications
    instructed, “Report and log of borings are available for Contractor’s information but
    is not a warranty of subsurface conditions, nor is it a part of the Contract
    Documents.” Section S1.0 of the plans, regarding treatment of the soil beneath the
    building, specified: “Perform any cut operations to expose to the top of the limestone
    strata. For proposal purposes, contractor shall assume 6 ft of remove and replace
    –2–
    shall be necessary. The geotechnical engineer or a representative of the geotechnical
    engineer shall verify the top of the tan limestone.”1
    The geotechnical report contained an analysis of subsurface materials at the
    selected locations for purposes of formulating appropriate geotechnical design
    parameters for the new construction. Attached to the report were logs of widely-
    spaced borings taken at the site. The report indicated the recommendations were
    developed from borings depicting the subsurface conditions only at the specific
    boring locations and at the times designated in the boring logs. It stated that
    subsurface conditions at other locations may differ from those observed at the boring
    locations and the subsurface conditions at the boring locations may vary at different
    times of the year. The report warned that the scope of work “may not fully define
    the variability of subsurface material and conditions that are present on the site.”
    Bright reviewed the bid package and noted the instruction to assume six feet
    of remove and replace would be necessary. However, based on its employees’
    experience, Bright concluded it would not be economically feasible to excavate and
    replace six feet of material. Rather, Bright interpreted the boring logs to reflect that
    the top of tan limestone was expected to be encountered between two and four feet
    below ground level. Bright based its bid on the shallower depth for the top of tan
    limestone. According to Bright’s witnesses, it disclosed its bidding process to Pogue
    1
    The documents in the record refer to this strata variously as “tan shaly limestone,” “tan limestone,”
    or “shale limestone.” For simplicity we use the term tan limestone.
    –3–
    in a scope review prior to the final acceptance of the bid. Pogue’s witnesses deny
    that these discussions took place.
    Bright’s bid for the earthwork was accepted by Pogue. Prior to execution of
    the subcontract, Pogue sent a notice to proceed, which contained a listing of the
    earthwork as described in the plans and specifications, to Bright on May 10, 2016.
    Line item 57 in the initial notice to proceed stated, “Building Pad Subgrade
    preparation- overexcavation to limestone, moisture condition in 8” lifts with 1’ select
    fill cap or flex base.” Later that day, Pogue sent a revised notice to proceed changing
    line item 57 to read, “Building Pad Subgrade preparation- overexcavation to
    limestone, prep for ½” movement per Geotechnical Report with select fill of
    flexbase.” Bright contends this change in the notice to proceed reflected Pogue’s
    agreement that Bright would excavate to the top of tan limestone in accordance with
    the geotechnical report.
    Bright and Pogue executed the subcontract on June 1, 2016 and June 21, 2016
    respectively. Bright agreed to furnish all labor, material, equipment, services and
    supplies required for a complete job of Earthwork, as specifically described in the
    exhibit A.1, “in strict accordance with the project plans, specifications, notes, codes,
    ordinances, manufacturers’ recommendations and all applicable local, state and
    federal regulations.” Pogue agreed to pay Bright for described work and materials,
    and Bright agreed to accept, the sum of $945,000.00. Exhibit A.1 included section
    31A, which referenced the earthwork sections of the plans and specifications. Line
    –4–
    item 57 had the same language as item 57 in the revised notice to proceed. The
    subcontract represented “the entire and integrated Agreement between the parties
    and supersede[d] all prior negotiations, representations, or agreements, whether
    written or oral.”
    Bright began its work in June 2016. Mike Lipka, Bright’s field superintendent,
    testified that on June 21, Lee Johnson, the testing engineer onsite, instructed them to
    dig through a thin layer of hardpan to get to hard shale. Hardpan is a mix of clay and
    shale that is softer than actual shale limestone. Bright contends the geotechnical
    report did not accurately reflect the depth of the top of limestone and it was required
    to excavate an additional two feet or more beyond the depths it anticipated based on
    the boring logs. Bright claims this was beyond the scope of work reflected in item
    57 and caused Bright to incur over $325,000 in expenses.
