Pioneer Reserve, LLC v. United States , 125 Fed. Cl. 112 ( 2016 )


Menu:
  •      In the United States Court of Federal Claims
    No. 14-376C
    (Filed: February 16, 2016)
    *******************
    PIONEER RESERVE, LLC,
    Clean Water Act; mitigation
    Plaintiff,                       bank; contract interpretation;
    v.                                             incorporation of contract
    terms; breach of contract; 33
    THE UNITED STATES,                             C.F.R. § 332.3
    Defendant,
    ********************
    Douglas E. Kahle, Virginia Beach, VA, for plaintiff.
    Geoffrey Martin Long, Civil Division, Department of Justice,
    Washington, D.C., with whom were Steven J. Gillingham, Assistant Director,
    Robert E. Kirschman, Jr., Director, and Benjamin C. Mizer, Principal Deputy
    Assistant Attorney General, for defendant.
    _______________
    OPINION
    _______________
    BRUGGINK, Judge.
    Pioneer Reserve, LLC (“Pioneer” or “plaintiff”) brings this breach of
    contract case against the United States Government (“defendant”) pursuant to
    the Tucker Act, 
    28 U.S.C. § 1491
    . Plaintiff, the sponsor of the Pioneer Reserve
    Wetland Mitigation Bank, claims that the Umbrella Mitigation Banking
    Instrument (“UMBI”) entered into between Pioneer and the United States
    Army Corps of Engineers, Alaska District (“Corps”), was an enforceable
    contract between the parties, which the Corps breached. The government
    previously moved to dismiss on the grounds that the UMBI was not a contract.
    We rejected that argument. See Pioneer Reserve, LLC v. United States, 
    119 Fed. Cl. 201
     (2014). Pending are the parties’ motions for summary judgment.
    The matter is fully briefed, and oral argument was held on January 6, 2016.
    For the reasons stated below, we deny plaintiff’s motion for summary
    judgment, and we grant in part and deny in part defendant’s motion for
    summary judgment.
    BACKGROUND
    The facts and statutory background of this case have been set out at
    length in our previous opinion, in which we denied defendant’s motion to
    dismiss plaintiff’s complaint. 
    Id.
     We will therefore provide an abridged
    statement of the facts related to the pending motions.
    The UMBI
    The UMBI, signed September 9, 2011, “describes the establishment,
    use, operation, maintenance and long-term management of the Pioneer Reserve
    Wetland Mitigation Bank.” Def.’s App. 8. It provides that it “is an agreement
    made and entered into by Pioneer Reserve, LLC (Sponsor) and the U.S. Army
    Corps of Engineers, Alaska District (Corps).” 
    Id.
     The instrument establishes
    two parcels that comprise the Bank: the Seldon Bank Parcel and the Edgerton
    Bank Parcel. 
    Id.
     It indicates that the Edgerton Parcel, the parcel at issue here,
    contained 165.8 acres, 134.6 of which were wetlands and 31.2 of which were
    uplands.
    The instrument certifies 83.73 credits in the Seldon Bank Parcel and
    151.81 credits in the Edgerton Bank Parcel. 
    Id. at 17
    . There are several types
    of credits: palustrine, riparian, and marine.1 These credits can be purchased by
    third parties in order to offset environmental impacts to the same or similar
    type of habitat. Of Pioneer’s 151.81 Edgerton Parcel credits, 124.7 were
    palustrine. 
    Id.
     The instrument classified the rest of the parcel as uplands,
    riparian credits, or “buffer zones,” which are zones that lie in between other
    classifications.
    The instrument characterizes itself as a “legally binding and enforceable
    agreement between the District Engineer of the Corps, and a mitigation bank
    sponsor that formally establishes the mitigation Bank and stipulates the terms
    and conditions of its construction, operation, use and long-term management.”
    1
    Palustrine is a wetland system that consists of soggy highly-vegetated
    non-tidal areas such as marshes, bogs, swamps, bottomland forests, and small
    ponds. Marine wetlands are saltwater coastal wetlands. Riparian wetlands are
    those situated between land and a river or stream.
    
