Kingwood Commercial Properties, LLC v. Nova Consulting Group, Inc. ( 2020 )


Menu:
  •                                        In The
    Court of Appeals
    Ninth District of Texas at Beaumont
    __________________
    NO. 09-18-00321-CV
    __________________
    KINGWOOD COMMERCIAL PROPERTIES, LLC, Appellant
    V.
    NOVA CONSULTING GROUP, INC., Appellee
    __________________________________________________________________
    On Appeal from the 410th District Court
    Montgomery County, Texas
    Trial Cause No. 18-02-01397-CV
    __________________________________________________________________
    MEMORANDUM OPINION
    In this appeal, Kingwood Commercial Properties, LLC argues the trial court
    erred when it granted Nova Consulting Group, Inc.’s motion for summary judgment,
    which hinged on Nova’s claim that Kingwood’s claims were barred by the statute of
    limitations. We hold the trial court did not err by granting the motion, so we affirm.
    1
    Background
    We limit our background discussion to the facts relevant to the dispositive
    issue in Kingwood’s appeal. Here, the parties do not dispute that Kingwood bought
    two buildings from Colonnade Royal Forest Group, L.P. in September 2015. To
    finance the purchase, Kingwood’s lender obtained an environmental, property
    condition, and engineering assessment from Nova regarding the property Kingwood
    wanted to purchase.
    In July 2015, Nova provided Kingwood’s lender with its report. Nova’s report
    represents the building’s roofs are in “Good” condition. The report also states that
    “Nova does not anticipate the need for significant roof replacement during the [next
    twelve years].” When the transaction to purchase the property closed, Kingwood
    reimbursed its lender for the expense Kingwood’s lender incurred from hiring Nova
    to issue the report. Also, Kingwood alleged in its petition that it was an intended
    third-party beneficiary of Nova’s report.1
    On January 30, 2018, Kingwood sued Nova, alleging Kingwood relied on
    Nova’s findings when purchasing the property at issue. Less than three months after
    1Nova’s motion for summary judgment disputes Kingwood’s      claim that it was
    an intended beneficiary of its report. And Nova’s motion argued that Kingwood
    could not sue it for negligence on a breach of contract claim. We need not address
    these questions given our resolution of the statute of limitations defense, as
    Kingwood filed only a negligence claim.
    2
    the purchase, according to Nova’s petition, the property “sustained substantial water
    damage from water penetrating the roof.” Kingwood’s petition also alleges Nova
    acted negligently by failing to properly assess the condition of the roofs at the facility
    that it purchased, and Nova’s acts and omissions in reporting the condition of the
    property caused the damages Kingwood was seeking to recover in its suit.
    In response to the suit, Nova moved for summary judgment. In part, Nova’s
    motion argues the statute of limitations barred Kingwood’s negligence claim.2
    Kingwood responded, and it supported the response it filed with three exhibits: (1)
    an affidavit by Greg Huff, its managing member; (2) a loan closure statement on the
    property, dated September 16, 2015; and (3) a letter Kingwood’s attorney sent to
    Nova to inform it that Kingwood had relied on Nova’s report about the condition of
    the roofs when it purchased the property. According to the affidavit Huff filed, in
    late January 2016, he reviewed Nova’s inspection report but had not done so earlier
    because he “had been so consumed with learning the realities of owning and
    operating commercial real estate property (for the first time) and fixing the water
    damage, that [he] did not think about referring back to the initial . . . report.” Huff
    2Nova’s  motion also argues it owes no legal duty to Kingwood based on
    Nova’s common law negligence claim. It also argues that Kingwood is not a third-
    party beneficiary of the contract Nova signed with Kingwood’s lender.
    3
    then states that in February 2017, he contacted an attorney, who sent Nova a
    “demand letter” and after that, Kingwood filed suit.
    In July 2018, the trial court granted Nova’s motion for summary judgment.
    The trial court did not provide the parties with any written findings to explain its
    ruling. 3 The order the trial court signed states “the Defendant’s Motion for Summary
    Judgment is GRANTED as to the negligence claim asserted by Plaintiff which [is]
    the sole cause of action asserted by Plaintiff such that this Order disposes of all
    claims herein asserted.” After the trial court signed the final judgment, Kingwood
    moved for a new trial. But the trial court denied that motion.
    Kingwood pursed an appeal from the trial court’s ruling. According to
    Kingwood’s brief, the trial court erred in granting Nova’s motion because
    Kingwood’s cause of action did not accrue until February 2016, the date Huff first
    realized Kingwood had a “potential cause of action against [Nova].” 4
    3  Kingwood has not complained about the trial court’s inaction on its request
    for findings in its brief. That said, “a request for findings and conclusions following
    summary judgment can have no purpose, should not be filed, and if filed, should be
    ignored by the trial court[.]” IKB Indus. (Nigeria) Ltd. v. Pro-Line Corp., 
    938 S.W.2d 440
    , 441-42 (Tex. 1997).
