International Paper Company v. Signature Industrial Services, LLC and Jeffry M. Ogden ( 2020 )


Menu:
  •                           NUMBER 13-18-00186-CV
    COURT OF APPEALS
    THIRTEENTH DISTRICT OF TEXAS
    CORPUS CHRISTI - EDINBURG
    INTERNATIONAL PAPER COMPANY,                                                    Appellant,
    v.
    SIGNATURE INDUSTRIAL SERVICES, LLC
    AND JEFFRY M. OGDEN,                                                           Appellees.
    On appeal from the 60th District Court
    of Jefferson County, Texas.
    MEMORANDUM OPINION
    Before Chief Justice Contreras and Justices Benavides and Perkes
    Memorandum Opinion by Justice Benavides
    By eleven issues, appellant International Paper Company (IP) challenges the jury’s
    verdict awarding damages to appellees Signature Industrial Services, LLC (Signature)
    and Jeffry Ogden. IP’s first five issues challenge Signature’s claims and allege: (1-3)
    Signature failed to present legally sufficient evidence for its breach-of-contract, fraud, and
    promissory estoppel claims; (4) legally insufficient evidence supports Signature’s
    consequential damages award; and (5) a new trial should be granted because the jury
    awarded excessive actual damages to Signature. IP’s next three issues relate to Ogden’s
    claims and allege: (6) judgment should be rendered for IP on Ogden’s breach-of-contract
    claim because Ogden was neither a party to nor a third-party beneficiary to the contract
    between Signature and IP; (7) the evidence is legally or factually insufficient to support
    Ogden’s fraud claim; and (8) Ogden’s claim for mental anguish damages is not supported
    by legally sufficient evidence or in the alternative, a new trial should be granted on mental
    anguish damages because the award was excessive. In its ninth issue, IP asserts that a
    new trial is warranted in relation to both Signature and Ogden’s claims because the trial
    court erred in excluding the testimony of IP’s key expert. Issues ten and eleven relate to
    IP’s counterclaims and allege that: (10) judgment should be rendered in favor of IP and
    against Signature for IP’s costs incurred defending against Ogden’s claims; and (11)
    Signature should indemnify IP in the event that any portion of the judgment in favor of
    Ogden, and against IP, survives. We affirm in part and reverse and render in part.
    I.       BACKGROUND1
    The claims in this dispute involve a contract between Signature and IP to build a
    slaker for IP’s Orange, Texas paper mill in March 2014. IP asked Signature to assemble
    and install a new slaker, a large vessel that recycles certain chemicals used in the
    papermaking process, during the annual outage shutdown of the mill. IP initially
    approached Signature and other companies and asked them to bid on the slaker project;
    1 This case is before this Court on transfer from the Ninth Court of Appeals in Beaumont pursuant
    to a docket equalization order issued by the Supreme Court of Texas. See TEX. GOV’T CODE ANN. § 73.001.
    2
    however, Signature was the only company who executed a bid due to the state of IP’s bid
    package. The initial bid package lacked drawings and necessary documents, although
    seven addendums were later issued by IP. It was debated at trial if the addendums
    provided enough detail for Signature to make a complete bid. Nonetheless, Signature
    made a bid in the amount of $775,464.30 for the slaker project. It was also agreed that
    work that was not contained in the bid package could be paid through field charge orders
    (FCOs) that were mutually agreed to in writing and approved prior to work commencing.
    Signature began work on the slaker project in February 2014 and work was
    completed around early May 2014. The project was fraught with delays, which Signature
    attributed to IP. Soon after commencing the project, IP approved and paid FCOs
    submitted by Signature. During the course of the slaker project, IP representatives told
    Signature’s representatives that instead of submitting each FCO for approval prior to
    executing the work, verbal approval would be sufficient and Signature could just submit
    one large FCO upon completion of the project. The modification to the FCO procedure
    and what was required for payment is the crux of the lawsuit.
    Signature submitted multiple FCOs as the project wrapped up, and IP refused to
    pay the invoices submitted because the amounts far exceeded what IP had expected. IP
    claimed that Signature’s FCOs lacked the appropriate backup documentation needed to
    justify the amounts invoiced. After the project was completed in May 2014, IP and
    Signature held two meetings between their representatives to try to resolve the unpaid
    invoices. Neither meeting was successful and in August 2014, Signature filed this suit
    alleging fraud, breach of contract, and promissory estoppel. Signature claimed it had
    3
    seventeen unpaid invoices that IP refused to pay: ten relating to the slaker contract and
    seven related to other non-slaker projects.
    Ogden, Signature’s president, intervened in the lawsuit and alleged personal
    claims of fraud and breach of contract against IP based on the slaker contract. Ogden
    alleged he suffered actual damages because Signature was penalized for failing to pay
    its employees’ withheld payroll taxes2 to the Internal Revenue Service (IRS). According
    to Ogden, Signature used its employee trust funds to operate its business due to IP’s
    non-payment of invoices. Ogden alleged he became personally liable for those amounts
    and the IRS penalties on Signature. He also requested damages for mental anguish and
    damage to his credit reputation.
    A.      Signature’s Case-in-Chief
    1.      Claude Wilhelm
    Claude Wilhelm, Signature’s senior vice president, was Signature’s first witness at
    trial. Wilhelm testified that he had worked and developed relationships at the Orange mill
    before IP bought it and that Signature had worked many projects for IP at the mill, both
    before and during the slaker project. Wilhelm explained that the other partners in
    Signature wanted to turn down the slaker project initially because the bid documents were
    “inadequate.” He identified the different players involved in the slaker project: Steve
    Clayton, who was Signature’s project manager; Eddie Edwards, IP’s project manager;
    Ray Langley, IP’s construction manager; Greg Bennett, IP’s subsequent construction
    2 Payroll taxes are withholdings from an employee’s paycheck that are held in a trust account for
    the United States government and paid to the IRS. Signature had used its employees’ withheld payroll
    taxes for the business’s operating costs and was penalized by the IRS for doing so by the time of trial.
    4
    manager; Spencer Shawhan, IP’s engineering manager and Edwards’s supervisor; and
    Blake Spurlock, Signature’s subsequent project manager.
    Wilhelm explained that the bid for $775,464.30 was for the “knowns” on the slaker
    project and that Edwards had stated that changes required from the bid could be handled
    with FCOs. Wilhelm stated that the bid did not include piping, another source of contention
    between the parties. Signature was wary of submitting a bid initially because as Wilhelm
    said, “everything was off,” from labor to material, due to the vagueness of the documents
    submitted in the bid package. However, IP was on a tight timeline to get the project done
    during the shutdown and asked Signature to start before the contract was officially signed.
    There were issues from the outset3: the slaker was not clean as promised when Signature
    arrived and the cleaning caused delays, the drawings had engineering defects that had
    to be fixed, and a green liquor4 caustic liquid spill had occurred during the project and
    needed to be cleaned up before work could continue.
    According to Wilhelm, midway through the project, IP told Signature that the FCOs
    were coming in “too fast,” so Signature could just “capture it on a big field change order
    at the end.” Wilhelm stated there were e-mails documenting the change in procedure but
    Signature did not get the change modified in a contract. Additionally, there were constant
    changes in personnel. Wilhelm talked about a phone call he received following the green
    liquor spill stating that Clayton was now not allowed at the plant. When he arrived at the
    3 Wilhelm explained that the “knowns” bid included 6,100 man-hours of labor, but it took over
    16,000 man-hours to get the slaker project completed due to all the delays and changes that occurred.
    4
    Based on a general description at trial, the green liquor is a highly caustic liquid used in the
    papermaking process that could seriously burn and injure a person if they come into contact with it.
    5
    plant to determine what was happening, Signature’s documents regarding job details and
    records were missing from the trailer it had on IP’s property. Wilhelm confronted Shawhan
    and Bennett about the missing files, but neither claimed to know anything about the
    documents. Wilhelm explained that Signature was forced to recreate the missing
    documents in order to support the outstanding invoices. Wilhelm tried to explain how
    Signature developed the invoices and if certain invoices appeared to have labor that was
    duplicated, it was not billed twice.
    Signature’s counsel questioned Wilhelm about specific invoices, and he stated that
    one of the later invoices included a penalty of $350,000, including interest, because there
    was no cash flow coming into Signature and it had liens and payroll taxes that were
    becoming delinquent. He stated that the actual labor costs were $783,756, but that did
    not include other items from the contract such as rental equipment, materials, third-party
    labor, and company-owned equipment. When everything was included, Wilhelm told the
    jury that Signature was owed closer to $2.4 million dollars. He stated that Signature
    continued working because it relied on IP’s representation it could submit one final FCO
    invoice and it would be paid. Wilhelm admitted Signature struggled to recreate the backup
    documentation because of its missing documents and the fact that IP’s gate log system
    was not accurate.5 He explained to the jury that some of the invoices grouped types of
    workers and billed for the group, instead of by each individual worker, and that is why
    some invoices showed large amounts of hours. However, Wilhelm did agree that, prior to
    the change in procedure on submission of FCOs, Signature did not have any issues
    5
    Throughout the trial, IP argued that it used the gate logs to keep track of the workers’ time and to
    verify the invoices.
    6
    getting the invoices paid. Wilhelm told the jury that Signature lost work with Valero due to
    the vendor liens and financial issues that occurred because of the nonpayment on the
    slaker project. Wilhelm also told the jury about the proposed sale of Signature to Primoris.
    In May 2014, Primoris made an offer of $42 million to buy Signature. At the end of 2013,
    however, Signature was “upside down,” meaning it was spending more than it was
    earning. Signature ultimately turned down Primoris’s offer.
    On Ogden’s cross-examination, Wilhelm testified that Ogden is a personal signer
    and the active individual on the bank agreements Signature had, because he backed
    everything on a personal level. Wilhelm agreed that the other owners of Signature
    assigned Ogden their rights to sue for personal damages as it related to this contract with
    IP. Wilhelm explained that if he received information from IP, he would have told Ogden
    the same information, including the e-mail chain that acknowledged the changes to the
    FCO submission procedure.
    IP’s cross-examination of Wilhelm centered around the disputed invoices. Wilhelm
    would not agree with IP that the invoices contained errors, even though in his earlier
    deposition, he admitted the invoices contained different mark-up percentages than were
    agreed to in the slaker contract. He told IP that he believed the invoices should have been
    paid in full even if overbilling was included, suggesting that IP could “short pay”6 what
    was overbilled. Wilhelm argued that although some of the drawings included piping,
    Edwards knew Signature’s bid would not include piping and accepted that. Wilhelm stated
    6 “Short pay” is a concept the parties described where a company would pay an agreed upon
    portion of the disputed bill and try to negotiate the remaining amount before paying it.
    7
    he was asking the jury to award money based off of the field time sheets that documented
    the daily work, and he believed the unpaid amount owed according to those time sheets
    was $1.1 million dollars. He explained that, during the meeting in July 2014 between IP
    and Signature, Shawhan offered to pay around $200,000 to $300,000 of the $1.1 million
    owed, but Signature refused to accept that amount. Wilhelm admitted that after Signature
    filed its lawsuit, he went back through and billed for any unbilled time. Although he earlier
    testified that the disputed invoices reflected $1.1 million in owed funds, after the lawsuit
    was filed, Wilhelm revised that figure and estimated that Signature was owed $2.4
    million.7 He also said that the tax implications were between $5 million to $6 million and
    discussed losing the sale of Signature to Primoris for $42 million.
    2.      Eddie Edwards
    Edwards testified that he worked for Ford, Bacon, and Davis (FBD), an engineering
    firm that has a standing contract with IP in Orange and worked on projects for IP on an
    “as-needed” basis. Edwards explained that he was considered an IP representative, used
    IP’s e-mail server, and reported directly to Shawhan, and that FBD was the contracting
    firm.
    His position meant he had total responsibility for getting the slaker project prepared
    and constructed. Edwards stated when he first got involved in the project, there was no
    engineering package, and only enough information to generate a basic estimate. Towards
    the end of 2013, as the project manager, he was not getting the engineering drawings
    and details from FBD that he needed to put the project together. Edwards advised IP that
    7  However, during his testimony, Wilhelm stated that Signature was owed $2.1 million, but got paid
    $1.1 million by IP (two payments of $775,000 and $225,000).
    8
    he was unsure if they should do the slaker project during the shutdown because of the
    lack of documents he wanted, but his expressed sentiment was considered unacceptable
    by IP, who wanted to continue with the project. IP wanted the slaker replaced because it
    was ineffective, in poor condition, and hampering production at the mill.
    Edwards took the bid package to multiple contractors, but the others could not do
    the project. He went back to Signature after the others turned the slaker project down and
    asked if there was any way it could do the project. Edwards agreed that the plans he
    presented were preliminary and more for “information only” and did not believe that
    Signature’s bid of $775,000 included piping. Signature’s bid was for the “knowns” and
    when drawings changed and were more accurate, then an FCO would be done. Edwards
    explained that the $775,000 bid was a Time & Materials (T & M) “not to exceed” contract,
    which meant that the company is paid for the work up to a maximum of $775,000, but any
    work over the bid amount for “knowns” would not be paid by IP.