    On July 14, 2016, Bright’s senior estimator, Ken Swayze, e-mailed Pogue’s
    project manager, Landon Kids, requesting a meeting to discuss overages on the
    project. Swayze stated that Bright had “gone over roughly 35% on both haul off and
    select fill due to rock being deeper than indicated on borings.” After reviewing the
    plans and specifications, Kids determined that the work Bright performed was within
    its scope of work under the contract and a change order was not warranted. Pogue
    also claimed that a request for a change order was not timely because Bright
    discovered the alleged overage more than 21 days before it contacted Pogue. Bright
    –5–
    also never submitted an itemization of the additional expenses to support a request
    for a change order.
    On August 15, 2016, Bright made a claim for over $1.2 million on Pogue’s
    payment bond issued by Hartford. Bright later supplemented the claim to state that
    over $760,000 was due. On January 16, 2017, Bright filed this suit against Pogue
    and Hartford, asserting claims for breach of contract, quantum meruit, promissory
    estoppel, unjust enrichment, and payment under the payment bond. In addition to its
    answer raising affirmative defenses, Pogue filed a counterclaim to recover its
    attorney’s fees under the terms of the subcontract.
    Pogue subsequently filed a traditional and no-evidence motion for summary
    judgment on all of Bright’s claims. Among other grounds, Pogue stated that Bright
    had no evidence that Pogue breached the contract. The trial court granted the motion
    for partial summary judgment without specifying the grounds for its ruling. Pogue
    filed a motion for attorney’s fees with supporting affidavits. After a hearing on the
    motion, the trial court granted the motion and rendered a final judgment that Bright
    take nothing on its claims and that Pogue recover its attorney’s fees. This appeal
    followed.
    Standard of Review
    We review the trial court’s summary judgment de novo. Provident Life &
    Accident Ins. Co. v. Knott, 
    128 S.W.3d 211
    , 215 (Tex. 2003). A no-evidence motion
    for summary judgment under rule 166a(i) must challenge specific elements of the
    –6–
    opponent’s claim or defense on which the opponent will have the burden of proof at
    trial. TEX. R. CIV. P. 166a(i). The opponent must then present summary judgment
    evidence raising a genuine issue of material fact to support the challenged elements.
    Id. A party
    moving for traditional summary judgment has the burden to prove that
    there is no genuine issue of material fact and it is entitled to judgment as a matter of
    law. TEX. R. CIV. P. 166a(c); Mann Frankfort Stein & Lipp Advisors, Inc. v. Fielding,
    
    289 S.W.3d 844
    , 848 (Tex. 2009). If, as here, the trial court’s order does not state
    the grounds on which it granted summary judgment, we will affirm if any of the
    theories advanced by the summary judgment movant are meritorious. Pain Control
    Inst., Inc. v. GEICO Gen. Ins. Co., 
    447 S.W.3d 893
    , 897 (Tex. App.—Dallas 2014,
    no pet.). “When reviewing a summary judgment, we take as true all evidence
    favorable to the nonmovant, and we indulge every reasonable inference and resolve
    any doubts in the nonmovant’s favor.” Valence Operating Co. v. Dorsett, 
    164 S.W.3d 656
    , 661 (Tex. 2005).
    Discussion
    A.     Ambiguity
    In its first two issues, Bright argues the trial court erred by granting summary
    judgment because the subcontract is ambiguous regarding Bright’s scope of work.
    Specifically Bright contends the subcontract is ambiguous as to the depth to which
    Bright was obligated to excavate in exchange for the subcontract price of $945,000.
    –7–
    Determining whether a contract is ambiguous is a question of law. Coker v.
    Coker, 
    650 S.W.2d 391
    , 394 (Tex. 1983). Absent ambiguity, a contract is construed
    as a matter of law. Plains Expl. & Prod. Co. v. Torch Energy Advisors Inc., 
    473 S.W.3d 296
    , 305 (Tex. 2015). We must ascertain and give effect to the parties’
    intentions as expressed in the writing itself. Italian Cowboy Partners, Ltd. v.
    Prudential Ins. Co. of Am., 
    341 S.W.3d 323
    , 333 (Tex. 2011). In discerning the
    parties’ intent, “we must examine and consider the entire writing in an effort to
    harmonize and give effect to all the provisions of the contract so that none will be
    rendered meaningless.”
