BNM Ventures, LLC v. Shannon Green ( 2023 )


Menu:
  • AFFIRMED in part; REVERSED and RENDERED in part; VACATED and
    REMANDED and Opinion Filed June 16, 2023
    S  In The
    Court of Appeals
    Fifth District of Texas at Dallas
    No. 05-22-00474-CV
    BNM VENTURES, LLC, Appellant
    V.
    SHANNON GREEN, Appellee
    On Appeal from the 95th District Court
    Dallas County, Texas
    Trial Court Cause No. DC-20-08630
    MEMORANDUM OPINION
    Before Justices Reichek, Nowell, and Garcia
    Opinion by Justice Reichek
    In this appeal following a bench trial, BNM Ventures, LLC challenges the
    trial court’s judgment in favor of Shannon Green on his claim for breach of a
    settlement agreement. BNM brings two issues generally asserting the evidence does
    not support the trial court’s finding of breach or its award of damages. Because we
    conclude Green failed to adduce any evidence at trial to show the cost-of-completion
    damages he sought to recover were reasonable, we reverse the trial court’s award of
    those damages and render judgment that Green recover no remedial damages.
    Because the remaining damages are unchallenged, they are affirmed. We remand
    the case to the trial court for a reassessment of attorney’s fees in light of this
    disposition.
    Background
    BNM constructed a home and sold it to Green in April 2019. Several weeks
    later, the area received substantial rainfall and the house flooded. Green hired
    Lighthouse Engineering, L.L.C. to do a drainage inspection.
    A report prepared by Lighthouse concluded there were several issues with the
    water drainage on the property, including that the grading around the house did not
    meet the minimum requirements of the International Residential Code (“IRC”).
    Lighthouse drafted an engineering report recommending remediation measures and
    attached a drawing outlining their recommendations.
    On August 8, 2019, Green’s attorney sent Michael White, BNM’s managing
    partner, a notice of construction defects pursuant to the Texas Residential
    Construction Liability Act. Among the defects listed in the notice were that the
    “driveway was improperly constructed and allows water to run toward the house,”
    and the “final grade was improperly completed on the front and left sides of the
    Property, which causes water to drain toward the house, rather than away from it.”
    Following a mediation, Green and BNM entered into a settlement agreement in
    which BNM agreed to,
    Modify the driveway and grading per the Lighthouse
    Engineering, LLC report attached as Exhibit “B.” Post-
    completion inspection by an engineer will be performed at
    –2–
    Shannon Green’s expense within 15 days from the date that
    BNM notifies Mr. Green that repairs are believed to be complete;
    if the post-completion inspection determines that the
    modifications made by BNM did not conform to the
    specifications set forth in Exhibit “B,” BNM will make further
    modifications until those specifications are met.
    In May 2020, White informed Green that BNM’s work was ready for
    inspection. The Lighthouse engineer who drafted the original report determined the
    repairs did not conform to the report’s specifications. White disputed the engineer’s
    conclusion, particularly with respect to the driveway, stating the report was “very
    ambiguous.” According to White, the report did not require the driveway to be
    broken out and replaced to the extent Lighthouse now claimed was necessary. White
    ceased work on the exterior of the house and said he wanted the parties’ attorneys to
    resolve the conflict.
    On June 1, Green’s attorney sent an email to BNM’s attorney stating that
    Green would be “hiring another contractor to finish the exterior work that [BNM]
    refuses to complete.” Two days later, Green sent a text message to White stating he
    was not sure if White was “waiting on a deal” to complete the repairs, but he was
    hiring another company to complete the work. Lighthouse issued an inspection
    report the same day stating the work done by BNM was deficient in several ways
    including, (1) the grading around the perimeter did not meet the minimum required
    by the IRC, and (2) the driveway was not broken out and “swaled” as recommended
    in the repair plan.
    –3–
    On June 29, Green received a bid from Armadillo Fences, Decks and
    Remodels stating the cost to make the necessary modifications to his property would
    be $8,600. Payment by credit card would add an additional service charge of
    $301.15. The estimate stated it was also “HIGHLY recommended” to have sod laid
    on the property. Ten days later, Armadillo Fences provided Green with an estimate
    of $4,288.05 to install 2,199 square feet of sod. Green hired Armadillo Fences and
    the record shows the company completed the drainage work and laid sod. Green
    paid the estimated amounts, including the credit card fee.