    4 Kingwood does not argue that the four-year statute of limitations, which
    applies to contract actions, applies to its claim.
    4
    Standard of Review
    Appellate courts review rulings granting summary judgments under a de novo
    standard. To apply that standard, we review the appellate record “in the light most
    favorable to the nonmovant, indulging every reasonable inference and resolving any
    doubts against the motion.”5 When a trial court does not specify the grounds it relied
    on to grant the motion, we will affirm the ruling if any of the grounds asserted in the
    motion have merit.6
    To prevail on a motion for summary judgment, Nova had the burden to either
    conclusively negate at least one element of Kingwood’s negligence claim or to
    establish it had a right to prevail on an affirmative defense as a matter of law. 7 Once
    Nova did so, the trial court was required to grant the motion unless Kingwood
    produced enough evidence to defeat the grounds for summary judgment that Nova
    raised in its motion, including its claim that the statute of limitations barred
    Kingwood’s claims. 8
    5 City of Keller v. Wilson, 
    168 S.W.3d 802
    , 824 (Tex. 2005).
    6 See Lightning Oil Co. v. Anadarko E&P Onshore, LLC, 
    520 S.W.3d 39
    , 45
    (Tex. 2017).
    7 Tex. R. Civ. P. 166a(c); KCM Fin. LLC v. Bradshaw, 
    457 S.W.3d 70
    , 79
    (Tex. 2015); Provident Life and Acc. Ins. Co. v. Knott, 
    128 S.W.3d 211
    , 215-16
    (Tex. 2003).
    8 See Lujan v. Navistar, Inc., 
    555 S.W.3d 79
    , 84 (Tex. 2018).
    5
    Analysis
    Nova’s motion raises two grounds for summary judgment. One asserts the
    two-year statute of limitations bars Kingwood’s claim alleging Nova committed acts
    or omissions that raise a fact issue showing it was negligent. The second asserts
    Nova owed Kingwood no legal duties because Nova is not a third-party beneficiary
    of the contract between Nova and Kingwood’s lender. We need to address the issue
    challenging the trial court’s ruling that limitation bars Kingwood’s claims first
    because it is dispositive of Kingwood’s appeal. 9
    Based on the arguments in the motions, we imply the trial court applied the
    two-year statute of limitations to bar Kingwood’s claims.10 Here, Kingwood has not
    argued that some other limitations period applies to its claims. Thus, to show it was
    entitled to summary judgment based on the two-year limitations period argued in the
    motion for summary judgment and response, Nova had to conclusively prove
    Kingwood’s claims arose more than two years before Kingwood filed suit. 11 Also,
    9  See Tex. R. App. P. 47.1; Lightning Oil 
    Co., 520 S.W.3d at 45
    .
    10 See Tex. Civ. Prac. & Rem. Code Ann. § 16.003(a) (providing the statute
    of limitations for negligence is two years).
    11 Schlumberger Tech. Corp. v. Pasko, 
    544 S.W.3d 830
    , 833-34 (Tex. 2018)
    (“A defendant moving for summary judgment on the affirmative defense of
    limitations bears the burden of conclusively establishing the elements of that
    defense. This includes conclusively establishing when the cause of action accrued.”)
    (cleaned up).
    6
    since Kingwood alleged the discovery rule applied to its claims, Nova had to
    establish either that (1) the discovery rule did not apply, or that if it applied, (2) the
    summary judgment evidence established Kingwood should have, acting reasonably,
    discovered or actually discovered the roof was in a condition that required repairs
    more than two years before Kingwood sued.12
    We will assume (without deciding) the discovery rule applies to Kingwood’s
    claim. In its brief, Nova argues Kingwood’s claim accrued no later than December
    2015. Kingwood’s evidence shows that by November 2015, the roofing company it
    hired told Kingwood the roof needed repairs and by December 2015, Kingwood
    began repairing the roof. The record shows Kingwood waited for more than two
    years after commencing the repairs to the damage caused by water penetrating its
    building’s roof to file suit. In its brief, Kingwood does not dispute that in December
    2015, it knew the roof needed repairs; instead, Kingwood suggests it did not discover
    it could sue Nova until February 2016, the date Kingwood’s attorney informed
    Kingwood, through Huff, that Kingwood had a claim.