    Id. (quoting J.M.
    Davidson, Inc. v. Webster, 
    128 S.W.3d 223
    , 229 (Tex. 2003)) (internal quotation marks omitted). No single provision taken
    alone is given controlling effect; rather, each must be considered in the context of
    the instrument as a whole. Plains 
    Expl., 473 S.W.3d at 305
    . We also give words their
    plain, common, or generally accepted meaning unless the contract shows that the
    parties used words in a technical or different sense.
    Id. A contract
    is not ambiguous if the contract’s language can be given a certain
    or definite meaning. El Paso Field Servs., L.P. v. MasTec N. Am., Inc., 
    389 S.W.3d 802
    , 806 (Tex. 2012). But if the contract is subject to two or more reasonable
    interpretations after applying the pertinent construction principles, the contract is
    ambiguous, creating a fact issue regarding the parties’ intent.
    Id. Summary judgment
    is not the proper vehicle for resolving disputes about an ambiguous contract. Plains
    
    Expl., 473 S.W.3d at 305
    .
    –8–
    Extrinsic evidence of the parties’ intent is not admissible to create an
    ambiguity. David J. Sacks, P.C. v. Haden, 
    266 S.W.3d 447
    , 450 (Tex. 2008)
    (explaining that evidence outside the four corners of a contract cannot be used to
    create an ambiguity). However, the contract may be read in light of the
    circumstances surrounding its execution to determine whether an ambiguity exists.
    Plains 
    Expl., 473 S.W.3d at 305
    . The rule that extrinsic evidence in not admissible
    to create an ambiguity “‘obtains even to the extent of prohibiting proof of
    circumstances surrounding the transaction when the instrument involved, by its
    terms, plainly and clearly discloses the intention of the parties, or is so worded that
    it is not fairly susceptible of more than one legal meaning or construction.’” Sun Oil
    Co. v. Madeley, 
    626 S.W.2d 726
    , 732 (Tex. 1981) (quoting Lewis v. E. Tex. Fin. Co.,
    
    146 S.W.2d 977
    , 980 (Tex. 1941)). Mere disagreement over the interpretation of an
    agreement does not necessarily render the contract ambiguous. Plains 
    Expl., 473 S.W.3d at 305
    .
    Both parties agree that Bright was obligated to excavate to the top of tan
    limestone as verified by the geotechnical representative. According to Bright, the
    dispute is over the amount of money Bright would be paid for that work. Pogue
    contends Bright agreed to perform the scope of work, including excavating to the
    top of tan limestone as verified by the geotechnical representative, for a fixed price.
    A change order would only be warranted if Bright had been required to perform
    work beyond the defined scope of work.
    –9–
    Focusing solely on line item 57, Bright asserts the scope of work is
    ambiguous. Item 57 states, “Building Pad Subgrade preparation- overexcavation to
    limestone, prep for ½” movement per Geotechnical Report with select fill of
    flexbase.” Bright contends the phrase “per Geotechnical Report” limits Bright’s
    scope of work to excavating only to the depths of limestone shown in the boring logs
    and any additional excavation would be at an additional cost.
    Even though the specifications state the geotechnical report was provided for
    information only and the borings are not a warranty of subsurface conditions, the
    references in the subcontract to the report require an examination of its substance.
    The difficulty with Bright’s interpretation is that the geotechnical report does not
    support the contention that Bright was obligated to excavate only to the depths of
    limestone shown in the boring logs. The report states its recommendations were
    based on the information from widely spaced test borings depicting the “subsurface
    conditions only at the specific boring locations and at the particular time designated
    in the logs.” The geotechnical report specifically noted that subsurface conditions at
    other locations may differ from those observed at the boring locations and the scope
    of work may not fully define the variability of subsurface materials and conditions
    present on the site. And it warned that the nature and extent of variations between
    borings may not become evident until construction.