    Id. at 12
    . It further states that the instrument “may only be amended or
    modified with the written approval of the Sponsor and Corps.” 
    Id. at 15
    .
    The UMBI was amended in November 2013. 
    Id. at 586
    . The effect of
    the amendment was to change the characterization of certain portions of
    Pioneer’s Edgerton Parcel from wetlands to uplands. 
    Id. at 546, 586
    . Plaintiff
    contends that the net result was to eliminate all but 16.92 palustrine credits
    with respect to the Edgerton Parcel. Defendant, however, maintains that the
    amendment resulted in nothing more than a change in mapping and
    classification.
    The parties disagree about how the amendment came about and whether
    the change was bilateral. Defendant contends that plaintiff agreed to the
    change, but plaintiff denies that. There is no question that the amendment
    followed numerous discussions between Calliandra Donn, Pioneer’s Principal,
    and the Corps. In September 2012, Nicole Hayes, a representative of the
    Corps, emailed Donn the map revision that the Corps was considering. Pl.’s
    App. 71. Hayes had visited the property, which apparently caused her to be
    concerned that areas mapped as wetlands were actually uplands.
    Donn initially responded favorably, apparently under the impression
    that the proposed revisions would actually give Pioneer more of a preferable
    type of credit. Def.’s App. 237 (Excepts of deposition testimony of Calliandra
    Donn). She subsequently sent Hayes a revised table A-6, showing credit
    calculations for Pioneer’s Edgerton Parcel, which she had updated to reflect
    the Corps’ map revisions. Pl.’s App. 73. Hayes emailed Donn again in October
    2012, informing Donn that the Corps was still waiting on internal review. 
    Id. at 83
    . In May 2013, the Corps sent another letter to Donn. This letter
    mentioned the proposed changes to Pioneer’s mitigation bank as well as
    Pioneer’s concerns regarding these changes. 
    Id. at 84-85
    . Although the record
    presents no earlier reference to Pioneer declining to modify the UMBI, the
    May 2013 letter further requested that Pioneer reconsider declining the
    opportunity to modify the UMBI. 
    Id. at 85
    . The Corps warned that “without a
    modification to the [UMBI], the Corps intends to suspend credit sales for the
    incorrectly designated portions of this parcel in accordance with Section VII.
    N. of the Umbrella MBI.” 
    Id.
    Following the events detailed above, the Corps issued the amended
    UMBI in November 2013. Def.’s App. 586. Whether plaintiff signed off on
    this change is an issue which we discuss in detail later.
    3
    The Alaska Railroad Corporation’s § 404 Permit
    When it created the mitigation bank, plaintiff was aware that the Alaska
    Railroad Corporation (“ARRC”) planned to construct a railroad extension that
    would impact wetlands and other water resources, triggering a need for
    mitigation credits. This railroad extension, called the Port MacKenzie Rail
    Extension Project (“PMRE”) would be located within the service area of
    Pioneer’s mitigation bank, thus satisfying the requirement that compensatory
    mitigation “be located within the same watershed as the impact site . . . .” 
    33 C.F.R. § 332.3
    (b)(1) (2015).
    Indeed, ARRC was issued a Department of the Army (“DA”) permit
    pursuant to Section 404 of the Clean Water Act, 
    33 U.S.C. § 1344
    , on
    September 10, 2012, authorizing “the discharge of 1,618,587 cubic yards of
    fill material into 95.8 acres of waters of the U.S., including wetlands, as part
    of the construction of a 35.8-mile rail line . . . .” Def.’s App. 386. The permit
    was conditioned on ARRC purchasing a total of 160.2 wetlands credits. 
    Id. at 389
    . It directed that 16.92 palustrine credits be purchased from Pioneer, and
    143.38 palustrine credits be purchased from the Su-Knik Mitigation Bank
    (“Su-Knik”). 
    Id.
     According to the deposition of Lieutenant Colonel Mark
    DeRocchi, a member of the Corps, the Corps directed ARRC to buy most of
    its credits from Su-Knik because the Corps was under the impression that
    Pioneer had only 16.92 credits to sell. Pl.’s App. 39. Benjamin Soseith, a
    member of the Corps and project manager for the PMRE permit, stated in his
    deposition that Pioneer had only 16.92 credits to sell which were of the type
    appropriate to mitigate the PMRE's impacts. 
    Id. at 30
    .
    The permit is accompanied by a record of decision (“ROD”), which
    contains a section explaining the preference for compensatory mitigation for
    the PMRE project. Def.’s App. 495. This section explains that similar habitat
    credits of Pioneer’s Edgerton parcel are the ecologically preferred source of
    compensatory mitigation, and notes that this parcel “contains some credits of
    the same habitat type that support the Little Susitna Watershed (
    33 C.F.R. § 332.3
    (a)-(c)) where the PMRE is located.” 
    Id.
     It listed as the second most
    ecologically preferred source of compensatory mitigation similar habitat
    credits of Su-Knik’s Big South Lake parcel. 
    Id.
    After its permit was issued, ARRC entered into negotiations with
    Pioneer in an attempt to reach agreement on a price for the 16.92 Edgerton
    4
    palustrine credits. 
    Id. at 561
    . Pioneer asked for approximately $146,800 per
    credit for the 16.92 credits, for a total of $2.496 million. 
    Id. at 241
    . ARRC, on
    the other hand, offered a much lower price of $346,000 total. 
    Id.
     Unable to
    reach agreement with Pioneer at what ARRC viewed to be a reasonable price,
    ARRC submitted a request to the Corps for modification of its DA permit. 
    Id. at 560
    . In its request, ARRC explained that purchasing credits from Pioneer
    was cost prohibitive. 
    Id. at 561
    . It proposed three alternatives: (1) allow ARRC
    to purchase its 160.2 credits from either Pioneer or Su-Knik; (2) allow ARRC
    to use an in-lieu fee provider as an alternative to a mitigation bank; or (3)
    allow ARRC to purchase the 16.92 credits it was directed to purchase from
    Pioneer from either Pioneer or Su-Knik through a competitive bidding process.
    