    First, we must decide when Kingwood’s claim accrued. Ordinarily, causes of
    action accrue when someone suffers a legal injury. 13 Thus, a cause of action accrues
    12   See
    id. at 834.
          13
    Id. 7 when
    “a wrongful act causes a legal injury, even if the fact of injury is not discovered
    until later, and even if all resulting damages have not yet occurred.”14 Even so, there
    are exceptions to the legal injury rule. The discovery rule is the exception Kingwood
    relies on; but it delays the accrual date on a claim only until the injured party knew
    or in the exercise of reasonable diligence should have known that a wrongful act
    injuring it had occurred.
    Even more, the discovery rule is a “very limited exception to statutes of
    limitations[.]”15 It is available only “when the nature of the plaintiff’s injury is both
    inherently undiscoverable and objectively verifiable.” 16 And even when the
    discovery rule applies, the date a claim accrues “does not linger until a claimant
    learns of actual causes and possible cures.” 17 Instead, “[o]nce a claimant learns of a
    wrongful injury, the statute of limitations begins to run even if the claimant does not
    yet know the specific cause of the injury; the party responsible for it; the full extent
    of it; or the chances of avoiding it.” 18
    14Id. (cleaned up).
    15 Wagner & Brown, Ltd. v. Horwood, 
    58 S.W.3d 732
    , 734 (Tex. 2001)
    (cleaned up).
    16
    Id. 17 PPG
    Indus., Inc. v. JMB/Houston Ctrs. Partners Ltd. P’ship, 
    146 S.W.3d 79
    , 93 (Tex. 2004).
    18 Exxon Corp. v. Emerald Oil & Gas Co., L.C., 
    348 S.W.3d 194
    , 207 (Tex.
    2011) (cleaned up).
    8
    The summary judgment evidence shows Kingwood’s claim for negligence
    accrued more than two years from the date it sued. For instance, Kingwood attached
    a certificate of merit to the original petition it used to launch the suit. The certificate
    of merit, signed by Javier Godoy (an engineer) states water entered Kingwood’s
    building on October 30, 2015, which required Kingwood to repair severe damage to
    sections of the roof. Huff’s affidavit reflects Kingwood obtained a quote to repair
    the property in November 2015 and the repairs began that December. Thus, the
    evidence shows Kingwood learned more than two years before it sued that water had
    penetrated its building’s roof and the roof needed repairs.
    Kingwood argues Huff’s affidavit raises a fact issue about the date it first
    learned it had a legal claim. But in cases to which the discovery rule applies, a cause
    of action accrues, under Texas law, when the fact of the injury is known, not when
    the plaintiff first learns who is responsible for causing the injury. After all, the statute
    of limitations on negligence claims allows the injured party two years from the date
    it learns of the injury to figure out who to sue. 19
    We express no opinion about whether the discovery rule applies to this case.
    But even if and assuming that it does, Kingwood’s pleadings and the summary
    judgment evidence shows Kingwood was aware the roof to its building had been
    19   See Tex. Civ. Prac. & Rem. Code Ann. § 16.003(a).
    9
    damaged more than two years before it sued. 20 Here, the evidence shows Kingwood
    knew Nova provided a report about the property’s condition and knew of its injury
    more than two years before it sued Nova. We hold the trial court had no choice but
    to grant Nova’s motion based on Nova’s statute of limitations defense. 21
    Conclusion
    Because Nova established that Kingwood’s claims accrued more than two
    years before Kingwood sued, we hold the statute of limitations bars Kingwood’s
    claim for negligence. Given that conclusion, we need not address Kingwood’s other
    argument, which suggests it is a third-party beneficiary of the contract between Nova
    and Kingwood’s lender since Kingwood did not file any claims alleging Nova was
    liable to it based on any claims sounding in contract.22 For these reasons, the trial
    court’s judgment is
    AFFIRMED.
    20 See Emerald 
    Oil, 348 S.W.3d at 207
    (“Once a claimant learns of a wrongful
    injury, the statute of limitations begins to run even if the claimant does not yet know
    the specific cause of the injury; the party responsible for it; the full extent of it; or
    the chances of avoiding it.”) (cleaned up);
    id. at 209
    (“Knowledge of injury initiates
    the accrual of the cause of action and triggers the putative claimant’s duty to exercise
    reasonable diligence to investigate the problem, even if the claimant does not know
    the specific cause of the injury or the full extent of it.”) (cleaned up).
    21 See
    id. 22 See
    Tex. R. App. P. 47.1.
    10
    _________________________
    HOLLIS HORTON
    Justice
    Submitted on January 28, 2020
    Opinion Delivered April 30, 2020
    Before McKeithen, C.J., Kreger and Horton, JJ.
    11