Raytheon Company v. United States ( 2015 )


Menu:
  •            In the United States Court of Federal Claims
    No. 15-77C
    (Filed Under Seal: June 5, 2015)
    (Reissued: June 18, 2015)*
    *************************************
    RAYTHEON COMPANY,                   *
    *
    Plaintiff,              *
    *
    v.                                 *
    *
    THE UNITED STATES,                  *
    *
    Defendant,              *
    *
    and                                 *
    *
    LOCKHEED MARTIN CORPORATION *
    and NORTHROP GRUMMAN SYSTEMS *
    CORPORATION,                        *
    *
    Defendant-Intervenors.  *
    *************************************
    OPINION AND ORDER ON PLAINTIFF’S RCFC 62(c) MOTION
    In this bid protest, plaintiff Raytheon Company (“Raytheon”), the contract awardee,
    challenges the decision of the United States Air Force (“Air Force”) to take corrective action
    based on the statements made by a Government Accountability Office (“GAO”) attorney during
    an outcome prediction conference held in conjunction with protests lodged by defendant-
    intervenors Lockheed Martin Corporation (“Lockheed”) and Northrop Grumman Systems
    Corporation (“Northrop”). In a May 11, 2015 Opinion and Order, the court denied Raytheon’s
    motion for judgment on the administrative record and granted the remaining parties’ cross-
    motions for judgment on the administrative record, allowing the Air Force to proceed with its
    proposed corrective action. Presently before the court is Raytheon’s motion for a stay of the
    court’s judgment and to enjoin the Air Force from proceeding with its proposed corrective action
    or awarding a new contract pending appeal. For the reasons set forth below, the court denies
    Raytheon’s motion.
    *
    This reissued Opinion and Order incorporates the agreed-to redactions proposed by the
    parties on June 17, 2015. The redactions are indicated with bracketed ellipses (“[. . .]”).
    I. BACKGROUND
    Several years ago, the Air Force initiated the Three-Dimensional Expeditionary Long-
    Range Radar (“3DELRR”) acquisition program to replace its existing AN/TPS-75 radar system.1
    Slip op. 2. During the current phase of the procurement–Engineering and Manufacturing
    Development (“EMD”)–Raytheon, Lockheed, and Northrop submitted proposals to further
    develop, build, and test a radar system. 
    Id. at 5.
    The Air Force determined that all of the
    proposals were technically acceptable and ultimately awarded the EMD contract to Raytheon. 
    Id. at 14.
    In postaward debriefings, the Air Force disclosed the price of the contract it awarded to
    Raytheon to Lockheed and Northrop. 
    Id. at 15.
    Both Lockheed and Northrop protested the Air Force’s award decision at the GAO. 
    Id. After extensive
    proceedings, 
    id. at 15-18,
    the GAO attorney assigned to the protest held an
    alternative dispute resolution outcome prediction conference with the parties, 
    id. at 19.
    During
    the conference, the GAO attorney advised the parties that she anticipated sustaining the protests
    on two grounds: (1) the Air Force erred in its technical evaluation of Raytheon’s proposal and
    (2) the Air Force conducted unequal and misleading discussions regarding the parties’ cost/price
    proposals. 
    Id. at 19-20.
    She therefore recommended that the Air Force take corrective action to
    cure the defects that she identified. 
    Id. at 20.
    The following day, the Air Force indicated that
    based on the GAO attorney’s statements during the outcome prediction conference, it would take
    corrective action to cure the identified defects. 
    Id. As a
    result, the GAO dismissed the protests
    lodged by Lockheed and Northrop as moot. 
    Id. Shortly thereafter,
    on January 26, 2015, Raytheon filed the current bid protest, arguing
    that the Air Force’s decision to take corrective action was arbitrary, capricious, and unreasonable
    because the GAO attorney’s determinations were themselves unreasonable. 
    Id. at 21.
    The
    parties fully briefed cross-motions for judgment on the administrative record and the court heard
    argument. 
    Id. at 21-22.
    Ultimately, in its May 11, 2015 Opinion and Order, the court concluded
    that the GAO attorney’s determinations were reasonable and that the Air Force’s decision to take
    corrective action based on those determinations was therefore rational. 
    Id. at 34-44.
    Consequently, it denied Raytheon’s protest. 
    Id. at 44-45.
    The clerk entered judgment on May
    13, 2015.
    The following day, Raytheon filed a notice of appeal. It also filed a motion seeking to
    stay the court’s judgment and enjoin the Air Force from either proceeding with its proposed
    corrective action or awarding a new contract pending appeal. The parties have fully briefed
    1
    With one exception, the court derives the facts in this decision from its May 11, 2015
    Opinion and Order (“Slip op.”), which contains a full recitation of the pertinent factual and
    procedural history. The remaining fact is a quotation from the solicitation that appears in the
    administrative record (“AR”); the court paraphrased this quotation in its May 11, 2015 Opinion
    and Order.
    -2-
    Raytheon’s motion pursuant to an expedited briefing schedule set by the court. The court deems
    oral argument unnecessary.
    II. DISCUSSION
    Raytheon moves to stay the court’s judgment and enjoin the Air Force from proceeding
    with its proposed corrective action pending appeal pursuant to Rule 62(c) of the Rules of the
    United States Court of Federal Claims (“RCFC”), which provides: “While an appeal is pending
    from an interlocutory order or final judgment that grants, dissolves, or denies an injunction, the
    court may suspend, modify, restore, or grant an injunction on terms for bond or other terms that
    secure the opposing party’s rights.” In entertaining a motion under RCFC 62(c), the court
    considers four factors: (1) whether the moving party has made a strong showing that it is likely
    to succeed on the merits; (2) whether the moving party will be irreparably injured absent the
    requested relief; (3) whether requested relief will substantially injure the other parties interested
    in the proceeding; and (4) the public interest. Hilton v. Braunskill, 
    481 U.S. 770
    , 776 (1987);
    Standard Havens Prods., Inc. v. Gencor Indus., Inc., 
    897 F.2d 511
    , 512 (Fed. Cir. 1990); Alaska
    Cent. Express, Inc. v. United States, 
    51 Fed. Cl. 227
    , 229 (2001). The court need not assign each
    factor equal weight. Standard Havens 
    Prods., 897 F.2d at 512
    . Consequently, relief is
    appropriate where the moving party “‘establishes that it has a strong likelihood of success on
    appeal, or where, failing that, it can nonetheless demonstrate a substantial case on the merits,’
    provided the other factors militate in [its] favor.” 