    Edwards stated he had great faith in Signature as a company, that they did quality
    work and had excellent craftspeople, and he was satisfied with the work Justin Hall,
    Signature’s construction coordinator, did on the FCOs. When Edwards walked into the
    Orange mill on the date of the scheduled shutdown, the slaker was still in operation. The
    slaker was not shut down for another two days, and then Signature needed to clean it in
    order to begin the project. Edwards agreed that things at the jobsite were chaotic but felt
    they were under control. He pushed for FBD to provide “better” drawings, helped draw up
    the FCOs, assisted in getting them approved by IP’s managers, but conceded that
    sometimes he had issues getting the FCOs signed. Edwards testified that the FCOs
    9
    started “building up” because there were multiple issues that needed to be fixed, until
    Shawhan finally told him to “just get the work done and we’ll worry about it later.” Edwards
    notified the Signature people of the change to the FCO procedure by e-mail.
    During the project, Shawhan terminated Langley due to a supposed “safety issue”
    and assigned Bennett to replace him. Edwards received an e-mail from Bennett saying
    the FCOs would “go forward on verbal approval,” explaining that any procedure change
    should have gone through him, as he was higher on the “chain of command.” When
    Edwards spoke to Shawhan regarding the change in procedure, Shawhan supported
    Bennett, and Edwards felt his job authority had been “reduced to zero.” Later in the
    project, Edwards had pre-planned days he had requested off to visit his child, but
    Shawhan told him that since the project was behind, if he took the days off, he should not
    return to the mill.
    On cross-examination, Edwards thought that based on the bid package, he would
    have expected $100,000 to $200,000 worth of changes, but it was a particularly
    challenging project. Edwards explained that he dealt with the first four FCOs and asked
    Hall for clarification if it was needed. He also said that when Signature was told to hold
    the FCOs until the end, Edwards never told Signature that they would not need to “prove”
    their charges with the appropriate backup documentation; he would have expected the
    same quality of proof he received in the beginning.
    3.      Ray Langley
    Langley worked for IP and was asked to come on as a construction manager for
    the shutdown but was later given the slaker project. He stated that he felt IP’s bid package
    10
    for the slaker project was “middle of the road”: enough to determine the basics, but not
    enough to put finishing touches on the bid or determine the final dollar amount. He agreed
    that Signature was being asked to bid the “knowns” with a good deal of “unknowns” to
    come. Langley and Edwards contacted Signature, asking them to bid on the project and
    “bail them out” because no one else had bid on the project. Langley thought the project
    was poorly planned, but Troy Waddell, the production manager over the pulp mill area,
    which includes the slaker, said he would accept nothing less than being finished on
    schedule.
    Langley told the jury that the team on the slaker project was Edwards, Clayton,
    and himself. He thought highly of Edwards, stating he was one of the best he had worked
    with. Langley said Clayton was extremely safety-minded, held multiple weekly safety
    meetings, and was a perfectionist in his bookkeeping and data. Langley did not feel that
    Shawhan and Bennett were a “part” of the team; instead he felt they were problematic for
    the project. He explained that e-mails were a big part of the communication method and,
    although Edwards copied Shawhan on almost every e-mail so that he would know what
    was going on, Shawhan rarely responded to e-mails and frequently said he did not know
    information even when he was copied on the e-mails.
    Langley testified that he was fired because he supposedly allowed a load to be
    lifted over some men who were working, which is a safety violation. He stated that the
    normal procedure was to shut down the area and move people away so that the load
    could be lifted safely. He also said that, generally, when a dangerous situation occurred,
    IP would conduct a “safety stand-down,” where it held a meeting to explain the problem
    11
    and how to prevent the issue from happening, as well as require a report to be filled out,
    even if the situation was a “near-miss.” Langley told the jury that no documents regarding
    this “safety” violation were found, and he believed the incident was “made up.” He stated
    Shawhan simply told him that “things weren’t working out” and let him go. Langley relayed
    that there were multiple times during the project where Signature would be asked to
    perform work that was authorized by Edwards and himself, but Shawhan would refuse to
    approve the FCOs and pay for the work. Langley disagreed with Shawhan because
    Langley stated that he had asked Signature to perform the work in question. Once
    Shawhan terminated him, when he returned to collect his belongings in his office, his
    computer and field journal were gone.
    Langley also stated that Bennett had a bad opinion of Signature, stating that they
    would bid low and then want to do FCOs on everything; Langley disagreed. In his
    experience, he felt that Signature only requested FCOs on things that “needed to be
    done.” He stated that he never heard anyone else at IP express a bad opinion of
    Signature.
    On cross-examination, Langley agreed that although Shawhan complained about
    the FCOs and said he would not approve them, he would eventually change his mind and
    sign his approval on the FCOs. He also stated that Shawhan was a good engineer but
    not a good “people person.” Langley explained that the FCOs that he turned in for
    payment were properly documented, but he does not know about the FCOs and invoices
    that were submitted after he was terminated. He testified that he left the project before
    Edwards and Clayton did.
    12
    4.     Greg Bennett
    Bennett testified that Shawhan asked him to come work on the slaker project.
    When he arrived in the area, he noticed some unsafe work conditions were present.
    Bennett said he was not present when the green liquor spill occurred but looked into IP’s
    “lockout/tagout” procedures the next day, and he determined that IP’s operations had
    “messed up” the procedure. Bennett agreed that it was IP’s operations’ responsibility to
    prevent incidents like the green liquor spill from occurring. He stated that when he came
    onto the project, he started correcting safety issues, but had never been involved in a
    slaker installation before. Bennett also said he did not talk to Langley, did not know how
    far along in the job Signature was, and had just heard the project was over the completion
    deadline.
    Bennett asked Shawhan for assistance in the project, and Shawhan sent four
    additional men to help him. Bennett conceded that he did not know as much as the men
    who were actually working on the project. Although he stated there were times he felt that
    there were “too many” Signature workers on site, he was not aware of anyone being sent
    home because they were unnecessary. Bennett explained that on T & M not to exceed
    contracts, it was up to the contractors to manage the manpower and not go over the bid
    amount.
    5.     Steve Clayton
    Clayton testified that he was asked by Signature to go to IP and handle projects at
    the Orange mill. Clayton stated he was assigned to supervise around thirty projects at IP
    when he was there. Clayton explained that Edwards, Langley, and himself were a team
    13
    and he was involved in the decision to bid for the slaker project. Clayton did have initial
    reservations about the slaker project, but Edwards assured him everything would be
    taken care of, and Clayton had no doubt they could get the project completed in the
    appropriate timeframe. Signature bid the “knowns,” but knew there would be costs and
    changes outside of the initial bid. Clayton said he was getting “big revisions” before the
    contract was ever signed and he did not have the drawings to fabricate the pipes when
    the project started.
    Clayton arrived to the job on February 21, 2014, to do some work in advance of
    the shutdown but caught some design defects on the drawings that neither the IP safety
    people or engineers had noticed. This caused a delay because the drawings had to be
    redesigned to address the safety issues and IP’s approval took “awhile.” Clayton stated
    “everyone knew” there was more to the project than the initial bid. He also explained that,
    when the project was slated to start, Signature had to spend two days cleaning out the
    slaker because it was not ready to be replaced.
    Clayton continued to describe the delays Signature faced on the project. He stated
    that not a week went by where Signature was not stopped for “some sort of delay.”
    Clayton and Edwards agreed that a 19% overrun on the bid price was a low number
    considering all of the issues that occurred. Edwards had told him not to fabricate any pipe
    until they received isometric drawings from FBD, and having to wait delayed the rest of
    the project because it delayed the background work. He explained that he had to “rush”
    work, materials, or equipment, which caused it to be more expensive. He did agree with
    Bennett that due to the downtime, he sometimes had workers “just standing around,” but
    14
    IP would not allow him to send them home. Clayton explained to the jury that even though
    an FCO does not affect the T & M contract, he still tried to keep IP happy and manage
    Signature’s money well by asking to send workers home if they were not needed at a
    particular time.
    Clayton testified that when Bennett came on to the project, he changed the
    protocol and told Signature to not stop and wait for updated drawings and he stated that
    all the FCOs would be on verbal approval. Clayton disagreed that they should proceed
    without the drawings and opined the job “went out of control” after Bennett made the
    changes to the FCO procedure. Clayton also explained that Signature had paperwork of
    every job they received in the office and kept records of employee clock-ins separately
    because they did not trust the gate system IP used.
    Clayton talked about his experience working with Bennett and said it was “terrible.”
    He had previous safety concerns regarding the green liquor area, had showed Bennett
    that the lines were not properly locked out, and asked him not to turn them on. Shortly
    after their conversation, the green liquor line was turned on and almost severely burned
    Signature workers. Clayton said there was no investigation by IP into how the green liquor
    spill occurred, but Signature was told to clean up the spill the following day, although they
    were never given a material data safety sheet which explained how to handle the product.
    Clayton explained that the green liquor had also ended up in the slaker, so he refused to
    put his workers back in the slaker, and it caused issues with Bennett and Shawhan. It
    was later determined that there were seven places on the green liquor line that were not
    properly locked and tagged; Clayton stated that Bennett did not “have a clue.” Shawhan
    15
    got a variance to work on the slaker again; Clayton was not allowed back on the job site
    and banned from the mill.
    Clayton stated that he received multiple e-mails regarding the quality of the work,
    how good progress had been on the slaker project, and how well he had handled the
    project from Edwards. He never believed that Signature would not get paid for its work.
    Clayton told the jury that he attended the meeting in July with Wilhelm and Ogden. They
    were asked to bring books so they could go over and close out the bill. He stated the
    meeting lasted less than an hour, IP never looked at Signature’s books, and Shawhan
    stated he had a number in mind, which was around $200,000. Toni Hanson, IP’s senior
    source buyer, told Signature they would talk through things and get the bills “ironed out,”
    but it never happened. Clayton also filed a lawsuit against IP.
    On cross, Clayton said the contract terms were not met on the job because IP
    directed them to “do things differently.” Edwards told him that Signature did not need to
    provide a detailed description of labor and what had been done in order to get paid.
    Clayton disagreed with Edwards’s previous testimony in which Edwards stated he never
    told Signature not to provide a detailed description of the labor. Clayton agreed that if the
    bills and invoices looked incorrect, the parties should sit down and talk about them. He
    also stated that some of the invoices did not match up, but IP should have called and
    discussed the mistakes, instead of not saying anything at all. He explained there were
    multiple billings for piping because the piping kept changing; it was not a double-billing
    issue but he would have to look at the drawings to understand it.
    16
    6.     Anitra Collins and Roman Gallo
    Collins is the mill manager at the Orange mill, and Gallo is her boss. Collins
    testified that she relied on IP managers at the mill, especially on projects where she does
    not have direct knowledge and control. She stated that she did not have direct control of
    the slaker project. Collins explained that the annual outage at the plant is normally for
    nine days in the spring. The slaker project was considered an “end-of-life” project and the
    unit needed to be replaced. She said there were two slakers in Orange and if one went
    down, it limited their production.
    Collins talked about the payment process at IP. She stated they generally would
    issue a purchase order (PO) to a contractor to perform work for a certain amount, which
    would describe the work they were allowed to perform. If there were any changes, either
    in scope or amount, IP had to approve in the form of an FCO before the contractor could
    complete the work. The contractor was required to document and justify the change and
    have it approved by all the necessary people before any work was started. She said the
    burden to get change orders approved is on the contractor, and they were trained when
    they came to IP not to do any additional work until it was approved. Collins explained that
    even if Shawhan, Bennett, or Edwards told a contractor to do work without a PO or FCO,
    it was the contractor’s responsibility to make sure it had an approved PO to complete the
    work it was doing. She did state that Edwards could have told a contractor to do additional
    work without an FCO as long as there were still funds available on the original PO. If a
    contractor is asked to do work outside of the PO without the appropriate approval, then
    the contractor is supposed to refuse to complete the work. Collins said there should not
    17
    have been communication from a project manager that said to “get work done, we’ll make
    it up with an FCO later.” She reiterated that it was Signature’s responsibility to refuse to
    do the work without an approved FCO.
    Gallo was the vice president responsible for all aspects of the overall operations
    of the mill. He stated that FBD was in charge of the engineering on the slaker project and
    that a typical outage takes seven to fourteen days. Gallo did not know why the engineering
    drawings were not complete and was not aware of any specific issues with the project.
    He agreed that the green liquor spill was not Signature’s fault, that policy and procedure
    were not followed, and the cleanup was not in the original scope of work. Gallo also said
    that if a contractor goes onto the premises and does work, they should get paid even if
    they did not have an FCO approved in advance.
