Leafguard of Texas, Inc. v. Stephen Ray Guidry ( 2023 )


Menu:
  •                                        In The
    Court of Appeals
    Ninth District of Texas at Beaumont
    ________________
    NO. 09-21-00034-CV
    ________________
    LEAFGUARD OF TEXAS, INC., Appellant
    V.
    STEPHEN RAY GUIDRY, Appellee
    ________________________________________________________________________
    On Appeal from the 60th District Court
    Jefferson County, Texas
    Trial Cause No. B-203,669
    ________________________________________________________________________
    MEMORANDUM OPINION
    Leafguard appeals from a take-nothing judgment as to its claim against Guidry
    and a monetary judgment in favor of Guidry on Guidry’s counterclaim. Appellant
    raises six issues in this appeal: 1) the court improperly allowed Guidry’s witness to
    testify as an expert when Guidry failed to properly designate the witness as an expert;
    2) the evidence is insufficient to prove Leafguard breached the contract; 3) the
    evidence is insufficient to prove any damages were caused by Leafguard; 4) the
    1
    evidence is insufficient to support the award of past and future damages to Guidry;
    5) there is insufficient evidence to support the attorney fee award; and 6) because
    Guidry failed to pay the amount due under the contract, Leafguard is entitled to
    judgment for the contract amount. We reverse and remand.
    I. Background
    In 2017, Hurricane Harvey damaged Guidry’s home, including portions of the
    roof and some interior drywall. Guidry retained Leafguard 1 to make repairs to his
    home including updating and replacing his siding and windows at a total contract
    price of $34,613.2 After installation, Guidry notified Leafguard of some problems
    with the work and Leafguard made further repairs, replaced the siding, and it
    replaced several of the windows at its own expense. Guidry argued that despite
    Leafguard’s remedial measures, problems remained. For that reason, Guidry did not
    pay Leafguard anything for the work and eventually Leafguard filed a lawsuit
    against Guidry for the contract price, plus interest and attorney’s fees. In the Original
    and Amended Petitions, Leafguard alleged claims for breach of contract, quantum
    meruit, unjust enrichment, prompt payment, and sought attorney’s fees, costs, and
    interest. Guidry filed a general denial and then counterclaimed, alleging that
    1
    Leafguard’s complete name is Leafguard of Texas, Inc., d/b/a Beldon
    Houston.
    2
    There were separate contracts for the siding and the windows, as well as a
    change order.
    2
    Leafguard’s work was not only substandard, but that it caused damage to his home,
    requiring him to incur substantial repair costs.
    After a bench trial, the trial court found in favor of Guidry as to his claims for
    breach of contract and awarded Guidry damages in the amount of $26,236 in past
    damages and $27,703.20 in future damages, together with attorney’s fees in the
    amount of $10,000. The trial court denied any relief to Leafguard on its claims. The
    trial court entered findings of fact and conclusions of law in support of its judgment.
    Leafguard timely filed a notice of appeal.
    Summary of Evidence Presented at Trial
    A. Christopher Jackson’s Testimony
    Leafguard’s general manager, Christopher Jackson, testified about his
    responsibilities in the case, noting that he became involved in the matter only after
    Guidry failed to pay for the work that Leafguard had performed. He authenticated
    the contracts between Leafguard and Guidry and stated that they reflected normal
    rates and materials for the windows and siding that were the subject of the contracts.
    Jackson sent technicians to the project location to verify correct sizes and
    measurements and indicated that Guidry reported no problems with the work until
    Leafguard requested payment of the contract price, in approximately June or July of
    2018.
    3
    According to Jackson, after payment became an issue, Guidry complained that
    the siding was the wrong color and incorrectly installed, and that the windows
    leaked. Jackson acknowledged that the siding, as initially installed, was not the color
    that Guidry had ordered, the windows were not properly caulked, and that the first
    siding subcontractor Leafguard hired had painted the siding, voiding the warranty.
    Leafguard consequently removed the siding that was the wrong color and installed
    all new siding in the correct color. When removing that siding, Leafguard’s new
    siding contractor discovered that Guidry’s house needed additional bracing and
    fasteners so that the finished project would meet Texas Department of Insurance
    standards for windstorm compliance. This discovery increased the scope of the work
    and Leafguard issued a change order, which Guidry signed, for an additional $2500.