    Id. at 513
    (quoting 
    Hilton, 481 U.S. at 778
    ).
    And, when the equitable factors weigh decidedly in the moving party’s favor, “‘it will ordinarily
    be enough that the [moving party] has raised questions going to the merits so serious, substantial,
    difficult and doubtful, as to make them a fair ground for litigation . . . .’” 
    Id. (quoting Hamilton
    Watch Co. v. Benrus Watch Co., 
    206 F.2d 738
    , 740 (2d Cir. 1953)); accord Alaska Cent.
    
    Express, 51 Fed. Cl. at 230
    (“[I]f the equities weigh heavily in favor of maintaining the status
    quo, this court may grant an injunction under RCFC 62(c) where the question raised is novel or
    close, especially when the case will be returned to the trial court should the movant succeed.”).
    A. Likelihood of Success on the Merits
    Raytheon first contends that it is likely to succeed on the merits of its appeal, asserting
    that the court erred by upholding the Air Force’s decision to take corrective action with respect to
    both the technical evaluation of Raytheon’s proposal and the cost/price discussions. The court
    begins by addressing the technical evaluation issue.
    1. The Technical Evaluation of Raytheon’s Proposal
    a. Factual Background
    During an earlier phase of the 3DELRR procurement, a team of independent subject-
    matter experts (“independent review team”) with expertise in radar system design, hardware,
    -3-
    software, testing, and signal processing prepared a Technology Readiness Assessment report for
    each offeror’s proposed radar system. Slip op. 2-3. In those reports, the independent review
    team identified the radar systems’ critical technology elements (“CTEs”) and assigned each CTE
    a Technology Readiness Level (“TRL”). 
    Id. at 2.
    Raytheon’s CTE 1 was its Gallium Nitride
    High Power Amplifier [. . .] (“GaN HPA [. . .]”), a [. . .] its proposed radar system’s [. . .]
    subsystem. 
    Id. at 3-4.
    However, notwithstanding its initial description of Raytheon’s CTE 1 as
    the GaN HPA [. . .], the independent review team considered two components of the [. . .]–the
    GaN HPA and [. . .]–as the new and novel critical technologies that required TRL assessment.
    
    Id. at 4-5.
    In the solicitation for the current phase of the 3DELRR procurement, the Air Force
    described the proposal requirements and its evaluation criteria. 
    Id. at 5-7.
    In paragraph 5.3.1.3
    of section L of the solicitation, the Air Force indicated that offerors were to provide the following
    information in their technical proposals: “The Offeror shall identify all critical technology
    elements (CTEs) of the design solution that have changed since [the pre-EMD phase of the
    procurement] . . . . For each modified/new CTE identified, provide the current TRL, the source
    of the rating, and full substantiation with supporting data.” AR 41250; accord Slip op. 5.
    Pursuant to paragraph 2.4.1.3 of section M of the solicitation, the Air Force would evaluate
    whether the technical proposals met the stated requirements “based on,” in part: “Substantiation
    of at least a Technology Readiness Level 6 (TRL 6) for all Critical Technology Elements (CTEs)
    of the design solution that have changed since the Pre-EMD Preliminary Design Review (PDR).
    One CTE must be a Gallium Nitride (GaN) High Power Amplifier (HPA)-based
    Transmit/Receive (T/R) module.” Slip op. 7.
    In its technical proposal, Raytheon did not describe any significant changes to its [. . .]
    subsystem, and expressly represented that since the pre-EMD period, it had not introduced any
    “new technologies” to its “design solution.” 
    Id. at 7-8.
    Raytheon further represented that its
    CTEs had not changed and that its radar system prototype “successfully demonstrated all Pre-
    EMD phase CTEs at TRL 6 and the overall design maturity in a relevant environment.” 
    Id. at 8.
    However, Raytheon did change the design of its CTE 1 by [. . .]. 
    Id. Raytheon acknowledged
    this change during discussions in its response to an Evaluation Notice (“EN”) issued by the Air
    Force in which the Air Force requested information regarding Raytheon’s proposed production
    cost savings. 
    Id. at 9.
    Specifically, Raytheon noted:
    [. . .]
    
    Id. The Air
    Force reviewed this response and ultimately deemed the discussion issue resolved.
    
    Id. When evaluating
    the offerors’ final proposal revisions, the Air Force’s technical
    evaluators reviewed Raytheon’s proposal for compliance with the solicitation’s technical
    requirements. 
    Id. at 13.
    These technical evaluators were advised by four members of the original
    independent review team. 
    Id. With respect
    to the requirement that the offerors substantiate TRL
    -4-
    6 ratings for each of the CTEs that had changed since the pre-EMD period, Kevin Ray, the chief
    evaluator for the relevant technical subfactor, remarked:
    Raytheon substantiated all criteria listed in Section M 2.4.1.3.
    The Technology Readiness Assessment (TRA) Independent Review Team
    (IRT) assessed all Raytheon’s Critical Technology Elements (CTEs) at
    Technology Readiness Level 6 (TRL 6) during the Pre-Engineering and
    Manufacturing Development (Pre-EMD) Period of the Technology Development
    (TD) Phase. Raytheon listed the same CTEs in the EMD proposal as those
    identified in the Pre-EMD Period. In addition, Raytheon identified one CTE as a
    Gallium Nitride (GaN) High Power Amplifier (HPA)-based Transmit/Receive
    (T/R) module which met the Government’s requirement.
    TRA IRT members reviewed and analyzed Volume II, Paragraph 1.3,
    Pages II-86 to II-88. The IRT members confirmed the CTEs listed were the
    original CTEs approved by the team in 2013 and there were no changes to the
    CTEs since the Pre-EMD Period Preliminary Design Review (PDR) where
    Raytheon was assessed at TRL 6. Raytheon described each CTE in the following
    Volume II pages.
    1. Pages II-19 to II-21 and the classified Volume IIA, Figure IIA-1.0.1-6
    System Architecture for the T/R Line Replaceable Unit (LRU) and the
    receive LRU.
    
    Id. at 13-14.
    In its protest before the GAO, Lockheed challenged the Air Force’s technical evaluation
    of Raytheon’s CTE 1, arguing that because Raytheon’s proposed GaN HPA [. . .] was different
    from the GaN HPA [. . .] it demonstrated during the pre-EMD period, the Air Force improperly
    considered Raytheon’s CTE 1 to be assessed at TRL 6. 