    Gallo stated that, based on his understanding of the situation, FCOs were not
    submitted prior to work being done and the parties were negotiating and working things
    out, but negotiations had not been completed. He understood there had been a review of
    the project after it was completed, and it was determined to be over budget and delayed
    in time. He said the review determined that FBD and the leadership of Signature were
    inadequate, and it was not a craftsmanship issue. Gallo agreed that if it was IP’s
    leadership that caused additional expenses due to their decisions, then IP is responsible
    for those expenses; proper documentation should have been put together to show IP was
    accountable. He said he could understand how Signature might rely upon an e-mail
    stating it could proceed on verbal approval of the FCOs. Although he agreed that IP’s
    standard practices were not adhered to, Gallo stated that Signature could have refused
    18
    to do the work outside the scope of the contract. He did also say that in “this specific case,
    the choices that Signature made at that point in time can be understood.”
    7.     Michael Moreno and Chris Wolohan
    Moreno and Wolohan testified regarding the attempted sale of Signature to
    Primoris. Moreno, Signature’s corporate representative, stated that Primoris showed
    interest starting in early 2014. Moreno explained that the original plan with Signature was
    to try and build up the business and then sell it within three to five years. The sale would
    have been a cash purchase to acquire the entire enterprise. He stated the sale process
    begins with him, then gets handed to both parties’ operational and technical team, and
    then to lawyers who would finalize the deal. Moreno said Signature received the first letter
    of intent from Primoris dated May 19, 2014. However, Moreno stated that Signature’s lost
    income from the contract with IP prevented Primoris from justifying the acquisition to its
    shareholders and caused it to decline to follow through with the purchase. Moreno told
    the jury that the loss of $3 million had a domino effect on Signature: it lacked working
    capital, the loss created tax issues, and other customers became wary about dealing with
    Signature due to its financial situation and cancelled pre-awarded work they had
    scheduled. He explained the payroll tax issues “morphed into something greater” as time
    went on. However, even with the issues, Primoris issued a second letter of intent to
    Signature on September 2, 2014, as talks had continued through the summer. Moreno
    stated that Signature turned down the September letter of intent because there was not
    enough “up-front” money, and it had concerns about the contingent payment portion that
    19
    would have occurred after closing.8 Moreno also conceded that Primoris wanted the IRS
    lien resolved to a “satisfactory level” before closing and that the previous issues had
    gotten to the point where Primoris would move forward and close.
    Wolohan was the head of corporate development for Primoris. He explained to the
    jury that Primoris is one of the largest construction companies in the country. The first
    letter of intent Primoris issued on May 19, 2014 proposed an “asset purchase.” He stated
    that the total consideration of the purchase was $42 million, with the initial cash at closing
    being $32 million plus an additional $10 million in contingency payments spread out
    through the next few years. Wolohan said there was a second letter of intent issued on
    May 23, 2014 but sent by e-mail in June 2014. The second letter included the same
    consideration but changed the net tangible assets at closing from $17.5 million to $15
    million. The September letter of intent was still for $42 million total, but at closing,
    Signature would have received $27 million, and $15 million would be a contingency or
    added-value consideration to be paid the following April based on various conditions.
    Signature did not accept any of these offers. Wolohan explained there were additional
    letters of intent issued in 2016: one for $10.5 million, and a second for $10.45 million.
    Wolohan stated that Primoris took its letters of intent seriously, and it set what it
    felt were “realistic earn-out targets.” If Primoris issued a letter of intent, there was an
    expectation and hope to close the transaction. He explained that when he evaluated
    Signature, Primoris was impressed with its ability to win work, and that was one of the
    8 The May letter of intent had different closing conditions and contingent payment numbers.
    Moreno described the September letter of intent as having conditions that turned the deal into an “asset
    purchase with a contingent payment based on future income that the company could generate.” If Signature
    did not meet the required numbers, then Primoris would not pay the additional amounts.
    20
    reasons Primoris pursued Signature.
    Wolohan testified that the letters of intent were non-binding on both parties. He
    also agreed with IP that, based on Signature’s initial book sheets, Wolohan found it to be
    a “stressed company” from late 2013 to early 2014, and he had concerns about
    Signature’s financial projections for the future being accurate or attainable. Wolohan
    agreed that the dispute between Signature and IP was a concern of Primoris’s in this
    deal, but that not remitting payroll taxes to the IRS was also a cause for concern. He
    stated that Signature’s substantial bank debt would need to be paid at closing or require
    releases before the deal would have been completed. Wolohan also explained that the
    changed cash closing amount was due to risk allocation with Signature.
    8.     Jeff Ogden
    Ogden testified Signature consisted of five owners. He explained that a business
    like Signature’s is relationship-based—the company develops and fosters relationships
    by doing good work for clients and it relies on word-of-mouth referrals and good
    experiences. Ogden stated that, in his other business ventures, there were several times
    they fell behind on payroll taxes because it is sometimes necessary to decide who to pay
    first: the workers or the IRS. Ogden said he always paid his workers and vendors first. He
    testified that Signature’s 2013 payroll taxes were paid in full by early 2014, before work
    on the slaker began.
    Ogden felt that $775,000 would not have completed the slaker project and even at
    the outset, there were major modifications that Signature was making. He said Signature
    completed the first two phases of the project without IP having to hire another contractor
    21
    but he did not consider the project complete because IP did not allow Signature to
    hydrotest the slaker—even though it was an industry standard to have the contractor run
    the test. Ogden estimated that Signature’s workers spent 16,300 to 17,000 man-hours on
    the project. He stated that the personnel changes took a toll on the project: Shawhan took
    over Edwards’s job, Bennett took over for Langley (and IP had to bring in five other people
    to perform Langley’s job), and Clayton was replaced by Signature’s employee Blake
    Spurlock, whom Ogden felt did not have the right type of experience for the project.
    Ogden discussed the meetings between Signature and IP. He stated that the
    questions IP sent to them before the meetings were “ridiculous and impossible to answer.”
    Shawhan went through the disputed invoices during the meeting and said he would not
    pay for any downtime because they should have managed their workers better. Ogden
    said Shawhan offered Signature $200,000 to pay the disputed invoices, but Ogden stated
    that $200,000 would just cover the piping materials they ordered. There was contentious
    dialogue between Hanson, Clayton, and Wilhelm during the meeting, with the latter two
    leaving before the conclusion. Ogden told the jury that Hanson said she could not pay
    him without Shawhan’s signature on the forms. Ogden went into the meeting prepared to
    discuss all the figures and brought who he considered to be the people he needed. Ogden
    felt that the questions IP posed could have been answered if both sides had been actually
    willing to sit down and look at the information, but it did not happen.
    Ogden also discussed the sale to Primoris. He stated that Signature’s financials
    deteriorated from the upward trajectory it originally had shown when Primoris made its
    initial $42 million offer. Signature would not have been able to meet the projections
    22
    because “word” was out that it was having financial issues, and the “targets” Primoris set
    for Signature to meet were unattainable. Ogden agreed that if he could “go back in time,”
    he would have accepted Primoris’s initial offer but he would not have had to consider less
    beneficial offers had IP paid the invoices.
    On cross-examination, Ogden was presented with a 2013 audit showing Signature
    had current assets of $11,986,151, liabilities of $15,656,725, and $6 million in revolving
    debt to CommunityBank. Ogden stated “that’s how you run a business” when discussing
    the debt. The 2013 tax liabilities were paid off in January or February 2014, and the late
    first-quarter payroll taxes were for non-slaker projects that were also being disputed.
    Besides the tax issues, Signature was affected by a “catastrophic” event that occurred at
    an Exxon plant, and although Signature was exonerated from fault, there was a period of
    lost jobs and revenue for Signature following the event.9 IP also asked Ogden about an
    incident where Hanson asked Signature not to invoice the FCOs until they were able to
    resolve the issues, but Wilhelm submitted the invoices anyway because it showed as
    revenue and could be used to borrow money from the bank.
    Ogden also clarified that the audit showed the wrong information. He stated that
    Signature’s total assets were $23,584,869, its total liabilities were $20,262,427, and its
    members’ capital was $3,322,442, which left them with $3.2 million on the “right” side.
    9.      Spencer Shawhan
    Shawhan testified that he was the project engineer as well as the acting
    9 Although Ogden testified that he did not believe the event at Exxon “caused problems” with
    Signature’s financials, he did state that it lost “five months” of jobs and revenue until Signature was
    exonerated by Exxon’s investigation as to liability for the accident.
    23
    engineering manager at the Orange plant. Edwards was his project manager on the slaker
    project and put together the team to develop the project. Shawhan explained that there
    are three types of drawings used in the bid process: preliminary, bid, and construction.
    He recalled that the engineering drawings were not ready when Edwards wanted to solicit
    bids, but he does not recall Edwards telling him they should wait on the slaker. IP’s total
    budget for the slaker was $3.4 million, but he does not consider the project finished
    because he cannot figure out what IP owes Signature to this date. Shawhan felt they
    could build the slaker for $775,000 and that there were enough details in the bid and
    addendums to put together an appropriate estimate. He did not think more detailed
    drawings were required and was unaware that Edwards had requested them.
    Shawhan stated that he normally does not see the invoices or backup
    documentation but has in this case due to the litigation. Normally, the documents go to
    an auditing group that reviews them and will directly contact the vendor if there is an
    issue. It is the auditing group who decides who gets paid, not him. He said he did see the
    FCOs and backups Signature submitted, and he and Hanson tried to question several
    things but “never had an opportunity to.”
    Shawhan explained that the Signature contract allowed for extra work to be done
    on a T & M basis and that standard procedure required extra work to be approved in
    advance. The first FCOs that Signature submitted were approved, contained the proper
    documents, and Signature was paid. Shawhan agreed Bennett gave the instruction to
    move forward absent drawings and to continue the project on verbal approval only.
    Shawhan stated that neither he nor Bennett has the authority to give that order or make
    24
    changes to the contract, but he did not do anything to correct the order even though it
    was a violation of IP’s policy. He also agreed that there were issues with the project that
    Signature was not responsible for, such as the green liquor spill, and he recommended
    paying the entire invoice involved. Shawhan testified that he intended to pay Signature
    for the work it performed and thinks it should be paid for that work. However, he also
    testified that Signature could not be paid because negotiations ended, and the lawsuit
    was filed.
    Shawhan explained that Langley was fired because he allowed a safety violation
    to occur. But Shawhan acknowledged that he did not do anything to stop the safety
    violation, even though he saw it, and he did not know if there was a safety stand-down
    meeting regarding the incident. He also conceded that Langley was the only person
    running the slaker project, but when Bennett replaced him, they had to bring in more
    people to help on the project.
    Regarding the hydrotest, Shawhan said the slaker was tested the first time it was
    filled up with green liquor and did not leak; although the industry standard is to test it with
    water first. He also wrote a memo to Collins regarding the project, but he did not tell her
    that he approved the FCOs verbally, that he had witnessed safety violations, or that
    Bennett violated company policy by authorizing a final, large FCO. He blamed everyone
    but Bennett and himself. Shawhan tried to create his own Powerpoint presentation to
    understand Signature’s invoices but said it was “difficult” to do “without having the benefit
    of getting to talk to them.” He also told the jury that he and Hanson did not realize the
    piping was not in the original bid request and nothing in the proposal indicated it was not
    25
    part of the amount.
    On cross-examination, Shawhan agreed that Signature did good work on the
    slaker. He felt IP prepared a “good bid package” that was sufficient to put together a good
    estimate. Shawhan stated that, even though Signature was told it could proceed with
    verbal authorization, everything still needed proper backup documentation, and the
    auditing department determines if an FCO is paid or not. He explained he preferred the
    prior approval of FCOs to avoid the situation they were in currently. He said there was
    never a plan or scheme with Edwards to not pay Signature. Shawhan was surprised by
    some of the disputed invoices items, such as piping, that had been included on previous
    paid invoices, but was also showing up in some of the later disputed invoices.
    He said in April 2014, when Signature requested $2.1 million but offered to settle
    for $1.7 million, the disputed invoices had not even been submitted to IP. While he agrees
    that Signature is owed more than what was in the original bid, he disputes the amount
    Signature demands. He could not recall Ogden telling him anything about “killing” the sale
    of Signature during the July meeting.
    10.     Don Coker
    Coker was Signature’s expert on company valuation. Coker said there are certain
    categories that you can add up to determine the number for damages. He used the
    following: the Primoris letter of intent, owner equity and assets, and IRS penalties and
    liabilities.10 He explained that he used the amount Primoris offered Signature because he
    considered it a bona fide offer. Coker stated that a bona fide offer from a knowledgeable
    10Coker explained that the IRS liabilities comprised penalties only and did not include any actual
    tax because that would have been owed regardless of IP’s actions.