    Id.
     ARRC later withdrew its initial request and submitted a new one, limited
    to a request that it be permitted to purchase the 16.92 credits from Great Land
    Trust instead of Pioneer. 
    Id. at 573
    . The Corps approved the latter request on
    January 28, 2013. 
    Id. at 577
    . ARRC then went ahead with its purchases from
    entities other than Pioneer.
    Plaintiff filed suit on May 5, 2014, asserting that the amendment to the
    UMBI and the Corps’ failure to adhere to applicable regulations constituted a
    breach of contract. We denied defendant’s motion to dismiss on November 21,
    2014. The parties’ cross-motions for summary judgment were subsequently
    filed on October 21, 2015.
    DISCUSSION
    In its current motion, plaintiff argues that the Corps breached the
    contract in two ways: by unilaterally reducing the number of credits available
    for sale in Pioneer’s Edgerton Bank Parcel and by failing to make use of
    Pioneer’s mitigation bank credits in accordance with 
    33 C.F.R. § 332
     (“the
    Final Rule”), which plaintiff alleges was incorporated into the UMBI. As a
    result of the breach, plaintiff contends that it suffered direct damages in the
    form of lost profits of $12,655,800.
    Regarding the unilateral reduction of credits, plaintiff argues that it
    never consented to the modification of the UMBI. Therefore, the Corps’
    reduction of plaintiffs’ available palustrine credits constituted a breach.
    According to plaintiff, had the number of credits not been reduced, ARRC
    would have purchased them.
    Plaintiff’s argument with respect to the Final Rule is that it was
    5
    incorporated into the UMBI and that the Corps violated the regulations by
    directing ARRC to purchase credits from an out-of-service mitigation bank
    when Pioneer had credits available. Plaintiff also contends that, because
    Pioneer’s bank credits were the highest-rated source of compensatory
    mitigation, the regulations required the Corps to direct ARRC to purchase
    them. Thus, by failing to adhere to the regulations, plaintiff argues, the Corps
    breached the UMBI.
    Defendant begins by repeating an argument we rejected earlier, namely,
    that it did not assume any contractual duty by entering into the UMBI.
    Recognizing that the law of the case for now is that the UMBI is a contract, it
    goes on to make other arguments. It first argues that a unilateral reduction of
    credits never occurred. Instead, it contends that the revision of UMBI Table
    A-6 to reflect a different number of palustrine credits was agreed to by
    Calliandra Donn, Pioneer’s principal. I.e., the amendment to the UMBI was
    bilateral.
    Defendant also makes a number of counter-arguments with respect to
    plaintiff’s contention that the Corps’ regulatory actions with respect to
    ARRC’s permit process constituted a breach of the UMBI. Defendant begins
    by challenging the assertion that the Final Rule was incorporated into the
    UMBI, but goes on to argue that even if it was, the incorporation was not
    specific enough to convert the regulatory obligations with respect to ARRC
    into contract terms with plaintiff. In defendant’s view, the Corps’ ability to
    determine appropriate compensatory mitigation for a DA permit, particularly
    for a third party, is separate and distinct from the UMBI and, equally
    important, the Corps is clothed with substantial discretion on the regulatory
    side which precludes any concerns plaintiff might raise in enforcing the
    UMBI.
    Defendant further argues that, as a result of the decision of the United
    States District Court for the District of Alaska in Walther v. United States,
    