    Id. at 16.
    During a hearing convened by
    the GAO, Mr. Ray testified that the Air Force (1) considered the GaN HPA and [. . .] as the new
    and novel critical technologies that required TRL assessment; (2) did not consider the circulator
    to be a critical technology; (3) determined that although [. . .] the circulator [. . .] would require
    [. . .] to be redesigned, neither of the critical technologies in CTE 1 (the GaN HPA and [. . .])
    were affected by the design change; (4) did not believe that [. . .] the circulator would impact
    performance; and (5) did not request, and Raytheon did not provide, any information regarding
    the proposed redesigned [. . .], such as the new design or test data. 
    Id. at 17.
    Upon considering
    all of the evidence, the GAO attorney advised the parties during the outcome prediction
    conference that she intended to sustain Lockheed’s protest on this issue. 
    Id. at 19-20.
    She stated
    that the record reflected that Raytheon’s CTE 1 was the [. . .] GaN HPA [. . .], not just the GaN
    HPA and [. . .], and that Raytheon’s [. . .], as redesigned with the circulator [. . .], was never
    tested. 
    Id. at 19.
    Accordingly, she opined that the Air Force erred in concluding that Raytheon’s
    -5-
    CTE 1 was at TRL 6. 
    Id. at 20.
    The Air Force decided to take corrective action based on the
    GAO attorney’s determinations. 
    Id. b. The
    Court’s Ruling
    Based on the evidence in the administrative record, the court concluded that the Air Force
    did not comply with the evaluation scheme set forth in the solicitation. Specifically, it explained:
    Based on the contemporaneous evidence contained in the administrative
    record, it is readily apparent that despite the various labels used to denote
    Raytheon’s CTE 1, the independent review team and the Air Force’s technical
    evaluators focused their evaluation of the maturity of Raytheon’s CTE 1 on the
    new and novel aspects of the GaN HPA [. . .]–the GaN HPA and [. . .]. Indeed,
    neither the members of the independent review team nor the Air Force’s technical
    evaluators–the individuals with the relevant knowledge and expertise–expressed
    any concern that the introduction of COTS circulators or the [. . .] would affect the
    TRL of Raytheon’s CTE 1.
    Normally, a procuring agency’s technical assessments, such as the ones
    made by the Air Force with respect to Raytheon’s CTE 1, must be afforded the
    greatest possible deference. E.W. Bliss Co. v. United States, 
    77 F.3d 445
    , 449
    (Fed. Cir. 1996); Beta Analytics Int’l, Inc. v. United States, 
    67 Fed. Cl. 384
    , 395
    (2005) (“The evaluation of proposals for their technical excellence or quality is a
    process that often involves the special expertise of procurement officials, and thus
    reviewing courts give the greatest deference possible to these determinations.”).
    . . . In light of the highly deferential standard applicable in these circumstances,
    the court has no difficulty concluding, based on the evidence in the administrative
    record, that the independent review team and the Air Force’s technical evaluators
    reasonably assessed that the design change proposed by Raytheon would not
    affect the TRL of Raytheon’s CTE 1. The members of the independent review
    team in particular possessed expertise in radar system design, hardware, software,
    testing, and signal processing, and it is eminently reasonable to conclude that they
    applied that expertise in determining that the use of COTS circulators and the
    redesign of the [. . .] would not affect the technical maturity of Raytheon’s GaN
    HPA [. . .].
    Problematically, however, the Air Force did not comply with the
    solicitation when it evaluated Raytheon’s GaN HPA [. . .]. Pursuant to the
    solicitation, the contractors were required to substantiate a TRL 6 assessment for
    any CTEs that had changed since the conclusion of the pre-EMD period.
    Raytheon’s CTE 1 was its GaN HPA [. . .], and not just portions of its GaN HPA
    [. . .], such as the GaN HPA or [. . .]. Accordingly, Raytheon was required to
    substantiate that the changes it made to the design of its GaN HPA [. . .]–using
    -6-
    COTS circulators and [. . .]–did not affect the TRL of the GaN HPA [. . .].
    Raytheon did not do so. Thus, the Air Force’s conclusion that Raytheon
    substantiated TRL 6 ratings for each of the CTEs that had changed since the pre-
    EMD period was erroneous. The Air Force should have required Raytheon to
    substantiate the TRL 6 rating of its changed CTE 1, and its failure to do so caused
    its assessment of Raytheon’s CTE 1 to be in violation of the evaluation scheme set
    forth in the solicitation. The Air Force’s evaluation of the technical maturity of
    Raytheon’s CTE 1 was therefore arbitrary and capricious. See, e.g.,
    CRAssociates, Inc. v. United States, 
    102 Fed. Cl. 698
    , 713 (2011) (noting that a
    procuring agency’s departure from the evaluation scheme set forth in a solicitation
    can “lead to the award . . . being set aside as arbitrary, capricious or otherwise
    contrary to law”). Consequently, the GAO attorney’s findings on this issue were
    rational, and the Air Force’s reliance on her findings in deciding to take corrective
    action was also rational.
    
    Id. at 36-37.
    c. Raytheon’s Contention
    In disagreeing with the court’s ruling, Raytheon focuses on the provisions of the
    solicitation concerning the information that offerors were required to provide regarding CTEs
    and the criteria by which the Air Force would evaluate changed CTEs. Specifically, Raytheon
    contends that there was no language in the solicitation requiring offerors to provide
    substantiation of TRL 6 for changed CTEs that postdated the changes made to the CTEs–in other
    words, new substantiation. Therefore, Raytheon argues, it was permitted to submit substantiation
    with its proposal that was based on assessments made during the pre-EMD period and predated
    the changes it made to its CTE 1. Raytheon further argues that the Air Force’s technical
    evaluators were entitled to rely on such substantiation if they believed that it was adequate to
    support the TRL 6 assessment for that CTE. During the earlier proceedings before this court,
    Raytheon strenuously argued that the Air Force’s technical evaluation of its CTE 1 should be
    afforded great deference. However, Raytheon did not specifically argue, as it does now, that
    under the relevant language of the solicitation, it was not required to provide substantiation of
    changed CTEs that postdated the changes to those CTEs. The court therefore did not address that
    argument in its decision denying Raytheon’s bid protest. Nevertheless, in furtherance of the full
    and fair administration of justice, the court will describe Raytheon’s newly advanced contention.
