Ultimate Concrete, LLC v. United States ( 2019 )


Menu:
  •              In the United States Court of Federal Claims
    No. 14-549C
    (Filed: March 26, 2019)
    )    Keywords: Contract Disputes Act
    ULTIMATE CONCRETE, LLC,                       )    (“CDA”), 
    41 U.S.C. § 7104
    ; Contract
    )    Interpretation; Motion for
    Plaintiff,              )    Reconsideration; RCFC 59(a).
    )
    v.                                     )
    )
    THE UNITED STATES OF AMERICA,                 )
    )
    Defendant.              )
    )
    )
    )
    Thomas M. Keranen, Clark Hill PLC, Detroit, Michigan, for Plaintiff, with whom was Jeffrey M.
    Gallant, Clark Hill PLC.
    James W. Poirier, Trial Attorney, Commercial Litigation Branch, Civil Division, U.S.
    Department of Justice, Washington, D.C., for Defendant, with whom were Claudia Burke,
    Assistant Director, Robert E. Kirschman, Jr., Director, and Joseph H. Hunt, Assistant Attorney
    General.
    OPINION AND ORDER
    KAPLAN, Judge.
    Plaintiff Ultimate Concrete, LLC (“UC”) has moved for reconsideration of the Court’s
    January 10, 2019 Opinion and Order (ECF No. 139), in which the Court granted-in-part and
    denied-in-part UC’s motion for summary judgment as to certain of its claims in this action
    brought pursuant to the Contract Disputes Act, 
    41 U.S.C. § 7104
     (“CDA”). For the reasons
    discussed below, UC’s motion is DENIED.
    BACKGROUND
    The Court previously set forth the facts of this case in its January 10 opinion. See
    Ultimate Concrete, LLC v. United States, 
    141 Fed. Cl. 463
    , 466–473 (2019) (“Ultimate Concrete
    I”). It therefore presumes familiarity with the case and provides only a brief factual overview
    below. The Court will focus exclusively on UC’s “REA 7-8-9” claim, which is the sole claim at
    issue in UC’s motion for reconsideration.
    This case concerns a contract dispute between UC and the United States Section of the
    International Boundary and Water Commission (“IBWC”). In 2010, UC and IBWC entered into
    a contract under which UC was to “rehabilitate, renovate, and perform new construction on an
    existing levee on the Rio Grande River.” 
    Id.
     at 465–66. The disputed question at issue in this
    motion for reconsideration is whether an amendment to the solicitation allowed UC to leave in
    place preexisting clay material placed on the levee by IBWC in-house crews in 2009 (“the 2009
    clay”).
    It is undisputed that the original specifications and drawings required the contractor to
    excavate the 2009 clay. 
    Id. at 476
    . About one week before bids were due, IBWC issued an
    amended solicitation. 
    Id. at 468
    . Among other changes, having received several questions about
    the 2009 clay—including its quality and quantity—IBWC added language to the solicitation
    specifications stating, in pertinent part: “Approximately 232,300 tons of impervious material has
    been placed on the levee and may be suitable embankment at the contractor’s discretion.” 
    Id.
     UC
    interpreted this sentence to mean that it had the option of leaving the 2009 clay in place on the
    levee. 
    Id.
     at 468–69. Based on this assumption, UC significantly revised its price downward
    immediately before submitting its bid. 
    Id. at 469
    .
    UC won the contract because it submitted the lowest bid. 
    Id.
     As contract performance
    progressed, however, it became clear that UC and IBWC disagreed as to whether UC was
    required to excavate the 2009 clay or could permissibly leave it in place. According to the
    government, the language stating that the subject clay material “may be suitable embankment at
    the contractor’s discretion” meant that the contractor had the option to reuse the clay material by
    placing it back on the levee in the process of rebuilding the structure after the required
    excavation. Therefore, IBWC ordered UC to excavate the clay despite UC’s protests. 