    That change order and the agreements for the work were entered into evidence
    without objection. According to the original agreement, the scope of the work
    included removal of the existing vinyl siding and application of “Hardie” “autumn
    tan” siding for $14,900; the installation of 14 “AMI 2000 series beige” windows for
    $17,203; and a subsequent change order to replace fascia and soffits for $2500. The
    work orders reflect the dimensions and location of each window, as well as the
    lengths of the fascia, soffits, and frieze boards to be installed.
    Jackson denied that Leafguard or its contractors disturbed Guidry’s roof while
    installing, removing, or reinstalling the siding or the windows.
    4
    According to Jackson, Guidry’s complaints about window leaks prompted
    Leafguard to attempt to identify the problem, but it was unable to do so.
    Notwithstanding Leafguard’s inability to identify the alleged window leaks, it
    replaced six of the fourteen windows it had installed, at no additional cost to Guidry.
    Although the windows passed inspection for hurricane compliance purposes, the
    reinstalled siding was not inspected because Guidry did not permit the inspector to
    perform the inspection. Jackson explained the procedures by which the fascia and
    soffits were installed by Leafguard’s contractors, and how they accomplished the
    installation without lifting the shingles; he insisted they did not disturb the roof.
    B. Stephen Guidry’s Testimony
    Guidry, the defendant and counter-plaintiff, testified that although he did sign
    the contracts with Leafguard, the Leafguard salesman misrepresented various
    unspecified contractual terms. Guidry further testified that Leafguard’s
    workmanship was unacceptable, in that Leafguard damaged his roof, causing it to
    leak, and he testified that “some of the windows” that Leafguard installed also
    leaked. He further stated that the material Leafguard used was thicker than the vinyl
    siding that previously was installed on his house. Guidry stated that the use of this
    thicker material resulted in the roof failing to overhang the fascia, which caused
    water to leak into his house. He denied that his prior vinyl fascia boards were
    composed of a thin sheet of vinyl wrapped around a board, rendering the vinyl fascia
    5
    material approximately the same thickness as the new siding material that Leafguard
    installed. He further stated that leaks developed only after Leafguard performed its
    work. Guidry acknowledged that after Hurricane Harvey, C & H Roofing repaired
    sections of his then three-year-old roof. He stated, however, that because only a
    small portion of the roof needed repair after the hurricane, he neither needed nor
    received a new windstorm certificate for his roof when C & H completed its repair
    work. He also testified that C & H installed a new roof after Hurricane Harvey, and
    that it was windstorm certified at that time. Guidry testified later that he did not
    receive a new windstorm certification after Hurricane Harvey for the limited amount
    of repair work C & H performed.
    Guidry explained that he took photographs of the work but he was unable to
    state whether the pictures were taken before, during, or after Leafguard performed
    work on the property. He also confirmed that he had not paid Leafguard any money
    for the work and averred that all the windows needed replacement—even though
    only two of them leaked. Guidry’s testimony contradicted his earlier testimony that
    six of his windows leaked after Leafguard replaced them. Although Guidry insisted
    that Leafguard had raised the shingles on the roof, thereby damaging his roof, he
    could produce no evidence that it occurred.
    6
    C. Kenneth McCurtain’s Testimony
    McCurtain, a carpenter, testified that although he had performed previous
    work for Guidry, he became familiar with the issues relevant to this case when
    Guidry called him to evaluate some cosmetic issues in Guidry’s kitchen. At that
    time, Guidry apprised the witness of his complaints of roof and window leaks.
    McCurtain inspected the eaves and windows and concluded the windows were
    improperly installed. McCurtain testified that due to shoddy workmanship, the
    overhang eaves were rotting, and the fascia boards were incorrectly installed and
    were “too far out[]” for the roof decking to cover them. In his opinion, this
    shortcoming permitted water to leak into Guidry’s house. He testified the proper
    remedy would require the replacement of the entire roof.
    McCurtain testified that he did not remedy the leaks around the windows, but
    instead performed interior drywall work, which he identified in Guidry’s photos. He
    indicated that the only way to address the air and water leaks would be to install new
    windows because the current windows might bend or break during the reinstallation
    process. He also stated that all Guidry’s windows leaked.
    When asked about the price of the repair work, McCurtain testified that the
    repair estimates he provided in July of 2019, over a year before the trial date, were
    reasonable at the time and place given, but the estimates should be adjusted upward
    twenty percent to account for increased material and labor costs. In addition, he
    7
    testified that Guidry paid him $5462 and $5874, for repair projects that he completed
    on Guidry’s residence.