    –10–
    The report contains recommendations for improvements to obtain ½ inch and
    1 inch movement of the floor slab. The school district in this case selected the ½ inch
    movement option. The report states:
    6.2.1 Subgrade Improvement for ½ inch Movement
    Movement of the floor slab could be reduced to about ½ inch, by
    improving subsurface conditions to the top of tan shaly limestone
    encountered at depths ranging from 2 to 4 ft below existing grade in the
    building borings. Tan shaly limestone was not encountered in Borings
    9, 10, and 15, but it is believed to be close to the termination depth of 5
    ft below existing grade. Subsurface improvement can consist of over-
    excavating the existing clayey soils to the top of tan shaly limestone
    and backfilling with non-expansive material to achieve final grade.
    During construction, our office personnel should verify the top of tan
    shaly limestone. In choosing this method of slab movement reduction,
    the Owner is accepting some post construction seasonal movement of
    the floor slab (about ½ inch).
    This section indicates that limiting slab movement to ½ inch would require
    improving the subsurface conditions to the top of tan shaly limestone, which was
    encountered in some of the borings at depths of two to four feet below ground.
    However, three borings did not encounter tan limestone, though it is expected to be
    close to five feet below ground. The report explains that subsurface improvement
    means “over-excavating the existing clayey soils to the top of tan shaly limestone
    and backfilling with non-expansive material to achieve final grade.” It emphasizes
    that during construction, the engineer’s office should verify the top of tan limestone.
    Bright interprets the phrase “per Geotechnical Report” in line item 57 as
    limiting its scope of work to excavating to the depth of limestone shown in the boring
    –11–
    logs. Based on the language in the geotechnical report this is not reasonable.
    Although the report notes that tan limestone was encountered in some of the borings
    at relatively shallow depths, the recommendation for achieving ½ inch slab
    movement was to “over-excavate to the top of tan shaly limestone,” which should
    be verified by the geotechnical engineer during construction. Nothing in the report
    indicates that the contractor should excavate only to the depths of limestone shown
    in the boring logs. Indeed, three of the borings did not encounter limestone at all.
    Nor does the geotechnical report state that a contractor would be entitled to
    additional compensation for excavating beyond the depths of limestone shown in the
    boring logs.
    Looking beyond the geotechnical report, we consider the entire contract to
    determine the intent of the parties and whether the contract is ambiguous. Line item
    57 is one of 71 line items making up Exhibit A.1 to the subcontract. It does not
    expressly deal with the price Bright agreed to accept for its work. At the beginning
    of the subcontract, Bright agreed to provide all labor, material, equipment, services,
    and supplies required for a complete job of Earthwork in strict compliance with the
    project plans and specifications. Pogue agreed to pay Bright for described work and
    materials, and Bright agreed to accept, the sum of $945,000.00. Sheet S1.0 of the
    plans called for a bid to perform “any cut operations to expose the top of the shaly
    limestone strata” and instructed that the geotechnical engineer or a representative
    shall verify the top of limestone.
    –12–
    In exhibit A.1 to the subcontract, Bright agreed to provide all labor, material,
    equipment and supervision required to complete the Earthwork scope of work
    including but not limited to the items in section 31A. This included furnishing and
    installing all portions of the scope of work described in several specified sections of
    the specifications. Section 1.1.3 of the subcontract general provisions provides that
    the subcontractor’s work
    shall include the performing and furnishing by Subcontractor of all
    supervision, labor, materials, plant, scaffolding, hoisting, tools,
    equipment, supplies, and all other things necessary for the construction
    and completion of the Work, as described in its Subcontract, and all
    Work incidental thereto or reasonably inferable therefrom, in strict
    accordance and in full compliance with the terms of the Contract
    Documents.
    Thus, Bright agreed to provide all work necessary to perform the work
    described, which Bright concedes included excavating to the actual, not estimated,
    top of tan limestone, for the contract price. Bright presented no evidence that the
    Earthwork scope of work in the plans and specifications referenced in the
    subcontract was limited to excavation to depths shown only in the boring logs.
    Bright’s interpretation that line item 57 limited its scope of work to excavating to
    the depths indicated in the boring logs is inconsistent with the remainder of the
    subcontract.
    Further, the subcontract provides that it is the entire integrated agreement
    between the parties and supersedes all prior negotiations, representations, or
    agreements. This clause precludes any agreement prior to the subcontract, such as
    –13–
    an agreement that the “per geotechnical report” language in line item 57 actually
    meant Bright would be entitled to additional compensation if it excavated beyond
    the depths shown in boring logs.