    2015 WL 6872437
     (D. Alaska Nov. 9, 2015), collateral estoppel precludes
    plaintiff from proving causation in connection with its breach claim. In that
    case, plaintiff challenged the validity of Su-Knik’s banking credits, arguing
    that it suffered economic injury as a result of the Corps’ failure to adhere to the
    applicable regulations. Defendant argues here that the District Court’s decision
    in Walther–that the permittees were unlikely to have purchased Pioneer’s
    credits even if they had been available and that the Corps did not violate the
    terms of the UMBI during its determination of appropriate compensatory
    6
    mitigation for the PMRE permit–forestalls plaintiff’s causation argument in
    the current case.
    This court will only grant summary judgment “if the movant shows that
    there is no genuine dispute as to any material fact and the movant is entitled
    to judgment as a matter of law.” Rules of the Court of Federal Claims
    (“RCFC”) 56(a). We therefore will examine the facts to determine whether a
    genuine dispute exists regarding any element of Pioneer’s claim.
    Whether the UMBI Was Breached
    A threshold question concerns the terms of the contract. Specifically,
    did Pioneer agree to the amendment, and was the Final Rule incorporated as
    part of the contract? If Pioneer did not agree to the amendment, then because
    of the instrument’s requirement that it “only be amended or modified with the
    written approval of the Sponsor and Corps,” the Corps breached the contract
    by unilaterally amending it. If the Final Rule was incorporated into the UMBI,
    then the Corps breached the agreement only if it did not adhere to the Final
    Rule in its decision-making related to the PMRE permit.
    A. UMBI Modification
    Thus, we must first decide whether Pioneer breached the UMBI through
    a unilateral modification to the number of credits Pioneer had available to sell
    from its Edgerton Parcel. This is answered in part by the fact that the UMBI
    clearly states that it “may only be amended or modified with the written
    approval of [Pioneer] and the Corps.” Def.’s App. 22. The UMBI was in fact
    amended in November 2013. 
    Id. at 586
    . Therefore we must determine whether
    both Pioneer and the Corps consented to this modification. We will only grant
    summary judgment if there is no genuine dispute of material fact regarding
    whether both parties consented to the modification.
    The original UMBI provided Pioneer with a total of 151.81 credits in
    its Edgerton Parcel. 
    Id. at 52
    . Of these 151.81 credits, 124.7 were palustrine.
    