    26
    buyer is what to consider in determining the value of a company and therefore, this was
    his estimate of what Signature was worth as a company. He also believed the unpaid bill
    to Signature was very critical because it could not pay its expenses, so that is how it
    ended up with a negative net worth. He explained the following regarding owner equity
    and assets:
    •   previous to 2016:
    total assets:          $23,584,869
    total liabilities:     $20,262,427
    owners’ equity:        $3,322,442
    •   March 2016:
    total assets:          $15,684,844
    total liabilities:     $24,793,903
    owners’ equity:        $-9,109,059
    He said that when a customer or lender perceives a company to be in financial distress,
    it can lead to the loss of business, which can make the situation worse. He felt the damage
    to Signature was traceable to IP’s action and lack of payment. He agreed with Ogden that
    some of a business’s catastrophic events can trickle down to the owners of a company.
    In order to determine Signature’s damages, Coker took the following figures:
    •   Primoris offer:             $42,000,000
    •   Owners’ equity loss:        $12,431,501
    •   IRS penalties:              $1,853,132
    •   Total sum:                  $56,284,633
    On cross-examination, Coker admitted he had taken a one-week business course
    from Harvard University on valuation, but his degree was in political science. He agreed
    there were multiple $42 million offers from Primoris to Signature with different conditions
    27
    attached. He also said that Signature would have made around $11.1 million from the
    sale with all the debt gone and assets transferred to Primoris. However, the June letter of
    intent based a substantial amount of the $32 million in cash on earnout, which is based
    on future expected value and business that Signature would get from its customers. He
    explained he determined Signature’s pro forma revenue (i.e., his estimate of what
    Signature would be worth at that time) by comparing its March 2016 balance sheet to a
    December 2013 balance sheet, but he did not analyze any of the invoices to determine if
    Signature was owed $2.4 million by IP in 2014. IP argued the disputed invoices amounted
    to $1,000,085, while Coker said the $2.4 million amount considered the slaker and “other
    jobs.” He believed Signature was considered a “stressed company” in late 2013, because
    it had not been paid for another IP project called the “bale conveyer” project.11 Coker did
    not think the Exxon event in 2013 was a “significant factor” in Signature’s financial
    situation.
    Coker repeatedly referenced other projects between Signature and IP, but not the
    slaker project. When questioned about the taxes, IP showed through documentation that
    Signature was behind $2.168 million at the end of 2013, and was also behind during the
    first quarter of 2014, prior to the slaker project being completed. Coker stated that the
    Primoris offer would be the “minimal value for the company.” He testified that he did not
    do a market value analysis of Signature, but just looked at existing financial statements.
    11Coker disagreed that the bale conveyer project also happened in 2014. He stated that IP “slow-
    paid” Signature for the project.
    28
    B.     Ogden’s Case-in-Chief
    1.      John Ulzheimer
    Ulzheimer was an expert witness hired to do an impact analysis on what kind of
    damages Ogden suffered and the impact on his credit reputation. He explained his
    assignment was to provide an inventory of the severely derogatory information on
    Ogden’s credit reports due to the failed business relationship. He presumed the
    information was present because of the actions of IP, and he was asked to determine
    what his credit score would have been without these derogatory marks. He told the jury
    he decided to do an impact analysis due to the lack of any other major derogatory entries
    to the credit report.
    Ulzheimer stated that Ogden had $9,000 of credit card debt on a defaulted
    American Express credit card, a tax lien, and a hard inquiry into his credit in January
    2017, which would have affected his credit score. The tax lien is the IRS tax lien Ogden
    acquired from Signature. He believed that getting rid of the tax lien and American Express
    card settlement would boost Ogden’s credit score close to seventy points. However, the
    lien payments were also coming from Signature, not Ogden personally.
    2.      Jeff Ogden
    Ogden testified again, this time relating to his personal cause of action against IP.
    He said he personally guaranteed all of Signature’s liabilities and that everything he owns
    is collateralized in Signature. He told the jury that he is signed on as the managing
    member and president of Signature, the grantor on the business, and as an individual at
    the bank.
    29
    Ogden stated that he is not delinquent on his personal taxes, but due to him being
    the trustee and managing member of Signature, the IRS penalized him for Signature’s
    delinquencies on payroll taxes. The 2014 payroll taxes Signature owed were:
    1st Quarter:         $127,553,39
    2nd Quarter:         $1,000,888.26
    3rd Quarter:         $754,253.21
    4th Quarter:         $912,279.64
    Total:               $2,803,974.50
    He stated that once the workers were paid, he begged IP to pay him. At the July meeting,
    Ogden told IP they were ruining Signature by not paying and he was losing the sale to
    Primoris, but Shawhan still did not want to pay him. Due to lack of payment, Signature
    now pays the IRS $7,000 a month to cover the tax lien. Ogden explained that he took a
    “massive” paycut and cut expenses in order to make it work. He also told the jury that he
    defaulted on Signature’s bank debt and if the payments are not made on that, the bank
    and IRS can come after his personal items.
    Ogden testified that, even though he would have received a tax refund as an owner
    of Signature in 2014, because they were operating at a loss, the IRS took his overpayment
    and applied it to the lien amount and would continue to do so until the lien was paid in
    full. He said due to the situation, he has had additional lawsuits filed against both
    Signature and him personally, it had destroyed friendships and relationships, and he was
    “barely” keeping Signature’s doors open. Ogden explained that he relied on IP to pay
    Signature, and that was why he put his name “on the line” with the IRS.
    Ogden told the jury that when Signature first started, it used his personal American
    Express card for business expenses because there was a larger line of credit available.
    30
    But when financial issues started and it became delinquent, American Express wrote off
    $111,483 in debt and closed the account.
    Ogden also explained the assignment from Signature. He stated that all the other
    partners in Signature assigned him the right to sue for personal damages under the IP
    contract. The other owners in Signature could file bankruptcy and walk away from the
    company, but Ogden said he could not because he was personally liable for Signature’s
    debts. Ogden also was not aware of anything in the corporate documents that said the
    other owners in Signature could not assign their rights to him to sue.
    Ogden testified that he felt that Shawhan was not truthful with Signature and if
    Ogden had known that submitting one big final FCO was a violation of IP’s policy, then
    he would have “done things differently” and not put his company “at stake.” He explained
    that he personally relied on the information relayed to him and contained in the e-mails.
    The credit reputation damage he suffered was due to the tax lien and American
    Express debt. Ogden had his credit checked in January 2017 in an attempt to purchase
    a truck. However, he said that once the credit was checked, the interest rate would have
    been higher than the principal, so he did not end up purchasing the vehicle. Ogden stated
    that there is no doubt in his mind that the damage to his credit reputation is a result of IP
    not paying Signature.
    Ogden also explained his mental and emotional stress. He said he does not sleep
    much, his phone rings constantly, and he is overwhelmed. He stated his family
    relationship has suffered, and he is like a “zombie.” He suffered from embarrassment and
    does not leave his house much. His family attempted to help by getting him an emotional
    31
    support dog. He felt that IP should be “ashamed of themselves,” that his business was
    “gone,” his name is “gone in the industry,” and he has nothing to “fall back on.” Ogden
    cannot contribute any other cause to Signature failing other than IP not paying the
    invoices.
    C.       IP’s Case-in-Chief
    1.    Toni Hanson
    As the senior sourcing buyer for IP, Hanson was involved in the commercial and
    contract side of the slaker project. Edwards got her involved in the project in June 2013
    and she focused on purchasing the equipment needed. Hanson said that $3.4 million was
    the total appropriation for the project, which would cover engineering costs, Edwards’s
    salary, other contract employees they needed to hire (not including Signature),
    installation, equipment, and a contingency fund for unexpected costs.
    In January 2014, Edwards was concerned with the bid package because the scope
    of work had not been completed and it needed another revision, but the necessary
    drawings were not available. Hanson explained that IP does not normally send out bid
    packages that are incomplete; occasionally it happens, but drawings have to be complete
    and sent to the bidder before the final bid comes in. Edwards assured her that would
    happen in this situation and sent the bid package to five bidders. He sent out addendums
    to the original bid package afterwards that included drawings and “other documents.”
    Hanson stated that only Signature submitted a bid and there was substantial work going
    on with other companies in the area at the same time, as well as demands from the oil
    field.
    32
    Hanson stated that Signature never told IP that it was having financial difficulties;
    otherwise, IP’s finance department would have looked into Signature closely. Hanson
    also testified that Signature did not tell IP it was attempting to sell the company during
    that time frame, which would have been a “huge red flag for awarding business.” Hanson
    said that she included a sample contract in the bid package so Signature could see the
    terms they would be agreeing to in the contract. Signature made a few changes to the
    terms of the bid contract and was awarded the work on February 21, 2014, when she sent
    it a draft contract. Hanson explained that she has the authority to award work without an
    issued PO as a purchasing agent, but not everyone has the authority to do so.
    Article ten of the contract refers to lien releases which Signature was required to
    execute before receiving final payment. She asked Wilhelm for the releases twice via e-
    mail. Hanson also explained that the contract contained an indemnity clause that required
    Signature to comply with federal law relating to its employees’ taxes. Hanson did not
    believe that Signature agreed to indemnify IP for liability from Ogden’s lawsuit.
    At the April 2014 meeting, IP gave Shawhan six additional FCOs. Hanson said that
    if FCOs come in after work is completed, then IP requires the vendor to provide complete
    documentation. That is considered an industry standard, not just something unique to IP.
    However, even without the formal FCO process, the contractor should have let the project
    manager know the costs. The project manager is required to have “intimate knowledge”
    of how the work is progressing, what work still remained, and how much cost should
    remain. Hanson stated that Edwards had already authorized an additional $275,000 and
    IP thought the April meeting would involve another $300,000 to “wrap” up the remainder
    33
    of the outstanding costs. Signature’s invoices asked for over $1 million in addition to
    previously approved amounts. Hanson said there was no “scheme” involved to “string”
    Signature along and not pay them. Hanson requested backup documentation to support
    the FCOs presented because Signature had just presented a one-page document on their
    letterhead with a brief description and no backup documentation. It was Hanson’s job to
    investigate the charges and verify they were accurate. She agreed that Signature did
    send her documents, but she said it did not identify which documents went with each FCO
    and IP could not “make heads or tails out of it.” Hanson stated that IP had never had a
    vendor who was not able to prove up their charges properly.
    She was willing to pay Signature if they could prove up the charges, so Hanson
    wrote out questions for Signature to direct them to the information required for each FCO;
    she also wanted to verify it was not the same amounts IP had already paid for. However,
    Hanson said she did not get answers to most of her questions. As an example, Hanson
    explained that half of the labor cost in the original $775,000 bid was for pipe fitters and
    the original bid had $60,000 of pipe included. However, one of the FCOs requested
    $529,000 and stated it was for “all piping fabrication and steel installation not included in
    the original bid,” so she wanted clarification on the difference. Hanson agreed that
    Signature sent her more concise information, but Signature never told her they could not
    provide certain backup because its documents were stolen. She also stated that some of
    the backup Signature did provide raised concerns about the way it was billing IP—for
    example, trucks being billed hourly instead of daily or within the original scope of work,
    and one person billed forty hours in one day.
    34
    Hanson testified that at the July meeting, both sides tried to sit down and
    understand the charges, but Signature could not explain “why documents were where
    they were.” She agreed that Shawhan said IP could justify $200,000 to $300,000 but
    would need help to justify the rest. Wilhelm responded by saying that he wanted “one
    hundred percent or nothing” or he would sue. Hanson did not remember any of the
    Signature representatives stating that IP was “destroying their business” or “harming a
    sale.” She disagreed that she told Signature that she would pay them, but Shawhan
    “wouldn’t let” her. Hanson stated she was not convinced all the charges Signature claimed
    were valid.
    Hanson also talked about the bid process. She stated that the approval of the
    FCOs was necessary so IP could keep track of what is going on with a project, but also
    so it can plan the budget and make sure there is sufficient money to pay the FCOs.
    Hanson said it is the vendor’s job to present the documentation in a concise way in order
    for IP to understand. She contacted Shawhan regarding questions she had on the project
    and expected him to know what went on. She also stated that she did not contact Edwards
    because he was no longer employed by IP. Hanson agreed that she finally got more
    detailed documentation, but the work was not paid because by then, Signature had filed
    its lawsuit. Hanson disclosed that IP made a payment of $550,021 into the registry of the
    court prior to trial.
    On July 22, 2014, Hanson sent an e-mail to Ogden in which she attached the
    payment history for outstanding POs on the slaker project, a list of outstanding invoices,
    and several notices of liens and lawsuits that had been filed. She wanted to understand
    35
    why Signature claimed the invoices had not been paid, when IP had paid Signature
    $1,018,487.63, and she needed to have all outstanding invoices paid and lien waivers
    from each of the vendors. Hanson stated that she never refused to pay Signature if it
    provided the appropriate backup, and she had expected Signature to walk her through
    the explanations of the FCOs at the meeting but it never happened.
    2.     Justin Hall
    Hall was the construction coordinator for Signature at the Orange mill. He was
    involved in the scheduling, planning, and estimating for projects, and in having the time
    sheets signed by the clients. Hall stated he was involved in estimating the slaker job and
    could only “bid the knowns.” He was in charge of the time sheets (containing labor hours
    and costs) IP would sign, as well as change orders and any turnover packages that came
    out of the project. Hall also acted as the “go-between” for Hanson and Signature.