    II. Standard of Review
    Leafguard’s arguments fall into two categories: abuse of discretion as to
    evidentiary rulings, and sufficiency of the evidence to support the trial court’s
    judgment.
    As for the legal sufficiency challenges to the judgment, evidence is legally
    insufficient to support a finding when: (1) the record discloses a complete absence
    of evidence of a vital fact; (2) the court is barred by rules of law or of evidence from
    giving weight to the only evidence offered to prove a vital fact; (3) the evidence
    offered to prove a vital fact is no more than a mere scintilla; or (4) the evidence
    establishes conclusively the opposite of a vital fact. Crosstex N. Tex. Pipeline, L.P.
    v. Gardiner, 
    505 S.W.3d 580
    , 613 (Tex. 2016) (citation omitted). Evidence is also
    considered legally insufficient if it is conclusory, meaning that it “asserts a
    conclusion with no basis or explanation.” Windrum v. Kareh, 
    581 S.W.3d 761
    , 768-
    70 (Tex. 2019).
    In a bench trial, as the sole judge of the credibility of the witnesses and the
    weight to give their testimony, the trial court may choose to believe one witness and
    disbelieve another. City of Keller v. Wilson, 
    168 S.W.3d 802
    , 819 (Tex. 2005). The
    trial court also “may disregard even uncontradicted and unimpeached testimony
    8
    from disinterested witnesses.” Id. at 820. But it is “not free to believe testimony that
    is conclusively negated by undisputed facts.” Id. In our appellate review, we “credit
    favorable evidence if [a] reasonable [trier of fact] could, and disregard contrary
    evidence unless [a reasonable trier of fact] could not.” Id. at 827. “The final test for
    legal sufficiency must always be whether the evidence at trial would enable
    reasonable and fair-minded people to reach the verdict under review.” Id.
    In challenging the factual sufficiency of the evidence supporting an adverse
    finding on which Leafguard did not have the burden of proof at trial, Leafguard must
    demonstrate that there is insufficient evidence to support the adverse
    findings. Croucher v. Croucher, 
    660 S.W.2d 55
    , 58 (Tex. 1983); Am. Interstate Ins.
    Co. v. Hinson, 
    172 S.W.3d 108
    , 120 (Tex. App.—Beaumont 2005, pet.
    denied). When reviewing a factual sufficiency challenge, we consider and weigh all
    the evidence in support of and contrary to the trial court’s finding. Maritime
    Overseas Corp. v. Ellis, 
    971 S.W.2d 402
    , 406-07 (Tex. 1998). We set aside a finding
    only if it “is so contrary to the overwhelming weight of the evidence as to be clearly
    wrong and unjust.” Dyson v. Olin Corp., 
    692 S.W.2d 456
    , 457 (Tex. 1985) (citation
    omitted).
    III. Analysis
    We will first consider the sufficiency of the evidence points raised by
    Leafguard in its second, third, fourth, fifth and sixth issues. Guidry’s theory of the
    9
    case is that Leafguard materially breached its contract with him, thereby excusing
    his admitted failure to pay the contract price and exposing Leafguard to liability for
    its alleged damage to his home.
    A. The Contract
    In its findings of fact and conclusions of law, the trial court found that
    Leafguard materially breached its contract with Guidry, thus excusing Guidry’s
    further performance under the parties’ contract, including Guidry’s payment for the
    materials and installation services that Leafguard provided. Assuming, for purposes
    of this analysis, that the trial court correctly determined that Leafguard materially
    breached the contract before Guidry’s payment became due, the inquiry does not end
    there; Leafguard’s material breach, if any, would not necessarily excuse Guidry’s
    failure to pay the contract amount if Guidry treated the contract as continuing. See
    Long Trusts v. Griffin, 
    222 S.W.3d 412
    , 415 (Tex. 2006) (per curiam).
    Guidry contends that a material breach by one contracting party will excuse
    further performance by the other party. We agree that a material breach may entitle
    the non-breaching party to terminate the contract and sue the breaching party for the
    breach if he chooses to do so. See 
    id.