    Id.
     After the modification took place, the Edgerton Parcel was left with a total
    of 151.6 credits, 36.36 of which were palustrine. 
    Id. at 588
    . During 2012 and
    2013, there were numerous communications between Calliandra Donn and the
    Corps regarding the modification to the UMBI. Pl.’s App. 71-85. At one point
    during these communications, Donn provided the Corps with an updated table
    7
    A-6, reflecting the new proposed credit numbers in Pioneer’s Edgerton Parcel.2
    Def.’s App. 247. Donn, however, contends that at this point in time, she was
    unaware of the impact of the changes to the UMBI. 
    Id. at 237
     (Excerpts of
    deposition testimony of Calliandra Donn). Subsequent to this event, the Corps
    sent Donn a letter mentioning Pioneer’s disagreement with the proposed
    modifications. 
    Id.
     According to Donn’s later declaration, the Corps had
    informed her that it was only considering a technical mapping change, and
    Pioneer was unaware that any proposed changes would have an effect on the
    number, type, or value of Pioneer’s credits. 
    Id. at 121
    .
    Based on the facts provided, there is no clear proof that Pioneer
    consented to the modification of the UMBI. As a result, there are fact issues
    that preclude summary judgment for defendant on the basis of consent to the
    modification.
    B. Final Rule Incorporation
    To the extent that plaintiff argues that the Final Rule was incorporated
    into the UMBI and thus that the UMBI was breached through the Corps’
    decision to direct ARRC to buy only 16.92 credits from Pioneer and the rest
    from Su-Knik, we disagree. To incorporate extrinsic material by reference, a
    contract
    must explicitly, or at least precisely, identify the written material
    being incorporated and must clearly communicate that the
    purpose of the reference is to incorporate the referenced material
    into the contract (rather than merely to acknowledge that the
    referenced material is relevant to the contract, e.g., as
    background law or negotiating history).
    Northrop Grumman Inform. Tech., Inc. v. United States, 
    535 F.3d 1339
    , 1345
    (Fed. Cir. 2008). The UMBI, under the heading “II. AUTHORITIES” provides
    that “[t]he establishment, use, operation, and maintenance of the bank will be
    carried out in accordance with . . . [the Final Rule] . . . .” Def.’s App. 9. This
    statement does not explicity indicate that the parties intended to incorporate the
    Final Rule as an enforceable term of the contract. A contract must always be
    2
    However, the revised Table A-6 sent by Donn to Hayes is not the same as the
    revised Table A-6 actually adopted in the modifications to the UMBI.
    Compare Def.’s App. 247 with Def.’s App. 588.
    8
    carried out in accordance with applicable law; this reference does no more than
    point out the Final Rule as relevant background law.
    Notwithstanding whether the Final Rule was incorporated into the
    UMBI, we agree with defendant’s argument that the regulations afford the
    Corps some level of discretion, which insulates its PMRE permit decision from
    collateral scrutiny in an action here for damages. The Corps has discretion in
    determining appropriate compensatory mitigation methods associated with a
    specific DA permit.3 See 
    33 C.F.R. § 332.3
    . Thus, the regulations allowed the
    government discretion to determine which type of compensatory mitigation
    was most appropriate for the PMRE project, meaning that the Corps was not
    contractually bound to a third party (Pioneer) to require ARRC to buy
    Pioneer’s credits. The UMBI does not supersede this discretion, as it states
    that it “does not in any manner affect statutory authorities and/or
    responsibilities of the signatory parties.” Def.’s App. 9. Defendant is thus
    entitled to partial summary judgment as to the incorporation issue.
    If the UMBI was Breached, Whether it Caused Plaintiff’s Damages
    Plaintiff assumes that, but for the breach, ARRC would have purchased
    all of its credits for its PMRE impacts from Pioneer at a price of $79,000 per
    credit. Plaintiff bases its credit price upon two prior sales of its mitigation bank
    credits to the Alaska Department of Transportation, one in July 2013 and one
    in January 2014. Both sales involved a price of $79,000 per credit.
    3
    While plaintiff is correct that the regulations do mandate certain
    considerations to be made when selecting appropriate compensatory
    mitigation, plaintiff fails to recognize that several subsections of the
    regulations also operate to give the Corps discretion notwithstanding the
    required considerations. For example, plaintiff points to the regulations’