    In its May 11, 2015 Opinion and Order, the court, without the benefit of Raytheon’s
    present argument, interpreted the solicitation to require offerors to substantiate TRL 6
    assessments for changed CTEs using evidence that postdated the changes. Pursuant to section L
    of the solicitation, offerors were to provide, for each changed CTE, “the current TRL, the source
    of the rating, and full substantiation with supporting data.” And, pursuant to section M of the
    solicitation, the Air Force was required to determine whether offerors substantiated a TRL 6
    assessment for all changed CTEs. A fair reading of these provisions is that the Air Force was
    -7-
    concerned that an offeror might redesign a CTE to lower its costs (and, hence, its proposed price)
    without regard for whether the CTE’s technical maturity would be adversely affected. Thus, to
    mitigate that risk, the Air Force wanted evidence that the offeror assessed the TRL of the CTE
    after it redesigned the CTE to ensure that the CTE’s TRL was not adversely affected by the
    design change.
    However, as Raytheon notes in its RCFC 62(c) motion, the relevant solicitation
    provisions do not expressly limit what evidence an offeror could provide to substantiate a TRL 6
    assessment of a changed CTE. Accordingly, Raytheon asserts, offerors could provide evidence
    that either predated or postdated the change to the CTE,2 and it was the Air Force’s responsibility
    to determine whether that evidence was sufficient. Raytheon’s interpretation of the solicitation is
    not unreasonable. Nevertheless, the Air Force ultimately concluded that the language of the
    solicitation it drafted required a different result. Hence, it determined that corrective action was
    appropriate.
    In sum, there exist two fair readings of the relevant solicitation provisions–the one acted
    upon by the Air Force, the agency that drafted the solicitation, and the one newly advanced by
    Raytheon in its RCFC 62(c) motion. Given that the court was not asked to evaluate Raytheon’s
    present contentions when ruling on the parties’ cross-motions for judgment on the administrative
    record, the determination of which interpretation of the relevant solicitation provisions is correct
    will necessarily be for the Federal Circuit to decide in the first instance. As such, the court
    cannot conclude that Raytheon has made a strong showing of a likelihood of success on the
    merits or even a substantial case on the merits on this aspect of its appeal. See 
    Hilton, 481 U.S. at 776
    ; Standard Havens 
    Prods., 897 F.2d at 512
    ; Alaska Cent. 
    Express, 51 Fed. Cl. at 229
    ; see
    also Nken v. Holder, 
    556 U.S. 418
    , 434 (2009) (noting that to make the required showing, “[i]t is
    not enough that the chance of success on the merits be better than negligible” and that “[m]ore
    than a mere possibility of relief is required” (internal quotation marks omitted)). As discussed
    2
    In its reply in support of its RCFC 62(c) motion, Raytheon contends that “[t]he CTE’s
    post-change TRL must be substantiated, but there is no reason that the substantiation must
    involve more testing or data when a modification is so innocuous as not to affect the CTE’s
    technology maturity.” Reply 6. It then remarks that “[h]ypothetically, if the design change
    involved no more than a different color for the CTE’s housing, surely the CTE need not be
    retested in order to prove that the TRL rating is unaffected” and that “there is obviously a
    continuum of design changes with regard to their relative impact on the CTE’s technology
    maturity.” 
    Id. Raytheon’s hypothetical
    scenario is unavailing. While the court agrees with
    Raytheon’s proposition that there is a continuum of design changes–on one end of the continuum
    are the design changes that are so significant that they most assuredly would affect technical
    maturity, and at the other end of the continuum are the design changes that are so minor that they
    most assuredly would not affect technical maturity–the solicitation makes no such distinction.
    Rather, offerors were to identify any CTE that had changed since the pre-EMD period and
    substantiate a TRL 6 assessment for those changed CTEs.
    -8-
    below, the court reaches the same conclusion with respect to Raytheon’s contentions regarding
    the cost/price discussions.
    2. The Cost/Price Discussions
    a. Factual Background
    As noted above, in the solicitation for the current phase of the 3DELRR procurement, the
    Air Force described the proposal requirements and its evaluation criteria. Slip op. 5-7. In section
    L of the solicitation, the Air Force indicated that offerors were to identify and support their
    proposed cost reductions in the cost/price volumes of their proposals. 
    Id. at 6.
    Then, in section
    M of the solicitation, the Air Force described its criteria for evaluating proposed costs and prices.
    
    Id. at 7.
    The Air Force’s evaluation was to include an assessment of whether the offerors’
    cost/price proposals were reasonable and realistic. 
    Id. Raytheon, Lockheed,
    and Northrop proposed vastly different approaches to reducing the
    costs of contract performance. In its proposal, Raytheon identified [. . .] in cost reductions that
    included [. . .] for independent research and development (“IR&D”). 
    Id. at 8.
    In contrast,
    Lockheed proposed [. . .]. 
    Id. And, Northrop
    identified [. . .] cost reductions totaling [. . .], but
    did not include a reduction for IR&D. 
    Id. After accounting
    for their cost reductions, Raytheon
    offered the lowest total price [. . .]; Northrop offered [. . .]; and Lockheed offered [. . .]. 
    Id. at 9.
    During discussions, the Air Force sent similar ENs to Raytheon and Northrop regarding
    the reasonableness and realism of their proposed cost reductions. 
    Id. at 10.
    Both ENs provided:
    In accordance with (IAW) [Federal Acquisition Regulation (“FAR”)] 31.205-18
    and [10 U.S.C. § 2320], any cost claimed or considered to be IR&D or a capital
    investment shall not be allowable as indirect charges for work implicitly required
    for performance (necessary to perform the contract) or explicitly required to be
    done by the terms of the contract. Any such costs should be considered as direct
    charges to the 3DELRR contract. Further, unless properly segregated and agreed
    to as unallowable costs IAW FAR Part 31, any such costs may be deemed
    unrealistic.
    
    Id. In its
    response to this EN, Raytheon challenged the Air Force’s interpretation of the rules
    regarding the allowability of IR&D costs, noting that the United States Court of Appeals for the
    Federal Circuit (“Federal Circuit”) had held in ATK Thiokol, Inc. v. United States, 
    598 F.3d 1329
    (Fed. Cir. 2010), that research and development costs were allowable as IR&D costs unless
    specifically required by the contract. Slip op. 11. In contrast, Northrop did not raise any
    objections to the Air Force’s statements regarding the allowability of IR&D costs. 