     (citation omitted). When, however, the
    nonbreaching party decides to treat the contract as continuing, even after the other
    party materially breached the agreement, the nonbreaching party may not then seek
    to excuse his own nonperformance. See Dowtech Specialty Contractors, Inc. v. City
    10
    of Weinert, 
    630 S.W.3d 206
    , 216 (Tex. App.—Eastland 2020, pet. denied). Here, the
    record reflects that Guidry chose to continue the contract and therefore he was not
    excused from paying Leafguard under the contracts. Specifically, we note that
    Guidry did not elect to terminate the contract, bring in a new contractor to do the
    job, or file suit as soon as he learned that Leafguard had installed the wrong siding
    on his house. Instead, he claimed the benefit of his contractual bargain and requested
    Leafguard to provide and install the siding specified in the contract. Guidry likewise
    requested and received replacement windows for the windows that were alleged to
    have been improperly installed, and he gave Leafguard the opportunity to cure its
    defects. Guidry did not sue Leafguard until December 5, 2019, nearly eight months
    after Leafguard sued Guidry for payment. Given this evidentiary and procedural
    posture of the case, we hold Guidry treated the window and siding contracts as
    ongoing, and therefore may not refuse payment based on Leafguard’s previous
    material breach.
    Guidry counterclaimed for breach of contract. “There are two measures of
    damages for the breach of a construction contract: (1) remedial damages, which is
    the cost to complete or repair less the unpaid balance on the contract price, and (2)
    difference-in-value damages, which is the difference between the value of the
    building as constructed and its value had it been constructed according to the
    contract.” (citations omitted). See McGinty v. Hennen, 
    372 S.W. 3d 625
    , 627 (Tex.
    11
    2012) (per curiam). The trial court found in favor of Guidry and made the following
    findings regarding damages: “[past damages] in the amount of $26,236.00…[and]
    future [damages] in the amount of $27,703.20 payable to Guidry. It appears that
    Guidry attempted to establish, to some extent, a claim for remedial damages through
    McCurtain’s testimony about various costs to repair the alleged damage. The
    damages award is not supported by the evidence.
    Guidry’s evidence alleging faulty installation of either the siding or windows
    caused damage to the interior of his home are not supported by evidence that such
    costs were reasonable and necessary. It is not sufficient that the costs were of a
    nature and character that they were necessary and an amount was actually paid for
    them. Evidence showing the amounts paid were “reasonable” is also required. 
    Id.,
    citing Mustang Pipeline Co. v. Driver Pipeline Co., 
    134 S.W.3d 195
    , 200 (Tex.
    2004) (per curiam).
    B. Legal and Factual Sufficiency
    Leafguard contends the evidence is legally and factually insufficient to
    support the trial court’s judgment awarding damages to Guidry. We will “sustain
    a legal-sufficiency challenge to an adverse finding if our review of the evidence
    demonstrates a complete absence of a vital fact, or if the evidence offered is no more
    than a scintilla.” Burbage v. Burbage, 
    447 S.W.3d 249
    , 259 (Tex. 2014). A factual
    sufficiency challenge, on the other hand, requires us to evaluate the evidence as a
    12
    whole, and determine whether it supports the judgment. Maritime Overseas Corp.,
    971 S.W.2d at 406-07. When both legal and factual sufficiency are in dispute, we
    first address the matter of legal sufficiency. See Windrum, 581 S.W.3d at 781.
    1. The Windows
    McCurtain and Guidry testified that some of the windows leaked, and
    McCurtain opined the windows were improperly installed because they were not
    installed with the top of each window above the frieze board, and that this error
    permitted rainwater to enter Guidry’s house. This testimony is legally sufficient
    evidence that the windows were not correctly installed. We therefore must proceed
    to review the factual sufficiency of the evidence question.
    The record contains evidence that there was leakage around some of the
    windows. Despite the contrary evidence that the windows did not leak when
    Leafguard tested them on multiple occasions, the trial court, as trier of fact, could
    have believed that there was leakage around some of the windows. Because windows
    would not be expected to leak, absent a construction defect, the trial court could have
    made an implicit finding that Leafguard improperly installed the windows, that
    improper installation proximately caused the leaks, and that Leafguard therefore was
    liable to Guidry for any resulting damages.
    The damage evidence regarding the windows consists of McCurtain’s
    testimony that his company performed interior drywall finish work at a cost of
    13
    $5,874. McCurtain testified that all new windows would need to be installed because
    the existing windows, if removed and reinstalled, “can break, they can bend, they
    could - - anything could happen to them to where they’re not as sturdy as they were
    before.” Guidry’s evidence was factually insufficient to show the price paid for the
    work performed was reasonable and necessary. See McGinty, 
    372 S.W.3d at 627
    (describing the measure of damages). Absent evidence that the amount paid was
    reasonable, no damages can be awarded based on the evidence in the record. 
    Id.