    requirement that mitigation be “in-kind,” meaning that it is of the a similar
    type as the impacted resource. Br. in Supp. of Pl.’s Mot. for Summ. J. 20.
    However, there is no such requirement; the regulations merely provide that in-
    kind mitigation is preferable to out-of-kind mitigation. 
    33 C.F.R. § 332.3
    (e)(1). Plaintiff further refers to 
    33 C.F.R. § 332.3
    (b), which provides
    that when considering mitigation options, the Corps must give preference to
    requiring use of a mitigation bank’s credits as mitigation if the environmental
    impacts are located within the bank’s service area. See 
    id.
     § 332.3(b)(1).
    Again, this is merely a preference rather than a requirement.
    9
    Defendant responds that this is, at best, speculative, because ARRC had
    other compensatory mitigation options aside from Pioneer’s Edgerton Parcel
    credits which it could have utilized to mitigate the PMRE impacts. It points out
    two sales that plaintiff ignores–Su Knik’s sale of 143.28 credits to ARRC at
    $10,000 per credit and GLT’s sale of 16.92 credits to ARRC at $29,084 per
    credit.
    In support of the motions on this issue, we have the following facts: The
    PMRE permit was issued on September 10, 2012, directing ARRC to buy
    16.92 credits from Pioneer’s Edgerton Parcel and its remaining credits from
    Su-Knik. Def.’s App. 389. According to Lieutenant Colonel Mark DeRocchi,
    a member of the Corps, the Corps directed ARRC to buy most of its credits
    from Su-Knik because Pioneer had only 16.92 credits to sell. Pl.’s App. 39.
    Benjamin Soseith, another member of the Corps who served as project
    manager for the PMRE permit, stated that Pioneer had only 16.92 credits to
    sell that were of the type appropriate to mitigate the PMRE’s impacts. Id. at
    30. The ROD for ARRC’s permit included an evaluation of the most
    ecologically preferred options for compensatory mitigation, which found that
    Pioneer’s Edgerton Parcel was the most preferred option, followed by Su-
    Knik’s Big South Lake Parcel. Def.’s App. 495. We also know that, on
    November 9, 2012, ARRC requested a modification to its permit, citing in part
    the fact that it viewed purchasing 16.92 of Pioneer’s credits at approximately
    $146,800 per credit as cost prohibitive. Id. at 560-65.
    Leading up to the issuance of the PMRE permit were discussions
    between Hayes and Pioneer, as well as between Hayes and the bank’s
    interagency review team (“IRT”), which is the entity involved in creating the
    UMBI, regarding a possible reclassification of some areas of Pioneer’s
    Edgerton Parcel. These discussions were triggered by Hayes’ visit to the
    Edgerton Parcel in May 2012, during which she discovered that areas mapped
    as wetlands were actually uplands. Id. at 544. Hayes expressed these concerns
    to the IRT via email in July 2012. Id. at 549. On September 7, 2012, Hayes
    sent an email to Donn notifying her of the UMBI revision that the Corps was
    considering, which reclassified portions of the Edgerton Parcel. Id. at 552.
    Even if this arguably breached the UMBI, what it nevertheless exposes is the
    possibility that the Corps would not have been bound, in its permitting
    capacity, to consider 124.7 of the Edgerton credits as “like” palustrine credits
    appropriate to mitigate the impacts of the PMRE.
    In short, even if we found that there was a breach, fact issues are
    10
    present. For plaintiff to prevail and show that the alleged breach did in fact
    cause Pioneer’s damages, it would need to provide more information regarding
    other available compensatory mitigation options for the PMRE project and
    facts indicating that Pioneer’s credits were the most likely option–notably, a
    showing that the improper classification of the Edgerton Parcel’s uplands areas
    as wetlands did not render Pioneer’s credits unsuitable to mitigate the impacts
    of the PMRE. Additionally, this court would require evidence that the ADOT
    impacts are similar to the PMRE impacts such that they warrant similar credit
    types and prices. Defendant, on the other hand, has failed to present evidence
    showing that as a matter of law, plaintiff cannot prove damages.
    CONCLUSION
    For the foregoing reasons, we deny plaintiff’s motion for summary
    judgment, and we grant in part and deny in part defendant’s motion for
    summary judgment. The parties are directed to confer and propose by March
    8, 2016, jointly if possible, a schedule leading to trial in October 2016.
    s/Eric G. Bruggink
    ERIC G. BRUGGINK
    Judge
    11
    

Document Info

Docket Number: 14-376

Citation Numbers: 125 Fed. Cl. 112

Filed Date: 2/16/2016

Precedential Status: Precedential

Modified Date: 1/13/2023