    Id. Moreover, in
    response to another EN in which the Air Force requested information, such as “[. . .]/IR&D
    planning statements,” to substantiate how Northrop planned to fund contract performance during
    -9-
    three specified fiscal years, Northrop explained that “[t]he execution of this contract does not
    require [. . .]/IR&D funding . . . .” 
    Id. at 9.
    As later explained at the GAO hearing, upon reviewing Raytheon’s EN response and
    consulting with the Defense Contract Management Agency, the Air Force changed its position
    with respect to the allowability of IR&D costs; it determined that Raytheon’s position was
    correct. 
    Id. at 12,
    17-18. Accordingly, in the follow-up EN that it sent to Raytheon, the Air
    Force did not address Raytheon’s statements regarding IR&D costs, 
    id. at 12,
    suggesting that it
    accepted Raytheon’s position. However, in the follow-up EN that it sent to Northrop, the Air
    Force did not advise Northrop that it had changed its position regarding the allowability of IR&D
    costs and that its earlier statement was therefore incorrect. 
    Id. Further, although
    the Air Force
    did not send an EN regarding the allowability of IR&D costs to Lockheed, it [. . .] during
    discussions. 
    Id. at 13.
    In its final proposal revision, Raytheon reduced its total proposed price to [. . .], which
    reflected an IR&D cost reduction of [. . .]. 
    Id. Northrop proposed
    a price of [. . .] in its final
    proposal revision, an amount that [. . .]. 
    Id. Lockheed, in
    its final proposal revision, [. . .] its
    total proposed price to [. . .], which reflected [. . .]. 
    Id. In its
    protest before the GAO, Northrop contended that the Air Force’s cost/price
    discussions were misleading because the Air Force accepted Raytheon’s understanding of the
    allowability of IR&D costs, but never advised Northrop of its changed understanding, preventing
    it from proposing IR&D cost reductions in line with the IR&D cost reductions proposed by
    Raytheon [. . .]. 
    Id. at 16.
    Specifically, it contended:
    If Northrop Grumman had known of the Air Force’s changed
    interpretation, it would have responded by protesting the interpretation’s illegality
    and/or submitting a radically changed proposal. Northrop Grumman is a very
    large corporation with billions in assets and revenue. [. . .] Had Northrop
    Grumman known of the Air Force’s expansive view of IR&D, which permitted
    offerors to propose IR&D that violated the FAR and the Air Force instruction
    provided to Northrop Grumman, Northrop Grumman could have proposed the
    types and quantities of IR&D [. . .].
    
    Id. Upon considering
    all of the evidence, the GAO attorney advised the parties during the
    outcome prediction conference that she intended to sustain Northrop’s protest on this issue. 
    Id. at 19-20.
    She stated that the record reflected that the Air Force changed its understanding
    regarding the allowability of future IR&D costs, but never advised Northrop of its changed
    understanding. 
    Id. at 20.
    She therefore opined that the Air Force’s discussions with Northrop
    were misleading and unequal. 
    Id. The Air
    Force decided to take corrective action based on the
    GAO attorney’s determinations. 
    Id. -10- b.
    The Court’s Ruling
    Based on the evidence in the administrative record, the court concluded that the Air
    Force’s discussions with Northrop regarding the allowability of IR&D costs were misleading and
    unequal. Specifically, it explained:
    Raytheon contends that discussions regarding the allowability of IR&D
    costs were neither misleading nor unequal, and there is support in the
    administrative record for its position. During the first round of discussions,
    Northrop unambiguously disclaimed any reliance on IR&D cost reductions in
    response to one EN, and at the same time raised no objections to the Air Force’s
    statements regarding the allowability of IR&D costs in response to a separate EN.
    As a result, when the Air Force decided not to pursue further discussions with
    Northrop regarding IR&D costs, there is a nonfrivolous argument to be made that
    the Air Force was merely tailoring its discussions to Northrop’s proposal pursuant
    to FAR 15.306(d)(1).
    Nevertheless, the evidence in the administrative record weighs more
    heavily in favor of Northrop’s contention that the discussions were misleading and
    unequal. After the Air Force received the contractors’ responses to the initial set
    of ENs, it determined that a statement it had communicated to Raytheon and
    Northrop regarding the allowability of IR&D costs no longer accurately
    represented its position. By not lodging any further objections to Raytheon’s [. . .]
    proposed IR&D cost reductions, the Air Force signaled [. . .] that it was
    permissible to propose such reductions. However, the Air Force never advised
    Northrop of its changed understanding of the allowability of IR&D costs.
    Through its silence, the Air Force misled Northrop into believing that it would not
    accept IR&D cost reductions. Moreover, by advising only Raytheon [. . .] that it
    would accept IR&D cost reductions notwithstanding the language of its ENs, the
    Air Force engaged in unequal discussions with the contractors. At bottom, it was
    the Air Force’s duty to ensure that all three contractors were competing on a level
    playing field. See, e.g., Joseph L. DeClerk & Assocs., Inc. v. United States, 
    26 Cl. Ct. 35
    , 46 (1992), cited in [Sys. Application & Techs., Inc. v. United States,
    
    691 F.3d 1374
    , 1383 (Fed. Cir. 2012)]; see also FAR 1.102-2(c)(3) (requiring
    procuring agencies to treat all prospective contractors “fairly and impartially”).
    By misleading Northrop regarding its position on the allowability of IR&D costs
    and advising only Raytheon [. . .] that it had changed its position, the Air Force
    violated that duty. Consequently, the GAO attorney’s conclusion that the Air
    Force engaged in misleading and unequal discussions concerning the allowability
    of IR&D costs was rational, and the Air Force’s reliance on her conclusion in
    deciding to take corrective action was also rational.
    
    Id. at 41.
    -11-
    c. Raytheon’s Contentions
    Raytheon contends that the court’s conclusion that the Air Force acted rationally when
    deciding to take corrective action with respect to the misleading and unequal cost/price
    discussions is incorrect on two grounds. As an initial matter, Raytheon reiterates an argument
    that it first advanced during the merits proceedings: the substantially similar ENs that the Air
    Force sent to Raytheon and Northrop contained a misstatement of law regarding the allowability
    of IR&D costs, and the Air Force’s failure to correct its misstatement cannot constitute
    misleading or unequal discussions. In its May 11, 2015 Opinion and Order, the court rejected
    this argument, concluding that the FAR’s requirement of a fair and level playing field during all
    aspects of a procurement superseded the decisional law cited by Raytheon in which the courts
    ruled that misrepresentations of law cannot, absent unusual circumstances, form the basis for
    rescinding or reforming a contract between the federal government and a private party.3
    Raytheon now contends that the applicability of the misstatement-of-law precedent to discussions
    conducted during a procurement is an issue of first impression that should be considered, de
    novo, by the Federal Circuit on appeal.