    Id.
     at 469–
    70. UC complied with IBWC’s instructions, tracking all costs for what it perceived to be out-of-
    scope work. 
    Id. at 470
    . UC later submitted a certified claim to the contracting officer and
    ultimately filed the present lawsuit, requesting an equitable adjustment in the amount of
    $10,354,216.06. 
    Id. at 472
    . UC labeled this claim its “REA 7-8-9 claim” because it concerned a
    request for equitable adjustment (“REA”) on Typical Sections 7, 8, and 9 of the levee as denoted
    on the solicitation drawings.
    In Ultimate Concrete I, the Court considered the arguments of the parties in their
    respective motions for summary judgment and found UC’s interpretation of the contract
    unreasonable. 
    Id.
     at 474–79. Conversely, the Court concluded that the government’s
    interpretation was reasonable as a matter of law. 
    Id.
     Accordingly, the excavation of the 2009 clay
    fell within the scope of the contract and UC was not entitled to an equitable adjustment. The
    Court denied UC’s motion for summary judgment as to its REA 7-8-9 claim and granted the
    government’s motion on the same claim. 
    Id. at 482
    .
    UC has now moved for reconsideration of this part of the Court’s ruling. For the reasons
    set forth below, UC’s motion for reconsideration is denied.
    DISCUSSION
    I.     Standard for Granting a Motion for Reconsideration
    Under Rule 59(a) of the Rules of the Court of Federal Claims, the Court may grant a
    motion for reconsideration “(A) for any reason for which a new trial has heretofore been granted
    2
    in an action at law in federal court; (B) for any reason for which a rehearing has heretofore been
    granted in a suit in equity in federal court; or (C) upon the showing of satisfactory evidence,
    cumulative or otherwise, that any fraud, wrong, or injustice has been done to the United States.”
    To meet this standard, a party generally must demonstrate that the court has committed a
    “manifest error of law[] or mistake of fact.” Johnson v. United States, 
    126 Fed. Cl. 558
    , 560
    (2016) (quoting Bishop v. United States, 
    26 Cl. Ct. 281
    , 286 (1992)). “[O]rdinarily” the moving
    party “must show either that an intervening change in controlling law has occurred, evidence not
    previously available has become available, or that [granting] the motion is necessary to prevent
    manifest injustice.” CBS Corp. v. United States, 
    75 Fed. Cl. 498
    , 501 (2007) (quotation omitted);
    see also Johnson, 126 Fed. Cl. at 560. Whether to grant reconsideration lies within the sound
    discretion of the court. See Yuba Nat. Res., Inc. v. United States, 
    904 F.2d 1577
    , 1583 (Fed. Cir.
    1990). Because the standard for reconsideration is a high one, the court should not grant the
    motion unless the party has made “a showing of extraordinary circumstances which justify
    relief.” Biery v. United States, 
    818 F.3d 704
    , 711 (Fed. Cir. 2016) (quoting Caldwell v. United
    States, 
    391 F.3d 1226
    , 1235 (Fed. Cir. 2004)), cert. denied, 
    137 S. Ct. 389
     (Mem.) (2016).
    II.    UC’s Motion
    In its motion for reconsideration, UC does not argue that there has been an intervening
    change in controlling law or that previously unavailable evidence has become available. Its
    motion is predicated on an argument that the Court committed an error of law when, rather than
    applying what UC calls the “reasonable bidder” or “reasonable contractor” standard, it required
    UC to demonstrate that its interpretation of the contract was “correct.” Quoting Renda Marine,
    Inc. v. United States, 
    66 Fed. Cl. 639
    , 652 (Fed. Cl. 2005), UC observes that “a contractor ‘does
    not bear the burden of interpreting [the] contract [documents] correctly, only of interpreting
    [them] reasonably.’” Pl.’s Mot. for Reconsideration (“Pl.’s Mot.”) at 3, ECF No. 142 (alterations
    in original). UC’s argument lacks merit.