    BNM filed this suit seeking a declaratory judgment that the settlement
    agreement did not require more construction than was required by “the plain
    language and plain meaning” of the original Lighthouse engineering report. BNM
    asked the court to specifically declare that BNM’s interpretation of the report’s
    specifications for the driveway was correct. BNM stated there was a justiciable
    controversy because Green indicated his intention to recover the additional costs of
    having the repairs performed “pursuant to his own interpretation of the Lighthouse
    report.” Green brought a counterclaim for breach of contract asserting that BNM
    refused to make the changes necessary for its work to conform to the original
    engineering report’s specifications. BNM moved for, and was granted, an order of
    mediation. No settlement resulted.
    A trial was conducted before the court without a jury. White testified he
    believed the work performed by BNM was consistent with the engineering report
    –4–
    prepared by Lighthouse. White further testified BNM did not refuse to finish the
    drainage work, but had merely paused the work to allow the attorneys for both sides
    to resolve the issue of what the Lighthouse report required. White conceded the
    grading around the house did not meet the minimum slope required by the IRC, but
    stated the code provides exceptions to that requirement.       White did not ask
    Lighthouse whether reliance on an exception would be permitted.
    Michael Gandy, owner of Lighthouse, testified the engineering report clearly
    required the driveway to be broken out and rebuilt to divert water away from the
    house and meet code requirements. The work done by BNM, according to Gandy,
    was insufficient to resolve the property’s drainage issues. Gandy stated he could
    find no record of anyone from BNM contacting his office to get clarification or
    resolve any ambiguities in the report. He further stated there was nothing about the
    property that would cause it to fall under an exception to the IRC’s grading
    requirement.
    Green testified he hired Armadillo Fences only after BNM walked off the job.
    He stated he was concerned the house was not safe while the work was left undone.
    After he sent the text to White saying he was going to hire someone else, White
    never responded that BNM was willing and able to make the modifications
    Lighthouse said were needed for the work to meet the report’s specifications. Green
    agreed that the settlement agreement did not require BNM to install sod.
    –5–
    George Francey, a general contractor with Armadillo Fences, testified he
    generated the estimate of $8,600 for the drainage work based on the original
    Lighthouse report, the inspection report, and a site inspection he performed of the
    property. Francey said he believed the $4,288 sod installation was necessary to keep
    the dirt used to regrade the property from washing away. Francey agreed that the
    type of sod he used was more expensive than Bermuda grass. But, he opined the
    work he performed was “reasonable and necessary to keep the water from coming
    into the house.” When questioned about what portions of the total amounts charged
    were for labor and what portions were for materials, Francey stated he did not know.
    Neither the estimate nor the invoice for the drainage work contained a breakdown of
    costs.
    After hearing the evidence, the trial court denied BNM’s request for a
    declaratory judgment and ruled in favor of Green on his claim for breach of contract.
    The court specifically found that BNM breached the settlement agreement by failing
    to correct the deficiencies cited by Lighthouse following its inspection. As damages,
    the judgment awarded Green the amounts he paid Armadillo Fences for the drainage
    work and sod as well as the expenses he incurred mediating both his original
    construction liability claim and the dispute over the settlement agreement in this
    case. BNM brought this appeal.
    –6–
    Analysis
    I. Evidence of Breach
    In its first issue, BNM contends the evidence does not support the trial court’s
    conclusion that BNM breached the settlement agreement.1                              BNM argues the
    evidence shows instead that Green fired BNM before it was given a chance to
    complete the repairs in accordance with Lighthouse’s instructions. In reviewing a
    legal sufficiency challenge to the evidence, we credit evidence that supports the
    verdict if a reasonable factfinder could have done so and disregard contrary evidence
    unless a reasonable factfinder could not have done so. Akin, Gump, Strauss, Hauer
    & Feld, L.L.P. v. Nat’l Dev. & Research Corp., 
    299 S.W.3d 106
    , 115
    (Tex.2009); City of Keller v. Wilson, 
    168 S.W.3d 802
    , 827 (Tex.2005). We consider
    all the evidence in the light most favorable to the prevailing party and indulge every
    reasonable inference in that party’s favor. St. Joseph Hosp. v. Wolff, 
    94 S.W.3d 513
    ,
    520–21 (Tex. 2003). The evidence is legally sufficient if “more than a scintilla of
    evidence exists.” Browning–Ferris, Inc. v. Reyna, 
    865 S.W.2d 925
    , 928 (Tex. 1993).
    More than a scintilla of evidence exists if the evidence furnishes some reasonable
    basis for differing conclusions by reasonable minds about a vital fact’s existence.
    Litton Loan Servicing, L.P. v. Manning, 
    366 S.W.3d 837
    , 840 (Tex. App.—Dallas
    1
    Although the issue asserted in BNM’s brief is that the trial court abused its discretion in finding BNM
    in breach, we liberally construe the argument to challenge the sufficiency of the evidence supporting the
    finding. TEX. R. APP. P. 38.9.