     In
    addition, we note that in its Findings of Fact and Conclusions of Law, the trial court
    found that Guidry had sustained incidental damages, notwithstanding the fact that
    the parties’ contracts conspicuously disclaimed liability for incidental or
    consequential damages. For this additional reason, the trial court erred in awarding
    the enumerated elements of incidental/consequential damage. Therefore, any award
    of consequential damages is disallowed. We sustain Leafguard’s fourth point. We
    will remand the case to the trial court for a new trial to determine whether and to
    what extent any windows must be replaced and the reasonable and necessary cost
    therefor.
    2. Soffit and Fascia
    Guidry’s complaint was that the Leafguard product, workmanship, or both,
    somehow caused the fascia boards to extend farther toward the outermost edge of
    the roof shingles than they previously had, and that this change caused water to leak
    14
    into Guidry’s home. Specifically, Guidry contended that the new fascia boards that
    Leafguard installed were thicker than the prior fascia boards, and that Leafguard had
    installed “kickers” that lengthened the rafter tails, thus extending the roof line
    beyond its earlier profile.
    The evidence is legally sufficient to support Guidry’s position, in that Guidry,
    himself, testified regarding the thickness of the new fascia boards Leafguard
    installed, and further testified that Leafguard’s work extended the rafter tails. This
    evidence alone, if believed by the trial court, is legally sufficient to support the trial
    court’s finding. As Leafguard has observed, however, a comparison of the “before”
    and “after” photographs indicates that both of Guidry’s theories of recovery are
    factually inaccurate, thus extinguishing any possibility that the trial court’s judgment
    is supported by factually sufficient evidence. In particular, we note that the
    photographs taken before Leafguard’s work commenced show a certain amount of
    shingle overhang, and the photographs taken after McCurtain’s work was completed
    show the same,3 thereby belying the argument that the outer edge of the newly
    installed fascia boards was somehow closer to the edge of the shingles than were the
    3
    The new windows had beige frames, as required by the terms of the contract.
    It is therefore a simple matter to identify the old windows as being the ones with the
    brown frames. Because Guidry stated that Leafguard performed the window
    replacement work before performing the siding and fascia work, we can identify the
    old siding, fascia, and shingle overhang by viewing the photographs showing the old
    windows.
    15
    old fascia boards that Leafguard had replaced. The evidence actually shows the
    opposite fact of what the court found. Therefore, we find the evidence factually
    insufficient to support this finding.
    Even if this evidence were factually sufficient to support a decision that
    Leafguard’s fascia work required remediation, the evidence fails to show the
    reasonable cost of doing so. Here, as with the windows, the evidence shows only the
    amount paid for the work. Absent evidence that the amount paid was reasonable, no
    damages can be awarded based on the evidence in the record. 
    Id.
     We sustain
    Leafguard’s second point. We will remand the case to the trial court for a new trial
    to determine whether and to what extent remediation is required by the installation
    of the fascia and soffits and, if found, the reasonable and necessary cost therefor.
    See Cain v. Bain, 
    709 S.W.2d 175
    , 176 (Tex. 1986) (per curiam).
    3. The Overhang 4
    McCurtain’s testimony arguably constitutes some evidence that Guidry’s
    overhang was “inadequately built.” His testimony further supports the proposition
    that in 2019, $9658 would have been a reasonable cost to repair Guidry’s overhang
    and that this figure would have increased twenty percent by the time of trial.
    Guidry’s testimony does not, however, establish that Leafguard built, or contracted
    4
    In the context of this case, it appears, but is not certain, that Guidry, Guidry’s
    attorney, and McCurtain were using the term “overhang” to refer to plywood roof
    decking.
    16
    to build, the overhang on Guidry’s house. Instead, the evidence establishes the
    opposite fact. Photos produced by Guidry show deteriorated, old decking which no
    longer reached the edge of the roofline. The contract did not provide for Leafguard
    to replace any roof decking. This defect would have been hidden from Leafguard
    when installing the fascia, and there is evidence this defect was within the purview
    of the roofing company that replaced all, or part of, the roof after Hurricane
    Harvey—depending upon which version of Mr. Guidry’s testimony is accepted.
    Given the lack of evidence that Leafguard was in any way responsible for the
    allegedly substandard construction of the overhang, Leafguard cannot be held liable
    for the cost of modifying it to meet an acceptable standard. For this reason, the trial
    court erred in awarding Guidry the estimated cost of repairing the overhang.