    First and foremost, UC has mischaracterized the legal standard the Court applied when it
    entered summary judgment as to the REA 7-8-9 claim. The Court examined the language upon
    which UC relied and determined its meaning on the basis of well-established principles of
    contractual interpretation. It explicitly ruled that the government’s reading of the contract was a
    reasonable one but that UC’s was not. See Ultimate Concrete I, 141 Fed. Cl. at 474 (“[T]he
    Court concludes that UC’s interpretation of . . . the contract is not reasonable.”); id. at 475
    (“UC’s interpretation of the contract is unreasonable.”) (capitalization altered). And, because it
    found the government’s interpretation (but not UC’s) consistent with the language of the
    contract, it declined to allow UC to rely upon extrinsic evidence “to create an ambiguity” that
    otherwise did not exist. See City of Tacoma, Dep’t of Pub. Utils. v. United States, 
    31 F.3d 1130
    ,
    1134 (Fed. Cir. 1994).
    Thus, as noted above, the issue before the Court was the proper interpretation of a
    sentence that had been added to one of the specifications by an amendment to the solicitation.
    The Court held that the government’s interpretation of the operative sentence comported with the
    its language and also harmonized it with the rest of the contract. On the other hand, the Court
    found UC’s reading of the sentence unreasonable because, among other reasons: 1) it could not
    be reconciled with the specifications and drawings governing the construction of the levee,
    3
    which required the contractor to excavate down to benching lines that were below the clay
    material on the existing embankment; 2) it ignored that the subject of the sentence in question
    was the “232,300 tons of impervious [clay] material” that had been placed on the levee; and 3) it
    was grammatically unsustainable (because if the word “embankment” were intended to be used
    as a noun, then it would have been preceded by an article). The Court also rejected as
    unsupported by the record an argument UC repeats here, that the phrase “suitable embankment”
    has a specialized meaning to persons experienced in the construction of levees.
    “[A] motion for reconsideration is not a forum in which a losing party may re-argue its
    case.” Prati v. United States, 
    82 Fed. Cl. 373
    , 377 (2008). Yet UC’s motion for reconsideration
    largely repeats and/or repackages points that it made in its motion for summary judgment and
    which the Court has already carefully considered and rejected as described above.
    The Court declines to revisit these repeated and repackaged arguments but notes that UC
    does not engage with, or even acknowledge, the primary principle upon which the Court relied in
    its summary judgment decision, which is that a contract “must be considered as a whole and
    interpreted so as to harmonize and give reasonable meaning to all of its parts.” Coast Fed. Bank,
    FSB v. United States, 
    323 F.3d 1035
    , 1038 (Fed. Cir. 2003) (citing McAbee Constr., Inc. v.
    United States, 
    97 F.3d 1431
    , 1435 (Fed. Cir. 1996)). Nor does UC come to terms with the
    Court’s textual analysis of the operative sentence itself, which supports the government’s
    interpretation and refutes UC’s.
    The Court also notes that it is not persuaded by UC’s argument that in deciding whether
    its reading of the contract was reasonable, the Court should have given consideration to “the
    circumstances of the bidding process,” specifically that UC had “limited time to review” the
    revisions that were made to the solicitation shortly before bids were due. Pl.’s Mot. at 11. As the
    court observed in Renda Marine, “a government contractor, regardless of its size, locality, or
    experience, is obligated to understand the complexities and consequences of its undertaking . . .
    and to study all aspects of the contract before submitting its bid.” 66 Fed. Cl. at 655 (internal
    citations, quotations, and alterations omitted); see also Giesler v. United States, 
    232 F.3d 864
    ,
    870 (Fed. Cir. 2000) (holding that it is incumbent upon contractors to “read and consider the
    specifications thoroughly”) (quoting Liebherr Crane Corp. v. United States, 
    810 F.2d 1153
    , 1157
    (Fed. Cir. 1987)); see also R.B. Wright Constr. Co. v. United States, 
    919 F.2d 1569
    , 1572 (Fed.