    –7–
    2012, pet. denied). The final test for legal sufficiency must always be whether the
    evidence at trial would enable reasonable and fair-minded people to reach the verdict
    under review. Del Lago Partners, Inc. v. Smith, 
    307 S.W.3d 762
    , 770 (Tex. 2010).
    To evaluate a factual sufficiency challenge, we consider and weigh all the
    evidence. Dow Chem. Co. v. Francis, 
    46 S.W.3d 237
    , 242 (Tex. 2001) (per curiam).
    We can set aside a verdict only if the evidence is so weak or the finding is so against
    the great weight and preponderance of the evidence that it is clearly wrong and
    unjust. 
    Id.
     We must not substitute our judgment for that of the factfinder and should
    remain cognizant that the factfinder is the sole judge of witness credibility. Golden
    Eagle Archery, Inc. v. Jackson, 
    116 S.W.3d 757
    , 761 (Tex. 2003).
    BNM does not dispute on appeal that the work it performed on Green’s house
    failed to meet the specifications of the Lighthouse report. Instead, BNM contends
    only that it was prevented from completing its performance under the settlement
    agreement because Green hired another contractor. Prevention of performance is an
    affirmative defense that must be pleaded or else it is waived. Orr v. Broussard, 
    565 S.W.3d 415
    , 422 (Tex. App.—Houston [14th Dist.] 2018, no pet.). In addition, the
    party asserting prevention of performance must obtain findings of fact on that issue.
    
    Id.
     In this case, BNM did neither.
    Even assuming the issue was preserved for our review, we conclude the
    evidence supports the trial court’s finding that BNM breached the agreement. To
    show that its performance was prevented, BNM needed to show it made an attempt
    –8–
    to complete performance and performance was refused. See Dorsett v. Cross, 
    106 S.W.3d 213
    , 217-18 (Tex. App.—Houston [1st Dist.] 2003, pet. denied). There is
    no evidence in the record that BNM ever offered or attempted to make the
    modifications Lighthouse determined were necessary to bring BNM’s work into
    compliance with the engineering report made the basis of the settlement agreement.
    Indeed, BNM consistently asserted, both before and through trial of this case, that
    the work it did met the report’s specifications and no modifications were required.
    Although BNM may have believed its work met the specifications of the report, it
    agreed to make whatever modifications an inspection deemed necessary, and it
    refused to do so. The initial refusal to do any further work until the parties’ lawyers
    “worked it out” occurred before Green informed BNM it was hiring another
    contractor. Accordingly, we conclude the evidence is sufficient to support the trial
    court’s finding of breach. We resolve BNM’s first issue against it.
    II. Evidence of Completion Cost Damages
    In its second issue, BNM contends the evidence does not support the trial
    court’s award of damages. BNM argues Green failed to submit any evidence to
    show the amount he paid Armadillo Fences was reasonable. 2 We agree.
    2
    Again, the issue asserted in BNM’s brief is that the trial court “abused its discretion in
    awarding damages without adequate proof.” We construe the argument to challenge the legal
    sufficiency of the evidence to support the implied finding that the damages sought by Green were
    reasonable and necessary. TEX. R. APP. P. 38.9; see also Vickery v. Comm’n for Lawyer Discipline,
    
    5 S.W.3d 241
    , 258 (Tex. App.—Houston [14th Dist.] 1999, pet. denied) (appellant may challenge
    implied findings for legal and factual sufficiency).
    –9–
    “The party seeking to recover the cost of completion in a breach of contract
    case has the burden to prove that the damages sought are reasonable and necessary.”
    Mustang Pipeline Co., Inc. v. Driver Pipeline Co., Inc., 
    134 S.W.3d 195
    , 200 (Tex.
    2004). To establish reasonableness, a party must show more than simply “the nature
    of the injuries, the character of and need for the services rendered, and the amounts
    charged therefore.” McGinty v. Hennen, 
    372 S.W.3d 625
    , 627 (Tex. 2012) (quoting
    Dallas Ry. & Terminal Co. v. Gossett, 
    294 S.W.2d 377
    , 383 (Tex. 1956). There
    must be some other evidence showing that the amounts charged are reasonable. 
    Id.