    4. The Roof
    The record contains unsupported accusations by Guidry that Leafguard
    damaged Guidry’s roof “by lifting the shingles” in some places when applying the
    fascia and soffit boards. This evidence is factually insufficient to support the trial
    court’s judgment.
    The trial court awarded Guidry the entire cost of replacing his roof as that
    figure was established by McCurtain’s testimony. The record, however, lacks
    factually sufficient evidence to show that Leafguard damaged the roof or that Guidry
    needed a new roof. Quite the contrary, Guidry’s testimony indicates that he wanted
    17
    a whole new roof at least partially so that there would be no areas of nonmatching
    shingles. McCurtain’s testimony regarding the possible need for a new roof is
    conclusory, at best, in that it omits an explanation of how Leafguard actually caused
    the damage to the roof and why the entire roof, or any part of it, ostensibly needed
    replacement. This testimony therefore constitutes no evidence of probative force
    upon which the trial court could have found that Guidry’s roof needed to be replaced,
    and it consequently was error to award Guidry this element of damages.
    Although Guidry’s testimony also suggests that he wanted, or needed, a new
    roof so that his roof would qualify for a windstorm inspection certificate, the
    evidence in the record is factually insufficient to establish that Leafguard caused the
    alleged damage to Guidry’s roof. Instead, it is equally likely that the roof issues were
    attributable to residual, unrepaired hurricane damage. Guidry’s argument that his
    roof did not used to leak is not evidence of Leafguard’s supposed malfeasance, but
    instead relies on the fallacy of post hoc ergo propter hoc. Because mere chronology
    will not support a finding of causation, we must reverse the trial court’s implicit
    finding that Leafguard damaged Guidry’s roof to the extent that Guidry needed a
    new roof. See Wortham Bros., Inc. v. Haffner, 
    347 S.W.3d 356
    , 361 (Tex. App.—
    Eastland, 2011, no. pet.) (Generally, expert testimony is required to establish the
    necessity and reasonableness of subsequent roof replacements); see also Cain v.
    Bain, 709 S.W.2d at 176 (the court of appeals must consider and weigh all the
    18
    evidence, and should set aside the verdict only it if is so contrary to the
    overwhelming weight of the evidence as to be clearly wrong and unjust) (citations
    omitted).
    We sustain Leafguard’s second and third points of error and remand these
    issues to the trial court for a new trial.
    C. Attorneys’ Fees
    Having sustained Leafguard’s issues two through four, we will not address
    the issues of damages and attorney fees and remand those issues to the trial court for
    determination at a new trial.
    Accordingly, we reverse the decision of the trial court, and conclude that
    under the rationale of Long Trusts, Guidry is obligated to pay Leafguard at least
    some amount of the contract price of $34,613,5 plus interest and attorney’s fees as
    contractually provided. See Long Trusts, 222 S.W.3d at 415-16; Rohrmoos Venture
    v. UTSW DVA Healthcare, LLP, 
    578 S.W.3d 469
    , 488-89 (Tex. 2019) (noting that
    parties may contractually provide for a reasonable attorney’s fee). This sum should
    be offset by Guidry’s reasonable and necessary repair costs, if such costs are raised
    by Guidry’s pleadings and properly substantiated by the evidence. See McGinty, 
    372 S.W.3d at 627
     (describing the measure of damages).
    This figure represents the siding cost of $14,900, the window cost of
    5
    $17,213, and an agreed change order for $2500.
    19
    IV. Conclusion
    The judgment of the trial court is not factually supported by the evidence.
    Leafguard conclusively established that Guidry failed to pay the contract price for
    the work it performed; and Guidry’s evidence in support of his counterclaims lacks
    sufficient factual support to sustain the judgment in this case. Having sustained
    issues two through four, we decline to reach issues one, five and six as ruling on
    those issues would not afford the Appellant any greater relief. Tex. R. App. P. 47.1.
    This case is reversed and remanded for a new trial to establish the contractual
    liability of Guidry to Leafguard and to determine any reduction of the contract price
    to which Guidry may be entitled, including either party’s reasonable and necessary
    attorney fees, consistent with this opinion.
    REVERSED AND REMANDED.
    ________________________________
    JAY WRIGHT
    Justice
    Submitted on June 2, 2022
    Opinion Delivered May 11, 2023
    Before Horton, Johnson and Wright, JJ.
    20
    

Document Info

Docket Number: 09-21-00034-CV

Filed Date: 5/11/2023

Precedential Status: Precedential

Modified Date: 5/12/2023