    Bright also contends the risk of unknown subsurface conditions was placed
    on the contractor or owner, but the express language of the contract and subcontract
    belie this contention. In its subcontract, Bright agreed that it “assume[d] all
    obligations, risks and responsibilities to Contractor which Contractor has assumed
    toward the Owner.” Section 00 31 32 of the specifications states that:
    1.04 RESPONSIBILITY
    A. Bidders are expected to examine the site and subsurface
    investigation reports and then decide for themselves the character of the
    materials to be encountered.
    B. The Owner and Architect assume no responsibility for variations of
    subsoil quality or conditions.
    C. The Owner and the Architect assume no responsibility for any
    conclusions or interpretations made on the basis of subsurface
    information contained in the contract documents.
    Thus, Bright, not Pogue or the school district, assumed the risk of the conclusions
    and interpretations Bright made based on the subsurface information contained in
    the geotechnical report.
    In addition, Bright acknowledged that the subcontract and the contract
    documents were adequate and sufficient to provide for the performance and
    completion of the work and included “all Work, whether or not specified, which
    reasonably may be inferred to be required for the completion of the Work in
    –14–
    accordance with all applicable laws, codes and professional standards.” The risk that
    the top of limestone was deeper than indicated in boring logs fell on Bright because
    the scope of work under the subcontract included excavating to the top of limestone.
    Reviewing the contract as a whole, we conclude Bright’s interpretation of the
    subcontract is not reasonable and the contract is not ambiguous. See Columbia Gas
    Transmission Corp. v. New Ulm Gas, Ltd., 
    940 S.W.2d 587
    , 589 (Tex. 1996) (“For
    an ambiguity to exist, both interpretations must be reasonable.”). We overrule
    Bright’s first and second issues. Because Bright was not entitled to additional
    payment, we need not address issues three and four regarding waiver or excuse for
    Bright’s failure to timely submit a change order. TEX. R. APP. P. 47.1.
    B.     Alternative claims
    Because we conclude there is no evidence that Pogue breached the subcontract
    and the subcontract includes the subject matter, summary judgment was proper on
    Bright’s alternative claims of quantum meruit, promissory estoppel, and on the
    payment bond. See Vortt Exploration Co. v. Chevron U.S.A., Inc., 
    787 S.W.2d 942
    ,
    944 (Tex. 1990) (quantum meruit applies only when no express contract covers the
    subject matter); Guar. Bank v. Lone Star Life Ins. Co., 
    568 S.W.2d 431
    , 434 (Tex.
    Civ. App.—Dallas 1978, writ ref’d n.r.e.) (promissory estoppel not applicable if
    promise is part of valid contract); Dealers Elec. Supply Co. v. Scroggins Const. Co.,
    Inc., 
    292 S.W.3d 650
    , 653 (Tex. 2009) (noting payment-bond beneficiary who has
    not been paid may sue principal or surety, jointly or severally, on payment bond).
    –15–
    We overrule Bright’s fifth, sixth, and seventh issues.
    Conclusion
    We conclude the contract is not ambiguous and there is no evidence Pogue
    breached the contract. Accordingly, the trial court did not err by granting summary
    judgment on Bright’s causes of action. We affirm the trial court’s judgment.
    /Erin A. Nowell/
    ERIN A. NOWELL
    JUSTICE
    180820F.P05
    –16–
    Court of Appeals
    Fifth District of Texas at Dallas
    JUDGMENT
    BRIGHT EXCAVATION, INC.,                       On Appeal from the 191st Judicial
    Appellant                                      District Court, Dallas County, Texas
    Trial Court Cause No. DC-17-00591.
    No. 05-18-00820-CV           V.                Opinion delivered by Justice Nowell.
    Justices Myers and Osborne
    POGUE CONSTRUCTION CO., LP                     participating.
    AND HARTFORD FIRE
    INSURANCE CO., Appellees
    In accordance with this Court’s opinion of this date, the judgment of the trial
    court is AFFIRMED.
    It is ORDERED that appellees Pogue Construction Co., LP and Hartford
    Fire Insurance Co. recover their costs of this appeal from appellant Bright
    Excavation, Inc.
    Judgment entered this 21st day of April, 2020.
    –17–