    In this case, there was no evidence presented to show that the amount charged
    by Armadillo Fences was reasonable for the work performed. Although Francey
    stated the work done was reasonable and necessary to resolve Green’s drainage
    problems, he offered no testimony to justify the price charged for the work. The
    only testimony concerning cost showed the sod Armadillo Fences chose to install
    was the more expensive option. Furthermore, Green conceded the sod was outside
    the scope of the work specified in the Lighthouse report. Without testimony
    regarding the reasonableness of the amounts charged to complete the work
    contracted for, the evidence is insufficient to support the award. Id.; see also GHP
    Nail Systems, LLC v. Benelux Cosmetics B.V., 
    651 S.W.3d 574
    , 584-85 (Tex. App.—
    Houston [14th Dist.] 2022, no pet.); Perry Homes v. Alwattari, 
    33 S.W.3d 376
    , 385
    (Tex. App.—Fort Worth 2000, pet. denied) (evidence repairs were necessary without
    evidence expenses were reasonable insufficient to support award of repair damages).
    –10–
    Green argues the words “reasonable” and “necessary” need not be used so
    long as there is sufficient evidence for the trier of fact to conclude the costs were
    reasonable. See CCC Grp., Inc. v. S. Cent. Cement, Ltd., 
    450 S.W.3d 191
    , 200 (Tex.
    App.—Houston [1st Dist.] 2014, no pet.). But, Francey testified only as to the scope
    of the work performed and the total amount paid. Mere proof of amounts charged
    or paid does not demonstrate reasonableness. Ebby Halliday Real Estate, Inc. v.
    Murnan, 
    916 S.W.2d 585
    , 589 (Tex. App.—Fort Worth 1996, writ denied). While
    in some cases evidence concerning the process of how costs were calculated will be
    sufficient to support the reasonableness of the ultimate price, no such evidence was
    submitted here. See McGinty, 372 S.W.3d at 628.
    Green additionally argues BNM failed to preserve this issue by not raising it
    in the trial court. In a civil nonjury case, a complaint regarding the legal or factual
    sufficiency of the evidence—including a complaint challenging the damages found
    by the trial court—may be raised for the first time on appeal. TEX. R. APP. P. 33.1(d).
    We resolve BNM’s second issue in its favor.
    III. Conclusion
    BNM does not challenge the trial court’s award to Green of the expenses he
    incurred in connection with the mediation of his original claim under the Texas
    Residential Construction Liability Act and the mediation of the claims in this case.
    We recognize that mediation expenses are generally considered costs of suit.
    However, in this case, the mediation of Green’s original construction liability claim
    –11–
    occurred before this suit was filed. Because the trial court did not order the
    mediation of the construction liability claim, the expenses of that mediation were
    necessarily awarded as damages rather than court costs. See TEX. CIV. PRAC. & REM.
    CODE ANN. § 154.054; Spears v. Huber, No. 07-11-0193-CV, 
    2012 WL 933780
    , at
    *4 (Tex. App.—Amarillo 2012, no pet.) (court may award expenses of mediation it
    ordered as court costs). The significant reduction in the amount of damages awarded
    to Green compels us to give the trial court an opportunity to reconsider its assessment
    of attorney’s fees. See Young v. Qualls, 
    223 S.W.3d 312
    , 314 (Tex. 2007) (per
    curiam). Accordingly, we reverse the trial court’s award of completion costs and
    render judgment that Green recover no remedial damages. We further vacate the
    award of attorney’s fees and remand this case to the trial court for a redetermination
    of reasonable and necessary fees to be awarded. We affirm the trial court’s judgment
    in all other respects.
    /Amanda L. Reichek/
    AMANDA L. REICHEK
    JUSTICE
    220474F.P05
    –12–
    S
    Court of Appeals
    Fifth District of Texas at Dallas
    JUDGMENT
    BNM VENTURES, LLC, Appellant                   On Appeal from the 95th District
    Court, Dallas County, Texas
    No. 05-22-00474-CV           V.                Trial Court Cause No. DC-20-08630.
    Opinion delivered by Justice
    SHANNON GREEN, Appellee                        Reichek. Justices Nowell and Garcia
    participating.
    In accordance with this Court’s opinion of this date, the judgment of the trial
    court is AFFIRMED in part, REVERSED AND RENDERED in part, and
    VACATED AND REMANDED in part. We REVERSE that portion of the trial
    court's judgment awarding SHANNON GREEN $13,351.73 and RENDER
    judgment that he take nothing by his claim for remedial damages. We further
    VACATE the portion of the trial court’s judgment awarding SHANNON GREEN
    his attorney’s fees. In all other respects, the trial court's judgment is AFFIRMED.
    We REMAND this cause to the trial court for further proceedings consistent with
    this opinion.
    It is ORDERED that each party bear its own costs of this appeal.
    Judgment entered this 16th day of June 2023.
    –13–