    Specifically, Raytheon contends that there is a substantial likelihood that it will succeed
    on the merits on appeal because (1) there is no distinction between a misstatement of law made
    by the government during the discussions phase of a procurement and a misstatement of law
    discovered by a contracting party after the execution of the contract; (2) a misstatement of law is
    analogous to a patent ambiguity and must be challenged prior to contract award; and (3) the court
    erroneously focused on the Air Force’s actions and disregarded Northrop’s knowledge of the law.
    The court is not persuaded by Raytheon’s contentions.
    There is no question that the misstatement-of-law principle applies to contracts awarded
    via a competitive procurement. Indeed, had the Air Force advised all of the offerors that it
    intended to interpret the law concerning the allowability of IR&D costs in one manner, but then,
    upon determining that it was mistaken, did not advise any of the offerors of its changed
    interpretation, the offeror awarded the contract would likely be unsuccessful in requesting
    contract reformation or rescission to remedy the legal misstatement. Notably, however, in those
    circumstances, the Air Force would have treated the offerors equally by not advising any of them
    of its changed position. In contrast, under the circumstances that actually exist in this case, the
    Air Force did not treat all of the offerors equally; once it determined that its interpretation of the
    3
    In the decisions relied upon by Raytheon, the party alleging a misstatement of law was
    either the party in contractual privity with the federal government or the legal representative of
    the party in contractual privity. See generally Mills v. United States, 
    410 F.2d 1255
    (Ct. Cl.
    1969); Edwards v. United States, 
    19 Cl. Ct. 663
    (1990); C & L Constr. Co. v. United States, 6 Cl.
    Ct. 791 (1984). In contrast, although Raytheon is in contractual privity with the Air Force, it is
    not seeking the rescission or reformation of their contract. Rather, Raytheon is challenging the
    ability of another offeror to seek the rescission of Raytheon’s contract with the Air Force.
    -12-
    law was mistaken, it suggested to some, but not all, of the offerors that its position had changed.
    Therefore, regardless of what Northrop knew or did not know about the law concerning the
    allowability of IR&D costs, it did not know how the Air Force actually planned to treat IR&D
    costs–information that the Air Force provided to Raytheon [. . .]. With the benefit of the GAO
    attorney’s outcome prediction statement, the Air Force recognized that it had supplied the
    offerors with different information regarding the allowability of IR&D costs and appropriately
    decided to take corrective action to remedy the information disparity.
    The second basis for Raytheon’s challenge to the court’s conclusion that the Air Force
    acted rationally in deciding to take corrective action is that the court erred in concluding that
    Northrop had established prejudice before the GAO. As with its previous contention, Raytheon
    first made this argument during the merits proceedings. The court rejected Raytheon’s
    arguments in its May 11, 2015 Opinion and Order, noting that the evidence in the record before
    the GAO–that (1) all three contractors submitted technically acceptable proposals; (2) the
    difference between Northrop’s final proposed price of [. . .] and Raytheon’s final proposed price
    of [. . .] was [. . .]; (3) Raytheon proposed IR&D cost reductions of [. . .]; and (4) Northrop is a
    large government contractor with extensive financial resources–was sufficient to support the
    implicit conclusion of the GAO attorney that Northrop possessed the financial means to propose
    IR&D cost reductions [. . .], making it possible for Northrop to overcome the differential in
    proposed prices.
    Raytheon has not persuaded the court that its original ruling regarding prejudice was
    incorrect. As noted by the court in its May 11, 2015 Opinion and Order, a protestor can prevail
    on a claim only if it demonstrates that it was prejudiced by a significant error in the procurement
    process. Data Gen. Corp. v. Johnson, 
    78 F.3d 1556
    , 1562 (Fed. Cir. 1996). To establish
    prejudice, a protestor need not prove that it would have won the contract but for the alleged error
    in the procurement. Bannum, Inc. v. United States, 
    404 F.3d 1346
    , 1358 (Fed. Cir. 2005).
    Rather, a protestor “must show that there was a ‘substantial chance’ it would have received the
    contract award absent the alleged error.” Banknote Corp. of Am. v. United States, 
    365 F.3d 1345
    , 1350 (Fed. Cir. 2004) (quoting Emery Worldwide Airlines, Inc. v. United States, 
    264 F.3d 1071
    , 1086 (Fed. Cir. 2001)). The evidence in the record before the GAO is sufficient to meet
    this standard. Contrary to Raytheon’s assertion, Northrop was not required to provide the GAO
    with specific examples of IR&D cost reductions it could propose to demonstrate a substantial
    chance of being awarded the contract had the Air Force not conducted unequal and misleading
    discussions; it was enough that Northrop demonstrated its capacity to propose such cost
    reductions.
    Moreover, in arguing that Northrop did not adequately establish prejudice before the
    GAO, Raytheon imposes requirements on the GAO that have no basis in the law. The Air
    Force’s decision to take corrective action was based on a GAO attorney’s outcome prediction
    statement, not a formal GAO decision. There is no statutory or regulatory requirement that such
    a statement address every finding that would be required in a written decision from the GAO.
    Indeed, it would defeat the purpose of outcome prediction–the prompt resolution of protests, see
    -13-
    4 C.F.R. § 21.10(e) (2014)–if the assigned GAO attorney was required to address every element
    of a protestor’s claim during the outcome prediction conference. Thus, Raytheon’s attempt to
    impute such a requirement on the GAO attorney in this case is untenable.
    In short, Raytheon has not established a likelihood of success on the merits, or even a
    substantial case on the merits, with respect to the Air Force’s decision to take corrective action to
    remedy its misleading and unequal cost/price discussions.
    B. The Equitable Factors
    Raytheon has not demonstrated either a likelihood of success or a substantial case on the
    merits of its appeal. However, assuming, strictly for the for the sake of argument, that Raytheon
    had established at least a substantial case on the merits, it would not be entitled to relief under
    RCFC 62(c) because, as explained below, Raytheon has not demonstrated that the equitable
    factors weigh in its favor.