    Hall explained that there were two other employees that had a similar job and the
    three of them handled the forty-four projects Signature was working on at the mill. He
    stated that they used a trailer that IP had given them as their office, and Clayton’s office
    was located in the same trailer. He believed that Blake Riley, with Signature, was the
    main person tracking the slaker project. According to Hall, a Signature foreman would
    keep track of the men and their hours worked while in the field and then he would turn
    that sheet into a timekeeper after every shift. The timekeeper would input the sheet into
    payroll, compare it against the gate log, and prepare the timesheet. Clayton would
    approve the timesheet and it would then be taken to the project manager for approval.
    Hall stated that a timesheet is different from a payroll sheet, and the payroll sheet would
    36
    be attached to the invoice submitted to IP as backup. Signature also used the payroll
    sheet to determine the workers’ pay.
    Hall testified that Edwards wanted Signature to “hold all change orders until the
    end of the project and submit them at the end of the project” to reduce the amount of
    change orders he received daily. Hall was not aware that multiple change orders were
    submitted after the project ended. He was later tasked with reconstructing the backup
    documents for the disputed invoices.
    On cross-examination, Hall stated that the backup documentation was kept in a
    file cabinet or bookshelf in the trailer. He said that, when he and his colleagues came in
    one morning, all the documentation had been taken and someone had reported seeing a
    person from IP in the trailer area. Signature ended up without several binders of
    information which contained information from all forty-four jobs at the Orange mill. Hall
    explained that they had no backup data for any of the jobs, so they had to reconstruct
    everything.
    3.      Ron Michalk
    Michalk was Signature’s controller and chief financial officer during the Primoris
    sale negotiations. His job was to provide the information that Primoris requested of
    Signature. He explained that negotiations were confidential in 2014.
    Michalk talked about how Signature was supposed to make weekly deposits for its
    payroll taxes. However, as the financial situation deteriorated, Signature began using the
    money to pay vendors and finance the company, just “try[ing] to stay alive.” Michalk
    agreed that in December 2013, Signature was “cash-strapped” and struggling to meet its
    37
    financial obligations. He said that in 2014, Signature lost $6.8 million, used its payroll
    money for operations, and the owners ran personal expenses through the company, with
    Ogden and Wilhelm doing so the most.
    Michalk stated that Signature’s financial situation improved in 2015 because it
    completed some good turnaround projects.
    4.      Barry Loder
    Loder worked as a consultant for Signature, to help with strategic consulting and
    teaching Signature how to build and grow the business. He created a Powerpoint
    presentation for discussions with Primoris. He felt that three things impeded Signature’s
    ability to prosper: insufficient working capital, slow-pay accounts receivable, and
    inadequate financing. Primoris could have come in and provided the working capital to
    grow the business and achieve the projections he had helped develop with the
    management. He felt Primoris’s first offer was good and he personally would have
    advised Signature to take it. Loder also thought the September 2014 offer from Primoris
    was “still a relatively good offer.”
    5.      Richard Domercq
    Domercq was the valuation consultant hired by IP to evaluate Coker’s report,
    Signature’s financial status, and compare the invoices. He found there were seven
    “disputed” invoices that totaled $1,085,000. Domercq felt that $535,000 was overbilled
    and the maximum valid charges contained in the invoices totaled $550,000. He came to
    that determination by looking for duplicate billing or expenditures that were not within the
    scope of the contract.
    38
    Domercq stated that Signature provided IP with a weekly labor and cost approval
    form of its own making that was sorted by “craft” or type of work, instead of by individual
    employee. The form grouped a “bunch of people” together and billed them as a group,
    instead of showing a daily detail for each individual worker. Domercq and his team created
    a spreadsheet listing every employee, taking information from the hours tracking form.
    He found that Signature had billed 23,000 hours for the slaker project, of which 13,506
    were disputed. The cost report from Signature showed 15,783 hours, Domercq’s analysis
    showed 16,244 hours, and Signature billed almost 23,000. He attributed the differences
    to overbilling. He felt that Signature had overbilled $635,000, but he admitted there was
    some labor that was not billed so he gave Signature a credit for that in the amount of
    $141,000. Domercq stated that he relied on the master payroll in developing his analysis
    and found that the $550,000 was supported by Signature’s backup. He also said that IP
    paid liens that totaled $95,840, so if the jury considered that as an offset, Signature was
    still owed $454,000.
    Domercq also reviewed Coker’s report. He stated that Coker did not do an
    independent verification of the information Signature gave him, but instead made
    assumptions contrary to the facts. Domercq testified that the biggest assumption Coker
    made was that, when the slaker project was completed, IP owed Signature $2.4 million
    and refused to pay. He said Coker also assumed one could measure the value of the
    company by stockholders’ equity and did not look at the other factors that could have
    affected the financial condition. In his professional opinion, Domercq did not feel it was
    reasonable to conclude that a $500,000 to $1 million invoice dispute would be a
    39
    substantial factor in bringing about the decline of the stockholders’ equity.
    6.     Bryan Byrd (Bill of Exception)
    Byrd’s testimony was excluded by the trial court, who found it to be cumulative to
    other witnesses. Byrd explained his experience was in T & M contracts and backup
    documentation. He said there was enough detail found in the bid package and seven
    addendums to construct a detailed bid on piping for the project. He also felt one needed
    training in construction to be able to interpret the drawings and understand Signature’s
    bid. He stated that based on the cost for labor in the bid, piping would have been included
    in those numbers.
    In speaking about specific disputed FCOs, Byrd found the backup to not have
    enough detail or description to support them. He felt the information was not adequately
    detailed, there were too many questions regarding the scope of work changes that were
    asserted, and there were too many documents that showed that Signature was
    responsible for the extra work to support the scope of the FCOs.
    D.     Verdict
    The jury found for Signature and Ogden on all the questions submitted to it. For
    breach of contract, promissory estoppel, and fraud, the jury awarded $2,442,515.28 in
    actual damages and $56,284,633 in consequential damages. Regarding Ogden, on
    breach of contract, the jury awarded $2.8 million in actual damages, $111,000 for past
    credit reputation damage, and $1.3 million for future credit reputation damage. On his
    fraud claim, the jury awarded Ogden $13 million for past mental anguish damages and
    $50 million for future mental anguish damages.
    40
    E.     Indemnity Claims, Post-Trial Motions, and Judgment
    Following the trial, the parties agreed to have IP’s indemnity claims heard by the
    trial court. IP had filed a motion to enforce the indemnity provision in Article 8.6 of the
    slaker contract,12 claiming that Signature should indemnify it for its attorney’s fees, costs,
    and expert fees used to defend against Ogden’s claims. At a hearing held on July 24,
    2017, IP stated Signature’s duty to indemnify was based on the slaker contract and
    Signature’s failure to pay the payroll taxes to the IRS opened IP up to liability. IP also
    argued Signature had not filed an answer to its counterclaim for indemnity and had thus
    waived any affirmative defenses. The trial court granted Signature leave to file an answer
    on the same day as the hearing. Later, the trial court denied IP’s motion to enforce
    12   Article 8.6 of the slaker contract stated:
    6. Indemnity. The CONTRACTOR [Signature] assumes the defense and the entire
    responsibility and liability for any and all damage or injury of any kind or nature whatsoever
    (including resulting death) to all persons, whether employed by the CONTRACTOR or
    otherwise, including but not limited to (a) employees and agents of subcontractors of
    CONTRACTOR or COMPANY [IP], or (b) any other third party, and to all property (other
    than the work itself as set out in paragraph 7 below) caused by, resulting from, arising out
    of, or occurring in connection with the performance by CONTRACTOR, or any
    subcontractor or agent of CONTRACTOR, of this AGREEMENT. In the event the liability
    of the CONTRACTOR shall arise by reason of the sole negligence of COMPANY, then and
    only then, the CONTRACTOR shall not be liable under the provisions of this paragraph. If
    any person makes a claim for any such damage or injury (including death resulting
    therefrom) as hereinabove described, the CONTRACTOR agrees to indemnify and save
    harmless the COMPANY, its agents, servants and employees from and against any and
    all loss, damage, injury or expense including reasonable attorney's fees that the
    COMPANY may sustain as a result of any such claims, and the CONTRACTOR agrees to
    assume, on behalf of the COMPANY, the defense of any action at law or in equity, which
    may be brought against the COMPANY upon such claim and to pay on behalf of the
    COMPANY upon its demand, the amount of any judgment that may be entered against the
    COMPANY in any such action. In any suit or claim by COMPANY, CONTRACTOR hereby
    expressly waives any immunity from suit which might otherwise be conferred by the
    Workers’ Compensation laws of any jurisdiction and which would preclude enforcement of
    the indemnification clause of the AGREEMENT by COMPANY, and CONTRACTOR further
    agrees to pay any reasonable attorney's fees as are incurred by the COMPANY in securing
    compliance with the provisions of this indemnification.
    41
    indemnity.
    The trial court entered its judgment on December 14, 2017, awarding Signature
    $58,174,672 in actual and consequential damages minus offset amounts, 13 as well as
    prejudgment and additional interest. Ogden was awarded $67,211,000 in actual and
    consequential damages, as well as prejudgment and additional interest. Both parties were
    awarded attorney’s fees in varying amounts.
    On January 12, 2018, IP filed a motion for judgment notwithstanding the verdict
    and a motion for new trial, which were overruled by operation of law. This appeal followed.
    II.     SUFFICIENCY OF THE EVIDENCE RELATED TO SIGNATURE’S CLAIMS
    By its first three issues, IP alleges that Signature failed to present legally sufficient
    evidence for (1) its breach of contract, (2) fraud, and (3) promissory estoppel claims.
    A.      Standard of Review
    A legal sufficiency challenge will be sustained when the record shows: (1) the
    complete absence of a vital fact; (2) the court is barred by rules of law or evidence from
    giving weight to the only evidence offered to prove a vital fact; (3) the evidence offered to
    prove a vital fact is no more than a scintilla; or (4) the evidence conclusively establishes
    the opposite of a vital fact. City of Keller v. Wilson, 
    168 S.W.3d 802
    , 810 (Tex. 2005). The
    test for legal sufficiency is “whether the evidence at trial would enable reasonable and
    fair-minded people to reach the verdict under review.”
    Id. at 827.
    We review the evidence
    in the light most favorable to the verdict, crediting any favorable evidence if a reasonable
    13 The trial court reduced the jury’s verdict by $550,021 representing the amount IP had deposited
    into the registry of the court before trial, and an additional settlement of $2,500 representing an earlier
    settlement with another early party to this case.
    42
    fact-finder could and disregarding any contrary evidence unless a reasonable fact-finder
    could not.
    Id. at 821–22,
    827. In our review, we are mindful that the jury remains the sole
    judge of witnesses’ credibility and the weight to be given to their testimony.
    Id. at 819–20.
    Moreover, in our legal sufficiency review, we must show deference to the jury’s resolution
    of conflicts in the evidence, and we must presume that the jury resolved all conflicts in
    favor of the verdict.
    Id. at 820–21.
    A party who challenges the legal sufficiency of the evidence to support an issue
    upon which he did not have the burden of proof at trial must demonstrate on appeal that
    there is no evidence to support the adverse finding. State Office of Risk Mgmt. v. Pena,
    
    548 S.W.3d 84
    , 90 (Tex. App.—Corpus Christi–Edinburg 2018, no pet.); Luce v. Interstate
    Adjusters, Inc., 
    26 S.W.3d 561
    , 566 (Tex. App.—Dallas 2000, no pet.) (citing Croucher v.
    Croucher, 
    660 S.W.2d 55
    , 58 (Tex. 1983)).
    When a party attacks the legal sufficiency of an adverse finding on an issue on
    which that party has the burden of proof at trial, the complaining party must demonstrate
    on appeal that the evidence establishes, as a matter of law, all vital facts in support of the
    issue. Dow Chem. Co. v. Francis, 
    46 S.W.3d 237
    , 241 (Tex. 2001) (per curiam). We
    review a matter of law challenge by first examining the record for evidence that supports
    the adverse finding, while ignoring all evidence to the contrary.
    Id. If we
    do not find
    evidence to support the finding, we will then examine the entire record to determine if the
    contrary proposition is established as a matter of law.
    Id. “The point
    of error should be
    sustained only if the contrary proposition is conclusively established.”
    Id. The fact
    finder is the sole judge of the witnesses’ credibility and may choose to
    43
    believe one witness over another. Golden Eagle Archery, Inc. v. Jackson, 
    116 S.W.3d 757
    , 761 (Tex. 2003). We may not substitute our own judgment for that of the jury, even
    if we would reach a different answer based on the evidence. GTE Mobilnet of S. Tex. Ltd.