    Cir. 1990) (quoting and applying same proposition from Liebherr).
    Magnus Pacific Corp. v. United States (“Magnus”), the primary case on which UC relies
    for a contrary proposition, is inapposite. See generally 
    133 Fed. Cl. 640
     (2017). In that case,
    shortly before bids were due on a levee reconstruction project, “the entire set of specifications for
    the project was revised and fully replaced” and IBWC provided answers to bidder questions that
    “encompassed fundamental changes to the project and revised or replaced contract language.” 
    Id. at 649
    . Expert testimony submitted by the plaintiff and credited by the court showed that “the
    solicitation lacked essential data” and that “the levee design set forth in the plans and
    specifications did not reflect the conditions on the existing levee.” 
    Id.
     The court agreed with the
    plaintiff’s expert “that the level of error and missing information in the solicitation documents,
    and the sweeping last minute changes to the solicitation that were made during the bidding
    process, were problematic.” 
    Id.
    4
    The Court disagrees with UC’s contention that the facts in Magnus were “very similar to
    those here.” Pl.’s Mot. at 11. As the Court noted in its original opinion, the new provision on
    which UC relies did not implement “sweeping changes”; it merely clarified existing
    requirements in response to certain written questions submitted by other offerors after a site
    visit.1 It is only when the provision is given the unreasonable reading UC proposes that it results
    in a significant change to existing requirements.
    Further, in Magnus, the issue to which the court found the last-minute changes relevant
    was not whether the plaintiff had proffered a reasonable interpretation of the contract. Rather, it
    was whether—for purposes of the plaintiff’s defective specifications claim—the defects were
    “patent” or “latent” ones. 133 Fed. Cl. at 692. Resolution of that issue was dependent on
    questions of fact, including the obviousness of the defects in the solicitation—i.e., whether there
    were “facial discrepancies that a bidder noticed or should have noticed.” Id. In that context, the
    court found as a matter of fact that “given the analytical effort required to discern th[e] particular
    defect in the solicitation, particularly in light of the time constraints, the inconsistency [at issue]
    was a hidden defect that would not be discovered upon facial inspection or through reasonable
    and customary care.” Id. at 693.
    The REA 7-8-9 claim is not a defective specifications claim, and the issue presently
    before the Court does not involve whether such a defect existed or whether it was a latent or
    patent one. The issue before the Court is the interpretation of one of the terms of the contract,
    which involves a question of law. The Magnus decision therefore does not support UC’s
    argument that the Court should have taken into account the amount of time UC had to submit its
    bid when assessing the reasonableness of UC’s interpretation of the contract.
    CONCLUSION
    For the foregoing reasons, UC has not demonstrated that the Court committed a manifest
    error of law or fact in its previous opinion and order. Therefore, UC’s motion for reconsideration
    is DENIED.
    1
    In that regard, UC repeats its contention that the disputed language in the addendum was added
    in response to a question posed during the site inspection asking if the existing embankment
    could be left in place. Pl.’s Mot. at 5. As the Court previously observed, the pre-bid meeting
    minutes stated that questions “must be submitted in writing” and “verbal answers to question[s]
    [were] not binding.” Ultimate Concrete I, 141 Fed. Cl. at 467–68. Further, “there were no written
    questions submitted about whether the embankment that had been rehabilitated the preceding
    year by the in-house crews could be left in place.” Id. at 467. Rather, the Court observed, the
    written questions concerned the quality and amount of clay material used to build the existing
    embankment that would be available for salvage, which was consistent with the government’s
    interpretation of the operative sentence in the amended solicitation. Id.
    5
    IT IS SO ORDERED.
    s/ Elaine D. Kaplan
    ELAINE D. KAPLAN
    Judge
    6