    1. Irreparable Injury
    “When assessing irreparable injury, ‘[t]he relevant inquiry in weighing this factor is
    whether plaintiff has an adequate remedy in the absence of an injunction.’” Overstreet Elec. Co.
    v. United States, 
    47 Fed. Cl. 728
    , 743 (2000) (quoting Magellan Corp. v. United States, 27 Fed.
    Cl. 446, 447 (1993)); see also Younger v. Harris, 
    401 U.S. 37
    , 43-44 (1971) (noting that “the
    basic doctrine of equity jurisprudence [is] that courts of equity should not act . . . when the
    moving party has an adequate remedy at law and will not suffer irreparable injury if denied
    equitable relief”). Raytheon first contends that it would be irreparably injured if the Air Force
    was permitted to take corrective action because it would be “forced to expend the time, effort,
    and expense to recompete with itself as well as with Lockheed and Northrop for the contract that
    [it] already lawfully won, and to demonstrate the maturity of technology” that has already been
    found to be technically mature. Mot. 16. In both of the decisions relied upon by Raytheon in
    support of this contention, the court determined that the corrective action proposed by the
    government was unlawful; in other words, the protestors–the original contract awardees–
    succeeded on the merits of their claims. See Sys. Application & Techs., Inc. v. United States,
    
    100 Fed. Cl. 687
    , 719 (2011), 
    aff’d, 691 F.3d at 1374
    ; Sheridan Corp. v. United States, 95 Fed.
    Cl. 141, 154 (2010). As a result, the court in each case concluded that the protestors would be
    irreparably injured by having to unnecessarily recompete for contracts that, as confirmed by the
    court, they had already lawfully won. Sys. Application & 
    Techs., 100 Fed. Cl. at 720-21
    ;
    Sheridan 
    Corp., 95 Fed. Cl. at 155
    .
    Raytheon, however, is not in the same position as the protestors in Systems Application
    & Technologies and Sheridan Corp. In its May 11, 2015 Opinion and Order, the court concluded
    that the Air Force’s decision to take corrective action was a rational response to errors in the
    procurement. In other words, the court concluded that Raytheon could not be considered the
    lawful awardee of the EMD contract. If the contract was not properly awarded to Raytheon in
    -14-
    the first instance, Raytheon being required to compete for the contract anew does not constitute
    an irreparable injury. Moreover, Raytheon has not established that it is likely to succeed, or has a
    substantial case, on the merits of its appeal before the Federal Circuit. As a result, the court
    cannot characterize the recompetition as unnecessary and, consequently, it cannot characterize
    Raytheon’s participation in the recompetition as an irreparable injury. See also 
    Nken, 556 U.S. at 434-35
    (noting that the possibility of irreparable injury is insufficient to satisfy the factor).
    Raytheon also contends that if the Air Force quickly takes corrective action and awards a
    new EMD contract before the Federal Circuit rules on its appeal, it would be left without a
    remedy. This contention is not compelling. If, after corrective action, the Air Force awarded
    Raytheon the EMD contract for a second time, Raytheon would still have a claim for bid
    preparation and proposal costs incurred during the purportedly unnecessary recompetition. See
    28 U.S.C. § 1491(b)(2) (2012). And, an award of the EMD contract to Lockheed or Northrop
    after corrective action would not moot Raytheon’s claim that the decision to take corrective
    action was irrational; if the Air Force chose to proceed with contract performance with the new
    awardee, it would be doing so at the risk of having its decision to take corrective action
    overturned and the newly awarded contract invalidated.
    Finally, Raytheon contends that it would be irreparably injured if it prevails on appeal
    after being forced to recompete for the EMD contract because it would have expended additional
    resources to win a contract that it had already won. Such an injury is not irreparable; Raytheon
    conceivably could amend its complaint or file a new complaint, as appropriate, to recover bid
    preparation and proposal costs for any costs it incurred during its participation in a new
    competition later deemed to be improper. See 
    id. In sum,
    Raytheon has not established that it would be irreparably injured if it was denied
    relief under RCFC 62(c). Although this finding would be sufficient to end its inquiry on the
    equitable factors, the court will address the other factors for the sake of completeness.
    2. Harm to the Other Interested Parties
    Under the next equitable factor, Raytheon argues that the harm it would suffer in the
    absence of relief under RCFC 62(c) outweighs the harm to the Air Force if the court prevented
    the Air Force from taking corrective action and reawarding the EMD contract.4 In advancing this
    argument, Raytheon does not identify any way in which the Air Force might be injured if the
    court granted its RCFC 62(c) motion. Rather, Raytheon contends that the Air Force would be
    injured if the court denied Raytheon’s motion and permitted the Air Force to take corrective
    4
    Raytheon does not address the harm that might be suffered by the other interested
    parties–Lockheed and Northrop. A discussion of the harms that those contractors might suffer if
    the court prevented the Air Force from taking corrective action and reawarding the EMD contract
    is not necessary for the resolution of Raytheon’s RCFC 62(c) motion.
    -15-
    action and reaward the EMD contract. In those circumstances, Raytheon asserts, the Air Force
    would be expending resources for an unnecessary recompetition.
    In its response to Raytheon’s RCFC 62(c) motion, defendant, unsurprisingly, describes
    how the Air Force would be harmed if it was not permitted to proceed with corrective action. It
    generally contends that if the court granted Raytheon’s motion, the Air Force’s mission would be
    adversely affected and the Air Force would incur additional costs to sustain the existing radar
    system. Specifically, it contends that (1) the existing radar system “[. . .], limiting the system’s
    ability to distinguish between our aircraft and an adversary aircraft” and rendering the 3DELRR
    system critical to national defense; (2) the existing radar system “is reaching the end of its service
    life and is becoming more difficult and costly to maintain”; (3) because each existing radar
    system is operational only [. . .], the Air Force must [. . .] existing radar systems “[. . .] to ensure
    that near-continuous air surveillance can be maintained to support ongoing operations”; and (4)
    there are “diminishing manufacturing sources for spare parts and material shortages,” leading to
    increased maintenance costs for the existing radar system. Def.’s Resp. 17-18 (relying on a
    declaration from Steven D. Wert, the Air Force Program Executive Officer for Battle
    Management at the Air Force Life Cycle Management Center, Hanscom Air Force Base,
    Massachusetts). In sum, defendant asserts that the delay in the 3DELRR procurement that would
    result from preventing the Air Force from taking corrective action would be harmful because the
    Air Force would be required “to extend the useful life of an increasingly expensive and less
    effective radar system.” 