    P’ship v. Pascouet, 
    61 S.W.3d 599
    , 616 (Tex. App.—Houston [14th Dist.] 2001, pet.
    denied) (citing Maritime Overseas Corp. v. Ellis, 
    971 S.W.2d 402
    , 407 (Tex. 1998)).
    B.     Breach of Contract
    By its first issue, IP argues that the evidence is legally insufficient to support the
    jury’s verdict as to breach of contract. To prevail on a breach of contract claim, a plaintiff
    must prove: (1) the existence of a valid contract; (2) performance or tendered
    performance by the plaintiff; (3) breach of the contract by the defendant; and (4) damages
    to the plaintiff resulting from that breach. First Nat'l Bank of Edinburg v. Cameron
    County, 
    159 S.W.3d 109
    , 112 (Tex. App.—Corpus Christi–Edinburg 2004, pet. denied).
    1.     Jury Questions
    The jury was asked to consider the following questions related to breach of
    contract:
    Question No. 1(a)
    Did Signature and IP agree that Signature would provide labor, material,
    and services in exchange for payment from IP?
    In deciding whether the parties reached an agreement, you may consider
    what they said and did in light of the surrounding circumstances, including
    any earlier course of dealing. You may not consider the parties’
    unexpressed thoughts or intentions.
    Answer “Yes” or “No” with respect to each of the following:
    (1)    Slaker Project
    44
    Answer:       Yes
    (2)    Non-Slaker Project
    Answer:       Yes
    Question No. 1(b)
    Did IP fail to comply with such agreements?
    Answer “Yes” or “No” with respect to each of the following:
    (1)    Slaker Project
    Answer:       Yes
    (2)    Non-Slaker Project
    Answer:       Yes
    2.     Condition Precedent or Covenant
    IP argues that it was not required to pay the disputed invoices because Signature
    provided insufficient backup documentation to support the invoices. IP states that the
    backup documentation was a condition precedent to its requirement to pay, and because
    that condition was not met by Signature, IP was not obligated to pay.
    A “condition precedent is an event that must happen or be performed before a right
    can accrue to enforce an obligation.” Solar Application Eng’g, Inc. v. T.A. Operating Corp.,
    
    327 S.W.3d 104
    , 108 (Tex. 2010) (quoting Centex Corp. v. Dalton, 
    840 S.W.2d 952
    , 956
    (Tex. 1992)); see also RESTATEMENT (SECOND) OF CONTRACTS § 224 (1981) (“A condition
    is an event, not certain to occur, which must occur, unless its non-occurrence is excused,
    before performance under a contract becomes due.”). A covenant, as distinguished from
    a condition precedent, is an agreement to act or refrain from acting in a certain way. Solar
    45
    Application Eng’g, 
    Inc., 327 S.W.3d at 108
    . Breach of a covenant may give rise to a cause
    of action for damages but it does not affect the enforceability of the remaining provisions
    of the contract unless the breach is material or is a total breach.
    Id. In order
    to determine whether a condition precedent exists, the intention of the
    parties must be ascertained; and that can be done only by looking at the entire contract.
    Criswell v. European Crossroads Shopping Ctr., Ltd., 
    792 S.W.2d 945
    , 948 (Tex. 1990)
    (op. on reh’g). “In order to make performance specifically conditional, a term such as ‘if,’
    ‘provided that,’ ‘on the condition that,’ or some similar phase of conditional language must
    normally be included.”
    Id. at 948.
    When “no conditional language is used and another
    reasonable interpretation of the contract is possible, ‘the terms will be construed as a
    covenant in order to prevent a forfeiture.’”
    Id. Here, Article
    4 of the contract stated:
    CONTRACTOR [Signature] shall send to COMPANY [IP] on the 15 and 30
    day of each month a detailed statement of all reimbursable costs incurred
    and actually paid by CONTRACTOR during the preceding period, together
    with original payrolls for labor, checked and approved by persons
    satisfactory to COMPANY, and all receipted bills, paid original invoices or
    other documents requested by COMPANY. Within thirty (30) days from the
    receipt of the statement, COMPANY agrees to pay CONTRACTOR the
    amount of the statement.
    Prior to final acceptance of the Project, CONTRACTOR shall deliver to
    COMPANY a statement, together with satisfactory evidence, that all
    payrolls, material bills[,] and other indebtedness incurred by
    CONTRACTOR and all subcontractors in the performance of this
    AGREEMENT have been paid[,] and CONTRACTOR agrees to hold
    COMPANY harmless on account thereof. COMPANY may at any time
    withhold payment of all or any part of the Contract Price to such extent as
    may be necessary to protect itself from loss on account of:
    (a)    defective work not remedied;
    46
    (b)    claims filed by third parties or reasonable evidence indicating the
    probable filing of such claims;
    (c)    failure of CONTRACTOR to make payments due to subcontractors
    or suppliers of material or labor;
    (d)    a reasonable doubt that the Project can be completed for the balance
    then unpaid under this AGREEMENT;
    (e)    an existing breach of the AGREEMENT by CONTRACTOR; or
    (f)    damage to another person, firm or entity caused by acts or omissions
    of CONTRACTOR.
    When the ground or grounds for withholding payment are removed to the
    satisfaction of the COMPANY, CONTRACTOR’S right to payments [sic] as
    herein provided shall thereupon be reinstated.
    Signature argues in its brief that none of the requisite terms are contained in the IP slaker
    contract to change this requirement into a condition precedent. We agree.
    The slaker contract required documentation to be approved by “persons
    satisfactory” to IP and once the statement was received, it would be paid within thirty
    days. There is no specific language that says IP was only required to pay when it agreed
    the documentation was complete or anything to that effect. The jury rejected IP’s
    contention that it did not have to pay the invoices because there was not sufficient
    documentation presented. Since there was no conditional language found within the
    contract and there were multiple interpretations of how the contract could be read, we
    construe the language as a covenant. See
    id. Because we
    agree that the documentation
    requirement was not a condition precedent to IP’s requirement to pay, we move to the
    breach of contract argument.
    47
    3.     Breach
    Under the elements required for a breach of contract, the evidence showed there
    was a valid contract between IP and Signature, that Signature performed the job
    requested under the contract, and Signature was damaged due to the non-payment that
    resulted. See First Nat’l Bank of 
    Edinburg, 159 S.W.3d at 112
    . IP admitted during trial
    that Signature was owed money for the slaker project; however, the amount owed was in
    contention.
    IP is required to show that there was no evidence to support the adverse finding it
    is challenging. See 
    Pena, 548 S.W.3d at 90
    . However, the evidence presented showed
    that Signature performed its principal obligation: to construct and install a new slaker. The
    parties agreed that the initial FCOs were submitted with approved documentation and
    were paid by IP with little issue. It was after IP’s representatives made changes to how
    the invoices were to be submitted that issues arose. The jury heard testimony from
    multiple witnesses stating that FCOs were approved verbally, submitted with
    documentation, and then never paid.
    The jury was entitled to disbelieve IP’s witnesses who claimed the documentation
    was insufficient and therefore, it was not required to pay the disputed invoices. See
    Golden 
    Eagle, 116 S.W.3d at 761
    . In any event, the jury was also presented with
    thousands of pages of evidence showing the invoices and documentation Signature
    submitted to IP, and it could have reasonably found the documentation was sufficient to
    justify payment. See 
    Pascouet, 61 S.W.3d at 616
    . The evidence at trial was sufficient to
    48
    “enable reasonable and fair-minded people to reach the verdict under review.” See City
    of 
    Keller, 168 S.W.3d at 827
    ; see 
    Pena, 548 S.W.3d at 90
    .
    IP raises multiple additional sub-issues regarding the breach of contract claim—
    for example, it argues Signature failed to prove the disputed amounts of the invoices, the
    invoices were not accurate, and the invoices were in excess of what IP’s expert, Domercq,
    testified was owed—but those points were all fact issues that were within the domain of
    the jury to consider. The jury determined which facts and witnesses to believe or
    disbelieve, and we defer to its findings. See City of 
    Keller, 168 S.W.3d at 820
    –21; Golden
    
    Eagle, 116 S.W.3d at 761
    ; 
    Pascouet, 61 S.W.3d at 616
    . IP additionally complains that the
    jury was not given instructions on waiver, frustration, impracticability, or other doctrines
    that would have allowed it to consider Signature’s inability to provide detailed invoices in
    determining whether a breach occurred. However, IP does not raise an issue on appeal
    related to the jury charge, so we will not consider jury charge issues. See TEX. R. APP. P.
    38.1.
    There was more than a “scintilla of evidence” presented at trial to support the jury’s
    findings, in response to questions 1(a) and 1(b) of the jury charge, that IP breached the
    slaker contract. See City of 
    Keller, 168 S.W.3d at 810
    . We overrule IP’s first issue.
    C.      Fraud
    By its second issue, IP alleges the evidence is legally insufficient to support the
    jury’s verdict for fraud. The jury charge contained the following question and instructions
    regarding fraud:
    Did IP commit fraud against Signature?
    49
    Fraud occurs when:
    (1)    A party makes a material misrepresentation, and
    (2)    The misrepresentation is made with knowledge of its falsity or made
    recklessly without any knowledge of the truth and as a positive
    assertion, and
    (3)    The misrepresentation is made with the intention that it should be
    acted on by the other party, and
    (4)    The other party justifiably relies on the misrepresentation and
    thereby suffers injury.
    “Misrepresentation” means a promise of future performance made with an
    intent, at the time the promise was made, not to perform as promised.
    To hold [IP] liable for fraud, you must find that a single employee of [IP]
    committed all elements of fraud while acting within the scope of his
    employment.
    A promise of future performance constitutes an actionable misrepresentation if the
    promise was made with no intention of performing at the time it was made. Formosa
    Plastics Corp. USA v. Presidio Eng’rs & Contractors, Inc., 
    960 S.W.2d 41
    , 48 (Tex. 1998)
    (op. on reh’g). The mere failure to perform a contract is not evidence of fraud.
    Id. At trial,
    Signature had to present evidence that IP made representations with the intent to deceive
    and with no intention of performing as represented. See
    id. Additionally, the
    evidence
    presented must be relevant to IP’s intent at the time the representation was made. See
    id. As noted
    supra, the jury agreed with Signature and found IP committed fraud.
    In our review of this finding, “all of the record evidence must be considered in a
    light most favorable to the party in whose favor the verdict has been rendered, and every
    reasonable inference deducible from the evidence is to be indulged in that party’s favor.”
    Id. Anything more
    than a scintilla of evidence is legally sufficient to support the finding.
    Id. 50 Signature
    alleged that IP changed the procedure for the submissions of the FCOs
    in order to induce Signature to continue the work to meet the timetable IP wanted.
    Although there was evidence to support some of the required elements of fraud, Signature
    did not prove all the elements needed. See First Nat’l Bank of 
    Edinburg, 159 S.W.3d at 112
    . There was no evidence presented that, when IP informed Signature that it had
    changed the procedures used to submit the FCOs, it also had no intention of performing.
    Prior to Signature being told to alter the procedure used, IP had regularly made payments
    relating to prior invoices submitted under the slaker contract. There was no evidence that,
    when Bennett changed the procedure used, it was so IP could avoid paying the invoices
    or not perform on the contract.
    Additionally, in order to support the fraud finding, Signature was required to present
    evidence that all the elements of fraud as defined in the jury charge could be attributed to
    one employee of IP. See Dynegy, Inc. v. Yates, 
    345 S.W.3d 516
    , 531 (Tex. App.—San
    Antonio 2011), rev’d on other grounds, 
    422 S.W.3d 638
    (Tex. 2013). Signature was
    unable to satisfy this requirement. Evidence was presented that Edwards and Bennett
    were the main IP representatives that made modifications, both orally and through e-mail,
    to the FCO submission procedure. At trial, Signature presented evidence that Shawhan
    refused to pay the disputed FCO invoices. However, Shawhan was not the IP
    representative who made the changes to the FCO submission procedure that Signature
    detrimentally relied on; it was Edwards and Bennett. Therefore, Signature failed to
    present proof that only one employee committed the fraud as required by the jury charge.
    51
    The evidence is legally insufficient to support the jury’s finding that IP committed fraud
    against Signature. We sustain IP’s second issue.
    D.     Promissory Estoppel
    By its third issue, IP challenges the jury’s finding regarding promissory estoppel.
    IP argues that Signature’s promissory estoppel claim is based on IP’s performance under
    the slaker contract, and it states that Signature cannot recover under a promissory
    estoppel theory because there was a valid, enforceable contact between the parties. We
    agree with IP.
    “Promissory estoppel operates to enforce an otherwise unenforceable promise; ‘[i]t
    cannot replace an enforceable contract.’” Superior Laminate & Supply, Inc. v. Formica
    Corp., 
    93 S.W.3d 445
    , 449 (Tex. App.—Houston [14th Dist.] 2002, pet. denied) (quoting
    Vogel v. Travelers Indem. Co., 
    966 S.W.2d 748
    , 754 (Tex. App.—San Antonio 1998, no
    pet.)). A claim for promissory estoppel and a contract claim are mutually exclusive claims;
    a litigant cannot recover on one if it recovers on the other. Doctors Hosp. 1997, L.P. v.