    Id. at 18.
    Raytheon disputes defendant’s assertion that the Air Force would be harmed if the court
    prevented it from taking corrective action. In particular, Raytheon contends that the Air Force
    cannot be very concerned over the prospect of a delay in the 3DELRR procurement because (1) it
    did not seek to override the automatic stay of performance put in place when Northrop and
    Lockheed lodged their protests at the GAO and (2) it voluntarily stayed taking corrective action
    during the pendency of this bid protest.5 However, Raytheon fails to acknowledge that the GAO
    is required by statute to resolve bid protests within 100 days, 31 U.S.C. § 3554(a) (2012), and
    that a procuring agency typically will agree to maintain the status quo if the United States Court
    of Federal Claims agrees to resolve the bid protest in an expeditious manner. In other words, the
    delays in those circumstances are known quantities. In contrast, even when the Federal Circuit
    agrees to an expedited briefing and argument schedule for an appeal, as it has in this case, it is
    not obligated to issue an expedited decision on the appeal. Because the date of the Federal
    Circuit’s decision cannot be ascertained, the Air Force would have no way of knowing how long
    the 3DELRR procurement might be delayed if the court granted Raytheon’s RCFC 62(c) motion.
    5
    Raytheon advances a number of other arguments regarding the harm that might be
    suffered by the Air Force if the court prevented the Air Force from taking corrective action.
    However, those arguments are aimed at the substance of Mr. Wert’s declaration, and not at the
    harm alleged by defendant in its response to Raytheon’s RCFC 62(c) motion. Accordingly, the
    court declines to address them.
    -16-
    The court finds that the Air Force would be harmed by such an indeterminate delay in a critical
    procurement.
    In fact, contrary to Raytheon’s contention otherwise, the delay of the 3DELRR
    procurement could be substantial if the court granted Raytheon’s RCFC 62(c) motion. In a
    declaration filed with the Federal Circuit and subsequently filed in this court, the Air Force
    represents that it does not anticipate completing its corrective action and reawarding the EMD
    contract until early December 2015–approximately six months from now. Thus, if the court
    granted Raytheon’s RCFC 62(c) motion but the Federal Circuit denied Raytheon’s appeal, the
    delay to the 3DELRR procurement would equal the time that the Federal Circuit took to issue its
    decision (briefing and argument will themselves take three months), plus the six months the Air
    Force needs to take corrective action. In short, the delay would be at least nine months.
    To conclude, given that Raytheon has not established an irreparable injury and that
    defendant has demonstrated that a delay could seriously harm the Air Force, the balance of harms
    does not weigh in Raytheon’s favor.
    3. Public Interest
    In addressing the third equitable factor, Raytheon correctly asserts that “the public has a
    strong and overriding interest in maintaining the integrity of the procurement process.” Mot. 17-
    18. It argues that the Air Force’s decision to take corrective action and the court’s conclusion
    that the Air Force’s decision was rational “will upset a lawful contract, and sanction a subsequent
    unfair competition in which Raytheon must compete against itself for a contract it already won,
    due to” the Air Force’s disclosure of its price to Lockheed and Northrop during postaward
    debriefings. 
    Id. at 18.
    Raytheon also contends that “the diversion of critical Agency resources to
    an unnecessary competition . . . thwarts the public interest.” 
    Id. Defendant, in
    turn, advances three reasons why the public interest supports allowing the
    Air Force to proceed with its corrective action. First, it contends that the court has already
    examined and upheld the Air Force’s decision to take corrective action, and that there is a public
    interest in allowing an agency to conduct a procurement without excessive judicial interference.
    Second, it asserts a national security interest in replacing the existing, aging radar system with a
    radar system that is capable of detecting current threats. Third, it argues that the public’s interest
    in the integrity of the procurement process is best served by having the Air Force conduct the
    3DELRR procurement in accordance with the solicitation and the FAR, which the proposed
    corrective action will accomplish.
    The court agrees with defendant that the public interest is best served when a
    procurement is conducted openly and fairly in accordance with the solicitation and the FAR.
    See, e.g., Bona Fide Conglomerate, Inc. v. United States, 
    96 Fed. Cl. 233
    , 242 (2010); PGBA,
    LLC v. United States, 
    57 Fed. Cl. 655
    , 663 (2003); Overstreet 
    Elec., 47 Fed. Cl. at 744
    . In this
    -17-
    case, the Air Force determined that corrective action was necessary to comply with the
    solicitation and the FAR, and the court concluded that the Air Force’s determination was
    rational. Consequently, the public’s interest in an open and fair competition is aligned with the
    status quo. Raytheon has therefore not established that the public interest weighs in its favor.
    C. Weighing the Four Factors
    In sum, Raytheon has not demonstrated either a likelihood of success or a substantial case
    on the merits of its appeal. Nor has Raytheon established that the remaining equitable
    factors–irreparable injury, injury to the other interested parties, and the public interest–weigh in
    its favor. Accordingly, Raytheon is not entitled to relief under RCFC 62(c).
    III. CONCLUSION
    For the reasons set forth above, the court DENIES Raytheon’s motion for a stay of the
    court’s judgment and to enjoin the Air Force from proceeding with its proposed corrective action
    or awarding a new contract pending appeal.
    The court has filed this ruling under seal. The parties shall confer to determine agreed-to
    proposed redactions. Then, by no later than Wednesday, June 17, 2015, the parties shall file a
    joint status report indicating their agreement with the proposed redactions, attaching a copy of
    those pages of the court’s ruling containing proposed redactions, with all proposed
    redactions clearly indicated.
    Also, the parties have not yet filed redacted versions of all of the documents that they
    filed under seal.6 Paragraph 12 of the February 12, 2015 amended protective order contemplates
    that the parties will complete the redaction process promptly. Accordingly, the parties shall be in
    full compliance with the redaction requirement as soon as possible, but by no later than
    Friday, July 10, 2015.
    IT IS SO ORDERED.
    s/ Margaret M. Sweeney
    MARGARET M. SWEENEY
    Judge
    6
    As of the date of this decision, redacted versions of the following sealed documents
    have not been filed: docket entries 50, 52, 56, 58, 59, 66, 70, 72, 73, 74, 86, 87, 92, 93, 94, 95,
    and 97.
    -18-