    Sambuca Hous., L.P., 
    154 S.W.3d 634
    , 637 (Tex. App.—Houston [14th Dist.] 2004, pet.
    abated).
    Here, the jury awarded damages in favor of Signature under both a theory of
    breach of contract and promissory estoppel. We have already held the evidence was
    sufficient to support the breach of contract finding. Therefore, because there was a valid
    contract in place between the parties, Signature cannot recover under a theory of
    promissory estoppel. See
    id. We sustain
    IP’s third issue.
    III.   SIGNATURE’S DAMAGES AWARDS
    52
    By its fourth and fifth issues, IP challenges the damages awarded to Signature. By
    its fourth issue, IP claims there is legally insufficient evidence to support the award of
    consequential damages based on testimony of Signature’s expert. By its fifth issue, IP
    argues that a new trial should be granted because the jury awarded excessive actual and
    consequential damages to Signature based on the evidence presented.
    A.     Standard of Review
    The standard of review for legal insufficiency is addressed in Section II(A). The
    standard of review for excessive damages is the factual sufficiency of the evidence. See,
    e.g., 
    Ellis, 971 S.W.2d at 406
    –07; Pope v. Moore, 
    711 S.W.2d 622
    , 624 (Tex. 1986) (per
    curiam); Miller v. Argumaniz, 
    479 S.W.3d 306
    , 313 (Tex. App.—El Paso 2015, pet.
    denied). The court of appeals should employ the same test for determining excessive
    damages as for any factual sufficiency questions. 
    Ellis, 971 S.W.2d at 406
    . When
    considering a factual sufficiency challenge to a jury’s verdict, courts of appeals must
    consider and weigh all of the evidence, not just that evidence which supports the verdict.
    Id. at 406–07.
    We can set aside the verdict only if it so contrary to the overwhelming
    weight of the evidence that the verdict is clearly wrong and unjust.
    Id. at 407.
    The court
    of appeals is not a fact finder and may not pass upon the witnesses’ credibility or
    substitute its judgment for that of the jury, even if the evidence would clearly support a
    different result.
    Id. If the
    court of appeals determines that the evidence supports a jury’s verdict, it is
    not required to detail all of the evidence supporting the judgment when it affirms the trial
    court’s judgment for actual damages.
    Id. On the
    other hand, when reversing a trial court’s
    53
    judgment for factual insufficiency, the court of appeals must detail all the evidence
    relevant to the issue and clearly state why the jury’s finding is factually insufficient or so
    against the great weight and preponderance of the evidence that it is manifestly unjust.
    Id. The court
    of appeals must explain how the contrary evidence greatly outweighs the
    evidence supporting the verdict.
    Id. B. Jury
    Question
    Relating to the breach of contract claim, question number 1(c) of the jury charge
    stated the following regarding damages:
    What sum of money, if any, if paid now in cash, would fairly and reasonably
    compensate Signature for its damages, if any, that resulted from IP’s failure
    to comply?
    ...
    Answer separately in dollars and cents for damages, if any.
    (1)    The difference, if any, between the payment Signature received from
    IP for its work and the payment Signature would have received from
    IP if IP had complied with the agreements.
    Answer:       $2,442,515.28
    (2)    Damages to Signature’s company value, if any, that were a natural
    and probable consequence of such failure to comply, and that were
    foreseeable to Signature and IP when the agreements were made.
    Answer:       $56,284,633.00
    C.     Actual Damages
    To recover damages for breach of contract, a plaintiff must show that he suffered
    a pecuniary loss as a result of the breach. AZZ Inc. v. Morgan, 
    462 S.W.3d 284
    , 289 (Tex.
    App.—Fort Worth 2015, pet. ref’d). “Such losses must be the natural, probable, and
    54
    foreseeable consequence of the defendant’s conduct.” Peterson Grp., Inc. v. PLTQ Lotus
    Grp., L.P., 
    417 S.W.3d 46
    , 64 (Tex. App.—Houston [1st Dist.] 2013, pet. denied). A
    plaintiff may not recover breach-of-contract damages if those damages are remote,
    contingent, speculative, or conjectural.
    Id. Generally, the
    measure of damages for breach
    of contract is that which restores the injured party to the economic position he would have
    enjoyed if the contract had been performed. 
    AZZ, 462 S.W.3d at 289
    .
    Although the amount owed under the disputed invoices was a hotly contested
    issue throughout trial, the jury sided with Signature and awarded the $2.4 million
    Signature claimed it was owed. Signature introduced thousands of pages of documents
    into evidence for the jury to review and determine the proper amount of money Signature
    was owed. Although IP argues that Signature admitted it was owed less than $2.4 million
    and the slaker project invoices do not add up to $2.4 million, the jury also was allowed to
    consider non-slaker projects as part of the breach of contract questions.
    We have considered and weighed all of the evidence, not just that evidence which
    supports the verdict. 
    Ellis, 971 S.W.2d at 406
    –07. However, we cannot say that based on
    all of the evidence presented that the finding of $2.4 million in breach of contract damages
    is clearly wrong and unjust.
    Id. at 407.
    The jury is the sole factfinder and we defer to its
    finding, even if the evidence would support a different result.
    Id. at 407.
    Additionally, to
    the extent IP makes a legal sufficiency argument as to the actual damages award, based
    on the evidence presented we cannot say the evidence was less than a scintilla or no
    evidence. See City of 
    Keller, 168 S.W.3d at 810
    ; 
    Pena, 548 S.W.3d at 90
    . We must show
    deference to the jury’s resolution of conflicts in the evidence, and we must presume that
    55
    the jury resolved all conflicts in favor of the verdict. See City of 
    Keller, 168 S.W.3d at 820
    –
    21. Therefore, we overrule IP’s fifth issue as it relates to the award of actual damages.
    D.      Consequential Damages
    IP’s challenge to the consequential damages relates to Question 1(c)(2)’s answer.
    Consequential damages result from the defendant’s wrongful acts. Arthur Anderson &
    Co. v. Perry Equip. Corp., 
    945 S.W.2d 812
    , 816 (Tex. 1997). Foreseeability is a
    fundamental prerequisite to the recovery of consequential damages for breach of
    contract. Basic Capital Mgmt., Inc. v. Dynex Commercial, Inc., 
    348 S.W.3d 894
    , 901 (Tex.
    2011). Consequential damages are those damages that result naturally, but not
    necessarily, from the defendant’s wrongful acts. Stuart v. Bayless, 
    964 S.W.2d 920
    , 921
    (Tex. 1998) (per curiam). Consequential damages are generally not recoverable unless
    the parties contemplated at the time they made the contract that such damages would be
    a probable result of the breach. Id.; 
    AZZ, 462 S.W.3d at 289
    .
    Coker testified that he determined the amount suggested as damages by totaling
    three figures: (1) $42 million, representing the Primoris offer; (2) $12,431,501,
    representing the owners’ equity loss; and (3) $1,853,132, representing the IRS penalties
    Signature incurred. The jury’s consequential damages award equaled the amount Coker
    recommended: $56,284,633. IP argues that Coker’s testimony was not probative because
    he “assumed” certain facts; Signature, as a company, was not able to recover company
    value14 and there was no evidence of foreseeability to support the damages award.
    14 The case IP references in its brief for this argument relates to “lost profits” and market value in
    a land condemnation case, State v. Luby’s Fuddruckers Restaurants, LLC, 
    531 S.W.3d 810
    (Tex. App.—
    Corpus Christi–Edinburg 2017, pet. ref’d). We do not find the analysis on point for this case.
    56
    “When an expert opinion is admitted into evidence without objection, ‘it may be
    considered probative evidence even if the basis for the opinion is unreliable.’” Hous.
    Unlimited, Inc. Metal Processing v. Mel Acres Ranch, 
    443 S.W.3d 820
    , 829 (Tex. 2014)
    (quoting City of San Antonio v. Pollock, 
    284 S.W.3d 809
    , 828 (Tex. 2009)). “But if no basis
    for the opinion is offered, or the basis offered provides no support, the opinion is merely
    a conclusory statement and cannot be considered probative evidence, regardless of
    whether there is no objection.” 
    Pollock, 284 S.W.3d at 828
    . “This is because the
    evidentiary value of expert testimony is derived from its basis, not from the mere fact that
    the expert has said it.” Hous. 
    Unlimited, 443 S.W.3d at 829
    .
    Coker explained during his testimony that he came to his determination that
    Signature was worth $42 million based on the Primoris offer. He testified that a “bona fide
    offer” is what one “should consider the value of the company” to be because the offer was
    from a “knowledgeable buyer.” However, in order to award consequential damages based
    on the Primoris offer, the jury was required to find that the offer was “foreseeable” at the
    time the agreement was made. Moreno testified that Signature and Primoris began
    discussions in early 2014 and the first letter of intent was issued in May 2014, after the
    slaker project was completed. Moreno also said he did not have a conversation with IP
    about the possible acquisition and was not aware that anyone else from Signature told IP
    either. Michalk testified that negotiations between Signature and Primoris were
    confidential in 2014. There was no evidence presented that IP had any knowledge of the
    attempted sale of Signature at the time the agreement was made. Therefore, the $42
    57
    million in consequential damages resulting from the failure of the Primoris transaction is
    not supported by legally sufficient evidence. See City of 
    Keller, 168 S.W.3d at 810
    .
    Coker also testified that, although IP does not have to pay the IRS taxes for
    Signature, he felt it was responsible for the interest—he explained that Signature was
    unable to pay the taxes when they were due because IP had not paid the disputed
    invoices. However, the evidence showed that Signature was behind on its payroll taxes
    as early as 2013 and no slaker contract invoice had become due at that point. Coker
    testified that he used figures from documents Signature provided to him, instead of
    determining the figures himself. Ogden also testified that even though Signature had been
    behind on payroll taxes in 2013, it had “caught up” on the delinquent payroll taxes as of
    2014 before the slaker project began. Still, there was no evidence that IP would have
    “foreseen” that Signature would use the money it withheld for payroll taxes to pay its other
    financial requirements. Therefore, the jury’s award of $1,853,132 in IRS penalties was
    not supported by legally sufficient evidence. See
    id. Coker also
    explained how he determined the owners’ equity shares which the jury
    included in its damages award. Coker stated that if one takes the actual net worth of a
    company and subtracts its liabilities, the remainder equals the owners’ equity. Coker
    testified that he determined the owners’ equity numbers by comparing a December 31,
    2013 balance sheet with the March 11, 2016 pro forma closing sheet.15 IP countered with
    its expert, Domercq, who felt that that Coker’s determinations regarding the disputed
    15 Testimony showed that Coker identified the pro forma balance sheet as an indication of “what
    you think it’s going to be.” IP asked if it was an “estimated or projected balance sheet” and not an actual
    number, to which Coker responded in the affirmative.
    58
    invoices and owners’ equity numbers were incorrect. Domercq explained that Coker did
    not consider any other factors that could have contributed to Signature’s financial
    condition other than the disputed unpaid invoices.
    However, the jury could have also considered other testimony to arrive at its award
    for the owners’ equity numbers. Wilhelm testified that Signature lost work, including
    projects with Valero, due to the situation that arose between Signature and IP, which
    called into question Signature’s financial status. See Hoppenstein Props., Inc. v.
    McLennan Cnty. Apprisal Dist., 
    341 S.W.3d 16
    , 21 (Tex. App.—Waco 2010, no pet.)
    (providing that profits that plaintiff would have realized under contract between parties are
    direct damages, while profits plaintiff would have realized on other contracts are
    consequential damages). Ogden testified that Signature’s reputation suffered in the
    industry because Signature’s finances deteriorated, and it was unable to pay vendors and
    subcontractors due to the unpaid invoices. Additionally, there was testimony presented
    that Signature had struggled financially in 2013 due to a previous accident that occurred
    on a job with Exxon, which reduced its work during the investigation. Ogden explained
    that Signature lost about five months of jobs and revenue until it was exonerated in the
    Exxon accident. Testimony spoke of how “word” spreads in the industry, and Signature’s
    business was impacted by the accident according to Signature’s witnesses.
    Coker stated that he did not perform any independent market value analysis of
    Signature—instead, he relied on Primoris’s market value analysis done in April or May
    2014, and he looked at existing financial statements and the pro forma closing sheet to
    determine the equity amounts. Nevertheless, there was more than a scintilla of evidence
    59
    to support his determination that the owners lost $12.4 million in equity based on the
    evidence presented by Coker and other witnesses. See City of 
    Keller, 168 S.W.3d at 810
    ;
    
    Ridgway, 135 S.W.3d at 601
    . The jury could consider both Coker’s testimony and any
    other witnesses that presented testimony regarding the issues Signature faced due to the
    unpaid disputed invoices. See 
    Stuart, 964 S.W.2d at 921
    . The jury could have inferred
    that IP knew that the delay in paying invoices or refusing to pay invoices would cause
    Signature to struggle financially and IP would have been able to foresee the results that
    came about. See
    id. Moreover, Coker
    explained how he determined the owners’ equity amounts of $3
    million and $-9 million and the jury also heard additional testimony about Signature’s
    financial status throughout the time period in question. Because it was foreseeable that
    not paying invoices to a company who had struggled financially in the year before would
    cause major financial issues, the $12,431,501 consequential damages award was
    supported by sufficient evidence. See
    id. Therefore, we
    overrule that part of IP’s fourth issue regarding the owners’ equity
    damages and sustain the remainder of the issue.
    IV.    SUFFICIENCY OF THE EVIDENCE RELATED TO OGDEN’S CLAIMS
    By issues six and seven, IP challenges the sufficiency of the evidence to support
    Ogden’s claims.
    A.    Standard of Review
    We follow the same standard of review as laid out in Section 2A relating to
    Signature’s breach of contract claims.
    60
    B.     Assignment of Rights and Breach of Contract
    The benefits and burdens of a contract belong solely to the contracting parties,
    and no person can sue upon a contract unless he is a party to it or in privity with it. First
    Bank v. Brumitt, 
    519 S.W.3d 95
    , 104 (Tex. 2017). An exception to this general rule permits
    a person who is not a party to the contract to sue for damages caused by its breach if the
    person qualifies as a third-party beneficiary or an assignee. See id.; Brown v. Mesa
    Distribs., Inc., 
    414 S.W.3d 279
    , 284 (Tex. App.—Houston [1st Dist.] 2013, no pet.).
    An assignment is a manifestation by the owner of a right of his intention to transfer
    such right to the assignee. 
    Brown, 414 S.W.3d at 284
    . Unless qualified, the assignment
    is a transfer of one whole interest. See Concierge Nursing Ctrs., Inc. v. Antex Roofing,
    Inc., 
    433 S.W.3d 37
    , 45 (Tex. App.—Houston [1st Dist.] 2013, pet denied). Following an
    unqualified assignment, the assignor loses all rights to enforce the contract. See Mobil
    Oil Corp. v. Tex. Commerce Bank-Airline, 
    813 S.W.2d 607
    , 609 (Tex. App.—Houston [1st
    Dist.] 1991, no writ). Any right to performance by the assignor is extinguished. See
    id. In order
    to establish standing to maintain a breach of contract action, a plaintiff
    must either show it had third-party-beneficiary status or privity with a party to the contract.
    
    Brown, 414 S.W.3d at 284
    . Privity is established by proof that the defendant was a party
    to an enforceable contract with either the plaintiff or a party who assigned its cause of
    action to the plaintiff.
    Id. at 284–85.
    Whether a third party may sue to enforce the parties’ agreement depends not on
    whether the third party will benefit or on whether the parties knew that the third party
    would benefit, but on whether the contracting parties “intended to secure a benefit to [a]
    61
    third party” and “entered into the contract directly for the third party’s benefit.” First 
    Bank, 519 S.W.3d at 104
    (quoting Stine v. Stewart, 
    80 S.W.3d 586
    , 589 (Tex. 2002) (per
    curiam)).
    To determine whether the contracting parties intended to directly benefit a third
    party and entered into the contract for that purpose, courts must look solely to the
    contract’s language, construed as a whole.
    Id. at 102.
    The contract must include a “clear
    and unequivocal expression of the contracting parties’ intent to directly benefit a third
    party” and any implied intent to create a third-party beneficiary is insufficient.
    Id. (quoting Tawes
    v. Barnes, 
    340 S.W.3d 419
    , 425 (Tex. 2011).
    The contract between Signature and IP stated:
    Article 23.    LIMITATIONS   ON                    ASSIGNMENT               AND
    SUBCONTRACTORS:
    CONTRACTOR [Signature] shall not assign the AGREEMENT, its rights or
    obligations, without the prior written consent of COMPANY [IP], no[r] shall
    CONTRACTOR assign any money due or to become due without the prior
    written consent of COMPANY. Nothing in the AGREEMENT shall create
    any contractual relation between any subcontractors and COMPANY, and
    CONTRACTOR agrees that it is fully responsible to COMPANY for the acts
    and omissions of subcontractors.
    The contract is unambiguous that Signature did not have the right to assign its
    claims to Ogden without IP’s approval. However, even if Signature did have the
    unrestricted right to assign its claims under the contract, it would lose its right to sue for
    breach of contract upon assignment. See Mobil Oil 
    Corp, 813 S.W.2d at 609
    . Signature
    did not argue it gave up its rights under the contract to allow Ogden to sue; instead, it and
    Ogden both sued under the same argument. Ogden based his breach of contract claims
    on Signature’s breach of contract claims. But both entities cannot be entitled to pursue a
    62
    breach of contract claim against IP. See
    id. Signature also
    had no claim to pursue for
    Ogden’s personal damages, so that would be a claim it would be unable to assign. At
    best, Signature could have assigned Ogden its claims for breach of contract, but based
    on the allegations argued in the lawsuit, it did not.
    Although Ogden argued that IP did not preserve the issue because there was no
    jury question regarding Ogden’s breach of contract claims and the jury was allowed to
    decide if Signature assigned the right to sue for Ogden’s personal damages, the evidence
    is legally insufficient to support Question 4(a). It is apparent that Signature did not intend
    to assign its rights to Ogden, as it continued to pursue its own breach of contract allegation
    against IP. See
    id. We sustain
    IP’s sixth issue.
    Since we hold that Signature did not properly assign its breach of contract rights
    to Ogden, the damages awarded to Ogden under Question 4(c) related to breach of
    contract must be reversed.
    C.     Fraud
    Ogden’s fraud claim is also linked to Signature’s claims, and we have decided that
    Signature’s fraud claims were supported by legally insufficient evidence. The jury charge
    contained the same elements for fraud as in Signature’s claims but additionally included
    the following:
    A party commits fraud indirectly when it makes false representations to a
    third party with the intent that it be repeated to deceive the injured party or
    makes a false representation with information that would lead a reasonable
    man to conclude that there is an especial likelihood that it would reach the
    injured party and would influence the injured party’s conduct.
    63
    There was no evidence presented that IP made any statements knowing affirmatively that
    Ogden would individually rely on them. We previously found that the evidence was
    insufficient to support a fraud finding because Signature did not prove that a “single
    employee” committed all the elements of fraud within the scope of his employment. Here,
    there was no evidence presented that any single IP employee made misrepresentations
    to Signature intending for Ogden to act on them. See Dynegy, 
    Inc., 345 S.W.3d at 531
    .
    We sustain IP’s seventh issue.
    Since we hold that Ogden’s fraud claim is supported by legally insufficient
    evidence, the damages awarded to Ogden under Question 5(b) related to fraud must be
    reversed. Ogden was also awarded mental anguish damages due to the finding of fraud,
    which must also be reversed. We sustain IP’s eighth issue.
    V.      IP’S EXPERT WITNESS TESTIMONY
    By its ninth issue, IP alleges that the trial court abused its discretion when it
    excluded testimony from IP’s expert, Byrd, on the ground that his testimony was
    cumulative. We assume, but do not decide, that the trial court erred by excluding Byrd’s
    testimony. We proceed to evaluate whether the error is reversible. See TEX. R. APP. P.
    44.1(a) (“No judgment may be reversed on appeal on the ground that the trial court made
    an error of law unless the court of appeals concludes that the error complained of: (1)
    probably caused the rendition of an improper judgment; or (2) probably prevented the
    appellant from properly presenting the case to the court of appeals.”).
    A judgment may not be reversed unless the error “can be said to have contributed
    in a substantial way to bring about the adverse judgment.” Lorusso v. Members Mut. Ins.,
    64
    
    603 S.W.2d 818
    , 819–20 (Tex. 1980) (citing King v. Skelly, 
    452 S.W.2d 691
    , 696 (Tex.
    1970)). This rule is based on our understanding that “a litigant is not entitled to a perfect
    trial for, indeed, few trials are perfect.”
    Id. at 819.
    The determination of whether the error
    probably caused the rendition of an improper judgment “necessarily is a judgment call
    entrusted to the sound discretion and good senses of the reviewing court.” McCraw v.
    Maris, 
    828 S.W.2d 756
    , 759 (Tex. 1992), and we have recognized “the impossibility of
    establishing a specific test for determining harmful error.” Caffe Ribs, Inc. v. State, 
    487 S.W.3d 137
    , 145 (Tex. 2016) (citing State v. Cent. Expressway Sign Assocs., 
    302 S.W.3d 866
    , 870 (Tex. 2009)); see also 
    Lorusso, 603 S.W.2d at 821
    (citing Standard Fire Ins. v.
    Reese, 
    584 S.W.2d 835
    (Tex. 1979)).
    The role excluded evidence plays in the context of trial is important, and the
    supreme court has provided guidelines to assist trial courts in applying the reversible error
    standard. See Cent. Expressway Sign 
    Assocs., 302 S.W.3d at 870
    . Exclusion is likely
    harmless if the evidence was cumulative or if the rest of the evidence was so one-sided
    that the error likely made no difference in the judgment.
    Id. By contrast,
    exclusion of the
    evidence is likely harmful if it was “crucial to a key issue.”
    Id. Thus, in
    determining whether the exclusion of evidence was harmful, we must
    review the entire record and we apply the same standard—whether the erroneous
    exclusion of evidence probably caused the rendition of an improper judgment—even
    when the excluded evidence related to a key issue. Gunn v. McCoy, 
    554 S.W.3d 645
    ,
    668 (Tex. 2018).
    65
    IP argues that Byrd’s testimony was crucial because it rebutted Signature’s
    evidence presented about piping drawings. However, multiple witnesses testified about
    the drawings prior to Byrd. Although piping was an issue discussed in terms of whether it
    was included in Signature’s original bid, we conclude that excluding Byrd’s more technical
    testimony did not cause the rendition of an improper judgment. See
    id. Piping, its
    inclusion or lack thereof in the original bid, and its costs in the disputed
    invoices was one of many expenses IP challenged. The jury accepted the full amount of
    the disputed invoices that Signature claimed. Therefore, it is unlikely that Byrd’s testimony
    would have swayed the jury in such a manner that the judgment would be different. See
    id. Additionally, multiple
    witnesses testified about the piping, drawings, re-drawings, and
    issues regarding mistakes throughout the weeks-long trial. We find it unlikely that Byrd’s
    testimony would have changed the outcome of the jury’s decision and we overrule IP’s
    ninth issue.
    VI.    INDEMNITY
    By its tenth issue, IP argues the trial court committed reversible error by refusing
    to enforce Signature’s duty to indemnify.
    The slaker contract contained an indemnity provision that stated: “In the event the
    liability of the CONTRACTOR [Signature] shall arise by the reason of the sole negligence
    of COMPANY [IP], then and only then, the CONTRACTOR shall not be liable under the
    provisions of this paragraph.” The claims raised during trial solely related to what
    Signature and Ogden claimed was IP’s negligence.
    66
    Here, within the four corners of the contract, the language specifically stated that
    Signature would not be liable under the indemnification section if liability arose by reason
    of “the sole negligence of” IP. The lawsuit arose because IP did not pay the disputed
    invoices, and that disagreement is what gave rise to Ogden’s claims against IP. Because
    Ogden’s damages were due to the actions of IP, Signature was not required to indemnify
    IP for the costs it incurred defending against Ogden. We overrule IP’s tenth issue.16
    VII.    CONCLUSION
    In summary, we overrule IP’s issue regarding Signature’s breach of contract claim
    and its challenge to the breach of contract actual damages. We affirm the trial court’s
    judgment as to actual damages.
    We sustain IP’s issues related to Signature’s fraud and promissory estoppel
    claims. We reverse the trial court’s judgment as to fraud and promissory estoppel claims
    and render judgment that Signature take nothing by way of those claims.
    We further hold there is legally insufficient evidence to support the consequential
    damages award of $42 million for the lost sale opportunity and $1,853,132 million in IRS
    penalties. We reverse and render judgment that Signature take nothing by way of its
    request for damages arising from the loss of the Primoris sale and IRS penalties.
    Additionally, we affirm the consequential damages relating to the owners’ lost equity in
    the amount of 12,431.501.
    16 IP’s eleventh issue is relevant only if any of Ogden’s claims survived our review. Because we
    sustained IP’s issues as to all of Ogden’s claims, this issue is now moot and we do not address it. See TEX.
    R. APP. P. 47.1.
    67
    We also sustain IP’s issues related to Ogden’s claims for breach of contract and
    fraud. We reverse the portion of the trial court’s judgment awarding damages to Ogden
    under those causes of action, and we render a take-nothing judgment on behalf of IP.
    GINA M. BENAVIDES,
    Justice
    Delivered and filed the
    30th day of April, 2020.
    68